Date post: | 18-Jan-2016 |
Category: |
Documents |
Upload: | eustace-lang |
View: | 222 times |
Download: | 0 times |
Chamonix XV January 2006 T.Pettersson EDMS:701925 1
Session 6 - LHC Installation
Installation – some issues
Chamonix XV January 2006 T.Pettersson EDMS:701925 2
Session 6 - LHC Installation
Contents
• Still on time? – S. Weisz (TS)• Security - a reminder – M.Vadon (TS)• LHC Access system – progress – P.Ninin (TS)• SPS Access system – 2006 – E. Manola-Poggioli• QRL installation and first experiences of
operation– G. Riddone (TS)• MME Workpackages for LHC - V. Vuillemin (TS)• ELQA – S. Russenchuck (AT)
Chamonix XV January 2006 T.Pettersson EDMS:701925 3
Session 6 - LHC Installation
Schedule
• Ramping-up of many new activities in 2005:– Repair, installation and tests of the QRL– Surface logistics, preparation and underground transports of
magnets – Alignment, interconnect in a difficult environment (space & co-
activities
• Good progress has been made but present rates have to be further increased to meet our success oriented schedule.
• E.g. magnet transport has doubled from a nominal 10/week to 20/week. Presentation indicated some areas of concern that are being attended to by the project. New official schedule will be released during the spring taking into account learning curves, resource allocations etc..
Chamonix XV January 2006 T.Pettersson EDMS:701925 4
Session 6 - LHC Installation
Access systems - Access Point LHC0
PADMAD
Display
Signalisation
Tokens Distributors
Badge readerIntercom
Biometry
Radiation key
Chamonix XV January 2006 T.Pettersson EDMS:701925 5
Session 6 - LHC Installation
Security
• An accident may have catastrophic consequences on the whole project
• The level of safety revels the respect of the schedule, of quality and of the environment
• Everybody shall be involved
• Compression of the planning must be done without compromise on safety
Chamonix XV January 2006 T.Pettersson EDMS:701925 6
Session 6 - LHC Installation
SPS Upgrade Project: phases and milestones
t
Système d’accès SPS
actuel
Système d’accès SPS
actuel
NouveauSystème
d’accès SPS
Mesures compensatoires
Ru
n
’06
SP
S
Ru
n ‘
07
S
PS
+L
HC
Ru
n ‘
’08
S
PS
+L
HC
Introduction d’une voie
câbléeredondante
*Date suivant le schedule des accelerateurs
Voie câbléeredondante
Shutdow
n
Shutdow
n
Chamonix XV January 2006 T.Pettersson EDMS:701925 7
Session 6 - LHC Installation
Compensatory measures 2006: connection with the AUG chains
Chamonix XV January 2006 T.Pettersson EDMS:701925 8
Session 6 - LHC Installation
Status of the QRL installation
Chamonix XV January 2006 T.Pettersson EDMS:701925 9
Session 6 - LHC Installation Flushing and cool-down
configuration
Sector 7-8 Sector 8-1
Point 8
Sur
face
Cav
ern
QSCA QSCB
QSRB
QURC
QUIC
QURA
Sha
ft
QSCC QSCC
Tun
nel
Storage
QURC
QSRA
Chamonix XV January 2006 T.Pettersson EDMS:701925 10
Session 6 - LHC Installation
QRL - performance
• Cold reception tests performed for sectors 7-8 (A and B) and 8-1 • Successful thermo-mechanical validation of the QRL design• Thermometer accuracy, much better than specification• Heat inleaks to 50-75 K (headers E and F) circuit within specification • For sector 7-8 (sub-sectors A and B) heat inleaks to 4-20 K (headers
B, C and D) above specification. • For sector 8-1 heat inleaks to 4-20 K circuit are within specification• Other QRL sectors cold tested with the cryo-magnets:
Chamonix XV January 2006 T.Pettersson EDMS:701925 11
Session 6 - LHC Installation
GENERAL COMMENTS
Jan – April 2006: 11’000 h scheduled in TS assembly workshopmeans 16 – 17 persons full timefully bookedovertime work will be necessary
All our jobs are on the LHC priority list (like the DFB’s, CMS ECAL, …)Only possibility for new items in this period: TS-MME helps in finding a solution towards outsourcing.
Risks will have to be taken in outsourcing most of the activities for AT-VAC,which are not “multiple technology” items. This will require to monitor closely the production in industries (require also efforts).
There are always LHC urgencies (LEIR, SSS in bldg 904, ATLAS) for specificwelding requiring expertise.
No manpower available for the collimators outside the people in the design area.
Priority needed from AB on AB/ATB versus AB/BDI requests.
MME Workpackages
Chamonix XV January 2006 T.Pettersson EDMS:701925 12
Session 6 - LHC Installation
Chamonix XV January 2006 T.Pettersson EDMS:701925 13
Session 6 - LHC Installation
First Series ELQA-PAQ
– Successful qualification of the hardware and software
– NC discovered (EDMS 696203) crossing of spool piece busbars inside SSS HCLQATH001-CR000046
– Time for automatic test (preparation, continuity and highpot checks): 56 min
– Time for manual diagnostic of NC: 90 min
– Handling of NC, MTF, Emails, Meetings, Decision making: Endless
Chamonix XV January 2006 T.Pettersson EDMS:701925 14
Session 6 - LHC Installation
Electrical Quality Assurance and Mr. Polarity
• Electrical Quality Assurance (AT-MEL-EM + HNINP)– To ensure the integrity of the electrical circuits during machine assembly and
commissioning and to guarantee that the electrical interconnections correspond to the LHC powering layout. To ensure traceability of checks while considering all electrical non-conformities
– ELQA is not concerned with the qualification of individual components (polarity, continuity, labeling, electrical integrity, voltage taps, magnet type and position)
• Magnet Polarity Coordination (Mr. Polarity)– To ensure the coherence in the definition of the magnet polarities among MAD
input files, the LHC reference database, field computations, field measurements, interconnection works and the powering of electrical circuits
– To liaise with the different groups responsible for production, measurement, interconnection and powering of the LHC magnets, including the magnets for the arcs, the insertion regions and the transfer lines.
Chamonix XV January 2006 T.Pettersson EDMS:701925 15
Session 6 - LHC Installation
Ready for 8 fronts of QA…
Chamonix XV January 2006 T.Pettersson EDMS:701925 16
Session 6 - LHC Installation
Conclusions
• Schedule – good progress has been made but present rates have to be further increased to meet our success oriented schedule. Presentation indicated some areas of concern that are being attended to. New official schedule will be released during the spring.
• Security – accidents can and must be prevented. Responsibilities are DG-DH-GL-project engineer – no parallel hierarchy exists in matters of security.
• Access systems – LHC is back on track and doing good progress. SPS will be a major challenge to do in parallel.
• QRL – Supplier is getting closer to nominal rates. Issues about leak detection and repair will be permanently present.
• MME support – Presently there is no slack left in the group’s resource allocation. The design office and workshops are providing a major effort handling both planned and unplanned activities – Any new incidents or any badly organised projects will have to wait or will cause delays in other important activities.
• ELQA - Tools are ready. Strategy to be applied must include a global overview of the arcs (act locally, think globally). Treatment of non conformities is highly time consuming. As-built database mandatory.