+ All Categories
Home > Documents > Secondary-Use Battery Energy Storage Systems · Secondary-Use Battery Energy Storage Systems ......

Secondary-Use Battery Energy Storage Systems · Secondary-Use Battery Energy Storage Systems ......

Date post: 01-Apr-2018
Category:
Upload: doanthu
View: 227 times
Download: 4 times
Share this document with a friend
21
Secondary-Use Battery Energy Storage Systems Michael Starke, PhD Power and Energy Systems Oak Ridge National Laboratory ORNL Team: Phil Irminger, Ben Ollis, Brandon Johnson, Omer Onar, George Andrews
Transcript

Secondary-Use Battery Energy

Storage Systems

Michael Starke, PhD

Power and Energy Systems

Oak Ridge National Laboratory

ORNL Team:

Phil Irminger, Ben Ollis, Brandon Johnson, Omer Onar, George Andrews

2 Presentation name

I would like to thank Dr. Imre Gyuk, Program Manager of the Electrical Energy Storage Program for DOE’s Office of

Electricity for his support and funding.

3 Presentation name

Project Overview

• Supporting the industry investigation into vehicle battery secondary-use through testing, demonstration, and modeling.

– Potentially a cost competitive energy storage technology

– Validate reliability and safety – working with industry to troubleshoot and test systems under operational conditions

– Examining regulatory environment – investigating hurdles that are institutional

– Industry acceptance – build confidence in this technology.

3

4 Presentation name

Current Activities

HARDWARE

SYSTEMS INTEGRATION

SOFTWARE

• Energy Storage – Used EV Batteries

• Energy Management System

• Electric Grid

An effective partnership that merges

equipment, technical know-how, and

infrastructure:

ORNL is testing and demonstrating the technology as a

third party.

5 Presentation name

GM/ABB Quote

" The collaboration between ORNL, GM, and ABB has been instrumental in confirming the opportunity to utilize automotive second use batteries in a grid based application. The high quality of the extended ORNL testing gave us a deeper understanding of design, installation, and operation of energy storage devices. The team used the sophisticated lab environment to examine a wide range of performance scenarios not possible at a single production installation site.“ – General Motors

6 Presentation name

The Technology

Grid Application (25kW/50kWhr)

• Expected capacity for 10 Years

of Operation

• 5 Volt Battery Packs

• 5 kW per Volt Battery

• Air Cooled/Heated

Automotive Application

– Capacity for 10 Years in Automotive Application

– Power 111kW

– Liquid Cooled / Heated

GM Chevy Volt Battery

Re-Packaged

ABB Enclosure

7 Presentation name

Testing Setup at ORNL

• ORNL objective for testing: Provide real world examination systems integration and applications with the flexibility to capture many different case scenarios.

ORNL Distribution

System

750kVA, 13.8kV/2.4kV

Circuit #22.4kV System

750kVA, 2.4kV/480V

480V, 3 Phase, 60Hz

2.4kV, 3 Phase, 60Hz

13.8kV, 3 Phase, 60Hz 480V Distribution

Panel

Disconnect Switch

37.5kVA, 120V-240V/480V

Programmable Load Bank (240V,

Split Phase, 24kW)

Community Energy Storage (240V, Split

Phase, 25kW)

Disconnect Switch

480V, 3 Phase, 60Hz

240V, Split Phase, 60Hz

480V/2.4kV

50kW PV

50kVA inverter

15kW PV

1 Hardware

2 Communications

3 Controls

8 Presentation name

Hard/Soft: Communication and Control

Communications

and Control

and Measure &

Validate

Communications

and control done

through Serial,

Modbus over Serial,

and TCP/IP

- All integrated

through

Matlab/Labview

DECC Facility

Communications Cable, RS232/RS485

over Modbus

Communications Cable, RS232

ORNL/Distribution

CT/VT

CT/VT

CES

ROOFTOP PV

CONTROL/COMPUTING

GRID

M&V

CT/VT

LOAD

9 Presentation name

Hardware: Equipment Inside DECC

480V/240V(split-phase)

Transformer

Islanding

Contactor/Relay

Programmable

Load Bank

Emergency

Disconnect

10 Presentation name

Battery

Enclosure Inverter

Hardware: Equipment Outside DECC

Emergency

Disconnects

PV Array

11 Presentation name

Interface

Set of pre-programmed controls

CES Alarms

Manual Control

State display

12 Presentation name

Controls and Programs

PV Forecast

Load Factor Control Points

SOC Estimate

text message

Cloud Cover

Solar Irradiance/PV output

Residential Model Consumption

% Cloud Cover Temperature (C)

Temperature

solarirradiance

GA Optimization

kW load

kW PV

Measured Data

Main ControlEmergency Monitoring

Data Acquistion

Load Bank

Shutoff

email

Data Processing

Data

Historian

Data

Load Bank Temp

Temperature (C)

Control Mode, P, Q

Storage

• Auto-runs at 12:00AM

• Controls depend on selected settings.

