+ All Categories
Home > Documents > Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of...

Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of...

Date post: 20-May-2020
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
44
LHC status and commissioning Sector 34 incident present understanding Picking up the pieces Making sure it doesn’t happen again Schedule before beam Schedule 2009-2010 Re-commissioning with beam 2009 2010 run 23/03/2009 1 LHC status and commissioning Mike Lamont
Transcript
Page 1: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

LHC status and commissioning

Sector 34 incident – present understanding

Picking up the pieces

Making sure it doesn’t happen again

Schedule before beam

Schedule 2009-2010

Re-commissioning with beam

2009 – 2010 run

23/03/2009 1LHC status and commissioning

Mike Lamont

Page 2: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

1. What went wrong

Page 3: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Ruptured bus-bar interconnection

LHC status and commissioning23/03/2009 3

Page 4: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Electrical joint in 12 kA bus bar

Cable Junction Box

Cross-section

Upper Tin/Silver

Soldering alloy Layer

Inter-Cable Tin/Silver

Soldering Alloy Layer

Superconducting

Cable in Copper

Stabilizer

Upper Copper

Profile

Lower Copper U

Profile

Lower Tin/Silver

Soldering Alloy Layer

Completed

Junction

23/03/2009 4LHC status and commissioning

“What makes a good joint?”

A. Verweij

No electrical contact between wedge and U-profile

with the bus on at least 1 side of the joint

No bonding at joint with the

U-profile and the wedge

A resistive joint of about

220 n with bad electrical

and thermal contacts with the stabilizer

Page 5: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Thermal runaway – model versus reality

LHC status and commissioning

-400

-200

0

200

400

600

800

1000

-20 -15 -10 -5 0

Time [s]

Vo

ltag

e [

mV

]

0

100

200

300

400

500

600

700

Tem

p [

K]

V_meas (Timber)

V_meas (QPS data)

V_sim [mV]

T_sim [K]

23/03/2009 5Arjan Verweij

Voltage across the splice and temperature rise

Page 6: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

2. Pick up the pieces

Message: huge amount of work

required to repair the damage

Page 7: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Fix the problem

Take all damaged magnets out

53 total, 39 dipoles, 14 SSSs (Short Straight Section – quad++)

Fix the cryogenics supply line

Fix and clean the beam vacuum

Repair the magnets

Test repaired magnets and spares used

Re-install

Re-interconnect

Cool

Test

LHC status and commissioning23/03/2009 7

Page 8: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Damage: magnet displacements

QQBI.27R3

23/03/2009 8LHC status and commissioning

Page 9: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Remove and repair

LHC status and commissioning 923/03/2009

Remove damaged magnets Preparation of recovery facilities

Page 10: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

SMI2

B26 (2111): first de-cryostating

SSS-243 (replace Q23)

SSS-369 (replace Q32)

SSS-277 (replace Q22)

SSS-055 (replace Q27)

23/03/200910 LHC status and commissioning

Lucio Rossi

Page 11: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

904

Q32 SSS-200: under de-cryostating with Q31 and Q29

23/03/200911 LHC status and commissioning

Page 12: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

SMA18

LHC status and commissioning 1223/03/2009

A22 (1085)/ B22 (3118) / C22 (1071): under preparation for cold testing

Page 13: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Beam Vacuum cleaning

LHC status and commissioning23/03/2009 13

Page 14: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Beam Vacuum Contamination – S34

LHC status and commissioning

Point 3

Point 4

23/03/2009 14

Miguel

Jimenez

Plus

Cryogenic Supply Line

Beam Instrumentation

Civil engineering

Quench Protection system

etc..

Page 15: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

3. Try and make sure it

never happens again

1. Find any other bad splices

2. Improve protection

3. Reduce potential damage

Page 16: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Take remedial action

Check all splices

QPS snapshot and calorimetry in situ (5/8 sectors)

Bus-bar splice resistance measurements by means of nano-

voltmeters

Check old SM18 data

Better protection

Extended QPS system – local rather than global bus-bar

protection

Minimize collateral damage

Anticipate Maximum Credible Incident (MCI)

New relief ports

New jacks

LHC status and commissioning23/03/2009 16

Page 17: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Calorimetry

LHC status and commissioning 1723/03/2009

0

10

20

30

40

50

60

70

80

1.85

1.87

1.89

1.91

1.93

1.95

1.97

1.99

18:00 19:00 20:00 21:00 22:00

Val

ve o

pe

nin

g [%

], c

urr

en

t [kA

], C

C f

low

[g/s

]

Co

ld-m

ass

tem

pe

ratu

e [K

]

LBALA_24R3_TT821.POSST

LBALA_25R3_TT821.POSST

LBALA_26R3_TT821.POSST

LBALA_27R3_TT821.POSST

LBALB_24R3_TT821.POSST

LBALB_26R3_TT821.POSST

LBBLA_24R3_TT821.POSST

LBBLA_25R3_TT821.POSST

LBBLA_26R3_TT821.POSST

LBBLA_27R3_TT821.POSST

LBBLD_25R3_TT821.POSST

LBBLD_27R3_TT821.POSST

LQASB_23R3_TT821.POSST

LQOAA_25R3_TT821.POSST

LQOBA_24R3_TT821.POSST

LQOBA_26R3_TT821.POSST

QRLAA_25R3_CV910.POSST

QRLAB_23R3_CV910.POSST

QURCA_4_FT201.POSST

RPTE.UA43.RB.A34:I_MEAS

L. Tavian

Resistive heating of bad splices can be measured.

