2
Demolition
There will always be a need for demolition as
buildings deteriorate with age to the point of
instability and where existing buildings must be
replaced in the cause of redevelopment.
3
Demolition
Demolition is one of the most dangerous activities
undertaken in the construction industry.
An accident on demolition work is much more likely
to be fatal and serious than on other construction
work.
4
Demolition
There are various causes attributing the accidents
in demolition works:
structure to be demolished without adequate
background information;
incompliance with planned work method;
site management staff and operatives acquire
insufficient training to identify the hazards, etc.
5
Demolition
Generally, demolition works should be planned in
similar details to other building operations or works
of engineering construction.
To ensure safety and health of workers, a safe
system of demolition work need to be estabished
and implemented carefully.
6
Pre-demolition survey
Prior to demolition taking place, it is necessary to
collect data as well as on-site surveys on the
building to be demolished, in order to establish the
safe system of work.
The system will be determined by a pre-demolition
survey undertaken by a competent person,
appointed by the employer.
7
Pre-demolition survey
The pre-demolition survey should identify:
The nature and method of construction of the
building;
The arrangement of buildings adjacent to that for
demolition and the condition of this adjoining
property;
The location of underground services, e.g. water
mains, electricity cables, gas pipes, drains, sewers,
telephone cables, etc;
8
Pre-demolition survey
The previous use of premises, e.g. for the storage of
inflammable substances;
The presence of dangerous substances, e.g. asbestos
lagging;
The method of bonding of the main load-bearing
walls;
The system of shoring or other supports necessary
during demolition;
9
Pre-demolition survey
The presence of cantilevered structures, their form of
construction and the nature of the danger;
The presence of basements, cellars, vaults or other
spaces affecting the structure of adjoining properties;
The potentially dangerous effects of removing
superstructure stabilizing loads from an old
basement or vault retaining walls;
10
Pre-demolition survey
The presence of storage tanks below and above
ground, and the nature of their contents; and
The actual sequence of operations, which should
generally take place in the reverse order of building
erection.
11
Pre-demolition
Before the demolition begins, a risk assessment
should be conducted to assess the condition of the
demolition works, to find out any foreseeable
hazards and to devise and adopt suitable safety
measures.
The use of a demolition hazard checklist is
recommended.
12
Structural Design
To study the design of the building structure is a
very important step in the survey.
If special design such as arches, pre-stressed
reinforcement, reinforcement under tension, curtain
wall or thin shell is observed, special shoring and
demolition method should be adopted.
13
Structural Design
It has to find out whether the structure is capable to
withstand the increasing load as the process
proceeds.
Temporary support and suitable method could be
devised to cope with the additional loading.
14
Structural Design
The structural survey should note variation to the
original plan due to structural alterations and
additions.
Special precautions should be observed to handle
structural alteration such as external metal cages,
water cooling towers and canopies, etc.
15
Structural Design
Buildings or structures may have seriously
weakened after heavily used for many years or
exposed to adverse environment.
The protective element of reinforced bar may be
corroded or the concrete may be weakened by
weathering. The structural integrity of the building
may not be as safe as its original design.
It is important to determine the structural condition
as serious deterioration may impose restrictions on
the demolition method.
16
Hazards associated with the
previous use of the building
The previous use of the building may have
produced hazards requiring detailed surveys to be
carried out.
In buildings where chemicals may have been stored
and used, such as factory buildings and hospitals,
hazards associated with flammable material and
substances hazardous to health should be
identified.
17
Hazards associated with the
previous use of the building
This survey should be conducted by experienced
and competent persons and should observe:
Dangerous goods stores may co-exist with boilers
or other naked flame processes in hospitals or
industrial undertakings.
Storage of hazardous substances may exist. Large
quantities of toxic or harmful chemicals may be
used in some of the manufacturing processes.
18
Hazards associated with the
previous use of the building
Hazardous substances may also exist in building
material or industrial installations, e.g. asbestos
may exist in heat insulating material in boiler rooms,
lead may exist in paints, chemicals may exist in
pipes radio-active material may exist in equipment.
19
Building Services
The survey should cover also the installation of
building services such as electricity, gas, water
pipes, drainage, telephone, radio an TV lines.
Written confirmation should be obtained from the
relevant authorities before commencement of the
demolition works to ensure that all known supplies
have been cut off from the site except those
required for the execution of the work.
20
Safe working method statement
The precaution to combat the identified hazards,
protect workers and remove hazardous material
together with the preferred demolition procedure,
should be set out in a method statement approved
by the relevant authorities.
A detailed method statement, produced before work
starts, is essential for safe working. It should
identify problems and their solutions, and form a
reference for site supervision.
21
Safe working method statement
The method statement should be easy to
understand and suitably illustrated by diagrams;
should be agreed by and known to all levels of
management and supervision, including those of
the sub-contractors.
Working method should be revised to cope with
unforeseeable hazards during the demolition
process and any changes should be made know to
all parties concerned.
22
Safe working method statement
The method statement should include controlling
measures to ensure that the sequence and method
by which the elements of a building are to be
demolished must be decided before work starts.
At each stage of work a conscious appraisal of risk
of collapse must be made, the precautions worked
out and workforce properly controlled to ensure that
the precautions are put into practice.
