+ All Categories
Home > Documents > Seite 1 - ashraethailand · Seite 1 COOLING AND HEATING OF BUILDINGS BY ACTIVATING THE THERMAL MASS...

Seite 1 - ashraethailand · Seite 1 COOLING AND HEATING OF BUILDINGS BY ACTIVATING THE THERMAL MASS...

Date post: 23-Jul-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
11
COOLING AND HEATING OF BUILDINGS BY ACTIVATING THE THERMAL MASS WITH EMBEDDED HYDRONIC PIPE SYSTEMS Bjarne W. Olesen, Ph.D., Head of R&D, Wirsbo-VELTA, Germany Professor, Technical University of Denmark EMBEDDED PIPE SYSTEMS Max. - Min. surface temperatures 40 17 27 17 35 20 29 20 15 20 25 30 35 40 45 Floor Ceiling Wall o C Heating Cooling Perimeter SURFACE HEATING AND COOLING Heat transfer coefficient 8,0 8,0 6,0 11,0 11,0 7,0 5,5 6,5 7,5 8,5 9,5 10,5 11,5 Floor Ceiling Wall W/m 2 K Heating Cooling COOLING CAPACITY Cooling capacity in W/m²for the following example 17 mm PEX-pipe 45 mm concrete above pipes Concrete ~ 1,2 W/mK Space temperature 26 °C Supply water temperature 14 °C Return water temperature 19 °C 75 150 300 0,01 0,1 25 37 46 20 27 32 0 10 20 30 40 50 W/m 2 T mm R b m 2 K/W Max. heating-cooling-capacity 160 72 42 99 165 42 99 42 0 20 40 60 80 100 120 140 160 180 200 Floor ceiling wall Heating Cooling Perimeter W/m 2
Transcript
Page 1: Seite 1 - ashraethailand · Seite 1 COOLING AND HEATING OF BUILDINGS BY ACTIVATING THE THERMAL MASS WITH EMBEDDED HYDRONIC PIPE SYSTEMS • Bjarne W. Olesen, Ph.D., • Head of R&D,

Seite 1

COOLING AND HEATING OF BUILDINGSBY ACTIVATING THE THERMAL MASS

WITH EMBEDDED HYDRONIC PIPE SYSTEMS

• Bjarne W. Olesen, Ph.D.,• Head of R&D, Wirsbo-VELTA, Germany• Professor, Technical University of Denmark

EMBEDDED PIPE SYSTEMS

Max. - Min. surface temperatures

40

17

27

17

35

20

29

20

15

20

25

30

35

40

45

Floor

Ceiling Wall

oC

HeatingCooling

Perimeter

SURFACE HEATING AND COOLINGHeat transfer coefficient

8,08,0

6,0

11,011,0

7,0

5,56,5

7,5

8,5

9,5

10,5

11,5

Floor

Ceiling

Wall

W/m2K

HeatingCooling

COOLING CAPACITY• Cooling capacity in W/m²for the following example• 17 mm PEX-pipe• 45 mm concrete above pipes• Concrete ~ 1,2 W/mK• Space temperature 26 °C• Supply water temperature 14 °C• Return water temperature 19 °C

75150300

0,01

0,1

25

3746

2027 32

0

10

20

30

40

50

W/m2

T mm

Rb m2K/W

Max. heating-cooling-capacity

160

72

42

99

165

42

99

42

020406080100120140160180200

Floor

ceiling wall

HeatingCooling

Perimeter

W/m2

Page 2: Seite 1 - ashraethailand · Seite 1 COOLING AND HEATING OF BUILDINGS BY ACTIVATING THE THERMAL MASS WITH EMBEDDED HYDRONIC PIPE SYSTEMS • Bjarne W. Olesen, Ph.D., • Head of R&D,

Seite 2

RADIANT FLOOR COOLING

No cooling - decreased performance Low energy costs Low operation costs

Constant temperature Draught Noise SBS High energy costs High operation costs

Temperature ramps Reasonable energy costs Low operation costs

COMFORT-PERFORMANCE

People 100

Energy 1

COMFORT-PERFORMANCE THERMAL COMFORT

• OPERATIVE TEMPERATURE• -0,5 < PMV < +0,5 ; PPD < 10 %

• SPACES WITH MAINLY SEDENTARYOCCUPANTS :

– SUMMER CLOTHING 0,5 clo– ACTIVITY LEVEL 1,2 met

• 23 °C < to < 26 °C.