Temperature drift during 7 kA current flat top (15 Sep 2008)

Page 18: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Calorimetry

LHC status and commissioning23/03/2009 18

Remove

Remove

Measurements in cold sectors have revealed

potential problems in splices inside magnets

Page 19: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

QPS can also see “bad” splices

LHC status and commissioning 1923/03/2009

Sector A12: A15R1 – C19R1: Dipole Measurements made on 03.11.08

0.7mV/7kA=100nOhm0.7mV*7kA=4.9W

Snapshot at 03.09.08 : 0.85mV*8.4kA=7.1W

B16R1 => 2334

05/11/2008 Zinour Charifoulline, AT/MEI

Page 20: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Improved quality control

LHC status and commissioning23/03/2009 20

Ultrasound splices

Page 21: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Quench Detection

21

1. The quench is detected based on voltage measurements over the coils (U_mag_A, U_mag_B).

2. The energy is distributed over the entire magnet by force-quenching with quench heaters.

3. The power converter is switched off.

4. The current within the quenched magnet decays in < 200 ms, circuit current now flows through

the ‚bypass‘ diode that can stand the current for 100-200 s.

5. The circuit current/energy is discharged into the dump resistors.

Dump

resistorDump

resistor

Power

converter

Page 22: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Quench Protection System upgrade

Upgrade required to cover:

local rather than global coverage of bus bars

symmetric quenches

Massive job

New electronics

Massive cabling effort

QPS update is on the critical path for the re-start of LHC

LHC status and commissioning 2223/03/2009

240 km of cables (= Chamonix – Venezia)

4400 individual cables

7800 connectors

0 errors permitted

Page 23: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Maximum Credible Incident

LHC status and commissioning 2323/03/2009

MCI ?

080919 incident

L. Tavian

Alleviate knock-on effects - try and cater for the worse

Page 24: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Improved pressure relief

F. Bertinelli

Additional relief valves on dipole vacuum enclosure

23/03/2009 24LHC status and commissioning

• Four warm sectors: equip all dipoles with one DN200 flange and relief valve

• Four cold sectors: equip all SSS flanges with relief valves, fit relief valves on

dipoles in 2010 shutdown

plus stand alone magnet and feed boxes

plus improved SSS jacks

Page 25: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

4. Schedule until beam

Message: There is a lot of work going

on all around the ring:

- repair

- consolidation

Page 26: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Chamonix - baseline decisions

Relief valves

4 warm sectors

Inner triplets & stand alone magnets

Feed boxes

Compensatory measures on SSSs in cold sectors

New quench protection system fully deployed in 2009

Magnets out in S12 and S67

Calorimetric, QPS, electrical measurements ASAP on all

sectors not yet checked.

LHC status and commissioning 2623/03/2009

Page 27: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Arcs

LHC status and commissioning 2723/03/2009

Katy Foraz

Page 28: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Long Straight Sections

LHC status and commissioning 2823/03/2009

Katy Foraz

Page 29: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

With powering tests

LHC status and commissioning 2923/03/2009

Katy Foraz

Fair to say that the schedule is very tight

Page 30: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

4. Schedule with beam

Page 31: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Gains 20 weeks of LHC physics (independent of “slip”)

23/03/2009

Schedule with running in winter months

31LHC status and commissioning

Steve Myers

Page 32: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Schedule outline

Normal operation of the whole complex up to mid-

November 2009.

Operation of Linac2, PSB, PS and SPS with LHC beams

only from mid-November to the beginning of April.

Technical stop around Christmas

exact length to be defined.

Normal operation of the whole complex from April until

end October 2010.

LHC status and commissioning23/03/2009 32

Page 33: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

5. Beam Commissioning

Page 34: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Beam – Chamonix baseline

4 TeV “on the way” to 5 TeV (no higher in 2010)

Physics at 5 TeV

Start with low number of bunches, low intensity

increase slowly 1,4,12,43, 156….

