PITTSBURGH, PENNSYLVANIA, MAY 2-4 2013

COLLAPSE ANALYSIS OF A

METAL TRUSS STRUCTURE

Chiara Crosti, Franco Bontempi

“Sapienza” University of Roma, [email protected], [email protected]

Page 2: Sei2013 crosti

[email protected]

2/22

Radiohead’s concert, 2012

Image taken from: http://abcnews.go.com/Entertainment/stage-collapses-

radiohead-concert

killing/story?id=16587415#.UGrriE3A9_c

Country music concert, 2011

Image taken from: http://www.billboard.com/news/

Big valley Jamboree, 2009

Image taken from: http://www.cbc.ca/news/canada/edmonton/story/2012/01/

20/edmonton-charges-stayed-big-valley-jamboree.html

Jovanotti’s concert, 2011

Image taken from: http://tg24.sky.it/tg24/cronaca/photogallery/201

1/12/12/crollo_palco_concerto_jovanotti_trieste

.html

FORENSIC ASPECTS

Page 3: Sei2013 crosti

http://www.udine20.it/wp-content/uploads/2012/03/palco-laura-pausini.jpg

CASE STUDY

AIM OF THIS WORK:

The aim of this work was not to define who made the mistake, but:

a. to investigate which kind of “error” could have compromised the safety of

this structure; and,

b. to evaluate the consequence of these “errors” in terms of global structural

response.

[email protected]

3/22 FORENSIC ASPECTS

Page 4: Sei2013 crosti

A temporary structure can be defined as a structure that can be readily and completely

dismantled and removed from the site between periods of actual use.

They comprise 3 distinct elements:

1. The foundations – designed to both support the structure and hold it down (due to wind-

uplift, sliding or over-turning).

2. The superstructure – to carry all the imposed vertical (gravity) loads safely to the ground,

e.g. people, equipment.

3. The stability system – bracing and other specialist members to resist horizontal loads, e.g.

due to crowd movement and wind loads.

TEMPORARY DEMOUNTABLE STRUCTURES (TDM)

[email protected]

4/22 FORENSIC ASPECTS

Page 5: Sei2013 crosti

A temporary structure can be defined as a structure that can be readily and completely

dismantled and removed from the site between periods of actual use.

They comprise 3 distinct elements:

1. The foundations – designed to both support the structure and hold it down (due to wind-

uplift, sliding or over-turning).

2. The superstructure – to carry all the imposed vertical (gravity) loads safely to the ground,

e.g. people, equipment.

3. The stability system – bracing and other specialist members to resist horizontal loads, e.g.

due to crowd movement and wind loads.

Management & Administration

Design Built-up Load-in

EVENT

Load-out Break-down

TEMPORARY DEMOUNTABLE STRUCTURES (TDM)

[email protected]

4/22 FORENSIC ASPECTS

Page 6: Sei2013 crosti

SWISS CHEESE MODEL (Reason, 1997)

FORENSIC ASPECTS

[email protected]

5/22

Page 7: Sei2013 crosti

Management &

Administration

Inadequate site

investigation

Inappropriate

ground condition

Inadequate safety

plan

………..

Inadequate

structural design

Failure to adopt

Building Codes

Inadequate loads

estimation

……..

Improper construction procedure

Improper working position

Breach of regulation or code of

practice

………..

SWISS CHEESE MODEL (Reason, 1997)

FORENSIC ASPECTS

[email protected]

6/22

Built-up Load-in Design

Page 8: Sei2013 crosti

Management &

Administration

Inadequate site

investigation

Inappropriate

ground condition

Inadequate safety

plan

………..

Inadequate

structural design

Failure to adopt

Building Codes

Inadequate loads

estimation

……..

Improper construction procedure

Improper working position

Breach of regulation or code of

practice

………..

