SEDA. UMAR AMIN 01270 HASNAIN JAVAID 01025 AMMAR SHAFI 6178 ALI FARAS 2722. Roles & Responsibilities. CONTENTS. Budget. Duration. Synopsis. Purpose. Scope. SEDA. Deliverables. Approach. - PowerPoint PPT Presentation
Popular Tags:
19
PROJECT MANAGEMENT
Transcript
Page 1: SEDA

PROJECT MANAGEMENT

Page 2: SEDA

PROJECT MANAGEMENT

SEDAUMAR AMIN 01270

HASNAIN JAVAID 01025AMMAR SHAFI 6178 ALI FARAS 2722

Page 3: SEDA

Deliverables

Scope

CONTENTS Roles & Responsibilities

Budget

Duration

Synopsis

Purpose

SEDA

Approach

Work Break down Structure

Communication Plan

Risk Analysis

R & R MatrixPROJECT MANAGEMENT

Page 4: SEDA

Roles & Responsibilities

Hasnain javaid (PM)

monitoring and controlling project; approving project changes; quality

assurance, Donors Relations

PROJECT MANAGEMENT

Page 5: SEDA

Contents Amount In $ In RupeesDBMS system for billing

341$ 30,000

ARCHITECTURE 398 35,000

Meeting with the technical people and society

227 20,000

Site Analysis 170 15,000

Examination details 170 15,000

Solar Plates 28409 2,500,000

Wires 1705 150,000

Poles 1705 150,000

Construction of a control room and labor

3239 285000

Total 36400$ Rs.3,200,000

PROJECT MANAGEMENT

Page 6: SEDA

PROJECT MANAGEMENT Duration

Ending: 1st March 2012

Starting: 5th Dec 2011

3.25 months

(13 Weeks)

Phase I: Research and data analysis (2 week)

Phase II: (Planning) Sponsor meetings and finalize details (3 weeks)

Phase III: Construction and installing (4 weeks)

Phase IV: Training of staff (2 week)

Phase V: Activation of cells (1 week)

Phase VI: Closure of project (1 week)

Page 7: SEDA

Synopsis

This project is related to the

development of the small villages

where short fall of electricity is much more as compared

to the cities.

This project will start initially from

certain small villages of GUJRAT and would be further

continued to other areas of Pakistan in

future.

we will target 3 villages initially. Basically we will

provide electricity using our solar

plants situated at a vacant site near

GUJRAT.

PROJECT MANAGEMENT

Page 8: SEDA

BUSINESS NEED

The basic purpose of this project is to help Pakistan government and people of the Pakistan. To help Pakistanis villagers which are badly affected by the energy crisis. Change their way of living

style and mobilize local community.

PROJECT MANAGEMENT

Page 9: SEDA

PROJECT MANAGEMENT

Page 10: SEDA

PROJECT MANAGEMENT

To fulfill electricity needs

of the local community and

give them relaxation.

Our aim is that no more load

shedding provides

electricity on cheap rates and

contributes towards the

development of Pakistan.

we can create more value to the society and in a result better and educated society

will develop.

Page 11: SEDA

PROJECT MANAGEMENT

Major DeliverablesTo provide them solar energy electricity on

monthly bills.

To educate them the value of energy

Creating job opportunities

Page 12: SEDA

Approach:

PROJECT MANAGEMENT

Page 13: SEDA

COMMUNICATION PLANNING

PROJECT MANAGEMENT

Page 14: SEDA

Communication Format Frequency Distribution

Group meeting Intranet Daily 11 am-1 pm (Except Saturdays and Sundays).

Team members will access to this material

Weekly Report Emails and meetings

End of the week. Performance of the member and updates regarding the project.

Technical Reports Email/Phone and also in meetings

All Mondays IT Department

Budget Discussion

MS Excel Weekly Sponsor, Project manager.

•Procurement•Installation

Intranet/E-mail Daily basis at the end of the day a list will be made for the items that will be required by the manager for installation of solar plates/panels.

Procurement, finance and manager will discuss these problems.

Milestones Email, Intranet and meetings

Weekly All stakeholders.PROJECT MANAGEMENT

Page 15: SEDA

Roles & Responsibility Matrix:Project Item

Sponsor

Project Manager

Public Project Team

Survey C A I R

Group/stakeholders Meetings

I R C R AND A

Procurement

R C I A

Installation

I A C R

R RESPONSIBLE

A ACOUNTABLE

C CONSULTED

I INFORMED

PROJECT MANAGEMENT

Page 16: SEDA

RISK REGISTER

PROJECT MANAGEMENT

Page 17: SEDA

no

Description of risk

Impact on project Level of risk

change

Date of review

Mitigation actions

responsibility

1 SPONSER Delay in the project completion.

If project sponsors reduce then some facilities will be cut down

high

No change

01.12.11

Re-scope project, focusing on time and resources.

Project manager

2 Villagers response

Lack of interest or support of villagers will give tough time to project.

highNo change

20.11.11

Show their benefits while interviewing them

Project team

3 Ownership of beneficiaries after project closure.

Project will be grounded and the facility will be shut down soon after its hand overing to target society.

low

No change

05.03.12

Take a group of people from the village and educate them about the working (technicality) of the project.

Project Manager

4 Risk of late Billing

Company would face financial problems due to non payments of Utility bills, Staff salary

medium

No change

T.B.C Cut down the services

Finance manager

Page 18: SEDA

PROJECT MANAGEMENT

WBS:Ms word

Page 19: SEDA

PROJECT MANAGEMENT


Recommended