+ All Categories
Home > Documents > SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated...

SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated...

Date post: 10-Apr-2018
Category:
Upload: vothuan
View: 213 times
Download: 1 times
Share this document with a friend
58
BASIC ASSESSMENT REPORT (For official use only) Application Number: Date Received: Basic assessment report in terms of the Environmental Impact Assessment Regulations, 2010, promulgated in terms of the National Environmental Management Act, 1998 (Act No. 107 of 1998), as amended. Kindly note that: 1. This basic assessment report is a standard report that may be required by a competent authority in terms of the EIA Regulations, 2010 and is meant to streamline applications. Please make sure that it is the report used by the particular competent authority for the activity that is being applied for. 2. The report must be typed within the spaces provided in the form. The size of the spaces provided is not necessarily indicative of the amount of information to be provided. The report is in the form of a table that can extend itself as each space is filled with typing. 3. Where applicable tick the boxes that are applicable in the report. 4. An incomplete report may be returned to the applicant for revision. 5. The use of “not applicable” in the report must be done with circumspection because if it is used in respect of material information that is required by the competent authority for assessing the application, it may result in the rejection of the application as provided for in the regulations. 6. This report must be handed in at offices of the relevant competent authority as determined by each authority. 7. No faxed or e-mailed reports will be accepted. 8. The report must be compiled by an independent environmental assessment practitioner. 9. Unless protected by law, all information in the report will become public information on receipt by the competent authority. Any interested and affected party should be provided with the information document.docx 1
Transcript
Page 1: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

(For official use only)

Application Number:Date Received:

Basic assessment report in terms of the Environmental Impact Assessment Regulations, 2010, promulgated in terms of the National Environmental Management Act, 1998 (Act No. 107 of 1998), as amended.

Kindly note that:

1. This basic assessment report is a standard report that may be required by a competent authority in terms of the EIA Regulations, 2010 and is meant to streamline applications. Please make sure that it is the report used by the particular competent authority for the activity that is being applied for.

2. The report must be typed within the spaces provided in the form. The size of the spaces provided is not necessarily indicative of the amount of information to be provided. The report is in the form of a table that can extend itself as each space is filled with typing.

3. Where applicable tick the boxes that are applicable in the report.

4. An incomplete report may be returned to the applicant for revision.

5. The use of “not applicable” in the report must be done with circumspection because if it is used in respect of material information that is required by the competent authority for assessing the application, it may result in the rejection of the application as provided for in the regulations.

6. This report must be handed in at offices of the relevant competent authority as determined by each authority.

7. No faxed or e-mailed reports will be accepted.

8. The report must be compiled by an independent environmental assessment practitioner.

9. Unless protected by law, all information in the report will become public information on receipt by the competent authority. Any interested and affected party should be provided with the information contained in this report on request, during any stage of the application process.

10. A competent authority may require that for specified types of activities in defined situations only parts of this report need to be completed.

document.docx 1

Page 2: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

SECTION A: ACTIVITY INFORMATION

Has a specialist been consulted to assist with the completion of this section?

YES

If YES, please complete the form entitled “Details of specialist and declaration of interest”for appointment of a specialist for each specialist thus appointed:Any specialist reports must be contained in Appendix D.

1. ACTIVITY DESCRIPTION

Describe the activity, which is being applied for, in detail1:The proposed Roodepoort Strengthening Project involves the construction of 2 x 400kV power lines of approximately 30km long from existing Apollo-Pluto 400kV power line to a new 400/88kV Demeter Main Transmission Station (MTS).

The scheme is required in order to increase the security and reliability of electricity supply to meet the increasing needs for existing Eskom customers and to make provision for the projected increasing demand in the coming years,

In addition to the construction of the lines themselves, Eskom Holdings SoC Limited (Eskom) (“the applicant”) proposes to construct a 400/88kV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under pressure as a result of demand growth. The new substation and transmission line is needed to strengthen the network in the Load Centre including Cosmo City and the surrounding area. The strengthening project is considered to be vital infrastructure in the context of priority growth plans in this area that include township projects and extensions, industrial expansion and employment growth as well as increased demand from existing occupiers and landowners.

In summary, the proposed project will consists of the following:

The total area studied as part of this BAR is 132km².

As notes previously this includes 6 corridor options as follows:

Option 1- 14.54km2

Option 2- 20.99km2

Option 3- 14.83km2

Option 4- 17.57km2

Option 5- 15.05km2

Option 6 – 14.93km2

Servitude size

Although the study area has included a 1km wide corridor for the full length of the proposed infrastructure, the actual width of the servitude will only be 110m (55m either side of the centre of the power line). The study has been carried out in this way to ensure thoroughness of study as well as allowing the flexibility to define the precise location of 1 Please note that this description should not be a verbatim repetition of the listed activity as contained in the relevant Government Notice, but should be a brief description of activities to be undertaken as per the project description.

document.docx 2

Page 3: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

towers in consultation with landowners as well as taking into account any mitigation measures recommended in this BAR.

Transmission Power Line Specifications

2x400kV Transmission power lines looping in and out from the existing 400kV Pluto – Apollo transmission power line.

Double or single circuit power lines.

Span form pylon to pylon is 300 to 350m.

Pylon design is based on the use of cross rope type towers with self supporting structures on bends.

Six substation options have been assessed.

Substation A is located on Portion 2 of the farm Nietgedacht 535 JQ and Portion 4 & RE 36 of Zandspruit 191 IQ

Substation B is located on Portions 42, 56, 67, 105 and 121 of the farm Zandspruit 191 IQ

Substation C is located on Portion 49 and 305 of the farm Rietfontein 189 IQ and on Portion R and 3 of farm Whitestones 188 IQ

Substation D is located on Portions 22, 68 and 69 of Farm Nietgedacht 535JQ

Substation E is located on Portion 58, 59 and the remainder of the Farm Bulfontein 533 JQ

Transmission Substation Specifications

3x 315 MVA; 400/88 KV Demeter Substation.

Substation size = 500m x 500m (25ha)

1x Telecommunication tower

1x Oil dam

1x Access road to the proposed substation

2. FEASIBLE AND REASONABLE ALTERNATIVES

“alternatives”, in relation to a proposed activity, means different means of meeting the general purpose and requirements of the activity, which may include alternatives to—(a) the property on which or location where it is proposed to undertake the activity;(b) the type of activity to be undertaken;(c) the design or layout of the activity;(d) the technology to be used in the activity;(e) the operational aspects of the activity; and

document.docx 3

Page 4: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

(f) the option of not implementing the activity.

Describe alternatives that are considered in this application. Alternatives should include a consideration of all possible means by which the purpose and need of the proposed activity could be accomplished in the specific instance taking account of the interest of the applicant in the activity. The no-go alternative must in all cases be included in the assessment phase as the baseline against which the impacts of the other alternatives are assessed. The determination of whether site or activity (including different processes etc.) or both is appropriate needs to be informed by the specific circumstances of the activity and its environment. After receipt of this report the competent authority may also request the applicant to assess additional alternatives that could possibly accomplish the purpose and need of the proposed activity if it is clear that realistic alternatives have not been considered to a reasonable extent.

2(a) Substation Site alternatives:

Describe site alternative A (S1), for the activity described above, or for any other activity alternative:Substation A is located on Portion 2 of the farm Nietgedacht 535 JQ and Portion 4 & RE 36 of Zandspruit 191 IQ. The proposed substation site is currently part of the existing Lion Park, approximately 1.8 km east of the N14 adjacent to two main roads namely Malibongwe Dr and the R114. It’s positioned between smallholdings at Nooitgedacht to the west, Cosmo City to the south, Farmall agricultural holding on the east and Millgate and Chartwell to the North. It is approximately 2.8 km west of the nearest water course, the Klein-JukskeiRivier. It is expected that the access road to the substation would be off either Malibongwe Drive or the R114.

Describe site alternative B (S2), if any, for the activity described above, or for any other activity alternative:Substation B is located on Portions 42, 56, 67, 105 and 121 of the farm Zandspruit 191 IQ. The proposed substation is near Zandspruit informal settlement in Mogale City and is approximately 1.5 km east of Beyers Naude Drive and 1km south of the Dalkeith 88/11kV distribution substation. The proposed substation is positioned south of Cosmo City, north of Zandspruit, 3.5km west of Northgate. Access to the substation would be from Marina Street.

Describe site alternative C (S3), if any, for the activity described above, or for any other activity alternative:Substation C is located on Portion 49 and 305 of the farm Rietfontein 189 IQ and on Portion R and 3 of farm Nooitgedacht 534 IQ. The proposed substation is situated 1.8km south of the N14 and it is approximately 1km east of an existing main road (Beyers Naude Drive), adjacent to a planned Demeter 88kV substation in Mogale City Local MunicipalityThe proposed substation is located approx 3km west of Cosmo City and 4km west of Muldersdrif se loop river. Access to the substation would be via Beyers Naude Drive.