COLLAPSE

SWISS CHEESE MODEL (Reason, 1997)

FORENSIC ASPECTS

[email protected]

6/22

Built-up Load-in Design

Page 9: Sei2013 crosti

BUILD-UP PHASES (CASE STUDY)

Positioning on the ground

of the load distribution

plates

Positioning of the bases of

the columns

Assembling on the floor of

the roof structure called

“Space Roof”

Assempled and anchored

secondary beams

Lifting the columns of the

roof structure and

anchoring the top of the

columns to the roof

Assembling of the hung

beams and other

components of the stage

(lighting, video, etc.)

Rigging phase Delivery of the structure

for its use

Technical-administrative

testing

COLLAPSE

INVESTIGATION ON TECHINAL CAUSES OF THE COLLAPSE

[email protected]

7/22

Page 10: Sei2013 crosti

INVESTIGATION ON TECHINAL CAUSES OF THE COLLAPSE

[email protected]

8/22

BUILD-UP PHASES (CASE STUDY)

Page 11: Sei2013 crosti

INVESTIGATION ON TECHINAL CAUSES OF THE COLLAPSE

[email protected]

8/22

BUILD-UP PHASES (CASE STUDY)

Page 12: Sei2013 crosti

COLLAPSE

INVESTIGATION ON TECHINAL CAUSES OF THE COLLAPSE

[email protected]

8/22

BUILD-UP PHASES (CASE STUDY)

Page 13: Sei2013 crosti

15/22

FINITE ELEMENT MODEL

INVESTIGATION ON TECHINAL CAUSES OF THE COLLAPSE

[email protected]

9/22

ton

A

B

C

1 2

16

m

21

.8 m

33 m

a

b

c d e

f

g h i l m

a (ton) 8.7

b (ton) 6.5

c (ton) 8.7

d (ton) 2.3

e (ton) 2.3

f (ton) 7.75

g (ton) 4.3

h (ton) 5.6

I (ton) 5.6

l (ton) 6.7

m (ton) 6.7

MATERIAL: ALUMINIUM

EN AW-6082 T6

Page 14: Sei2013 crosti

EUROCODE

φ 0.005

kc 1.224745 > 1

nc 1

ks 1.224745 > 1

ns 1

φ0 0.005

N 2.25E+05 N

φN 1.13E+03 N

This structure is designed to be indoor; therefore the structural elements were

designed to carry vertical loads but may not have been designed for lateral loads. That

could be a fatal error in the design phase, in fact, following what prescribed in the

UNI ENV 1999-1-1:2007, in order to run global analyses, it is necessary to take

account of horizontal forces due to the imperfections of the elements composing the

structure.

FAILURE TO ADOPT STANDARD PROCEDURES

INVESTIGATION ON TECHINAL CAUSES OF THE COLLAPSE

[email protected]

NO HORIZONTAL LOADS

NO BRACING MEMBERS

10/22

Page 15: Sei2013 crosti

Top of the column

Bottom of the column

Rigid or Hinged

Rigid or Hinged

IMPROPER CONSTRUCTION PROCEDURE

INVESTIGATION ON TECHINAL CAUSES OF THE COLLAPSE

[email protected]

11/22

Page 16: Sei2013 crosti

[email protected]

1 kN

Rigid

Rigid

A

1 kN

Hinged

Rigid

B

1 kN

Rigid

Hinged

C

Columns going through the space roof Column not going through the space roof

1 kN

Rigid

Rigid

A

1 kN

Hinged

Rigid

B

1 kN

Rigid

Hinged

C

Node 42 Node 42

INVESTIGATION ON TECHINAL CAUSES OF THE COLLAPSE

A

B

C

12/22

Page 17: Sei2013 crosti

RIGID HINGED RIGID

A

A

B

B

C

C

RIGID RIGID HINGED

RIGID HINGED RIGID

RIGID RIGID HINGED

16 m

14 m

INVESTIGATION ON TECHINAL CAUSES OF THE COLLAPSE

A

B

C

λBuckling= 13.57

λBuckling= 8.26

λBuckling= 2.61

λ: Linear Buckling Eigenvalue

[email protected]

