CFO Martin Burrell
FiReControl and Firelink Project Director
CFO Martin Burrell
FiReControl and Firelink Project Director
Objectives
General update on the Firelink and FiReControl projects
Advise of forthcoming regional decisions
General update on the Firelink and FiReControl projects
Advise of forthcoming regional decisions
Firelink Airwave – Macquarie ( New owners ) currently part way through recruiting an
extra 35 project staff.
Firelink schedule
Phase A works for the SE due completetion by 11 Aug 2008 with the exception of Surrey and Buckinghampshire who are awaiting “C Soft” hardware installation.
Phase B has now had realism adjustment and dates for the SE are now: 12/05/2008 to 11/05/2009.
Confusion over call off items functionality and use for Regional control (Pump Bay Voice Terminals). May delay Statement Of Brigade Requirements. (SOBR)
Airwave – Macquarie ( New owners ) currently part way through recruiting an extra 35 project staff.
Firelink schedule
Phase A works for the SE due completetion by 11 Aug 2008 with the exception of Surrey and Buckinghampshire who are awaiting “C Soft” hardware installation.
Phase B has now had realism adjustment and dates for the SE are now: 12/05/2008 to 11/05/2009.
Confusion over call off items functionality and use for Regional control (Pump Bay Voice Terminals). May delay Statement Of Brigade Requirements. (SOBR)
Take up of early Mobile Data Terminals at Phase B of Firelink has been abandoned over concerns that the additional work would upset the phase B schedule. Individual FRS’s discussions at the end of phase B may allow MDT’s in some FRS’s subject to Airwaves ability to deliver.
Costs
PBVT costs could double to meet FiReControl requirements. (Request To Talk function must be added) many FRS’s are dramatically changing their SOBR’s due to confusion over this issue.
On going concerns over cost of call off contract.
Joint issue. A Review of the concept of ops is to be presented to PUG and SOG. A Draft will be presented in Feb. The concept of ops will be across both projects to ascertain what will be required to meet the proposed mode of operation.
Take up of early Mobile Data Terminals at Phase B of Firelink has been abandoned over concerns that the additional work would upset the phase B schedule. Individual FRS’s discussions at the end of phase B may allow MDT’s in some FRS’s subject to Airwaves ability to deliver.
Costs
PBVT costs could double to meet FiReControl requirements. (Request To Talk function must be added) many FRS’s are dramatically changing their SOBR’s due to confusion over this issue.
On going concerns over cost of call off contract.
Joint issue. A Review of the concept of ops is to be presented to PUG and SOG. A Draft will be presented in Feb. The concept of ops will be across both projects to ascertain what will be required to meet the proposed mode of operation.
Firelink
Draft National Framework
Fire and Rescue Authorities must support the rollout of Firelink by:
Co-operating with the suppliers by giving access to vehicles and existing control rooms, and by ensuring that training programmes are completed to timetable, providing all reasonable support.
Assisting the Firelink programme with testing of the new system and migration of radio communications to the RCC.
Fire and Rescue Authorities must support the rollout of Firelink by:
Co-operating with the suppliers by giving access to vehicles and existing control rooms, and by ensuring that training programmes are completed to timetable, providing all reasonable support.
Assisting the Firelink programme with testing of the new system and migration of radio communications to the RCC.
Business Case
Review of Assumptions – still taking place
Bottom Line more important than principles and discussion
Current operating costs being requested through FSC 60/2007 - Fire and Resilience Programme - Legacy Systems Cost Assurance (Firelink and FiReControl). Overseen by PKF.
Needs to take account of costs of “out-of-scope” and “in-scope, in-FRS”, I.e. costs that will remain with FRS after cutover
CLG committed to release an update in Feb v1.1 with limited detail
Further release June v1.2 with up to date detail e.g. revised assumptions, current costs and an annex for each regions costs (subject to ministerial agreement).
Fire Service Circular due out this week consulting on cost apportionment for allocation of savings.
Review of Assumptions – still taking place
Bottom Line more important than principles and discussion
Current operating costs being requested through FSC 60/2007 - Fire and Resilience Programme - Legacy Systems Cost Assurance (Firelink and FiReControl). Overseen by PKF.