Describe site alternative D (S4), if any, for the activity described above, or for any other activity alternative:Substation D is located on Portions 22, 68 and 69 of Farm Nietgedacht 535JQ. The proposed substation is surrounded by a number of main roads including next to Cedar/6 th road with the N14 to the north and R114 on its south. It in the centre of two distribution substation; approx 1.5 west the planned Ithuba 88kv and 3.5km east of the Charwell 88/11kv substations. The nearest water courses lies approx 2.5km north (Jukskei River) and 1.5 km east (Klein-Jukskeirivier) of the proposed substation. The access road would come off either Cedar Road or the R114.

Describe site alternative E (S4), if any, for the activity described above, or for any other activity alternative:

document.docx 4

Page 5: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

Substation E is located on Portion 58, 59 and the remainder of the Farm Bulfontein 533 JQ. The proposed substation next to the planned Ithuba 88kv distribution substation, about 5km north of the Load Centre (Cosmo City and surroundings) and approx 3km south of the Lanseria Airport. It is also situated less than 1km east of the R512 (Malibogwe dr) adjacent to an existing main road (6th/Cedar rd) from which the access road would be constructed.

Route alternatives Describe route alternative 1 (R1), for the activity described above, or for any other activity alternative:Route alternative 1 is approximately 1km long connecting from the existing 400kV Apollo-Pluto heads southerly on farm Rietfontein 532 JQ (Diepsloop Nature Reserve) following the existing Klevebank/Lomond 88kV distribution line, crossing the N14 highway and the R144 main road then the Jukskei River. The proposed line then turns west following the existing 88kV distribution line on the northern boundary of the Chartwell Agricultural Holdings, then turns south following the Klein-Jukskei River and the existing 88kV distribution line. It then heads south-west still following the existing distribution line, it eventually runs over the northern boundaries of both portion 22 and 23 of Nietgedacht 535 JQ to join the R144 main road. It follows this road southerly up to R512 (Malibongwe Drive) into the proposed substation A at the Lion Park. This route can terminate at either substation D or A however for assessment purposes the longer of the two options (terminating at substation A) has been used to ensure the assessment of a ‘worst case scenario’.

Describe route alternative 2 (R2), if any, for the activity described above, or for any other activity alternative:Route alternative 2 is approximately 20km long connecting from the existing 400kV Apollo-Pluto line. It runs south on the eastern boundary of the farm Rietfontein 532 JQ following the existing 400kV transmission line then it crosses the N14 highway following a westerly turn to join the R144. It then turns south crossing the Jukskei River following the existing Klevebank/Lomond 88kV distribution line. The proposed line then turns west following the existing 88kV distribution line on the northern boundary of the Chartwell Agricultural Holdings, then makes a southerly turn following the Klein-Jukskei River and the exising 88kV distribution line., It then heads south-west still following the existing distribution line past the easterly boundary of Millgate and western boundary of Farmall agricultural holdings. The proposed line can terminate at the proposed substation D, A or continue following the existing distribution line southerly on western boundary of Cosmo City into the proposed substation B. For assessment purposes, the longest route terminating at substation B has been used.

Describe route alternative 3 (R3), if any, for the activity described above, or for any other activity alternative:Route alternative 3 line is approximately 15km long connecting from the existing 400kV Apollo-Pluto on the southern side of the farm Tweefontein 523 JQ running south-westerly in the middle of farm Zwartkop 525JQ crossing the Crocodile River then a 88kv distribution line (Crocodile/Lanseria). It then joins a main road (Beyers Naude Drive) running in a southerly direction for approx 2.5 km. The proposed line then turn west towards the eastern boundary of the farm Driefontein 179 IQ, follows the boundary for 1km before turning in a south-easterly direction back onto Beyer Naude Drive for 1.2km then making a easterly turn into the proposed substation C.

Describe route alternative 4 (R4), if any, for the activity described above, or for any other activity alternative:

document.docx 5

Page 6: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

Route alternative 4 is approximately 17km long connecting from the existing 400kV Apollo-Pluto on the western area of the farm Rietfontein 532 JQ heading in a south-easterly direction crossing an existing 88kV distribution line (Lanseria/Tee). At the southern boundary of the Reitfontein farm the line then turns south west, crossing the N14 and running to the east of R144. The line then crosses over to the west of R114 (to avoid Thabo Mbeki Informal Settlement) running parallel to the N14 for approximately 7km. This alternative coul;d use either substation option D or C however for assessment purposes the longer of the two has been used, thus connecting with substation option C.

Describe route alternative 5 (R5), if any, for the activity described above, or for any other activity alternative:Proposed route 5 is approx 15km in length; it will connect to the Apollo – Pluto 400KV lines on the farm Lindley 528JQ. The lines will run underground though the farms Lindley 528JQ, Bultfontein 533 JQ. At 6th Road the lines will emerge on the farm Bultfontein 533LQ. The lines will then loop in/out at substation E on the farm Bultfontein 533JQ. Alternatively the overhead lines can proceed south-westerly through Nooitgedaght 524 IQ to substation C on Rietfontein 189 IQ portion 49 and 305 and portion 3 & remainder of Whitestone 188 IQ connecting with substation option C which has been used for assessment purposes.

Describe route alternative 6 (R6), if any, for the activity described above, or for any other activity alternative:Route alternative 6 power lines is approx 15km long, it will connect to the Apollo – Pluto 400kV lines on Lindley 528JQ following an existing main road (Beyers Naude Drive) in a southerly direction crossing an existing 88kV distribution line and the N14 highway, 2km after the highway it eventually turns east into substation C on Rietfontein 189 IQ portion 49 and 305 and portion 3 & remainder of Whitestone 188 IQ. This route would terminate at substation option C.

(2)(b) Activity alternatives:

Describe activity alternative 2 (a), if any, for any or all of the site alternatives as appropriate:There are no feasible or viable alternatives to the proposed activities that would deliver the necessary upgrade/strengthening in this area.

Describe activity alternative 2 (A2), if any, for any or all of the site alternatives as appropriate:N/A

Describe activity alternative 2 (A2), if any, for any or all of the site alternatives as appropriate:N/A

Paragraphs 3 – 13 below should be completed for each alternative.

3. ACTIVITY POSITION

Indicate the position of the activity using the latitude and longitude of the centre point of the site for each alternative site. The co-ordinates should be in degrees and decimal minutes. The minutes should have at least three decimals to ensure adequate accuracy. The projection that must be used in all cases is the WGS84 spheroid in a national or local projection.List alternative sites, if applicable.

Latitude (S): Longitude (E):

document.docx 6

Page 7: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

Alternative:Alternative S12 (Substation A) 25 o 59.928‘ 27 o 56.054‘Alternative S2 (Substation B) 26 o 2.709‘ 27 o 54.608‘Alternative S3 (Substation C) 26 o 1.556‘ 27 o 52.928‘Alternative S4 (Substation D) 25 o 58.324‘ 27 o 56.805‘Alternative S5 (Substation E) 25 o 57.899‘ 27 o 55.582‘

In the case of linear activities:Latitude (S): Longitude (E):

Alternative Route 1 Starting point of the activity 25 o 54. 608‘ 27 o 57.525‘ Middle/Additional point of the activity 25 o 58.103’ 27 o 57.717‘ End point of the activity 25 o 59.831’ 27 o 55.503’Alternative Route 2 Starting point of the activity 25o 54.202’ 27o 58.998’ Middle/Additional point of the activity 25o 58.299’ 27o 57.346’ End point of the activity 26o 2.717’ 27o 54.641’Alternative Route 3 Starting point of the activity 25o 55.905‘ 27o 50.998‘ Middle/Additional point of the activity 25o 59.717’ 27o 51.394’ End point of the activity 26o 1.794’ 27o 52.849’Alternative Route 4 Starting point of the activity 25 o 54.849‘ 27 o 56.633‘ Middle/Additional point of the activity 25 o 58.762’ 27 o 55.758‘ End point of the activity 26o 1.494’ 27o 53.065’Alternative Route 5 Starting point of the activity 25o 55.242’ 27o 53.927’ Middle/Additional point of the activity 25o 58.600’ 27o 55.489’ End point of the activity 26o 1.494’ 27o 53.065’Alternative Route 6 Starting point of the activity 25o 55.428‘ 27o 53.017‘ Middle/Additional point of the activity 25o 58.996’ 27o 51.602’ End point of the activity 26o 1.794’ 27o 52.849’

For route alternatives that are longer than 500m, please provide an addendum with co-ordinates taken every 250 meters along the route for each alternative alignment. Please see Appendix G-1

4. PHYSICAL SIZE OF THE ACTIVITY

Indicate the physical size of the preferred activity/technology as well as alternative activities/technologies (footprints):Alternative: Size of the

activity (approx ha):

Alternative A13(Substation A) 287Alternative A2 (Substation B) 25Alternative A3 (Substation C) 25Alternative A3 (Substation D) 25Alternative A3 (Substation E) 25

2 “Alternative S..” refer to site alternatives.3 “Alternative A..” refer to activity, process, technology or other alternatives.

document.docx 7

Page 8: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

or, for linear activities:

Alternative:

Length of the activity(approx km):

Alternative A1 (Route 1) 19Alternative A2 (Route 2) 20Alternative A3 (Route 3) 14Alternative A3 (Route 4) 16Alternative A3 (Route 5) 14Alternative A3 (Route 6) 14

Indicate the size of the alternative sites or servitudes (within which the above footprints will occur):

Alternative:Size of the site/servitude:

Alternative A1 (Route 1) 110mAlternative A2 (Route 2) 110m Alternative A3 (Route 3) 110m Alternative A3 (Route 4) 110m Alternative A3 (Route 5) 110m Alternative A3 (Route 6) 110m

5. SITE ACCESS

Final locations and specifications of all access routes will be determined during design phase of the project. Descriptions below are only a guide and are subject to change.

