+ All Categories
Home > Documents > Seminar on Water security in bulgaria - World...

Seminar on Water security in bulgaria - World...

Date post: 02-May-2018
Category:
Upload: lamthuan
View: 218 times
Download: 3 times
Share this document with a friend
17
SEMINAR ON WATER SECURITY IN BULGARIA SOFIA, SEPTEMBER 18-19, 2017 DAM SAFETY IN ROMANIA
Transcript

SEMINAR ON WATER SECURITY IN BULGARIA

SOFIA, SEPTEMBER 18-19, 2017

DAM SAFETY IN ROMANIA

Overview• Romania has built 2,617 dams out of which 246 are large and medium dams and

1260 are small dams, as per ICOLD classification

• 75% of all dams have been built between 1965 and 1989

• 32 dams wait for commissioning as are still in various stages of construction

• Total storage capacity of large dams commissioned = 12.35 billion m3

Seminar on Water Security in Bulgaria - Dam Safety in Romania 2September 18-19, 2017

Overview (2)

• Dams ownership is shared mainly by the “Romanian Waters” Administration

(ANAR) and the hydropower company “Hidroelectrica”, with six dams owned by

various industrial plants

• 61 % of dams have multiple purposes (water supply, hydropower, irrigation and

almost all have flood protection purpose)

September 18-19, 2017Seminar on Water Security in Bulgaria - Dam Safety in Romania 3

Legal and regulatory arrangements for dam safety

• Water Law #107/1996 is the main regulatory act for dam safety setting the guiding rules for dam safety

• Complementary implementation regulations and technical norms

• ICOLD (2012) risk analysis methodology

• Responsibilities:• Dam Manager (local)

• Dam Owner (central)

• Line ministry (central)

• CONSIB (consultative technical body) – pivotal role in dam safety system

• reviews organization of dam monitoring system

• reviews periodic technical reports on dams’ safety operation

• advises upon the operational rules for dams

• recommends the preparation of technical reviews of hydraulic infrastructure with high failure risk

• recommends the structural interventions to enhance the safety of infrastructure at risk

September 18-19, 2017Seminar on Water Security in Bulgaria - Dam Safety in Romania 4

Distribution of roles and responsibilities for dam safety

September 18-19, 2017Seminar on Water Security in Bulgaria - Dam Safety in Romania 5

Dam accidents and incidents

• Belci Dam failure (July 1991) – Conditions:

• high flood,

• technical defections at micro-hydropower plant

• power supply to action the hydro-mechanical equipment failed because of heavy rainfall

• Consequences: dam failed, 25 fatalities, 250 households washed away

• Certej Tailings Dam (October 1971) -

• the tailings dam failed after a long period of heavy rainfalls, spilling cyanide over the town

• Consequences: 89 fatalities, four apartment buildings and five households washed away

• Incidents:

• Vidraru Dam – over discharge of reservoir without early warning alerted the local

population

• Paltinu Dam – severe seepage through shoulders required grouting and consolidation

September 18-19, 2017Seminar on Water Security in Bulgaria - Dam Safety in Romania 6

• Belci Dam • Paltinu Dam

September 18-19, 2017Seminar on Water Security in Bulgaria - Dam Safety in Romania 7

Enhancing Safety of Dams at Risk (1)

• Assessment of safety risk done by ANAR and CONSIB in 1999-2001 for most dams

• 9 large dams found with safety problems and operational restrictions recommended

• WB technical and financial support requested in 2002

• Hazard Risk Mitigation and Emergency Preparedness Project (HRMEP) – 2005-2012

• 1 project dam (Dridu Dam) further damaged by heavy floods in 2005

• Initial project cost US$204 Million / Floods and Dam Safety component US$ 101 Million

• Works costs share: US$ 88.3 M, of which US$ 39 M floods and US$ 49.3 M for dams

• Project scope: 12 flood protection sites and 13 dams

• Final project component costs US$ 101 M with US$ 88.5 M for works

• Works costs share: US$ 35.5 M floods and US$ 53 M dam safety

• Project scope: 9 flood protection sites and 6 dams – mainly because of costs overrun

September 18-19, 2017Seminar on Water Security in Bulgaria - Dam Safety in Romania 8

Enhancing Safety of Dams at Risk (2)

• HRMEP Project financed safety interventions for 4 large dams and 2 small dams

• All dams had restrictions in operations imposed by their deficiencies, mainly with

respect to stability and seepage

• All dams operated at water free board level lower than designed – for safety

• Safety restrictions imposed limitation of services for all users

• Serious deficiencies of feasibility studies found at engineering design stage!