Needs to take account of costs of “out-of-scope” and “in-scope, in-FRS”, I.e. costs that will remain with FRS after cutover
CLG committed to release an update in Feb v1.1 with limited detail
Further release June v1.2 with up to date detail e.g. revised assumptions, current costs and an annex for each regions costs (subject to ministerial agreement).
Fire Service Circular due out this week consulting on cost apportionment for allocation of savings.
Implementation Funding FSC due out this month detailing
Additional 2007-08 New Burdens Funding
CSR 07 national funding covering the 3 financial years
2008 – 09 = £27m
2009 – 10 = £36.6m
2010 – 11 = £29.
These funds cover transition activities, LACC companies, Regional Project Teams, specific one-off staff costs + staff pool for wave one regions
FSC due out this month detailing
Additional 2007-08 New Burdens Funding
CSR 07 national funding covering the 3 financial years
2008 – 09 = £27m
2009 – 10 = £36.6m
2010 – 11 = £29.
These funds cover transition activities, LACC companies, Regional Project Teams, specific one-off staff costs + staff pool for wave one regions
Draft National Framework
Fire and Rescue Authorities must make preparations to move their control service to the Regional Control Centre network in line withthe FiReControl transition plan
co-operate fully with the FiReControl technology supplier
report progress regularly to Communities and Local Government using the tools provided for that purpose.
Fire and Rescue Authorities must make preparations to move their control service to the Regional Control Centre network in line withthe FiReControl transition plan
co-operate fully with the FiReControl technology supplier
report progress regularly to Communities and Local Government using the tools provided for that purpose.
Transition Planning Transition and Resource plans continue to be developed
Checkpoint 1 – signed off by all FRSs
Checkpoint 2 due 4.4.08
Major risks: data/IT systems; Convergence (information from EADS/CLG delayed)
EADS:
Still not quite where they would wish to be, but confident in achieving Oct 09 cutover
Transition and Resource plans continue to be developed
Checkpoint 1 – signed off by all FRSs
Checkpoint 2 due 4.4.08
Major risks: data/IT systems; Convergence (information from EADS/CLG delayed)
EADS:
Still not quite where they would wish to be, but confident in achieving Oct 09 cutover
Business Continuity
Project timescales – national go live Oct 09 (May 2010 for South East)
Technical Risk Assessments
Personnel Risk Assessments
All FRSs must have business continuity plans in place should FiReControl or any individual FRSs have any difficulties in meeting project timescales
Project timescales – national go live Oct 09 (May 2010 for South East)
Technical Risk Assessments
Personnel Risk Assessments
All FRSs must have business continuity plans in place should FiReControl or any individual FRSs have any difficulties in meeting project timescales
General
Regional Communications event 25th March in London
LACC
May be asked to take on the lease by May 2008
Legal and Financial advisors update
First two meetings held. Next meeting early Feb
• Peter Jones (WSCC - Chair)
• Andy Dransfield (Bucks - Vice Chair)
RCC Director appointed
• Mathew Goodwin (NHS background)
• Hoping to start April/May 2008 (subject to security clearance)
Regional Communications event 25th March in London
LACC
May be asked to take on the lease by May 2008
Legal and Financial advisors update
First two meetings held. Next meeting early Feb
• Peter Jones (WSCC - Chair)
• Andy Dransfield (Bucks - Vice Chair)
RCC Director appointed
• Mathew Goodwin (NHS background)
• Hoping to start April/May 2008 (subject to security clearance)
General
Resilience Programme (FiReControl. Firelink and New Dimensions)
All 3 projects have different consultants supporting CLG
CLG shortly going out to tender for 1 consultancy to support the resilience programme.
Review of FiReControl Concept of Operations taking place and will now include Firelink. Draft ready in February.
Resilience Programme (FiReControl. Firelink and New Dimensions)
All 3 projects have different consultants supporting CLG
CLG shortly going out to tender for 1 consultancy to support the resilience programme.
Review of FiReControl Concept of Operations taking place and will now include Firelink. Draft ready in February.