COMFORT CRITERIA

EN-ISO 7730

Comfort requirements Temperature rangeClassPPD PMV Winter

1.0 clo 1.2met

Summer0.5 clo 1.2

met

[%] [/] [°C] [°C]

A < 6 -0.2 < PMV < + 0.2 21-23 23.5-25.5

B < 10 -0.5 < PMV < + 0.5 20-24 23.0-26.0

C < 15 -0.7 <PMV < + 0.7 19-25 22.0-27.0

CR 1752

Definition of comfort conditions according to DIN 1946

Optimal range

Allowed temperatures

Allowedtemperatures

Page 3: Seite 1 - ashraethailand · Seite 1 COOLING AND HEATING OF BUILDINGS BY ACTIVATING THE THERMAL MASS WITH EMBEDDED HYDRONIC PIPE SYSTEMS • Bjarne W. Olesen, Ph.D., • Head of R&D,

Seite 3

Airport Bangkok Airport Bangkok

Figure 1

Figure 2

SBIA Concourse Case 1East-West oriented, Fritted Glass 76% -> 0%

constant temperature of 13°C for floor coolingrealistic schedules for occupancy

10121416182022242628303234363840424446

2496 2520 2544

Tem

pera

ture

in °C

AmbientAir (Conditioned Levels)Air (Lower Unconditioned Zone)Air (Higher Unconditioned Zone)Floor Cooling InletFloor Cooling OutletSurface of Cooled FloorOperative Temperature

Figure 3

SBIA Concourse Case 2East-West oriented, Fritted Glass 76% -> 0%

constant inlet temperature of 13°C for floor coolingrealistic schedules for occupancy

0

25

50

75

100

125

150

175

200

225

250

275

300

2496 2520 2544

Coo

ling

Pow

er in

kW

Total Sensible + Latent LoadTotal Sensible Cooling LoadFloor Cooling FluidSensible Cooling Recirculating AirSensible Cooling Supply AirDehumidifcation Supply Air

Figure 4

Page 4: Seite 1 - ashraethailand · Seite 1 COOLING AND HEATING OF BUILDINGS BY ACTIVATING THE THERMAL MASS WITH EMBEDDED HYDRONIC PIPE SYSTEMS • Bjarne W. Olesen, Ph.D., • Head of R&D,

Seite 4

SBIA Terminal BuildingCooling loads for Terminal Building

realistic schedules for occupancy

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

2496 2520 2544

Coo

ling

Pow

er in

kW

Total Sensible + Latent LoadTotal Sensible Cooling LoadFloor Cooling FluidSensible Cooling Recirculating AirSensible Cooling Supply AirDehumidifcation Supply Air

Figure 5

SBIA Terminal Buildingupper level, check in

realistic schedules for occupancy

1012141618202224262830323436384042444648

2496 2520 2544

Tem

pera

ture

in °C

Ambient [°C]Air (Conditioned Levels) [°C]Air (Lower Unconditioned Zone) [°C]Air (Higher Unconditioned Zone) [°C]Floor Cooling Inlet [°C]Floor Cooling Outlet [°C]Surface of Cooled Floor [°C]Operative Temperature [°C]

Figure 6

Figure 7 FIGURE 8

Airport Bangkok OPEN AIR THEATER BREGENZ

Page 5: Seite 1 - ashraethailand · Seite 1 COOLING AND HEATING OF BUILDINGS BY ACTIVATING THE THERMAL MASS WITH EMBEDDED HYDRONIC PIPE SYSTEMS • Bjarne W. Olesen, Ph.D., • Head of R&D,

Seite 5

OPEN AIR THEATER BREGENZ

ROOM 404

ROOM304

Hall

Sky-light

Window

WindowSteelsupport

Pipes

BREGENZ

OPEN AIR THEATER BREGENZBREGENZ

Operative Temperatur 08.08-14.08.1999

14

16

18

20

22

24

26

28

30

32

34

7.8.9812:00

8.8.980:00

8.8.9812:00

9.8.980:00

9.8.9812:00

10.8.980:00

10.8.9812:00

11.8.980:00

11.8.9812:00

12.8.980:00

12.8.9812:00

13.8.980:00

13.8.9812:00

14.8.980:00

14.8.9812:00

15.8.980:00

15.8.9812:00

Zeit

Tem

pera

tur [

°C]

