834310 00 91 13 - 1 ADDENDUM
SECTION 00 91 13
ADDENDUM
Addendum No. 03
Owner: City of Coleman
Contract: Bid Package No. 4 – General Construction
Project: Sewage Lagoon / Pump Station Improvements Date: 5/2/18
Owner’s Contract No.: Engineer’s Project No.: 834310
ENGINEER: Fleis & VandenBrink Engineering, Inc.
NOTICE TO ALL PROSPECTIVE BIDDERS
BIDS DUE: Wednesday, May 9, 2018 at 2:00 PM -- ISSUED TO ALL PLANHOLDERS OF RECORD
=====================================================================================
This Addendum is a part of the Contract Documents and modifies the previously issued Bidding Documents. Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may result in rejection of the Bid.
General Note:
The electrical plans have been completely replaced. A majority of the other changes are piping and structures. The restoration of the Lagoon side slopes has not changed.
SPECIFICATION CHANGES
ITEM NO. 1:
Section 00 41 00 BID FORM
Revised quantities and pay items.
ITEM NO. 2:
Section 01 22 00 – MEASUREMENT AND PAYMENT
Paragraph 1.04.A.10 – Replace the words “rip rap” with “concrete”.
Paragraph 1.04.A.15 – Add “and wood walkway” after “…removal of existing structure”; Replace the words “slide gates” with “gate valves”; Replace the word “grating” with “hatch”; Remove the words “walkways, footings and handrail”.
Paragraph 1.04.A.16 – Replace this part with the following: 16. Slide Gate Replacement: Counted and paid for each slide gate that is replaced by size.
Paragraph 1.04.A.29 – Add the words “and armor stone” after the words “rip rap”.
Paragraph 1.04.A.39 – Delete all of this part.
Paragraph 1.04.A.42 – Add “including flowable fill” at the end of the sentence.
Paragraph 1.04.A.46 - Add “manual hoist, “ after “doors and hardware,”.
Paragraph 1.04.A.51 - Add the following paragraph after part 1.04.A.50:
51. Temporary Haul Road: Provide a temporary haul road along the west side of the Lagoons for sludge removal. Remove when no longer needed. Restore per section 32 92 00.
ITEM NO. 3:
Section 06 74 13 FIBERGLASS REINFORCED GRATING
Add this section in its entirety.
ITEM NO. 4:
Section 08 30 10 ACCESS HATCHES
834310 00 91 13 - 2 ADDENDUM
Part 2.01.A, 2.01.B, and 2.01.C – Add item 9 to each section as follows:
9. Manufacturer standard protective grating for required loading.
ITEM NO. 5:
Section 26 05 10 – ELECTRICAL GENERAL PROVISIONS
Paragraph 1.10 - Add the following after paragraph 1.09.:
1.10 ELECTRIC UTILITY WORK:
A. Electric Utility Work. CONTRACTOR shall coordinate the new 480 volt, three phase electric service from the existing Pump station to the new Building on the OWNERS behalf. All costs associated with the relocation of the electric service shall be paid for by the OWNER.
ITEM NO. 6
Section 26 60 03 – SUBMERSIBLE PROBE CONTROL SYSTEM FOR PUMP STATION
Replace paragraph 2.06.C in its entirety with the following:
C. Submersible pump station controls shall be mounted on a wall or floor mount NEMA 1 or 12 Painted Steel Enclosure.
ITEM NO. 7:
Section 26 60 03 – SUBMERSIBLE PROBE CONTROL SYSTEM FOR PUMP STATION
Paragraph 2.08 – Delete this section in its entirety.
ITEM NO. 8:
Section 26 60 03 – SUBMERSIBLE PROBE CONTROL SYSTEM FOR PUMP STATION
Replace paragraph 2.10.J in its entirety with the following:
J. Install OWNER supplied VFD and NEMA 1 Enclosure with all components shown on wiring diagrams. Provide door operated or flange mounted disconnect switch capable of being locked in the open position connected to VFD circuit breaker.
ITEM NO. 9:
Section 26 60 03 – SUBMERSIBLE PROBE CONTROL SYSTEM FOR PUMP STATION
Replace paragraph 2.10.L in its entirety with the following:
L. Manufacturers: Design basis VFD is ABB or ENGINEER approved equal by Rockwell Automation, Yaskgowa, Eaton, GE or Square D.
ITEM NO. 10:
Section 26 60 03 – SUBMERSIBLE PROBE CONTROL SYSTEM FOR PUMP STATION
Replace paragraph 2.14 in its entirety with the following:
A. HMI Shall be an integral part of PLC below. Mount OWNER supplied HMI on Pump Station Control Panel Door. All programming and software for HMI by Kennedy Industries.
ITEM NO. 11:
Section 26 60 03 – SUBMERSIBLE PROBE CONTROL SYSTEM FOR PUMP STATION
Paragraph 2.15 - Add the following after item C.:
D. Cellular Modem required for communications with SCADA SYSTEM in specification in 40 94 43. 01, shall be provided by the OWNER through Kennedy Industries. Kennedy Industries shall establish communications with OWNERS Cellular Carrier on OWNERS behalf. OWNER shall pay for monthly cellular service charge.
ITEM NO. 12:
Section 26 60 03 – SUBMERSIBLE PROBE CONTROL SYSTEM FOR PUMP STATION
Paragraph 2.19 - Add the following after item paragraph 2.18:
2.19 MAGNETIC FLOW METERS (Furnished and installed in Bid Package No. 4):
A. TAG FIT:
1. All flow meter Manufacturers shall submit results of flow calibration tests to confirm the stated accuracy. 3 Point NIST traceable calibration certificate to be supplied with each meter.
B. Magnetic type:
1. General:
834310 00 91 13 - 3 ADDENDUM
a. Designed for metering raw sewage . b. Accuracy: Within ± 0.2% of measured value for all flow velocities above 3 fps. c. Microprocessor based. d. Magnetic induction type proportional to velocity. e. Complete with ground rings. Grounding probes or electrodes are not acceptable. f. Provide required lengths of cabling between meter tube and remote mounted transmitter.
Installing CONTRACTOR to verify required length. No splicing of cabling shall be permitted.
2. Meter tube: a. 304 stainless steel flow tube. Epoxy coated carbon steel body housing. b. Polyurethane liner or hard rubber liner. c. Electrodes: Hastelloy-C d. Connections: Flanged, ANSI Class 150. e. Epoxy coated: 2 coats for a minimum of 7 mils. f. Approved for installation in NEC Class 1, Division 2, Group D Hazardous Area. g. NEMA 6P rating or equivalent for submergence in meter chamber.
3. Schedule a. Line sizes as required on drawings. b. Provide cast iron flange mounted spool piece to match for removal and maintenance of
mag meter.
4. Flow Tube Mounted Transmitter: a. One flow tube mounted transmitter. b. Microprocessor based converter. c. Programming of the flow converter shall be accomplished without removing the glass
cover via 4 optical keys or remotely with hand held HART terminal or with vendor and protocol independent PC configuration software: PACTWARE
d. Transmitter shall display instantaneous and totalized flow. e. Outputs:
1) Isolated 4-20 mAdc proportional and calibrated to stated flow range. 2) Empty pipe detection with dry contact relay output. Form A contacts shall be rated for
120 vac, 20 amps. 3) Converter shall have HART Smart protocol as standard. 4) Pulse or analog output. 5) One (1) status Form A relay output. Contacts shall be rated for 120 VAC, 5 amps.
f. Power: 120-VAC, 60 Hz. g. Calibrate
1) FIT- 0-1500 GPM = 4-20 mA Influent Flow Meter. h. Manufacturer:
1) ABB ProcessMaster. 2) Rosemont. 3) Endress and Hauser 4) or ENGINEER Approved Equal.
ITEM NO. 13
Section 31 20 01 – LAGOON LINER AND BERM REPAIRS
Add this section in its entirety.
ITEM NO. 14
Section 33 05 20 – SITE PROCESS PIPING
Add this section in its entirety.
ITEM NO. 15
Section 33 05 24 – HORIZONTAL DIRECTIONAL DRILLING
Remove this section in its entirety.
ITEM NO. 16:
Section 35 20 16 – HYDRAULIC GATES
Add the following from Part 2.02.A.3:
4. Slide gates shall be Waterman Industries C-20 Canal Gate or approved equal.
ITEM NO. 17:
Section 35 20 16 – HYDRAULIC GATES
834310 00 91 13 - 4 ADDENDUM
Add the following section after 2.02:
2.03 STOP GATES
A. General: 1. Provide in accordance with the stop plate schedule shown on the Drawings and AWWA C562
except for lifting device and stem requirements. 2. Flush bottom seal: Neoprene ASTM D-2000. 3. Leakage shall not exceed 0.1 gallons per minute per foot of seating perimeter when the head,
whether seating or unseating, is at the top of the slide. 4. Frame shall incorporate ultra-high molecular weight (UHMW) polymer seats that contact both
sides of the slide plate.
B. Handles: 1. External handles: Aluminum casting welded to the slide. 2. Internal handles: Slot cut into the slide with pipe hand grip welded to top of slot. 3. Provide 2 handles in stop plates 36-inch or wider.
ITEM NO. 18
Section 40 23 00 – PROCESS PIPING SYSTEMS
Add this section in its entirety.
ITEM NO. 19
Appendix A – NPDES DISCHARGE PERMIT
Insert the attached Discharge Permit into Appendix A
DRAWING CHANGES
ITEM NO. 20:
Sheets CS-E05:
Replace entire set with attached set of drawings.
ATTACHMENTS:
Specification Section 00 41 00 BID FORM (9 pages)
Specification Section 01 22 00 MEASUREMENT AND PAYMENT (7 pages)
Specification Section 06 74 13 FIBERGLASS REINFORCED GRATING (3 pages)
Specification Section 26 60 03 SUBMERSIBLE PROBE CONTROL SYSTEM FOR PUMP STATION WITH SPEED CONTROL (9 pages)
Specification Section 31 20 01 LAGOON LINER AND BERM REPAIRS (3 pages)
Specification Section 33 05 20 SITE PROCESS PIPING (7 pages)
Specification Section 40 23 00 PROCESS PIPING SYSTEMS (5 pages)
Appendix A – NPDES DISCHARGE PERMIT (36 pages)
Complete Set of Plans (21 pages)
END OF SECTION
834310 00 41 00 - 1 BID FORM ADDENDUM NO. 3
SECTION 00 41 00
BID FORM – ADDENDUM NO. 3
THIS BID FORM MUST BE SUBMITTED WITH THE PROPOSAL PROJECT IDENTIFICATION:
City of Coleman
Sewage Lagoon / Pump Station Improvements
Bid Package No. 4 – General Construction
ARTICLE 1 – BID RECIPIENT 1.01 This Bid is submitted to:
City of Coleman
201 E. Railway Street
Coleman, MI 48618 1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an
Agreement with OWNER in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.
ARTICLE 2 – BIDDER’S ACKNOWLEDGEMENTS 2.01 Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without
limitation those dealing with the disposition of Bid security. This Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of OWNER.
ARTICLE 3 – BIDDER’S REPRESENTATIONS 3.01 In submitting this Bid, Bidder represents that:
A. Bidder has examined and carefully studied the Bidding Documents, and any data and reference items identified in the Bidding Documents, and hereby acknowledges receipt of the following Addenda:
Addendum No. Addendum Date
B. Bidder has visited the Site, conducted a thorough, alert visual examination of the Site and
adjacent areas, and become familiar with and satisfied itself as to the general, local and Site conditions that may affect cost, progress, and performance of the Work.
C. Bidder is familiar with and has satisfied itself as to all Laws and Regulations that may
affect cost, progress, and performance of the Work.
834310 00 41 00 - 2 BID FORM ADDENDUM NO. 3
D. Bidder has carefully studied all: (1) reports of explorations and tests of subsurface
conditions at or adjacent to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site that may be identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings, and (2) reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that may be identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings.
E. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and any Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder; and (3) Bidder’s safety precautions and programs.
F. Bidder agrees, based on the information and observations referred to in the preceding
paragraph, that no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price(s) bid, within the times required, and in accordance with the other terms and conditions of the Bidding Documents.
G. Bidder is aware of the general nature of work to be performed by OWNER and others at
the Site that relates to the Work as indicated in the Bidding Documents. H. Bidder has given ENGINEER written notice of all conflicts, errors, ambiguities or
discrepancies that Bidder has discovered in the Bidding Documents, and confirms that the written resolution thereof by ENGINEER is acceptable to Bidder.
I. The Bidding Documents are generally sufficient to indicate and convey understanding of
all terms and conditions for the performance and furnishing of the Work. J. The submission of this Bid constitutes an incontrovertible representation by Bidder that
Bidder has complied with every requirement of this Article, and that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.
ARTICLE 4 – BIDDER’S CERTIFICATION 4.01 Bidder certifies that:
A. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation;
B. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid;
C. Bidder has not solicited or induced any individual or entity to refrain from bidding; and
D. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 4.01.D:
834310 00 41 00 - 3 BID FORM ADDENDUM NO. 3
1. “corrupt practice” means the offering, giving, receiving, or soliciting of any thing of value likely to influence the action of a public official in the bidding process;
2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition;
3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels; and
4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.
ARTICLE 5 – BASIS OF BID 5.01 Bidder shall provide Bid prices for all of the individual Work Items listed. Each Work Item price
provided is to become an integral part of the Bid Total amount.
5.02 Bidder understands that each Work Item shall include all related Site Work, Demolition, Structural, Process, Electrical, Instrumentation and Control work necessary to produce/deliver each Work Item in accordance with the Contract Documents and as a complete and fully functional facility improvement.
5.03 Bidder acknowledges that the Work is funded by the Michigan Economic Development Corporation (MEDC) in the form of an Infrastructure Capacity Enhancement (ICE) Grant.
5.04 Bidder will complete the Work in accordance with the Contract Documents for the following
price(s):
Item
No. Work Area Unit Qty Unit Price Amount
1 General Conditions (5% Max) LS 1 $ $
2 Temporary Soil Erosion and Sedimentation Control LS 1 $ $
3 Preconstruction Video LS 1 $ $
4 Surface Restoration SYD 15,500 $ $
5 Bioretention Pond LS 1 $ $
6 Strip Topsoil at Ex. Roadways, Side Slopes & New HMA Area CYD 6,000 $ $
7 Measurement of Topsoil Removal (Allowance) LS 1 $ 3,000.00 $ 3,000.00
8 Granular Subbase, 6 inch (under lagoon roadway) SYD 7,800 $ $
9 Granular Subbase, 12 inch (under new HMA) SYD 1,050 $ $
10 Aggregate Base, 6 inch (under new HMA) SYD 1,050 $ $
834310 00 41 00 - 4 BID FORM ADDENDUM NO. 3
11 HMA Mix, Base Course, 3C SYD 1,050 $ $
12 HMA Mix, Top Course, 4C SYD 1,050 $ $
13 Aggregate Surface Course, 6 inch, at Lagoons SYD 7,800 $ $
14 Aggregate Surface Course, 6 inch, access road to lagoons SYD 2,900 $ $
15 Concrete Sidewalk, 6 inch SFT 240 $ $
16 Salvage Ex Pump Station Equipment LS 1 $ $
17 Salvage Ex Generator EA 1 $ $
18 Salvage Ex Electrical Panel EA 1 $ $
19 Abandon Ex Pump Station and Wet Well, Fill, and Cap LS 1 $ $
20 Pump Station Building LS 1 $ $
21 Wet Well LS 1 $ $
22 Install Owner Supplied Equipment in Wet Well LS 1 $ $
23 Valve Chamber LS 1 $ $
24 Meter Pit LS 1 $ $
25
Control Structure A, including stop plates, pipe fittings, and fiberglass grating LS 1 $ $
26
Control Structure B, D, & F including Gate Valves, hatch, and removal of existing EA 3 $ $
27 Remove and replace slide gate, 12 inch EA 3 $ $
28 Remove and replace slide gate, 18 inch EA 3 $ $
29 Sludge Removal - Lagoon #1 LS 1 $ $
30 Sludge Removal - Lagoon #2 LS 1 $ $
31 Sludge Removal - Lagoon #3 LS 1 $ $
32 Transfer Water to Appropriate Lagoon LS 1 $ $
33 Remove Ex Concrete at Lagoon Interior Slopes SYD 6,000 $ $
34 Embankment, Clay (Side Slopes and roadway) CYD 5,000 $ $
35 Measurement of Clay Embankment (Allowance) LS 1 $ 3,000.00 $ 3,000.00
36 Clay Compaction Testing (Allowance) LS 1 $ 5,000.00 $ 5,000.00
834310 00 41 00 - 5 BID FORM ADDENDUM NO. 3
37 Rip-Rap at Lagoons (Armor Stone), 9 inch including Geotextile Fabric SYD 23,500 $ $
38 Remove and Salvage Ex 15 inch Gate Valve EA 2 $ $
39 Remove Ex Sanitary Sewer, 12 inch, Outfall Pipe LF 197 $ $
40 Remove Ex Sanitary Sewer, 15 inch, Transfer Pipe LF 116 $ $
41 Remove Ex Sanitary Sewer, 18 inch, Outfall Pipe LF 1,050 $ $
42 Sanitary Sewer, 10 inch LF 50 $ $
43 Sanitary Sewer, 12 inch, from Control Structure A to Treatment Cells 1, 2, & 3 LF 870 $ $
44 Sanitary Sewer, 12 inch, decant pipe LF 160 $ $
45 45° Bend, 12 inch EA 11 $ $
46 Sanitary Sewer, 12 inch, overflow pipe LF 90 $ $
47 Sanitary Sewer, 12 inch, outfall pipe LF 160 $ $
48 Sanitary Sewer, 15 inch LF 90 $ $
49 Sanitary Sewer, 12 inch, transfer pipe LF 120 $ $
50 Sanitary Sewer, 18 inch, outfall pipe LF 1,050 $ $
51 Sanitary Manhole, 4 foot dia EA 1 $ $
52 Connect to Existing Manhole, 10 inch EA 1 $ $
53 Connect to Existing Seepage Chambers, 12 inch EA 6 $ $
54 Connect to Existing Manhole, 15 inch EA 1 $ $
55 Connect to Existing Seepage Chambers, 18 inch EA 5 $ $
56 Connect to Existing Parshall Flume, 18 inch EA 2 $ $
57 Connect to Existing Chlorine Building, 12 inch EA 1 $ $
58 Plug Ex San Sewer, 10 inch EA 1 $ $
59 Plug Ex San Sewer, 15 inch EA 1 $ $
60 Gate Valve, 12 inch, at Transfer Pipe EA 2 $ $
61 Gate Valve, 12 inch, at Outfall EA 1 $ $
62 90° Bend, 12 inch EA 3 $ $
63 45° Bend, 12 inch EA 2 $ $
834310 00 41 00 - 6 BID FORM ADDENDUM NO. 3
64 Force Main, 8 inch, Open Cut LF 600 $ $
65 Force Main, 8 inch, Directionally Drilled LF 750 $ $
66 45° Bend, 8 inch EA 2 $ $
67 Lateral, 8" x 8" EA 1 $ $
68 Cut and Plug Ex. Force Main and fill with flowable fill, 8 inch EA 3 $ $
69 Gate Valve and Box, 8 inch EA 1 $ $
70 Bypass Cleanout, 8 inch EA 2 $ $
71 Remove Ex Culvert, 15 inch LF 90 $ $
72 Storm Sewer, 10 inch, PVC LF 40 $ $
73 Storm Sewer, 12 inch, PVC LF 50 $ $
74 Culvert, 48 inch, CMP LF 20 $ $
75 Connect to existing storm sewer EA 2 $ $
76 Rip-Rap at Outlets, 12 inch SYD 125 $ $
77 Remove 6' Chainlink Fence & Gate LF 1,320 $ $
78 Chain Link Fence, 6 foot LF 1,400 $ $
79 Chain Link Operable Gate EA 1 $ $
80 Temporary Haul Road LS 1 $ $ BID TOTAL: ($ ) (use words) (use figures) ARTICLE 6 – TIME OF COMPLETION 6.01 Bidder agrees that the Work will be substantially complete and will be completed and ready
for final payment in accordance with the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.
6.02 Bidder accepts the provisions of the Agreement as to liquidated damages.
6.03 TIME ALTERNATE:
If Bidder takes exception to the Contract Time(s) stipulated in the Agreement, Bidder is requested to stipulate below his proposed alternate time(s) and completion dates for performance of the Work.
834310 00 41 00 - 7 BID FORM ADDENDUM NO. 3
ARTICLE 7 – SUBCONTRACTOR LISTING: 7.01 Bid is submitted on the basis of the use of the following Subcontractors and Suppliers:
WORK ITEM FIRM CITY
Sludge Removal
Building Construction
Electrical
Paving
Rip Rap Materials
Site Restoration
Please note for each work item, if work is to be performed by Bidder or Subcontractor. If by Subcontractor, provide name and City for each Subcontractor. Failure to list Subcontractors with the Bid waives Bidder's rights to a change in Contract Time or Price or withdrawal of Bid and Bid Security, in the event OWNER has reasonable objections to any Subcontractor. If Subcontractors are not identified above, OWNER shall have the right to reject any Subcontractor for reasonable cause. In this case, the apparent low Bidder shall engage a Subcontractor acceptable to OWNER and waives the right to withdraw Bid and Bid Security, and further, waives right to a change in Contract Time or Price due to failure to list.
ARTICLE 8 – ATTACHMENTS TO THIS BID 8.01 The following documents are submitted with and made a condition of this Bid:
A. Required Bid security;
B. List of Proposed Subcontractors;
C. List of Proposed Equipment Suppliers;
D. Evidence of authority to do business in the state of the Project; or a written covenant to obtain such license within the time for acceptance of Bids;
ARTICLE 9 – DEFINED TERMS 9.01 The terms used in this Bid with initial capital letters have the meanings stated in the
Instructions to Bidders, the General Conditions, and the Supplementary Conditions. ARTICLE 10 – BID SUBMITTAL
834310 00 41 00 - 8 BID FORM ADDENDUM NO. 3
10.01 This Bid is submitted by:
If Bidder is: An Individual Name (typed or printed): By:
(Individual’s signature) Doing business as: A Partnership Partnership Name: By: (Signature of general partner -- attach evidence of authority to sign) Name (typed or printed): A Corporation Corporation Name: (SEAL) State of Incorporation: Type (General Business, Professional, Service, Limited Liability): By: (Signature -- attach evidence of authority to sign) Name (typed or printed): Title: (CORPORATE SEAL) Attest
Date of Qualification to do business in Michigan is ____/____/_________.
A Joint Venture Name of Joint Venture: First Joint Venturer Name: (SEAL) By: (Signature of first joint venture partner -- attach evidence of authority to sign)
834310 00 41 00 - 9 BID FORM ADDENDUM NO. 3
Name (typed or printed): Title: Second Joint Venturer Name: (SEAL) By: (Signature of second joint venture partner -- attach evidence of authority to sign) Name (typed or printed): Title:
(Each joint venturer must sign. The manner of signing for each individual, partnership, and corporation that is a party to the joint venture should be in the manner indicated above.)
Bidder's Business Address Phone No. _____________________________________ Fax No. E-mail ________________________________________ SUBMITTED on , 20____. State Contractor License No. (where applicable).
END OF SECTION
SP 01 22 00 01 22 00 - 1 MEASUREMENT AND PAYMENT
SECTION 01 22 00
MEASUREMENT AND PAYMENT PART 1 - GENERAL 1.01 SUMMARY:
A. This Section includes, but is not necessarily limited to, descriptions of the method of measurement and basis of payment criteria applicable to the Work. It also includes the form of Application for Payment to be used by CONTRACTOR in requesting payment for Work performed under the Contract.
1.02 SUBMITTALS:
A. Application for Payment: Submit three (3) copies to ENGINEER on the attached form or related format with supporting documentation as required by the Contract Documents.
1.03 MEASUREMENT OF QUANTITIES:
A. Measurement devices: 1. Weigh scales: Inspected, tested and certified. 2. Platform scales: Of sufficient size and capacity to accommodate the conveying
vehicle. 3. Metering devices: Inspected, tested and certified.
B. Measurement by volume: Measured by cubic dimension using mean length, width and
height or thickness.
C. Measurement by area: Measured by square dimension using mean length and width or radius.
D. Linear measurement: Measured by linear dimension, at the item centerline.
1.04 MEASUREMENT AND PAYMENT SCHEDULE:
A. The following schedule outlines the method of measurement and basis of payment to be used on the project. Requirements for materials and methods described under each item are included in the related specification SECTION.
1. Inspection and testing fees: Payment by OWNER, unless specifically noted
otherwise.
2. General Conditions, Bonds, Insurance and Mobilization: Shall be paid for on a lump sum basis for the CONTRACTOR’s costs to provide required bonds and insurances, mobilization and miscellaneous requirements stipulated in Section 00 72 00 – GENERAL CONDITIONS. This quantity shall not exceed 5% of the total contract amount. Fifty percent (50%) will be paid on the first Application for Payment and twenty five percent (25%) will be paid on the second and third Applications for Payment.
3. Above ground video survey: Lump sum complete and delivered to OWNER.
SP 01 22 00 01 22 00 - 2 MEASUREMENT AND PAYMENT
4. Shoring: All shoring required for construction, safety and convenience will be considered temporary and included in construction items.
5. Dewatering for Construction: Payment by CONTRACTOR and included in
construction items. 6. Temporary soil erosion and sedimentation control: Paid for as a lump sum to provide
temporary soil erosion and sedimentation control per the plans. 7. Granular material trench backfill: Include in cost of utility. 8. Bedding area trench backfill: Include in cost of utility.
9. Strip Topsoil: Measured and paid for by the cubic yard in place. Measurement by the
ENGINEER will be completed by a detailed survey of surface before and after removal of top soil (see allowance). Volumes will be determined by survey data utilizing CAD software.
10. Remove Existing Concrete: Measured and paid for by the square yard rip rap
removed.
11. Transfer Water: Paid for as a lump sum to transfer water to available lagoon cells per the sequence of construction in section 01 11 00. This includes labor and equipment for all transfers required to work on all cells.
12. Sludge Removal: Paid for as a lump sum for removing the sludge of each lagoon per
the sequence of construction in section 01 11 00.
13. Clay Embankment: Measured and paid for by the cubic yard compacted in place. Measurement by the ENGINEER will be completed by a detailed survey of surface before and after placement of clay (see allowance). Volumes will be determined by survey data utilizing CAD software.
14. Clay Compaction Testing: Paid for as a lump sum for compaction testing of clay
embankment by the ENGINEER (see allowance).
15. Control Structure: Paid for as a each control chamber installed including removal of existing structure and wood walkway, new concrete structure, gate valves, hatches
and/or grating, connection of piping.
16. Slide Gate Replacement: Counted and paid for each slide gate that is replaced
by size.
17. Surface restoration: Measured and paid for by the square yard. Grading, topsoil surface (4”), seeding, fertilizing and mulch are included as part of this item. See limits on plan.
18. Granular subbase: Calculated from the proposed roadway section and paid for by the
square yard for specified thickness, compacted in place where used and authorized by the ENGINEER.
19. Aggregate base and surface course: Measured and paid for by the square yard for
specified thickness, placed and compacted.
SP 01 22 00 01 22 00 - 3 MEASUREMENT AND PAYMENT
20. Bituminous mix (base and top courses): Measured and paid for by the square yard, placed and compacted at the specified thickness.
21. Concrete sidewalk: Measured and paid for by the square foot for specified thickness.
22. Miscellanious concrete items: Counted and paid for each concrete items placed
including reinforcing and embeds. 23. Chain Link Fence: Measured and paid for by the linear foot by the fence height,
installed. 24. Chain Link Operable Gate: Measured and paid for each operable chain link gate
installed including motor and controls.
25. Remove Chain Link Fence: Meaured and paid for by the linear foot for fence and gate removed including any concrete footings.
26. Adjustment of castings between successive paving courses: Include in cost of
structure or bituminous mix. 27. Storm sewer pipe: Measured horizontally on the surface along the pipe centerline
from center to center of structures and paid for by the linear foot by the pipe size and classification, installed and backfilled.
28. Storm sewer culvert: Measured horizontally on the surface along the pipe centerline
and paid for by the linear foot by the pipe size and classification, installed and backfilled.
29. Rip rap and armor stone: Measured and paid for by the square yard placed,
including geotextile fabric below the rip rap and armor stone, toed in place for each size and thickness of rip-rap specified.
30. Remove existing storm sewer and culvert: Measured and paid for by the linear foot
removed, including excavation, backfill and disposal of the pipe removed. 31. Connect to existing storm sewer: Counted and paid for by the unit including removal
of existing plug or bulkhead and furnishing adapter fittings, if necessary. 32. Sanitary sewer pipe: Measured horizontally on the surface along the pipe centerline
from center to center of manholes and paid for by the linear foot by the pipe size and type, installed, backfilled and accepted.
33. Standard sanitary manhole: Counted and paid for by the unit, including drop
connections and manhole casting, installed and backfilled. 34. Connect to existing sanitary manhole or structure: Counted and paid for by the unit,
including coring of existing manhole and related work. 35. Remove existing sanitary sewer: Measured and paid for by the linear foot removed,
including excavation, backfill and disposal of pipe removed.
36. Remove and salvage existing sanitary gate valves: Paid for each gate valve removed by size specified and delivery to location directed by OWNER.
SP 01 22 00 01 22 00 - 4 MEASUREMENT AND PAYMENT
37. Abandon and fill existing sanitary wet well and pump chamber: paid for by the lump sum including removing the existing building, removing the top four (4) feet of the manholes, plugging openings, filling the manholes with granular material, and placing concrete cap.
38. Force main pipe: Measured horizontally on the surface along the pipe centerline and
paid for by the linear foot, installed, backfilled and accepted. 39. Deleted
40. Force main fittings: Counted and paid for by the unit, including reaction backing,
restraints and related work. 41. Force main valve and box: Counted and paid for as a unit.
42. Cut and Plug existing force main: Counted and paid for each section of pipe cut and
plugged as specified including flowable fill. 43. Salvage existing pump station equipment: Paid for as a lump sum including removal
of existing equipment and delivery to location directed by OWNER. 44. Salvage existing electrical equipment: Paid for each unit removed and delivered to
location directed by OWNER.
45. Bioretention Pond: Paid for as a lump sum including excavation, backfill, underdrain, overflow structure and casting, grading, geotextile fabric, and plantings.
46. Pump Station Building: Paid for as a lump sum including footings, framing, siding,
roofing, insulation, windows, doors and hardware, manual hoist, station piping, electrical work, installation of OWNER furnished instrumentation, VFD’s and controls, HMA, site work, sidewalks, excavation and backfill, stone swale, and other related items.
47. Wet Well: Paid for as a lump sum including excavation, backfill, precast concrete structure, hatch(es), fillets, and piping as shown on the plans.
48. Wet Well Equipment: Paid for as a lump sum including installation of pumps, guide rails, transducer, floats and all other OWNER supplied equipment within the wet well.
49. Valve Chamber: Paid for as a lump sum including excavation, backfill, precast concrete structure, hatch(es), piping, fittings, and valves as shown on the plans.
50. Meter Pit: Paid for as a lump sum including excavation, backfill, precast concrete structure, hatch(es), piping, and meter as shown on the plans.
51. Temporary Haul Road: Provide a temporary haul road along the west side of
the Lagoons for sludge removal. Remove when no longer needed. Restore per
section 32 92 00
PART 2 - PRODUCTS Not Used. PART 3 - EXECUTION
SP 01 22 00 01 22 00 - 5 MEASUREMENT AND PAYMENT
3.01 FORMS:
A. Attached are the following forms:
1. Application for Payment. 2. Schedule of Values.
3.02 SCHEDULES (N/A):
END OF SECTION
SP 01 22 00 01 22 00 - 6 MEASUREMENT AND PAYMENT
APPLICATION FOR PAYMENT NO.
To: (OWNER)
From: (CONTRACTOR)
Contract:
Project:
OWNER’s Contract No. ENGINEER’s Project No.
For Work accomplished through the date of: .
1. ORIGINAL CONTRACT PRICE: $
2. Net change by Change Orders: $
3. Current Contract Price (1 plus 2): $
4. TOTAL COMPLETED AND STORED TO DATE: $
5. RETAINAGE:
% of completed Work: $
% of Contract Price: $
% of stored material: $
Total Retainage: $
6. Total completed and stored to date less retainage (4 minus 5): $
7. LESS PREVIOUS PAYMENTS: $
8. AMOUNT DUE THIS APPLICATION (6 MINUS 7): $
Accompanying Documentation: CONTRACTOR’S Certification: The undersigned CONTRACTOR certifies, to the best of its knowledge, the following: (1) All previous progress payments received from OWNER on account of Work done under the Contract have been applied on account to discharge CONTRACTOR’s legitimate obligations incurred in connection with the Work covered by prior Applications for Payment; (2) Title to all Work, materials and equipment incorporated in said Work, or otherwise listed in or covered by this Application for Payment, will pass to OWNER at time of payment free and clear of all Liens, security interests, and encumbrances (except such as are covered by a bond acceptable to OWNER indemnifying OWNER against any such Lien, security interest, or encumbrances); and (3) All Work covered by this Application for Payment is in accordance with the Contract Documents and is not defective. Dated:
CONTRACTOR
By: Authorized Signature
Printed or Typed Name ENGINEER’s Recommendation: Payment of the above AMOUNT DUE THIS APPLICATION is recommended. Dated
ENGINEER
By: Authorized Signature
Printed or Typed Name
Application No. Date:
ITEM UNIT PRICE
ESTIMATED QUANTITY
SCHEDULE OF VALUES AMOUNT
QUANTITY COMPLETED
AMOUNT % MATERIAL STORED
AMOUNT COMPLETED AND STORED
1. $ $ $ $ $
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
TOTAL $ $ $ $ $
Note: Total Schedule of Values Amount should equal the current Contract Price.
834310 06 74 13 - 1 FIBERGLASS GRATINGS
SECTION 06 74 13
FIBERGLASS REINFORCED GRATINGS
PART 1 - GENERAL
1.01 SUMMARY:
A. Section includes: 1. This Section includes, but is not necessarily limited to, the furnishing and installation
of fiberglass reinforced gratings and related equipment as indicated on the Drawings, as specified herein, and as necessary for the proper and complete performance of the Work.
B. Related Sections: 1. Documents affecting work in this Section include, but are not necessarily limited to:
a. General Conditions, Supplementary Conditions and Sections in Division 1 of these Specifications.
1.02 DESIGN AND PERFORMANCE REQUIREMENTS:
A. Design criteria:
1. Live load: 100 psf. 2. Allowable deflection: 1/8-inch.
1.03 SUBMITTALS
A. Submit in accordance with Section 01 33 00 - Submittals. B. Samples:
1. Submit a 1’-0” square Sample of fiberglass grating for review prior to ordering.
C. Shop Drawings: 1. Submit for fiberglass reinforced grating. 2. Required information:
a. Dimensions. b. Details. c. Required field measurements. d. Fabrication and installation tolerances.
D. Certificates:
1. Submit for fiberglass reinforced grating. 2. Submit manufacturer’s certification that materials meet Specification requirements.
1.04 QUALITY ASSURANCE
A. Qualifications:
1. Fabrication and installation personnel: a. Trained and experienced in the fabrication and installation of the materials and
equipment. b. Knowledgeable of the original design and the reviewed Shop Drawings.
834310 06 74 13 - 2 FIBERGLASS GRATINGS
PART 2 - PRODUCTS
2.01 MANUFACTURERS:
A. Fibergrate Corporation, Dallas, Texas. B. Imco Reinforced Plastics, Inc., Moorestown, New Jersey. C. Strongwell Corporation (formerly Morrison Molded Fiber Glass Company), Bristol, VA. D. or ENGINEER approved equal.
2.02 MATERIALS:
A. Gratings: 1. Fiberglass reinforced polyester. 2. Bearing and cross bars: 2 inches deep, 2 inches on center. 3. Color: Grey or reviewed equal. 4. Deck: 3/16 inch plate with anti-slip surface where indicated on the Drawings.
B. Fiberglass resin: Type suitable for outside usage. C. Hold down clips:
1. J-type standard stainless steel with stainless steel nut, bolt and washer. 2. Four feet on center each edge. 3. Minimum four per panel.
D. Other materials:
1. Other materials not specifically described but required for a complete and proper installation of fiberglass gratings shall be new, first quality of their respective kinds, and as selected by the CONTRACTOR subject to the review of the ENGINEER.
2.03 FABRICATION:
A. Field measurements and dimensions: 1. Field measure dimensions prior to fabrication 2. Fabricate gratings to the field dimensions with tolerances as indicated on the
reviewed shop drawings. B. Cut or sanded surfaces:
1. Coat cut or sanded surfaces with resin which contains air inhibiting additives. C. Fabricated assemblies requiring 2 or more of the following components shall be
fabricated by a single fabricator: 1. Grating. 2. Railing. 3. Structural shapes.
834310 06 74 13 - 3 FIBERGLASS GRATINGS
PART 3 - EXECUTION
3.01 INSTALLATION
A. Install gratings, support frames and related materials in conformance with: 1. The shop drawings reviewed by the ENGINEER. 2. The Manufacturer’s recommendation.
B. Field drill holes in supporting members for hold down clips and touch up supporting
members in conformance with Section 09 90 00 – Painting and Coating. C. Cut panels to a tolerance of plus or minus 1/8-inch from dimensions shown on Shop
Drawings.
D. Maximum allowable gap between panels: ½-inch.
E. Cut panels to provide continuous banding bar around panels.
F. Cut openings for piping, conduit, and other penetrations. 3.02 FIELD QUALITY CONTROL:
A. Remove defective work and replace with materials that meet Specification requirements.
3.03 CLEANING:
A. Clean materials installed under this Section in accordance with Section 01 74 00 –Cleaning and Waste Management.
END OF SECTION
834310 26 60 03 - 1 SUBMERSIBLE PROBE CONTROL SYSTEM FOR PUMP STATION WITH SPEED CONTROL
SECTION 26 60 03
SUBMERSIBLE PROBE CONTROL SYSTEM FOR PUMP STATION WITH SPEED CONTROL [Two Pump System]
PART 1 - GENERAL 1.01 SUMMARY:
A. Section includes: 1. This Section includes, but is not necessarily limited to, the installation of an OWNER
supplied submersible probe control system as indicated on the Drawings, as specified herein, and as necessary for the proper and complete performance of the Work.
1.02 SYSTEM DESCRIPTION:
A. Submersible Probe Control: 1. The pumps shall be controlled by a submersible probe suspended in the pump chamber
and a programmable logic controller (PLC) and a Human Machine Interface (HMI). Floats shall serve as a back-up control system. All control circuits in wet well shall be intrinsically safe.
2. Sequence of Operation: a. All elevations and setpoints described in operations sequence below shall be operator
adjustable from the HMI on the front of the pump station control panel. 1) Scale the level transducer to “0.00-10.00 feet". All setpoint adjustments shall be
in 0.01' increments. b. Operations Sequence
1) As the water level in the wet well rises to the elevation shown for “First Pump On”, the first pump shall be activated. The first pump shall stay on until the level is pumped down to first pump off level.