Substation ADoes ready access to the site exist? YES NOIf NO, what is the distance over which a new access road will be built m

Describe the type of access road planned:

Malibongwe Drive passes through Site A in a West-East direction. This site can also be accessed via R512, which passes approximately 130m west of Site A.

Substation BDoes ready access to the site exist? YES NOIf NO, what is the distance over which a new access road will be built m

Describe the type of access road planned:

Marina Street passes a few meters (approximately 15m) west of Site B. This tar road can be used to access the site. There is also a secondary road that passes through the site that can be used for this purpose. The secondary road would need to be upgraded to a tar road approximately 6m wide.

Substation CDoes ready access to the site exist? NOIf NO, what is the distance over which a new access road will be built ~600m

Describe the type of access road planned:

document.docx 8

Page 9: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

Marina Street passes a few meters (approximately 15m) west of Site B. This tar road can be used to access the site. There is also a secondary road that passes through the site that can be used for this purpose. The secondary road would need to be upgraded to a tar road approximately 6m wide. Beyers Naude passes approximately 600m west of Site C. An access road approximately 600m long and 6m wide will need to be build from Beyers Naude to Site C. Alternatively, College Road, which passes through the site, can be upgraded to tar road.

Substation DDoes ready access to the site exist? YES NOIf NO, what is the distance over which a new access road will be built m

Describe the type of access road planned:

6th/Cedar Rd passes next to the site and could be used for access to the site.

Substation EDoes ready access to the site exist? YESIf NO, what is the distance over which a new access road will be built

Describe the type of access road planned:

6th/Cedar Rd passes approximately 10m south of Site E. This route could be used for access. There are several other routes around the site and another cutting through the site that could be upgraded for access.

Include the position of the access road on the site plan and required map, as well as an indication of the road in relation to the site. (Please see Appendix A)

6. SITE OR ROUTE PLAN

A detailed site or route plan(s) must be prepared for each alternative site or alternative activity. It must be attached as Appendix A to this document.

The site or route plans must indicate the following:6.1 the scale of the plan which must be at least a scale of 1:500;6.2 the property boundaries and numbers of all the properties within 50 metres of the site; 6.3 the current land use as well as the land use zoning of each of the properties adjoining the site or

sites; 6.4 the exact position of each element of the application as well as any other structures on the site; 6.5 the position of services, including electricity supply cables (indicate above or underground), water

supply pipelines, boreholes, street lights, sewage pipelines, storm water infrastructure and telecommunication infrastructure;

6.6 all trees and shrubs taller than 1.8 metres; 6.7 walls and fencing including details of the height and construction material; 6.8 servitudes indicating the purpose of the servitude; 6.9 sensitive environmental elements within 100 metres of the site or sites including (but not limited

thereto): rivers; the 1:100 year flood line (where available or where it is required by DWA); ridges; cultural and historical features; areas with indigenous vegetation (even if it is degraded or invested with alien species);

document.docx 9

Page 10: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

6.10 for gentle slopes the 1 metre contour intervals must be indicated on the plan and whenever the slope of the site exceeds 1:10, the 500mm contours must be indicated on the plan; and

6.11 the positions from where photographs of the site were taken.

(Please see Appendix A)

7. SITE PHOTOGRAPHS

Colour photographs from the centre of the site must be taken in at least the eight major compass directions with a description of each photograph. Photographs must be attached under Appendix B to this form. It must be supplemented with additional photographs of relevant features on the site, if applicable.

(Please see Appendix B)

8. FACILITY ILLUSTRATION

A detailed illustration of the activity must be provided at a scale of 1:200 as Appendix C for activities that include structures. The illustrations must be to scale and must represent a realistic image of the planned activity. The illustration must give a representative view of the activity.

(Please see Appendix C)

9. ACTIVITY MOTIVATION

9(a) Socio-economic value of the activity

What is the expected capital value of the activity on completion?RXXX

What is the expected yearly income that will be generated by or as a result of the activity?

R – Not yet known

Will the activity contribute to service infrastructure? YESIs the activity a public amenity? NOHow many new employment opportunities will be created in the development phase of the activity?What is the expected value of the employment opportunities during the development phase?

Unknown.

What percentage of this will accrue to previously disadvantaged individuals?How many permanent new employment opportunities will be created during the operational phase of the activity?What is the expected current value of the employment opportunities during the first 10 years?What percentage of this will accrue to previously disadvantaged individuals?

9(b) Need and desirability of the activity

Motivate and explain the need and desirability of the activity (including demand for the activity):

NEED:1. Was the relevant provincial planning department involved in the

application?YES

2. Does the proposed land use fall within the relevant provincial planning framework?

YES

document.docx 10

sheila, 2012-10-17,
Henry to give value
Page 11: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

3. If the answer to questions 1 and / or 2 was NO, please provide further motivation / explanation: N/A

DESIRABILITY:1. Does the proposed land use / development fit the surrounding area? YES2. Does the proposed land use / development conform to the relevant

structure plans, SDF and planning visions for the area?YES

3. Will the benefits of the proposed land use / development outweigh the negative impacts of it?

YES

4. If the answer to any of the questions 1-3 was NO, please provide further motivation / explanation: N/A

5. Will the proposed land use / development impact on the sense of place? YES6. Will the proposed land use / development set a precedent? NO7. Will any person’s rights be affected by the proposed land use /

development?YES

8. Will the proposed land use / development compromise the “urban edge”? YES9. If the answer to any of the question 5-8 was YES, please provide further motivation /

explanation. (5) A visual impact assessment which includes the concept of impacts on a ‘sense of place is included at Appendix D. It is noted in particular that part two of the proposed option encroach into the Cradle of Humankind World Heritage Site and therefore have the potential to significantly impact the sense of place associated with this internationally recognised heritage resource. Furthermore, parts of a number of the route options are characterised by game farms, nature conservation, agricultural activities (chicken, horse and vegetable farming), tourism industries, businesses and residential areas. Corridor 1 has the lowest overall visual sensitivity since it traverses mostly built-up and residential landscapes, while Corridor 3 is likely to have the highest since it traverses the largest areas of natural looking landscapes in the Cradle of Humankind. Corridor 3 should therefore be considered the ‘no-go’ option within the context of the study and the visual and cultural landscape. Substation site D is likely to have the highest overall visual sensitivity due to the surrounding landscape (which consists of a fair number of smallholdings with grassy areas in between them) while substation site A is likely to have the lowest as it is positioned close to industrial activities.

Many residents refer to a ‘country feel’ and it must be acknowledged that sensitive design and location of the proposed lines will be required to mitigate the impacts on these resources. With essential infrastructure such as that proposed there must be a balance between the perspectives of individuals and the national interest and for this reason the best possible alternative has been recommended, taking into account existing infrastructure and landscape character as well as the visual absorbtion capacity of given areas. It should however be acknowledged that the construction of transmission lines will have an impact on the sense of place in certain locations regardless of the mitigation measures employed.

(6) From an environmental perspective, it is usually preferable that new infrastructure should be placed close to existing infrastructure thereby limiting the impact of the new power lines to an area already disturbed by such developments. The study area has already been altered due to the existing infrastructure and the extent of the impact of the new infrastructure will be limited or absorbed to some degree by the existing

document.docx 11

Page 12: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

impacts. Areas that are devoid of infrastructure should be avoided where possible. Experience has shown that routing power lines in this manner generally achieves the least impact solution. With this in mind, the construction of transmission lines will set a precedent for the development of future linear infrastructure in the area, such as roads, railway lines, other transmission line projects, or pipelines. (7) The proposed transmission line will be mostly located on privately owned land, thus impacting on the rights of certain individuals owning the land in the area. Eskom will have to reach agreements with all affected land owners to decide upon appropriate compensation measures.

