Seite 1
COOLING AND HEATING OF BUILDINGSBY ACTIVATING THE THERMAL MASS
WITH EMBEDDED HYDRONIC PIPE SYSTEMS
• Bjarne W. Olesen, Ph.D.,• Head of R&D, Wirsbo-VELTA, Germany• Professor, Technical University of Denmark
EMBEDDED PIPE SYSTEMS
Max. - Min. surface temperatures
40
17
27
17
35
20
29
20
15
20
25
30
35
40
45
Floor
Ceiling Wall
oC
HeatingCooling
Perimeter
SURFACE HEATING AND COOLINGHeat transfer coefficient
8,08,0
6,0
11,011,0
7,0
5,56,5
7,5
8,5
9,5
10,5
11,5
Floor
Ceiling
Wall
W/m2K
HeatingCooling
COOLING CAPACITY• Cooling capacity in W/m²for the following example• 17 mm PEX-pipe• 45 mm concrete above pipes• Concrete ~ 1,2 W/mK• Space temperature 26 °C• Supply water temperature 14 °C• Return water temperature 19 °C
75150300
0,01
0,1
25
3746
2027 32
0
10
20
30
40
50
W/m2
T mm
Rb m2K/W
Max. heating-cooling-capacity
160
72
42
99
165
42
99
42
020406080100120140160180200
Floor
ceiling wall
HeatingCooling
Perimeter
W/m2
Seite 2
RADIANT FLOOR COOLING
No cooling - decreased performance Low energy costs Low operation costs
Constant temperature Draught Noise SBS High energy costs High operation costs
Temperature ramps Reasonable energy costs Low operation costs
COMFORT-PERFORMANCE
People 100
Energy 1
COMFORT-PERFORMANCE THERMAL COMFORT
• OPERATIVE TEMPERATURE• -0,5 < PMV < +0,5 ; PPD < 10 %
• SPACES WITH MAINLY SEDENTARYOCCUPANTS :
– SUMMER CLOTHING 0,5 clo– ACTIVITY LEVEL 1,2 met
• 23 °C < to < 26 °C.
COMFORT CRITERIA
EN-ISO 7730
Comfort requirements Temperature rangeClassPPD PMV Winter
1.0 clo 1.2met
Summer0.5 clo 1.2
met
[%] [/] [°C] [°C]
A < 6 -0.2 < PMV < + 0.2 21-23 23.5-25.5
B < 10 -0.5 < PMV < + 0.5 20-24 23.0-26.0
C < 15 -0.7 <PMV < + 0.7 19-25 22.0-27.0
CR 1752
Definition of comfort conditions according to DIN 1946
Optimal range
Allowed temperatures
Allowedtemperatures
Seite 3
Airport Bangkok Airport Bangkok
Figure 1
Figure 2
SBIA Concourse Case 1East-West oriented, Fritted Glass 76% -> 0%
constant temperature of 13°C for floor coolingrealistic schedules for occupancy
10121416182022242628303234363840424446
2496 2520 2544
Tem
pera
ture
in °C
AmbientAir (Conditioned Levels)Air (Lower Unconditioned Zone)Air (Higher Unconditioned Zone)Floor Cooling InletFloor Cooling OutletSurface of Cooled FloorOperative Temperature
Figure 3
SBIA Concourse Case 2East-West oriented, Fritted Glass 76% -> 0%
constant inlet temperature of 13°C for floor coolingrealistic schedules for occupancy
0
25
50
75
100
125
150
175
200
225
250
275
300
2496 2520 2544
Coo
ling
Pow
er in
kW
Total Sensible + Latent LoadTotal Sensible Cooling LoadFloor Cooling FluidSensible Cooling Recirculating AirSensible Cooling Supply AirDehumidifcation Supply Air
Figure 4
Seite 4