2) If the water level in the wet well rises to the elevation shown for “Second Pump On”; the second pump shall be activated. The second pump shall stay on until the level is pumped down to the second pump off elevation.
3) Program an operator adjustable on and off setpoint level in feet for both pumps. The titles of each and shall be: a. First Pump "On 730.60 Feet, Off 728.60 Feet". b. Second Pump "On 731.00 Feet, Off 729.60 Feet"
4) If the water level in the wet well rises to the high water level, an alarm shall be activated. Program an operator adjustable trip and reset setpoint level in feet for the high level alarm. The titles shall be: a. High Level Alarm "Trip 731.60 Feet, "Reset 731.35 Feet".
5) If the water level in the wet well decreases to the level shown as low level, the low level alarm will be activated. Low level alarm shall provide redundant “Off” for all pumps. Program an operator adjustable trip and reset setpoint level in feet for the low level alarm. The titles shall be: a. Low Level Alarm "Trip 726.60 Feet, "Reset 726.85 Feet ".
6) A backup level control using a start and stop float switch will serve as a redundant level control in the event of a PLC failure. Program the Variable Frequency Drives (VFD) to recognize PLC failure as input out of range (less than 4 mA or more than 20 mA) and go to 60 Hz speed. The back up level control shall start both pumps in sequence with a short time delay as shown on drawings.
c. Automatic Mode Speed Control: 1) Both pumps are controlled by variable frequency drives (VFD) and the PLC when
the HMI HAND-OFF AUTO switch is placed in the AUTO mode of operation. Program the PLC analog output range and VFD input range to 30 Hz equals
834310 26 60 03 - 2 SUBMERSIBLE PROBE CONTROL SYSTEM FOR PUMP STATION WITH SPEED CONTROL
minimum speed or 4 mA speed reference input and 60 Hz equals maximum speed or 20 mA speed reference input.
2) Program an operator adjustable minimum and maximum speed setpoint levels in feet for both pumps. The titles of each shall be: a. Speed One Pump, "Min Speed X.XX Feet, Max Speed X.XX Feet". b. Speed Two Pumps, "Min Speed X.XX Feet, Max Speed X.XX Feet".
3) Regardless of how many pumps are being called to run all pumps will run at the same speed. As the wet well level increases the output speed will increase proportionally between the minimum speed setpoint and maximum speed setpoint. As the liquid level decreases, the speed signal shall be reduced proportionally until the minimum speed setpoint is reached.
4) Independent of the PLC controls, minimum pump speed limit must be set in the VFD at startup to 40 Hz using the design basis of 1,000 GPM Pump. This number may change depending on pump supplied under this contract. This VFD parameter will prevent the operator from setting the speed of the pump too low and out of the performance curve range.
5) Program a 24 hour clock in the PLC that at 24:00 hours adjustable, will run whichever pump is online at 100 percent until it reaches the off set point. Then reset the 24 hour clock and begin the cycle again. This will prevent a single pump from running more than one day and not exercising the other pumps. This also serves to evacuate the force main of any solids that may have settled during the 24 hour period.
d. Hand Mode Speed Control: 1) If either of the pumps are selected to be operated in HAND mode a dry contact
input between the HMI HAND-OFF-AUTO switch shall be a PLC input to indicate the pump was placed in the HAND mode of operation. This shall force the PLC output to 20 mA so the selected pump will run at full speed.
e. Pump Alternation: 1) Both pumps shall be automatically alternated in sequence as determined by the
automatic alternator in the PLC and the HMI screen. Program a "Next To Run" indicator on the HMI screen. In the Manual Mode the operator will select what the fixed sequence shall be. This permits a pump to be moved to a lesser priority in the sequence while they may be taken out of service. In the manual mode the operator will select between 1-2 or 2-1 sequence on the HMI.
2) The two modes of operation for the alternator shall be "Automatic" and "Manual". B. HMI Pilot Devices:
1. Program the HMI with the following pilot devices and operator adjustable control parameters. a. HAND-OFF-AUTO switch (each pump). b. Run Indicator (each pump). c. Elapsed Time Meter (each pump). d. 24 Hour Pump Run Clock. e. Lead Lag Selector f. Pump On and Off Setpoints g. Speed Control Minimum and Maximum Setpoints.
C. Hard Wired Pilot Devices: 1. Provide the following hard wired pilot devices on the control panel door front
a. Back Up Level Control On-Off Switch and Red Indicator Light b. High Level Alarm Float Red Indicator Light c. Power Failure Red Indicator Light d. Alarm Reset Pushbutton e. Pump Overtemperature Red Indicator Light (each pump).
834310 26 60 03 - 3 SUBMERSIBLE PROBE CONTROL SYSTEM FOR PUMP STATION WITH SPEED CONTROL
D. Alarm System: 1. Local Alarms: Program the HMI with the following alarm conditions.
a. High wet well water level. b. Power outage. c. Low wet well water level. d. Pump seal failure (each pump). e. Pump overtemp (each pump). f. Back-up control on. g. Lag Pump Ran (anytime the second pump is called to run). h. Pump Station On Generator Power i. Generator Fail
2. Station Alarms: The exterior station alarm light shall be energized by the following: a. High wet well level. b. Backup control on. c. Low wet well level.
3. Remote Alarms: The following alarm conditions shall be monitored remotely by Kennedy Industries, KISM. a. High wet well water level. b. Power outage. c. Low wet well water level. d. Pump seal failure (each pump). e. Pump overtemp (each pump). f. Back-up control on. g. Lag Pump Ran. h. Pump Station On Generator Power i. Generator Fail.
1.03 SUBMITTALS AND OPERATION AND MAINTENANCE DATA:
A. Submit under provisions of Section 01 33 00: Submittals. B. Certification of approval by U.L. to fabricate Industrial Control Panels (i.e., UL Form 3000-387).
1. Shop Drawings and Manufacturers Data:
a. Float switches b. All equipment and electrical enclosures c. Control Enclosures
C. Schematic Drawings and Wiring Diagrams using quality control manufacturer’s standards with
ladder diagram type, numbered logic rungs, numbered wires and terminations, contact references by type and line, detailed bill of material and equipment layout showing all components for the following: 1. Pump control systems. 2. Equipment enclosures. 3. Pump station control circuitry.
D. Proposed wiring color code. E. Proposed HMI Screens.
F. Provide Operations and Maintenance Data from Control Panel in accordance with Section 01 33 00: Submittals.
PART 2 - PRODUCTS
834310 26 60 03 - 4 SUBMERSIBLE PROBE CONTROL SYSTEM FOR PUMP STATION WITH SPEED CONTROL
2.01 Custom manufactured equipment (the control panel) shall be listed as an Industrial Control Panel (UL698A) or by another nationally recognized testing laboratory. Control panel manufacturer must have at least 5 years experience designing and constructing control panels used in the wastewater field.
2.02 RELAYS:
A. Time Delay: 1. Electric type.
2. Delay on energize as necessary. a. Minimum contact rating 10 ampere at 120 volt A.C. b. Design based on Diversified Electronics TSC-100 Series. ENGINEER approved equal
performance by Square D or Magnacraft acceptable.
B. Control: 1. Miniature plug-in type.
2. Minimum contact rating 10 ampere at 120 volt A.C. with necessary contacts as shown on drawings.
3. Square D, Potter Brumfield or ENGINEER approved equal. 2.03 FLOAT SWITCHES:
A. Hermetically sealed mechanical tilt with 60-foot suspension cable rated at a minimum of 13 ampere at 120 volt A.C.
B. SPST contact.
C. Corrosion resistant poly-propylene float, leakproof, shockproof, and corrosion resistant to
sewage. D. Shorter length suspension cords may be furnished provided they have sufficient length to reach
junction box without splice.
E. Design based on Gems/Warrick MBLU60W and MYEL60W. ENGINEER approved, equal features and product by Connery or SJE acceptable.
2.04 FLOAT SWITCH CONTROL RELAYS:
A. Intrinsically safe type. B. Minimum 2 independent contact. C. Maximum switching sensitivity of 10,000 ohms. D. Manufacturers: Design based on Warrick, Stahl, Crouse Hinds, Diversified Electronics or
ENGINEER approved equal. 2.05 POWER FAILURE RELAY:
A. Shall be able to monitor 3 phase, 480 volt with usually closed (closed with normal energized
power) 120 volt contact the control circuit, DPDT contacts.
B. Manufacturers: Time Mark B252B, Diversified Electronics or ENGINEER approved equal.
834310 26 60 03 - 5 SUBMERSIBLE PROBE CONTROL SYSTEM FOR PUMP STATION WITH SPEED CONTROL
2.06 CONTROLS FOR PUMP STATIONS:
A. Each pump shall be equipped with manual reset overload protection, lockout capable door or flange mounted circuit breaker mechanism, 6 digit elapsed time meters, relays, run lights, HOA switches with auto auxiliary contacts, cooling fans and Variable Frequency Drives.
B. Pump alternation shall be automatic.
C. Submersible pump station controls shall be mounted on a wall or floor mount NEMA 1
or 12 Painted Steel Enclosure.
2.07 FINISHES
A. Provide baked enamel finishes on exposed surfaces. B. Provide galvanized finishes for damp or wet locations.
C. Touch up or refinish damaged paint.
2.08 DELETED: 2.09 ACCESSORIES FOR CONTROL PANELS:
A. Nameplates: Minimum 1 inch x 3 inch white plastic with engraved black lettering.
B. Motor Nameplate: Obtain loose pump motor nameplate from pump supplier and affix to control
panel interior adjacent to controls for each pump with screws.
C. Pilot and Alarm Lights: 120 volt transformer type, push to test, 60 Hertz, with plastic lens and
color matched rings; furnish special tools for lamp replacement, if required.
D. Selector Switches and Push Buttons: Rated oil-tight not less than 120 volt, 10 ampere, 60
Hertz with maintained or momentary contacts as required. Provide legend plates "HAND-OFF-AUTO" or as shown on drawings.
2.10 PUMP STATION ADJUSTABLE FREQUENCY DRIVE (VFD) CONTROLS:
A. Provide solid state AC adjustable frequency controllers to provide stepless variable speed over a 30 percent to 100 percent of motor base 60 hertz speed range the pumps, horsepowers as indicated on drawings. Drive must be capable of segmented starting and stopping. 1. Start segment one range of 0-60 Hz adjustable, with an adjustable ramp time of 0-120
seconds. Program start segment one to go from 0-45 Hz in 2 seconds. 2. Start segment two range of 0-60 Hz adjustable, with an adjustable ramp time. Program
start segment two to go from 46-60 Hz in 30 seconds. 3. Stop segment one range of 60-0 Hz, adjustable with an adjustable ramp time of 0-120
seconds. Program stop segment one to go from 60-46 Hz in 30 seconds. 4. Stop segment two range of 60-0 Hz, adjustable with an adjustable ramp time. Program
start segment two to go from 45-0 Hz in 2 seconds.
B. The VFD shall be capable of running constant torque loads due to their nature with sewage pumps. 1. Provide with thermal and magnetic circuit breaker sized to VFD input. Provide padlocking
in “OFF” position. Operating voltage shall be 480 V, 3 phase as shown on drawings.
834310 26 60 03 - 6 SUBMERSIBLE PROBE CONTROL SYSTEM FOR PUMP STATION WITH SPEED CONTROL
C. Speed regulation with 100 percent load change shall be within 3 percent of maximum speed.
D. Power factor of motor and controller combined shall be a minimum of 0.90 lagging over entire speed and load range.
E. Service factor of combination motor and controller shall be a minimum of 1.15.
F. Designed to operate on 480 volt AC +/- 10 percent, 3 phase, 60 hertz input.
G. Control Signal: 4-20 mA from control panel (in automatic mode).
H. Input Protection: Provide internal DC link reactors to minimize power line harmonics and to
provide near unity power factor. DC link reactor shall be installed so that power fluctuations to the DC Capacitors shall be reduced to increase capacitor life. VFD's without a DC link reactor shall provide a 5% impedance line side reactor. 1. Phase sequence protection. 2. Protection during single phasing or loss of input. 3. Undervoltage trip provides shutdown in event of power drop or interruption. Automatic
reset. (Auto restart in ON position). 4. Input fusing, provide thermal mag circuit breaker with flange or door mounted lockoutable
disconnect switch. 5. Current limit, adjustable 100 percent – 50 percent of rated motor current. 6. Transient suppression protects components from line notching and spikes. 7. Input current shall not exceed 150 percent of motor full load current at start up.
I. Provide keypad mounted on cabinet panel door to display drive parameters, run status and
alarms. J. Install OWNER supplied VFD and NEMA 1 Enclosure with all components shown on
wiring diagrams. Provide door operated or flange mounted disconnect switch capable of being locked in the open position connected to VFD circuit breaker.
K. Entire variable frequency drive assembly shall carry UL508 listing.
L. Manufacturers: Design basis VFD is ABB or ENGINEER approved equal by Rockwell
Automation, Yaskgowa, Eaton, GE or Square D. 2.11 LOW VOLTAGE, LIGHTING AND POWER CONDUCTORS:
A. Identify each end of each conductor by wire marking tape or sleeve. This includes splice points
at all junction boxes. Mark on outer cover giving loop number and/or discrete wire number. B. Conductors provided on 120/240 and 480 volt power and control systems to be stranded per
ASTM B-8 soft drawn copper.
C. Insulation system shall be type THHN for field and MTW for panel, rated 600V as defined and listed in Article 310 of NEC.
D. Minimum size conductor utilized shall be #14 AWG for control circuits and #12 for power and
lighting circuits.
E. Color code conductor insulation as follows: Line Voltage -Black Grounding Conductor -Green Neutral -White
834310 26 60 03 - 7 SUBMERSIBLE PROBE CONTROL SYSTEM FOR PUMP STATION WITH SPEED CONTROL
Control -Red DC Circuits -Blue Voltage from External source -Yellow Intrinsically safe -Light Blue Color shall be integral with the insulation compound applied by cable manufacturer.
2.12 SEAL FAIL RELAYS AND OVERTEMPERATURE RELAYS: A. As recommended and furnished by pump Equipment vendor. Installed by Control Panel
manufacturer. 2.13 EXTERNAL OIL RESERVOIR MONITORING RELAYS: A. As recommended and furnished by pump Equipment vendor. Installed by Control Panel
manufacturer. Must be intrinsically safe. 2.14 PUMP STATION CONTROL PANEL HUMAN MACHINE INTERFACE (HMI):
A. HMI Shall be an integral part of PLC below. Mount OWNER supplied HMI on Pump Station Control Panel Door. All programming and software for HMI by Kennedy Industries.
2.15 PROGRAMMABLE LOGIC CONTROLLERS (PLC):
A. Pump Station Programmable logic controller shall have adequate inputs and outputs to perform
the design sequence of operation plus 10% spares. B. Manufacturer shall be Unitronics Vision 570 with two communications ports and processor
sized to be able to perform design sequence of operation functions or ENGINEER approved equal.
C. All programming and software for PLC by Kennedy Industries. D. Cellular Modem required for communications with SCADA SYSTEM in specification in
40 94 43. 01, shall be provided by the OWNER through Kennedy Industries. Kennedy Industries shall establish communications with OWNERS Cellular Carrier on OWNERS behalf. OWNER shall pay for monthly cellular service charge.
2.16 UNINTERRUPTIBLE POWER SUPPLY (UPS)
A. Furnish UPS in main control panel to provide minimum power supply of 120 vac at 50 watts
for 2 hours. B. UPS must be on line double conversion type. Standby UPS's are not acceptable. C. Connect the aforementioned components in accordance with the Control Circuits on the
drawings. 2.17 WET WELL SUBMERSIBLE PRESSURE TRANSDUCER:
A. Design based on Contegra SLX 130-MIS-5-60T-B or ENGINEER approved equal. B. Provide 60’ suspension cord. Calibrate 0-10'.
2.18 SURGE SUPRESSOR FROM PUMP STATION:
834310 26 60 03 - 8 SUBMERSIBLE PROBE CONTROL SYSTEM FOR PUMP STATION WITH SPEED CONTROL
A. 600 volt, 3 phase units, with conduit connection for attaching to electrical enclosure as required.
Three green status LED. 40 kA suppression.
B. Design based on Square D SDSA 3650 or Engineer Approved Equal by General Electric or Westinghouse.
C. Design is based on Panel Guard PG 100 Series manufactured by Intermatic Company.
Products with equal features and specification by Leviton and Leibert are acceptable.
2.19 MAGNETIC FLOW METERS (Furnished and installed in Bid Package No. 4): A. TAG FIT:
1. All flow meter Manufacturers shall submit results of flow calibration tests to confirm the stated accuracy. 3 Point NIST traceable calibration certificate to be supplied with each meter.
B. Magnetic type:
1. General: a. Designed for metering raw sewage . b. Accuracy: Within ± 0.2% of measured value for all flow velocities above 3 fps. c. Microprocessor based. d. Magnetic induction type proportional to velocity. e. Complete with ground rings. Grounding probes or electrodes are not acceptable. f. Provide required lengths of cabling between meter tube and remote mounted
transmitter. Installing CONTRACTOR to verify required length. No splicing of cabling shall be permitted.
2. Meter tube: a. 304 stainless steel flow tube. Epoxy coated carbon steel body housing. b. Polyurethane liner or hard rubber liner. c. Electrodes: Hastelloy-C d. Connections: Flanged, ANSI Class 150. e. Epoxy coated: 2 coats for a minimum of 7 mils. f. Approved for installation in NEC Class 1, Division 2, Group D Hazardous Area. g. NEMA 6P rating or equivalent for submergence in meter chamber.
3. Schedule a. Line sizes as required on drawings. b. Provide cast iron flange mounted spool piece to match for removal and
maintenance of mag meter.
4. Flow Tube Mounted Transmitter: a. One flow tube mounted transmitter. b. Microprocessor based converter. c. Programming of the flow converter shall be accomplished without removing the
glass cover via 4 optical keys or remotely with hand held HART terminal or with vendor and protocol independent PC configuration software: PACTWARE
d. Transmitter shall display instantaneous and totalized flow. e. Outputs:
1) Isolated 4-20 mAdc proportional and calibrated to stated flow range. 2) Empty pipe detection with dry contact relay output. Form A contacts shall be
rated for 120 vac, 20 amps. 3) Converter shall have HART Smart protocol as standard. 4) Pulse or analog output. 5) One (1) status Form A relay output. Contacts shall be rated for 120 VAC, 5
amps.
834310 26 60 03 - 9 SUBMERSIBLE PROBE CONTROL SYSTEM FOR PUMP STATION WITH SPEED CONTROL
f. Power: 120-VAC, 60 Hz. g. Calibrate
1) FIT- 0-1500 GPM = 4-20 mA Influent Flow Meter. h. Manufacturer:
1) ABB ProcessMaster. 2) Rosemont. 3) Endress and Hauser 4) or ENGINEER Approved Equal.
PART 3 - EXECUTION 3.01 INSTALLATION:
A. Install controls in accordance with Drawings, approved shop drawings, and manufacturer's recommendations.
3.02 START-UP AND TRAINING
A. Provide a service technician for eight (8) hours (not including any system programming, debugging, or travel time) to check out the system installation at system start-up for each pump station.
B. Provide a service technician for an additional four (4) hours to train the facility personnel in the
operation, adjustment and maintenance of the system for each pump station.
3.03 CLEANING: A. Prior to acceptance of the work of this Section, thoroughly clean all related areas in accordance
with Section 01 74 00 – Cleaning and Waste Management.
END OF SECTION
834310 31 20 01 - 1 LAGOON LINER AND BERM REPAIRS
SECTION 31 20 01
LAGOON LINER AND BERM REPAIRS
PART 1 - GENERAL 1.01 SUMMARY:
A. This Section includes repairs to the existing clay-lined lagoons, to be performed within existing Ponds, as indicated on the Drawings, and as directed by ENGINEER.
1.02 REFERENCES:
A. MDOT - Michigan Department of Transportation, “Standard Specifications for Construction”, 2012 edition.
B. ASTM - American Society of Testing Materials, latest edition.
1.03 DEFINITIONS:
A. Maximum Density: Maximum dry weight in pounds per cubic foot of a specific material.
B. Optimum Moisture: Percentage of water at maximum density.
C. Unsuitable Excavated Material: Muck, peat or organic material, or rock and gravel that is unsuitable for compaction or protection of liner or as determined by ENGINEER.
D. Engineered Material: Material that has been mechanically processed and separated to achieve a desired material classification.
E. Cohesive Material: Fine grained material which derives its resistance to displacement by manual attraction between particles of the mass, involving forces of molecular origin (i.e. Clays).
F. Proof Rolling: Applying test loads over the grade surface by means of a heavy pneumatic tire roller or other approved means, to locate and permit timely correction of deficiencies likely to adversely affect performance of the liner.
G. Erosion Control Gravel: Aggregate material which is placed over the liner in the areas designated on the Drawings.
1.04 JOB CONDITIONS:
A. If, during progress of the work, testing indicates that materials do not meet specified requirements, remove defective work and replace at no cost to the OWNER.
B. Protect and preserve all public and private property including existing vegetation,
landscape features, monuments within, along and adjacent to the work area.
834310 31 20 01 - 2 LAGOON LINER AND BERM REPAIRS
PART 2 - PRODUCTS
2.01 MATERIALS:
A. Clay:
1. New clay material shall be imported from off site, and shall have a saturated vertical hydraulic conductivity of not more than 1x10-7 cm/s, as determined using ASTM Method D5084-90.
B. Topsoil: Surface soils containing organic matters and productive of plant life.
C. Erosion Control Gravel (Armor Stone):
1. Shall be 4-inch to 8-inch sized limestone. 2. Shall be free of organic material, silt and clay. 3. Minimum of 90-percent of the material shall be crushed. 4. Material shall “lock-up” with itself to provide a stable surface without material slippage
when the water level is lowered and when the berm is used by operational personnel. D. Accessory Bentonite: Granular bentonite sealing clay used for penetration sealing and
repairs shall be natural sodium bentonite clay.
PART 3 - EXECUTION
3.01 PREPARATION: A. Topsoil Stripping:
1. Completely remove the topsoil to the required depth and within the grading limits prior to beginning excavation or embankment repair and re-construction.
2. Stockpile topsoil on the site at a location approved by the ENGINEER. B. Erosion Control:
1. Conform to MDOT 2.13.03, Section 01 57 13 – Temporary Soil Erosion and Sedimentation Control, and the approved Soil Erosion Control Plan.
2. Permanent: a. Apply permanent erosion and sedimentation control measures within seven (7)
days after the establishment of the final grade. b. Topsoil: Apply 4-inch minimum thickness as follows:
1) To exterior pond slopes. 2) To all disturbed areas.
c. Seed, mulch, and topsoil as specified in Section 32 92 00 – Surface Protection and Restoration.
3.02 EXCAVATION:
A. Excavation of Unsuitable Materials: 1. All materials determined by the ENGINEER to be unsuitable shall be excavated and
disposed of in accordance with Specification Section 33 47 20 – Lagoon Cleaning.
B. Excavation of Suitable Material: 1. Suitable excavated material shall be stockpiled on site, for later use, in an area
approved by the ENGINEER.
3.03 COMPACTION OF CLAY LINER SURFACE: A. Preparation of Surface of Clay Liner:
834310 31 20 01 - 3 LAGOON LINER AND BERM REPAIRS
1. Place new clay on the existing clay while in a dry condition. 2. Scarify the surface of the existing clay liner to a minimum depth of 3-inches. 3. Monitor moisture content of the clay liner to permit re-compaction to be conducted
when moisture content is not less than optimum.
B. Compaction: 1. Re-compact the surface of the clay liner using equipment that is suitable to provide
compaction effort to a minimum depth of 6-inches. 2. Each lift shall be thoroughly and uniformly compacted to not less than 90% of the
maximum dry density, as determined by the modified proctor test (ASTM D1557-91). 3. Soil shall not be compacted at a moisture content that is less than optimum.
C. Proof Roll Surface:
1. Upon completion of re-compaction of clay liner surface, perform two complete passes over areas.
2. Correct deficiencies identified during proof rolling. a. Fill depressions with compacted clay liner material.
3.04 TESTING AND INSPECTION:
A. Place and compact all required materials and provide proper control of moisture content of the material and other details necessary to obtain satisfactory results. 1. Remove materials that cannot be compacted with manipulation and moisture control
and replace it with suitable material at no cost to the OWNER.
B. Correct any deficiencies resulting from insufficient or improper compaction. Retest if required.
C. Provide equipment and personnel for access to test locations when requested by
ENGINEER. D. Maximum Density Standards:
1. Cohesive soils: ASTM D1557 (Modified Proctor). 2. Granular soils: Michigan Cone Test.
E. Field Density:
1. ASTM D-2922 (Nuclear).
F. Testing will be by ENGINEER or OWNER approved independent testing laboratory.
3.07 SURFACE PROTECTION AND RESTORATION:
A. Exterior Berms: Restore all disturbed areas with 4” topsoil, seed, and mulch blanket, in accordance with Section 32 92 00 – Surface Protection and Restoration. Fertilizer shall not be used.
3.08 SOIL EROSION AND SEDIMENTATION CONTROL: See SECTION 01 57 13 –
TEMPORARY SOIL EROSION AND SEDIMENTATION CONTROL.
END OF SECTION
834310 33 05 20 - 1 SITE PROCESS PIPING
SECTION 33 05 20
SITE PROCESS PIPING
PART 1 - GENERAL
1.01 SUMMARY
A. Section includes: 1. This Section includes, but is not necessarily limited to, the furnishing and installation of site
process pipe, valves and appurtenances as indicated on the Drawings, as specified herein, and as necessary for the proper and complete performance of the Work.
2. Work included: a. Buried site process piping and accessories as indicated on the Drawings and herein
specified. 3. Work not included:
a. Water mains. b. Buried process piping within 3 feet of building or structure penetration. c. Non-buried process piping. d. Natural gas piping, building waste, vent and drainage systems, and piping systems
to support HVAC systems.
B. Related Sections: 1. Documents affecting work of this Section include, but are not necessarily limited to:
a. General Conditions, Supplementary Conditions and Sections in Division 1 of these Specifications.
b. Section 31 20 00 – Earthwork. c. Section 31 23 33 – Trenching, Excavating, Backfilling and Compacting.
1.02 REFERENCES:
A. Except as herein specified or as indicated on the Drawings, the work of this Section shall comply with the following: 1. ASTM Standard Specifications:
a. B88 - Seamless Copper Water Tube. b. C443 - Joints for Circular Concrete Sewer and Culvert Pipe, Using Rubber Gaskets. c. C478 - Precast Reinforced Concrete Manhole Sections. d. C578 - Rigid, Cellular Polystyrene Thermal Insulation. e. C923 - Resilient Connectors Between Reinforced Concrete Manhole Structures and
Pipes. f. D449 - Asphalt Used in Dampproofing and Waterproofing. g. D2241 - Poly(Vinyl Chloride) (PVC) Pressure-Rated Pipe (SDR Series). h. D2466 - Poly(Vinyl Chloride) (PVC) Plastic Pipe Fittings, Schedule 40. i. D3139 - Joints for Plastic Pressure Pipes Using Flexible Elastomeric Seals.
2. ASTM Standard Test Method: a. C518 - Steady-State Thermal Transmission Properties by Means of the Heat Flow
Meter Apparatus. b. D1621 - Compressive Properties of Rigid Cellular Plastics.
3. AWWA Standards: a. C105 - Polyethylene Encasement for Ductile-Iron Piping for Water and Other
Liquids. b. C110 - Ductile-Iron and Gray-Iron Fittings, 3 In. through 48 In., for Water and Other
Liquids. c. C151 - Ductile-Iron Pipe, Centrifugally Cast, for Water or Other Liquids.
834310 33 05 20 - 2 SITE PROCESS PIPING
d. C153 - Ductile-Iron Compact Fittings, 3 in. Through 16 in., for Water and Other Liquids.
e. C550 - Protective Epoxy Interior Coatings for Valves and Hydrants. f. C600 - Installation of Ductile-Iron Water Mains and their Appurtenances. g. C605 - Underground Installation of Polyvinyl Chloride (PVC) Pressure Pipe and
Fittings for Water. h. C606 - Grooved and Shouldered Joints. i. C907 - Injection-Molded Polyvinyl Chloride (PVC) Pressure Fittings, 4 In. Through
12 In. (100 mm Through 300 mm), for Water Distribution.
1.03 DEFINITIONS
A. Abbreviations: 1. GHT: Garden Hose Thread. 2. NPT: American Standard Taper Pipe Thread also known as National Pipe Tapered. 3. NST: National Standard Thread also known as National Hose (NH) Thread.
1.04 SUBMITTALS:
A. Submit in accordance with Section 01 33 00 - Submittals.
B. Shop Drawings: 1. Submit for site process piping system components. 2. Required information:
a. Outline, cross-sections, assembly drawings, dimensions and engineering data. b. Inside lining and outside coating. c. Name of Manufacturer and model. d. Materials of construction.
C. Manufacturer' Literature: 1. Submit for all site process piping system components. 2. Required information: Manufacturer's installation instructions.
D. Operation and maintenance manuals: 1. Submit for valves and operators. 2. Required information:
a. Outline, cross-sections, assembly drawings, and engineering data.
E. Submit Manufacturer's certification that products and materials comply with these Specifications.
1.05 QUALITY ASSURANCE:
A. Qualifications: 1. Fabrication and installation personnel:
a. Trained and experienced in the fabrication and installation of the materials and equipment.
b. Knowledgeable of the design and the reviewed Shop Drawings.
1.06 DELIVERY, STORAGE AND HANDLING:
A. Receiving and storage: 1. All materials shall be delivered in original, unbroken, brand marked containers. 2. Handle and store materials:
a. In a manner which will prevent: 1) Deterioration or damage.
834310 33 05 20 - 3 SITE PROCESS PIPING
2) Contamination with foreign matter. 3) Damage by weather or elements.
b. In accordance with Manufacturer's directions.
B. Rejected material and replacements: 1. Reject damaged, deteriorated or contaminated material and immediately remove from the
Site. 2. Replace rejected materials with new materials at no additional cost to OWNER.
PART 2 - PRODUCTS
2.01 PIPE AND FITTINGS:
A. General: 1. Polyethylene encasement shall be placed on buried metal piping up to structures, including
process piping 5 ft outside of structures.
B. Ductile iron pipe (DIP): 1. Pipe: AWWA C151.
a. 12 inch diameter and smaller: Pressure Class 350. b. Greater than 12 inch diameter: Pressure Class 250.
2. Joints: a. Push on joint. b. Mechanical joint.
3. Joint restraint: a. Mechanical joint:
1) Ebaa Iron Sales, Inc., MegaLug Series 1100. 2) Star® Pipe Products Stargrip® series 3000. 3) Tyler Union TufGrip Series 1000. 4) Uni-Flange® Series 1400. 5) Or equal.
4. Fittings: a. Ductile iron or cast iron, pressure rated for 150 psi minimum. b. Fittings:
1) AWWA C110 or C153. 2) Fittings not covered by AWWA C110 or C153:
a) Laying dimensions: ANSI B16.1 Class 125; Manufacturer's standard for fittings not covered by ANSI B16.1.
b) Thickness design and pressure rating: AWWA C110 or C153, pressure rated for 250 psi.
3) Grooved joint fittings: a) AWWA C110 for fitting center-to-end dimensions. b) AWWA C110 or C153 for wall thickness design and pressure rating. c) AWWA C606 for rigid joints.
5. Gaskets: a. SBR rubber gaskets.
6. Lining: a. Cement-mortar, standard thickness, pipe and fittings.
7. Outside coating: Asphaltic coating, pipe and fittings. 8. Polyethylene encasement:
a. In accordance with AWWA C105.
C. Polyvinyl chloride (PVC) pipe: 1. Pipe:
a. 4 to 12 inch diameter: AWWA C900.
834310 33 05 20 - 4 SITE PROCESS PIPING
2. Fittings: a. 4 to 12 inch diameter: AWWA C907.
D. Polyethylene (PE) drainage pipe: 1. General:
a. Dual wall corrugated heavy duty pipe with annular exterior corrugations. b. Pipe:
1) 8- through 24-inch shall meet ASTM F667. c. Standard connections shall be water-tight and meet the requirements of the ASTM
D3212. Gaskets shall be installed by the pipe manufacturer. d. Fittings shall conform to ASTM F405 or ASTM F667. e. Material properties: Pipe and fitting material shall be high density polyethylene
conforming with the minimum requirements of cell classification 423410C as defined and described in the latest version of ASTM D3350; or ASTM D1248 Type III, Class C, Category 4, Grade P33.
2.02 MANHOLES AND CATCH BASINS:
A. Precast reinforced concrete: 1. ASTM C 478. 2. Base section: Base riser section with integral floor. 3. Joint gasket: Rubber gasket conforming to ASTM C 443. 4. Bituminous waterproofing: ASTM D449.
B. Pipe connectors: 1. ASTM C923. 2. Metal components: Series 300 non-magnetic stainless steel. 3. Press-Seal Gasket Corporation; PSX:Direct Drive or approved equal.
C. Steps: 1. Provide either cast iron or plastic steps. 2. Cast iron:
a. Model 8509 by East Jordan Iron Works; Model R-1980-J by Neenah Foundry Company; or equal.
b. Minimum dimensions: 10 inches deep by 14 inches wide, 5-inch tread depth, 1-inch by 1-inch tread section with 2-inch rail height.
3. Plastic: a. Copolymer polypropylene plastic manhole steps with Grade 60 No. 4 reinforcing bar
core. b. Grip width shall be 14 inches and depth 6 inches. c. Provide PS2-PF as manufactured by M.A. Industries, Inc., Peachtree City, GA; or
equal.
D. Corrosion prevention: 1. Contractor’s choice. 2. Antimicrobial admixture:
a. Use an EPA registered liquid antimicrobial admixture in concrete, grout and mortar used on the chamber.
b. The antimicrobial additive shall render the concrete uninhabitable for bacterial growth.
c. The additive manufacturer shall have successfully demonstrated prevention of microbial induced corrosion in sanitary sewers.
d. Field repairs and fillet construction shall be made with admixture manufacturer’s premixed grout or equal.
834310 33 05 20 - 5 SITE PROCESS PIPING
e. The amount of antimicrobial admixture to be used shall be as recommended by the manufacturer. The amount shall be included in the total water content of the concrete mix design.
f. Antimicrobial admixture manufacturer: 1) Review mix design to verify compatibility with other admixtures being used. 2) Perform effectiveness testing on production run specimens sent by precast
manufacturer. g. Air entrainment admixtures shall be anionic:
1) BASF Corporation, MasterAir® AE 90. 2) BASF Corporation, MasterAir® AE 200. 3) Or a neutralized vinsoll resin.
h. Accelerators not allowed. i. Mix time: 7 to 10 minutes to assure even dispersal of the product. j. Field repairs: Field repairs to the precast concrete shall be made using ConShield
Joint Set Grout pre-portioned and factory packaged that requires the addition of no other components. This repair grout may be used for filling joints, lift holes, damaged areas, creating benches and similar work.
k. Product surface marking: The antimicrobial additive shall be plainly stenciled on the exterior of each piece.
2.03 VALVE BOXES
A. Valves buried in parking areas or roadways: 1. Upper Section: Screw on adjoining center section and full diameter throughout. 2. Center Section: Minimum 5 inch inside diameter. 3. Base section: Fit over valve bonnet and shaped round for valves through 10 inch and oval
for 12 inch and over. 4. Materials of construction: Cast iron. 5. Height adjustment: Screw type. 6. Cover: Non-locking.
B. Lid marking: 1. Potable water lines: "WATER". 2. Wastewater sludge and drain Lines: "SEWER". 3. All others: No marking.
C. Coat inside and outside with bituminous varnish.
2.04 VALVES:
A. Gate valves: 1. Valves: AWWA C515 or C509. 2. Non-rising stem with 2 inch nut operator. 3. Coating: Coat valve inside and outside in accordance with AWWA C550. 4. Provide affidavit of compliance in accordance with AWWA C509/C515 Section 6.3. 5. Connections: Mechanical joint. 6. Comply with OWNER opening direction.
PART 3 - EXECUTION
3.01 INSTALLATION:
A. General: 1. Install items to be embedded before concrete is placed.
834310 33 05 20 - 6 SITE PROCESS PIPING
2. Fasten embedded items securely to prevent movement when concrete is placed. 3. Prevent entrance of foreign materials. 4. Install pipe, fittings and appurtenances in strict accordance with Manufacturer's
recommendations and as specified herein. 5. Line and grade:
a. Lay pipe to grades and elevations indicated on the Drawings. b. Where no grades are indicated, lay pipe with a minimum of 5 feet of cover below
final grade. 6. Take care in loading, transporting and unloading to prevent injury to the pipe or coatings.
Do not drop pipe or fittings. 7. Repair damage to coatings as directed by ENGINEER or OWNER. 8. Place insulation board over pipe where the bury depth is less than 42 inches. Insulation
width shall be 24 inch minimum, and at least 12 inches wider than the nominal pipe diameter.
B. Placement of pipe: 1. Bearing: Support entire Length of pipe barrel evenly with extra excavation at joints. 2. Bell and spigot: Clean and lubricate immediately prior to assembly.
C. Ductile iron pipe: 1. Install pipe and fittings and hydrants in accordance with AWWA C600 except as otherwise
provided herein. 2. Limit push-on and mechanical joint deflection to 80 percent of published values. 3. Provide fittings, in addition to those indicated on the Drawings, to cross utilities that may
be encountered upon opening the trench. 4. When cutting pipe is required, cut pipe by machine, leaving a smooth cut at right angles to
the axis of the pipe. Bevel cut end for push-on joint 30 degrees by grinding or filing back at least one-eighth inch.
5. Push-on joint assembly: a. Lay pipe with bell ends looking ahead. b. Insert gasket in the groove of the bell end of the pipe, and clean and lubricate the
joint surfaces. c. Insert plain end of the pipe to be entered in alignment with the bell of the pipe to
which it is to be joined, and push home with a jack or other means. d. After joining the pipe, use a metal feeler to make certain that the gasket is correctly
located. 6. Mechanical joint assembly: Do not use extension wrenches or pipe over handle of ordinary
ratchet wrench to secure greater Leverage. 7. Carefully inspect and hammer test pipe and fittings just prior to laying or installation. Install
no pieces that are found to be defective. 8. Encase buried ductile iron pipe in polyethylene in accordance with AWWA C105, including
process piping within 5 ft of structures.
D. If any defective pipe is discovered after it has been laid it shall be removed and replaced with a sound pipe in a satisfactory manner at no additional expense to OWNER.
E. Polyvinyl chloride (PVC) pipe: 1. General:
a. Provide support and thrust restraint at metal-body valves using concrete thrust blocks or other method reviewed by the ENGINEER.
