+ All Categories
Home > Documents > Senior Design Project

Senior Design Project

Date post: 14-Feb-2017
Category:
Upload: chawal-ukesh
View: 208 times
Download: 0 times
Share this document with a friend
39
American Leather Upholstery/Final Assembly Workstation Redesign Shrijan Shrestha Ukesh Chawal Indra Poudel
Transcript
Page 1: Senior Design Project

American Leather Upholstery/Final Assembly Workstation Redesign

Shrijan ShresthaUkesh Chawal

Indra Poudel

Page 2: Senior Design Project

Founder/CEO Bob Duncan American Leather was founded in 1990 Revolutionary idea: “ Custom leather furniture

could be made and shipped in three weeks or less.”

“just-in-time” Manufacturing From a small four person shop, the company

has grown into a thriving leader in the furniture industry, with over 130 different collections sold in over 650 stores

The factory, based just outside of Dallas, Texas

Introduction

Page 3: Senior Design Project

Redesign comfort sleeper upholstery/final assembly workstation to make employee more efficient.

Increase productivity by 10% Factors to consider:

◦ material flow◦ material handling◦ work station location in relation to steps in

upholstery process.

Objective

Page 4: Senior Design Project

Value Stream Map

Page 5: Senior Design Project

Manufactures Comfort Sleeper Comfort Sleeper

◦ Couch with sleep system◦ Can be converted into bed

Work Stations Involved:◦ Sewing Upholstery◦ Sub-Assembly Assembly◦ Deluxing Packaging

Line 6

Page 6: Senior Design Project

Bed Type Version Bed Size Bed Height

Foam V3 KH LL

Plush/Premier V5 KS HL

Gel Sleeper QP  

Temperpudic V6 QS  

    FS  

    TS  

    CS  

Type Of Beds

Page 7: Senior Design Project

Focal Point

Page 8: Senior Design Project

Upholstery 24 Workstations

One worker per station

worker uses the upholstery table to put the leather and fabric into the frame and then staple it together

Cycle Time: 40 minutes per order

 

Page 9: Senior Design Project

Sub-Assembly 2 Sub Assembly Station

2 workers per station

Sub assembler puts the frames and mattress together to make a bed

Cycle Time: 11.72 minutes

Page 10: Senior Design Project

Final Assembly 6 Final Assembly

One Assembler per Station

Assembler assembles Frames from upholstery and Bed from sub assembly station

Cycle Time: 19.2 minutes

Page 11: Senior Design Project

Process Flow

Page 12: Senior Design Project

Flow ChartUpholstery

Assembler

WIP on conveyor belt

Sub-Assembly

Bed In Transfer Cart

Final Assembly

Is bed Available

Order for bed

Yes

NO

Page 13: Senior Design Project

Walking Time and Distance

Lack of Sequencing

High WIP

Problems

Page 14: Senior Design Project

Walking Time and Distance

41 trips/ day (Sub-Assembler)

Time traveled by sub – assembler = 1.03 min / trip (42.23 min/day)

Distance traveled = 68.4m/trip (2804.4 m/day)

25 trips/day (Assembler)

Time traveled by Assembler = 1.10 min/ trip (27.50 min/day)

Distance Traveled = 58.8m/trip

(1470 m/day)

Page 15: Senior Design Project

Lack Of Sequencing Lack of Systematic

Ordering

Frames were completed and are placed in the conveyer belt but the beds were missing causing assembler to work on next WIP on conveyer belt

Page 16: Senior Design Project

High WIP

There were a lot of WIP in the moving cart

Total space covered by WIP is 2786.62 square ft.

Page 17: Senior Design Project

Barcode System of Ordering using MS Excel

Replacement of the upholstery table with modified transfer carts

Proposed Solution

Page 18: Senior Design Project

Barcode System

Page 19: Senior Design Project

Barcode System DesignedVersion Bed Type Bed Size Bed Height Barcode

V6 Temp KS LL

V6 Gel TS HL

V3 Foam QS

Sleeper Foam FS

V5 Plush CS

Page 20: Senior Design Project

How It Works

Page 21: Senior Design Project

Upholstery Table VS Cart

Page 22: Senior Design Project

Modification on Carts Wheel Lock

• Replacement of the regular wheels with lock wheels

Page 23: Senior Design Project

Before and After

Before After• Time saved• Space of WIP saved• More Sequenced

Page 24: Senior Design Project

For Sub Assembler, Total # of bed assembled = 41 beds per day Total time saved = 41 * 1.03 = 42.23 min per day Total time required for assembling the beds= 480 – 42.23 = 437.77

min = 7.29 hrs. (instead of regular 8 hrs.)

