+ All Categories
Home > Documents > September 2020 Emden/Leer University of Applied Science

September 2020 Emden/Leer University of Applied Science

Date post: 09-May-2022
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
13
September 2020 Emden/Leer University of Applied Science
Transcript
Page 1: September 2020 Emden/Leer University of Applied Science

September 2020

Emden/Leer University of Applied Science

Page 2: September 2020 Emden/Leer University of Applied Science

Report No:03 List of Process Description for Offshore Decommission Page 1 of 4

Project Acronym: DecomTools

Reference Number: Interreg North Sea Region

Project Number: 20180305091606

Project Title: Eco-Innovative concepts for the end of offshore wind energy

farms lifecycle

Activities and Deliverables: List of Process Description for Offshore Decommission

Report Number: 03

Reporting Eligibility Period: 01.03.2020 – 31.08.2020

Work Package: 4

Date of Issuance: 25.09.2020

Research Team

Authors: Hamed Askari (Emden/Leer University of Applied Science)

Marc Hillers (Emden/Leer University of Applied Science)

Dr. Marcus Bentin (Emden/Leer University of Applied Science)

Dr. Stephan Kotzur (Emden/Leer University of Applied Science)

Contributors: Dr. Shahin Jalili (University of Aberdeen)

Dr. Alireza Maheri (University of Aberdeen)

Page 3: September 2020 Emden/Leer University of Applied Science

Report No:03 List of Process Description for Offshore Decommission Page 2 of 4

Introduction

According to work package four of Decom Tools application, the deliverable by the name of "List

of Process Description for Offshore Decommission" shall be issued. A comprehensive study in the

wind industry as well as oil and gas industry has been conducted in order to provide the above-

mentioned document. Evidently, there are some similarities between offshore oil and gas industry

and offshore wind industry, in particular, in terms of marine operation1. Notwithstanding the

similarities in these two industries, there are some significant differences which has profound

impact notably in the logistic and supply chain. For instance, the number of installed assets in an

oil and gas field normally can vary between 1 to 5 structures whereas in an offshore wind parks, the

number of turbines in a wind park is approximately between 20 to 170 in 20192. Furthermore, the

wind turbine components are bulky due to its geometry and size. In conclusion, since the oil and

gas industry is a mature industry, the authors implemented the lesson learnt and methodology which

is coveted in the oil and gas industry. Then the methods and strategies are tailored into the nascent

wind industry.

One of the possible measures to fulfill the objectives of Decom Tools projects is to reduce the

duration of operation time of the installation and cable laying vessel. The installation vessel can be

either a heavy lift vessel or jack up vessel which is equipped with heavy lift crane. During execution

of marine operations, the installation and cable laying vessel play a colossal role in the

decommissioning project. They are the most expensive marine equipment for the decommissioning

project. Furthermore, they emit considerable level of CO2. One method to fulfill the objectives of

DecomTools project which are 20% cost reduction and 25% CO2 emission mitigation is to reduce

the working hours of mentioned vessels which lead to reduction of project cost and CO2 emission.

This can be attained by thoughtful planning, careful and elaborate preparation, and proper

conduction of the entire project.

1 Marine operation is any operation conducted using Vessels offshore, inshore or at terminals ashore (NORSOK Standard, 1995) 2 Offshore Wind in Europe Key trends and statistics 2019 (WindEurope, 2020)

Page 4: September 2020 Emden/Leer University of Applied Science

Report No:03 List of Process Description for Offshore Decommission Page 3 of 4

Hence, in this deliverable three different phases for the decommissioning has been devised as per

figure 1. The first stage is pre-decommissioning activities (most left figure) in which the preparatory

activities can be undertaken by deploying smaller and cheaper vessel equipped with remotely

operated vehicle (ROV) to make the site ready for removal and decommissioning process. To put

it more simply, by execution of the pre-decommissioning activities, the working hours of

installation and cable laying vessel will be reduced considerably. The second stage is removal and

transportation of offshore wind parks components to the onshore for further process and recycling.