2. Solvent welded pipe: a. Snake pipe in trench to allow for thermal contraction of the pipe. Use a temperature
variation of 60 degrees F to determine the loop offset distance. b. Dry surfaces to be joined. No solvent cementing in the rain. c. No solvent cementing when the temperature of the air or pipe exceeds 90 degrees
F.
834310 33 05 20 - 7 SITE PROCESS PIPING
3. Rubber-gasket joint pipe: a. Installation: AWWA C605. b. Anchor pipe at fittings in accordance with the Manufacturer's installation guide using
concrete thrust blocks or as approved by the ENGINEER. c. Field cut pipe: Cut end square and bevel to a 15º chamfer.
F. Manholes: 1. Base section placement: Full and even bearing. 2. Joints and Lift holes: Mortared finish on inside of concrete block and precast concrete units. 3. Top of casting elevation:
a. Gravel areas: 6 inches below surface. b. Bituminous base course: At base course grade. c. Final wearing surface: At finished grade. Adjustment of castings from base course
grade to finished grade is incidental. d. Ditches: 6 inches below ditch bottom or protruding not more than 6 inches above
slope; as applicable. e. Other areas: As directed by ENGINEER or OWNER.
4. Eliminate visible leakage.
G. Valves: 1. Set plumb. 2. Valve boxes:
a. Base section: Center and plumb over operating nut and 2 inches above bonnet joint. b. Upper section: Set cover ¼- inch below finished grade. c. Witnesses: Provide 3 measurements to permanent surface features. d. Place geotextile fabric around valve and valve box base to prevent sand migration
into valve box.
3.02 CLEANING:
A. Thoroughly clean all installed materials and products and related areas: 1. Prior to acceptance of the work of this Section. 2. In accordance with Section 01 74 00 – Cleaning and Waste Management.
END OF SECTION
834310 40 23 00 - 1 PROCESS PIPING SYSTEMS
SECTION 40 23 00
PROCESS PIPING SYSTEMS
PART 1 - GENERAL 1.01 SUMMARY:
A. Section includes: 1. This Section includes, but is not necessarily limited to, the furnishing and installation
of process piping as indicated on the Drawings, as specified herein, and as necessary for the proper and complete performance of the Work.
B. Related sections:
1. Documents affecting work of this Section include, but are not necessarily limited to: a. General Conditions, Supplementary Conditions and Sections in Division 1 of
these Specifications. b. Section 31 23 33 – Trenching, Excavating, Backfilling and Compacting c. Section 33 05 20 – Site Process Piping Systems. d. Section 40 92 10 – Process Valves.
C. Work included:
1. The work covered under this Section includes all non-buried piping, exterior or interior, indicated on the Drawings and herein specified.
D. Work not included:
1. The work not covered under this Section includes buried piping, which is greater than a distance of 5 feet from a structure penetration. The work does not include domestic cold and hot water systems, building waste, vent, drainage systems, and piping systems to support HVAC systems.
1.02 REFERENCES:
A. Except as herein specified or as indicated on the Drawings, the work of this Section shall comply with the following: 1. AWWA Standards:
a. C110 - Ductile-Iron and Gray-Iron Fittings, 3 inches through 48 inches, for Water and Other Liquids.
b. C115 - Flanged Ductile-Iron Pipe with Threaded Flanges. c. C151 - Ductile-Iron Pipe, Centrifugally Cast, for Water or Other Liquids.
1.03 SUBMITTALS:
A. Submit in accordance with Section 01 33 00 - Submittals.
B. Shop Drawings: 1. Submit showing details of construction and installation for process piping. 2. Show pipe diameter, wall thickness, length, materials, coatings, connections,
centerline elevations, and locations and dimensions of valves and fittings. 3. Indicate the location and centerline elevation of all wall sleeves and wall pipes. 4. Indicate the type and location of pipe supports on 8-inch pipe and larger. 5. Indicate the type and location of pipe couplings. 6. Indicate pipe joint gasket material, style, and location. 7. Indicate pipe joint bolting materials, sizes, and lengths.
834310 40 23 00 - 2 PROCESS PIPING SYSTEMS
8. Submit for heat trace, showing equipment rating, materials of construction, electrical requirements, and installation, operation and maintenance requirements.
C. Installation instructions:
1. Submit complete Manufacturer's installation instructions for all products. 2. Submit pipe Manufacturer's recommended span lengths between hangers or
supports for each pipe size and type.
D. Submit Manufacturer's certification that the products and materials conform to Specifications.
1.04 QUALITY ASSURANCE:
A. Qualifications: 1. Fabrication and installation personnel:
a. Trained and experienced in the fabrication and installation of the materials and equipment.
b. Knowledgeable of the design and the reviewed Shop Drawings. 1.05 DELIVERY, STORAGE AND HANDLING:
A. Receiving and storage: 1. All materials shall be delivered in original, unbroken, brand marked containers or
wrapping as applicable. 2. Handle and store materials:
a. In a manner which will prevent: 1) Deterioration or damage. 2) Contamination with foreign matter. 3) Damage by weather or elements.
b. In accordance with Manufacturer's directions.
B. Rejected material and replacements: 1. Reject damaged, deteriorated or contaminated material and immediately remove
from the Site. 2. Replace rejected materials with new materials at no additional cost to OWNER.
PART 2 - PRODUCTS 2.01 PIPE AND FITTINGS:
A. General: 1. All process piping 3” or larger shall be ductile iron unless otherwise specified or
indicated in Drawings. 2. All process piping smaller than 3” shall be seamless, galvanized steel unless
otherwise specified or indicated in Drawings. 3. Provide taps at locations indicated on the Drawings. 4. Gaskets containing asbestos not allowed.
B. Ductile Iron Pipe:
1. All pipe shall conform to ANSI A21.50/A21.51, AWWA C-151, Class 53. 2. Fittings:
a. For 3-inch diameter and larger, cast iron Class 250 or ductile iron Class 350, ANSI A21.10, AWWA C-110.
b. Coatings and linings shall match that of pipe.
834310 40 23 00 - 3 PROCESS PIPING SYSTEMS
3. Joints: a. Above ground and exposed pipe and fittings:
1) Flanged: Class 125, ANSI B16/1/AWWA C-115. a) Flange gaskets shall be the full face type in accordance with Appendix A
of AWWA C-110. 2) All joints between pipe, fittings, and equipment, shall be made up using
stainless steel hardware. b. Below ground (buried) pipe and fittings:
1) Restrained joint: Clow F-1058, mechanical joint with retainer gland, or approved equal.
2) Grooved Couplings: AWWA C-606, Victaulic type. c. Provide special ends, where required, to connect to structures, valves, pipe or
couplings of other manufacturers. 4. Prime Coatings and Linings:
a. All ductile iron piping shall be cement lined, standard thickness, in accordance with ANSI A21.4, AWWA C-104.
b. For below grade (buried) piping, the exterior shall be coated with an asphaltic coating in accordance with AWWA C-151.
2.02 SUPPORTS AND HANGERS:
A. General: 1. Furnish factory fabricated hangers and supports complete with inserts, clamps, bolts,
nuts, washers, and accessories. 2. Do not use perforated straps. 3. Equipment in submerged service shall be stainless steel.
B. Manufacturers:
1. Unistrut. 2. Michigan Hanger. 3. B-Line. 4. Strut Tech. 5. Aickinstrut. 6. Or equal.
2.03 WALL AND FLOOR SLEEVES:
A. Modular mechanical seal: 1. Interlocking links shaped to continuously fill the annular space between pipe and wall
opening. 2. Provide leak-free seal between passing pipe and sleeve. 3. Materials of construction:
a. Links: EDPM. b. Penetrations with liquid on one side: Stainless steel pressure plates and
fasteners. c. Other penetrations: Delrin pressure plates and zinc coated carbon steel
fasteners. 4. Furnish mechanical retaining assemblies at the locations indicated on the Drawings. 5. Manufacturers and types:
a. Thunderline Corporation, Link Seal. b. Calpico, Inc., Sealing Linx. c. Or equal.
834310 40 23 00 - 4 PROCESS PIPING SYSTEMS
2.04 FLANGE ADAPTOR:
B. Manufacturers and models: 1. Ebba Iron Sales, Inc.; Megaflange Series 2100. 2. Victaulic Company of America; Style 341 and 342 Vic-Flange Adapters.
PART 3 - EXECUTION 3.01 INSTALLATION:
A. General: 1. Install all process piping and accessories in conformance with:
a. The Submittals as reviewed by ENGINEER. b. The Manufacturer's recommendations.
2. Install items to be embedded before concrete is placed. 3. Fasten embedded items securely to prevent movement when concrete is placed. 4. Install items true to lines, grades, elevations, and locations as indicated on the
Drawings and herein specified. B. Supports and hangers:
1. Design of spacing and location for pipe supports and hangers shall be the responsibility of CONTRACTOR unless otherwise indicated on the drawings.
2. Install supports and hangers at less than maximum spacing recommended by pipe Manufacturer.
3. Adjust supports and hangers to bring pipe lines to proper elevations. 3.02 TESTING:
B. General: 1. Hydrostatically test the following process pressure piping lines:
a. All ductile iron pipe. 2. Tests shall be witnessed by ENGINEER. 3. Provide all necessary equipment (pumps, plugs, hoses, gages, etc.) to perform tests.
C. Procedure:
1. Pressure test procedure shall be in conformance with AWWA C 600, Section 4. 2. Duration: 2 hours. 3. Pressure: Maintain 150 pound per square inch. 4. Makeup water: From measurable source. 5. Maximum allowable leakage: L = SD P0.5
133,200 a. L = Allowable leakage, gallons per hour. b. S = Length of pipe tested, feet. c. D = Nominal diameter of pipe, inches. d. P = Average test pressure, pounds per square inch, gage.
6. No visible leaks.
D. Repairs: 1. In case of leakage under test, the leaks shall be discovered and repaired in an
approved manner and the section again tested until a satisfactory test is secured.
834310 40 23 00 - 5 PROCESS PIPING SYSTEMS
3.03 CLEANING:
A. Thoroughly clean all installed materials and products and related areas: 1. Prior to acceptance of the work of this Section. 2. In accordance with Section 01 74 00 – Cleaning and Waste Management.
END OF SECTION
APPENDIX A – NPDES PERMIT
PERMIT NO. MIG580000
STATE OF MICHIGAN DEPARTMENT OF ENVIRONMENTAL QUALITY
NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM
WASTEWATER DISCHARGE GENERAL PERMIT
WASTEWATER STABILIZATION LAGOON EFFLUENT In compliance with the provisions of the Federal Water Pollution Control Act (33 U.S.C. 1251 et seq., as amended; the “Federal Act”); Part 31, Water Resources Protection, of the Natural Resources and Environmental Protection Act, 1994 PA 451, as amended (NREPA); Part 41, Sewerage Systems, of the NREPA; and Michigan Executive Order 2011-1, wastewater that is associated with stabilization lagoon effluent that is adequately regulated by this general National Pollutant Discharge Elimination System (NPDES) permit, (the “General Permit”) is authorized to be discharged from facilities specified in individual “Certificates of Coverage” (COCs) in accordance with effluent limitations, monitoring requirements, and other conditions set forth in this General Permit. The applicability of this permit shall be limited to seasonal (spring/fall) discharges of sanitary or municipal wastewater that 1) have been adequately treated by a wastewater stabilization lagoon; 2) are not subject to the industrial pretreatment program requirements under the NREPA and R 323.2301 through R 323.2317 of the Michigan Administrative Code (Part 23 Rules); and 3) have been determined by the Michigan Department of Environmental Quality (the “Department”) not to need an individual permit. Aerobic lagoons, both mechanically aerated and non-mechanically aerated, which discharge treated sanitary wastewater, are included. The lagoon system shall 1) meet accepted design criteria as determined by the Department and 2) comply with secondary treatment standards for lagoon systems in Part I.A.1. of this General Permit and other requirements and limitations stated herein as specified in the COC. This permit does not authorize discharges determined by the Department to need individual NPDES permits or different general permits, or that may cause or contribute to a violation of the Water Quality Standards. In order to constitute a valid authorization to discharge, this permit must be accompanied by a COC issued by the Department. The COC will specify which sections of the General Permit apply at the individual facility, including if the Groundwater Monitoring for Lagoon Exfiltration/Leakage, Additional Final Effluent Limitation for Total Phosphorus, and/or Residuals Management Program for Land Application of Biosolids for New or Approved Programs. Unless specified otherwise, all contact with the Department required by this permit shall be to the position(s) indicated in the COC. This General Permit shall take effect April 1, 2014. The provisions of this permit are severable. After notice and opportunity for a hearing, this General Permit may be modified, suspended, or revoked in whole or in part during its term in accordance with applicable laws and rules. On its effective date, this General Permit shall supersede NPDES Permit No. MIG589000, expiring April 1, 2014. This General Permit shall expire at midnight, April 1, 2019. Issued January 29, 2014. Based on a request submitted on September 29, 2014, this permit was modified (minor) on October 2, 2014. Original Permit Signed by Philip Argiroff Philip Argiroff, Chief Permits Section Water Resources Division
PERMIT NO. MIG580000 Page 2 of 29 PART I
Section A. Effluent Limitations And Monitoring Requirements
PERMIT FEE REQUIREMENTS
In accordance with Section 324.3120 of the NREPA, the permittee shall make payment of an annual permit fee to the Department for each October 1 the permit is in effect regardless of the occurrence of a discharge. The permittee shall submit the fee in response to the Department's annual notice. The fee shall be postmarked by January 15 for notices mailed by December 1. The fee is due no later than 45 days after receiving the notice for notices mailed after December 1. In accordance with Section 324.3132 of the NREPA, the permittee shall make payment of an annual biosolids land application fee to the Department if the permittee land applies biosolids. In response to the Department's annual notice, the permittee shall submit the fee, which shall be postmarked no later than January 31 of each year.
CONTESTED CASE INFORMATION The terms and conditions of this General Permit shall apply to an individual facility on the effective date of a COC for the facility. Any person who is aggrieved by this permit may file a sworn petition with the Michigan Administrative Hearing System within the Michigan Department of Licensing and Regulatory Affairs, c/o the Michigan Department of Environmental Quality, setting forth the conditions of the permit which are being challenged and specifying the grounds for the challenge. The Department of Licensing and Regulatory Affairs may reject any petition filed more than 60 days after issuance as being untimely.
PERMIT NO. MIG580000 Page 3 of 29 PART I
Section A. Effluent Limitations And Monitoring Requirements
1. Final Effluent Limitations During the period beginning on the effective date of an individual COC under this General Permit, and lasting until the expiration of this permit or termination of the individual COC, the permittee is authorized to discharge treated sanitary wastewater to the surface waters of the state of Michigan. Effluent shall be discharged during high-flow conditions in the spring and/or fall of each year. There shall be no discharge from June 1 to September 30 and from January 1 to February 28/29 (see b. below). In addition, there shall be no discharge during periods of significant ice cover on the receiving stream unless authorized by the Department. Such discharge shall be limited and monitored by the permittee as specified below.
Maximum Limits for Maximum Limits for Quantity or Loading Quality or Concentration Monitoring Sample Parameter Monthly 7-Day Daily Units Monthly 7-Day Daily Units Frequency Type Flow (see b. below) (report) --- (report) MGD --- --- --- --- Daily Report Total Daily Flow Biochemical Oxygen Demand (BOD5) --- --- --- --- 30 45 --- mg/l see d. below Composite Total Suspended Solids Mar-May (see b. below) --- --- --- --- 70 100 --- mg/l see d. below Composite Oct-Dec --- --- --- --- 40 45 --- mg/l see d. below Composite Ammonia Nitrogen (as N) --- --- --- --- (report) --- --- mg/l see d. below Composite Total Phosphorous (as P) --- --- --- --- (report) --- --- mg/l see d. below Composite Geometric Mean Monthly 7-Day Fecal Coliform Bacteria --- --- --- --- 200 400 --- cts/ see d. below Grab 100 ml Minimum Maximum Daily Daily pH --- --- --- --- 6.5 --- 10 S.U. see d. below Grab Dissolved Oxygen --- --- --- --- 5.0 --- --- mg/l Daily Grab
a. Narrative Standard
The receiving water shall contain no turbidity, color, oil films, floating solids, foams, settleable solids, or deposits as a result of this discharge in unnatural quantities which are or may become injurious to any designated use.
b. Acceptable Discharge Periods If the Department determines that discharge periods of shorter duration than March 1 through May 31 and/or October 1 through December 31 are necessary to protect water quality, the reduced discharge periods will be stated in the COC. Upon approval by the Upper Peninsula District Supervisor, the spring discharge period may be extended to April 1 through June 21 for facilities located in the following counties: Baraga, Dickinson, Gogebic, Houghton, Iron, Keweenaw, Marquette, and Ontonagon.
PERMIT NO. MIG580000 Page 4 of 29 PART I
Section A. Effluent Limitations And Monitoring Requirements c. Discharges Outside of Acceptable Discharge Periods
For discharges outside the acceptable discharge periods, the permittee shall notify the Department of the potential noncompliance prior to discharge, as required by Part 1.A.6. of this General Permit.
d. Discharge Management
The discharge is to be managed consistent with the following requirements:
1) Cell Isolation - The permittee shall isolate a cell from cells receiving untreated sanitary wastewater at least two weeks in advance of a proposed discharge. There shall be no discharge to the surface waters from unisolated cells.
2) Pre-Discharge Sampling - The permittee shall sample the isolated cell for BOD5, Total
Suspended Solids, Ammonia Nitrogen, Total Phosphorus, Fecal Coliform Bacteria, and pH no more than two weeks in advance of a proposed discharge. Samples shall be drawn from a point approximately five feet from the edge of the cell and one foot beneath the water surface. All samples shall be grab samples. If more than two weeks will pass prior to the beginning of an actual discharge, additional pre-discharge samples shall be obtained, analyzed, and reported to the Department prior to discharge.
3) Discharge Approval Required - The permittee shall notify and receive approval from the appropriate District Supervisor or staff authorized to act on his/her behalf prior to discharge of any effluent for each discharge event. The permittee shall supply the results of all pre-discharge effluent samples and the results of a Dissolved Oxygen sample taken no more than 24 hours prior to notification.
4) Discharge Duration - Multiple discharge events are authorized in the spring and/or fall of each year in accordance with Part I.A.1.b. of this General Permit and the following provision. Discharge event duration shall not exceed 10 days within a 14-day period. The discharge may be continuous or intermittent during the event. After the discharge event is ended, the permittee shall wait a minimum of seven calendar days prior to initiating a new discharge event.
5) Discharge Sampling Frequency - Flow and Dissolved Oxygen shall be measured daily during discharge. All other parameters shall be measured the first day and every other day during discharge, including the last day of discharge. The Department may approve alternate sampling frequencies that are demonstrated to be representative of the discharge.
6) Discharge Sample Type and Location - The sampling for BOD5, Total Suspended Solids, Total
Phosphorus, and Ammonia Nitrogen shall be 3-portion composite samples or 24-hour composite samples of the effluent. The sampling for Dissolved Oxygen, Fecal Coliform Bacteria, and pH shall be grab samples of the effluent.
e. Discharge Monitoring Reports
Monthly Discharge Monitoring Reports (DMRs) shall be submitted for the months of October, November, December, March, April, and May whether or not there has been a discharge. Upper Peninsula facilities authorized under Part 1.A.1.b. of this General Permit shall also submit a monthly DMR for any approved discharge event. Daily DMRs shall be submitted only during months a discharge occurred.
f. Security Fencing
The lagoon shall be enclosed by security fencing. The fencing shall include gates wide enough to accommodate mowing machinery. All gates shall be locked to prevent unauthorized access. Metal warning signs shall be posted on the fencing. Lagoon systems that utilize sophisticated mechanical equipment should consider more secure fencing and access control.
g. Water Treatment Additives
This General Permit does not authorize the discharge of water additives without approval from the Department. Approval of water additives is authorized under separate correspondence. Water additives include any material that is added to water used at the facility or to a wastewater generated by the
PERMIT NO. MIG580000 Page 5 of 29 PART I
Section A. Effluent Limitations And Monitoring Requirements
facility to condition or treat the water. In the event a permittee proposes to discharge water additives, including an increased discharge concentration of a previously approved water additive, the permittee shall submit a request to the Department for approval. See Part I.A.5. of this General Permit, for information on requesting water treatment additive use.
h. Construction Approval
This General Permit does not authorize the construction or modification of any physical structures of the wastewater treatment facility. The permittee shall receive any required approval of plans and specifications from the appropriate Department before commencing construction of the wastewater treatment facility necessary for compliance with this General Permit.
2. Facility Operation and Maintenance The permittee shall comply with the inspection, operation, and maintenance program requirements specified below. An alternate facility operations program may be approved by the Department. a. Lagoon Inspection
The permittee shall inspect the lagoon facilities three times weekly year-round unless otherwise authorized by the Department. These inspections shall include:
1) the lagoon dikes for vegetative growth, erosion, slumping, animal burrowing or breakthrough,
and condition of the lagoon liner;
2) the lagoon for growth of aquatic plants, offensive odors, insect infestations, scum, floating sludge, and septic conditions;
3) the depth of the water in each cell and the freeboard; 4) the drain pipe to ensure there is no discharge;
5) the control structures and pump stations to assure that valves, gates, and alarms are set
correctly and properly functioning;
6) the lagoon security fence and warning signs; and
7) analysis for Dissolved Oxygen in each lagoon cell at least once weekly, except when the lagoons are ice covered. The data shall be kept as retained self-monitoring. See Part II.C.3. of this General Permit.
The permittee shall initiate steps to correct any condition that is not in accordance with the facility maintenance program outlined in Part I.A.2.b. of this General Permit. A record of the inspections shall be maintained by the permittee for a period of three years.
PERMIT NO. MIG580000 Page 6 of 29 PART I
Section A. Effluent Limitations And Monitoring Requirements b. Facility Maintenance
The permittee shall implement a Facility Maintenance Program that incorporates the following management practices unless otherwise authorized by the Department.
1) Vegetation shall be maintained at a height not more than six inches above the ground on lagoon
dikes and around the fencing.
2) At all times, the facility shall be maintained to prevent the negative effects of floating material and/or water perimeter emergent rooted aquatic plants on Dissolved Oxygen concentrations, treatment efficiency, nuisance organisms, offensive odors, or other measurable impacts. However, in no case, even without demonstrated impact, shall the floating material and/or water perimeter emergent rooted aquatic plants exceed 40 percent cover.
3) Dike damage due to erosion or animal burrowing shall be corrected immediately and steps
taken to prevent occurrences in the future. 4) The integrity of the lagoon liner shall be protected. Liner damages shall be corrected
immediately and steps taken to prevent future occurrences. 5) The occurrence of scum, floating sludge, offensive odors, insect infestations, and septic
conditions shall be minimized.
6) A schedule for the inspection and maintenance of the collection system, lift stations, mechanical and electrical systems, transfer stations, and control structures shall be developed and implemented.
c. Lagoon Drawdown Conditions
The permittee shall observe the following conditions when drawing down a cell for transfer or discharge, unless otherwise authorized by the Department.
1) Water discharged shall be removed from the surface two feet of the cell at a rate of less than
one foot per day. 2) The permittee shall maintain a minimum of two feet of freeboard in all cells at all times. 3) The permittee shall maintain a minimum of two feet of water in all cells at all times.
3. Groundwater Monitoring for Lagoon Exfiltration/Leakage Based on the information submitted in the permit application, the permittee may be required to install groundwater monitoring wells and conduct groundwater monitoring. The intent of such monitoring, if required, will be to demonstrate that the lagoons have not impacted, and are not likely to impact surface waters, in accordance with the Part 4, Water Quality Standards (Part 4 Rules), promulgated under Part 31, Water Resources Protection, of the NREPA, or groundwater above the standard described in R 323.2222 of Part 22, Groundwater Quality Administrative Rules (Part 22 Rules), promulgated pursuant to Part 31. Information that may be considered by the Department in making this determination include, but is not limited to: the date when the lagoon was constructed; construction design methods and materials, including whether liner specifications meet R 323.2237 of the Part 22 Rules or providing equivalency as allowed in R 323.2237; and indications of whether there is a direct vent to surface waters and if such vent complies with surface water quality standards. If the Department determines the permittee needs to conduct groundwater monitoring to verify and assure that leakage from the lagoons to the groundwaters and/or surface waters of the state is not causing unacceptable impacts, the following conditions shall apply: a. The permittee shall install groundwater monitoring wells around the perimeter of the lagoons to
document both groundwater water quality impacts and groundwater flow. A plan for the monitoring wells shall be submitted to the Department for approval within 90 days of notification by the Department.
PERMIT NO. MIG580000 Page 7 of 29 PART I
Section A. Effluent Limitations And Monitoring Requirements
Within 90 days of approval of the plan, unless the Department approves an extended period (not to exceed 180 days), the groundwater monitoring wells shall be installed.
b. The permittee shall submit a groundwater monitoring plan to the Department for approval within 90 days of the effective date of this permit. This groundwater monitoring plan may be submitted as part of the monitoring well work plan. The monitoring plan shall include monitoring of the groundwater elevation and the following parameters: total phosphorus, dissolved phosphorus, total inorganic nitrogen, sodium, chloride, pH, and specific conductance. Monitoring shall be conducted quarterly until the permittee is notified by the Department that the monitoring can end or be reduced.
c. The permittee shall begin implementation of the monitoring plan within 90 days of approval of the
monitoring plan, or upon installation of the monitoring well, whichever occurs last. The result of the monitoring shall be submitted to the Department quarterly.
d. Upon written notification by the Department that unacceptable leakage is impacting surface waters
and/or groundwater, the permittee shall develop a work plan to address the leakage. Within 6 months of such notification, the permittee shall submit an approvable lagoon leakage remediation work plan to the Department. The purpose of the work plan is to control exfiltration from the lagoon treatment system. The study shall include remediation methods, procedures, time schedules, and staff, as appropriate.
e. The permittee shall begin implementation of the lagoon leakage remediation work plan within 30 days of
approval of the work plan. f. The permittee shall complete implementation of the lagoon leakage remediation work plan and submit
an approvable final report with supporting data to the Department on or before within one year of approval of the work plan. The final report shall include a plan and schedule for continued maintenance and monitoring of the lagoon treatment system.
Based on the results of groundwater monitoring, the Department may require the permittee to obtain an individual permit, as described under Part 1.A.12 of this General Permit, to address compliance with R.323.2222 or surface water quality standards.
4. Additional Final Effluent Limitation for Total Phosphorus If the Department determines it is necessary to control total phosphorus discharges to protect downstream water quality, the discharge shall be limited and monitored by the permittee as specified below. Such determination will be indicated in the COC.
Maximum Limits for Maximum Limits for Quantity or Loading Quality or Concentration Monitoring Sample Parameter Monthly 7-Day Daily Units Monthly 7-Day Daily Units Frequency Type Total Phosphorous (as P) --- --- --- --- 1.0 --- --- mg/l see A.1.d.5 Composite above
5. Request for Discharge of Water Treatment Additives In the event a permittee proposes to discharge water additives, the permittee shall submit a request to discharge water additives to the Department for approval. Such requests shall be sent to the Permits Section, Water Resources Division, Department of Environmental Quality, P.O. Box 30458, Lansing, Michigan 48909, with a copy to the Department contact listed on the COC. Instructions to submit a request electronically may be obtained via the internet (http://www.michigan.gov/deqnpdes; then click on Applicable Rules and Regulations, which is under the Information banner, and then click on Water Treatment Additive Discharge Application Instructions). Written approval from the Department to discharge such additives at specified levels shall be obtained prior to discharge by the permittee. Additional monitoring and reporting may be required as a condition for the approval to discharge the additive.
PERMIT NO. MIG580000 Page 8 of 29 PART I
Section A. Effluent Limitations And Monitoring Requirements A request to discharge water additives shall include all of the following water additive usage and discharge information: a. Safety Data Sheet (formerly Material Safety Data Sheet); b. the proposed water additive discharge concentration with supporting calculations; c. the discharge frequency (i.e., number of hours per day and number of days per year); d. the monitoring point from which the product is to be discharged; e. the type of removal treatment, if any, that the water additive receives prior to discharge; f. product function (i.e., microbiocide, flocculant, etc.); g. a 48-hour LC50 or EC50 for a North American freshwater planktonic crustacean (either Ceriodaphnia sp.,
Daphnia sp., or Simocephalus sp.); and h. the results of a toxicity test for one other North American freshwater aquatic species (other than a
planktonic crustacean) that meets a minimum requirement of R 323.1057(2) of the Water Quality Standards.
Prior to submitting the request, the permittee may contact the Permits Section by telephone at 517-284-5568 or via the internet at the address given above to determine if the Department has the product toxicity data required by items g. and h. above. If the Department has the data, the permittee will not need to submit product toxicity data.
6. Untreated or Partially Treated Sewage Discharge Reporting and Testing Requirements In accordance with Section 324.3112a of the NREPA, if untreated sewage, including sanitary sewer overflows (SSO) and combined sewer overflows (CSO), or partially treated sewage is directly or indirectly discharged from a sewer system onto land or into the waters of the state, the person responsible for the sewer system shall immediately, but not more than 24 hours after the discharge begins, notify by telephone the Department, local health departments, a daily newspaper of general circulation in the county in which the permittee is located, and a daily newspaper of general circulation in the county or counties in which the municipalities whose waters may be affected by the discharge are located that the discharge is occurring. The permittee shall also annually contact municipalities, including the superintendent of a public drinking water supply with potentially affected intakes, whose waters may be affected by the permittee's discharge of combined sewage, and if those municipalities wish to be notified in the same manner as specified above, the permittee shall provide such notification. Such notification shall also include a daily newspaper in the county of the affected municipality. At the conclusion of the discharge, written notification shall be submitted in accordance with and on the “Report of Discharge Form” available via the internet at: http://www.deq.state.mi.us/csosso/, or, alternatively for CSO discharges, in accordance with notification procedures approved by the Department. In addition, in accordance with Section 324.3112a of the NREPA, each time a discharge of untreated sewage or partially treated sewage occurs, the permittee shall test the affected waters for Escherichia coli to assess the risk to the public health as a result of the discharge and shall provide the test results to the affected local county health departments and to the Department. The testing shall be done at locations specified by each affected local county health department, but shall not exceed ten tests for each separate discharge event. The affected local county health department may waive this testing requirement, if it determines that such testing is not needed to assess the risk to the public health as a result of the discharge event. The results of this testing shall be submitted with the written notification required above, or, if the results are not yet available, submit them as
PERMIT NO. MIG580000 Page 9 of 29 PART I
Section A. Effluent Limitations And Monitoring Requirements soon as they become available. This testing is not required if the testing has been waived by the local health department or if the discharge(s) did not affect surface waters. Permittees accepting sanitary or municipal sewage from other sewage collection systems are encouraged to notify the owners of those systems of the above reporting and testing requirements.
7. Facility Contact The “Facility Contact” was specified in the application. The permittee may replace the facility contact at any time, and shall notify the Department in writing within ten days after replacement (including the name, address, telephone number, and e-mail address, if available, of the new facility contact). a. The facility contact shall be (or a duly authorized representative of this person):
• for a corporation, a principal executive officer of at least the level of vice president, or a designated representative, if the representative is responsible for the overall operation of the facility from which the discharge described in the permit application or other NPDES form originates;
• for a partnership, a general partner; • for a sole proprietorship, the proprietor; or • for a municipal, state, or other public facility, either a principal executive officer, the mayor, village
president, city or village manager, or other duly authorized employee. b. A person is a duly authorized representative only if:
• the authorization is made in writing to the Department by a person described in paragraph a. of this section; and
• the authorization specifies either an individual or a position having responsibility for the overall operation of the regulated facility or activity such as the position of plant manager, operator of a well or a well field, superintendent, position of equivalent responsibility, or an individual or position having overall responsibility for environmental matters for the facility (a duly authorized representative may thus be either a named individual or any individual occupying a named position).
Nothing in this section obviates the permittee from properly submitting reports and forms as required by law.
8. Monthly Operating Reports For wastewater treatment facilities that serve the public, Part 41 of Act 451 of 1994 as amended, specifically Section 324.4106 and associated R 299.2953, requires that the permittee file with the Department, on forms prescribed by the Department, reports showing the effectiveness of the treatment facility operation and the quantity and quality of liquid wastes discharged into waters of the state. If the Department has determined that this provision is applicable, it will be indicated in the COC. FOR ALL NEW DISCHARGERS: For new facilities: Sixty days prior to start-up of the treatment facility the permittee shall submit to the Department a treatment facility monitoring program to meet this requirement. Upon approval by the Department the permittee shall implement the treatment facility monitoring program. The report forms and guidance are available on the Department website at http://www.michigan.gov/deq/0,1607,7-135-3313_44117---,00.html. These forms shall be maintained on-site and shall be provided to the Department for review upon request. These treatment facility monitoring records shall be maintained for a minimum of three years. FOR ALL EXISTING DISCHARGERS: Within 30 days of the effective date of the COC the permittee shall submit to the Department a treatment facility monitoring program to meet this requirement. Upon approval by the Department the permittee shall implement the treatment facility monitoring program. The reporting forms and guidance are available on the Department website at http://www.michigan.gov/deq/0,1607,7-135-3313_44117---,00.html. These forms shall be maintained on-site and shall be provided to the Department for review upon request. These treatment facility monitoring records shall be maintained for a minimum of three years.
PERMIT NO. MIG580000 Page 10 of 29 PART I
Section A. Effluent Limitations And Monitoring Requirements 9. Residuals Management Program (RMP) for Land Application of Biosolids: First RMP, including new uses (The individual COC indicates if applicable.) A permittee seeking authorization to land apply bulk biosolids or prepare bulk biosolids for land application shall develop and submit a Residuals Management Program (RMP) to the Department (see Part I.A.9.e. of this General Permit) for approval. Effective upon Department approval of the permittee’s RMP, the permittee is authorized to land apply bulk biosolids or prepare bulk biosolids for land application in accordance with the requirements established in R 323.2401 through R 323.2418 of the Michigan Administrative Code (Part 24 Rules), which can be obtained via the internet (http://www.michigan.gov/deq/ and on the left side of the screen click on Water, Biosolids & Industrial Pretreatment, Biosolids, then click on Biosolids Laws and Rules Information, which is under the Laws & Rules banner in the center of the screen). The permittee’s approved RMP, and any approved modifications thereto, are enforceable requirements of this General Permit. Incineration, landfilling, and other residual disposal activities shall be conducted in accordance with Part II.D.7. of this General Permit. a. RMP Approval and Implementation
A permittee seeking approval of an RMP shall submit the RMP to the Department (see Part I.A.9.e. of this General Permit) at least 180 days prior to the land application of biosolids. The permittee may utilize the RMP Electronic Form that can be obtained via the internet (http://www.michigan.gov/deq/, and on the left side of the screen click on Water, Biosolids & Industrial Pretreatment, Biosolids; then click on RMP Electronic Form, which is under the Downloads banner in the center of the screen) or obtain detailed requirements from the Department. The RMP shall become effective and shall be implemented by the permittee upon written approval by the Department.
b. Annual Report On or before October 30 of each year, the permittee shall submit an annual report to the Biosolids Program, Water Resources Division, Department of Environmental Quality, P.O. Box 30458, Lansing, Michigan 48909-7958, for the previous fiscal year of October 1 through September 30. At a minimum, the report shall contain:
1) a certification that current residuals management practices are in accordance with the approved
RMP, or a proposal for modification to the approved RMP; and 2) a completed Biosolids Annual Report Form, which can be obtained via the internet
(http:/www.michigan.gov/deq/, and on the left side of the screen click on Water, Biosolids & Industrial Pretreatment, Biosolids; then click on Biosolids Annual Report Form, which is under the Downloads banner in the center of the screen) or from the Department.
c. Modifications to the Approved RMP
Prior to implementation of modifications to the RMP, the permittee shall submit proposed modifications to the Department (see Part I.A.9.e. of this General Permit) for approval. The approved modification shall become effective upon the date of approval. Upon written notification, the Department may impose additional requirements and/or limitations to the approved RMP as necessary to protect public health and the environment from any adverse effect of a pollutant in the biosolids.
d. Recordkeeping
Records required by the Part 24 Rules shall be kept for a minimum of five years. However, the records documenting cumulative loading for sites subject to cumulative pollutant loading rates shall be kept as long as the site receives biosolids.
e. Contact Information RMP related submittals to the Department shall be to the address and telephone number listed in the COC.
PERMIT NO. MIG580000 Page 11 of 29 PART I
Section A. Effluent Limitations And Monitoring Requirements 10. Residuals Management Program for Land Application of Biosolids: APPROVED RMPs (The individual COC indicates if applicable.) The permittee is authorized to land apply bulk biosolids or prepare bulk biosolids for land application in accordance with the permittee’s approved RMP approved on the date specified in the COC and approved modifications thereto, in accordance with the requirements established in R 323.2401 through R 323.2418 of the Michigan Administrative Code (Part 24 Rules). The approved RMP, and any approved modifications thereto, are enforceable requirements of this General Permit. Incineration, landfilling, and other residual disposal activities shall be conducted in accordance with Part II.D.7. of this General Permit. The Part 24 Rules can be obtained via the internet (http://www.michigan.gov/deq/, and on the left side of the screen click on Water, Biosolids & Industrial Pretreatment, Biosolids; then click on Biosolids laws and Rules Information, which is under the Laws & Rules banner in the center of the screen). a. Annual Report
On or before October 30 of each year, the permittee shall submit to the Biosolids Program, Water Resources Division, Department of Environmental Quality, P.O. Box 30458, Lansing, Michigan 48909-7958, for the previous fiscal year of October 1 through September 30. At a minimum, the report shall contain:
1) a certification that current residuals management practices are in accordance with the approved
RMP, or a proposal for modification to the approved RMP; and 2) a completed Biosolids Annual Report Form, which can be obtained via the internet
(http://www.michigan.gov/deq/ and on the left side of the screen click on Water, Biosolids & Industrial Pretreatment, Biosolids; then click on Biosolids Annual Report Form, which is under the Downloads banner in the center of the screen) or from the Department.
b. Modifications to the Approved RMP
Prior to implementation of modifications to the RMP, the permittee shall submit proposed modifications to the Department (see Part I.A.9.e. for this General Permit) for approval. The approved modification shall become effective upon the date of approval. Upon written notification, the Department may impose additional requirements and/or limitations to the approved RMP as necessary to protect public health and the environment from any adverse effect of a pollutant in the biosolids.
c. Record Retention
Records required by the Part 24 Rules shall be kept for a minimum of five years. However, the records documenting cumulative loading for sites subject to cumulative pollutant loading rates shall be kept as long as the site receives biosolids.
d. Contact Information RMP related submittals to the Department shall be to the address and telephone number listed in the COC.