(9) Parts of the proposed development fall outside the urban edge, into the urban-rural transition zone. According to Mogale SDF 2011, these areas typically comprise low density urban development, low intensity, extensive land uses and semi-rural activities such as nurseries. The urban edge should therefore not denote a clear divide between urban and rural, but rather include management zones along the edge that make provision for a gradual transition from an urban to a rural environment. The area directly inside the urban edge should look at lower urban intensities, while the areas directly outside the urban edge should make provision for semi-rural and rural residential activities.

In this regard, the area that presents the most meaningful opportunity for future development is the area to the east of the N14, between Hendrik Potgieter Road in the south and the R512 in the north. This section of the N14 is seen as one of the next major provincial development corridors, spurred on by the development proposals currently taking shape around Lanseria Airport.

BENEFITS:1. Will the land use / development have any benefits for society in general? YES2. Explain:

Ensuring adequate future electricity supply and ensuring reliability of demand form the cornerstones of Eskom’s corporate objectives as well as those of government. The proposed development will be a factor on delivering against these key aims. Without such upgrades related projects such as the provision of low cost housing and the growth of local and regional industry cannot go forward. Therefore there are both direct and indirect benefits to society as a whole resulting from the proposed development and developments like it.

3. Will the land use / development have any benefits for the local communities where it will be located?

YES

4. Explain: At a local level, the upgrade will provide greater reliability of supply as well as provision for future needs thereby reducing stress on the network. The development will support the provision of low cost housing for local residents as well as growth and growth potential for local industry. Job creation and improved housing is a key factor in societal uplift for local communities and therefore such schemes provide a directly attributable benefit for local communities.

10. APPLICABLE LEGISLATION, POLICIES AND/OR GUIDELINES

List all legislation, policies and/or guidelines of any sphere of government that are applicable to the application as contemplated in the EIA regulations, if applicable:

document.docx 12

Page 13: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

Title of legislation, policy or guideline: Administering authority: Date:National Environmental Management Act, 1998 (Act 107 of 1998) (NEMA)

Provincial & National 27 November 1998

National Environmental management Act, Environmental Impact Assessment Regulations (as amended) 2010 (including listing notices)

Provincial and National 18th June 2010 (corrected 10th

December 2010)National Water Act 36 of 1998 Provincial & National 1998National Environmental Management: Air Quality Act 39 of 2004

Local February 2005

National Environmental Management: Biodiversity Act 10 of 2004

Provincial & National June 2004

National Environmental Management: Waste Act 59 of 2008

Provincial & National April 2009

National Heritage Resources Act 25 of 1999 Provincial & National April 1999

11. WASTE, EFFLUENT, EMISSION AND NOISE MANAGEMENT

11(a) Solid waste managementWill the activity produce solid construction waste during the construction/initiation phase?

YES

If yes, what estimated quantity will be produced per month? Estimated 15600Kg per month)

How will the construction solid waste be disposed of (describe)?The construction waste will be transported via waste dump truck to a registered landfill site. The exact quantity of waste produced is not known at this stage.Where will the construction solid waste be disposed of (describe)?The construction waste will be disposed at the nearest landfill site i.e. Marie Louise landfill site in the Roodepoort area.Will the activity produce solid waste during its operational phase? YESIf yes, what estimated quantity will be produced per month? 300kg/monthHow will the solid waste be disposed of (describe)?Municipal Waste StreamWhere will the solid waste be disposed if it does not feed into a municipal waste stream (describe)?N/AIf the solid waste (construction or operational phases) will not be disposed of in a registered landfill site or be taken up in a municipal waste stream, then the applicant should consult with the competent authority to determine whether it is necessary to change to an application for scoping and EIA.Can any part of the solid waste be classified as hazardous in terms of the relevant legislation?

NO

If yes, inform the competent authority and request a change to an application for scoping and EIA. Is the activity that is being applied for a solid waste handling or treatment facility?

NO

If yes, then the applicant should consult with the competent authority to determine whether it is necessary to change to an application for scoping and EIA.

11(b) Liquid effluent

Will the activity produce effluent, other than normal sewage, that will be disposed of in a municipal sewage system?

NO

If yes, what estimated quantity will be produced per month?

document.docx 13

tsepo, 2012-10-25,
Henry…
tsepo, 2012-10-25,
Henry..
Page 14: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

Will the activity produce any effluent that will be treated and/or disposed of on site?

NO

If yes, the applicant should consult with the competent authority to determine whether it is necessary to change to an application for scoping and EIA. Will the activity produce effluent that will be treated and/or disposed of at another facility?

NO

If yes, provide the particulars of the facility:Facility name: N/AContact person:Postal address:Postal code:Telephone: Cell:E-mail: Fax:Describe the measures that will be taken to ensure the optimal reuse or recycling of waste water, if any:

11(c) Emissions into the atmosphere

Will the activity release emissions into the atmosphere? YESIf yes, is it controlled by any legislation of any sphere of government? NOIf yes, the applicant should consult with the competent authority to determine whether it is necessary to change to an application for scoping and EIA. If no, describe the emissions in terms of type and concentration:During the construction phase, it is expected that there will be short term dust generation and emissions from vehicles and machinery. However the dust and emissions will have a medium to short term duration and have a limited impact on the very immediate surrounding rural areas. Where appropriate dust suppression measures will be implemented to reduce the impacts. It is recommended that construction vehicles be serviced and kept in good mechanical condition to minimise possible exhaust emission.

11(d) Generation of noise

Will the activity generate noise? YESIf yes, is it controlled by any legislation of any sphere of government? NOIf yes, the applicant should consult with the competent authority to determine whether it is necessary to change to an application for scoping and EIA. If no, describe the noise in terms of type and level:Short term noise impacts are anticipated during the construction phase of the project. It is however anticipated that the noise will be localised and contained within the construction site.In order to minimise the impacts of noise during the construction phase, construction activities should be restricted to between 07H00 and 17H00 Monday to Friday, and 8h00-13h00 on Saturdays. This is required to avoid noise disturbances outside normal working hours. All construction equipment must be maintained and kept in good working order to minimise associated noise impacts. The applicant must adhere to the relevant provincial noise control legislation (if any) as well as SANS 10103.

12. WATER USE

Please indicate the source(s) of water that will be used for the activity by ticking the appropriate box(es)municipal

document.docx 14

Page 15: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

If water is to be extracted from groundwater, river, stream, dam, lake or any other natural feature, please indicatethe volume that will be extracted per month: Unknown

(limited quantities)

Does the activity require a water use permit from the Department of Water Affairs?

NO

If yes, please submit the necessary application to the Department of Water Affairs and attach proof thereof to this application if it has been submitted.

13. ENERGY EFFICIENCY

Describe the design measures, if any, that have been taken to ensure that the activity is energy efficient:N/ADescribe how alternative energy sources have been taken into account or been built into the design of the activity, if any:N/A

SECTION B: SITE/AREA/PROPERTY DESCRIPTION

Important notes: 1. For linear activities (pipelines, etc) as well as activities that cover very large sites, it may be

necessary to complete this section for each part of the site that has a significantly different environment. In such cases please complete copies of Section C and indicate the area, which is covered by each copy No. on the Site Plan.

Section C Copy No. (e.g. A):

2. Paragraphs 1 - 6 below must be completed for each alternative.

3. Has a specialist been consulted to assist with the completion of this section?

YES

If YES, please complete the form entitled “Details of specialist and declaration of interest”for each specialist thus appointed:All specialist reports must be contained in Appendix D.

Property description/physical address:

As noted above the primary transmission activity involved six route options. In summary terms these options fall within three Local Municipalities namely; the City of Johannesburg, Mogale City and the City of Tshwane within the Gauteng Province Appendix A provides plans and further details on the precise locations and the farm and portions that will potentially be affected by these routes.(Farm name, portion etc.) Where a large number of properties are involved (e.g. linear activities), please attach a full list to this application. Please refer to Appendix GIn instances where there is more than one town or district involved, please attach a list of towns or districts to this application.

Current land-use zoning: Please refer to Appendix G

document.docx 15

Page 16: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

In instances where there is more than one current land-use zoning, please attach a list of current land use zonings that also indicate which portions each use pertains to , to this application.