Finally, the last phase is post-decommissioning marine operations. In this phase by executing post-

decommissioning activities which are mostly sets of survey activities, contractor carry out

remaining activities and then ascertain that the removal and decommissioning has been completed

successfully in accordance with project requirements and relevant codes and standards. However,

it should be noted that before installation of wind park, a certain set of activities and surveys were

conducted to make the site ready for the installation. The pre-decommissioning activities are not

exactly similar to the pre-installation operations. Similarly, pre-installation phase was carried out to

make the site ready for the installation.

Figure 1 Sequences of Marine Operations of Decommissioning of Offshore Wind Parks

Having considered that each wind farm has different components, the required marine operations

for pre-decommissioning and removal vary. These proposed activities are according to common

practice, industries recommendation, codes and standards. Therefore, in the document "Pre-

Page 5: September 2020 Emden/Leer University of Applied Science

Report No:03 List of Process Description for Offshore Decommission Page 4 of 4

Decommissioning Marine Operations of Offshore Wind Parks which is part of deliverable "List Of

Process Description For Offshore Decommission" with document number "DECOMTOOLS-WP4-

PDOWP-EDP-A3-001" necessary marine operations for each component has been introduced

(component wise).

Based on the application, the document should illustrate the required operation in the format of

even-driven-process. Therefore, the authors use the open source software by the name of Draw.io3

in order to show the overall process of decommissioning of offshore wind parks.

As it stated above, the decommissioning operation is divided into three different phases. Therefore,

for each phase a separate document is prepared. Each document has an identical name and number

which is following the below principal.

Project Name-Work Package Number- abbreviation of name of Document - Document Format-

Document Size- document number

DECOMTOOLS WP4 PDOWP EDP A3 001

Project name- Work package4-Pre-Decommissioning of Offshore Wind Parks-Event Driven Process-Sheet Size-Document No.

3 Draw.io is a flexible and open source software that can show the process in even-driven format.

Page 6: September 2020 Emden/Leer University of Applied Science

Pre-Decommissioning Marine Operations of Offshore Wind Parks (List Of Process Description For Offshore Decommission)

Refer To Note 2

Issued By Reviewed By Approved By

Hamed Askari Dr. Marcus Bentin WP Committee

Delivered To

Pre-Decommissioning Marine Operations of OffshoreWind Parks

NSR Joint Secretariat

DECOMTOOLS-WP4-PDOWP-EDP-A3-001 / Revision-00 Sheet 1 of 8

20 August 2020 4 September 2020 30 September 2020

Work Package Number: 04 C.5.1.1: List of Process Description

for Offshore Decommission

18 September 2020

Page 7: September 2020 Emden/Leer University of Applied Science

Note: 1. Prior to commencement of marine operations for offshore wind farms decommissioning, the different countries set various regulations which the developers have to fulfil them. Therefore, there is not a

prescribed set of actions for all nations. For example, in the UK, the developer must undertake environmental impact assessment (EIA) and they must discuss the issue with Department of Energy andClimate Change (DECC). In Germany, the developer must devise a decommissioning concept and procedure to justify the magnitude of security. Or in Denmark, an obligation to return the site to pre-installation condition should be devised which is part of contract of developers (assessment of offshore wind farm decommissioning requirements, DNV.GL,2016). Therefore, before commencement ofmaritime operations, different actions need to be taken in various countries and there is not one-size-fit all measures for all nations. In this document, the required actions and operations based oncommon practice are shown. There are two targets to conduct pre-decommissioning maritime operations. The most important aim is to devise a practical and detailed plan for removal of structures andcables by conduction of surveys in order to mobilize a right equipment and machinery. The omission or oversight to mobilize inadequate or extra personnel and equipment will have significant impacton project time, cost and CO2 emission. Therefore, a comprehensive study of field should be undertaken. Furthermore, prior to commencement of removal operation, some measures and steps haveto be implemented in order to make the wind park ready for removal of main components. These kind of operation and preparation require small vessel and specific tool which will contribute tominimizing the charter time of large WTIV and HLVs which will lead to decrease the overall cost of decommissioning.