13/22

Page 18: Sei2013 crosti

0

3

6

9

12

-1,0 -0,8 -0,6 -0,4 -0,2 0,0

Load

Facto

r (v

erti

cal

load

s)

Horizontal Displacement node 42 (m)

RIGID

HINGED

B C

RIGID

RIGID

A

RIGID

HINGED

B

A

B

C

ULF=11.3 ULF=7.86 ULF=1.53

INVESTIGATION ON TECHINAL CAUSES OF THE COLLAPSE

FINITE ELEMENT ANALYSIS RESULTS (Nonlinear)

[email protected]

14/22

Page 19: Sei2013 crosti

Cut-off bar,

No tension element

Translation Stiffness

Beam Rigid

link

Column

Hinge

Rigid

Unilateral

INVESTIGATION ON TECHINAL CAUSES OF THE COLLAPSE

FINITE ELEMENT ANALYSIS RESULTS (Nonlinear)

[email protected]

15/22

Page 20: Sei2013 crosti

-2,5E+04

-2,0E+04

-1,5E+04

-1,0E+04

-5,0E+03

0,0E+00

5,0E+03

-0,1 -0,08 -0,06 -0,04 -0,02 0 0,02 0,04 0,06 0,08 0,1

Lo

ad

(N

)

Displacement (m)

Compression Tension

Maximum Compressive Strength = 2100 Kg

Mechanical properties for the “cut-off bar”

[email protected]

16/22 INVESTIGATION ON TECHINAL CAUSES OF THE COLLAPSE

Page 21: Sei2013 crosti

0

2

4

6

8

10

12

-0,40 -0,35 -0,30 -0,25 -0,20 -0,15 -0,10 -0,05 0,00

Lo

ad

Fa

cto

r (v

erti

cal

loa

ds)

Horizontal Displacement node 42 (m)

A

D

Decreasing of 63 %

1 2 3

4 5

6 7

8

INVESTIGATION ON TECHINAL CAUSES OF THE COLLAPSE

FINITE ELEMENT ANALYSIS RESULTS (Nonlinear)

[email protected]

17/22

Case D: Column C2

Page 22: Sei2013 crosti

1 2 3

4 5

6 7

8

Compression Tension

INVESTIGATION ON TECHINAL CAUSES OF THE COLLAPSE

FINITE ELEMENT ANALYSIS RESULTS (Nonlinear)

[email protected]

18/22

5

6

3

4

8

7

Page 23: Sei2013 crosti

1 2 3

4 5

6 7

8

INVESTIGATION ON TECHINAL CAUSES OF THE COLLAPSE

FINITE ELEMENT ANALYSIS RESULTS (Nonlinear)

[email protected]

19/22

Page 24: Sei2013 crosti

INVESTIGATION ON TECHINAL CAUSES OF THE COLLAPSE

[email protected]

20/22

Page 25: Sei2013 crosti

INVESTIGATION ON TECHINAL CAUSES OF THE COLLAPSE

[email protected]

21/22

Page 26: Sei2013 crosti

CONCLUSION

[email protected]

Inadequate site

investigation

SWISS CHEESE MODEL (Reason, 1997)

Management &

Administration Design Built-up Load-in

COLLAPSE

1 2 3

4

5

6 7

8

NO HORIZONTAL LOADS

NO BRACING MEMBERS

Failure to adopt

Building Codes

Improper construction

procedure

COLLAPSE

22/22

Page 27: Sei2013 crosti

Inadequate site

investigation

SWISS CHEESE MODEL (Reason, 1997)

[email protected]

Management &

Administration Design Built-up Load-in

COLLAPSE

NO HORIZONTAL LOADS

NO BRACING MEMBERS

Failure to adopt

Building Codes

Improper construction

procedure

COLLAPSE

22/22 CONCLUSION


Recommended