• Inaccurate identification of scope of interventions led to substantial increase of costs

• 89% - the overall cost overrun for dam projects

• 180% - the cost overrun in the most expensive contract

• Consequence: 7 dams (including the most unsafe) could not be addressed!

September 18-19, 2017Seminar on Water Security in Bulgaria - Dam Safety in Romania 9

Enhancing Safety of Dams at Risk (3)

Population at Risk - initial

NamePopulation

At risk Affected Total

Dams in Program 338,085 1,225,000 1,563,085

Dridu 10,435 40,000 50,435

Varsolt 10,800 155,000 165,800

Berdu 138,000 138,000 276,000

Poiana Uzului 30,000 80,000 110,000

Maneciu 42,000 224,000 266,000

Valea de Pesti 8,000 30,000 38,000

Siriu 85,000 100,000 185,000

Lesu 280 35,000 35,280

Sanmihaiu 1,060 160,000 161,060

Taria 5,200 18,000 23,200

Catamarasti 950 80,000 80,950

Buftea 3,500 120,000 123,500

Pucioasa 2,860 45,000 47,860

Population Protected – 79%

NamePopulation

At risk Affected Total

Completed dams 208,445 787,000 995,445

Varsolt 10,800 135,000 145,800

Berdu 138,000 138,000 276,000

Maneciu 42,000 220,000 262,000

Taria 5,200 16,000 21,200

Catamarasti 950 78,000 78,950

Dridu 10,435 40,000 50,435

Sanmihaiu 1,060 160,000 161,060

September 18-19, 2017Seminar on Water Security in Bulgaria - Dam Safety in Romania 10

Enhancing Safety of Dams at Risk (4)

• Main deficiencies addressed through the Project:

• Seepage through the foundation and/or dam body

• Stability of foundation and dam shoulders

• Obsolete / nonfunctional hydro-mechanical equipment (bottom outlets, gates, spillway)

• Obsolete / nonfunctional instrumentation for monitoring, early warning

• Erosion of side slopes or downstream dam face

September 18-19, 2017Seminar on Water Security in Bulgaria - Dam Safety in Romania 11

Brief description of Project interventions (1)

• Varsolt Dam – medium size (17 m height, 40 mill. m3)

• Reservoir: multipurpose – water supply, flood protection

• Operation experience: the reservoir was originally designed as non-permanent and commissioned for

permanent use later. A dam foundation sealing was not necessary for a non-permanent used reservoir.

• Risk assessment: evaluated, category of importance “a – exceptionally important” - “high risks”.

• Rehabilitation measures:

• Sealing of dam body and foundation treatment (concrete cut-off wall – 0.6 m thick from the dam crest, 25 m deep).

• Reshaping of dam body (stability, drainage at the dam toe and downstream channel rehabilitation.

• Drilling of drains in the new gallery.

• Rehabilitation of the bottom tunnel and sealing of the old gallery.

• Construction of new bottom outlet structures on the left bank.

• Measures for sanitary protection and water quality assurance.

• Anti-erosion measures upstream of the reservoir.

• Rehabilitation of the monitoring system and upgrading of the alarm and warning system as well as seismic

activities detection system.

• Estimated costs US$ 7.4 Mill. Actual costs US$ 20.7 Mill.

September 18-19, 2017Seminar on Water Security in Bulgaria - Dam Safety in Romania 12

Brief description of Project interventions (2)

• Maneciu Dam – Large dam; Earth rock-fill dam with central clay core; H 78 m; W 58 Mm3

• Reservoir: multipurpose – water supply, flood control, irrigation and generating electricity.

• Operation experience: the dam was operated at a restricted water level compared to originally designed parameters.

Bottom outlet operation restricted due to too high flow velocities (valves, energy dissipater, no steel lining at concrete

structures and damages in downstream areas etc.). Seepage in spillway and damaged concrete. Slope instability occurred

on the left downstream bank.