Notes:

Wind Turbines DECOMTOOLS-WP4-PDOWP-EDP-A3-001 Sheet 03

Cables

High Voltage Substation

Metrological Mast

Pre-DecommissioningMarine Operations

Environment ImpactAssessment (EIA)

Give Notification to SeaUsers & Responsible Parties

Shut Down the WindTurbinesGeneral Activities

Component-WiseOperation

Disconnection of OWP fromGrid

DECOMTOOLS-WP4-PDOWP-EDP-A3-001 Sheet 04

DECOMTOOLS-WP4-PDOWP-EDP-A3-001 Sheet 05

DECOMTOOLS-WP4-PDOWP-EDP-A3-001 Sheet 08

Refer To Note 2

Issued By Reviewed By Approved By

Hamed Askari Dr. Marcus Bentin WP Committee

Delivered To

Sheet 2 of 8DECOMTOOLS-WP4-PDOWP-EDP-A3-001 / Revision-00

NSR Joint Secretariat

Pre-Decommissioning Marine Operations of Offshore Wind Parks

20 August 2020 4 September 2020 18 September 2020 30 September 2020

Work Package Number: 04C.5.1.1: List of Process Description for

Offshore Decommission

Refer to Note 1

Page 8: September 2020 Emden/Leer University of Applied Science

1. Disconnection means to release the cables between the nacelle and the tower physically. In other words, in case of unbolting the nacelle from tower, there should not be any connections and cablingfrom Nacelle to the tower. It can be achieved by disconnection of cables from hang-off or cutting the cables and trays depending on the situation and the design of that wind turbine.

2. Depending on the wind turbine size, just the gearbox contains an oil quantity of between 200 and 800 liters (Monitoring the Oil of Wind-Turbine Gearbox, D. Coronado & J. Wenske). However, thelarge wind turbine gearbox need approximately over 2000 liters of oil.One of the most failure of wind turbine is gearbox failure. There is possibility to have a leakage from gearbox afterreaching the lifetime of OWP. Therefore, the study and survey have to be undertaken to ascertain the zero probability of oil spill/leakage to the sea while lifting and transportation thenacelle in order to minimize the risk and hazard to the marine habitant and birds.

3. Hazardous materials can be any toxic and dangerous materials inside the nacelle including the fire, flame, smoke and gas detection systems that have nuclear source.4. Normally one cable hang-off is located inside the transition pieces. Therefor, by disassembly of cable hang-off, the cables between transition piece and tower can be disconnected. In

overall, by disconnection of cables and accessories (like cable trays) between nacelle and tower, between tower and transition piece and between transition piece and network, thestructure will be ready for further disassembly and removal.

Notes.

Pre-DecommissioningActivities Related to

Nacelle & RotorSecure the Rotor With

External ToolsOil Spill Probability (SP)

StudyRemove Hazardous

MaterialsDisconnection of Cables

from Nacelle

Pre-DecommissioningActivities Related to

WT Support Structure

Remove the MarineGrowth

Cut the Cables Between J/I Tube & Subsea

NetworkConnect the Buoy to the

End of Cables

Seabed Survey Aroundthe Structure

SP > 0

Refer to Note 3

Plug the Leekage orRemove the Oils from the

Gearbox & OtherRotaries Equipment

Deenergize the WT &Network

Refer to Note 1 Refer to Note 2Yes

No

Release the Cables Between Tower & TP

Inspect the Integrityof Primary, Secondary&Tertiary Structures

Refer to Note 4

UXO Observed

Debris Observed

Marine Archaeology

Special Marine Habitant

Yes

Yes

Log the ObservedObjects & Notify theConcerned Parties

Log the Observed Debris& Recover them

Yes

Yes

No

No

No

No

Finished

Finished

Wind Turbines

Refer To Note 2

Issued By Reviewed By Approved By

Hamed Askari Dr. Marcus Bentin WP Committee

Delivered To

Sheet 3 of 8DECOMTOOLS-WP4-PDOWP-EDP-A3-001 / Revision-00

NSR Joint Secretariat

Pre-Decommissioning Marine Operations of Offshore Wind Parks

Work Package Number: 04C.5.1.1: List of Process Description for

Offshore Decommission

20 August 2020 4 September 2020 18 September 2020 30 September 2020

Page 9: September 2020 Emden/Leer University of Applied Science

1. The cables are normally protected by three different strategies. The first method is burying the cable for 1-2 meters below the mudline (natural backfilling). If the burial of the cable isnot possible, the protection by means of tubular, mattress, sandbag and rock placement are options which is recommended by DNV-RP-J301. With any kind of non-burial protectionmethods, it is highly recommended to remove the protection and make the submarine cable ready for removal.