11. Expiration and Reissuance On or before October 1, 2018, a permittee seeking continued authorization to discharge under this General Permit beyond the permit’s expiration date shall submit to the Department a written request containing such information, forms, and fees as required by the Department. Without an adequate request, a permittee’s authorization to discharge will expire on April 1, 2019. With an adequate request, a permittee shall continue to be subject to the terms and conditions of the expired permit until the Department takes action on the request, unless this General Permit is terminated or revoked. If this General Permit is terminated or revoked, all authorizations to discharge under the permit shall expire on the date of termination or revocation. If this General Permit is modified, the Department will notify the permittee of any required action. Without an adequate response, a permittee’s authorization to discharge will terminate on the effective date of the modified
PERMIT NO. MIG580000 Page 12 of 29 PART I
Section A. Effluent Limitations And Monitoring Requirements permit. With an adequate response, a permittee shall be subject to the terms and conditions of the modified permit on the effective date of the modified permit unless the Department notifies the permittee otherwise. If a discharge is terminated, the permittee shall request termination of discharge authorization.
12. Requirement to Obtain Individual Permit The Department may require any person who is authorized to discharge by a COC and this General Permit to apply for and obtain an individual NPDES permit if any of the following circumstances apply:
1) the discharge is a significant contributor to pollution as determined by the Department on a case-by-case basis;
2) the discharger is not complying or has not complied with the conditions of the permit;
3) a change has occurred in the availability of demonstrated technology or practices for the control or abatement of waste applicable to the point source discharge;
4) effluent standards and limitations are promulgated for point source discharges subject to this General Permit; and
5) the Department determines that the criteria under which the permit was issued no longer apply.
Any person may request the Department to take action pursuant to the provisions of Rule 2191 (R 323.2191 of the Michigan Administrative Code).
PERMIT NO. MIG580000 Page 13 of 29 PART I
Section A. Effluent Limitations And Monitoring Requirements 13. Industrial Waste Pretreatment Program It is understood that the permittee does not receive the discharge of any type or quantity of substance which may cause interference with the operation of the treatment works; and, therefore, the permittee is not required to immediately develop an industrial pretreatment program in accordance with Section 307 of the Federal Act. The permittee is required to comply with Section 307 of the Federal Act upon accepting any such discharge for treatment. The permittee is required to notify the Department within 30 days if any user discharges or proposes to discharge such wastes to the permittee for treatment. Under no circumstances shall the permittee allow introduction of the following wastes into the waste treatment system: a. pollutants which cause pass through or interference; b. pollutants which create a fire hazard or explosion hazard in the sewerage system, including, but not
limited to wastestreams with a closed cup flashpoint of less than 140 degrees Fahrenheit or 60 degrees Centigrade using the test methods specified in Title 40 of the Code of Federal Regulations (CFR) 261.21;
c. pollutants which will cause corrosive structural damage to the sewerage system; but in no case,
discharges with pH less than 5.0, unless the works is specifically designed to accommodate such discharges;
d. solid or viscous pollutants in amounts which will cause obstruction to the flow in the sewerage system
resulting in interference; e. any pollutant, including oxygen demanding pollutants (BOD, etc.) released in a discharge at a flow rate
and/or pollutant concentration which will cause interference with the treatment plant; f. heat in amounts which will inhibit biological activity in the treatment plant resulting in interference; but in
no case, heat in such quantities that the temperature at the treatment plant exceeds 40 degrees Centigrade (104 degrees Fahrenheit) unless the Department, upon request of the permittee, approves alternate temperature limits;
g. pollutants which result in the presence of toxic gases, vapors, or fumes within the sewerage system in a
quantity that may cause acute worker health and safety problems; and h. any trucked or hauled pollutants, except at discharge points designated by the permittee. If information is gained by the Department that the permittee receives or is about to receive industrial wastes, then the permittee may be required to obtain an individual permit (see Part I.A.12. of this General Permit).
14. Industrial Waste (for non POTWs such as mobile home parks, campgrounds, nursing homes and marinas) Under no circumstances shall the permittee allow introduction of waste into the sewerage system other than domestic sewage generated by the facility named on the COC.
PERMIT NO. MIG580000 Page 14 of 29 PART II
Part II may include terms and /or conditions not applicable to discharges covered under this permit.
Section A. Definitions Acute toxic unit (TUA) means 100/LC50 where the LC50 is determined from a whole effluent toxicity (WET) test which produces a result that is statistically or graphically estimated to be lethal to 50% of the test organisms. Annual monitoring frequency refers to a calendar year beginning on January 1 and ending on December 31. When required by this permit, an analytical result, reading, value or observation shall be reported for that period if a discharge occurs during that period. Bioaccumulative chemical of concern (BCC) means a chemical which, upon entering the surface waters, by itself or as its toxic transformation product, accumulates in aquatic organisms by a human health bioaccumulation factor of more than 1000 after considering metabolism and other physiochemical properties that might enhance or inhibit bioaccumulation. The human health bioaccumulation factor shall be derived according to R 323.1057(5). Chemicals with half-lives of less than 8 weeks in the water column, sediment, and biota are not BCCs. The minimum bioaccumulation concentration factor (BAF) information needed to define an organic chemical as a BCC is either a field-measured BAF or a BAF derived using the biota-sediment accumulation factor (BSAF) methodology. The minimum BAF information needed to define an inorganic chemical as a BCC, including an organometal, is either a field-measured BAF or a laboratory-measured bioconcentration factor (BCF). The BCCs to which these rules apply are identified in Table 5 of R 323.1057 of the Water Quality Standards. Biosolids are the solid, semisolid, or liquid residues generated during the treatment of sanitary sewage or domestic sewage in a treatment works. This includes, but is not limited to, scum or solids removed in primary, secondary, or advanced wastewater treatment processes and a derivative of the removed scum or solids. Bulk biosolids means biosolids that are not sold or given away in a bag or other container for application to a lawn or home garden. Certificate of Coverage (COC) is a document, issued by the Department, which authorizes a discharge under a general permit. Chronic toxic unit (TUC ) means 100/MATC or 100/IC25, where the maximum acceptable toxicant concentration (MATC) and IC25 are expressed as a percent effluent in the test medium. Class B biosolids refers to material that has met the Class B pathogen reduction requirements or equivalent treatment by a Process to Significantly Reduce Pathogens (PSRP) in accordance with the Part 24 Rules. Processes include aerobic digestion, composting, anaerobic digestion, lime stabilization and air drying. Combined sewer system is a sewer system in which storm water runoff is combined with sanitary wastes. Daily concentration is the sum of the concentrations of the individual samples of a parameter divided by the number of samples taken during any calendar day. If the parameter concentration in any sample is less than the quantification limit, regard that value as zero when calculating the daily concentration. The daily concentration will be used to determine compliance with any maximum and minimum daily concentration limitations (except for pH and dissolved oxygen). When required by the permit, report the maximum calculated daily concentration for the month in the “MAXIMUM” column under “QUALITY OR CONCENTRATION” on the Discharge Monitoring Reports (DMRs). For pH, report the maximum value of any individual sample taken during the month in the “MAXIMUM” column under “QUALITY OR CONCENTRATION” on the DMRs and the minimum value of any individual sample taken during the month in the “MINIMUM” column under “QUALITY OR CONCENTRATION” on the DMRs. For dissolved oxygen, report the minimum concentration of any individual sample in the “MINIMUM” column under “QUALITY OR CONCENTRATION” on the DMRs.
PERMIT NO. MIG580000 Page 15 of 29 PART II
Daily loading is the total discharge by weight of a parameter discharged during any calendar day. This value is calculated by multiplying the daily concentration by the total daily flow and by the appropriate conversion factor. The daily loading will be used to determine compliance with any maximum daily loading limitations. When required by the permit, report the maximum calculated daily loading for the month in the “MAXIMUM” column under “QUANTITY OR LOADING” on the DMRs. Daily monitoring frequency refers to a 24-hour day. When required by this permit, an analytical result, reading, value or observation shall be reported for that period if a discharge occurs during that period. Department means the Michigan Department of Environmental Quality. Detection level means the lowest concentration or amount of the target analyte that can be determined to be different from zero by a single measurement at a stated level of probability. Discharge means the addition of any waste, waste effluent, wastewater, pollutant, or any combination thereof to any surface water of the state. Discharge event is a discrete occurrence during which effluent is discharged to the surface water up to 10 days of a consecutive 14 day period. Discharge point is the location where the point source discharge is directed to surface waters of the state or to a separate storm sewer. It includes the location of all point source discharges where storm water exits the facility, including outfalls which discharge directly to surface waters of the state and points of discharge which discharge directly into separate storm sewer systems. EC50 means a statistically or graphically estimated concentration that is expected to cause 1 or more specified effects in 50% of a group of organisms under specified conditions. Fecal coliform bacteria monthly is the geometric mean of the samples collected during a discharge event. Days with no discharge shall not be used to determine the value. The calculated monthly value will be used to determine compliance with the maximum monthly fecal coliform bacteria limitations. When required by the permit, report the calculated monthly value in the “AVERAGE” column under “QUALITY OR CONCENTRATION” on the DMR. If the period in which the discharge event occurred was partially in each of two months, the monthly value shall be reported on the DMR of the month in which the last day of discharge occurred. Fecal coliform bacteria 7-day is the geometric mean of the samples collected in any 7-day period during a discharge event. The calculated 7-day value will be used to determine compliance with the maximum 7-day fecal coliform bacteria limitations. Days with no discharge shall not be used to determine the value. When required by the permit, report the maximum calculated 7-day concentration for the month in the “MAXIMUM” column under “QUALITY OR CONCENTRATION” on the DMRs. If the 7-day period was partially in each of two months, the value shall be reported on the DMR of the month in which the last day of discharge occurred. Flow proportioned sample is a composite sample with the sample volume proportional to the effluent flow. General permit means a National Pollutant Discharge Elimination System permit issued authorizing a category of similar discharges. Geometric mean is the average of the logarithmic values of a base 10 data set, converted back to a base 10 number. Grab sample is a single sample taken at neither a set time nor flow. IC25 means the toxicant concentration that would cause a 25% reduction in a nonquantal biological measurement for the test population. Individual permit means a site-specific NPDES permit. Inlet means a catch basin, roof drain, conduit, drain tile, retention pond riser pipe, sump pump, or other point where storm water or wastewater enters into a closed conveyance system prior to discharge off site or into waters of the state.
PERMIT NO. MIG580000 Page 16 of 29 PART II
Interference is a discharge which, alone or in conjunction with a discharge or discharges from other sources, both: 1) inhibits or disrupts the POTW, its treatment processes or operations, or its sludge processes, use or disposal; and 2) therefore, is a cause of a violation of any requirement of the POTW's NPDES permit (including an increase in the magnitude or duration of a violation) or, of the prevention of sewage sludge use or disposal in compliance with the following statutory provisions and regulations or permits issued thereunder (or more stringent state or local regulations): Section 405 of the Clean Water Act, the Solid Waste Disposal Act (SWDA) (including Title II, more commonly referred to as the Resource Conservation and Recovery Act (RCRA), and including state regulations contained in any state sludge management plan prepared pursuant to Subtitle D of the SWDA), the Clean Air Act, the Toxic Substances Control Act, and the Marine Protection, Research and Sanctuaries Act. [This definition does not apply to sample matrix interference]. LC50 means a statistically or graphically estimated concentration that is expected to be lethal to 50% of a group of organisms under specified conditions. Maximum acceptable toxicant concentration (MATC) means the concentration obtained by calculating the geometric mean of the lower and upper chronic limits from a chronic test. A lower chronic limit is the highest tested concentration that did not cause the occurrence of a specific adverse effect. An upper chronic limit is the lowest tested concentration which did cause the occurrence of a specific adverse effect and above which all tested concentrations caused such an occurrence. MGD means million gallons per day. Monthly concentration is the sum of the daily concentrations determined during a discharge event divided by the number of daily concentrations determined. The calculated monthly concentration will be used to determine compliance with any maximum monthly concentration limitations. Days with no discharge shall not be used to determine the value. When required by the permit, report the calculated monthly concentration in the “AVERAGE” column under “QUALITY OR CONCENTRATION” on the DMR. If the seven day period was partially in each of two months, the monthly average shall be reported on the DMR of the month in which the last day of discharge occurred. For minimum percent removal requirements, the monthly influent concentration and the monthly effluent concentration shall be determined. The calculated monthly percent removal, which is equal to 100 times the quantity [1 minus the quantity (monthly effluent concentration divided by the monthly influent concentration)], shall be reported in the "MINIMUM" column under "QUALITY OR CONCENTRATION" on the DMRs. Monthly loading is the sum of the daily loadings of a parameter divided by the number of daily loadings determined during a discharge event. The calculated monthly loading will be used to determine compliance with any maximum monthly loading limitations. Days with no discharge shall not be used to determine the value. When required by the permit, report the calculated monthly loading in the “AVERAGE” column under “QUANTITY OR LOADING” on the DMR. If the seven day period was partially in each of two months, the monthly average shall be reported on the DMR of the month in which the last day of discharge occurred.. Monthly monitoring frequency refers to a calendar month. When required by this permit, an analytical result, reading, value or observation shall be reported for that period if a discharge occurs during that period. National Pretreatment Standards are the regulations promulgated by or to be promulgated by the Federal Environmental Protection Agency pursuant to Section 307(b) and (c) of the Federal Act. The standards establish nationwide limits for specific industrial categories for discharge to a POTW. No observed adverse effect level (NOAEL) means the highest tested dose or concentration of a substance which results in no observed adverse effect in exposed test organisms where higher doses or concentrations result in an adverse effect. Noncontact cooling water is water used for cooling which does not come into direct contact with any raw material, intermediate product, by-product, waste product or finished product. Nondomestic user is any discharger to a POTW that discharges wastes other than or in addition to water-carried wastes from toilet, kitchen, laundry, bathing or other facilities used for household purposes. Outfall is the location of a point source discharge where storm water or treated wastewater is discharged directly to the surface waters of the state.
PERMIT NO. MIG580000 Page 17 of 29 PART II
Partially treated sewage is any sewage, sewage and storm water, or sewage and wastewater, from domestic or industrial sources that is treated to a level less than that required by the permittee's National Pollutant Discharge Elimination System permit, or that is not treated to national secondary treatment standards for wastewater, including discharges to surface waters from retention treatment facilities. Point of discharge is the location of a point source discharge where storm water is discharged directly into a separate storm sewer system. Point source discharge means a discharge from any discernible, confined, discrete conveyance, including but not limited to any pipe, ditch, channel, tunnel, conduit, well, discrete fissure, container, or rolling stock. Changing the surface of land or establishing grading patterns on land will result in a point source discharge where the runoff from the site is ultimately discharged to waters of the state. Polluting material means any material, in solid or liquid form, identified as a polluting material under the Part 5 Rules (R 324.2001 through R 324.2009 of the Michigan Administrative Code). POTW is a publicly owned treatment works. Pretreatment is reducing the amount of pollutants, eliminating pollutants, or altering the nature of pollutant properties to a less harmful state prior to discharge into a public sewer. The reduction or alteration can be by physical, chemical, or biological processes, process changes, or by other means. Dilution is not considered pretreatment unless expressly authorized by an applicable National Pretreatment Standard for a particular industrial category. Quantification level means the measurement of the concentration of a contaminant obtained by using a specified laboratory procedure calculated at a specified concentration above the detection level. It is considered the lowest concentration at which a particular contaminant can be quantitatively measured using a specified laboratory procedure for monitoring of the contaminant. Quarterly monitoring frequency refers to a three month period, defined as January through March, April through June, July through September, and October through December. When required by this permit, an analytical result, reading, value or observation shall be reported for that period if a discharge occurs during that period. Regional Administrator is the Region 5 Administrator, U.S. EPA, located at R-19J, 77 W. Jackson Blvd., Chicago, Illinois 60604. Secondary containment structure means a unit, other than the primary container, in which significant materials are packaged or held, which is required by State or Federal law to prevent the escape of significant materials by gravity into sewers, drains, or otherwise directly or indirectly into any sewer system or to the surface or ground waters of this state. Separate storm sewer system means a system of drainage, including, but not limited to, roads, catch basins, curbs, gutters, parking lots, ditches, conduits, pumping devices, or man-made channels, which is not a combined sewer where storm water mixes with sanitary wastes, and is not part of a POTW. Significant industrial user is a nondomestic user that: 1) is subject to Categorical Pretreatment Standards under 40 CFR 403.6 and 40 CFR Chapter I, Subchapter N; or 2) discharges an average of 25,000 gallons per day or more of process wastewater to a POTW (excluding sanitary, noncontact cooling and boiler blowdown wastewater); contributes a process waste stream which makes up five (5) percent or more of the average dry weather hydraulic or organic capacity of the POTW treatment plant; or is designated as such by the permittee as defined in 40 CFR 403.12(a) on the basis that the industrial user has a reasonable potential for adversely affecting the POTW's treatment plant operation or violating any pretreatment standard or requirement (in accordance with 40 CFR 403.8(f)(6)).
PERMIT NO. MIG580000 Page 18 of 29 PART II
Significant materials Significant Materials means any material which could degrade or impair water quality, including but not limited to: raw materials; fuels; solvents, detergents, and plastic pellets; finished materials such as metallic products; hazardous substances designated under Section 101(14) of Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) (see 40 CFR 372.65); any chemical the facility is required to report pursuant to Section 313 of Emergency Planning and Community Right-to-Know Act (EPCRA); polluting materials as identified under the Part 5 Rules (R 324.2001 through R 324.2009 of the Michigan Administrative Code); Hazardous Wastes as defined in Part 111 of the NREPA; fertilizers; pesticides; and waste products such as ashes, slag, and sludge that have the potential to be released with storm water discharges. Significant spills and significant leaks means any release of a polluting material reportable under the Part 5 Rules (R 324.2001 through R 324.2009 of the Michigan Administrative Code). Stoichiometric means the quantity of a reagent calculated to be necessary and sufficient for a given chemical reaction. Storm water means storm water runoff, snow melt runoff, surface runoff and drainage, and non-storm water included under the conditions of Part I.D.3. SWPPP means the Storm Water Pollution Prevention Plan prepared in accordance with Part I.C. of this permit. Tier I value means a value for aquatic life, human health or wildlife calculated under R 323.1057 of the Water Quality Standards using a tier I toxicity database. Tier II value means a value for aquatic life, human health or wildlife calculated under R 323.1057 of the Water Quality Standards using a tier II toxicity database. Total maximum daily loads (TMDLs) are required by the Federal Act for waterbodies that do not meet Water Quality Standards. TMDLs represent the maximum daily load of a pollutant that a waterbody can assimilate and meet Water Quality Standards, and an allocation of that load among point sources, nonpoint sources, and a margin of safety. Toxicity reduction evaluation (TRE) means a site-specific study conducted in a stepwise process designed to identify the causative agents of effluent toxicity, isolate the sources of toxicity, evaluate the effectiveness of toxicity control options, and then confirm the reduction in effluent toxicity. Water Quality Standards means the Part 4 Water Quality Standards promulgated pursuant to Part 31 of the NREPA, being R 323.1041 through R 323.1117 of the Michigan Administrative Code. Weekly monitoring frequency refers to a calendar week which begins on Sunday and ends on Saturday. When required by this permit, an analytical result, reading, value or observation shall be reported for that period if a discharge occurs during that period. 3-portion composite sample is a sample consisting of three equal-volume grab samples collected at equal intervals over an 8-hour period. 7-day concentration is the sum of the daily concentrations determined during any 7 days of discharge during a discharge event divided by the number of daily concentrations determined. If the number of days of the discharge event is less than 7 days the number of actual days of discharge shall be used for the calculation. The calculated 7-day concentration will be used to determine compliance with any maximum 7-day concentration limitations. When required by the permit, report the maximum calculated 7-day concentration for the month in the “MAXIMUM” column under “QUALITY OR CONCENTRATION” on the DMR. If the seven day period was partially in each of two months, the value shall be reported on the DMR of the month in which the last day of discharge occurred.
PERMIT NO. MIG580000 Page 19 of 29 PART II
7-day loading is the sum of the daily loadings of a parameter divided by the number of daily loadings determined during any 7 consecutive days. If the number of days of the discharge event is less than 7 days the number of actual days of discharge shall be used for the calculation. The calculated 7-day loading will be used to determine compliance with any maximum 7-day loading limitations. When required by the permit, report the maximum calculated 7-day loading for the month in the “MAXIMUM” column under “QUANTITY OR LOADING” on the DMR. If the seven day period in which the discharge event occurred was partially in each of two months, the value shall be reported on the DMR of the month in which the last day of discharge occurred. 24-hour composite sample is a flow-proportioned composite sample consisting of hourly or more frequent portions that are taken over a 24-hour period. A time-proportioned composite sample may be used upon approval of the Department if the permittee demonstrates it is representative of the discharge. 25-year, 24-hour rainfall event or 100-year, 24-hour rainfall event means the maximum 24-hour precipitation event with a probable recurrence interval of once in 25 years or 100 years, respectively, as defined by the “Rainfall Frequency Atlas of the Midwest,” Huff and Angel, Illinois State Water Survey, Champaign, Bulletin 71, 1992, and subsequent amendments, or equivalent regional or state rainfall probability information developed there from.
PERMIT NO. MIG580000 Page 20 of 29 PART II
Section B. Monitoring Procedures
1. Representative SamplesSamples and measurements taken as required herein shall be representative of the volume and nature of the monitored discharge.
2. Test ProceduresTest procedures for the analysis of pollutants shall conform to regulations promulgated pursuant to Section 304(h) of the Federal Act (40 CFR Part 136 - Guidelines Establishing Test Procedures for the Analysis of Pollutants), unless specified otherwise in this permit. Test procedures used shall be sufficiently sensitive to determine compliance with applicable effluent limitations. Requests to use test procedures not promulgated under 40 CFR Part 136 for pollutant monitoring required by this permit shall be made in accordance with the Alternate Test Procedures regulations specified in 40 CFR 136.4. These requests shall be submitted to the Chief of the Permits Section, Water Resources Division, Michigan Department of Environmental Quality, P.O. Box 30458, Lansing, Michigan, 48909-7958. The permittee may use such procedures upon approval.
The permittee shall periodically calibrate and perform maintenance procedures on all analytical instrumentation at intervals to ensure accuracy of measurements. The calibration and maintenance shall be performed as part of the permittee’s laboratory Quality Control/Quality Assurance program.
3. InstrumentationThe permittee shall periodically calibrate and perform maintenance procedures on all monitoring instrumentation at intervals to ensure accuracy of measurements.
4. Recording ResultsFor each measurement or sample taken pursuant to the requirements of this permit, the permittee shall record the following information: 1) the exact place, date, and time of measurement or sampling; 2) the person(s) who performed the measurement or sample collection; 3) the dates the analyses were performed; 4) the person(s) who performed the analyses; 5) the analytical techniques or methods used; 6) the date of and person responsible for equipment calibration; and 7) the results of all required analyses.
5. Records RetentionAll records and information resulting from the monitoring activities required by this General Permit including all records of analyses performed, and calibration and maintenance of instrumentation, and recordings from continuous monitoring instrumentation shall be retained for a minimum of three years, or longer if requested by the Regional Administrator or the Department as required by Part 21 of Act 451 of 1994, as amended, R 323.2155 of the Michigan Administrative Code.
PERMIT NO. MIG580000 Page 21 of 29 PART II
Section C. Reporting Requirements 1. Start-up Notification for New or Upgraded Facilities If the permittee will not discharge during the first 60 days following the effective date of the facility’s COC, the permittee shall notify the Department within 14 days following the effective date of the COC, and then 60 days prior to the commencement of the discharge.
2. Submittal Requirements for Self-Monitoring Data Part 31 of the NREPA, specifically Section 324.3110(3) and R 323.2155(2) of Part 21, allows the Department to specify the forms to be utilized for reporting the required self-monitoring data. Unless instructed on the effluent limitations page to conduct “Retained Self Monitoring” the permittee shall submit self-monitoring data via the Department’s Electronic Environmental Discharge Monitoring Reporting (e2-DMR) system. The permittee shall utilize the information provided on the e2-Reporting website at https://secure1.state.mi.us/e2rs/ to access and submit the electronic forms. Both monthly summary and daily data shall be submitted to the Department no later than the 20th day of the month following each month of the authorized discharge period(s). The permittee may be allowed to submit the electronic forms after this date if the Department has granted an extension to the submittal date.
3. Retained Self-Monitoring Requirements If instructed on the effluent limits page (or otherwise authorized by the Department in accordance with the provisions of this permit) to conduct retained self-monitoring, the permittee shall maintain a year-to-date log of retained self-monitoring results and, upon request, provide such log for inspection to the Department (Department as defined on the COC). Retained self-monitoring results are public information and shall be promptly provided to the public upon request. The permittee shall certify, in writing, to the Department, on or before January 10th of each year, that: 1) all retained self-monitoring requirements have been complied with and a year-to-date log has been maintained; and 2) the application on which this permit is based still accurately describes the discharge. With this annual certification, the permittee shall submit a summary of the previous year’s monitoring data. The summary shall include maximum values for samples to be reported as daily maximums and/or monthly maximums and minimum values for any daily minimum samples. Retained self-monitoring may be denied to a permittee by notification in writing from the Department. In such cases, the permittee shall submit self-monitoring data in accordance with Part II.C.2., above. Such a denial may be rescinded by the Department upon written notification to the permittee. Reissuance or modification of this permit or reissuance or modification of an individual permittee’s authorization to discharge shall not affect previous approval or denial for retained self-monitoring unless the Department provides notification in writing to the permittee.
4. Additional Monitoring by Permittee If the permittee monitors any pollutant at the location(s) designated herein more frequently than required by this permit, using approved analytical methods as specified above, the results of such monitoring shall be included in the calculation and reporting of the values required in the DMR. Such increased frequency shall also be indicated. Monitoring required pursuant to Part 41 of the NREPA or Rule 35 of the Mobile Home Park Commission Act (Act 96 of the Public Acts of 1987) for assurance of proper facility operation shall be submitted as required by the Department.
PERMIT NO. MIG580000 Page 22 of 29 PART II
Section C. Reporting Requirements 5. Compliance Dates Notification Within 14 days of every compliance date specified in this permit, the permittee shall submit a written notification to the Department indicating whether or not the particular requirement was accomplished. If the requirement was not accomplished, the notification shall include an explanation of the failure to accomplish the requirement, actions taken or planned by the permittee to correct the situation, and an estimate of when the requirement will be accomplished. If a written report is required to be submitted by a specified date and the permittee accomplishes this, a separate written notification is not required.
6. Noncompliance Notification Compliance with all applicable requirements set forth in the Federal Act, Parts 31 and 41 of the NREPA, and related regulations and rules is required. All instances of noncompliance shall be reported as follows: a. 24-hour reporting - Any noncompliance which may endanger health or the environment (including maximum and/or minimum daily concentration discharge limitation exceedances) shall be reported, verbally, within 24 hours from the time the permittee becomes aware of the noncompliance. A written submission shall also be provided within five days. b. other reporting - The permittee shall report, in writing, all other instances of noncompliance not described in Part II.C.6.a. above at the time monitoring reports are submitted; or, in the case of retained self-monitoring, within five days from the time the permittee becomes aware of the noncompliance. Written reporting shall include: 1) a description of the discharge and cause of noncompliance; and 2) the period of noncompliance, including exact dates and times; or, if not corrected, the anticipated time the noncompliance is expected to continue, and the steps taken to reduce, eliminate, and prevent recurrence of the noncomplying discharge.
7. Spill Notification The permittee shall immediately report any release of any polluting material which occurs to the surface waters or groundwaters of the state, unless the permittee has determined that the release is not in excess of the threshold reporting quantities specified in the Part 5 Rules (R 324.2001 through R 324.2009 of the Michigan Administrative Code), by calling the Department at the number indicated in the COC, or if the notice is provided after regular working hours call the Department’s 24-hour Pollution Emergency Alerting System telephone number, 1-800-292-4706. Within ten days of the release, the permittee shall submit to the Department a full written explanation as to the cause of the release, the discovery of the release, response (clean-up and/or recovery) measures taken, and preventative measures taken or a schedule for completion of measures to be taken to prevent reoccurrence of similar releases.
PERMIT NO. MIG580000 Page 23 of 29 PART II
Section C. Reporting Requirements 8. Upset Noncompliance Notification If a process "upset" (defined as an exceptional incident in which there is unintentional and temporary noncompliance with technology based permit effluent limitations because of factors beyond the reasonable control of the permittee) has occurred, the permittee who wishes to establish the affirmative defense of upset, shall notify the Department by telephone within 24-hours of becoming aware of such conditions; and within five days provide in writing the following information: a. that an upset occurred and that the permittee can identify the specific cause(s) of the upset; b. that the permitted wastewater treatment facility was, at the time, being properly operated and maintained
(note that an upset does not include noncompliance to the extent caused by operational error, improperly designed treatment facilities, inadequate treatment facilities, lack of preventive maintenance, or careless or improper operation); and
c. that the permittee has specified and taken action on all responsible steps to minimize or correct any
adverse impact in the environment resulting from noncompliance with this permit. No determination made during administrative review of claims that noncompliance was caused by upset, and before an action for noncompliance, is final administrative action subject to judicial review. In any enforcement proceedings, the permittee, seeking to establish the occurrence of an upset, has the burden of proof.
9. Bypass Prohibition and Notification a. Bypass Prohibition - Bypass is prohibited, and the Department may take an enforcement action, unless:
1) bypass was unavoidable to prevent loss of life, personal injury, or severe property damage; 2) there were no feasible alternatives to the bypass, such as the use of auxiliary treatment
facilities, retention of untreated wastes, or maintenance during normal periods of equipment downtime. This condition is not satisfied if adequate backup equipment should have been installed in the exercise of reasonable engineering judgment to prevent a bypass; and
3) the permittee submitted notices as required under Part II.C.9.b. or 9.c. below.
b. Notice of Anticipated Bypass - If the permittee knows in advance of the need for a bypass, it shall submit
prior notice to the Department, if possible at least ten days before the date of the bypass, and provide information about the anticipated bypass as required by the Department. The Department may approve an anticipated bypass, after considering its adverse effects, if it will meet the three conditions listed in Part II.C.9.a. above.
c. Notice of Unanticipated Bypass - The permittee shall submit notice to the Department of an
unanticipated bypass by calling the Department at the number indicated in the COC (if the notice is provided after regular working hours, use the following number: 1-800-292-4706) as soon as possible, but no later than 24 hours from the time the permittee becomes aware of the circumstances.
d. Written Report of Bypass - A written submission shall be provided within five working days of
commencing any bypass to the Department, and at additional times as directed by the Department. The written submission shall contain a description of the bypass and its cause; the period of bypass, including exact dates and times, and if the bypass has not been corrected, the anticipated time it is expected to continue; steps taken or planned to reduce, eliminate, and prevent reoccurrence of the bypass; and other information as required by the Department.
PERMIT NO. MIG580000 Page 24 of 29 PART II
Section C. Reporting Requirements e. Bypass Not Exceeding Limitations - The permittee may allow any bypass to occur which does not cause
effluent limitations to be exceeded, but only if it also is for essential maintenance to assure efficient operation. These bypasses are not subject to the provisions of Part II.C.9.a., 9.b., 9.c., and 9.d., above. This provision does not relieve the permittee of any notification responsibilities under Part II.C.11. of this General Permit.
f. Definitions
1) Bypass means the intentional diversion of waste streams from any portion of a treatment facility
2) Severe property damage means substantial physical damage to property, damage to the treatment facilities which causes them to become inoperable, or substantial and permanent loss of natural resources which can reasonably be expected to occur in the absence of a bypass. Severe property damage does not mean economic loss caused by delays in production.
10. Bioaccumulative Chemicals of Concern (BCC) Consistent with the requirements of R 323.1098 and R 323.1215 of the Michigan Administrative Code, the permittee is prohibited from undertaking any action that would result in a lowering of water quality from an increased loading of a BCC unless an increased use request and antidegradation demonstration have been submitted and approved by the Department.
11. Notification of Changes in Discharge The permittee shall notify the Department, in writing, as soon as possible but no later than ten days of knowing, or having reason to believe, that any activity or change has occurred or will occur which would result in the discharge of: 1) detectable levels of chemicals on the current Michigan Critical Materials Register, priority pollutants or hazardous substances set forth in 40 CFR 122.21, Appendix D, or the Pollutants of Initial Focus in the Great Lakes Water Quality Initiative specified in 40 CFR 132.6, Table 6, which were not acknowledged in the application or listed in the application at less than detectable levels; 2) detectable levels of any other chemical not listed in the application or listed at less than detection, for which the application specifically requested information; or 3) any chemical at levels greater than five times the average level reported in the complete application (see the COC for the date[s] the complete application was submitted). Any other monitoring results obtained as a requirement of this permit shall be reported in accordance with the compliance schedules.
12. Changes in Facility Operations Any anticipated action or activity, including but not limited to facility expansion, production increases, or process modification, which will result in new or increased loadings of pollutants to the receiving waters must be reported to the Department by submission of an increased use request (application) and all information required under R 323.1098 (Antidegradation) of the Water Quality Standards; or b) by notice if the following conditions are met: the action or activity will not result in a change in the types of wastewater discharged or result in a greater quantity of wastewater than currently authorized by this permit; the action or activity will not result in violations of the effluent limitations specified in this permit; the action or activity is not prohibited by the requirements of Part II.C.10.; and the action or activity will not require notification pursuant to Part II.C.11.
Following such notice, the permit may be modified according to applicable laws and rules to specify and limit any pollutant not previously limited.
PERMIT NO. MIG580000 Page 25 of 29 PART II
Section C. Reporting Requirements 13. Transfer of Ownership or Control In the event of any change in control or ownership of facilities from which the authorized discharge emanates, the permittee shall submit to the Department 30 days prior to the actual transfer of ownership or control a written agreement between the current permittee and the new permittee containing: 1) the legal name and address of the new owner; 2) a specific date for the effective transfer of permit responsibility, coverage, and liability; and 3) a certification of the continuity of or any changes in operations, wastewater discharge, or wastewater treatment. If the new permittee is proposing changes in operations, wastewater discharge, or wastewater treatment, the Department may propose modification of this General Permit in accordance with applicable laws and rules.
14. Operations and Maintenance Manual For wastewater treatment facilities that serve the public (and are thus subject to Part 41 of the NREPA), Section 4104 of Part 41 and associated Rule 2957 of the Michigan Administrative Code allow the Department to require an Operations and Maintenance (O&M) Manual from the facility. Part 41 of Act 451 of 1994, as amended, specifically Section 324.4104 and associated R 299.2957, allow the Department to require an Operations and Maintenance (O&M) manual for the wastewater treatment facility. An up-to-date copy of the O&M manual shall be kept at the wastewater treatment facility. Upon request a copy of the O&M manual shall be provided to the Department. The Department may review the manual in whole or in part at their discretion and require modifications to it if portions are determined to be inadequate. At a minimum, the O&M manual should include the following information: permit standards, description and operation information for all equipment, staffing information, laboratory requirements, record keeping requirements, maintenance plan for equipment, emergency operating plan, safety program information and copies of all pertinent forms, as-built plans, and manufacturer’s manuals. Certification of the existence and accuracy of the operations and maintenance manual is required to be submitted to the Department at least 60 days prior to startup of a new wastewater treatment plant. Submittal of re-certifications will also be required 60 days prior to start-up of any substantial improvements or modifications made at the wastewater treatment plant.
15. Signatory Requirements All applications, reports, or information submitted to the Department in accordance with the conditions of this General Permit or the facility’s COC that require a signature shall be signed and certified as described in the Federal Act and the NREPA. The Federal Act provides that any person who knowingly makes any false statement, representation, or certification in any record or other document submitted or required to be maintained under this General Permit or the facility’s COC, including monitoring reports or reports of compliance or noncompliance, shall, upon conviction, be punished by a fine of not more than $10,000 per violation, or by imprisonment for not more than six months per violation, or by both.
PERMIT NO. MIG580000 Page 26 of 29 PART II
Section C. Reporting Requirements The NREPA (Section 3115(2)) provides that a person who at the time of the violation knew or should have known that he or she discharged a substance contrary to this part, or contrary to a permit, COC, or order issued or rule promulgated under this part, or who intentionally makes a false statement, representation, or certification in an application for or form pertaining to a permit or COC or in a notice or report required by the terms and conditions of an issued permit or COC, or who intentionally renders inaccurate a monitoring device or record required to be maintained by the Department, is guilty of a felony and shall be fined not less than $2,500.00 or more than $25,000.00 for each violation. The court may impose an additional fine of not more than $25,000.00 for each day during which the unlawful discharge occurred. If the conviction is for a violation committed after a first conviction of the person under this subsection, the court shall impose a fine of not less than $25,000.00 per day and not more than $50,000.00 per day of violation. Upon conviction, in addition to a fine, the court in its discretion may sentence the defendant to imprisonment for not more than two years or impose probation upon a person for a violation of this part. With the exception of the issuance of criminal complaints, issuance of warrants, and the holding of an arraignment, the circuit court for the county in which the violation occurred has exclusive jurisdiction. However, the person shall not be subject to the penalties of this subsection if the discharge of the effluent is in conformance with and obedient to a rule, order, permit, or COC of the Department. In addition to a fine, the attorney general may file a civil suit in a court of competent jurisdiction to recover the full value of the injuries done to the natural resources of the state and the costs of surveillance and enforcement by the state resulting from the violation.
16. Electronic Reporting Upon notice by the Department that electronic reporting tools are available for specific reports or notifications, the permittee shall submit all such reports or notifications as requited by this permit, electronically.
PERMIT NO. MIG580000 Page 27 of 29 PART II
Section D. Management Responsibilities 1. Duty to Comply All discharges authorized herein shall be consistent with the terms and conditions of this permit and the facility’s COC. The discharge of any pollutant identified in this permit and/or the facility’s COC more frequently than or at a level in excess of that authorized shall constitute a violation of the permit. It is the duty of the permittee to comply with all the terms and conditions of this permit and the facility’s COC. Any noncompliance with the Effluent Limitations, Special Conditions, or terms of this permit or the facility’s COC constitutes a violation of the NREPA and/or the Federal Act and constitutes grounds for enforcement action; for COC termination, revocation and reissuance, or modification; or denial of an application for COC renewal. It shall not be a defense for a permittee in an enforcement action that it would have been necessary to halt or reduce the permitted activity in order to maintain compliance with the conditions of this permit.
2. Operator Certification The permittee shall have the waste treatment facilities under direct supervision of an operator certified at the appropriate level for the facility certification by the Department, as required by Sections 3110 and 4104 of the NREPA.
3. Facilities Operation The permittee shall, at all times, properly operate and maintain all treatment or control facilities or systems installed or used by the permittee to achieve compliance with the terms and conditions of this permit. Proper operation and maintenance includes adequate laboratory controls and appropriate quality assurance procedures.
4. Power Failures In order to maintain compliance with the effluent limitations of this permit and prevent unauthorized discharges, the permittee shall either: a. provide an alternative power source sufficient to operate facilities utilized by the permittee to maintain
compliance with the effluent limitations and conditions of this permit; or b. upon the reduction, loss, or failure of one or more of the primary sources of power to facilities utilized by
the permittee to maintain compliance with the effluent limitations and conditions of this General Permit, the permittee shall halt, reduce, or otherwise control production and/or all discharge in order to maintain compliance with the effluent limitations and conditions of this permit.