Is a change of land-use or a consent use application required? YES NOMust a building plan be submitted to the local authority? NO

Locality map: An A3 locality map must be attached to the back of this document, as Appendix A. The scale of the locality map must be relevant to the size of the development (at least 1:50 000. For linear activities of more than 25 kilometres, a smaller scale e.g. 1:250 000 can be used. The scale must be indicated on the map.) The map must indicate the following: an indication of the project site position as well as the positions of the

alternative sites, if any; road access from all major roads in the area; road names or numbers of all major roads as well as the roads that provide

access to the site(s); all roads within a 1km radius of the site or alternative sites; and a north arrow; a legend; and locality GPS co-ordinates (Indicate the position of the activity using the

latitude and longitude of the centre point of the site for each alternative site. The co-ordinates should be in degrees and decimal minutes. The minutes should have at least three decimals to ensure adequate accuracy. The projection that must be used in all cases is the WGS84 spheroid in a national or local projection)

Please see Appendix A

1. GRADIENT OF THE SITE

Indicate the general gradient of the site.

Alternative SS A:Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than 1:5

Alternative SS B:Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than 1:5

Alternative SS C:Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than 1:5

Alternative SS D:Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than 1:5

Alternative SS E:Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than 1:5

Alternative Route Option 1:Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than 1:5

Alternative Route Option 2:Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than 1:5

Alternative Route Option 3:Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than 1:5

Alternative Route Option 4:Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than 1:5

Alternative Route Option 5:Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than 1:5

Alternative Route Option 6:

document.docx 16

Page 17: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than 1:5

2. LOCATION IN LANDSCAPE

Indicate the landform(s) that best describes the site:

Alternative SS A:

Ridgeline Plateau Side slope of hill/mountain

Closed valley

Open valley Plain Undulating plain/low

hills Dune Sea-front

Alternative SS B:

Ridgeline Plateau Side slope of hill/mountain

Closed valley

Open valley Plain Undulating plain/low

hills Dune Sea- front

Alternative SS C:Ridgeline Plateau Side slope of

hill/mountainClosed valley

Open valley Plain Undulating plain/low

hills Dune Sea-front

Alternative SS D:

Ridgeline Plateau Side slope of hill/mountain

Closed valley

Open valley Plain Undulating plain/low

hills Dune Sea-front

Alternative SS E:

Ridgeline Plateau Side slope of hill/mountain

Closed valley

Open valley Plain Undulating plain/low

hills Dune Sea-front

Alternative Route 1:Ridgeline Plateau Side slope of

hill/mountainClosed valley

Open valley Plain Undulating

plain/low hills Dune Sea-front

Alternative Route 2:Ridgeline Plateau Side slope of

hill/mountainClosed valley

Open valley Plain Undulating

plain/low hills Dune Sea-front

Alternative Route 3:Ridgeline Plateau Side slope of

hill/mountainClosed valley

Open valley Plain Undulating

plain/low hills Dune Sea-front

Alternative Route 4:

Ridgeline Plateau Side slope of hill/mountain

Closed valley

Open valley Plain Undulating

plain/low hills Dune Sea-front

Alternative Route 5:

Ridgeline Plateau Side slope of hill/mountain

Closed valley

Open valley Plain Undulating

plain/low hills Dune Sea-front

Alternative Route 6:

Ridgeline Plateau Side slope of hill/mountain

Closed valley

Open valley Plain Undulating

plain/low hills Dune Sea-front

3. GROUNDWATER, SOIL AND GEOLOGICAL STABILITY OF THE SITE

Is the site(s) located on any of the following (tick the appropriate boxes)? Substation- Alternative A: Alternative B: Alternative C: Alternative D:

Shallow water table (less than 1.5m deep) NO NO NO NODolomite, sinkhole or doline areas NO NO NO NO

document.docx 17

sheila, 2012-10-17,
To be confirmed by Eskom
Page 18: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

Seasonally wet soils (often close to water bodies) NO NO NO NOUnstable rocky slopes or steep slopes with loose soil

NO NO NO NO

Dispersive soils (soils that dissolve in water) NO NO NO NOSoils with high clay content (clay fraction more than 40%)

NO NO NO NO

Any other unstable soil or geological feature NO NO NO NOAn area sensitive to erosion NO NO NO NO

Substation- Alternative E:

Shallow water table (less than 1.5m deep) NODolomite, sinkhole or doline areas NOSeasonally wet soils (often close to water bodies) NOUnstable rocky slopes or steep slopes with loose soil

NO

Dispersive soils (soils that dissolve in water) NOSoils with high clay content (clay fraction more than 40%)

NO

Any other unstable soil or geological feature NOAn area sensitive to erosion NO

Route Alternative 1: Alternative 2: Alternative 3: Alternative 4:Shallow water table (less than 1.5m deep) NO NO NO NODolomite, sinkhole or doline areas NO NO NO NOSeasonally wet soils (often close to water bodies) NO NO NO NOUnstable rocky slopes or steep slopes with loose soil

NO NO NO NO

Dispersive soils (soils that dissolve in water) NO NO NO NO

document.docx 18

sheila, 2012-10-17,
To be confirmed by Eskom
Page 19: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

Soils with high clay content (clay fraction more than 40%)

NO NO NO NO

Any other unstable soil or geological feature NO NO NO NOAn area sensitive to erosion NO NO NO NO

Route Alternative 5: Alternative 6:Shallow water table (less than 1.5m deep) NO NODolomite, sinkhole or doline areas NO NOSeasonally wet soils (often close to water bodies) NO NOUnstable rocky slopes or steep slopes with loose soil

NO NO

Dispersive soils (soils that dissolve in water) NO NOSoils with high clay content (clay fraction more than 40%)

NO NO

Any other unstable soil or geological feature NO NOAn area sensitive to erosion NO NO

If you are unsure about any of the above or if you are concerned that any of the above aspects may be an issue of concern in the application, an appropriate specialist should be appointed to assist in the completion of this section. (Information in respect of the above will often be available as part of the project information or at the planning sections of local authorities. Where it exists, the 1:50 000 scale Regional Geotechnical Maps prepared by the Council for Geo Science may also be consulted).

A GEOTECH SPECIALIST WILL BE APPOINTED BY ESKOM TO CARRY OUT DETAILED GEOTECHNICAL ASSESSMENT OF THE PROJECT AREA.

4. GROUNDCOVER

Indicate the types of groundcover present on the site:The location of all identified rare or endangered species or other elements should be accurately indicated on the site plan(s).

Substation Alternatives:A Natural veld -

good conditionENatural veld with scattered aliensE

Natural veld with heavy alien infestationE

Veld dominated by alien speciesE

Gardens Sport field

Cultivated land

Paved surface

Building or other structure

B Natural veld - good conditionE

Natural veld with scattered aliensE

Natural veld with heavy alien infestationE

Veld dominated by alien speciesE

Gardens Sport field

Cultivated land

Paved surface

Building or other structure

document.docx 19

Page 20: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

C Natural veld - good conditionE

Natural veld with scattered aliensE

Natural veld with heavy alien infestationE

Veld dominated by alien speciesE

Gardens Sport field

Cultivated land

Paved surface

Building or other structure

D Natural veld - good conditionE

Natural veld with scattered aliensE

Natural veld with heavy alien infestationE

Veld dominated by alien speciesE

Gardens Sport field

Cultivated land

Paved surface

Building or other structure

E Natural veld - good conditionE

Natural veld with scattered aliensE

Natural veld with heavy alien infestationE

Veld dominated by alien speciesE

Gardens Sport field

Cultivated land

Paved surface

Building or other structure

Route Alternatives:1 Natural veld -

good conditionENatural veld with scattered aliensE

Natural veld with heavy alien infestationE

Veld dominated by alien speciesE

Gardens Sport field

Cultivated land

Paved surface

Building or other structure

2 Natural veld - good conditionE

Natural veld with scattered aliensE

Natural veld with heavy alien infestationE

Veld dominated by alien speciesE

Gardens Sport field

Cultivated land

Paved surface

Building or other structure

3 Natural veld - good conditionE

Natural veld with scattered aliensE

Natural veld with heavy alien infestationE

Veld dominated by alien speciesE

Gardens Sport field

Cultivated land

Paved surface

Building or other structure

4 Natural veld - good conditionE

Natural veld with scattered aliensE

Natural veld with heavy alien infestationE

Veld dominated by alien speciesE

Gardens Sport field

Cultivated land

Paved surface

Building or other structure

5 Natural veld - good conditionE

Natural veld with scattered aliensE

Natural veld with heavy alien infestationE

Veld dominated by alien speciesE

Gardens Sport field

Cultivated land

Paved surface

Building or other structure

6 Natural veld - good conditionE

Natural veld with scattered aliensE

Natural veld with heavy alien infestationE

Veld dominated by alien speciesE

Gardens Sport field

Cultivated land

Paved surface

Building or other structure

If any of the boxes marked with an “E “is ticked, please consult an appropriate specialist to assist in the completion of this section if the environmental assessment practitioner doesn’t have the necessary expertise.