2. In-service assets are all offshore and marine infrastructure that are installed in the sea for a specific purpose. They can be pipeline, submarine cable, X-Mass trees and so on.

3. Abandoned assets can be any offshore module such as pipeline, submarine cables, x-mass tree, single point mooring (SPM or SBM) and so forth that are inoperative and disused.

4. After installation of submarine cable, as installed seabed survey shall be conducted. This survey can be done periodically during lifetime of the cable as a maintenance scheme. Incase of finding free span underneath of the cable, the free span correction should take place. Normal practice for free span correction is installation of mattress, grout bags, sandbagsand so forth. Therefore, after recovery of the cable, this means can be either left in situ or can be recovered, depends on the number and size of free span correction. In thisdocument, the default scenario is full removal of the materials.

Notes:

Preparatory Activitieson Submarine Cables Seabed Survey

Refer to Note 1

UXO Observed

Debris Observed

Marine Archaeology

SpecialMarine Habitant

Yes

Yes Log the ObservedObjects

Log the Observed Debris& Recover them

Yes

Yes

No

No

No

NoIn-Service

Assets

Abandoned Assets

Crossings with Other Assets

The Target Cable Shall beCut at Both End

No

Yes

YesConnect Buoys at the

End of Cables

Log the UXO & Report toThe Responsible

Authority

Log & Mark The In-Service Assets

Refer to Note 3

Necessary Measures forRecovery & Disposal of

UXO

Yes

Notify the ConcernedParties for Taking Further

Step

Log the ObservedObjects

Notify the ConcernedParties for Taking Further

Step

Log Abandoned Assets& Mark them if

Necessary

Notify the ConcernedParties for Taking Further

Step

Securing the Cable toAvoid Moving

To Remove Means ofCable Protection

To Remove Crossing, ifany

To Remove Means ofCable Protection

Finished

No

Remove the Free SpanCorrection, if any

Refer to Note 2

Refer to Note 4

Refer To Note 2

Issued By Reviewed By Approved By

Hamed Askari Dr. Marcus Bentin WP Committee

Delivered To

Sheet 4 of 8DECOMTOOLS-WP4-PDOWP-EDP-A3-001 / Revision-00

NSR Joint Secretariat

Pre-Decommissioning Marine Operations of Offshore Wind Parks

Work Package Number: 04C.5.1.1: List of Process Description for

Offshore Decommission

The Target Cable is Underneath

20 August 2020 4 September 2020 18 September 2020 30 September 2020

Yes

No

No

No

Page 10: September 2020 Emden/Leer University of Applied Science

Pre-DecommissioningActivities Related to

Offshore High VoltageSubstation

Topside

1. Inside the offshore high voltage substation, normally, office, workshop and in some cases accommodation are existed (Ref. DNVGL-RP-0423). Therefore, in the preparatory phase, all the items insidethese mentioned places should be secured.

2. Most of switchgears, busbars and transformers are oil-filled, gas-filled (SF6) or air-filled (Ref. DNVGL-RP-0423).The release or leakage of the materials from gas-filled or oil-filled equipment endangerthe safety of personal and environment (Evaluation of SF6 Leakage from Gas Insulated Equipment on Electricity Networks in Great Britain,2018).Therefore, prior to lifting operation and transportation tothe shore, the survey should be conducted in order to ascertain that no leakage will be occurred. Otherwise, either the leakage should be plugged or the gas or oil which are dielectric substances shouldbe removed from the equipment based on existing regulation and manufacturer's instruction manual in order to make the safe decommissioning operation.

3. In addition to first note, the tertiary structures such as handrails and gratings should be secured, if they are loose. The inspection of fire extinguisher bottles, other safety equipment such as lifeboats, liferafts, the telecommunication devices and so forth should be undertaken to make sure none of them are loose to prevent falling during lifting operations.