5. Adverse Impact The permittee shall take all reasonable steps to minimize any adverse impact to the surface waters or groundwaters of the state resulting from noncompliance with any effluent limitation specified in this permit including, but not limited to, such accelerated or additional monitoring as necessary to determine the nature and impact of the discharge in noncompliance.
6. Containment Facilities The permittee shall provide facilities for containment of any accidental losses of polluting materials in accordance with the requirements of the Part 5 Rules (R 324.2001 through R 324.2009 of the Michigan Administrative Code). For a Publicly Owned Treatment Work (POTW), these facilities shall be approved under Part 41 of the NREPA.
PERMIT NO. MIG580000 Page 28 of 29 PART II
Section D. Management Responsibilities
7. Waste Treatment Residues Residuals (i.e. solids, sludges, biosolids, filter backwash, scrubber water, ash, grit, or other pollutants or wastes) removed from or resulting from treatment or control of wastewaters, including those that are generated during treatment or left over after treatment or control has ceased, shall be disposed of in an environmentally compatible manner and according to applicable laws and rules. These laws may include, but are not limited to, the NREPA, Part 31 for protection of water resources, Part 55 for air pollution control, Part 111 for hazardous waste management, Part 115 for solid waste management, Part 121 for liquid industrial wastes, Part 301 for protection of inland lakes and streams, and Part 303 for wetlands protection. Such disposal shall not result in any unlawful pollution of the air, surface waters, or groundwaters of the state.
8. Right of Entry The permittee shall allow the Department, any agent appointed by the Department or the Regional Administrator, upon the presentation of credentials: a. to enter upon the permittee’s premises where an effluent source is located or in which any records are
required to be kept under the terms and conditions of this permit; and b. at reasonable times to have access to and copy any records required to be kept under the terms and
conditions of this General Permit; to inspect process facilities, treatment works, monitoring methods, and equipment regulated or required under this permit; and to sample any discharge of pollutants.
9. Availability of Reports Except for data determined to be confidential under Section 308 of the Federal Act and Rule 2128 (R 323.2128 of the Michigan Administrative Code), all reports prepared in accordance with the terms of this permit shall be available for public inspection at the offices of the Department and the Regional Administrator. As required by the Federal Act, effluent data shall not be considered confidential. Knowingly making any false statement on any such report may result in the imposition of criminal penalties as provided for in Section 309 of the Federal Act and Sections 3112, 3115, 4106, and 4110 of the NREPA.
10. Duty to Provide Information The permittee shall furnish to the Department, within a reasonable time, any information which the Department may request to determine whether cause exists for modifying, revoking and reissuing, or terminating this General Permit or to determine compliance with the permit. The permittee shall also furnish to the Department, upon request, copies of records required to be kept by this permit. Where the permittee becomes aware that it failed to submit any relevant facts in a permit application, or submitted incorrect information in a permit application or in any report to the Department, it shall promptly submit such facts or information.
PERMIT NO. MIG580000 Page 29 of 29
PART II Section E. Activities Not Authorized by This Permit
1. Discharge to the Groundwaters This permit does not authorize any discharge to the groundwaters. Such discharge may be authorized by a groundwater discharge permit issued pursuant to the NREPA.
2. Facility Construction This General Permit does not authorize or approve the construction or modification of any physical structures or facilities. Approval for such construction for a POTW must be by permit issued under Part 41 of the NREPA. Approval for such construction for a mobile home park, campground, or marina shall be from the Water Resources Division, Michigan Department of Environmental Quality. Approval for such construction for a hospital, nursing home, or extended care facility shall be from the Division of Health Facilities and Services, Michigan Department of Consumer and Industry Services upon request.
3. Civil and Criminal Liability Except as provided in permit conditions on "Bypass" (Part II.C.9. pursuant to 40 CFR 122.41(m)), nothing in this General Permit shall be construed to relieve the permittee from civil or criminal penalties for noncompliance, whether or not such noncompliance is due to factors beyond the permittee’s control, such as accidents, equipment breakdowns, or labor disputes.
4. Oil and Hazardous Substance Liability Nothing in this permit shall be construed to preclude the institution of any legal action or relieve the permittee from any responsibilities, liabilities, or penalties to which the permittee may be subject under Section 311 of the Federal Act except as are exempted by federal regulations.
5. State Laws Nothing in this permit shall be construed to preclude the institution of any legal action or relieve the permittee from any responsibilities, liabilities, or penalties established pursuant to any applicable state law or regulation under authority preserved by Section 510 of the Federal Act.
6. Property Rights The issuance of this permit does not convey any property rights in either real or personal property, or any exclusive privileges, nor does it authorize violation of any federal, state, or local laws or regulations, nor does it obviate the necessity of obtaining such permits, including any other Department of Environmental Quality permits, or approvals from other units of government as may be required by law.
STATE OF MICHIGAN
DEPARTMENT OF ENVIRONMENTAL QUALITY
LANSINGRICK SNYDER
GOVERNOR
DAN WYANTDIRECTOR
August 6, 2015
City ClerkCity of Coleman201 East RailwayP.O. Box 504Coleman, Michigan 48618
Dear Sir or Madam:
SUBJECT: National Pollutant Discharge Elimination System (NPDES)Certificate of Coverage No. MIG580367Designated Name: Coleman WWSL
Your Certificate of Coverage (COC), issued under NPDES General Permit No. MIG580000, hasbeen processed in accordance with the appropriate State and Federal regulations.
The issuance of this COC does not authorize the violation of any federal, state, or local laws or regulations, nor does it obviate the need to obtain such permits, including any other Departmentof Environmental Quality (DEQ) permits, or approvals from other units of government, as may be required by law.
Please carefully review the effluent limitations and monitoring requirements contained in Certificate of Coverage No. MIG580367 (enclosed) and General Permit No. MIG580000. These requirements are subject to the criminal and civil enforcement provisions of both State and Federal law. Permit compliance and violations are audited by the DEQ and the United States Environmental Protection Agency.
If you need a copy of the General Permit, one can be obtained via the Internet at: (http://www.michigan.gov/deqnpdes - click on "General NPDES Permits," which is under the Permits banner), or you may call 517-284-5568 to request a paper copy be sent to you.
Please see the enclosed Appendix for a summary of the items in General Permit No. MIG580000 that have been added to, or revised from, the previous version of the General Permit (General Permit No. MIG589000).
The COC includes the following new requirements: Part I.A.3. of the General Permit – Groundwater Monitoring for Lagoon Exfiltration/Leakage
CONSTITUTION HALL ● 525 WEST ALLEGAN STREET ● P.O. BOX 30473 ● LANSING, MICHIGAN 48909-7973
www.michigan.gov/dnre ● (800) 662-9278
City of Coleman Wastewater Stabilization LagoonNPDES Certificate of Coverage No. MIG580367Page 2
You must comply with the limitations, monitoring requirements, and other responsibilities in accordance with General Permit No. MIG580000 and Certificate of Coverage No. MIG580367. Any reports, notifications, or questions regarding the NPDES program, the General Permit, or the enclosed COC should be directed to the DEQ office indicated on your COC.
Self-monitoring data is now required to be reported via the DEQ Electronic Environmental Discharge Monitoring Reporting (e2-DMR) system (see Part II.C.2. of the General Permit) unless stated otherwise in the General Permit or this letter.
If your NPDES permit application included data on water treatment additives proposed for use at your facility, you will be contacted by the DEQ under separate correspondence. The enclosed COC does not authorize the discharge of water additives. You must receive written approval prior to discharging any additives from your facility.
Sincerely,
Kevin C. CookLakes Erie and Huron Permits UnitPermits SectionWater Resources Division517-284-5585
kcc/sea
Enclosures cc/enc: Mr. William Cozat, Public Services Director, City of Coleman
Mr. Eric Cozat, Operator, City of Coleman Mr. Robert Lehmann, Saginaw Bay District Office, Water Resources Division, DEQ (electronic)Permits Section-ICIS, Water Resources Division, DEQFile
City of Coleman Wastewater Stabilization LagoonNPDES Certificate of Coverage No. MIG580367Page 3
*** IMPORTANT NOTICE ***
In August 2015, the DEQ, Water Resources Division (WRD), is planning to launch a new information system called MiWaters. MiWaters will be a state-of-the-art, comprehensive, Web-based permitting and compliance database. The system will replace over 25 applications and databases currently used by the WRD, some of which are over 30 years old.
MiWaters will establish a streamlined electronic permitting process, allowing Michigan to fulfill federal electronic reporting requirements and providing an online component for access to public information. The focus of MiWaters will be permitting and compliance, including NPDES Permits (including storm water permits) and Groundwater Discharge Permits. It will also includeelectronic reporting of untreated or partially-treated sanitary wastewater.
One of our focuses in developing MiWaters is to create a system that makes it easier for the WRD to communicate with, and provide services electronically to, our regulated community. Below is a list of some of the functions and features that MiWaters will provide:
• Permit applications will be submitted electronically.
• The current Electronic Environmental Discharge Monitoring Reporting (e2-DMR) system will be replaced with a more sophisticated system that will provide additional validation and feedback to permittees, and help detect and prevent errors prior to submittal.
• All permit-required submittals will be submitted electronically.
• Those with a MiWaters account will be able to manage permissions, deciding who can view, edit, and submit applications or submittals.
• Wastewater treatment plants will manage biosolids application sites online. Requests may be submitted through MiWaters with notification sent upon approval.
• MiWaters will provide near real-time notifications to the permittee of any violations determined by the system or by staff, providing permittees with an early “heads up” and opportunity to correct problems.
Upon implementation of MiWaters, paper applications forNPDES permits will no longer be accepted.
Additional information will be made available prior to the implementation of MiWaters.
* * * * *
City of Coleman Wastewater Stabilization LagoonNPDES Certificate of Coverage No. MIG580367Page 4
Appendix
Summary of the items in General Permit No. MIG580000 that have been added to, or revised from, the previous version of the General Permit (General Permit No. MIG589000):
Part I.A.1.b. – Acceptable spring discharge period for facilities in the western Upper Peninsula is April 1 through June 21. This period applies only upon approval from the appropriate District supervisor.
Part I.A.1.c. – For discharges outside the acceptable discharge periods, the permittee shall notify the DEQ of the potential noncompliance prior to discharge, as required. This requirement applies to all facilities.
Part I.A.1.d.2) – If more than two weeks pass prior to the beginning of discharge, additional pre-discharge samples shall be obtained and analyzed prior to discharge. This requirement applies to all facilities.
Part I.A.1.d.3) – The permittee shall supply the results of all pre-discharge effluent samples and the results of a Dissolved Oxygen sample taken no more than 24 hours prior to notification. This requirement applies to all facilities.
Part I.A.1.e. – Discharge monitoring reports shall be submitted for the months of October, November, December, March, April, and May, whether or not there has been a discharge. This requirement applies to all facilities. Those facilities in the western Upper Peninsula that have received approval to discharge in June must also submit a June report.
Part I.A.1.f. – Lagoon systems that utilize sophisticated mechanical equipment should consider more secure fencing and access control. This requirement applies to all facilities.
Part I.A.2.b.2) – At all times, the facility shall be maintained to prevent the negative effects of floating material and/or water perimeter emergent rooted aquatic plants on Dissolved Oxygen concentrations, treatment efficiency, nuisance organisms, offensive odors, or other measurable impacts. However, in no case, even without demonstrated impact, shall the floating material and/or water perimeter emergent rooted aquatic plants exceed 40 percent cover.
Part I.A.3. – Groundwater Monitoring for Lagoon Exfiltration/Leakage replacement language for Testing for Lagoon Exfiltration/Leakage section. This requirement applies to some facilities. Those facilities required to conduct this testing will have the requirement noted on their COC.
Part I.A.9. and Part I.A.10. – Residuals Management Program (RMP) for Land Application of Biosolids. The COC will indicate which one of the two requirements applies: First RMP,new uses, or Approved RMPs.
City of Coleman Wastewater Stabilization LagoonNPDES Certificate of Coverage No. MIG580367Page 5
Part II.A. – Definitions have been added for: annual monitoring frequency (previously yearly frequency of analysis); certificate of coverage; combined sewer system; discharge; discharge point; general permit; individual permit; inlet; monthly monitoring frequency (previously frequency of analysis); outfall; point of discharge; point source discharge; polluting material; quarterly monitoring frequency (previously quarterly frequency of analysis); secondary containment structure; separate storm sewer system; significant spills and significant leaks; stoichiometric; storm water; SWPPP; total maximum daily loads; weekly monitoring frequency (previously weekly frequency of analysis); and 25-year, 24-hour rainfall event or 100-year, 24-hour rainfall event.
Part II.C.6. – For 24-hour reporting, any noncompliance that may endanger health or the environment (including minimum and/or maximum daily concentration discharge limitation exceedances) shall be reported. This requirement applies to all facilities.
Part II.C.8.a. – Note that an upset does not include noncompliance to the extent caused byoperational error, improperly designed treatment facilities, inadequate treatment facilities, lack of preventative maintenance, or careless or improper operation. This requirement applies to all facilities.
Part II.C.8. – No determination made during administrative review of claims that noncompliance was caused by upset, and before an action for noncompliance, is a final administrative action subject to judicial review.
Part II.C.14. – Operations and Maintenance Manual. This requirement only applies to facilities that serve the public and are subject to Part 41.
Part II.C.15. – Signatory Requirements. This requirement applies to all facilities.
Part II.C.16. – Electronic Reporting. This requirement applies to all facilities.
Part II.D.10. – Duty to Provide Information. This requirement applies to all facilities.
V2
74
8.3
2
H3
V7
74
4.2
6
CITY OF COLEMAN
MIDLAND COUNTY, MICHIGAN
VICINITY MAP
MIDLAND COUNTY
CIT
Y O
F C
OL
EM
AN
, M
ID
LA
ND
C
OU
NT
Y M
IC
HIG
AN
SE
WA
GE
L
AG
OO
N/P
UM
P S
TA
TIO
N IM
PR
OV
EM
EN
TS
Know what's below.before you dig.Call
R
834310
2125 Ridgewood Dr, Suite 101
P: 989.837.3280
F: 989.837.3290
Midland, MI 48642
F&V PROJECT NO.
DESIGN. BUILD. OPERATE.
DATUM
VERTICAL: NAVD88
HORIZONTAL: NAD83
ALL PROPERTY AND/OR RIGHT-OF-WAY LINES
SHOWN ARE APPROXIMATE
THE LOCATION OF UNDERGROUND UTILITIES SHOWN
ARE APPROXIMATE AND ARE BASED ON PLANS
PROVIDED BY UTILITY COMPANIES AND / OR THE
CITY OF COLEMAN OR IN FIELD OBSERVATIONS.
N
COLEMAN OFF RAMP
IN
DU
ST
RIA
L D
RIV
E
PROJECT LOCATION
834310-Coleman ICE CS
050118 dand
CS
SEWAGE
LAGOONS
US
-1
0
LOCATION MAP
NO SCALE
SIXTH STREET
NORTH
UTILITIY CONTACTS
TELEPHONE:
FRONTIER COMMUNICATIONS
345 PINE AVENUE
ALMA, MI 48801
ATTENTION: MARK MARSHALL
PHONE: 989-463-0392
GAS:
CONSUMERS ENERGY
2400 WEISS STREET
SAGINAW, MI 48602
ATTENTION: MARCIA WILSON
PHONE: 989-791-5869
ELECTRIC:
CONSUMERS ENERGY
2400 WEISS STREET
SAGINAW, MI 48602
ATTENTION: RICH KLENDER
PHONE: 989-466-4279
CITY OF COLEMAN DPW:
PUBLIC SERVICES DIRECTOR
201 E. RAILWAY STREET
CITY OF COLEMAN, MI 48615
ATTENTION: BILL COZAT
PHONE: 989-465-9182
MIDLAND COUNTY DRAIN COMMISSIONER:
220 W. ELLSWORTH STREET
MIDLAND, MI 48640
ATTENTION: DOUGLAS ENOS
PHONE: 989-832- 6770
INDEX OF DRAWINGS
DESCRIPTION
SHEET
NO.
COVER SHEET CS
TOPOGRAPHIC - REMOVAL PLAN C01
SEWAGE LAGOON REPAIRS C02
TYPICAL BERM SECTION C03
PRIMARY CELL PHOTOS C04
LAGOON DETAILS C05
PUMP STATION SITE PLAN C06
PUMP STATION SITE UTILITY PLAN C07
PUMP STATION SITE GRADING PLAN C08
STANDARD DETAILS C09
DETAIL SHEET C10
DIVERSION STRUCTURE DETAIL SHEET C11
PUMP STATION PLAN - PROFILE P01
PROCESS FLOW SCHEMATIC & HYDRAULIC PROFILE P02
BUILDING FLOOR PLAN A01
BUILDING ELEVATIONS AND SECTION A02
ELECTRICAL LEGEND E01
ELECTRICAL SITE PLAN E02
ELECTRIC PANEL BUILDING ELECTRICAL PLAN E03
PUMP STATION WIRNG DIAGRAM E04
PUMP STATION WIRING DIAGRAM E05
SEWAGE LAGOON/PUMP STATION IMPROVEMENTS
WITH GREEN INFRASTRUCTURE
BIORETENTION POND
COLEMAN - MSC 216040 - ICE
APRIL 2018
ADDENDUM #3 05/01/18
744.5
745.5
745.4
744.7
743.5
742.7
743.6
743.2
743.5
743.8
749.8
750.4
750.3
744.1
744.4
743.9
744.4
743.5
743.8
743.6
750.4
750.3
749.9
749.8
744.3
744.3
HV
5
74
4.0
1
H3
749.9
FIELD LINE
HV
6
74
5.4
8
7
4
5
7
4
5
750
745
7
4
5
745
745
7
5
0
750
750
744.8
744.8
744.2
744.3
744.0
744.3
744.8
750.3
749.9
750.1
749.8
748.8
749.4
743.6
749.6
749.6
750.4
749.5
749.8
749.9
749.2
749.4
744.5
744.2
750.5
749.7
749.9
750.1
750.0
749.4
749.7
749.7
750.4
750.3
749.9
750.2
745.1
744.7
744.1
743.5
744.1
742.4
744.6
743.2
742.4
744.5
743.9
743.3
742.1
741.4
741.2
740.8
740.5
740.9
741.7
742.0
743.6
741.5
742.5
742.3
741.3
741.5
741.6
742.1
742.1
742.4
742.9
741.4
742.3
741.5
ST
AN
DIN
G
WA
TE
R
74
57
45
74
5
7
4
5
75
0
750
7
5
0
745
75
0
750
750
75
0
74
5
74
5
745
740
740
74
0
745
742.9
FIE
LD
LIN
E
FIE
LD
LIN
E
T
R
A
I
L
TRAIL
TR
AIL
TRAIL
TRAIL
TR
AIL
BR
US
H
F&V PROJECT NO.
DESIGN TEAM:
DRAWING INFORMATION:
CHECK BY:
REVISION:
CIT
Y O
F C
OL
EM
AN
MID
LA
ND
C
OU
NT
Y, M
IC
HIG
AN
SE
WA
GE
L
AG
OO
N/P
UM
P S
TA
TIO
N IM
PR
OV
EM
EN
TS
MAR 2018
834310
2125 Ridgewood Dr, Suite 101
P: 989.837.3280
F: 989.837.3290
Midland, MI 48642
DESIG
N. BU
ILD. O
PERATE.
3
AD
DE
ND
UM
N
O. 3
04/12/18
DJD
2
NORTH
CELL NO. 1 CELL NO. 2 CELL NO. 3
834310-Coleman ICE C01a
050118 dand
TO
PO
GR
AP
HIC
- R
EM
OV
AL
P
LA
N
GOB/DJD/DJD
C01
SECONDARY SEEPAGE CELL SECONDARY SEEPAGE CELLSECONDARY SEEPAGE CELL
REMOVE EXISTING CONCRETE TYP.REMOVE EXISTING CONCRETE TYP.
REMOVE EXISTING CONCRETE TYP.
NOTE:
REMOVE AND TRANSPORT
ALL EXISTING CONCRETE TO
D.P.W. STORAGE AREA FOR
CRUSHING
BM #1 EL. 745.48'
TOP OF CASTING ON WET WELL SW
CORNER OF PARCEL
BM #2 EL. 741.01'
TOP OF CASTING ON MANHOLE BEHIND
CHLORINE BUILDING AT SE CORNER OF PARCEL
REMOVE 12" CMP TYP.
REMOVE ALL 18" CMP
REMOVE CONTROL
CHAMBER
REMOVE CONTROL
CHAMBER
REMOVE CONTROL
CHAMBER
REMOVE WOOD CATWALK
REMOVE WOOD CATWALK
REMOVE WOOD CATWALK
STRIP TOPSOIL FROM TOP
OF BERMS FOR ROADWAY.
WASTE ON NORTH AND
WEST SIDES OF EXTERIOR
BANKS TYPICAL.
STRIP ALL TOPSOIL WITHIN
LIMITS OF HMA SURFACE
FOR PUMP HOUSE
REMOVE CHAINLINK FENCE
ALONG WEST LINE OF PROPERTY
REMOVE 15" CMP
REMOVE 15" CMP
REMOVE SLUDGE FROM CELL NO. 1 REMOVE SLUDGE FROM CELL NO. 2 REMOVE SLUDGE FROM CELL NO. 3
STRIP TOPSOIL FROM TOP
OF BERMS FOR ROADWAY
WASTE TOPSOIL ON NORTH AND
WEST SIDES OF EXTERIOR
BANKS TYPICAL.
BACKFILL AND ABANDON
EXISTING PUMP STATION
REFER TO SHEET C06
FOR DETAILS.
STRIP TOPSOIL ON
TOP AND BANK OF
BERMS
REFER TO SHT. C03
TYP. ALL INTERIOR BERMS
STRIP TOPSOIL ON
TOP AND BANK OF
BERMS
REFER TO SHT. C03
STRIP TOPSOIL ON TOP AND
ON INTERIOR BANK OF BERMS
STRIP TOPSOIL ON
TOP AND ON
INTERIOR OF BERMS
PLUG EXISTING 8"
PIPE WITH CONCRETE
TYPICAL 3 LOCATIONS
SEE DETAIL "I" ON
SHEET C05
STRIP TOPSOIL
ON TOP AND ON
INTERIOR BANK
OF BERMS
STRIP TOPSOIL
ON TOP AND ON
INTERIOR BANK
OF BERMS
REMOVE 12" CMP TYP.
SEEPAGE CHAMBER
TO REMAIN
SEEPAGE CHAMBER
TO REMAIN
CHLORINE BUILDING
TO REMAIN
REMOVE 12" CMP TYP.
REMOVE 18" CMP
Know what's below.before you dig.Call
R
SEEPAGE CHAMBER
TO REMAIN
CELL CAPACITY
CELL 1 15,863,692 GAL
CELL 2 8,145,588 GAL
CELL 3 7,959,478 GAL
LIMITS OF HMA
LEGEND
REMOVE PIPE
REMOVE CONCRETE
PARSHALL FLUME
TO REMAIN
REMOVE & SALVAGE EXISTING VALVE.
CUT & PLUG EXISTING 8" FORCE MAIN W/
CONCRETE AFTER NEW 8" PVC FORCE MAIN IS
PLACED INTO SERVICE, EXACT DEPTH UNKNOWN,
CONTRACTOR TO FIELD VERIFY
REMOVE & SALVAGE EXISTING VALVE.
CUT & PLUG EXISTING 8" FORCE MAIN W/
CONCRETE AFTER NEW 8" PVC FORCE MAIN IS
PLACED INTO SERVICE, EXACT DEPTH UNKNOWN,
CONTRACTOR TO FIELD VERIFY
REMOVE & SALVAGE EXISTING VALVE.
CUT & PLUG EXISTING 8" FORCE MAIN W/
CONCRETE AFTER NEW 8" PVC FORCE MAIN IS
PLACED INTO SERVICE, EXACT DEPTH UNKNOWN,
CONTRACTOR TO FIELD VERIFY
REMOVE 33-LF OF 12" PIPE
E
C05
E
C05
E
C05
744.5
744.8
745.5
743.5
742.7
743.2
743.5
743.8
749.8
750.4
750.3
744.1
744.4
743.9
744.4
743.8
743.6
750.4
750.3
749.9
749.8
744.3
HV
5
74
4.0
1
H3
749.9
FIELD LINE
HV
6
74
5.4
8
7
4
5
7
4
5
750
745
7
4
5
745
745
7
5
0
750
750
744.8
744.3
744.4
743.4
743.2
744.8
744.2
744.3
744.0
744.3
744.8
750.3
749.9
750.1
749.8
748.8
749.4
743.6
749.6
749.6
750.4
749.5
749.8
749.9
749.2
749.4
744.5
744.2
750.5
749.7
749.9
750.1
750.0
749.4
749.7
749.7
750.4
750.3
749.9
750.2
745.1
744.7
744.1
743.5
744.1
742.4
744.6
743.2
742.4
744.5
743.9
743.3
742.1
741.4
741.2
740.8
740.5
740.9
741.7
742.0
743.6
741.5
742.5
742.3
741.3
741.5
741.6
742.1
742.1
742.4
742.9
741.4
742.3
741.5
ST
AN
DIN
G
WA
TE
R
745
745
74
5
7
4
5
750
750
7
5
0
745
75
0
750
750
75
0
74
5
745
745
740
740
740
745
742.9
FIE
LD
LIN
E
T
R
A
I
L
TRAIL
TR
AIL
TRAIL
TRAIL
TR
AIL
BR
US
H
0+00
1+00
2+00
3+00
4+00
5+00
6+00
7+00
8+00
9+00
10+00
11+00
12+00
13+00
14+00
15+00
0+
00
1+
00
1+
27
0+
00
1+
00
1+
27
0+
00
1+
00
1+
27
0+
00
1+
00
1+
26
0+00 1+00 2+00 3+00 4+00 5+00 6+00 7+00 8+00 9+00 10+00 11+00 12+00 13+00 14+00 15+00
735
740
745
750
755
735
740
745
750
755
0+00 1+00 2+00 3+00 4+00 5+00 6+00 7+00 8+00 9+00 10+00 11+00 12+00 13+00 14+00 15+00
F&V PROJECT NO.
DESIGN TEAM:
DRAWING INFORMATION:
CHECK BY:
REVISION:
CIT
Y O
F C
OL
EM
AN
MID
LA
ND
C
OU
NT
Y, M
IC
HIG
AN
SE
WA
GE
L
AG
OO
N/P
UM
P S
TA
TIO
N IM
PR
OV
EM
EN
TS
MAR 2018
834310
2125 Ridgewood Dr, Suite 101
P: 989.837.3280
F: 989.837.3290
Midland, MI 48642
DESIGN. BUILD. OPERATE.
3
AD
DE
ND
UM
N
O. 3
04/12/18
DJD
2
834310-Coleman ICE C02
050118 dand
SE
WA
GE
L
AG
OO
N R
EP
AIR
S
INITIALS
C02
NORTH
SEWAGE LAGOON PLAN
CELL NO. 1 CELL NO. 2 CELL NO. 3
PLACE MINIMUM 12" LAYER OF ARMOR STONE TYP.
APPROX. BOTTOM
GEOTEXTILE FABRIC TYP.
APPROX. WATER LEVEL
DATE: 3-8-15
PROPOSED ARMOR STONE
BANK PROTECTION OVER
GEOTEXTILE FABRIC
PROPOSED 12' WIDE
GRAVEL ACCESS ROAD.
STRIP ALL TOPSOIL
PRIOR TO PLACEMENT
OF GRANULAR BASE AND
AGGREGATE SURFACE TYP.
PROPOSED 1 ON 3.5
SIDE SLOPE TYP.
SEE CROSS SECTION BELOW
25' RADIUS TYP.
75' RADIUS
35' RADIUS TYP.
25' RADIUS TYP.
25' RADIUS TYP.
PROPOSED 12' WIDE
GRAVEL ROADWAY
PROPOSED 12' WIDE
GRAVEL ROADWAYPROPOSED 12' WIDE
GRAVEL ROADWAY
PROPOSED 12' WIDE
GRAVEL ROADWAY
TOE OF ARMOR STONE
APPROX. EDGE OF WATER
DATED: 3-8-15
CONSTRUCT NEW
PUMP STATION
REFER TO SHT C06
SEWAGE LAGOON PROFILE
COUNTY DRAIN
NOTE:
PLACE TOPSOIL THAT IS EXCAVATED
FROM ROAD AREA ALONG EXTERNAL
SLOPES AS DIRECTED BY THE
ENGINEER, SEED ALL DISTURBED
AREAS & PLACE MULCH BLANKETS
REFER TO SHEET C07 FOR PROPOSED
LAGOON PIPING, STRUCTURES, GATES,
AND ANCILLARY WORK
PROPOSED 1 ON 3.5
SIDE SLOPE TYP.
PROPOSED 1 ON 3.5
SIDE SLOPE TYP.
APPROXIMATE LIMITS
OF RESTORATION
SHOWN HATCHED
10
'
5'
5'
APPROXIMATE LIMITS
OF RESTORATION
SHOWN HATCHED
EXISTING SIDE SLOPE TYP.
SEE PIPE
PENETRATION
DETAIL SHT. C03
PROPOSED 1 ON 3.5
SIDE SLOPE TYP.
SEE PIPE
PENETRATION
DETAIL SHT. C03
SEE PIPE
PENETRATION
DETAIL SHT. C03
30-LF OF 12" PVC C900
OVERFLOW PIPE
SEE PIPE PENETRATION
DETAIL SHEET C03
RIP-RAP AT SLOPE
PROPOSED 12' WIDE
GRAVEL ACCESS ROAD.
STRIP ALL TOPSOIL
PRIOR TO PLACEMENT
OF GRANULAR BASE AND
AGGREGATE SURFACE TYP.
PROPOSED 12' WIDE
GRAVEL ACCESS ROAD.
STRIP ALL TOPSOIL
PRIOR TO PLACEMENT
OF GRANULAR BASE AND
AGGREGATE SURFACE TYP.
DETAIL
6-FT DIA MANHOLE
12" - 45° BEND
12" - 45° BEND
12" D.I. PIPE TYP.
SEE SHEET C11
F&V PROJECT NO.
DESIGN TEAM:
DRAWING INFORMATION:
CHECK BY:
REVISION:
CIT
Y O
F C
OL
EM
AN
MID
LA
ND
C
OU
NT
Y, M
IC
HIG
AN
SE
WA
GE
L
AG
OO
N/P
UM
P S
TA
TIO
N IM
PR
OV
EM
EN
TS
MAR 2018
834310
2125 Ridgewood Dr, Suite 101
P: 989.837.3280
F: 989.837.3290
Midland, MI 48642
DESIG
N. BU
ILD. O
PERATE.
3
AD
DE
ND
UM
N
O. 3
04/12/18
DJD
2
TYPICAL BERM CROSS SECTION
BETWEEN CELLS
TYPICAL BERM CROSS SECTION
OUTER CELL
834310-Coleman ICE C03
050118 dand
TY
PIC
AL
B
ER
M S
EC
TIO
N
GOB\DJD\DJD
C03
APPROX. BOTTOM OF LAGOON 740.8
MAXIMUM WATER 748.50
MINIMUM WATER ELEVATION 742.8
PROPOSED TOP OF BANK 750.50
APPROX. BOTTOM OF LAGOON 740.8
PROPOSED TOP OF BANK 750.50
MINIMUM WATER ELEVATION 742.80
EXISTING GRADE
TRANSPORT AND PLACE
CLAY EMBANKMENT FILL C.I.P.
RESHAPE AND CONSTRUCT
TO 1:3.5 SLOPES TYP.
ALL INTERIOR SLOPES
TRANSPORT AND PLACE
CLAY EMBANKMENT FILL C.I.P.
RESHAPE AND CONSTRUCT
TO 1:3.5 SLOPES TYP.
ALL INTERIOR SLOPES
9" THICK LAYER OF ARMOR
STONE ON GEOTEXTILE FABRIC
STRIP ALL TOPSOIL AND ORGANIC
MATERIAL WITHIN THE INFLUENCE
OF NEW ROADWAY, PLACE MIN. 6" OF
MDOT CLII GRANULAR MATERIAL
ON GEOTEXTILE FABRIC
MIN. 6" OF 23A CRUSHED LIMESTONE
OR 23A CRUSHED CONCRETE
TRANSPORT AND PLACE
CLAY EMBANKMENT FILL C.I.P.
RESHAPE AND CONSTRUCT
1:3.5 SLOPES TYP.
ALL INTERIOR SLOPES
EXISTING GRADE
GEOTEXTILE FABRIC
3.5
1
3.5
1
3.5
1
GEOTEXTILE FABRIC
STRIP ALL TOPSOIL AND ORGANIC
MATERIAL WITHIN THE INFLUENCE
OF NEW ROADWAY, PLACE MIN. 6" OF
MDOT CLII GRANULAR MATERIAL
ON GEOTEXTILE FABRIC
WASTE EXCAVATED TOPSOIL FROM
ROADWAY ON WEST AND NORTH
EXTERIOR EMBANKMENTS AS
DIRECTED BY THE ENGINEER
SEED AND PLACE MULCH BLANKETS
12'
12'
MIN. 6" OF 23A CRUSHED LIMESTONE
OR 23A CRUSHED CONCRETE
CLAY FILL CIP
CLAY FILL CIP
9" THICK LAYER OF ARMOR
STONE ON GEOTEXTILE FABRIC
2' TYP.
6" T
YP
.
PLACE CONCRETE TO
HAUNCH OF PIPE
4'-0"
PIPE PENETRATION DETAIL
SCALE: NOT TO SCALE
9" ARMOR STONE
PLACE 8 LF OF BAGGED BENTONITE
AT ALL PIPE PENETRATIONS
GEOTEXTILE FABRIC
8' MIN.
MAXIMUM WATER 748.50
MINIMUM WATER ELEVATION 742.8
F&V PROJECT NO.
DESIGN TEAM:
DRAWING INFORMATION:
CHECK BY:
REVISION:
CIT
Y O
F C
OL
EM
AN
MID
LA
ND
C
OU
NT
Y, M
IC
HIG
AN
SE
WA
GE
L
AG
OO
N/P
UM
P S
TA
TIO
N IM
PR
OV
EM
EN
TS
MAR 2018
834310
2125 Ridgewood Dr, Suite 101
P: 989.837.3280
F: 989.837.3290
Midland, MI 48642
DESIG
N. BU
ILD. O
PERATE.
3
AD
DE
ND
UM
N
O. 3
04/12/18
DJD
2
FILL AND GRADE SIDE
SLOPES PLACE GEOTEXTILE
FABRIC AND MIN. 12" OF ARMOR
STONE
PRIMARY CELL NO. 1
REMOVE EXISTING CONCRETE
REMOVE ALL SLIDE VALVES
IN PRIMARY CELL NO. 1
FILL AND GRADE SIDE
SLOPES PLACE GEOTEXTILE
FABRIC AND MIN. 9" OF ARMOR
STONE
FILL AND GRADE SIDE
SLOPES PLACE GEOTEXTILE
FABRIC AND MIN. 12" OF ARMOR
STONE
REMOVE ALL SLIDE GATES
IN PRIMARY CELL NO. 2
PRIMARY CELL NO. 2
REMOVE EX.CONCRETE
FILL AND GRADE SIDE
SLOPES PLACE GEOTEXTILE
FABRIC AND MIN. 12" OF ARMOR
STONE
FILL AND GRADE SIDE
SLOPES PLACE GEOTEXTILE
FABRIC AND MIN. 12" OF ARMOR
STONE
FILL AND GRADE SIDE
SLOPES PLACE GEOTEXTILE
FABRIC AND MIN. 12" OF ARMOR
STONE
PRIMARY CELL NO. 3
REMOVE EX.CONCRETE
PRIMARY CELL NO. 3
REMOVE EX.CONCRETE
FILL AND GRADE SIDE
SLOPES PLACE GEOTEXTILE
FABRIC AND MIN. 12" OF ARMOR
STONE
FILL AND GRADE SIDE
SLOPES PLACE GEOTEXTILE
FABRIC AND MIN. 12" OF ARMOR
STONE
834310-Coleman ICE C04
050118 douglass
PR
IM
AR
Y C
EL
L P
HO
TO
S
GOB/DRS/DJD
C04
PROPOSED
12' WIDE
ROADWAY
TYP. ALL BERMS
REMOVE OUTLET STRUCTURE
IN PRIMARY CELL NO. 1
REMOVE OUTLET STRUCTURE
IN PRIMARY CELL NO. 2
REMOVE OUTLET STRUCTURE
AND CATWALK IN PRIMARY CELL NO. 3
REMOVE EXISTING WOODEN
CATWALK
NOTE:
1. STRUCTURE PHOTOS ARE TYPICAL FOR
ALL 3 PRIMARY CELLS.
2. WOODEN CATWALK PHOTOS ARE TYPICAL
FOR ALL 3 PRIMARY CELLS.
REMOVE EXISTING
WET WELL TO 4-FT
BELOW GRADE
REMOVE EXISTING
WOOD STUD PUMP
BUILDING
REMOVE EXISTING
PUMP STATION TO
4-FT BELOW GRADE
REMOVE EXISTING
WOOD STUD PUMP
BUILDING
F&V PROJECT NO.
DESIGN TEAM:
DRAWING INFORMATION:
CHECK BY:
REVISION:
CIT
Y O
F C
OL
EM
AN
MID
LA
ND
C
OU
NT
Y, M
IC
HIG
AN
SE
WA
GE
L
AG
OO
N/P
UM
P S
TA
TIO
N IM
PR
OV
EM
EN
TS
MAR 2018
834310
2125 Ridgewood Dr, Suite 101
P: 989.837.3280
F: 989.837.3290
Midland, MI 48642
DESIGN. BUILD. OPERATE.
3
AD
DE
ND
UM
N
O. 3
04/12/18
DJD
2
834310-Coleman ICE C05
050118 dand
LA
GO
ON
D
ET
AIL
S
GOB/DRD/DJD
C05
EX. FENCE ROW
TO BE REMOVED
ALONG WEST SIDE
DRAINAGE DITCH
REMOVE EXISTING
8" VALVE AND BOX.
5' MIN. COVERLAGOON FLOOR
±250'
G DETAIL OF 8" INLET
D INTERIOR WATER LEVEL CONTROLS
REMOVE EXISTING VALVE
& BOX CONTROL AND
SALVAGE FOR THE CITY
E TYPICAL EXISTING OUTLET WATER LEVEL CONTROLS
REMOVE EXISTING WOODEN ACCESS
WALKWAY TYP. FOR 3 LOCATIONS
SEE SHEET C04
ELEV. 750.50
2'
TOP OF DIKE 750.50
LAGOON FLOOR
APPROX. 740.8
REMOVE AND DISPOSED OF
EXISTING 15" CMP AND METAL
ANTI-SEEP RINGS
BED AND BACKFILL
ENTIRE TRENCH FOR
NEW PIPE IN 100%
CLAY MATERIAL C.I.P.