5. LAND USE CHARACTER OF SURROUNDING AREA

Indicate land uses and/or prominent features that does currently occur within a 500m radius of the site and give description of how this influences the application or may be impacted upon by the application:

Substation ANatural area Medium density residential Medium density residential High density residential Informal residentialA

Retail Commercial & warehousing Light industrial Medium industrialAN Heavy industrial

Power stationA Office/consulting room Military or police base/station/compound

Casino/entertainment complex

Hospitality facility

Open cast mine Underground mine Spoil heap or slimes dam Quarry, sand or borrow pit Dam or reservoirHospital/medical center School Tertiary education facility Church Old age home

Sewage treatment plantA Train station or shunting yardN Railway lineN Major road (4 lanes or more)N AirportN

document.docx 20

Page 21: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

Harbour Sport facilities Golf course Polo fields Filling stationH

Landfill or waste treatment siteA Plantation Agriculture River, stream or wetland Nature conservation areaMountain, koppie or ridge Museum Historical building Graveyard Archaeological site

Other land uses (describe):

Substation BNatural area Low density residential Medium density residential High density residential Informal residential

Retail Commercial & warehousing Light industrial Medium industrialAN Heavy industrial

Power stationA Office/consulting roomMilitary or police

base/station/compoundCasino/entertainment

complexHospitality facility

Open cast mine Underground mine Spoil heap or slimes dam Quarry, sand or borrow pit Dam or reservoirHospital/medical center School Tertiary education facility Church Old age home

Sewage treatment plantA Train station or shunting yardN Railway lineN Major road (4 lanes or more)N AirportN

Harbour Sport facilities Golf course Polo fields Filling stationH

Landfill or waste treatment siteA Plantation Agriculture River, stream or wetland Nature conservation areaMountain, koppie or ridge Museum Historical building Graveyard Archaeological site

Other land uses (describe):

Substation CNatural area Low density residential Medium density residential High density residential Informal residential

Retail Commercial & warehousing Light industrial Medium industrialAN Heavy industrial

Power stationA Office/consulting roomMilitary or police

base/station/compoundCasino/entertainment

complexHospitality facility

Open cast mine Underground mine Spoil heap or slimes dam Quarry, sand or borrow pit Dam or reservoirHospital/medical center School Tertiary education facility Church Old age home

Sewage treatment plantA Train station or shunting yardN Railway lineN Major road (4 lanes or more)N AirportN

Harbour Sport facilities Golf course Polo fields Filling stationH

Landfill or waste treatment siteA Plantation Agriculture River, stream or wetland Nature conservation areaMountain, koppie or ridge Museum Historical building Graveyard Archaeological site

Other land uses (describe): Microlight Airstrip

Substation DNatural area Low density residential Medium density residential High density residential Informal residential

Retail Commercial & warehousing Light industrial Medium industrialAN Heavy industrial

Power stationA Office/consulting roomMilitary or police

base/station/compoundCasino/entertainment

complexHospitality facility

Open cast mine Underground mine Spoil heap or slimes dam Quarry, sand or borrow pit Dam or reservoirHospital/medical center School Tertiary education facility Church Old age home

Sewage treatment plantA Train station or shunting yardN Railway lineN Major road (4 lanes or more)N AirportN

Harbour Sport facilities Golf course Polo fields Filling stationH

Landfill or waste treatment siteA Plantation Agriculture River, stream or wetland Nature conservation areaMountain, koppie or ridge Museum Historical building Graveyard Archaeological site

Other land uses (describe): Microlight Airstrip

Substation ENatural area Low density residential Medium density residential High density residential Informal residential

Retail Commercial & warehousing Light industrial Medium industrialAN Heavy industrial

Power stationA Office/consulting roomMilitary or police

base/station/compoundCasino/entertainment

complexHospitality facility

document.docx 21

Page 22: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

Open cast mine Underground mine Spoil heap or slimes dam Quarry, sand or borrow pit Dam or reservoirHospital/medical center School Tertiary education facility Church Old age home

Sewage treatment plantA Train station or shunting yardN Railway lineN Major road (4 lanes or more)N AirportN

Harbour Sport facilities Golf course Polo fields Filling stationH

Landfill or waste treatment siteA Plantation Agriculture River, stream or wetland Nature conservation areaMountain, koppie or ridge Museum Historical building Graveyard Archaeological site

Other land uses (describe):

Route 1Natural area Low density residential Medium density residential High density residential Informal residentialA

Retail Commercial & warehousing Light industrial Medium industrialAN Heavy industrial

Power stationA Office/consulting room Military or police base/station/compound

Casino/entertainment complex Hospitality facility

Open cast mine Underground mine Spoil heap or slimes dam Quarry, sand or borrow pit Dam or reservoirHospital/medical center School Tertiary education facility Church Old age home

Sewage treatment plantA Train station or shunting yardN Railway lineN Major road (4 lanes or more)N AirportN

Harbour Sport facilities Golf course Polo fields Filling station

Landfill or waste treatment siteA Plantation Agriculture River, stream or wetland Nature conservation area

Mountain, koppie or ridge Museum Historical building Graveyard Archaeological siteOther land uses (describe):

Route 2Natural area Low density residential Medium density residential High density residential Informal residential

Retail Commercial & warehousing Light industrial Medium industrialAN Heavy industrial

Power stationA Office/consulting room Military or police base/station/compound

Casino/entertainment complex

Hospitality facility

Open cast mine Underground mine Spoil heap or slimes dam Quarry, sand or borrow pit Dam or reservoirHospital/medical center School Tertiary education facility Church Old age home

Sewage treatment plantA Train station or shunting yardN Railway lineN Major road (4 lanes or more)N AirportN

Harbour Sport facilities Golf course Polo fields Filling stationH

Landfill or waste treatment siteA Plantation Agriculture River, stream or wetland Nature conservation area

Mountain, koppie or ridge Museum Historical building Graveyard Archaeological siteOther land uses (describe):

Route 3Natural area Low density residential Medium density residential High density residential Informal residential

Retail Commercial & warehousing Light industrial Medium industrialAN Heavy industrial

Power stationA Office/consulting room Military or police base/station/compound

Casino/entertainment complex

Hospitality facility

Open cast mine Underground mine Spoil heap or slimes dam Quarry, sand or borrow pit Dam or reservoirHospital/medical center School Tertiary education facility Church Old age home

Sewage treatment plantA Train station or shunting yardN Railway lineN Major road (4 lanes or more)N AirportN

Harbour Sport facilities Golf course Polo fields Filling stationH

Landfill or waste treatment siteA Plantation Agriculture River, stream or wetland Nature conservation areaMountain, koppie or ridge Museum Historical building Graveyard Archaeological site

document.docx 22

Page 23: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

Other land uses (describe): Microlight Airstrip

Route 4Natural area Low density residential Medium density residential High density residential Informal residentialA

Retail Commercial & warehousing Light industrial Medium industrialAN Heavy industrial

Power stationA Office/consulting room Military or police base/station/compound

Casino/entertainment complex

Hospitality facility

Open cast mine Underground mine Spoil heap or slimes dam Quarry, sand or borrow pit Dam or reservoirHospital/medical center School Tertiary education facility Church Old age home

Sewage treatment plantA Train station or shunting yardN Railway lineN Major road (4 lanes or more)N AirportN

Harbour Sport facilities Golf course Polo fields Filling station

Landfill or waste treatment siteA Plantation Agriculture River, stream or wetland Nature conservation area

Mountain, koppie or ridge Museum Historical building Graveyard Archaeological siteOther land uses (describe):

Route 5Natural area Low density residential Medium density residential High density residential Informal residentialA

Retail Commercial & warehousing Light industrial Medium industrialAN Heavy industrial

Power stationA Office/consulting room Military or police base/station/compound

Casino/entertainment complex

Hospitality facility

Open cast mine Underground mine Spoil heap or slimes dam Quarry, sand or borrow pit Dam or reservoirHospital/medical center School Tertiary education facility Church Old age home

Sewage treatment plantA Train station or shunting yardN Railway lineN Major road (4 lanes or more)N AirportN

Harbour Sport facilities Golf course Polo fields Filling station

Landfill or waste treatment siteA Plantation Agriculture River, stream or wetland Nature conservation areaMountain, koppie or ridge Museum Historical building Graveyard Archaeological siteOther land uses (describe):

Route 6Natural area Low density residential Medium density residential High density residential Informal residentialA

Retail Commercial & warehousing Light industrial Medium industrialAN Heavy industrial

Power stationA Office/consulting roomMilitary or police

base/station/compoundCasino/entertainment

complexHospitality facility

Open cast mine Underground mine Spoil heap or slimes dam Quarry, sand or borrow pit Dam or reservoirHospital/medical center School Tertiary education facility Church Old age home

Sewage treatment plantA Train station or shunting yardN Railway lineN Major road (4 lanes or more)N AirportN

Harbour Sport facilities Golf course Polo fields Filling stationH

Landfill or waste treatment siteA Plantation Agriculture River, stream or wetland Nature conservation area

Mountain, koppie or ridge Museum Historical building Graveyard Archaeological siteOther land uses (describe): Microlight Airstrip

If any of the boxes marked with an “N “are ticked, how will this impact / be impacted upon by the proposed activity?

document.docx 23

Page 24: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

Route5 runs along Malibongwe Dr right approximately 300m from Lanseria Runway. Should this option be taken forward, the proposed infrastructure would need to be undergrounded. Please refer to Appendix G for Civil Aviation Report which analysis impacts of the proposed development on the flight path around Lanseria Airport.