Aussentemperatur Büro 304 To Flur To Büro 404 To

BUILDING 1

0

10

20

30

40

50

60

70

80

<20 20-22 22-25 25-26 26-27 >27Perc

enta

ge o

f ope

rativ

e te

mpe

ratu

re a

ccor

ding

to D

IN 1

946

[%]

Hallway Room 304 Room 404 Room 414 Total for rooms 304, 404, 414 CONCRETE SLAB COOLING/HEATING

InsulationFloor

Concrete

Reinforcement

Pipe

Room

Room

Window

Page 6: Seite 1 - ashraethailand · Seite 1 COOLING AND HEATING OF BUILDINGS BY ACTIVATING THE THERMAL MASS WITH EMBEDDED HYDRONIC PIPE SYSTEMS • Bjarne W. Olesen, Ph.D., • Head of R&D,

Seite 6

CALCULATED TEMPERATURES CALCULATED TEMPERATURES

CALCULATED TEMPERATURES

Calculated cooling-heating capacity

Floor : 9 W/m2 5 W/m2 Ceiling : 39 W/m2 14 W/m2

Totat: 48 W/m2 19 W/m2

Floor : 9 W/m2 5 W/m2 Ceiling : 47 W/m2 16 W/m2

Total 56 W/m2 21 W/m2

Floor : 26 W/m2 15 W/m2 Ceiling : 37 W/m2 14 W/m2

Total : 63 W/m2 29 W/m2

Cooling HeatingSupply water temperature: 16 °C 25 °CReturn water temperature: 20 °C Space temperature: 26 °C 20 °C

CONCRETE SLABCOOLING/HEATING

• Building requirements– Well insulated– Window U-values < 1,2 W/m2K– Solar shielding– Cooling load ~30-50 W/m2

– Heat load < 20 W/m2 only system– 20 W/m2 < Heat load < 30 W/m2 optimal control– 30 W/m2 < Heat load , additional system

CONCRETE SLABCOOLING/HEATING

• Heating and cooling of multi-storeybuildings

• Offices, schools, commercial buildings• Heat storage/transfer between day and

night• Heat transfer between south and north

facing rooms ?• Use of dynamic computer simulations ?

Page 7: Seite 1 - ashraethailand · Seite 1 COOLING AND HEATING OF BUILDINGS BY ACTIVATING THE THERMAL MASS WITH EMBEDDED HYDRONIC PIPE SYSTEMS • Bjarne W. Olesen, Ph.D., • Head of R&D,

Seite 7

COMPUTER-SIMULATION COMPUTER-SIMULATION

COMPUTER-SIMULATION

CONTROL OF A COMBINED FLOOR HEATING-COOLING SYSTEM

Boiler Chiller

Room temp.-Humidity

Outside temp.

SupplyLimiter

ReturnMixing valve

Valves

VIVALDI

Operation time

Mai to SeptemberMean water temperature according to

outside temperatureOperation 24 hours

090518 – 60901

22-60902

°C % % %

<20 0,0 0,0 0,0

20-22 11,3 3,9 1,8

22-25 88,0 87,6 91,6

25-26 0,7 6,3 5,1

26-27 0,0 1,7 1,3

Temperatureinterval

>27 0,0 0,5 0,1

hours 1217 515 412Pump running

% 33 14 11

ART MUSEUMBREGENZ

Page 8: Seite 1 - ashraethailand · Seite 1 COOLING AND HEATING OF BUILDINGS BY ACTIVATING THE THERMAL MASS WITH EMBEDDED HYDRONIC PIPE SYSTEMS • Bjarne W. Olesen, Ph.D., • Head of R&D,

Seite 8

ART MUSEUM IN BREGENZ

• Design requirements– Air temperature variations during a day within 4 K– Relative humidity variations less than 6 % during a day.– Seasonal variations between 48 and 58 %– Room temperature in winter 18 oC to 22 oC– Room temperature in summer 22 oC to 26 oC, occasional up to 28 oC

• Design load 250 persons pr. day, 2 hours• Displacement ventilation < 0,2 h-1

• Floor area 2.800 m² , 4 floors• 28.000 m plastic pipes embedded in walls and floor slabs

ART MUSEUM BREGENZ

• 3.750 m² floor area• 4.725 m² embedded pipes• Condensing boiler• Ventilation 750 m3/h per floor (first

design was 25.000 m3/h

ART MUSEUM IN BREGENZ ARTMUSEUMBREGENZ

ART MUSEUM BREGENZ -Measurements

151617181920212223242526272829303132333435

2. O

kt

3. O

kt

4. O

kt

5. O

kt

6. O

kt

7. O

kt

8. O

kt

9. O

kt

10. O

kt

11. O

kt

12. O

kt

13. O

kt

14. O

kt

15. O

kt

°C

05101520253035404550556065707580859095100 %

t-Luft-5min-mean

t-Boden-5min-mean

rF-5min-meanV 230 500-1G 300-R !! V 200???