A DETAIL SEEPAGE CELL OUTLET CHAMBER
A
SECTION A-A
EXISTING OUTLET
STRUCTURE TO REMAIN
INV. ELEV. ±740.2
FROM CONTROL CHAMBER
TO SEEPAGE CELL
REMOVE AND REPLACE EXISTING
18" CMP WITH NEW 18" D.I. PIPE IN
CENTER AND SOUTHERN
CHAMBERS ONLY
BED AND BACKFILL
NEW PIPE IN 100%
CLAY MATERIAL C.I.P.
REMOVE & DISPOSE OF
EXISTING 15" CMP AND
METAL ANTI-SEEP RINGS
2'
PLACE 15" MJ GATE
VALVE AND BOX
REMOVE EXISTING
12" CMP PIPE
EXISTING SEEPAGE
CHAMBER TO REMAIN. SEE
DETAIL "B" THIS SHEET
CUT & PLUG EXISTING 8" C.I. PIPE W/
CONCRETE AFTER NEW FORCE MAIN IS
ACCEPTED AND PLACED INTO SERVICE
REMOVE AND REPLACE
EXISTING 18" CMP
WITH NEW 18" D.I. PIPE
REMOVE EXISTING CMP
PIPE AND REPLACE WITH
NEW 12" C900 PVC PIPE
MATCH EXISTING
INVERT 742.80
EXISTING SLIDE GATES
TO REMAIN
REPLACE EXISTING
SLIDE GATES PER
SCHEDULE ON SHT. C09
TOP ELEV. ±745.4
5'
INV 748.50INV 748.50
PLACE
30 LF - 12" D.I. PIPE.
2 EA - VERMIN GUARD, TYPE "B"
PLACE IN SAME TRENCH AS 12"
TRANSFER PIPE.
REMOVE EXISTING CMP
PIPE AND REPLACE WITH
NEW 12" D.I. PIPE
REMOVE EXISTING CMP
PIPE AND REPLACE WITH
NEW 12" C900 PVC PIPE
REMOVE EXISTING CMP
PIPE AND REPLACE WITH
NEW 12" D.I. PIPE
NORTH
GROUT NEW PIPE INTO
EXISTING STRUCTURE WITH
NON-SHRINK GROUT (TYP.)
FILL EXISTING PIPE W/
FLOWABLE FILL - MIX NUMBER 2
F TYPICAL PROPOSED OUTLET WATER LEVEL CONTROLS
REMOVE EXISTING
CONTROL CHAMBER.
LAGOON BOTTOM
740.80±
PROPOSED CONTROL STRUCTURE
SEE DETAIL SHEET C11
PROPOSED 12" D.I. PIPE
EXISTING SEEPAGE
CHAMBER TO REMAIN. SEE
DETAIL "B" THIS SHEET
SEE SHEET C03 FOR
TYPICAL BERM SECTIONS
SEE SHEET C07 FOR
RIP RAP INFORMATION
H TYPICAL FORCEMAIN DISCHARGE INTO LAGOON DETAIL
H
PROPOSED 8" D.I. PIPE. BED
AND BACKFILL ENTIRE TRENCH
IN 100% CLAY, C.I.P.
8" 45° BEND
5' M
IN
CO
VE
R
8" GATE VALVE
AND BOX
8" TEE
PLACE:
60 LF - 12" D.I. PIPE
I TYPICAL EXIST FORCEMAIN PLUG
FILL EXISTING PIPE
WITH FLOWABLE FILL
MIX NUMBER 2
PLUG EXISTING
PIPE WITH GROUT
I
PLACE VERMIN GUARDS
BOTH ENDS
NORTH
1 SECTION - CONTROL STRUCTURE A
12" CELL NO.1
INFLUENT
PROP. GRADE
EL. 750.50
TOP OF STRUCTURE
EL. 752.00
PROPOSED 1 1/2" FRP GRATING.
SEE SHEET C11
INFLUENT FORCEMAIN
BOTTOM OF STRUCTURE
EL. 746.00
CONNECT TO NEW 8"
FORCEMAIN
SP-1
STOP PLATE SCHEDULE
DIM. "A"
CHANNEL WIDTH
(INCHES)
SP-2 24
TAG
SP-1 24
CONTROL STRUCTURE A - TO POND NO.2
CONTROL STRUCTURE A - TO POND NO.1
DIM. "B" FRAME
HEIGHT (INCHES)
12
DIM. "C" PLATE
HEIGHT (INCHES)
27
LOCATION
EMBEDDED EXTERNAL FRP
MOUNTING
EMBEDDED
HANDLE
EXTERNAL
MATERIAL
FRP
SLOPE GROUT TO
OUTFLOW PIPES
1
CAST IN PLACE
CONCRETE
STRUCTURE
GROUT FLOW CHANNEL
BOTTOM OF CONCRETE
EL. 749.25
NOTES
HANDLE HEIGHT = 30"
PROPOSED CONTROL STRUCTURE A
SCALE: 3/8" = 1'-0"
SP-2 SP-3
SP-2 24CONTROL STRUCTURE A - TO POND NO.3EMBEDDED EXTERNAL FRP
12" CELL NO.2
INFLUENT
12" CELL NO.3
INFLUENT
2'
1'-5"
2' 1'-6" 2'1'-6"6"
10'
11'-4"
12'-4"
12" PVC - POND NO.3
INFLUENT
INV. 12" 746.80
PROPOSED 12" D.I. PIPE TYP.
INV 12" 741.80
INV 12" 746.80
INV 12" ±740.40
PROPOSED 6-FT DIA
MANHOLE
CONTROL STRUCTURE
SEE DETAIL ON THIS SHEET
PROPOSED GRAVEL
ROADWAY
8" 90° BEND
1.9741
BOTTOM OF POND
TOP OF F.M. PIPE
EL. 749.50
TOP OF PIPE TO CELLS 1, 2, & 3
EL. 749.00
8"
2'-5"
10'
7'-4"
8'-4"
PROPOSED CONTROL STRUCTURE A - GRATING PLAN
SCALE: 3/8" = 1'-0"
1
PROPOSED 1
1
2
" FRP GRATING. PROVIDE
4 SEPARATE PIECES. PROVIDE CUTOUT
FOR STOP PLATES. COORDINATE WITH
STOP PLATE MANUFACTURER.
STOP PLATE
(TYP. OF 3)
INV. 12" 744.80
INV. 12" 742.80
INV 12" 744.80
INV 12" 742.80
1227
1227
HANDLE HEIGHT = 30"
HANDLE HEIGHT = 30"
6'
10'
17'
24'
CENTERLINE ROADWAY
PLACE:
1 - FLANGED 90° BEND
1 - FLANGED PE 45° BEND
PLACE:
1 - FLANGED 90° BEND
1 - FLANGED - PE 45° BEND
PROPOSED 8" PVC C900
PIPE. BED AND BACKFILL
ENTIRE TRENCH IN 100%
CLAY, C.I.P.
PLACE:
1 - FLANGED 90° BEND
1 - FLANGED 45° BEND
2 SECTION - CONTROL STRUCTURE A
2
INV. 743.50
2'-11" 2'-10" 2'-11"8" 8"
10'
12"
2'
12" CELL NO.1
INFLUENT
12" CELL NO. 2
INFLUENT
12" CELL NO. 3
INFLUENT
2'-11"
2'-11"
2'-11"
SLOPE GROUT TO
DRAIN TYP.
SP-1 SP-3SP-2
PROPOSED 1 1/2" FRP
GRATING
SEE DETAIL SHT. C11.
5'
#4 REBAR
12" O.C. EW, 2" CLR
#5 REBAR 12. O.C."
E.W. E.F. 3" CLR.
3" C
LR
2" CLR
GROUT FLOW CHANNEL
EXDTEND REBAR TO
OUTSIDE FACE, LAP
BARS 2'-2" TYPICAL
#5 REBAR 12" O.C. EW,
INSIDE FACE 2" CLR
6"
4" 6A CRUSHED
LIMESTONE
4" 6A CRUSHED
LIMESTONE
NOTE:
BACKFILL AROUND
STRUCTURES
WITH 100% CLAY C.I.P.
SEE SHEET C11 FOR
OPENING
REINFORCEMENT
PROPOSED 12" D.I. PIPE
7
4
5
745
40'
SCALE: NONE
BYPASS AND CLEANOUT DETAIL
WATER TIGHT MANHOLE CASTING
6" ALUMINUM MALE CAMLOCK FITTING WITH DUST CAP
8" GATE VALVE AND BOX
1 CYD PEASTONE
2'Ø ASTM C-478
PRECAST PIPE
ADJUSTMENT RINGS
(4 MAX)
FORCE MAIN TRACING WIRE
WRAP TAG END OF TRACER WIRE AROUND INTERIOR
OF STRUCTURE. PROVIDE 8' (MIN) OF EXTRA WIRE
NOTE:
ALL JOINTS SHALL BE
RESTRAINED MECHANICAL
JOINTS
BLEND TO MATCH EX. GRADE
PROVIDE 1 ON 12 SIDE SLOPE.
LIM
IT
S O
F F
OR
CE
M
AIN
LIMITS OF LUMP SUM
FOR BYPASS AND CLEANOUT
NEW 8" PVC FORCE MAIN
8"X8" LATERAL
8" 45° BEND
8" 45° BEND
8" SPOOL PIECE
8" D.I. PIPE
F&V PROJECT NO.
DESIGN TEAM:
DRAWING INFORMATION:
CHECK BY:
REVISION:
CIT
Y O
F C
OL
EM
AN
MID
LA
ND
C
OU
NT
Y, M
IC
HIG
AN
SE
WA
GE
L
AG
OO
N/P
UM
P S
TA
TIO
N IM
PR
OV
EM
EN
TS
MAR 2018
834310
2125 Ridgewood Dr, Suite 101
P: 989.837.3280
F: 989.837.3290
Midland, MI 48642
DESIG
N. BU
ILD. O
PERATE.
3
AD
DE
ND
UM
N
O. 3
04/12/18
DJD
2
NORTH
Know what's below.before you dig.Call
R
SE
RV
IC
E D
RIV
E
PROPOSED ARMOR STONE BANKS
1
2
'
REGRADE EXISTING ROADWAY
REMOVE ALL UNACCEPTABLE
ORGANIC MATERIAL, PLACE
12" OF MDOT GRANULAR MATERIAL,
6" OF 23A CRUSHED LIMESTONE
OR CRUSHED CONCRETE (CIP) AND
4" OF HMA SURFACE
REGRADE DITCH BANK
PLACE 6" 6A STONE
WITH GEOTEXTILE FABRIC
ON ALL DISTURBED
BANK AREAS.
REGRADE DITCH BANK
PLACE 6" 6A STONE
WITH GEOTEXTILE FABRIC
ON ALL DISTURBED
BANK AREAS.
CUT AND CAP EXISTING 8"
FORCE MAIN AFTER
NEW FORCE MAIN IS
PLACED IN SERVICE
PLACE 8" FORCE MAIN
(SEE SHT. C08)
CONSTRUCT NEW BLDG.
CONSTRUCT HMA PARKING AREA REMOVE ALL
UNACCEPTABLE ORGANIC MATERIAL, PLACE
12" OF MDOT GRANULAR MATERIAL AND 8" OF 22A
CRUSHED LIMESTONE (CIP) AND 3" OF HMA SURFACE
INSTALL NEW GENERATOR
AND CONCRETE PAD
REMOVE EXISTING CULVERT
PLACE FILL IN EXISTING SWALE
DITCH AREA, BLEND TO MATCH
AT EL. 745
REMOVE PANEL AND GENERATOR
SALVAGE FOR THE CITY AFTER NEW
PUMP STATION IS ACCEPTED AND
PLACED INTO SERVICE
EXTEND UNDERGROUND POWER
FROM EXISTING POWER POLE
INSTALL NEW 24' SLIDE
GATE CONNECT TO EX.
FENCE TO EAST
20'
20'
7
7
7
7
7
3
3
3
3
8
14
20
20
26
26
26
26
26
SPACING 6-10' MAX.
ROLL JOINT
SILT FENCE
FENCE POSTS DRIVEN
INTO GROUND 1' MIN.
SILT FENCE B
ROLL JOINTS
FABRIC TO BE WRAPPED
AROUND FENCE POST
GEOTEXTILE FILTER
FABRIC FASTENED ON
UPHILL SIDE, TOWARDS
EARTH DISRUPTION
1' MIN.
6"x6" ANCHOR TRENCH
RIDGE OF COMPACTED
EARTH ON UPHILL SIDE
OF FILTER FABRIC
UNDISTURBED
VEGETATION
6" ANCHOR TRENCH
SILT FENCE A
1' M
IN
.
SOIL EROSION & SEDIMENTATION CONTROL
MEASURES
KEY DETAIL
1 TURBIDITY CURTAIN
2 GRUBBING OMITTED
3 PERMANENT /TEMPORARY SEEDING
4 DUST CONTROL
5 SODDING
6 VEGETATED BUFFER STRIPS
7 RIPRAP
8 AGGREGATE COVER
9 BENCHES
10 DIVERSION DIKE
11 INTERCEPTING DITCH
12 INTERCEPTING DITCH AND DIVERSION DIKE
13 GRAVEL FILTER BERM
14 GRAVEL ACCESS APPROACH
15 SLOPE DRAIN SURFACE
16TREES, SHRUBS AND PERENNIALS
17 PIPE DROP
18 DEWATERING WITH FILTER BAG
19 ENERGY DISSIPATERS
20 SEDIMENT TRAP
21 VEGETATIVE BUFFER
22 VEGETATIVE BUFFER AND WATERCOURSE
23 STREAM RELOCATION
24 SAND AND STONE BAGS
25 SAND FENCE AND DUNE STABILIZATION
26 SILT FENCE
27 PLASTIC SHEETS OR GEOTEXTILE COVER
28 MULCHING AND MULCH ANCHORING
29 INLET PROTECTION FABRIC DROP
30 INLET PROTECTION GEOTEXTILE AND STONE
31 INLET PROTECTION SEDIMENT TRAP
32 SLOPE ROUGHENING AND SCARIFICATION
33
MULCH BLANKETS AND HIGH VELOCITY
MULCH BLANKETS
34 COFFERDAM
35 TEMPORARY BYPASS CHANNEL
36 CONSTRUCTION DAM
37 CHECK DAM
67
-L
F O
F 1
5"
PV
C @
1
.0
%
PLACE 4' DIA MH #1A
RIM 745.50
INV 732.28 (15" N)
INV 732.38 (15" SE)
REMOVE AND SALVAGE FOR THE
CITY ALL PUMP CONTENTS AFTER
NEW PUMP STATION IS ACCEPTED
AND PLACED INTO OPERATION
834310-Coleman ICE C06
050118 dand
PU
MP
S
TA
TIO
N S
IT
E P
LA
N
GOB/DJD2/DJD2
C06
PLACE NEW FENCE
40' WEST OF EXISTING
CHAINLINK FENCE
REMOVE OLD FENCE AFTER
NEW FENCE IS INSTALLED
REMOVE
EXTEND EXISTING 48" CMP
CULVERT 20-FT TO WEST
INV. 738.90 (48" W)
PROPOSED BIORETENTION POND
SEE DETAIL SHT. C08
ADD 6" OF 23A CRUSHED LIMESTONE
OR 23A CRUSHED CONCRETE SURFACE
12' WIDE AND 2000' LONG
TO EXISTING ACCESS ROADWAY
26
ABANDON EX. WET WELL &
PUMP STATION SEE
REMOVAL PLAN THIS SHT
18'
4
5
-
L
F
O
F
1
2
"
P
V
C
@
4
.
4
%
PLACE 12" FES #1
INV 740.00 (12" NE)
PLACE 2' DIA CB #1
W/ EJ GR6124 GRATE
RIM 743.50
INV 741.90 (12" SW)
INV 739.90 (10" E)
MIN. 12" SUMP
±75'
NEW 75' EASEMENT
REMOVE
EXISTING
FENCE
26
38'
PROPOSED WET
WELL
PROPOSED VALVE
CHAMBER
NOTE:
COORDINATE LOCATION OF PROPANE
TANK FOR SUPPLY TO GENERATOR,
WITH LOCAL MUNICIPALITY
MH#1A, WET WELL, VALVE CHAMBER
AND NEW CONTROL STRUCTURES
TO ALL HAVE CORROSION INHIBITING
ADD MIXTURE.(SEE PROJECT SPEC.)
PROPOSED
METER MH
SEE SHT. P01
2
2
-
L
F
O
F
1
5
"
P
V
C
@
1
.
0
%
INV. 732.60 (15" NW)
TEMPORARILY
PLUG NEW PIPE
INV 732.50 NEW (10" S)
TEMPORARILY PLUG NEW PIPE
46-LF
O
F 10"
PV
C @
1.0%
PLACE 20-LF OF 8"
SCH-35 PVC CULVERT
INV. 741.50 (8" N)
INV. 741.20 (8" S)
BLEND SIDE SLOPE INTO
EXISTING CULVERT PLACE
GEOTEXTILE AND STONE
RIP-RAP AT END OF PIPE
NEW 8" FORCE MAIN
NOTE:
PLACE MINIMUM 4" OF TOPSOIL,
& SEED ALL DISTURBED AREAS
22
'
CONSTRUCT CAMLOCK
BYPASS CLEAN OUT
SEE DETAILS THIS SHEET
AND SHT. P01
INV. 10" 732.04
INV. 15" 731.61
PROTECT EX.
SAN. SWR.
PLACE 2 - 4" ELEC. CONDUIT
UNDER HMA SURFACE
TO BUILDING
6-LF OF 10" PERF PIPE
22
'
EXTEND EXISTING 8"STORM SEWER TO END
OF 48" PIPE REROUTE EX. 8" PIPE IF ENCOUNTERED
CONSTRUCT 4' WIDE X 6" THICK
CONCRETE SIDEWALK
PLACE 30-LF OF
10" HDPE PIPE
INV 738.0 (10" NE)
PLACE RIP-RAP SPILLWAY
PUMP STATION REMOVL PLAN
NO SCALE
REMOVE EXISTING BUILDING
REMOVE WET WELL TO 4' BELOW
EXISTING GRADE BACKFILL WITH 100%
MDOT CLII GRANULAR MATERIAL C.I.P.
REMOVE PUMP CHAMBER
TO 4' BELOW EXISTING GRADE
BACKFILL WITH 100% MDOT
CLII GRANULAR MATERIAL C.I.P.
REMOVE EXISTING CONCRETE
PLUG EXISTING 10" AND 15"
SANITARY SEWER INSIDE OF WET
WELL WITH CONCRETE AFTER
NEW PUMP STATION IS
OPERATIONAL
10'
15
'
CONSTRUCT 10'X15'X8"
CONCRETE PAD REINFORCED
WITH 6X6 / W2.9XW2.9 WWF
OVER REMOVED PUMP STATION
APPROX. 3' BELOW GRADE
PLACE MDOT CLII GRANULAR MATERIAL
OVER CONCRETE BACKFILL UP TO
AGGREGATE BASE.
LIMITS OF
FORCE MAIN
LIMITS OF
CLEANOUT
CAST IN PLACE
500 GALLON
PROPANE TANK
PAD 5'X10'X7" W/
6X6 / W2.9X2.9
WWF
26
26
26
14'
NEW GAS LINE TO
GENERATOR
(ABANDON)
(ABANDON)
PLACE 4" PVC
CONDUIT
74
4.2
74
4.1
74
4.5
74
4.8
74
5.5
74
5.4
74
4.7
74
3.5
74
3.4
74
3.5
74
3.5
74
2.7
74
3.6
74
3.8
74
3.2
74
3.5
74
3.6
74
3.8
74
9.8
75
0.4
75
0.3
74
4.1
74
4.4
74
4.3
74
3.9
74
4.1
74
4.6
74
3.7
74
4.4
74
3.8
74
3.5
74
3.8
74
3.4
74
3.6
75
0.4
75
0.3
74
9.9
74
9.8
74
4.3
74
4.3
75
0.5
HV
5
74
4.0
1
V2
74
8.3
2
H3
74
9.9
FIELD LINE
HV
6
74
5.4
8
7
4
5
7
4
5750
745
7
4
5745
745
7
5
0
750
750
745
74
4.8
74
4.3
74
4.4
74
3.4
74
3.2
74
4.8
74
4.2
74
4.3
74
4.0
74
4.3
74
4.8
75
0.3
74
9.9
75
0.1
74
9.8
74
8.8
74
9.4
74
3.6
74
9.6
74
9.6
75
0.4
74
9.5
74
9.8
74
9.9
74
9.2
74
9.4
74
4.5
74
4.2
75
0.5
74
9.7
74
9.9
75
0.1
75
0.0
74
9.4
74
9.7
74
9.7
75
0.4
75
0.3
74
9.9
75
0.2
74
5.1
74
4.7
74
4.1
74
3.5
74
4.1
74
2.4
74
5.6
74
4.6
74
3.2
74
2.4
74
4.5
74
3.9
74
3.3
74
2.1
74
1.4
74
1.2
74
0.8
74
0.5
74
0.6
74
0.9
74
0.8
74
1.3
74
1.5
74
1.5
74
1.7
74
2.0
74
3.6
74
1.9
74
1.5
74
1.9
74
4.6
74
2.5
74
2.3
74
1.3
74
1.3
74
1.5
74
1.1
74
1.6
74
1.4
74
2.1
74
2.1
74
1.5
74
5.3
74
2.4
74
2.9
74
1.4
74
1.1
74
1.7
74
1.2
74
2.3
74
1.3
74
1.5
74
1.3
ST
AN
DIN
G
WA
TE
R
HV
1
74
6.2
6
745
745
745
7
4
5
750
750
7
5
0
745
750
750
750
750
745
745
745
740
740
740
740
745
745
74
2.9
FIE
LD
L
IN
E
FIE
LD
L
IN
E
T
R
A
I
L
TRAIL
TR
AIL
TRAIL
TRAIL
TR
AIL
BR
US
H
NORTH
CELL NO. 1 CELL NO. 2 CELL NO. 3
834310-Coleman ICE C07
050218 dand
PU
MP
S
TA
TIO
N S
IT
E U
TIL
IT
Y P
LA
N
GOB/DJD/DJD
C07
SECONDARY SEEPAGE CELLSECONDARY SEEPAGE CELL
SECONDARY SEEPAGE CELL
F&V PROJECT NO.
DESIGN TEAM:
DRAWING INFORMATION:
CHECK BY:
REVISION:
CIT
Y O
F C
OL
EM
AN
MID
LA
ND
C
OU
NT
Y, M
IC
HIG
AN
SE
WA
GE
L
AG
OO
N/P
UM
P S
TA
TIO
N IM
PR
OV
EM
EN
TS
MAR 2018
834310
2125 Ridgewood Dr, Suite 101
P: 989.837.3280
F: 989.837.3290
Midland, MI 48642
DESIGN. BUILD. OPERATE.
3
AD
DE
ND
UM
N
O. 3
04/12/18
DJD
2
CONNECT NEW 8" F.M. TO NEW PUMP
STATION AFTER NEW 8" FORCE
MAIN IS ACCEPTED
PLACE 370-LF OF NEW
18" ADS N-12 DUAL WALL PIPE
PLACE 23-LF OF NEW
18" ADS N-12 DUAL WALL PIPE
PLACE 320-LF OF NEW
18" ADS N-12 DUAL WALL PIPE
PLACE 38-LF OF NEW
12" D.I. PIPE OPEN CUT
PLACE 324-LF OF NEW
18" ADS N-12 DUAL WALL PIPE
CHLORINE CONTACT
TANK TO REMAIN
ABANDON EXISTING 8"
FORCE MAIN AFTER NEW
8" PVC FORCE MAIN
IS PLACED INTO SERVICE
CONSTRUCT NEW CONTROL
STRUCTURE "D" INSTALL 4 NEW
GATES VALVES IN CONTROL
CHAMBER
SEE SHEET C09 & C011
PLACE 60-LF OF 12" D.I. PIPE
INSTALL NEW GATE VALVE
INV. 742.80 (12" W)
INV. 742.80 (12" E)
CONSTRUCT NEW SPILLWAY
KEY IN FILTER FABRIC
AND PLACE 8'X10'X12" OF
STONE RIP-RAP
PARSHALL FLUME
TO REMAIN, CONNECT
TO NEW PIPE
NOTE:
ALL PIPING PENETRATIONS IN
BERMS TO BE BEDDED IN AND
BACKFILLED WITH 100% CLAY
COMPACTED IN PLACE.
Know what's below.before you dig.Call
R
PLACE:
2 EA - 12" 45° BENDS
PLACE 590 LF - 8" PVC FORCE MAIN
SEE SITE PLAN
SHEET C06
PLACE 1400-LF OF 6' HIGH
CHAINLINK FENCE LOCATED
40' WEST OF EXISTING FENCE
REMOVE EXISTING FENCE
ALONG WEST LINE OF PROPERTY
AFTER NEW FENCE IS INSTALLED
BIORETENTION POND
SEE DTL. SHT C08
40
'
15
'
15
'
PLACE NEW 8" PVC FORCE MAIN
MIN. 15' FROM POWER POLES
PROTECT POWER POLES
NEW 6' CHAINLINK FENCE
CONSTRUCT NEW CONTROL
STRUCTURE "B" INSTALL 4 NEW
GATE VALVES IN CONTROL
CHAMBER
SEE SHEET C09 & C11
PLACE 60-LF OF 12" D.I. PIPE
INSTALL NEW GATE VALVE
INV 742.80 (12" W)
INV. 742.80 (12" E)
EXISTING 8"
TO BE ABANDONED
EXISTING 8"
TO BE ABANDONED TYP.
SEE SHEET C05
EXPOSE EXISTING 8"
FORCE MAIN
EXPOSE EXISTING 8"
FORCE MAIN
INSTALL 25-LF OF 12" D.I. PIPE
INV. 748.50 E
INV. 748.50 W
INSTALL 25-LF OF 12"
D.I.
INV. 748.50 (12" E)
INV. 748.50 (12"W)
20
'
10'
10'X20'X12"
RIP RAP SPILLWAY
TYP. 4 LOCATIONS
G
C05
F
C05
F
C05
F
C05
D
C05
D
C05
PLACE:
188 LF - 12" D.I. PIPE,
OPEN CUTPLACE:
490 LF - 12" D.I.PIPE, OPEN CUT
CONSTRUCT NEW CONTROL
STRUCTURE "F" INSTALL 4 NEW
GATE VALVES
SEE SHEET C09 & C11
PLACE 38-LF OF NEW
12" D.I. PIPE
(OPEN CUT)
PLACE 38-LF OF NEW
12" D.I. PIPE
(OPEN CUT)
PLACE:
182 LF - 12" D.I. PIPE,
OPEN CUT
PLACE:
430 LF - 12" D.I. PIPE
(OPEN CUT)
PLACE:
1 - 8" LATERAL
1 - 8" CLEANOUT
1 - 8" GATE VALVE
CONSTRUCT NEW CONTROL
STRUCTURE "A" SEE SHEET
C05
PLACE:
3 - LENGTHS OF 12" D.I. PIPE
2 - 45° BENDS
SEE DETAIL SHEET C05
PLACE:
3 - LENGTHS OF 12" D.I. PIPE
2 - 45° BENDS
SEE DETAIL SHEET C05
PLACE:
3 - LENGTHS OF 12" D.I. PIPE
2 - 45° BENDS
SEE DETAIL SHEET C05
PLACE 30-LF OF 12" D.I.
OVERFLOW PIPE
INV. 748.50 (12" W)
INV. 748.50 (12" E )
PLACE:
33-LF OF 12" D.I. PIPE
1 - EA 12" GATE VALVE & BOX
PLACE:
15-LF OF 12" D.I. PIPE
(TYP. FOR 3)
24
9
8
26
26
26
26
26
26
26
26
26
26
26
PLACE 12' WIDE TEMPORARY HAUL ROAD.
STRIP TOPSOIL, PLACE MIRIFI 600X FABRIC
UNDER 6" OF CRUSHED CONCRETE. REMOVE
WHEN NO LONGER NEEDED AND RESTORE
TO EXISTING CONDITION.
PLACE:
2 EA - 12" 45° BENDS
PLACE:
2 EA - 12"
45° BENDS
100' (TYP)
7
4
5
743.4
7
4
5
743.6
F&V PROJECT NO.
DESIGN TEAM:
DRAWING INFORMATION:
CHECK BY:
REVISION:
CIT
Y O
F C
OL
EM
AN
MID
LA
ND
C
OU
NT
Y, M
IC
HIG
AN
SE
WA
GE
L
AG
OO
N/P
UM
P S
TA
TIO
N IM
PR
OV
EM
EN
TS
MAR 2018
834310
2125 Ridgewood Dr, Suite 101
P: 989.837.3280
F: 989.837.3290
Midland, MI 48642
DESIG
N. BU
ILD. O
PERATE.
3
AD
DE
ND
UM
N
O. 3
04/12/18
DJD
2
NORTH
Know what's below.before you dig.Call
R
S
E
R
V
IC
E
D
R
IV
E
834310-Coleman ICE C08
050118 dand
PU
MP
S
TA
TIO
N S
IT
E G
RA
DIN
G P
LA
N
GOB/DJD2/DJD2
C08
TOP OF WET WELL 745.70
RIM 745.80
PUMP HOUSE
F.F. 745.80
TW 745.70
TB 745.30
TB 745.50
TB 745.50
TB 746.50
TG 744.90
TOP OF FILL AREA 745.00
TOP OF VALVE
CHAMBER
745.60
TB 749.30
LEGEND
TG TOP OF GRAVEL
TB TOP OF BITUMINOUS
TW TOP OF WALK
TP TOP OF RET. POND
BP BOTTOM OF RET. POND
BS BOTTOM OF SWALE
TG TOP OF GROUND
TB 746.00
TB 747.20
TB 744.50
RIM 743.50
MATCH EX.
MATCH EX.
MATCH EX.
TB 745.00
TB 745.00
TB 744.60
TB 744.80
BIORETENTION AREA
SEE SCHEMATIC THIS SHEET
BIORETENTION AREA
MAX WATER DEPTH = 18"
MAINTAIN ORIGINAL DRAINAGE PATTERN
1 ON 4 SLOPE
TB 745.50
TB 745.30
TB 745.45
TB 745.30
TB 754.30
TB 745.30
TB 745.20
1 ON 3 SLOPE TYP.
1 ON 3 SLOPE TYP.
BIORETENTION SCHEMATIC
SEE SHEET C06 FOR LIMITS OF BIORETENTION POND
MATCH EX.
±741.0
1 ON 3 SLOPE TYP.
BP 742.00TP 745.00
TW 745.70
TB 745.70
TB 745.40
TB 745.55
2-FT STONE BOTTOM SWALE
PROVIDE POSITIVE DRAINAGE
TO BIORETENTION POND
SEE DETAIL THIS SHEET
TB 745.80
TP 745.00
TP 745.00
TP 745.00
TP 745.00
TP 745.00
BS 745.00
BS 745.10
TB 745.45
TB 745.30
TB 745.30
TB 744.60
TB 745.60
TB 745.60
TB 750.00
TB 748.60
TB 747.90
TB 745.50
TB 744.90
TB 750.00
TB 750.00
RIM 744.80
ADJUST
RIM 744.80
RIM METER
PIT 745.50
TW 745.70
TB 745.00
ADJUST
RIM 744.50
BLEND TO MATCH
EXISTING GRADE
BLEND TO MATCH
EXISTING GRADE
BLEND TO MATCH
EXISTING GRADE
PLACE FILTER FABRIC AND
12" OF 9"-12" STONE RIP
RAMP ON NEW SLOPES
CONSTRUCT STONE SWALE
STRIP TOPSOIL
GROTEXTILE FABRIC
4" MDOT 34R DRAIN STONE
PROVIDE POSITIVE DRAINAGE
TO BIORETENTION PAND
PLACE 4" OF TOPSOIL
AND SEED ALL DISTURBED
AREAS
STONE SWALE DETAIL
TG 745.00
TG 745.00
TP 745.00
TB 750.50
1 ON 6 SLOPE TYP.
1 ON 6 SLOPE TYP.
REMOVE
12
"
MIN
.
12
"
MAX. PONDED WATER
DEPTH (6-18")
LEAF COMPOST OR
SHREDDED HARDWOOD
POSITIVE OVERFLOW SYSTEM
12" MIN. SUMP
6-LF OF 10" PERF. PIPE
WITH SOCK
12" OF UNIFORMLY GRADED
CLEAN WASHED MDOT CLII SAND
12"MDOT CLII
STORAGE BED
12" OF ON SITE
ACCEPTABLE TOPSOIL
MAX 3:1 SIDE
SLOPES TYP.
NON-WOVEN
GEOTEXTILE FABRIC.
2-FT DIAMETER
CATCH BASIN
BIORETENTION POND PLANTINGS
GRASSES & WILDFLOWERS
OUTER ZONE
90 MAPLE LEAF VIBURNUM
SMALL TREES
MIDDLE ZONE
30 SWITCHGRASS
LOWEST ZONE
15 RIVER BIRCH
LARGE TREES
REQUIRED PLANTING FOR BIORETENTION POND
BIORETENTION AREA = 1,500-SF
LOWEST ZONE
1500
100
= 15 LARGE TREES PER 100 SFT
MIDDLE ZONE
1500
100
X2 = 30 SMALL TREES PER 100 SFT
OUTER ZONE
1500
100
X6 = 90 GRASSES PER 100 SFT
13
'
22'
MAX LIMITS OF
PONDED WATER
O
U
T
E
R
Z
O
N
E
M
I
D
D
L
E
Z
O
N
E
L
O
W
E
S
T
Z
O
N
E
BS 745.20
TW 745.70
TW 745.70
TW 745.70
TW 745.70
RIM CLEAN
OUT 745.50
PROPOSED 8"
FORCE MAIN
BS 745.20
GENERAL NOTES
4"
6"
6"
NO SCALE
STORM SEWER & DRAIN
TRENCH DETAIL
BEDDING: M.D.O.T. CLASS IIGRANULAR MATERIALCOMPACTED TO AT LEAST95% OF MAX. DENSITY.
PIPE SIZE AND CLASS PERPLAN OR SPECIFICATIONS
100% MDOT CLII GRANULARMATERIAL BACKFILL
COMPACTED TO AT LEASAT95% OF MAX. DENSITY
1. ALL SURPLUS FILL MATERIAL AND TOPSOIL NOT USED ON SITE WILL BE REMOVED OFF SITE BY THE CONTRACTOR
2. CONTRACTOR TO OBTAIN ALL REQUIRED PERMITS FROM CITY OF COLEMAN, THE MIDLAND COUNTY DRAIN COMMISSIONER & SOIL EROSION AND SEDIMENTATION CONTROL PRIOR TO THE START OF CONSTRUCTION.
3. THE EXISTING UTILITIES SHOWN ON THE DRAWINGS ARE APPROXIMATE LOCATIONS. THE CONTRACTOR SHOULD CONTACT THE APPROPRIATE UTILITY COMPANY FOR THE EXACT LOCATION AND DEPTH OF EACH UTILITY.
4. THE CONTRACTOR SHALL ASSUME RESPONSIBILITY FOR PROTECTIONOF ALL EXISTING UTILITIES DURING CONSTRUCTION. ALL COSTSFOR LOCATING, PROTECTING, REMOVING, REPLACING, OR RELOCATING THESE UTILITIES SHALL BE INCIDENTAL TO CONSTRUCTION. ALL UTILITIES DAMAGED DURING CONSTRUCTIONSHALL BE REPAIRED WITH LIKE MATERIAL AT NO ADDITIONAL COST TOTHE OWNER.
5. CONTRACTOR SHALL VERIFY THE DEPTH AND HORIZONTAL LOCATIONOF ALL EXISTING UTILITIES BEFORE ANY WORK IS STARTED. THE EXACT LOCATION OF EXISTING UTILITIES SHALL BE DETERMINED BYHAND DIGGING.
6. CONTRACTOR SHALL NOTIFY PROPER GOVERNMENTAL INSPECTION AGENCY48 HOURS PRIOR TO STARTING CONSTRUCTION.
7. COMPACTED SAND BACKFILL M.D.O.T CLASS II LIMITED TO 1" MAXIMUM SIZE ORAPPROVED EQUAL IS TO BE USED EXCLUSIVELY IN ALL UTILITY TRENCHES ANDUNDER ALL PAVED AREAS THROUGHOUT THE COURSE OF THE PROJECT UNLESSOTHERWISE SPECIFIED AND COMPACTED TO 95% OF ITS MAXIMUM UNIT WEIGHTAS DETERMINED BY ASTM D 1557-78.
8. THE CONTRACTOR SHALL ABIDE BY ALL REQUIREMENTS OF THEMICHIGAN DEPARTMENT OF TRANSPORTATION REGARDING CONSTRUCTION, MAINTAINING TRAFFIC, BARRICADING, BORING,BACKFILL AND RESTORATION. THERE WILL BE NO ADDITIONALCOMPENSATION DUE THE CONTRACTOR FOR COMPLYING WITH THESE REQUIREMENTS.
9. THE CONTRACTOR SHALL BE REQUIRED TO COMPLETE ALL WORK INAN EXPEDITIOUS MANNER AND SHALL NOT STOP CONSTRUCTIONFOR EXTENDED PERIODS ONCE CONSTRUCTION HAS BEGUN.
10. THE CONTRACTOR SHALL FURNISH THE ENGINEER ONE COMPLETE SET OF"AS-BUILT" PLANS UPON COMPLETION OF THE PROJECT.
11. THE CONTRACTOR SHALL MAINTAIN IN SERVICE, ALL EXISTING SANITARY SEWER, WATER AND STORM SEWER SERVICE CONNECTIONS.
D
D
GRANULAR BACKFILL
COMPACTED
GRANULAR BACKFILL
COMPACTED
SHAPE FOR BARREL
OF PIPE
12"
12"
4" M
IN
D
12"
3" M
IN
METHOD I METHOD II
EXCAVATION FOR BELLS
DIRECTION OF FLOW
NOTES: 1. METHOD I: IN AREAS OF
UNCONSOLIDATED SOILS (SAND,
GRAVEL, ETC.) 2. METHOD II: IN
AREAS OF CONSOLIDATED SOILS
(CLAY, HARDPAN, ROCK, ETC.) 3.
METHOD III: IN AREAS INDICATED
ON DRAWINGS
APPROVED BACKFILL PLACED AND
COMPACTED A MINIMUM OF 24 HOURS
AFTER PLACING CONCRETE
METHODS OF BEDDING GRAVITY PIPE
3000 PSI
CONCRETE
CRADLE
CEMENT BLOCK OR
BRICK TO PRESERVE
LINE AND GRADE.
METHOD III
D/4
BOLTED & GASKETED
WATERPROOF CASTING
& COVER
SET CASTING
IN MASTIC
NEOPRENE COMPRESSION
NOTE:
REQUIRED IN LOCATIONS INDICATED ON DRAWING
WATER TIGHT MANHOLE COVER
FINISHED GRADE
RING (TYP.)