If any of the boxes marked with an "An" are ticked, how will this impact / be impacted upon by the proposed activity? If YES, specify and explain: N/A

If any of the boxes marked with an "H" are ticked, how will this impact / be impacted upon by the proposed activity. If YES, specify and explain: Both route 4 and route 5 run in close proximity to filling stations, it is proposed that appropriate mitigation measures are implemented to minimise risk to the filling stations. These may include undergrounding, as is the case with Route 5. A minimum distance of 100mfrom the filling station.

6. CULTURAL/HISTORICAL FEATURES

Are there any signs of culturally or historically significant elements, as defined in section 2 of the National Heritage Resources Act, 1999, (Act No. 25 of 1999), including Archaeological or palaeontological sites, on or close (within 20m) to the site?

Yes

If YES, explain:

See specialist report (Appendix D) and summary below.

If uncertain, conduct a specialist investigation by a recognised specialist in the field to establish whether there is such a feature(s) present on or close to the site.

Briefly explain the findings of the specialist:

During the background research for the Heritage Statement, 22 heritage resources were identified within the project area. In addition, eight heritage resources were identified during the site survey. They consist of the following:

Graveyards;

Iron Age Stone walled sites;

Stone Age sites; and

Historical sites; and

The Cradle of Humankind World Heritage Site).

Areas and sites of potential heritage value were identified during the site visit such as undisturbed

fields, river banks, rocky outcrops and historical dwellings. A sensitivity map was produced depicting

each route and substation option with identified heritage resources.

Will any building or structure older than 60 years be affected in any way? NOIs it necessary to apply for a permit in terms of the National Heritage Resources Act, 1999 (Act 25 of 1999)?

NO

If yes, please submit or, make sure that the applicant or a specialist submits the necessary application to SAHRA or the relevant provincial heritage agency and attach proof thereof to this application if such application has been made.

document.docx 24

Page 25: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

SECTION C: PUBLIC PARTICIPATION

1. ADVERTISEMENT

The person conducting a public participation process must take into account any guidelines applicable to public participation as contemplated in section 24J of the Act and must give notice to all potential interested and affected parties of the application which is subjected to public participation by—

(a) fixing a notice board (of a size at least 60cm by 42cm; and must display the required information in lettering and in a format as may be determined by the competent authority) at a place conspicuous to the public at the boundary or on the fence of—(i) the site where the activity to which the application relates is or is to be undertaken; and

(ii) any alternative site mentioned in the application;(b) giving written notice to—

(i) the owner or person in control of that land if the applicant is not the owner or person in control of the land;

(ii) the occupiers of the site where the activity is or is to be undertaken or to any alternative site where the activity is to be undertaken;

(iii) owners and occupiers of land adjacent to the site where the activity is or is to be undertaken or to any alternative site where the activity is to be undertaken;

(iv) the municipal councillor of the ward in which the site or alternative site is situated and any organisation of ratepayers that represent the community in the area;

(v) the municipality which has jurisdiction in the area; (vi) any organ of state having jurisdiction in respect of any aspect of the activity; and(vii) any other party as required by the competent authority;

(c) placing an advertisement in—(i) one local newspaper; or

document.docx 25

Page 26: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

(ii) any official Gazette that is published specifically for the purpose of providing public notice of applications or other submissions made in terms of these Regulations;

(d) placing an advertisement in at least one provincial newspaper or national newspaper, if the activity has or may have an impact that extends beyond the boundaries of the metropolitan or local municipality in which it is or will be undertaken: Provided that this paragraph need not be complied with if an advertisement has been placed in an official Gazette referred to in subregulation 54(c)(ii); and

(e) using reasonable alternative methods, as agreed to by the competent authority, in those instances where a person is desiring of but unable to participate in the process due to—(i) illiteracy;(ii) disability; or(iii) any other disadvantage.

2. CONTENT OF ADVERTISEMENTS AND NOTICES

A notice board, advertisement or notices must:

(a) indicate the details of the application which is subjected to public participation; and (b) state—

(i) that the application has been submitted to the competent authority in terms of these Regulations, as the case may be;(ii) whether basic assessment or scoping procedures are beingapplied to the

application, in the case of an application for environmental authorisation;

(iii) the nature and location of the activity to which the application relates;(iv) where further information on the application or activity can be obtained; and (iv) the manner in which and the person to whom representations in respect of the

application may be made.

3. PLACEMENT OF ADVERTISEMENTS AND NOTICES

Where the proposed activity may have impacts that extend beyond the municipal area where it is located, a notice must be placed in at least one provincial newspaper or national newspaper, indicating that an application will be submitted to the competent authority in terms of these regulations, the nature and location of the activity, where further information on the proposed activity can be obtained and the manner in which representations in respect of the application can be made, unless a notice has been placed in any Gazette that is published specifically for the purpose of providing notice to the public of applications made in terms of the EIA regulations.

Advertisements and notices must make provision for all alternatives.

4. DETERMINATION OF APPROPRIATE MEASURES

The practitioner must ensure that the public participation is adequate and must determine whether a public meeting or any other additional measure is appropriate or not based on the particular nature of each case. Special attention should be given to the involvement of local community structures such as Ward Committees, ratepayers associations and traditional authorities where appropriate. Please note that public concerns that emerge at a later stage that should have been addressed may cause the competent authority to withdraw any authorisation it may have issued if it becomes apparent that the public participation process was inadequate.

document.docx 26

Page 27: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

5. COMMENTS AND RESPONSE REPORT

The practitioner must record all comments and respond to each comment of the public before the application is submitted. The comments and responses must be captured in a comments and response report as prescribed in the EIA regulations and be attached to this application. The comments and response report must be attached under Appendix E.

6. AUTHORITY PARTICIPATION

Please note that a complete list of all organs of state and or any other applicable authority with their contact details must be appended to the basic assessment report or scoping report, whichever is applicable.

Authorities are key interested and affected parties in each application and no decision on any application will be made before the relevant local authority is provided with the opportunity to give input.

List of authorities informed:

document.docx 27

Page 28: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

1. National Departments:o Civil Aviation Authority-CAAo Department of Forestry and Fisherieso Department of Co-operate Governance and Traditional Affairso Department of Arts and Cultureo Department of Economics Developmento Department of Human Settlemento Department of Mineral Resources-DMRo Department of Tourismo Department of Water Affairso South Africa Heritage Resources-SAHRAo SANPARKo SANRAL

2. Provincial Governments:o Gauteng Department of Economic Developmento Gauteng Dept.Tourism (Cradle of Humankind)o Gauteng Department of Healtho Gauteng Dept. of Human Settlementso Gauteng Dept. of Agriculture and Rural Development-GDARDo Gauteng dept. of road and transport- GDRT

3. Local Governments:o City of Johannesburg (planning, electrical and environmental departments)o Mogale City(planning and electrical departments)o City of Tshwane(planning department)o Ward Councillors

Ward 23: Ward 48 Ward 96 Ward 100 Ward 114

o Codevcoo CDW Dept. of Housing and Local Governmento ANCYLo Rhema Hands of Compassion

List of authorities from whom comments have been received:

1. National Departments:o South Africa Heritage Resources-SAHRA

2. Provincial Governments:o Gauteng Dept. of Agriculture and Rural Development-GDARD

3. Local Governments:o Ward Councillors-100

(Please see Appendix E for these comments)

7. CONSULTATION WITH OTHER STAKEHOLDERS

Note that, for linear activities, or where deviation from the public participation requirements may be appropriate, the person conducting the public participation process may deviate from the requirements of that subregulation to the extent and in the manner as may be agreed to by the competent authority.

document.docx 28

Page 29: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

Proof of any such agreement must be provided, where applicable.Has any comment been received from stakeholders? YE

SIf “YES”, briefly describe the feedback below (also attach copies of any correspondence to and from the stakeholders to this application):

A separate comments and response report has been attached to this report and comments from stakeholders have been considered within the specialist reports. In summary the process is as follows.