Humidity

Air Temp.

Floor Temp

Office buildingStuttgart

• 1998• 11.000 m²• 3-4 floors• Operable windows• Co-generation• Solar collectors• Absorption cooling• Free cooling• Compressor cooling• Displacement ventilation

Page 9: Seite 1 - ashraethailand · Seite 1 COOLING AND HEATING OF BUILDINGS BY ACTIVATING THE THERMAL MASS WITH EMBEDDED HYDRONIC PIPE SYSTEMS • Bjarne W. Olesen, Ph.D., • Head of R&D,

Seite 9

Displacement ventilationAir supplyIntegrated convector for heating

Operative temperature sensor

Air temperature sensor

Data transmission

Operative temperatursensor

Data transmission

StuttgartStuttgart - 1999

5

10

15

20

25

30

35

40

3.8

4.8

5.8

6.8

7.8

8.8

9.8

10.8

11.8

12.8

13.8

14.8

15.8

16.8

17.8

18.8

19.8

20.8

21.8

22.8

23.8

24.8

25.8

26.8

27.8

28.8

29.8

30.8

31.8

Zeit

Tem

pera

tur

[°C

]

Luft Operative Taupunkt Außen

Page 10: Seite 1 - ashraethailand · Seite 1 COOLING AND HEATING OF BUILDINGS BY ACTIVATING THE THERMAL MASS WITH EMBEDDED HYDRONIC PIPE SYSTEMS • Bjarne W. Olesen, Ph.D., • Head of R&D,

Seite 10

Stuttgart

Stuttgart 24.07. - 28.07, 2000

20

21

22

23

24

25

26

24. J

ul

24. J

ul

25. J

ul

25. J

ul

26. J

ul

26. J

ul

27. J

ul

27. J

ul

28. J

ul

28. J

ul

29. J

ul

Zeit

Tem

pera

tur [

°C]

O1-Operative Büro 4. Stock Fenster-Ost F1-Fläche 4. Stock RucklaufO-Operative Büro 5. Stock Fenster-West O6-Operative Büro 5. Stock Fenster-Ost

StuttgartBUILDING 3

0

10

20

30

40

50

60

70

80

90

100

<20 20-22 22-25 25-26 26-27 >27

perc

enta

ge in

ope

rativ

e te

mpe

ratu

re ra

nges

ac

cord

ing

to D

IN 1

946

4th floor window west 4th floor window south 5th floor window west5th floor window east 5th floor middle meeting roomall offices except middle

STUTTGARTBUILDING 3

0

10

20

30

40

50

60

70

80

<1 (1-2) (2-3) (3-4) (4-5) (5-6) >6chan

ge in

ope

rativ

e te

mpe

ratu

re d

urin

g a

day

(8-1

8) [%

]

4th floor window west 4th floor window south 5th floor window west5th floor window east 5th floor middle meeting roomall offices except middle

Office building in Hamburg

• 2000• 14.000 m²• 7.500 m² slab cooling• Baseboard heaters• 2 ach, 18 °C• Operable windows

Transportation of modules

Page 11: Seite 1 - ashraethailand · Seite 1 COOLING AND HEATING OF BUILDINGS BY ACTIVATING THE THERMAL MASS WITH EMBEDDED HYDRONIC PIPE SYSTEMS • Bjarne W. Olesen, Ph.D., • Head of R&D,

Seite 11

INSTALLATION

PRE-FABRICATION

PRE-FABRICATION

CONCLUSIONS

• Hydraulic heating/cooling system with pipesembedded in the building structure is aninteresting alternative to full air conditioning

– High temperature cooling-low temperature heating– No noise– No draught– Low installation and running costs– Lower peak load and reduced equipment size– Lower building height– Combined with mechanical ventilation– Reduced capacity?– Acoustic?– Latent load?


Recommended