13 Presentation name

Testing Procedure (Systems Tests)

• Objectives:

– Obtain standard metrics (round-trip efficiency/ensure within bounds of standards)

– Demonstrate application examples

• Standard Metrics:

– Round-trip efficiency

– Harmonics, etc.

• Applications

– Load factor,

– Power factor,

– Renewable Integration,

– Islanding

Start

Charge Battery at Requested Power Level to 70% SOC

Rest Battery for 30 Minutes

Discharge Battery at Requested Power

Level for 30 minutes

Rest Battery for 30 Minutes

Time Since Last Power Level Change > 24 Hours?

At Maximum Power Level?

Increase Requested Power Level

No

Yes

No

Yes

Stop

Requested Power: 5

kW

14 Presentation name

Multiple Value Streams: Stacking Benefits (Load

Factor/Power Factor, Renewable Integration)

Grid (nearly flat)

Power (W)

Time (hr)

Power (Var)

SOC (%)

Time (hr)

Time (hr) Time (hr)

Histogram power factor

Target Set to 0.97

SOC target to return to 50%

15 Presentation name

Other Applications: Off-grid and PV Smoothing

Grid power

Battery-supplying

entire load

Power (kW)

Power (kW)

16 Presentation name

Initial Economic Approach

(Mixed Integer) Linear

Optimization Grid

Services

Battery Model

Data

Optimal Battery

Dispatch

Cost/Savings

17 Presentation name

• Arizona Public Service Company residential rate structures

• Year-long simulated load for 3 homes

• Dispatch the battery to minimize the homeowners’ cost

• Utilized efficiencies of real system, 10year/3000 cycle battery

Initial Economic Results

18 Presentation name

Initial Economic Results

19 Presentation name

ORNL Summary/Conclusions

• Developed controls and applications ES testing

• Demonstrated and tested ABB/GM secondary-use battery storage.

• Drafted a report on initial testing procedures (currently in review.)

• Obtained and evaluated PNNL optimization toolbox for ES.

• Developing models for distributed control of energy storage.

19

20 Presentation name

Future Tasks

• Continued testing of ABB/GM.

• Modeling and economics assessment for DES.

• Optimization of DES dispatch

• Development of refurbished secondary use ES with ATC New Technologies partners.

20

L1

L2

L3

S11

S12

S21

S22

S31

S32

C3

C2

C1

S1 S2 S3

S4 S5 S6

BMS

BMS

BMS

V1

I1

V2

V3

I3

Va

Vb

Vc

G12

G11

G21

G22

G31

G32

G1

G2 G3

G6G5G4

G11, G12

G1, G2, G3, G4, G5, G6

Estop1, SOC1, kWh1, kW1

Estop1, SOC1, kWh1, kW1

DC/DC Converter 1

V1, I1

Va, Vb, Vc

Ia, Ib, Ic

Inverter Control System

Preq, Qreq, Mode

DC/AC Inverter/Grid Connection

G1

La

Lb

Lc

Battery

I2

Battery

Battery

Ia

Ib

Ic

3ϕ 480VAC

600VDC

<500VDC,

25kW

L4

S41

S42

BMS

V4

I4

G41

G42Battery

L5

S51

S52

BMS

V5

I5

G51

G52Battery

<500VDC,

25kW

<500VDC,

25kW

<500VDC,

25kW

<500VDC,

25kW

C4

C5

100kW

21 Presentation name

Special thanks to Dr. Imre Gyuk for his dedication and support to ORNL and ES industry.

Questions?

21

PI : Michael R. Starke, PhD

Oak Ridge National Laboratory

Power and Energy Systems

Energy & Transportation Science Division

(865) 241-2573 office One Bethel Valley Road

(865) 574-9329 fax P.O. Box 2008, MS-6070

Oak Ridge, TN 37831


Recommended