Application to the DEAThe following documents were signed and submitted to the DEA on 31 May 2011 as required:

Application to undertake a listed activity EAP Declaration Specialists declaration form Acknowledgement letter was received from the DEA 07 June 2011

Stakeholder ConsultationAdverts

Invitation to register as I&APs on 31 August 2011 Circulate BID to registered I&APs on 16 September 2011 Circulate BID, with new sites to registered I&APs on 15 March 2012 Project was advertised on newspaper on 13 October 2011 on the Star, Beeld and Sowetan Additional routes and sites were advertised on 09 March 2012 on the Star, Beeld and Sowetan New BIDs, Comment forms, invitation letters to participate and registration forms have been

sent to Landowners on New Routes were circulated to registered I&APs on 19 March 2012MeetingsFocus Group Meetings – landowners who are directly affected by the power line (1km area) and substation.

Zwartkops – 03 August 2011 affected by 3 and 6 and substation C. Route 6 was not yet part of the study during this meeting.

Rietfontein - 04 August 2011 affected by Route 3 and substation C Driefontein and Rietfontein Landowners – 04 August 2011 affected by all six routes Chartwell

North – 08 June 2011 land owners directly affected by routes 1 and 2 as well as substations A and B.

North Champagne - 08 June 2011 affected by routes 1 and 2 and substation A and B. and substation sites, although at the time of this meeting, route 4,5 and 6 and substation E

were not yet part of the study. Nooitgedacht - 12 April 2012 all six routes and substations

Key Stakeholder Workshop – Government Departments, Utilities, NGO’s, Tourism Operators, Developers, Rate Payers Associations, CoHKWHS (Cradle) and SAHRA. Meetings was held at Ekudeni on 01 November 2011

Presentation was done by Lynette Groenewald (Urban Dynamics) on the development at Lion Park and surrounding areas.

Mr Anton Lotter (Croc City) gave presentation on the tourist and agricultural impact that the lines will have in the area.

Public Meetings – Registered Interested and Affected Parties Hebron College 18 October 2011 – Eastern Section of the study area Ekudeni 19 October 2011 – Western Section of the study area

Authorities – Meetings with Municipalities and Ward Councillors Consultation with Community Leaders and Councillors – Zandspruit and Cosmo City 24 June

2011 Consultation with Community Leaders and Councillors – Muldersdrift and Lanseria 29 June

2011 Meeting with Mogale City – 01 April 2011 Meeting with City of Johannesburg – 13 May 2011 Meeting with City of Tshwane – 26 July 2011

One-on-One Meetings – Meetings affected landowners to explain the project. 487 (89.7%) landowners were consulted using various consultation methods 8 (1.5%) were sent information 48 (8.8%) did not have contact details and were therefore not consulted

document.docx 29

tsepo, 2012-10-25,
Check with Clr
Page 30: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

SECTION D: IMPACT ASSESSMENT

The assessment of impacts must adhere to the minimum requirements in the EIA Regulations, 2010, and should take applicable official guidelines into account. The issues raised by interested and affected parties should also be addressed in the assessment of impacts.

1. ISSUES RAISED BY INTERESTED AND AFFECTED PARTIES

List the main issues raised by interested and affected parties.Comments made by I&AP’s are contained within the Comments and Response Report at Appendix E. Those listed below are the primary concerns identified:

Visual Impact of Power Lines- see Visual Impact Specialist Report Changes to landscape character- see See Visual Impact Specialist Report Risks associated with Electro-magnetic fields- see Appendix X addressing tower type

and EMF profiles. Loss/change to business- See Economic Impact Report and Visual Impact Report Desires that the line should be undergrounded- see BAR summary at Appendix X and

Appendix X describing costs and constraints associated with underground options. Comments on Biodiversity- see specialist reports on Avifauna, Flora and Fauna and

Wetlands. Potential loss of agricultural land (mainly smallholdings)- see Economic Impact

Assessment. Comments offering land to Eskom for the servitude Concerns regarding disruption during construction- considered by all specialists and in

the BAR. Concerns regarding reductions in property value- see Economic Impact Report

Response from the practitioner to the issues raised by the interested and affected parties (A full response must be given in the Comments and Response Report that must be attached to this report as Annexure E):See comments and response report at Appendix X

2. IMPACTS THAT MAY RESULT FROM THE PLANNING AND DESIGN, CONSTRUCTION, OPERATIONAL, DECOMMISSIONING AND CLOSURE PHASES AS WELL AS PROPOSED MANAGEMENT OF IDENTIFIED IMPACTS AND PROPOSED MITIGATION MEASURES

List the potential direct, indirect and cumulative property/activity/design/technology/operational alternative related impacts (as appropriate) that are likely to occur as a result of the planning and design phase, construction phase, operational phase, decommissioning and closure phase, including impacts relating to the choice of site/activity/technology alternatives as well as the mitigation measures that may eliminate or reduce the potential impacts listed.

Alternative (preferred alternative)Direct impacts:

Please see Specialist Report in Appendix D and Supplementary Report in Appendix G

Indirect impacts:

Please see Specialist Report in Appendix D and Supplementary Report in Appendix G

Cumulative impacts:

document.docx 30

Page 31: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

Please see Specialist Report in Appendix D and Supplementary Report in Appendix G

3. ENVIRONMENTAL IMPACT STATEMENT

Taking the assessment of potential impacts into account, please provide an environmental impact statement that summarises the impact that the proposed activity and its alternatives may have on the environment after the management and mitigation of impacts have been taken into account, with specific reference to types of impact, duration of impacts, likelihood of potential impacts actually occurring and the significance of impacts.

Our findings suggest that, although it is likely that the undergrounding option using Malibongwe Drive (Option 5a) will be preferred by the public and may result in a lower overall impact at a corridor level, this option is not considered feasible or reasonable based on the available knowledge. Furthermore, when examined at a servitude level it is less clear that such an option would result in significantly lower environmental impacts (it would need to run along the western side of Malibongwe Drive which is more sensitive than the eastern edge) than overhead lines, the impact of which can often be mitigated through placement and design considerations.. Given the cost of taking forward this option (up to 20 x the cost of an overhead line) it is our view that there is too much uncertainty regarding feasibility and insufficient environmental benefit to justify the cost of such a proposal thereby passing the test of reasonableness. Thus, taking into account all of the factors identified through extensive study, Route Corridor Option 1 and Substation Option A are recommended.

Alternative A (preferred alternative)Route Corridor 1 and Substation A are the preferred Alternatives. Though there are a number of potentially unavoidable impacts resulting from the selection of Route Corridor 1, these are generally limited to visual impact. The route is able to follow existing infrastructure for the majority of its length and furthermore can be sited in the most part in such a way that it only passes through areas of low to medium sensitivity. The mitigation measures outlined in specialist reports and the Environmental Management Plan appended to this document will need to be implemented as part of the proposed development.

Within Route options 1, 2 and 4, there is some scope to select a servitude which further minimises the impact of the proposed development. The servitude can be selected which affects only areas of low sensitivity and can be further modified to minimise land take and integrate with existing infrastructure such as roads and existing power lines. Detailed servitude selection will take place after further, more detailed surveys and a site walkover.

No-go alternative (compulsory)The “No Go” alternative is assumed to mean no development on the site, and the maintenance of the current status quo. This will not be in the best interest of the client and public, as infrastructural upgrades and development in relation to governing service delivery bodies within this region has already invested their trust into this development becoming realised.

document.docx 31

Page 32: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

SECTION E. RECOMMENDATION OF PRACTITIONER

Is the information contained in this report and the documentation attached hereto sufficient to make a decision in respect of the activity applied for (in the view of the environmental assessment practitioner)?

YES NO

If “NO”, indicate the aspects that should be assessed further as part of a Scoping and EIA process before a decision can be made (list the aspects that require further assessment):

If “YES”, please list any recommended conditions, including mitigation measures that should be considered for inclusion in any authorisation that may be granted by the competent authority in respect of the application:Mitigation measures for the impacts identified for this project are outlined in the the Specialist Report in Appendix D and Supplementary Report in Appendix G and there is also an Environmental Management Plan in Appendix FIs an EMPr attached? YES NOThe EMPr must be attached as Appendix F.

document.docx 32

Page 33: SECTION B: ACTIVITY INFORMATION - Eskom Home · Web viewkV substation and associated infrastructure. The study area is currently fed by Lulamisa grid system which is currently under

BASIC ASSESSMENT REPORT

SECTION F: APPENDIXES

The following appendixes must be attached as appropriate:

Appendix A: Site plan(s)

Appendix B: Photographs

Appendix C: Facility illustration(s)

Appendix D: Specialist reports

Appendix E: Comments and responses report

Appendix F: Environmental Management Programme (EMPr)

Appendix G: Other information

document.docx 33


Recommended