SBIA Terminal BuildingCooling loads for Terminal Building
realistic schedules for occupancy
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
2496 2520 2544
Coo
ling
Pow
er in
kW
Total Sensible + Latent LoadTotal Sensible Cooling LoadFloor Cooling FluidSensible Cooling Recirculating AirSensible Cooling Supply AirDehumidifcation Supply Air
Figure 5
SBIA Terminal Buildingupper level, check in
realistic schedules for occupancy
1012141618202224262830323436384042444648
2496 2520 2544
Tem
pera
ture
in °C
Ambient [°C]Air (Conditioned Levels) [°C]Air (Lower Unconditioned Zone) [°C]Air (Higher Unconditioned Zone) [°C]Floor Cooling Inlet [°C]Floor Cooling Outlet [°C]Surface of Cooled Floor [°C]Operative Temperature [°C]
Figure 6
Figure 7 FIGURE 8
Airport Bangkok OPEN AIR THEATER BREGENZ
Seite 5
OPEN AIR THEATER BREGENZ
ROOM 404
ROOM304
Hall
Sky-light
Window
WindowSteelsupport
Pipes
BREGENZ
OPEN AIR THEATER BREGENZBREGENZ
Operative Temperatur 08.08-14.08.1999
14
16
18
20
22
24
26
28
30
32
34
7.8.9812:00
8.8.980:00
8.8.9812:00
9.8.980:00
9.8.9812:00
10.8.980:00
10.8.9812:00
11.8.980:00
11.8.9812:00
12.8.980:00
12.8.9812:00
13.8.980:00
13.8.9812:00
14.8.980:00
14.8.9812:00
15.8.980:00
15.8.9812:00
Zeit
Tem
pera
tur [
°C]
Aussentemperatur Büro 304 To Flur To Büro 404 To
BUILDING 1
0
10
20
30
40
50
60
70
80
<20 20-22 22-25 25-26 26-27 >27Perc
enta
ge o
f ope
rativ
e te
mpe
ratu
re a
ccor
ding
to D
IN 1
946
[%]
Hallway Room 304 Room 404 Room 414 Total for rooms 304, 404, 414 CONCRETE SLAB COOLING/HEATING
InsulationFloor
Concrete
Reinforcement
Pipe
Room
Room
Window
Seite 6
CALCULATED TEMPERATURES CALCULATED TEMPERATURES
CALCULATED TEMPERATURES
Calculated cooling-heating capacity
Floor : 9 W/m2 5 W/m2 Ceiling : 39 W/m2 14 W/m2
Totat: 48 W/m2 19 W/m2
Floor : 9 W/m2 5 W/m2 Ceiling : 47 W/m2 16 W/m2
Total 56 W/m2 21 W/m2
Floor : 26 W/m2 15 W/m2 Ceiling : 37 W/m2 14 W/m2
Total : 63 W/m2 29 W/m2
Cooling HeatingSupply water temperature: 16 °C 25 °CReturn water temperature: 20 °C Space temperature: 26 °C 20 °C
CONCRETE SLABCOOLING/HEATING
• Building requirements– Well insulated– Window U-values < 1,2 W/m2K– Solar shielding– Cooling load ~30-50 W/m2
– Heat load < 20 W/m2 only system– 20 W/m2 < Heat load < 30 W/m2 optimal control– 30 W/m2 < Heat load , additional system
CONCRETE SLABCOOLING/HEATING
• Heating and cooling of multi-storeybuildings
• Offices, schools, commercial buildings• Heat storage/transfer between day and
night• Heat transfer between south and north
facing rooms ?• Use of dynamic computer simulations ?
Seite 7
COMPUTER-SIMULATION COMPUTER-SIMULATION
COMPUTER-SIMULATION
CONTROL OF A COMBINED FLOOR HEATING-COOLING SYSTEM
Boiler Chiller
Room temp.-Humidity
Outside temp.