4. For the lifting operation, all overhangs from the structure should be measured to ascertain during the lifting, the structure does not have any clash with the vessel structure and hull. Therefore, the surveyshould be conducted and measurement of all overhangs should be carried out in order to make sure that vessel can lift the structure.

Notes:

Lifting TrunnionExisted?

Weld New LiftingTrunnion

NDT Test of WeldedTrunnion

NDT Test of ExistingLifting Trunnion

Observed Any Defects? Repair the Joint

No

Yes

Inspect the StructuralIntergrity of Topside

Inspect the EquipmentFor Oil & Gas Leakage

Drain the Fuel ofAuxiliary Diesel

Generator

Leak Detected No Hazard For Lifting &Transportation

De-Energize theElectrical Equipment

Release the Connecting Cables Between Topside

& Jacket

Remove OtherHazardous Materials

Plug the Leake or Drainthe Materials

Secure The Loose Itemsin the Topside like the

Workshop/Office/Accommodation

Secure The TopsidesCranes

Drain the Fuel of Crane(If it is Diesel-Powered)

Ready For Lifting

Disassemble theConnecting PipesBetween Topside &

Jacket

Survey the ProtrudingObjects From Topside

Refer to Note 4

Refer to Note 2

Refer to Note 3

No

Yes

Yes

No

Refer to Note 1

Finished

Support Structure DECOMTOOLS-WP4-PDOWP-EDP-A3-001 Sheet 06

Refer To Note 2

Issued By Reviewed By Approved By

Hamed Askari Dr. Marcus Bentin WP Committee

Delivered To

Sheet 5 of 8DECOMTOOLS-WP4-PDOWP-EDP-A3-001 / Revision-00

NSR Joint Secretariat

Pre-Decommissioning Marine Operations of Offshore Wind Parks

Work Package Number: 04C.5.1.1: List of Process Description for

Offshore Decommission

20 August 2020 4 September 2020 18 September 2020 30 September 2020

Secure Life SavingAppliances

Page 11: September 2020 Emden/Leer University of Applied Science

Cut the Cables Between J/I Tube & Subsea

NetworkRecover the CableSupport Structure

Seabed Survey Aroundthe Structure

Inspect the Integrityof Secondary &Tertiary

Structures

Refer to Note 1

UXO Observed

Debris Observed

Marine Archaeology

Special Marine Habitant

Yes

Yes

Log the ObservedObjects & Notify theConcerned Parties

Log the Observed Debris& Recover them

Yes

No

No

No

Refer To Note 2

Issued By Reviewed By Approved By

Hamed Askari Dr. Marcus Bentin WP Committee

Delivered To

Sheet 6 of 8DECOMTOOLS-WP4-PDOWP-EDP-A3-001 / Revision-00

NSR Joint Secretariat

Pre-Decommissioning Marine Operations of Offshore Wind Parks

1. At entrance point of the J-I Tube underwater, normally a structure made of concrete in a shape of pyramid is installed in order to support the weight of cable between the seabed to theJ/Tube. This kind of support structure can be kept in situ or can be recovered. In this document entire removal is considered to prevent future claim from other sea users.

2. For the definition of secondary and tertiary structure, please refer to document number DECOMTOOLS-WP5-OWPPM-EDP-001-A3-01 product model, sheets 4 & 5.

Notes:

Connect the Buoy to theEnd of Cut Cables

Yes

DECOMTOOLS-WP4-PDOWP-EDP-A3-001 Sheet 07

DECOMTOOLS-WP4-PDOWP-EDP-A3-001 Sheet 07Pre-Decommissioning

Activities Related toSupport Structure of

OHVS

Refer to Note 2

Preparatory Activitieson Support Structure

Preparatory Activitieson Cable & Seabed

Around OHVS SupportStructure

Remove the MarineGrowth

Work Package Number: 04C.5.1.1: List of Process Description for

Offshore Decommission

20 August 2020 4 September 2020 18 September 2020 30 September 2020

Page 12: September 2020 Emden/Leer University of Applied Science

Refer to Note 1

Lifting TrunnionExisted?