23
Safe working method statement
A comprehensive method statement should include
the followings:
Work schedule and the sequence of demolition,
especially to the sequence of cantilever structure
demolition. Design suitable demolition method to
tackle with special structures, e.g. chimney, steel
structure, pre-stressed concrete, electric cable
tower and water-cooling tower.
24
Safe working method statement
Selection of suitable machinery and equipment.
Temporary shoring method and other precautionary
measures to safeguard the stability of any adjoining
and adjacent buildings.
Details of safety procedures to remove or cut off the
existing utility installations such as electrical, gas,
drains and other services.
25
Safe working method statement
Details of temporary services required for execution
of work.
Details of methods for dealing with flammable
material and gases.
Details of methods to be used for the disposal of
substances hazardous to health and any necessary
protective equipment.
26
Safe working method statement
Arrangement for the control of site transport used
for the removal of demolition debris.
Special precautions for entering confined space in
demolition site.
Arrangement for the protection of personnel and
public and the exclusion of unauthorized person.
27
Safe working method statement
Measures to protect the environment, e.g.
controlling the emission of excessive noise and
dust from demolition.
Contingency plan for typhoon, storm, flooding, fire,
explosion and industrial accident.
28
Demolition
Where possible, demolition should be carried out in
the reverse order of building erection.
No isolated freestanding wall should be left unless
judged to be secure by the competent person in
charge.
Scaffold working platforms should be used, all
refuse and debris being removed from these
temporary structures on a regular basis to avoid
overloading.
29
Demolition
Debris which has accumulated behind walls should
also be removed.
Independently supported working platforms over
any reinforced concrete slabs should be
demolished.
Support for members of framed structures must be
provided before gutting, along with temporary
props, bracing or guys to restrain remaining parts
of the building.
30
Demolition
On no account must operators work from the noor
being demolished, and site control must ensure that
all personnel are kept at a safe distance from the
scene of operations, when pulling arrangements,
demolition balls, pusher arms and/or explosives are
being used.
31
Demolition
An on-going system of inspection must be
maintained during demolition to detect further
hazards which may result from the demolition
process, e.g. loosened materials, overloaded floors.
32
Working at height
Whenever the demolition work has to be conducted
at heights, suitable working platforms or
scaffoldings should be erected.
They should be designed by a professional
engineer; erected, altered or demolished by
adequately trained and experienced workers under
the close supervision of a competent person.
33
Use of machinery
If the building is to be demolished by excavator, it
must be ascertained that the structure can
withstand the weight of the excavator and the
accumulated debris. Suitable propping should be
provided if found necessary
The machine must be maintained in a safe working
condition in accordance with the Regulations.
34
Use of machinery
The cab of all machines should be strong enough to
protect the operator against the fall of debris.
Machinery operator shall be properly trained in the
skill of demolition as well as safe practices so as to
maintain their level of awareness.
The excavator operator must take care not to
damage the beams and columns supporting the
excavator.
35
Debris and waste disposal
No part of the building under demolition shall be
allowed to be so overloaded with debris or material
as to render it unsafe to workers employed.
Special attention must be paid to the debris at
ground level as lateral force created by the debris
and the machinery under use would cause the side
wall to collapse.
Debris and rubbish shall be cleared regularly to
avoid overloading.
36
Debris and waste disposal
Debris may be allowed to fall through floor
openings but must be closely supervised. Under no
circumstances should debris be allowed to fall
outside the building.
Large pieces of debris shall be lowered properly by
cranes.
37
Safe working on Demolition
sites
All precautionary measures are in place before
commencement of demolition works. Pay special
attention to the demolition of special structures,
cantilever, chimney, and pre-stressed structure.
Ensure that a professional engineer has inspected
the structure/adjacent structure and a competent
person is in charge of the operation.
39
Safe working on Demolition
sites
Pay attention to the presence of flammable or
hazardous substances such as asbestos in
insulation, lead in paints and radio-active
substances in laboratory equipment.
In buildings where carcinogenic chemicals may
have been used or stored such as factory and
hospitals, associated hazards shall be identified by
an experienced competent person.
40
Safe working on Demolition
sites
Check and ensure that existing floors planned to be
used are not overloaded. Otherwise, shoring should
be installed to support the floors.
Provide sufficient shoring to prevent premature
structural collapse or damage to adjacent property.
41
Safe working on Demolition
sites
Ensure that the site is properly enclosed. Scaffold
with screen and catch-fan, and hoarding or covered
walkway shall be erected.
Erect warning and information notices.
Ensure that all ladders, cranes, cables and other
equipment are in good order.
42
Safe working on Demolition
sites
Ensure that suitable personal protective equipment
is provided and used during operation. Suitable
anchorage points for safety belts and safety
harnesses shall be identified and assessed by
competent persons or Professional Engineers.
Adequate protection and safe access for the public
and workers are provided at all times, including
protection from dust and noise hazards.
43
Safe working on Demolition
sites
Provide sedimentation/treatment system to prevent
silty / dirty water discharging into water courses or
public drains.
Properly plan the daily work. Complete the
scheduled work and check the stability condition of
the structure under demolition prior to leaving the
site at the end of each working day.