+ All Categories
Home > Documents > Sector Test – Preparation Layout in LSS7

Sector Test – Preparation Layout in LSS7

Date post: 16-Jan-2016
Category:
Upload: pisces
View: 53 times
Download: 0 times
Share this document with a friend
Description:
Sector Test – Preparation Layout in LSS7. Jan Uythoven (AB/BT) Thanks to Mike Lamont and the other ‘sector testers’. Sector Test: LSS7. Conditions and layout should be as close as possible to the final situation from injection to LSS7.R - PowerPoint PPT Presentation
Popular Tags:
9
1 Sector Test – Sector Test – Preparation Preparation Layout in LSS7 Layout in LSS7 Jan Uythoven (AB/BT) Thanks to Mike Lamont and the other ‘sector testers’
Transcript
Page 1: Sector Test – Preparation Layout in LSS7

1

Sector Test – PreparationSector Test – PreparationLayout in LSS7Layout in LSS7

Jan Uythoven (AB/BT)

Thanks to Mike Lamont and the other ‘sector testers’

Page 2: Sector Test – Preparation Layout in LSS7

Jan Uythoven, AB/BT

Chamonix@Divonne 2006, Layout in LSS7

Page 2

Sector Test:Sector Test:LSS7LSS7

Conditions and layout should be as close as possible to the final situation from injection to LSS7.R

By definition this is not possible for LSS7.R as this is the end of the sector to be tested

Beam 2

Beam

Dump

Shielding

Dispersion Suppressor

Long Straight SectionIP7

Page 3: Sector Test – Preparation Layout in LSS7

Jan Uythoven, AB/BT

Chamonix@Divonne 2006, Layout in LSS7

Page 3

What should not be What should not be installed in LSS7installed in LSS7

D4 and everything towards the IP not installed or not required

D3 may be installed, but will not see any beam Check interference with shielding behind dump

No collimators installed (no TCP, TCHS, TCM, TCG) Q6 & DFBM should be installed

Consists of 6 x MQTLH, not part of dispersion suppressor (up to Q8) Presently confirmed to be ready

not installed

DFBM

Page 4: Sector Test – Preparation Layout in LSS7

Jan Uythoven, AB/BT

Chamonix@Divonne 2006, Layout in LSS7

Page 4

Installation of Beam Dump Installation of Beam Dump in LSS7in LSS7

Temporary installation Beam dump same type as used for TI 8 tests

But SPS type transport system attached to it, to avoid installation of fixings in the ceiling

Positioned on temporary support (blocks)

‘Borrowed’ from TI 2 No additionally radiated equipment

Beam dump in place in TI 8 (smaller tunnel)

Additional shielding as used in TI 8

End of beam pipe

Page 5: Sector Test – Preparation Layout in LSS7

Jan Uythoven, AB/BT

Chamonix@Divonne 2006, Layout in LSS7

Page 5

Position of temporary Position of temporary dumpdump

not installed

Space for QRL return modulePosition dump at sufficient

distance from QRL return module:- mechanical interference- radiation

Q6 29 m

Page 6: Sector Test – Preparation Layout in LSS7

Jan Uythoven, AB/BT

Chamonix@Divonne 2006, Layout in LSS7

Page 6

Beam Dump AreaBeam Dump Area

Transport and installation of beam dump and additional shielding Need to be integrated in LHC planning

Path taken for the transport Time required for transport and installation (2 – 3 days) Possibly obstruct passage once installed

Details of obstruction from drawing with dump in position Assume 4 weeks for installation, operation, cool down,

removal Radiation issues

Remnant radiation: will effect access conditions after tests Check with work planned in this area

Need of radiation monitoring See talk of Helmut Vincke

Page 7: Sector Test – Preparation Layout in LSS7

Jan Uythoven, AB/BT

Chamonix@Divonne 2006, Layout in LSS7

Page 7

Other additional Other additional equipmentequipment

Additional BDI BCT half way between Q6 and beam dump: measure the intensities dumped on

the TED Additional BDI NOT installed

BLMs As there should be some already on Q6 BPM at Q6 will also indicate beam, besides the screen Radiation monitors near dump are foreseen

BTV Standard BTV installed less than 1 m in front of Q6

Vacuum pipe between sector valve on Q6 up to the beam dump Proposed is 4 sections of about 7 m each Stops about half a meter before dump, standard AlTi window with CC protection

against implosion The VADL installed on the left of Q6 includes an ion pump + pirani + penning

gauge for the part left of the sector valve No additional vacuum pumping or instrumentation required

Page 8: Sector Test – Preparation Layout in LSS7

Jan Uythoven, AB/BT

Chamonix@Divonne 2006, Layout in LSS7

Page 8

Access & VentilationAccess & Ventilation

Additional access door Temporary access door about 800 m in the arc 7 – 6 Access to part of sector 6 – 7 will not be possible

At least one day before the test (closing the zone) during the beam tests 2 – 3 days following the tests

See talk Pierre Ninin on the Temporary Access System

Collimation ventilation doors will not be installed For handling radioactive air produced at the collimators Not an issue for the sector tests (no collimators) Don’t want the doors, or chicanes for final layout, to ease

transport of equipment

Page 9: Sector Test – Preparation Layout in LSS7

Jan Uythoven, AB/BT

Chamonix@Divonne 2006, Layout in LSS7

Page 9

ConclusionsConclusions

Layout in LSS7 as will be used for the sector test will be identical to the nominal situation up to and including Q6.R7

Only additional equipment foreseen: Beam dump: TED from TI 2 and additional shielding BCT in front of TED Vacuum chamber between Q6 and TED

To be studied in more detail Transport of TED Effect of TED installation and radiation issues on the general

LHC planning Detailed layout drawing for sector test set-up in LSS7 to be

made in the coming months


Recommended