Estimated integrated luminosity

during first 100 days of operation.. ≈100pb-1

during next 100 days of operation.. ≈ 200 – 300 pb-1

End of 2010 run – one month ions

LHC status and commissioning23/03/2009 34

Page 35: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

LHC status and commissioning 35

Commissioning stages

Safely establish colliding beams as quickly as

possible

Initial optics:

β*= 11 m in IR 1 & 5

β*= 10 m in IR 2 & 8

Crossing angles off

Low bunch intensity

1, 12, 43, 156 bunches per beam

No parasitic encounters - no long

range beam-beam

Larger aperture in IRs

23/03/2009

50 ns

Page 36: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

LHC status and commissioning 36

Beam Commissioning to 5 TeV Collisions

Rings Total [days]

1 Injection and first turn 2 1

2 Circulating beam 2 2

3 450 GeV - initial 2 3

4 450 GeV - detailed 2 3

5 450 GeV - two beams 1 1

6 Snapback - single beam 2 3

7 Ramp - single beam(s) 2 6

8 Ramp - both beams 1 2

9 7 TeV - setup for physics 1 1

10 Physics un-squeezed 1 -

TOTAL TO FIRST COLLISIONS 22

11 Commission squeeze 2 6

12 Increase Intensity 2 6

13 Set-up physics - partially squeezed. 1 2

14 Pilot physics run

23/03/2009

Page 37: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Beam 2008 - Chamonix Summary 373/23/2009

Page 38: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

LHC status and commissioning 38

Stage A: First Collisions

2008 gives us some confidence in the machine

magnets, aperture, alignment, model, instrumentation, controls,

key sub-systems…

Approx 4 weeks to establish first collisions

Given reasonable machine availability (caveat)

Un-squeezed, low intensity

Optimistic – but not without cause

Continued commissioning thereafter

Increased intensity

Squeeze RHIC 2000:

- First beam April 3rd

- First successful ramp: June 1st

- First collisions June 12th

23/03/2009

Page 39: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

2009 – 2010 - ball park

LHC status and commissioning 3923/03/2009

MonthNo.

Bunches

Protons

per bunch

β*

[m]% Nom

Peak luminosity

cm-2s-1

Integrated

luminosity

1 Beam Commissioning

2 43 3 x 1010 4 0.4 1.2 x 1030 100 – 200 nb-1

3 43 5 x 1010 4 0.7 3.4 x 1030 ~2 pb-1

4 156 5 x 1010 2 2.5 2.5 x 1031 ~13 pb-1

5 156 7 x 1010 2 3.3 4.9 x 1031 ~25 pb-1

6 720 3 x 1010 2 6.7 4.0 x 1031 ~21 pb-1

7 720 5 x 1010 2 11.2 1.1 x 1032 ~60 pb-1

8 720 5 x 1010 2 11.2 1.1 x 1032 ~60 pb-1

9 720 5 x 1010 2 11.2 1.1 x 1032 ~60 pb-1

10 Ions

Total 200 – 300 pb-1

Push: bunches per beam, β*, bunch intensity

N bunches displaced for LHCb

Page 40: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Assumptions

8 hour fill length

5 hour turn around

20 hour luminosity lifetime

40% machine availability

rest of time: commissioning, machine development, access,

recovery etc.

No squeeze beyond β* = 2.0 m.

Aperture

Intensity limited to around 10% of nominal

LHC status and commissioning 4023/03/2009

Page 41: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Intensity limit in 2010?

LHC status and commissioning 4123/03/2009

“Cassandra has always been misunderstood

and misinterpreted as a madwoman or crazy

doomsday prophetess.” L. Fitton

Performance model to include

- energy dependence of cleaning efficiency

- quench limits.

The calculated total intensity limits at 5 TeV:

- are compatible with the figures shown

earlier (but not too much more)

Ralph Assmann

Page 42: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Stored energy

LHC status and commissioning 4223/03/2009

156 x 5 x1010 at 5 TeV – 6 MJ – already 5*Tevatron

Page 43: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

LHC status and commissioning 43

Stage B – 50 ns – just to make the point

Up to 1404 bunches

Parameter tolerances:

Tightened up. Optics/beta beating under control

Emittance conservation through the cycle

Collimator cleaning efficiency versus quench limit

Commission crossing angles.

Injection, ramp and partial squeeze

Long range beam-beam, effect on dynamic aperture,

Need for feedback

Orbit plus adequate control of tune and chromaticity through

snapback.

Lifetime and background optimization in physics

with a crossing angle and reduced aperture

Plus Machine Protection with increased intensity

23/03/2009

Page 44: Sector 34 incident present understanding€¦ · Bus-bar splice resistance measurements by means of nano-voltmeters Check old SM18 data Better protection Extended QPS system –local

Conclusions

Open heart surgery on-going – starting the stitching up

All splices to be measured carefully

Preventive measures to be deployed:

Relief valves, extended Quench Protection…

Beam scheduled for end September (tight)

Run through the winter - 10 month physics run aiming to

deliver a few 100s pb-1

LHC status and commissioning 4423/03/2009

It’s a beautiful machine but we will

have to progress carefully


Recommended