PRECAST CONCRETE ADJUSTING
RINGS WITH O-RINGS, OR HDPE
GRADE RINGS WITH BUTYL
SEALANT
MANHOLE CONE
4 EA. - 5/8" STAINLESS
ANCHOR BOLTS
5/8" THREADED
INSERT
METHODS OF BEDDING PRESSURE PIPE
EXCAVATION FOR BELLS
METHOD I METHOD II
GRANULAR BACKFILL
COMPACTED
GRANULAR BACKFILL
COMPACTED
BELL HOLE EXCAVATIONS
REQUIRED FOR METHODS I & II
SHAPE FOR BARREL
OF PIPE
NOTES:
1. METHOD I: IN AREAS OF UNCONSOLIDATED SOILS
(SAND, GRAVEL, ETC.)
2. METHOD II: IN AREAS OF CONSOLIDATED SOILS
(CLAY, HARDPAN, ROCK, ETC.)
12"
D
D
12"
3" M
IN
4" CONCRETE SIDEWALK
NOTES:
1.
1
2
" EXPANSION JOINTS SHALL BE MAXIMUM OF 50' ON
CENTER
2.
1
2
" EXPANSION JOINT MATERIAL SHALL BE PLACED
BETWEEN SIDEWALK AND RIGID STRUCTURES.
3. INSOFAR AS POSSIBLE, SIDEWALK SHALL BE DIVIDED INTO
SQUARE UNIT AREAS BY MEANS OF CUT CONTROL
JOINTS NOT MORE THAN 36 SFT OR LESS THAN 16 SFT.
1/4" RADIUS
TYP.
MIN OF 4" GRANULAR
MATERIAL
2% SLOPE
WALK WIDTH AS
SPECIFIED ON DRAWINGS
6" OF MDOT 22A CRUSHED
LIMESTONE OR CRUSHED
CONCRETE C.I.P.
220#/SYD MDOT 4C HMA
12" MIN. MDOT CLII
GRANULAR MTL. C.I.P.
NOT TO SCALE
PAVEMENT SECTION
TYPICAL HMA
220#/SYD MDOT 3C HMA
NO SCALE
ROADWAY AROUND LAGOONS
CROSS SECTION
6" OF MDOT 23A 100%CRUSHED LIMESTONE ORCRUSHED CONCRETE C.I.P.
12" MIN. MDOT CLIIGRANULAR MTL. C.I.P.
F&V PROJECT NO.
DESIGN TEAM:
DRAWING INFORMATION:
CHECK BY:
REVISION:
CIT
Y O
F C
OL
EM
AN
MID
LA
ND
C
OU
NT
Y, M
IC
HIG
AN
SE
WA
GE
L
AG
OO
N/P
UM
P S
TA
TIO
N IM
PR
OV
EM
EN
TS
MAR 2018
834310
2125 Ridgewood Dr, Suite 101
P: 989.837.3280
F: 989.837.3290
Midland, MI 48642
DESIG
N. BU
ILD. O
PERATE.
3
AD
DE
ND
UM
N
O. 3
04/12/18
DJD
2
834310-Coleman ICE C09
050118 dand
ST
AN
DA
RD
D
ET
AIL
S
GOB\DRS\DJD2
C09
TAG
SG-1
SLIDE GATE SCHEDULE
WIDTH (DIA)
HEIGHT
INVERT TO
OPERATING
FLOOR
SEATING
HEAD
UNSEATING
HEAD
5.0'
4.8'12"
RAIL & STEM
MATERIAL
LOCATIONFRAME
MOUNTING
FRAME
OPENING
DIRECTION
STEM SERVICE
FREQUENCY
OF OPERATION
304 SS CS-CSM S UPWARD MANUAL
RS
KEY:
EP = END OF PIPE
EC = END OF CHANNEL
IC = IN CHANNEL
SM = SURFACE MOUNTED
EM = EMBEDDED
S = SELF CONTAINED
NSC = NOT SELF CONTAINED
RS = RISING STEM
NRS = NON RISING STEM
304 SS = 304 STAINLESS STEEL
316 SS = 316 STAINLESS STEEL
ALUM = ALUMINUM
OPEN/CLOSE
ACTUATOR
TYPE MOUNTING
SIZE OF GATE
SG-2
18"
304 SS CS-CSM UPWARD MANUAL
RS OPEN/CLOSE
SG-3
SG-4
SG-5
SG-6
CS-E
CS-E
CS-G
CS-G
SM
SM
SM
SM
UPWARD
UPWARD
304 SS
304 SS
304 SS
304 SS
MANUAL
MANUAL
MANUAL
MANUAL
RS
RS
RS
RSOPEN/CLOSE
OPEN/CLOSE
OPEN/CLOSE
OPEN/CLOSE
HANDWHEEL
OPERATOR
12"
18"
12"
18"-
4.9'
4.8'
4.9'
4.8'
4.9'
CS-X = CONTROL STRUCTURE NUMBER
S-X = SLIDE GATE NUMBER
3.0'
-
-
-
-
-
5.0'
5.0'
5.0'
5.0'
5.0'
3.0'
3.0'
3.0'
3.0'
3.0'
UPWARD
UPWARD
HANDWHEEL
HANDWHEEL
HANDWHEEL
HANDWHEEL
HANDWHEEL
S
S
S
S
S
GEOTEXTILE FABRIC
PROCESS VALVE SCHEDULE (3" DIA. AND LARGER)
SIZE (in.)
6
TYPE
CHECK
ACTUATOR COMMENTS
VALVE CHAMBER
LOCATION
FLANGED
VALVE NO.
6
9
8
7
5
3
2
1 -
10
11
4
6 CHECK -
6 GATE HANDWHEEL
6 GATE HANDWHEEL
6 GATE NUT
6 GATE NUT
6 GATE NUT
6 GATE NUT
8 GATE NUT
12 GATE NUT
12 GATE NUT
FORCEMAIN BETWEEN VALVE CHAMBER AND METER MANHOLE
CLEANOUT
FORCEMAIN DOWNSTREAM OF METER MANHOLE
CLEANOUT
FORCEMAIN TO CONTROL STRUCTURE A
CARRIER PIPE
VERMIN GUARD - TYPE B
SCALE: NOT TO SCALE
3" x 3" OPENINGS USING 6 GAUGE
STAINLESS STEEL WIRE. TACK
WELD AT EACH INTERSECTION
1/2" Ø STAINLESS STEEL
BOLTS, NUTS & WASHERS
(DOUBLE NUT)
316 STAINLESS STEEL CLAMP
BANDS 1 1/2" WIDE x 1/4" THICK
CIRCUMFERENTIAL WIRES
2"
2"
FLANGED
FLANGED
FLANGED
MJ, BURIED W/ VALVE BOX
MJ, BURIED W/ VALVE BOX
MJ, BURIED W/ VALVE BOX
MJ, BURIED W/ VALVE BOX
MJ, BURIED W/ VALVE BOX
MJ, BURIED W/ VALVE BOX
MJ, BURIED W/ VALVE BOX
VALVE CHAMBER
VALVE CHAMBER
VALVE CHAMBER
TRANSFER BETWEEN CELL NO. 2 AND CELL NO. 3
TRANSFER BETWEEN CELL NO. 1 AND CELL NO. 2
FLANGED JOINT
MECHANICAL JOINT
PIPE/FITTING SYMBOLS
VALVE SYMBOLS
GATE VALVE
EQUIPMENT TAG NUMBERS
VALVE NUMBERX
PROCESS LEGEND
SLIDE GATE NUMBERSG-X
CHECK VALVE
COMPACTED FILL
OR EX. GRADE
SECTION B-BSECTION A-A
B
B
A A
TYPICAL STOP PLATE DETAILS
SCALE: NOT TO SCALE
BOX OUT AND FILL WITH
GROUT AS RECOMMENDED
BY MANUFACTURER
FLUSH BOTTOM
NEOPRENE SEAL
STIFFENERS AS REQUIRED
* NOTES:
1. PLATE HEIGHT AND PLATE WIDTH DO NOT
TAKE INTO ACCOUNT BEARING SURFACE OF
PLATE
2. COORDINATE TOP OF PLATE FRAME WITH
ANY GRATING SUPPORT ANGLES
PLA
TE
H
EIG
HT
*
FR
AM
E H
EIG
HT
UHMW POLYETHYLENE
SEALS
PLATE WIDTH*
LIFTING HANDLE
SLIDE PLATE NUMBERSP-X
FE-1 FLOWMETER NUMBER
12
12
12
12
12
12
12
12
GATE
GATE
GATE
GATE
GATE
GATE
GATE
GATE
NUT
NUT
NUT
NUT
NUT
NUT
NUT
NUT
12
13
14
15
16
17
18
19
FLANGED, W/ RISER AND BOX
FLANGED, W/ RISER AND BOX
FLANGED, W/ RISER AND BOX
FLANGED, W/ RISER AND BOX
FLANGED, W/ RISER AND BOX
FLANGED, W/ RISER AND BOX
FLANGED, W/ RISER AND BOX
FLANGED, W/ RISER AND BOX
20
21
22
23
24
12
12
12
12
12
GATE
GATE
GATE
GATE
GATE
NUT
NUT
NUT
NUT
NUT MJ, BURIED W/ VALVE BOX
FLANGED, W/ RISER AND BOX
FLANGED, W/ RISER AND BOX
FLANGED, W/ RISER AND BOX
FLANGED, W/ RISER AND BOX
DECANT FROM CELL NO. 1
DECANT FROM CELL NO. 1
DECANT FROM CELL NO. 1
DISCHARGE FROM CONTROL STRUCTURE B
DECANT FROM CELL NO. 2
DECANT FROM CELL NO. 2
DECANT FROM CELL NO. 2
DISCHARGE FROM CONTROL STRUCTURE D
DECANT FROM CELL NO. 3
DECANT FROM CELL NO. 3
DECANT FROM CELL NO. 3
DISCHARGE FROM CONTROL STRUCTURE F
DISCHARGE FROM CHLORINE CONTACT BUILDING
MANHOLE WALL
EXISTING MANHOLE
PIPE CONNECTION
EXISTING
SEWER PIPE
CORE DRILL EX MH WALL.
INSERT KOR-N-SEAL
FLEXIBLE PIPE TO MH
CONNECTOR OR EQUAL.
INTERIOR EXTERIOR
UTILITY
SPRING LINE
FINISHED BACKFILL GRADE
CROWN
INVERT
UTILITY TRENCHING, EXCAVATING
AND BACKFILLING TERMINOLOGY
SP
EC
IA
L P
IP
E
FO
UN
DA
TIO
N
BE
DD
IN
G A
RE
A
TR
EN
CH
B
AC
KF
ILL A
RE
A
CO
MP
AC
T T
O 95
% M
AX
. D
EN
SIT
Y
GRANULAR
MATERIAL
BACKFILL
SUITABLE EXCAVATED MATERIAL
OR
GRANULAR MATERIAL BACKFILL
12
"1
2"
6A STONE BACKFILL
TOP OF
BEDDING
BARREL
GRADE
PAYMENT
LINE
GEOTEXTILE
FABRIC
10'-0" MAX
6'-0
"4" M
AX
TOP RAIL CONT.
CORNER POST(GATE
POST SIMILAR)
BRACE
LINE POST
3/8" TRUSS ROD ASSY
BOTTOM WIRE
2'-1
0"M
IN
3'-0"M
IN
(T
YP
)
(T
YP
)
SCALE: 1/2" = 1'-0"
CHAIN LINK FENCE
16"SQ OR 16"Ø CONC
CORNER BASE(GATE POST
BASES SIMILAR SIZE)
12"WX6"D CONC.CURB
9"DIA CONC.
BASE(TYP)
DIAMOND
MESH FABRIC
AUTOMATIC SLIDING GATE DETAIL
NOT TO SCALE
4" OD POST
KEEPER
POST TOP
CHAIN LINK FABRIC
2" SQ ALUM
UPRIGHT
4" OD
POST
24' WIDE GATE
LENGTH IN ACCORDANCE WITH
ASTM F1184
CONCRETE IN ACCORDANCE
WITH GATE MANUFACTURER'S
RECOMMENDATIONS. (TYPICAL)
6'-0" F
EN
CE
GATE CONSTRUCTION SHALL MEET ASTM F1184
AND CHAIN LINK MANUFACTURER'S INSTITUTE
PRODUCT MANUAL RECOMMENDATIONS.
ROLLER GUARD
(REQUIRED)
OPERATOR
RECEIVER
(CABLE IN SEPARATE
CONDUIT)
PVC CONDUIT TO BUILDING
FOR POWER CABLES
PLACE CONTACT SENSORS
PER MANUFACTURERS
REQUIREMENTS
PLACE CONTACT SENSORS
PER MANUFACTURERS
REQUIREMENTS
CHAIN DRIVE PER
MANUFACTURERES REQUIREMENT
F&V PROJECT NO.
DESIGN TEAM:
DRAWING INFORMATION:
CHECK BY:
REVISION:
CIT
Y O
F C
OL
EM
AN
MID
LA
ND
C
OU
NT
Y, M
IC
HIG
AN
SE
WA
GE
L
AG
OO
N/P
UM
P S
TA
TIO
N IM
PR
OV
EM
EN
TS
MAR 2018
834310
2125 Ridgewood Dr, Suite 101
P: 989.837.3280
F: 989.837.3290
Midland, MI 48642
DESIG
N. BU
ILD. O
PERATE.
3
AD
DE
ND
UM
N
O. 3
04/12/18
DJD
2
834310-Coleman ICE C10
050118 dand
DE
TA
IL
S
HE
ET
GOB/DRS/DJD2
C10
NOTE:
POWER PER MANUFACTURES
RECOMMENDATION
OPERATOR LOCATION PER
MANUFACTURER
12" Ø DECANT - D.I.P.
INV. EL. 742.80
TRANSFER STRUCTURE NO. 2 PLAN
SCALE: 1/2" = 1'-0"
CONTROL STRUCTURE B. D. & F SECTIONAL PLAN
SCALE: 1/2" = 1'-0"
2
SECTION
2
12" Ø D.I.P. TRANSFER
EL. 741.80
GROUT FLOW CHANNEL
SLOPE TO OUTLET
FLOOR BOX
12" Ø GATE VALVE W/
EXTENDED STEM & 2" NUT
(TYP OF 4)
2" PVC STANDPIPE, TAP
12" DIP. SUPPORT PVC PIPE
FROM STRUCTURE WALL
TOP OF CONCRETE
EL. 750.50
RUBBER BOOT (TYP)
12" Ø - D.I. PIPE
FROM CELL NO. 2
12" Ø - D.I. PIPE -
FROM CELL NO. 2
12" Ø - D.I. PIPE
FROM CELL NO. 2
12" 45° BEND
(TYP OF 2)
12" Ø - PVC - TO
LAGOON NO. 3
NORTH
NORTH
24"X36" ALUMINUM H-20
WHEEL LOAD HATCH
PRECAST TOP SLAB. REINFORCE
FOR H-20 LOADING.
FLOOR BOX
(TYP OF 6)
PROVIDE BRASS PLATE W/ VALVE
NUMBER NEXT TO EACH FLOOR BOX.
RAM SET IN PLACE W/ S.S. NAILS
12" Ø DECANT - D.I.P.
INV. EL. 744.80
12" Ø DECANT - D.I.P.
(SHOWN OUT OF
ROTATION)
INV. EL. 746.80
6' Ø PRECAST MANHOLE
STRUCTURE W/ INTEGRAL
BOTTOM SLAB
2" PVC STANDPIPE, TAP
12" DIP. SUPPORT PVC PIPE
FROM STRUCTURE WALL
TYPICAL DECANT PIPE DETAIL
SCALE: 1/2" = 1'-0"
HWL = 748.50
TOP OF BERM EL. 750.50
9" ARMOR STONE
LAGOON NO. 1 INV. EL. = 744.80
LAGOON NO. 2 INV. EL. = 744.80
LAGOON NO. 3 INV. EL. = 744.80
NOTE:
SEE PIPE PENETRATION DETAIL, SHEET C03(TYP)
F&V PROJECT NO.
DESIGN TEAM:
DRAWING INFORMATION:
CHECK BY:
REVISION:
CIT
Y O
F C
OL
EM
AN
MID
LA
ND
C
OU
NT
Y, M
IC
HIG
AN
SE
WA
GE
L
AG
OO
N/P
UM
P S
TA
TIO
N IM
PR
OV
EM
EN
TS
MAR 2018
834310
2125 Ridgewood Dr, Suite 101
P: 989.837.3280
F: 989.837.3290
Midland, MI 48642
DESIGN. BUILD. OPERATE.
3
AD
DE
ND
UM
N
O. 3
04/12/18
DJD
2
834310-Coleman ICE C11
050218 dand
DIV
ER
SIO
N S
TR
UC
TU
RE
D
ET
AIL
S
HE
ET
INITIALS
C11
LAGOON NO. 1 INV. EL. = 742.80
LAGOON NO. 2 INV. EL. = 742.80
LAGOON NO. 3 INV. EL. = 742.80
LAGOON NO. 1 INV. EL. = 746.80
LAGOON NO. 2 INV. EL. = 746.80
LAGOON NO. 3 INV. EL. = 746.80
PROVIDE OPENING FOR
2" PVC STANDPIPE
PROVIDE OPENING FOR
2" PVC STANDPIPE
2
'-
0
"
3
'-
0
"
6-FT DIA. PRECAST
MANHOLE STRUCTURE
PR
EC
AS
T B
OT
TO
M 4
2"
12"
1'-0"
1'-2"
1'-6"
2'-0"
2'-6"8
7
6
5
4
"D" BAR SIZE
NOTES:
"N" BARS @ 3" IN EACH MAT, TYP.
FOR ALL OPENINGS, WALL AND
FLOOR. "N" SHALL EQUAL OR
EXCEED 1/2 TIMES THE MAXIMUM
NUMBERS OF BARS INTERRUPTED
BY THE OPENING IN ANY ONE
DIRECTION. THE DIAGONAL BARS
SHALL BE EQUAL IN DIA. TO THE
LARGEST BAR INTERRUPTED.
OPENING REINFORCEMENT TYPE A
SCALE: NOT TO SCALE
3
"
C
L
R
T
Y
P
"
D
"
1/4"
3/1
6"
2"
REMOVABLE
FRP COVER
L 2 1/2" x 2 1/2" x 1/4"
ALUMINUM ANGLE
PLUS 1/4" SHIM PLATE
1/4" x 3/4" x 6" BENT BAR
@ 1'-6" O.C. WELDED TO
ANGLE
FRP SUPPORT DETAIL
NO SCALE
60°
LWL ALARM 726.60
LEAD PUMP OFF 728.60
HWL ALARM 731.60
LAG PUMP ON 731.00
LEAD PUMP ON 730.60
LAG PUMP OFF 729.60
F&V PROJECT NO.
DESIGN TEAM:
DRAWING INFORMATION:
CHECK BY:
REVISION:
CIT
Y O
F C
OL
EM
AN
MID
LA
ND
C
OU
NT
Y, M
IC
HIG
AN
SE
WA
GE
L
AG
OO
N/P
UM
P S
TA
TIO
N IM
PR
OV
EM
EN
TS
MAR 2018
834310
2125 Ridgewood Dr, Suite 101
P: 989.837.3280
F: 989.837.3290
Midland, MI 48642
DESIG
N. BU
ILD. O
PERATE.
3
AD
DE
ND
UM
N
O. 3
04/12/18
DJD
2
834310-Coleman ICE P01
050118 douglass
PR
OP
OS
ED
C
OL
EM
AN
P
UM
P S
TA
TIO
N
GOB/DRS/DJD
P01
PROPOSED CAMLOCK
CLEAN OUT
PROPOSED METERING
MANHOLE PLAN
PROPOSED VALVE CHAMBER PLAN
PROPOSED 7'X7' DIA WET WELL PROFILE
PROPOSED 5-FT. DIA. METERING
MANHOLE PROFILE
PROPOSED 7'X7' DIA. VALVE CHAMBER PROFILE
GENERAL NOTES:
1. ALL PIPE INSTALLED AS PART OF WET WELL AND
VALVE CHAMBER CONSTRUCTION SHALL BE 6"
CLASS 52 OR 53 DUCTILE IRON PIPE WITH
FLANGED JOINTS INSIDE OF STRUCTURES AND
MECHANICAL JOINTS OUTSIDE OF STRUCTURES
UNLESS OTHERWISE NOTED.
2. DETAILS AND INSTALLATION OF PUMP AND
PLUMBING WITHIN THE WET WELL WILL BE AS
REQUIRED PER THE PUMP MANUFACTURES
SPECIFICATIONS.
3. CONTRACTOR SHALL FURNISH PLANS OF THE
COMPLETE PUMP INSTALLATION FOR APPROVAL
4. BACKFILL ENTIRE VOID AREA AROUND
STRUCTURES WITH 100% MDOT 6A STONE C.I.P.
5. CONTRACTOR SHALL DEWATER THE SITE AS
REQUIRED TO CONSTRUCT SANITARY SEWER,
PUMPING STATION AND VALVE CHAMBER,
CONTRACTOR SHALL ALSO TAKE APPROPRIATE
MEASURES TO PREVENT WET WELL FROM
FLOATING DURING CONSTRUCTION AND SHALL BE
RESPONSIBLE FOR ANY AND ALL DAMAGES
INCURRED DUE TO SAME.
100% MDOT 6A STONE BACKFILL C.I.P.
PIPE SUPPORT
TYP.
1
4
" TAPPED
NIPPLE & PETCOCK
6" DUCTILE IRON
DISCHARGE PIPE
CAST BOTTOM
SECTION OF VALVE
CHAMBER IN ONE
PIECE
3500 PSI CONC. WITH #4
REBAR @ 10" O.C. EACH
WAY, EACH FACE
REBAR TO BE DESIGNED
FOR HS20 LOADING
3500 PSI CONC.
WITH #4 REBAR @
10" O.C. EACH WAY
2" EMBED
3500 PSI CONC.
FILLETS
DUPLEX
PUMP
SYSTEM
STAINLESS STEEL
LIFT CHAIN
MORTARED RUBBER JOINT
CAST BOTTOM
SECTION OF
VALVE CHAMBER IN
ONE PIECE
REBAR TO BE DESIGNED
FOR HS20 LOADING
GUIDE RAIL
PER MFG.
REQUIREMENTS
CONCRETE PAD FOR
PROPOSED BUILDING
SEE SHEET A01
TOP OF CHAMBER
ELEV. = 745.60
TOP OF WET WELL
ELEV. 745.70
FLOOR OF CHAMBER
ELEV. 737.60
4' DIA CONC. MANHOLE
6" MAG METER
CONNECT TO
VALVE CHAMBER
UNDISTURBED SOIL
CONCRETE PAD FOR
PROPOSED BUILDING
TOP OF CHAMBER
ELEV. = 745.50
6" DUCTILE IRON
DISCHARGE PIPE
90° BEND
90° BEND
CORE AND PLACE MODULAR
MECHANICAL SEAL AT PIPE
OPENINGS (TYP.)
REFER TO SITE PLAN
FOR EXACT LOCATION
OF INFLUENT PIPES
1/4" TAPPED NIPPLE
PETCOCK TO BE SPACED
A MIN. 6" FROM WALL TO
ACCOMMODATE GAUGES
EDGE OF CONC.
PAD FOR FLOOR
OF BUILDING
6" DUCTILE IRON
DISCHARGE PIPE
6" CHECK VALVE
6" CHECK VALVE
6" GATE VALVE
6" GATE VALVE
1/4" TAPPED NIPPLE
PETCOCK TO BE SPACED A
MIN. 6" FROM WALL TO
ACCOMMODATE GAUGES
1
4
" TAPPED
NIPPLE &
PETCOCK
6" TRUE WYE
SPOOL PIECE TYP.
6" LONG RADIUS
45° BEND TYP.
MANHOLE STEPS
@ 16" O.C. CENTER
UNDER OPENING
WET WELL AND VALVE
CHAMBER CENTERLINE
7'X7' PRECAST CONCRETE BOX
CULVERT STACKED END TO END
WITH WATERPROOF JOINTS
6" GATE VALVE
6"X8" REDUCER
PROPOSED 8" FORCE MAIN
MIN. 6" MDOT 6A STONE CIP
MIN. 6" MDOT 6A STONE CIP
MIN. 8" MDOT 6A STONE CIP
2 - 45° BENDS
DUPLEX PUMP SYSTEM
CAMLOCK
CLEANOUT
6" GATE VALVE
2 - 6" 45° BENDS
TOP OF PAD
ELEV. = 724.60
LEVEL TRANSDUCER CONTEGRA
MODEL SLX 130 INSTALL PER
MANUFACTURERS REQUIREMENTS
24"X36" H20 LOADING
ALUMINUM HATCH
AND SAFETY GRATE
CENTER M.H. STEPS
UNDER OPENING
6" MAG METER
5'-0"
CONNECT TO MAG
METER IN METER
CHAMBER
PROPOSED 7'X7' DIA WET WELL PLAN
2 - 6" 45° BENDS
12'
2'-6"
10"
2'-6"
7'-0"
21'-1-1/2"
LOWEST INLET INV. = 731.61 (15" S.)
INLET INV. = 732.04 (10" N.)
24"X36" H20 LOAD
ALUMINUM HATCH
12"
1'-3"
1'-8"
CONCRETE
CHAMFER
7'X7' PRECAST CONCRETE BOX
CULVERT STACKED END TO END
WITH WATERPROOF JOINTS
2'-6"
36"X60" ALUMINUM H20 LOADING HATCH
WITH STAINLESS STEEL SLAM-LOCK
AND SAFETY GRATE.
EXTEND 6" PVC
AIR VENT TO
BUILDING EXTEND
UP TO ROOF LINE.
SEE SHEET A01
PROVIDE S.S. SLIDE RAIL
SUPPORTS PER MFTRS.
REQUIREMENT
2'-6"
100% MDOT 6A STONE BACKFILL C.I.P.
PLACE 100% MDOT 6A
STONE BACKFILL
AROUND CAMLOCK
CLEAN OUT
4' DIA CONC. MANHOLE
12'
NO SCALE
NO SCALE
NO SCALE
PLACE
3
4
" EXPANSION JOINT WITH
RUBBER SEALANT AROUND
PERIMETER OF WET WELL
36"X60" ALUMINUM H20 LOADING HATCH
WITH STAINLESS STEEL SLAM-LOCK
AND SAFETY GRATE.
NOTE:
REFER TO SHT C06 FOR
LOCATION OF EXISTING
10" SANITARY SEWER
PROTECT WHEN CROSSING.
ABANDON AFTER NEW PIPE
IS CONNECTED TO WET WELL
AND NEW PUMP STATION IS
ACCEPTED AND PLACED INTO
SERVICE.
WET WELL
PAY ITEM
VALVE
CHAMBER
PAY ITEM
VALVE
CHAMBER
PAY ITEM
METER PIT
PAY ITEM
ME
TE
R P
IT
PA
Y IT
EM
ITEMS IN THE SHADED
AREA ARE PURCHASED BY
THE OWNER TO BE INSTALLED
IN THIS CONTRACT
INFLUENT PIPES
NOT PART OF THE
WET WELL PAY ITEM
6" GATE VALVE
8" LATERAL
5' M
IN
3' M
IN
.
2'-2 1/2"
7'
6" MJ SLEEVE
7'
CORE AND PLACE MODULAR
MECHANICAL SEAL AT PIPE
OPENINGS (TYP.)
18'
PIPING CENTERLINE ELEV. = 739.10
FLOOR OF MANHOLE ELEV. 737.60
GROUT BOTTOM OF
MANHOLE TO CREATE SUMP
GROUT BOTTOM OF
MANHOLE TO CREATE SUMP
1
INTERIOR WALL
PIPE
EXERIOR WALL
WALL SLEEVE DETAIL
SCALE: NOT TO SCALE
CONCRETE WALL
FILL ANNULAR SPACE WITH
NON-SHRINK GROUT,
TROWEL SMOOTH
MODULAR
MECHANICAL SEAL
1" THICK RIGID
FOAM INSULATION
7'
EXTEND 6" PVC
AIR VENT TO
BUILDING EXTEND
UP TO ROOF LINE.
SEE SHEET A01
31
42
5
6
7
8"
10'
8"
1'-3"
730
735
740
745
750
755
760
HYDRAULIC PROFILE
CONTROL
STRUCTURE A
TREATMENT
CELL NO. 1
CONTROL
STRUCTURES B, D, & F
SEEPAGE CELL CONTROL
STRUCTURES C, E, & G
ARNOLD DRAINCHLORINE
CONTACT BLDG
730
735
740
745
750
755
760
TREATMENT
CELL NO. 2
TREATMENT
CELL NO. 3
CONTROL
STRUCTURES C, E, & G
8" INF. FORCEMAIN
CONTROL
STRUCTURE A
CONTROL
STRUCTURE B
12
" D
IP
- C
EL
L
NO
.3
IN
F.
12" DIP - CELL
NO.1 DECANT
12" DIP - CELL
NO.1 EFF.
LEGEND & ABBREVIATIONS
INF. INFLUENT
EFF. EFFLUENT
DIA. DIAMETER
DIP DUCTILE IRON PIPE
SS STAINLESS STEEL
HDPE HIGH DENSITY POLYETHYLENE
ALUM ALUMINUM
FLOW DIRECTION
EQUIPMENT TAG
VALVE TAG
SLIDE GATE TAG
SLIDE PLATE TAG
SLIDE GATE
BUTTERFLY VALVE
CHECK VALVE
BALL VALVE
GATE VALVE
PUMP
BLOWER
P-#
#
SG-#
PROCESS FLOW SCHEMATIC
ARNOLD DRAIN
EM
ER
GE
NC
Y 1
2" D
IP
E
FF
.
FR
OM
T
RE
AT
ME
NT
C
EL
LS
15
12" DIP - CELL
NO.1 DECANT
SP-2
SP-1
SP-3
TREATMENT
CELL NO. 1
TREATMENT
CELL NO. 2
TREATMENT
CELL NO. 3
CONTROL
STRUCTURE D
12" DIP - CELL
NO.2 EFF.
19
CONTROL
STRUCTURE F
12" DIP - CELL
NO.3 EFF.
23
CONTROL
STRUCTURE C
CONTROL
STRUCTURE E
CONTROL
STRUCTURE G
SEEPAGE CELL NO. 1
SEEPAGE CELL NO. 2
SEEPAGE CELL NO. 3
12" DIP - CELL
NO.1 DECANT
12" DIP - CELL
NO.2 DECANT
12" DIP - CELL
NO.2 DECANT
12" DIP - CELL
NO.2 DECANT
12" DIP - CELL
NO.3 DECANT
12" DIP - CELL
NO.3 DECANT
12" DIP - CELL
NO.3 DECANT
18
" D
IP
- C
EL
L
NO
. 2
&
3
E
FF
.
1
2
"
D
I
P
-
C
E
L
L
N
O
.
2
I
N
F
.
12" DIP - CELL
NO.1 INF.
12" DIP - CELL NO. 2
& 3 TRANFER
12" DIP - CELL NO. 2 & 3
EMERG. OVERFLOW
12" DIP - CELL NO. 1
& 2 TRANFER
12" DIP - CELL NO. 1 & 2
EMERG. OVERFLOW
18
" D
IP
- C
EL
L
NO
. 3
E
FF
.
CHLORINE
CONTACT BLDG
12" PVC - CELL NO. 3 &
SEEPAGE EMERG. OVERFLOW
PARSHALL
FLUME
SP-#
SG-3
SG-4
SG-1
SG-2
SG-5
SG-6
20
21
22
16
17
18
12
13
14
11
10
24
834310_P2
050118 douglass
PR
OC
ES
S F
LO
W S
CH
EM
AT
IC
&
H
YD
RA
UL
IC
P
RO
FIL
E
GOB, DRS, DJD2
P02
752.00
HWL 748.50
12" PVC EMERGENCY OVERFLOW
EL. 748.50
1
2
"
P
V
C
I
E
.
7
4
2
.
8
0
B
O
T
T
O
M
O
F
P
O
N
D
E
L
.
7
4
0
.
8
12" PVC EMERGENCY OVERFLOW
IE. 748.50
750.50
STOP PLATES
SP-1 TOP EL. 750.25
SP-2 TOP EL. 750.25
SP-3 TOP EL. 750.25
8
"
P
V
C
I
E
7
4
9
.
0
0
P
R
O
P
.
8
"
F
M
I
E
.
7
4
9
.
5
0
750.50
HWL 748.50 HWL 748.50
HWL 742.00
F&V PROJECT NO.
DESIGN TEAM:
DRAWING INFORMATION:
CHECK BY:
REVISION:
CIT
Y O
F C
OL
EM
AN
MID
LA
ND
C
OU
NT
Y, M
IC
HIG
AN
SE
WA
GE
L
AG
OO
N/P
UM
P S
TA
TIO
N IM
PR
OV
EM
EN
TS
MAR 2018
834310
2125 Ridgewood Dr, Suite 101
P: 989.837.3280
F: 989.837.3290
Midland, MI 48642
DESIG
N. BU
ILD. O
PERATE.
3
AD
DE
ND
UM
N
O. 3
04/12/18
DJD
2
B
O
T
T
O
M
O
F
P
O
N
D
E
L
.
7
4
0
.
8
B
O
T
T
O
M
O
F
P
O
N
D
E
L
.
7
4
0
.
8
1
2
"
P
V
C
I
E
.
7
4
2
.
8
0
1
2
"
P
V
C
I
E
.
7
4
2
.
8
0
1
2
"
P
V
C
D
R
A
W
O
F
F
I
E
.
7
4
2
.
8
0
1
2
"
P
V
C
I
E
.
7
4
2
.
8
0
1
2
"
P
V
C
I
E
.
7
4
2
.
8
0
12" PVC EMERGENCY OVERFLOW
IE. 748.50
1
2
"
P
V
C
I
E
.
7
4
0
.
5
0
1
2
"
P
V
C
I
E
.
7
3
7
.
7
0
1
2
"
P
V
C
I
E
.
7
3
7
.
3
5
1
2
"
C
M
P
I
E
.
7
3
7
.
3
5
1
2
"
P
V
C
I
E
.
7
4
1
.
8
0
1
2
"
P
V
C
D
E
C
A
N
T
I
E
.
7
4
4
.
8
0
1
2
"
P
V
C
D
E
C
A
N
T
I
E
.
7
4
6
.
8
0
5" 8" 5"
BOTTOM OF FOOTING
SEALANT & EXPANSION MATERIAL (1/2")6" CONCRETE SLAB WITH6 X 6 - 2.9 X 2.9 WWF
VAPOR BARRIER (10 MIL, CLASS A)PERIMETER INSULATION(EXTRUDED POLYSTYRENE, 3"X24", R15)COMPACTED GRANULAR FILL(12",MDOT CLASS II)REINFORCING (#4 TOP & BOTTOM)
REINFORCING (TWO #5)
REINFORCING(#4 VERT. @ 32" OC)
CONCRETE FOOTING
CONCRETE FOUNDATIONWALL
FINISH FLOOR
4'-0"
10"
5 1/2" 2 1/2"
3"(CLR)
NORTH
FLOOR PLAN
SCALE: 1/4" = 1'-0"
NORTH
FOUNDATION PLAN
SCALE: 1/4" = 1'-0"
NORTH
ROOF PLAN
SCALE: 1/4" = 1'-0"
(2) 3'-0" X 2'-0" VINYL
AWNING WINDOWS
INSULATED 4'-0" X 6'-10"
HM DOOR & FRAME
4" CONCRETE SLAB W/6X6 -
W2.9 X W2.9 W.W.F. OVER
6 MIL VAPOR BARRIER ON
MIN. 6" COMPACTED
GRANULAR FILL (TYP.)
834310-Coleman ICE A02-A03
LAYOUT
050118 douglass
BU
IL
DIN
G F
LO
OR
P
LA
N
GOB/DJD/DJD
A01
20
'-0
"
8'-0
"
4'-0"
INSULATED OVERHEAD
GARAGE DOOR BOTH
SIDES OF BUILDING
2'-0
"
24"X12" FOOTING
40
'-0
"
20'-0"
20
'-0
"
20'-0"
WET WELL
8"X8" TUBE STEEL
COLUMN
8"X8" TUBE STEEL COLUMN
TYP. 2 LOCATIONS
W8X15 STEEL I-BEAM
CLIP TO 8" STEEL
TUBE COLUMNS
38
'-0
"
8'-0
"
W6X12 STEEL I-BEAM.
BOLT TO 8" STEEL
BEAM PLACE OVER
HATCH IN WET WELL
20'-0"
19'-4"
20'-0"
18' RIDGE VENT
22'-0"
12" OVERHANG
3
4
" EXPANSION JOINT
WITH RUBBER SEALANT
AROUND PERIMETER OF
PROPOSED WET WELL
AND AT BUILDING PAD
W8X15 STEEL I-BEAM
CLIP TO 8" STEEL
TUBE COLUMNS
WET WELL
22'-0"
F&V PROJECT NO.
DESIGN TEAM:
DRAWING INFORMATION:
CHECK BY:
REVISION:
CIT
Y O
F C
OL
EM
AN
MID
LA
ND
C
OU
NT
Y, M
IC
HIG
AN
SE
WA
GE
L
AG
OO
N/P
UM
P S
TA
TIO
N IM
PR
OV
EM
EN
TS
MAR 2018
834310
2125 Ridgewood Dr, Suite 101
P: 989.837.3280
F: 989.837.3290
Midland, MI 48642
DESIG
N. BU
ILD. O
PERATE.
3
AD
DE
ND
UM
N
O. 3
04/12/18
DJD
2
6'-0"
6'-1
0"
BEAM POCKET
3 - 2"X4" POST TO ACCOMMODATE
8" STEEL I-BEAM TYP.
8'-0
"
8'-4"
BEAM POCKET
3 - 2"X4" POST TO ACCOMMODATE
8" STEEL I-BEAM TYP.
20
'-0
"
19'-4"
17
'-8
"
17
'-8
"
THICKEN SLAB TO 12" AT
PERIMETER. PLACE
2 - #4 REBAR CONTINUOUS
2' DIA. REINFORCED
CONC. PIER. TYP.
2 LOCATIONS
6" THICK CONC. SLAB
REINFORCED WITH 6X6 /
W2.9XW2.9 WWF
SAWCUT CONTROL JOINTS
1
A01 A02
W6X12 BEAM
VENT THROUGH ROOF
FROM WET WELL
1'-0"
1'-0
"
6" MDOT CLII GRANULAR MATERIAL
W6X6 - W2.9XW2.9 WWF
2" MIN. COVER
6" 3500 PSI
CONCRETE
2 - #4 BAR
CONTINUOUS
3" MIN. COVER
6"
6"
THICKENED SLAB DETAIL
NO SCALE
WET WELL VENT
12" X 12"
ROOF VENTS
TYP. FOR 3
19
'-0
"
1
A01 A02
1
A01 A02
SCALE: 1/2"=1'-0"
A
A02 A01
FOUNDATION DETAIL
NORTH ELEVATION
SCALE: 1/4" = 1'-0"
WEST ELEVATION
SCALE: 1/4" = 1'-0"
PRE-FINISHED ALUM.