Weld New LiftingTrunnion

NDT Test of WeldedTrunnion

NDT Test of ExistingLifting Trunnion

Observed Any Defects? Repair the Joint

No

Ready For Lifting

No

Yes

1. The support structure of offshore high voltage substation can be installed in two different methods. Piled structure and gravity-based structure (GBS). Installation of GBS are takenplace in two different methods. Some of them can be de-ballasted and refloated and others cannot. Even some of the GBS that can be refloated, due to corrosion of piping andballasting system, new systems would have to be installed to assure the reliability of the system (Decommissioning offshore concrete platforms, prepared Atkins Process Limited andOlav Olsen A/S for the Health and Safety Executive 2003). In addition to GBS, the most installed type of piled structures is lattice type.The study in this document covers thoseinstalled GBS that can be ballasted and refloated and secondly the lattice structures.

2. Structural integrity of the concrete structures during removal could be compromised by pre-existing structural cracking and other defects which have arisen during the installations’service lives(Decommissioning offshore concrete platforms, prepared Atkins Process Limited and Olav Olsen A/S for the Health and Safety Executive 2003,p 4). Therefore, theobserved crack shall be rectified to avoid accident during towage.

Notes:

Yes

Piled Structure

Gravity Based Structure

DefectiveInstall Functional Ballast

System or Repair theExisiting one

Function TestNo

Ready For Ballasting &Towing

Yes

Refer to Note 1 Finished

NDT Test to Check the Structural integrity of the

structures

Check Functionality ofBallasting System

Defects Observed

Change the Oils ofRotary Equipment, if

needed

Repair the DefectsYes

No

Refer to Note 2

Refer to Note 2

DECOMTOOLS-WP4-PDOWP-EDP-A3-001 Sheet 06

Refer To Note 2

Issued By Reviewed By Approved By

Hamed Askari Dr. Marcus Bentin WP Committee

Delivered To

Sheet 7 of 8DECOMTOOLS-WP4-PDOWP-EDP-A3-001 / Revision-00

NSR Joint Secretariat

Pre-Decommissioning Marine Operations of Offshore Wind Parks

Work Package Number: 04C.5.1.1: List of Process Description for

Offshore Decommission

20 August 2020 4 September 2020 18 September 2020 30 September 2020

Page 13: September 2020 Emden/Leer University of Applied Science

Refer to Note 1

Disassemble TheFunctional

Instrumentation

Disconnect the cablesBetween Sections of

Towers Function Test ofInstrumentation

1. All the functional instrumentation can be disassembled except the AtoN (aids to navigation) and aviation lights. This equipment shall be kept in order to prevent accident with othervessels, helicopters, aircrafts and so forth.

Notes:

Equipment &Instrumentation

Support StructureNo

Pre-DecommissioningActivities Related to

Meteorological Mast

Seabed Survey Aroundthe Structure

Lifting TrunnionExisted?

Weld New LiftingTrunnion

NDT Test of WeldedTrunnion

NDT Test of ExistingLifting Trunnion

Observed Any Defects? Repair the Joint

No

Yes

Ready For Lifting

No

Yes

Remove the MarineGrowth

Cut the Cables Between J/I Tube & Subsea

NetworkConnect the Buoy to the

End of CablesInspect the Integrity

of Primary, Secondary&Tertiary Structures

UXO Observed

Debris Observed

Marine Archaeology

Special Marine Habitant

Yes

Yes

Log the ObservedObjects & Notify theConcerned Parties

Log the Observed Debris& Recover them

Yes

Yes

No

No

No

No

Finished

Secure Life SavingAppliances

Refer To Note 2

Issued By Reviewed By Approved By

Hamed Askari Dr. Marcus Bentin WP Committee

Delivered To

Sheet 8 of 8DECOMTOOLS-WP4-PDOWP-EDP-A3-001 / Revision-00

NSR Joint Secretariat

Pre-Decommissioning Marine Operations of Offshore Wind Parks

Work Package Number: 04C.5.1.1: List of Process Description for

Offshore Decommission

20 August 2020 4 September 2020 18 September 2020 30 September 2020


Recommended