SupplyLimiter
ReturnMixing valve
Valves
VIVALDI
Operation time
Mai to SeptemberMean water temperature according to
outside temperatureOperation 24 hours
090518 – 60901
22-60902
°C % % %
<20 0,0 0,0 0,0
20-22 11,3 3,9 1,8
22-25 88,0 87,6 91,6
25-26 0,7 6,3 5,1
26-27 0,0 1,7 1,3
Temperatureinterval
>27 0,0 0,5 0,1
hours 1217 515 412Pump running
% 33 14 11
ART MUSEUMBREGENZ
Seite 8
ART MUSEUM IN BREGENZ
• Design requirements– Air temperature variations during a day within 4 K– Relative humidity variations less than 6 % during a day.– Seasonal variations between 48 and 58 %– Room temperature in winter 18 oC to 22 oC– Room temperature in summer 22 oC to 26 oC, occasional up to 28 oC
• Design load 250 persons pr. day, 2 hours• Displacement ventilation < 0,2 h-1
• Floor area 2.800 m² , 4 floors• 28.000 m plastic pipes embedded in walls and floor slabs
ART MUSEUM BREGENZ
• 3.750 m² floor area• 4.725 m² embedded pipes• Condensing boiler• Ventilation 750 m3/h per floor (first
design was 25.000 m3/h
ART MUSEUM IN BREGENZ ARTMUSEUMBREGENZ
ART MUSEUM BREGENZ -Measurements
151617181920212223242526272829303132333435
2. O
kt
3. O
kt
4. O
kt
5. O
kt
6. O
kt
7. O
kt
8. O
kt
9. O
kt
10. O
kt
11. O
kt
12. O
kt
13. O
kt
14. O
kt
15. O
kt
°C
05101520253035404550556065707580859095100 %
t-Luft-5min-mean
t-Boden-5min-mean
rF-5min-meanV 230 500-1G 300-R !! V 200???
Humidity
Air Temp.
Floor Temp
Office buildingStuttgart
• 1998• 11.000 m²• 3-4 floors• Operable windows• Co-generation• Solar collectors• Absorption cooling• Free cooling• Compressor cooling• Displacement ventilation
Seite 9
Displacement ventilationAir supplyIntegrated convector for heating
Operative temperature sensor
Air temperature sensor
Data transmission
Operative temperatursensor
Data transmission
StuttgartStuttgart - 1999
5
10
15
20
25
30
35
40
3.8
4.8
5.8
6.8
7.8
8.8
9.8
10.8
11.8
12.8
13.8
14.8
15.8
16.8
17.8
18.8
19.8
20.8
21.8
22.8
23.8
24.8
25.8
26.8
27.8
28.8
29.8
30.8
31.8
Zeit
Tem
pera
tur
[°C
]
Luft Operative Taupunkt Außen
Seite 10
Stuttgart
Stuttgart 24.07. - 28.07, 2000
20
21
22
23
24
25
26
24. J
ul
24. J
ul
25. J
ul
25. J
ul
26. J
ul
26. J
ul
27. J
ul
27. J
ul
28. J
ul
28. J
ul
29. J
ul
Zeit
Tem
pera
tur [
°C]
O1-Operative Büro 4. Stock Fenster-Ost F1-Fläche 4. Stock RucklaufO-Operative Büro 5. Stock Fenster-West O6-Operative Büro 5. Stock Fenster-Ost
StuttgartBUILDING 3
0
10
20
30
40
50
60
70
80
90
100
<20 20-22 22-25 25-26 26-27 >27
perc
enta
ge in
ope
rativ
e te
mpe
ratu
re ra
nges
ac
cord
ing
to D
IN 1
946
4th floor window west 4th floor window south 5th floor window west5th floor window east 5th floor middle meeting roomall offices except middle
STUTTGARTBUILDING 3
0
10
20
30
40
50
60
70
80
<1 (1-2) (2-3) (3-4) (4-5) (5-6) >6chan
ge in
ope
rativ
e te
mpe
ratu
re d
urin
g a
day
(8-1
8) [%
]
4th floor window west 4th floor window south 5th floor window west5th floor window east 5th floor middle meeting roomall offices except middle
Office building in Hamburg
• 2000• 14.000 m²• 7.500 m² slab cooling• Baseboard heaters• 2 ach, 18 °C• Operable windows
Transportation of modules
Seite 11
INSTALLATION
PRE-FABRICATION
PRE-FABRICATION
CONCLUSIONS
• Hydraulic heating/cooling system with pipesembedded in the building structure is aninteresting alternative to full air conditioning
– High temperature cooling-low temperature heating– No noise– No draught– Low installation and running costs– Lower peak load and reduced equipment size– Lower building height– Combined with mechanical ventilation– Reduced capacity?– Acoustic?– Latent load?