• Risk assessment: evaluated, category of importance “b – significant important”, - “medium risks”

• Earthquake risk assessment: the dam is located in a zone of a very high seismicity (zone A).

• Rehabilitation measures:

• Rehabilitation of the bottom outlet: steel lining between valve chamber, dissipater and injections; improvement of

other structures, new energy dissipater.

• Rehabilitation of the spillway channel: sealing of joints in the concrete structures with various methods,

improvement of the concrete quality in sections with high flow velocities through usage of highly resistant concrete

(20 cm thick).

• Rehabilitation of the downstream left slope: protection with riprap between elevation 557 and 610 m a. S. L.;

Rehabilitation works above 610 m a. S. L.; Additional local measures.

• Rehabilitation of the monitoring system, alarm and warning system as well as the seismic system.

September 18-19, 2017Seminar on Water Security in Bulgaria - Dam Safety in Romania 13

Brief description of Project interventions (3)

• Dridu Dam: Gated weir, main fill dam; Medium dam; H=18 m, W=45 M m3

• Operation experience : severe local erosions of river banks caused by wave actions, seepage through

dam body; cavitation problems in spillway section; locally damaged sealing and revetment in channels;

damaged hydraulic weir gates; seepage under right side foundation after 2005 flood.

• Risk assessment: evaluated, category of importance “b – significant important”, “medium risks”.

• Earthquake risk assessment: the dam is located in a medium high seismic zone (zone C).

• Rehabilitation measures:

• Cut-off wall executed through “soil mixing” - innovative method in Romania

• Rehabilitation – protection - of the river banks to stop erosion

• Rehabilitation of the existing dam drainage system: new collecting system and pumping facilities.

• Rehabilitation of the main dam: drillings and drains from the inspection gallery, construction of a

new sealing blanket – depth 7 m from dam crest.

• Rehabilitation of the spillway channel: reconstruction of bottom sills, riprap and reinforced concrete

structures

• Rehabilitation of the hydro-mechanical equipment.

• Implementing a new information system for the water management, warning and alarm system, etc.

September 18-19, 2017Seminar on Water Security in Bulgaria - Dam Safety in Romania 14

Deferred intervention - example• Siriu Dam: Large, earth-rock-fill dam central clay core; H=122 m; W=155 Mm3

• Reservoir: multipurpose – water supply, irrigation, hydropower, flood protection; Operation restricted

• Operation experience: seepage rates of 15 to 18 l/s were observed in drainage gallery during impounding at an

elevation 50 m below normal water board level; problems at hydro-mechanical equipment (bottom outlet, intake gallery,

valve chamber etc.); slope instabilities on the left bank downstream; reduced operation capacity of spillway.

• Risk assessment: evaluated, category of importance “A – exceptional important” - “high risks”.

• Earthquake risk assessment: the dam is located in a highly seismic zone (zone b).

• Proposed repair and rehabilitation measures:

• Grouting and drainage works in existing galleries plus new, exceeding gallery and piezometers to stabilize the left

slope and to decrease seepage.

• Refurbishment and rehabilitation of hydro-mechanical, electrical equipment and drainage system

• Bottom outlet, valve chamber

• Intake gallery, valve chamber

• Spillway valves and gates

• Intermediate (semi depth) outlet, gates

• Water supply system, pipe

• Rehabilitation of the monitoring system, emergency and alarm system, seismic system etc.

• Rehabilitation of the dam crest and repair works at the downstream dam slope.

September 18-19, 2017Seminar on Water Security in Bulgaria - Dam Safety in Romania 15

Lessons Learned

• Slow adaptation process of technical staff (designers, planners) to technological

progress and changed economics of public investment

• Poor planning capacity at administrative levels (ministry, water authority), unable

to do a reasonable prioritization of investment – led to

• The change of generations occurred in early ‘90s did not enable preservation of the

same innovative capacity in staff lacking practical experience in design, planning

• Insufficient understanding of changes in procurement practice introduced by the

harmonization with international principles and rules

• Reluctance to accept presence of foreign specialists, challenging their capacity to

understand the local traditions

September 18-19, 2017Seminar on Water Security in Bulgaria - Dam Safety in Romania 16

THANK YOU

Gabriel Ioniță, Irrigation Engineer

[email protected]

September 18-19, 2017Seminar on Water Security in Bulgaria - Dam Safety in Romania 17


Recommended