DRIP EDGE
PRE-FINISHED ALUM.
FASCIA
2X6 SUB-FASCIA
PRE-FINISHED ALUM. SOFFIT
PROVIDE VENTED PANELS AS
REQ'D TO MEET VENTING
REQUIREMENTS. PROVIDE AN
EQUAL NUMBER AT EACH EAVE
CLOSURE TRIM @
BOTTOM EDGE OF
SIDING
6" CONCRETE SLAB W/6X6 - W2.9 X W2.9
WWF OVER 10 MIL, CLASS A VAPOR BARRIER ON
MIN. 12" COMPACTED MDOT CL II GRANULAR MTL.
PRE-FINISHED STEEL
SIDING - PERPENDICULAR
TO TRUSSES
PRE-ENGINEERED WOOD
TRUSSES @ 24" O.C.
1
2
" OSB ROOF SHEATHING
INSULATION BAFFLES (1" NOM.)
EXTEND MIN. 12" BEYOND
LIMITS OF INSULATION
BLOWN FIBERGLASS
INSULATION (R36, MIN)
3
1
2
" KRAFT FACED (R-13)
BATT INSULATION
ASPHALT SHINGLES
PRE-FINISHED ALUM.
FASCIA
8"X8" GALVANIZED AND
PAINTED SQUARE TUBE STEEL
APPROX. FIN. GRADE
APPROX. FIN. GRADE
INSULATED 4'-0" X 6'-10"
HM DOOR & FRAME
7'-0
"
6
12
6
12
ASPHALT SHINGLES
PRE-FINISHED ALUM.
DRIP EDGE
TWO TONE METAL SIDING
COLORS BY OWNER
APPROX. FIN. GRADE
6
12
"SIMPSON" H2.5 (OR EQUAL)
HURRICANE TIES AT EACH
END OF TRUSS / RAFTER
834310-Coleman ICE A02-A03
LAYOUT
050118 douglass
BU
IL
DIN
G E
LE
VA
TIO
NS
A
ND
S
EC
TIO
N
GOB/DJD/DJD
A02
I
C
E
&
W
A
T
E
R
S
H
I
E
L
D
4
'
B
E
Y
O
N
D
I
N
T
E
R
I
O
R
W
A
L
L
WAYNE DALTON STEEL OVERHEAD
INSULATED GARAGE DOORS
EACH SIDE OF BUILDING W/ OPERATORS
REINFORCED CONCRETE
SLAB
W8X28 GALVANIZED AND
PAINTED STEEL BEAM
W6X12 GALVANIZED AND
PAINTED STEEL BEAM
FOR TROLLEY HOIST
BOLTED TO 8" BEAM
RIDGE VENT
9'-4
"
9'-4
"
RIDGE VENT
2X4 STUDS @ 16" O.C W/
7
16
" OSB SHEATHING ON EACH
SIDE AND FULL THICKNESS
BATT INSULATION
ALUMINUM THRESHOLD
"Z" FURRING TRIM
@ WAINSCOTING
CLOSURE TRIM
@ BOTTOM EDGE
OF SIDING
"TYVEK" OR EQUAL
BUILDING WRAP
DBL. 2X8 HEADER
AT OPENINGS
1
2
" OSB SHEATHING ON
BOTTOM OF TRUSSES
ASPHALT SHINGLES
OVER 15# FELT
J-CHANNEL
AROUND
DOOR &
WINDOWS
2' DIA PIER
2' DIA PIER
6'-0
"
TREATED 2X4 SILL PLATE AND
SILL SEALER W/
1
2
" X 8" ANCHOR
BOLTS @ 32" O.C. MAX.
PRE-FINISHED ALUM.
VENTED SOFFIT
2 - TONE METAL SIDING OVER
1.5", R 7.5 POLYSTYRENE
BOARD INSULATION.
COLORS BY OWNER
40
" W
AIN
SC
OT
IN
G
PRE-FINISHED STEEL
SIDING - COLOR BY OWNER
THICKEN SLAB AT
PERIMETER
8"X8" SQUARE TUBE
STEEL COLUMN
W8X15 STEEL BEAM W8X15 STEEL BEAM
ALUMINUM FASCIA
BEAM CONNECTION DETAIL
NO SCALE
ALUMINUM VENTED SOFFIT
- PERPENDICULAR TO TRUSSES
UNDER ROOF
F&V PROJECT NO.
DESIGN TEAM:
DRAWING INFORMATION:
CHECK BY:
REVISION:
CIT
Y O
F C
OL
EM
AN
MID
LA
ND
C
OU
NT
Y, M
IC
HIG
AN
SE
WA
GE
L
AG
OO
N/P
UM
P S
TA
TIO
N IM
PR
OV
EM
EN
TS
MAR 2018
834310
2125 Ridgewood Dr, Suite 101
P: 989.837.3280
F: 989.837.3290
Midland, MI 48642
DESIG
N. BU
ILD. O
PERATE.
3
AD
DE
ND
UM
N
O. 3
04/12/18
DJD
2
BACKFILL AROUND BUILDING
WITH MDOT CLII GRANULAR
MATERIAL COMPACTED IN PLACE
BOLT TO COLUMN
6" GALVANIZED AND
PAINTED STEEL BEAM
BOLTED TO 8" BEAM
PAINT PROTRUDING SECTION
OF BEAM WITH SAFETY YELLOW
WELD STOP ON
END OF BEAM
6'-0"
THICKEN PAD UNDER
PORCH AREA
12"
6" PVC VENT FROM WET WELL
APPROX. WET WELL LOCATION
EXTEND ATTIC INSULATION
12" BEYOND WALL
1'-0"
RIDGE VENT
1
1
1'-0
"
6" PVC VENT FROM WET WELL
SCALE: 1/2"=1'-0"
1
A01 A02
SECTION
A
A02 A01
WORKING DAYS:
CALL MISS DIG
BEFORE YOU DIG
CALL 3 FULL
811
1-800-482-7171
OR
IN GROUND PULL BOX
POLE MOUNTED SITE LIGHTING
MOTOR CONTROL CENTER
PANELBOARD, FLUSH MOUNTED
PANELBOARD, SURFACE MOUNTED
INGROUND PULL BOX
P
CIRCUIT BREAKER
FUSIBLE DISCONNECT SWITCH
SINGLE LINE DIAGRAM SYMBOLS
BUILDING / SITE SYMBOLS
LIGHTING SYMBOLS
BUILDING / SITE SYMBOLSCONTROL CIRCUIT WIRING DIAGRAM SYMBOLS
SURGE ARRESTORSA
OVERHEAD ELECTRICAL w/ POLES
HAND-OFF-AUTO SWITCHHOA
REPEAT CYCLE TIMERRCT
BELOW GRADE WIRING
DISCONNECT SWITCH, "F" - FUSED
F
CONDUCTORS IN 3/4" C. INCLUDES 1 #12 GND.
HASHMARKS INDICATE QUANTITY OF #12 CURRENT CARRYING
HOMERUN INDICATES PANELBOARD "LPA" CIRCUIT NUMBER 1
LPA1
POWER TRANSFORMER
FIELD WIRING
MOUNTED OUTLET BOX.
CONTROL TRANSFORMER
GROUND CONNECTION (SCHEMATIC)
ELECTRICAL CONNECTION
x
x
AUTO
OFF
HAND
R
3-POSITION SELECTOR SWITCH
PUSH-TO-TEST PILOT LIGHT
PUSHBUTTON, NORMALLY OPEN
PUSHBUTTON, NORMALLY CLOSED
LEVEL SWITCH, NORMALLY OPEN
LEVEL SWITCH, NORMALLY CLOSED
LIMIT SWITCH, NORMALLY OPEN
LIMIT SWITCH, NORMALLY CLOSED
PRESSURE SWITCH, NORMALLY OPEN
PRESSURE SWITCH, NORMALLY CLOSED
FLOW SWITCH, NORMALLY OPEN
FLOW SWITCH, NORMALLY CLOSED
ON-DELAY TIMING CONTACT,
NORMALLY OPEN
ON-DELAY TIMING CONTACT,
NORMALLY CLOSED
OFF-DELAY TIMING CONTACT,
NORMALLY OPEN
OFF-DELAY TIMING CONTACT,
NORMALLY CLOSED
RELAY CONTACT, NORMALLY OPEN
RELAY CONTACT, NORMALLY CLOSED
TERMINAL BLOCK
FUSE
CONTROL TRANSFORMER
SOLENOID VALVE (WIRING DIAGRAM)
SURFACE OR PENDANT (CEILING) MOUNTED
CIRCUIT #3.
EMERGENCY OR NIGHT LIGHT, INCANDESCENT
OR HID, CEILING OR WALL MOUNTED.
SURFACE OR RECESS MOUNTED FLUORESCENT,
CEILING OR WALL EXIT LIGHTXX
BARE-LAMP FLUORESCENT STRIP.
SINGLE RECEPTACLE, MOUNTED 12" A.F.F.
DUPLEX RECEPTACLE, MOUNTED 12" A.F.F.
QUADRUPLEX RECEPTACLE, MOUNTED 12" A.F.F.
DUPLEX RECEPTACLE WITH GFI, MOUNTED 42" A.F.F.
SINGLE 3 PHASE RECEPTACLE, MOUNTED 12" A.F.F.
TELEPHONE OUTLET, WALL MOUNTED 12" A.F.F.
S
SINGLE-POLE SWITCH, MOUNTED 42" A.F.F.
SM
MANUAL MOTOR STARTING SWITCH, MOUNTED 42" A.F.F.
PUSHBUTTON STATION
BELL
HORN
JUNCTION BOX CONNECT TO
J
MOTOR STARTER, NEMA SIZE 2
DISCONNECT SWITCH, NON - FUSED
COMBINATION MOTOR STARTER, NEMA SIZE 1
T
THERMOSTAT, WALL MOUNTED, 5'-0" A.F.F.
THREE-PHASE MOTOR
SINGLE-PHASE MOTOR
EQUIPMENT AS REQUIRED
3 3
INCANDESCENT, OR HID, "3" INDICATED
"3" INDICATES CIRCUIT #3
3
"1" INDICATES FIXTURE TYPE,
"100" INDICATES TOTAL FIXTURE WATTAGE
1
100
"ab" MEANS 2 SWITCHES FOR CIRCUIT "a"
AND CIRCUIT "b"
3
(SEE FIXTURE SCHEDULE)
a,b
(2)
(1)
NORMALLY CLOSED
TEMPERATURE SWITCH
NORMALLY OPEN
TEMPERATURE SWITCH
SV
SOLENOID VALVE (PLAN DRAWING, P & ID)
GROUND ROD (PLAN DRAWING)
GROUND ROD (SINGLE LINE DIAGRAM)
30A
3P
CIRCUIT BREAKER IN PANEL OR SWITCHBOARD, 30 AMP,
3 POLE
2
1
5
INTERCOM STATION DESK MOUNTED.
ON FLUSH WALL MOUNTED OUTLET BOX, 42" AFF.
SURFACE MULTI-OUTLET RACEWAY WITH RECEPTACLES IN RACEWAY 24" ON CENTER,
INTERCOM STATION OUTLET, FLUSH WALL MOUNTED OUTLET BOX 12" AFF.
C
MAMMETER, VOLTMETER, AS REQUIRED (REFER TO SPECIFICATIONS)
DATA PROCESSING OUTLET MOUNTED ON FLUSH OUTLET BOX, 12" AFF.
J
J
JUNCTION BOX, FLUSH WALL MOUNTED.
SD
FIRE ALARM SMOKE DETECTOR, PHOTO ELECTRIC TYPE, ON FLUSH CEILING
CENTERED ABOVE THE PULL STATION. PROVIDE CONDUIT AND WIRE BETWEEN OUTLET BOXES.
AUDIO-VISUAL ALARM INDICATING DEVICE IN FLUSH WALL MOUNTED OUTLET BOX, 7'-6" AFF,
FIRE ALARM MANUAL PULL STATION, ON FLUSH WALL MOUNTED OUTLET BOX 42" AFF AND
FIRE ALARM MANUAL PULL STATION, ON FLUSH WALL MOUNTED OUTLET BOX, 42" AFF.
JUNCTION BOX CONCEALED ABOVE ACCESSIBLE CEILING AREA.
OCCUPANCY SENSOR SWITCH IN FLUSH WALL MOUNTED OUTLET BOX. 7'-6" AFF.
SECONDARY SURGE ARRESTOR
834310-Coleman Ice-E01
050118 douglass
EL
EC
TR
IC
AL
L
EG
EN
D
GOB\DRS\DJD2
E01
F&V PROJECT NO.
DESIGN TEAM:
DRAWING INFORMATION:
CHECK BY:
REVISION:
CIT
Y O
F C
OL
EM
AN
MID
LA
ND
C
OU
NT
Y, M
IC
HIG
AN
SE
WA
GE
L
AG
OO
N/P
UM
P S
TA
TIO
N IM
PR
OV
EM
EN
TS
MAR 2018
834310
2125 Ridgewood Dr, Suite 101
P: 989.837.3280
F: 989.837.3290
Midland, MI 48642
DESIG
N. BU
ILD. O
PERATE.
3
AD
DE
ND
UM
N
O. 3
04/12/18
DJD
2
NORTH
EXISTING WET WELL
ELECTRICAL SITE PLAN
1
SHEET NOTES:
VERIFY LOCATION AND ELEVATION OF EXISTING UTILITIES
PRIOR TO CONSTRUCTION.
CAP SPARE CONDUITS AND ZIP TIE #4 IRON TO END FOR
LOCATING IN THE FUTURE.
CONFIRM GAS LINE SIZE WITH GENERATOR SUPPLIER. BURY
AT 3'-0" DEPTH.
REFER TO SPECIFICATION SECTION 23 11 23 FOR NEW GAS
SERVICE REQUIREMENTS.
REFER TO SPECIFICATION SECTION 26 05 10 FOR RELOCATED
ELECTRIC SERVICE REQUIREMENTS.
GENERATOR SIGNAL AND ALARM WIRING BETWEEN,
GENERATOR, ATS AND PUMP CONTROL PANEL FOR
GENERATOR START, GENERATOR FAULT AND TWO SPARES.
BATTERY CHARGER, BLOCK HEATER AND MAINTENANCE
RECEPTACLE CIRCUITS TO LPA.
OWNER FURNISHED, CONTRACTOR INSTALLED.
2
3
4
5
6
PROPOSED BUILDING
ABANDON EX. PUMP STATION AND REMOVE
EXISTING UNDERGROUND ELECTRIC/PHONE
SERVICE AFTER NEW PUMP STATION IS PLACED
INTO SERVICE. RETURN EXISTING ABOVE GRADE
SWITCHGEAR TO OWNER
EXISTING POWER POLE AND
OVERHEAD SERVICE TO
REMAIN. NEW UNDEGROUND
SERVICE FROM POLE TO METER
BY CONSUMERS ENERGY
5
5
ELECTRIC SERVICE
ENTRANCE LOCATION
AND METER
10#14 & 1#14 GND, 3/4" C.
SEE SINGLE LINE
DIAGRAM FOR POWER
CONDUCTORS AND
CONDUIT
6#12 & 1#12 GND, 3/4" C.
7
7
GENERATOR. SEE
FOUNDATION DETAIL
THIS SHEET
6
HMA PARKING AREA
PROPOSED WET WELL
834310-Coleman Ice-E02
050118 dand
EL
EC
TR
IC
AL
S
IT
E P
LA
N
GOB\DRS\DJD2
E02
F&V PROJECT NO.
DESIGN TEAM:
DRAWING INFORMATION:
CHECK BY:
REVISION:
CIT
Y O
F C
OL
EM
AN
MID
LA
ND
C
OU
NT
Y, M
IC
HIG
AN
SE
WA
GE
L
AG
OO
N/P
UM
P S
TA
TIO
N IM
PR
OV
EM
EN
TS
MAR 2018
834310
2125 Ridgewood Dr, Suite 101
P: 989.837.3280
F: 989.837.3290
Midland, MI 48642
DESIG
N. BU
ILD. O
PERATE.
3
AD
DE
ND
UM
N
O. 3
04/12/18
DJD
2
PROPOSED VALVE CHAMBER
4 - 2" CONDUIT
2 #12 & 1 #12 GND, 3/4"C
FOR POWER TO AUTOMATIC GATE
FROM A 12/14
PROPANE TANK FOUNDATION
(TANK BY OWNER)
GAS LINE3
GENERATOR FOUNDATION
SECTION
3'-6"
VARIES
ALL SIDES
MAINTAIN 3" CLEAR
AS RECOMMENDED BY MANUFACTURER.
GENERATOR SHALL BE ANCHORED TO FOUNDATION
#5@12" O.C.
TOP & BOTTOM
@ 18" O.C. W/
#4 BENT BARS
IF NOT NOTED.
ADJACENT SIDEWALK OR FINISHED GRADE
BE AS NOTED ON SITE PLAN OR 6" ABOVE
TOP OF GENERATOR FOUNDATION SHALL
CHAMFER EXPOSED
EDGES 3/4"x3/4"
24" LAP
PER GENERATOR MANUFACTURER. BASE BID ON 10'-0".
PE
R G
EN
ER
AT
OR
MA
NU
FA
CT
UR
ER
BA
SE
B
ID
O
N 5'-0"
COORDINATE WITH GENERATOR
ELECTRICAL AND FUEL LINES.
OPENING AS REQUIRED FOR
MANUFACTURER.
PROVIDE ONE EXTRA BAR EACH SIDE
OF OPENING FOR EACH BAR CUT.
PLAN
#4 STIRRUPS
@ 18" O.C.
TOP & BOTTOM
#5@12" O.C.
2
LEVEL CONTROL MOUNTING DETAIL
SCALE: NONE
PROVIDE INSULATING BUSHING ON CONDUIT END
NYLON CABLE TIES (TYP)
STAINLESS STEEL BAR SUPPORT
USA BLUE BOOK MD-47715 OR EQUAL
CABLES TO CONTROL PANEL(TYP)
CONDUIT TO JUNCTION BOX
ALLOW 4' MIN. OF SLACK FOR
ADJUSTMENT OF FLOATS/TRANSDUCER
ATTACH TO CONCRETE HATCH OPENING
W/ 3/8" X 3" SS CONCRETE EXPANSION
ANCHORS
#14 THWN LIGHT
JUNCTION BOX
EQUAL (TYP.)
SPLICES. 3M OR
600V. WIRE NUT
NUTS
SUBMERSIBLE TRANSDUCER CORD
FLOAT CABLES (TYP)
1-1/2" PVC COATED RIGID METAL CONDUIT TO WET WELL.
NOTE:
WITHIN THIS JUNCTION BOX AND CONDUITS.
ONLY INTRINSICALLY SAFE CONDUCTORS SHALL BE PERMITTED
LEVEL CONTROL
JUNCTION BOX DETAIL
NEMA 7
BLUE CONDUCTORS
ON BOTH SIDE OF WIRE
PROVIDE WIRE NUMBER
PVC COATED RIGID METAL CONDUIT
TO WET WELL SIZED FOR MOTOR CABLE
BASE BID ON 1 1/2"
BOX DETAIL (TYP. OF 2)
MOTOR LEAD JUNCTION
SIZED TO HP.
BLACK FOR POWER
RED FOR SEAL/O-TEMP
THWN CONDUCTORS.
PROVIDE WIRE NUTS FOR
SEAL FAIL AND OVERTEMP
LEADS
POWER DISTRIBUTION
BLOCK FOR PUMP
MOTOR LEADS
NEMA 7 JUNCTION BOX
LEADS
MOTOR POWER
LEADS
FAILURE
PUMP SEAL
LEADS
TEMPERATURE
OVER-
PROVIDE WIRE NUMBERS ON
BOTH SIDES OF SPLICES
PUMP
CONDUIT BODY w/CONDUIT
AND CONDUCTORS TO VFD
WP 120, 20 AMP GFI
DUPLEX RECEPTACLE
Know what's below.before you dig.Call
R
EXPLOSIONPROOF CONDUIT
SEAL FITTING
CONDUIT BODY w/CONDUIT
AND CONDUCTORS TO VFD
EXPLOSIONPROOF CONDUIT
SEAL FITTING
MAKE A LOOP IN
TRANSDUCER CORD
FOR FUTURE
SPLICING
METERING MAHOLE IS NEC
CLASS 1, DIV.2 LOCATION
PCP
PCP
C
1" C
8
2
A5
A11
UH-1
S
MDP
S1
2
S1
2
S1
A5
2
S1
S S S
11
11
2
2
A2
3
A1
A1
A2
A2
4
PCP
2
MDP
I
A5
UH-1
A5
J J J
A3
I
A4
A5
7
PCP
B
NORTH
BUILDING ELECTRICAL PLAN
3
2
SHEET NOTES:
CONFIRM CONDUCTOR SIZING WITH GENERATOR SUPPLIER.
OBTAIN METER BASE FROM UTILITY AND INSTALL WHERE
SHOWN. COORDINATE EXISTING ELECTRICAL SERVICE
RELOCATION ON OWNERS BEHALF. REFER TO SPECIFICATION
SECTION 26 05 10 FOR ADDITIONAL REQUIREMENTS.
SIZE FUSES TO SSA MANUFACTURER RECOMMENDATIONS.
REFER TO SINGLE LINE DIAGRAM FOR ALL HOMERUN WIRE
AND CONDUIT SIZES NOT SHOWN.
SIZE BREAKER BASED ON VFD INPUT.
OWNER FURNISHED, CONTRACTOR INSTALLED.
1
5
UNDERGROUND ELECTRIC SERVICE
SEE SINGLE LINE DIAGRAM
84" A.F.F.
WALL MOUNT
CEILING MOUNT
PUMP STATION FIXTURE AND HVAC SCHEDULE
MCGRAW EDISON
ISS-FO2-LED-E1-BL3-BZ-P120
120V LED WALL PAK w/PHOTO CELL70170
4
TYPE
MOUNTING
120V LED
WW NO.
LAMPTOTAL
TYPE DESCRIPTION
282561
2
NOTE:
APPROVED EQUAL PERFORMANCE
BY OTHERS ACCEPTED FOR TYPES
1-4.
METALUX
4ILED-LD4-7-WG-120V-L840-CD-U
3
10'-0" A.F.F.
EMERGENCY LIGHTING120V LED9220
7'-0" ABOVE GRADE
WALL MOUNT120V LED10110EDWARDS 48FLEDR-N5. FLASHING
RED BEACON. SHATTER RESISTENT,
NEMA 4 HOUSING
6
2
834310-Coleman Ice-E03
050118 davet
EL
EC
TR
IC
P
AN
EL
B
UIL
DIN
G E
LE
CT
RIC
AL
P
LA
N
GOB/DRS/DJD2
E03
F&V PROJECT NO.
DESIGN TEAM:
DRAWING INFORMATION:
CHECK BY:
REVISION:
CIT
Y O
F C
OL
EM
AN
MID
LA
ND
C
OU
NT
Y, M
IC
HIG
AN
SE
WA
GE
L
AG
OO
N/P
UM
P S
TA
TIO
N IM
PR
OV
EM
EN
TS
MAR 2018
834310
2125 Ridgewood Dr, Suite 101
P: 989.837.3280
F: 989.837.3290
Midland, MI 48642
DESIG
N. BU
ILD. O
PERATE.
3
AD
DE
ND
UM
N
O. 3
04/12/18
DJD
2
Know what's below.before you dig.Call
R
MB
LPA
MCB
RELOCATE EXISTING 480 VOLT,
3Ø, 4W UNDERGROUND SERVICE.
METER BASE
(MB)
SINGLE LINE DIAGRAM
C
N
E
150A 3P
G
70 KW GENERATOR
NG
FORCE MAIN, FOUNDATION STEEL, (2) ELECTRODES
150 AMP
AUTOMATIC
TRANSFER
SWITCH(ATS)
U
1
1 #6, 3/4" C.
MAIN CIRCUIT
BRAKER (MCB)
ISOLITE ELS-24-125-2TM-LED
w/SURELIGHT WG7
BACKUP CONTROL ON
LOSS OF POWER/PHASE
PUMP 1 ON
10
HIGH LEVEL ALARM
LOW LEVEL ALARM
42 3
1
VOLTAGE
MAIN C.B.
BUS SIZE
DESCRIPTION
OUTSIDE LIGHT
OUTSIDE RECEPTACLE
19
23
21
20
20
17
15
13
11
7
9
3
5
1
1 180
CONTROL RM. RECEPTACLES
TOTALS
2
PUMP CONTROL PANEL
4
LTS.
SURFACE ENCLOSURE
LOAD CENTER
LOCATION
20
AMPSNO.
1
POLES
CIRCUIT
1
VA
50
CONTROL RM LIGHTS
BUILDING
OUTLETS
REC. OTHER
"LP-A"
DESCRIPTION
VOLT AMP.
ØA ØB
180
20
24
22
18
16
14
12
1 20
10
8
4
6
POLES
120/208, 3Ø
40 AMP
REC.
OUTLETS
LTS.
7
OTHER
VA
50
AMPS
CIRCUIT
1 20
100 AMP
NO.
2
1
550
230
3010 1330
MAIN CONTROL PANEL
100
20
1 1000
1180
GEN BLOCK HEATER
201
1
6
3'-0" MAX.
5
5'-0" (T
YP
.)
PUMP CONTROL PANEL (PCP) LAYOUT
NOTE:
CONTROL PANEL DRAWING SHOWN IS CONCEPTUAL. CONTRACTOR RESPONSIBLE FOR DIMENSIONED
CONTROL PANEL DOOR AND SUBPANEL LAYOUT. THESE LAYOUTS SHALL BE PROVIDED AS PART OF
THE CONTROL PANEL SUBMITTAL TO THE ENGINEER FOR APPROVAL. REFER TO SPECIFICATIONS
FOR ADDITIONAL CONTROL PANEL REQUIREMENTS. CONTRACTOR MAY FURNISH WALL MOUNT
ENCLOSURE OR FLOOR MOUNT AS SHOWN IN LAYOUT.
9
1"x3" WHITE w/ 3/16" BLACK LETTERING
1
3
2
5
4
6
8
7
HMI
NAME PLATE LIST
13
7
10
NEMA 1
PUMP 2 OVERTEMPERATURE ALARM
PUMP 1 OVERTEMPERATURE ALARM
PUMP 2 ON
12"
98
11 12
PUMP 1 HOA
PUMP 2 HOA
13
12
11
BACKUP CONTROL ON-OFF
EXTERIOR ALARM LIGHT TEST
14ALARM RESET
14
1100
4
CONDUIT AND WIRE SCHEDULE
CONDUCTORCONDUIT CONDUIT
NOTES
REF. QTY.QTY.
SIZE
A
(6) #14 & 1 #14 GND
1 3/4"
B
(1) 18/2 SH/TW/PR
1 3/4"
C MFR. STANDARD CORD 1 AS SHOWN AS REQUIRED
D
(2) 18/2 SH/TW/PR
1 3/4"
E
(2) #14 & (1) #14 GND
1 3/4"
F
(3) #14 & (1) #14 GND
1 3/4"
G
(4) #14 & (1) #14 GND
1 3/4"
H
(5) #14 & (1) #14 GND
1 3/4"
I
(7) #14 & (1) #14 GND
1 3/4"
J
(2) #12 & (1) #12 GND
1 3/4"
K
(3) #12 & (1) #12 GND
1 3/4"
L
(4) #12 & (1) #12 GND
1 3/4"
M
(3) #10 & (1) #10 GND
1 3/4"
N
(3) #8 & (1) #10 GND
1 1"
O
(3) #2 & (1) #6 GND
1 1-1/4"
P
(4) #10 & (1) #10 GND
1 3/4"
Q(2) #10 & (1) #10 GND
1 3/4"
R
(3) 1/0 & (1) #6 GND
1 2"
S
(4) #6 & (1) #6 GND
1 1-1/4"
T PULL STRING 1 2" SPARE
U
(4) 1/0 & (1) #6 GND
1 2"
R
CB2
SECONDARY
SURGE
ARRESTOR
MAIN DISTRIBUTION PANEL (MDP) 480 VOLT - 225 AMP BUS - 30 CKT.
20
PUMP 1
CB4
20A
3P
LP-A
XFA
480-120/208
15 KVA
SPACE
(TYP.)
VFD 1
MLO
M
SSA
N
J
N
20
PUMP 1
VFD 2
N
J
N
CB1
30A
3P
7
S
M
CB3
7
CB5
20A
3P
UH-1
K
ATSMDP SSA
XFA
PCP
PUMP 2
VFD
PUMP 1
VFD
LEVEL CONTROL JUNCTION BOX.
SEE DETAIL, SHEET E02
MOTOR LEAD JUNCTION BOX 1 & 2.
SEE DETAIL, SHEET E02
WET WELL, NEC CLASS 1,
DIV.1, GROUP D
HAZARDOUS AREA
5
OVER DOOR
EXTERIOR MOUNT120V LED WALL PAK w/PHOTO CELL AND25250MCGRAW EDISON
ISS-FO2-LED-E1-BL3-BZ-P120-CWB120
COLD WEATHER BATTERY BACK UP
6CEILING MOUNT480 VOLT, THREE PHASE 7.5 KW
7500QMARK MUH 074 w/CEILING MOUNT
BRACKET
FORCED AIR ELECTIC HEATER
7WALL MOUNT
DIGITAL WALL THERMOSTATQMARK TH114A24DBA
6
6
6
R
O
6
6 6
6
50
1
ØC
1080
200
200
1280
GEN RECPTACLE
GEN BATT CHARGER
GATE OPERATOR
-
180 1 20
100 1 20
200 1 20
200 1 20
1
1
4
6
6
6
CONDUITS TO WET WELL
SHEET NOTES:
1 ALL PUMP CONTROL PANEL CONTROL COMPONENTS
FOR LEVEL CONTROLLER, BACK UP CONTROL, PUMP
UTILITIES AND EXTERIOR ALARM LIGHT CIRCUITS SHALL
BE IN NEMA 1 ENCLOSURE.
2 REFER TO ALL DIVISION 26 ELECTRICAL SPECIFICATIONS
FOR ADDITIONAL REQUIREMENTS.
3 SIZE BREAKER TO VFD INPUT.
4 SIZE VFD TO MOTOR HORSEPOWER.
5 NEMA 1 ENCLOSED
6 SHIP PUMP CONTROL PANEL PHASE MONITOR AND VFDS
LOOSE FOR INSTALLATION BY CONTRACTOR.
N
L1
120 VAC FROM LPA
BACK-UP LEVEL CONTROL SYSTEM
LEVEL CONTROL POWER SUPPLY
EXTERIOR ALARM LIGHT CIRCUIT
CABINET GFI CONVENIENCE RECEPTACLE
PUMP CONTROL PANEL CONTROL POWER DISTRIBUTION
PUMP UTILITIES POWER SUPPLY
2
FLOWMETER
HIGH LEVEL
ALARM RELAY
INTRINSICALLY
SAFE RELAY
INTRINSICALLY
SAFE RELAY
ISR2ISR1
LOW LEVEL ALARM
FLOAT/BACK-UP
PUMP OFF
CR1
SET @ 60 SEC
120 VAC
L2L1
LOW LEVEL
ALARM TIMER
0-10 MINUTES
SET @ 1 MIN
R
LOW LEVEL
ALARM RELAY
LOW LEVEL
ALARM
TR2
0-600 SEC.
HIGH LEVEL ALARM
FLOAT/BACK-UP
PUMP ON
BACK-UP
CONTROL START
RELAY
BACK-UP CONTROL
SYSTEM ON
R
HIGH LEVEL
ALARM
R
TR1
0-600 SEC.
DELAY LAG
BACK-UP PUMP
SET @ 15 SEC
TR2
PUMP CONTROL PANEL BACK UP LEVEL CONTROL WIRING DIAGRAM
1 2
HIGH LEVEL
ALARM TIME
DELAY RELAY
AR1
OFFON
BACK- UP CONTROL
480 VAC
FROM MDP
100%
SPEED C
x
START
VFD
x
HAND
OFF
AUTO
x
x
PUMP 1
VFD - CONSTANT TORQUE
KEYPAD ON VFD 1 CABINET DOOR
RUN
INPUT
4-20 MA
VFDVFD
FAULT
JB
FROM
CONTROL
FROM
CONTROL
TO
CONTROL
TO
CONTROL
TO
CONTROL
3
54
L1
L2
L3
EMERGENCY BY-PASS
NORMAL BYPASS
x
x
BY-PASS
EMERGENCY
MOTOR
CURRENT
MONITOR TO
CONTROL
REACTOR
FROM BACK UP
CONTROL
100%
SPEED C
x
START
VFD
x
HAND
OFF
AUTO
x
x
PUMP 2
KEYPAD ON VFD 1 CABINET DOOR
RUN
INPUT
4-20 MA
VFDVFD
FAULT
JB
FROM
CONTROL
FROM
CONTROL
TO
CONTROL
TO
CONTROL
TO
CONTROL
3
L1
L2
L3
EMERGENCY BY-PASS
NORMAL BYPASS
x
x
BY-PASS
EMERGENCY
MOTOR
CURRENT
MONITOR TO
CONTROL
REACTOR
FROM BACK UP
CONTROL
20
TO LOSS OF PHASE /
VOLTAGE ALARM
1A
1A
1A
3 PHASE
MONITOR
RELAY
(PMR)
MONITOR
3 PHASE
RELAY
3#12 & 1#12GND
5
TO LOSS OF PHASE /
VOLTAGE ALARM
FIT
F&V PROJECT NO.
DESIGN TEAM:
DRAWING INFORMATION:
CHECK BY:
REVISION:
CIT
Y O
F C
OL
EM
AN
MID
LA
ND
C
OU
NT
Y, M
IC
HIG
AN
SE
WA
GE
L
AG
OO
N/P
UM
P S
TA
TIO
N IM
PR
OV
EM
EN
TS
MAR 2018
834310
2125 Ridgewood Dr, Suite 101
P: 989.837.3280
F: 989.837.3290
Midland, MI 48642
DESIG
N. BU
ILD. O
PERATE.
3
AD
DE
ND
UM
N
O. 3
04/12/18
DJD
2
480 VAC
FROM MDP
480 VAC
FROM MDP
20
6
VFD - CONSTANT TORQUE
54 6
834310-Coleman Ice-E04
050118 dand
PU
MP
S
TA
TIO
N W
IR
NG
D
IA
GR
AM
INITIALS
E04
834310-Coleman Ice-E05
050118 douglass
PU
MP
S
TA
TIO
N W
IR
IN
G D
IA
GR
AM
GOB/DRS/DJD2
E05
SHEET NOTES:
1 REFER TO ALL DIVISION 26 ELECTRICAL SPECIFICATIONS
FOR ADDITIONAL REQUIREMENTS.
2 FUSES SHOWN TO BE SIZED BY CONTROL PANEL
SUPPLIER.
1
LEVEL CONTROL WIRING DIAGRAM
2 3
DO5
DO3
DO4
DO1
DO0
N
G
L
DO2COMMON ALARM
RELAY
DI2
DI3
CR2
CR3
DI6
DI7
DI8
PMR
DI5
DI4
DI1
DI0
PUMP 1 ON
PUMP 2 ON
PUMP 1
OVERTEMP
PUMP 2
OVERTEMP
3 PHASE
MONITOR
S
AI3
AI3
S
-
+
ISB
MFG. CABLE
SH
-
+
SUBMERSIBLE
PRESSURE
TRANSDUCER
SA
SH
-
+
S
-
+
LEVEL
CONTROLLER
SH
AI4-
AI4+
FLOWMETER
AR4
AR5
AR6
AR7
PUMP 1 SEAL
FAIL
PUMP 2 SEAL
FAIL
AR2
LOW LEVEL
ALARM FLOAT
+
-
PUMP 1
CALLED TO
STARTER
AR4
CR4CR1
PUMP 2
CALLED TO
STARTER
AR5
TR2
0-600CR5
SEC
LOSS OF PHASE
ALARM RELAY
P1HT
1SFR
PUMP 1 OVER TEMP
ALARM RELAY
LOSS OF PHASE
ALARM RELAY
PUMP 1 OVER
TEMP ALARM
PUMP 2 OVER
TEMP ALARM
AR5
AR4
P2HT
PUMP 2 OVER TEMP
ALARM RELAY
2SFR
PUMP 1 SEAL FAIL
ALARM RELAY
PUMP 1 SEAL
FAIL ALARM
PUMP 2 SEAL FAIL
ALARM RELAY
PUMP 2 SEAL
FAIL ALARM
R
R
R
R
R
PUMP CONTROL PANEL PUMP UTILITIES WIRING DIAGRAM
VFD AUX
VFD AUX
120 VAC
L2L1
AR2
AR1
AR3
TEST
EXTERIOR
ALARM LIGHT
120 VAC
NL1
R
AR8
PUMP CONTROL PANEL EXTERIOR ALARM LIGHT WIRING DIAGRAM
PUMP 1 RUN
INDICATION RELAY
PUMP 2 RUN
INDICATION RELAY
1 2
1
PMR
DI9
VFD1
VFD2
PUMP 1
FAULT
PUMP 2
FAULT
DI10
DI11
1AUTO AUX
2AUTO AUX
PUMP 1
IN AUTO
PUMP 2
IN AUTO
DI12
CR1
BACKUP
CONTROL ON
D13
AR1
HIGH LEVEL
ALARM FLOAT
PUMP 2
START
PUMP 1
START
3
PUMP 1
AMPS
AI1+
AI1-
SH
AI2+
AI2-
SH
PUMP 2
AMPS
F&V PROJECT NO.
DESIGN TEAM:
DRAWING INFORMATION:
CHECK BY:
REVISION:
CIT
Y O
F C
OL
EM
AN
MID
LA
ND
C
OU
NT
Y, M
IC
HIG
AN
SE
WA
GE
L
AG
OO
N/P
UM
P S
TA
TIO
N IM
PR
OV
EM
EN
TS
MAR 2018
834310
2125 Ridgewood Dr, Suite 101
P: 989.837.3280
F: 989.837.3290
Midland, MI 48642
DESIG
N. BU
ILD. O
PERATE.
3
AD
DE
ND
UM
N
O. 3
04/12/18
DJD
2
COM
+12VDC-12VDC
GND
BATTERY
GND
DOOR MOUNTED DISPLAY(HMI)
COM
L1N
GND
24VDC PS
+24VDC- 24VDC
+12VDC-12VDC
GND
BATTERY
OMNI
DIRECTIONAL
ANTENNA
SURGE
ARRESTOR
ANTENNA
CABLE
+24VDC- 24VDC
GND
COM
+24VDC- 24VDC
CELULAR MODEM
ANT
COM
120 VAC
NL1
L1N
GND
TVSS
2
5
SH
A0-
A0+
PUMP 1
SPEED REFERENCE
SH
A1-
A1+
PUMP 2
SPEED REFERENCE