Similarly for Final Assembler, Total time required for assembling the beds = 480 – 27.5 = 452.5 min

= 7.54 hrs. (instead of regular 8 hrs.)

Data Analysis After Solution

Page 25: Senior Design Project

For Sub-Assembler, ( Wage/ hr. = $11)

Total expenditure for four employees in 8 hrs. = 4 * 8 * $11 = $352 per shift Total expenditure for four employees in 7.29 hrs. = 4 * 7.29 * $11 = $320.76 per shift Total amount saved = $352 - $320.76 = $31.24 per shift

= $62.48 per day = $1374.56 per month = $16,494.72 per year

Similarly for Assembler, ( Wage/ hr. = $11)

Total amount saved = $528 - $497.64 = $30.36 per shift = $60.72 per day = $1335.84 per month = $16,030.08 per year

Total saving per year = $32,524.8

Cost Analysis

Page 26: Senior Design Project

Cost of one wheel lock = $42 Total cost of wheel lock for 24 upholstery = $4,032 Total cost of the flat screen monitor = 2 * $500 = $1000 Total cost = $5,032

Calculated savings per year = $32,524.8 Total amount saved per month = $2,710 Payback Period = 2 months.

Pay Back Period

Page 27: Senior Design Project

For Sub-Assembly, After the solution, In 7.29 hrs. was needed to assemble 164 beds

Before the solution, In 7.29 hrs. total number of beds assembled = 7.29*164/8 = 150 beds

Therefore, extra number of beds = 164 – 150 = 14 beds Hence, Productivity = 14/150*100=9.33%

Similarly For Assembler,

Productivity = 9/141*100= 6.4%

Productivity

Page 28: Senior Design Project

People• COO of American Leather • Manager• Employee

Final Assembler Sub Assembler Upholstery employee Material handler

Page 29: Senior Design Project

Materials• Measuring Tape• Stop Watch• Laser tape

Page 30: Senior Design Project

Information• Problem Solving Tools• Cad layout• Distance Travelled• Cycle Time• Production Rate

Page 31: Senior Design Project

Equipment• Fork Lift• Moving Cart• Tools (Screw, Hammer, Hydraulic Tightening, Nuts) • Computers• Flat Screen Television

Page 32: Senior Design Project

Energy

• Electricity

• Hydraulic

Page 33: Senior Design Project

Realistic Constraints ECONOMIC• Amount saved = $32,524.8 per year • Save Expenditure

ENVIRONMENTAL• Trash can recommended • Spare parts Handling

SOCIAL• Role of workers and the managers

POLITICAL• Convenient management

Page 34: Senior Design Project

ETHICAL• As an engineer, we are expected to exhibit the highest standards of honesty and integrity.

Engineers must perform under a standard of professional behavior that requires adherence to the highest principles of ethical conduct.

• Contract with American Leather.

HEALTH AND SAFETY• Health factors were considered

MANUFACTURABILITY• Engineers helps to manufacture more products.• Increase in productivity

SUSTAINABILITY• Will help American Leather to compete with others in future

Realistic Constraints

Page 35: Senior Design Project

Course Title Knowledge and skills acquired that were used in this projectIE 1105 Introduction to Industrial Engineering Lab

 PowerPoint presentation and deliver an oral report.

IE 2305 Computer Applications in Industrial Engineering Lab 

Programming in Excel and prepare the bar code.

IE 3301 

IE 3314

Engineering ProbabilityEngineering Research Methods

 

EXCEL for performing descriptive statistics

IE 3312 Economics for Engineers 

Payback period, Financial summary.

IE 3315  Operations Research I 

Networking Problems, Shortest Path

IE 3343 Metrics and Measurement 

Time study , Work Design

IE 4303 Production and Inventory Control 

Work In Progress (WIP), Productivity, Cycle time (CT), Just in time (JIT) 

IE 4308 Statistical Quality Control 

Process diagnosis, capability and improvement of the system.

 

IE 4343  Facilities Planning and Design 

Analyze flow, space, and activity relationships with impact to material handling and design layout alternatives

 

IE 4344 Human Factors Engineering 

Measure and understand human capacities for work, table design and physical movements

 

IE 4350 Industrial Engineering Capstone Design 

Design Project , Professional ethical responsibility and contemporary issues

 

IE KNOWLEDGE AND SKILLS

Page 36: Senior Design Project

Initial investment was $5,032 and the payback period is 2 months.

Total area saved is 2786.62 square ft. The total amount of money saved is $32,524.8

per year Total time saved by a worker is 42.23 min per day

in the sub – assembly section while in the final assembly section is 27.5 min per day.

Conclusion and Summary

Page 38: Senior Design Project
Page 39: Senior Design Project

Recommended