+ All Categories
Home > Documents > Session 6 - LHC Installation Chamonix XV January 2006 T.Pettersson EDMS:7019251 Installation –...

Session 6 - LHC Installation Chamonix XV January 2006 T.Pettersson EDMS:7019251 Installation –...

Date post: 18-Jan-2016
Category:
Upload: eustace-lang
View: 222 times
Download: 0 times
Share this document with a friend
16
Chamonix XV January 2006 T.Pettersson EDMS:701925 1 Session 6 - LHC Installation Installation – some issues
Transcript
Page 1: Session 6 - LHC Installation Chamonix XV January 2006 T.Pettersson EDMS:7019251 Installation – some issues.

Chamonix XV January 2006 T.Pettersson EDMS:701925 1

Session 6 - LHC Installation

Installation – some issues

Page 2: Session 6 - LHC Installation Chamonix XV January 2006 T.Pettersson EDMS:7019251 Installation – some issues.

Chamonix XV January 2006 T.Pettersson EDMS:701925 2

Session 6 - LHC Installation

Contents

• Still on time? – S. Weisz (TS)• Security - a reminder – M.Vadon (TS)• LHC Access system – progress – P.Ninin (TS)• SPS Access system – 2006 – E. Manola-Poggioli• QRL installation and first experiences of

operation– G. Riddone (TS)• MME Workpackages for LHC - V. Vuillemin (TS)• ELQA – S. Russenchuck (AT)

Page 3: Session 6 - LHC Installation Chamonix XV January 2006 T.Pettersson EDMS:7019251 Installation – some issues.

Chamonix XV January 2006 T.Pettersson EDMS:701925 3

Session 6 - LHC Installation

Schedule

• Ramping-up of many new activities in 2005:– Repair, installation and tests of the QRL– Surface logistics, preparation and underground transports of

magnets – Alignment, interconnect in a difficult environment (space & co-

activities

• Good progress has been made but present rates have to be further increased to meet our success oriented schedule.

• E.g. magnet transport has doubled from a nominal 10/week to 20/week. Presentation indicated some areas of concern that are being attended to by the project. New official schedule will be released during the spring taking into account learning curves, resource allocations etc..

Page 4: Session 6 - LHC Installation Chamonix XV January 2006 T.Pettersson EDMS:7019251 Installation – some issues.

Chamonix XV January 2006 T.Pettersson EDMS:701925 4

Session 6 - LHC Installation

Access systems - Access Point LHC0

PADMAD

Display

Signalisation

Tokens Distributors

Badge readerIntercom

Biometry

Radiation key

Page 5: Session 6 - LHC Installation Chamonix XV January 2006 T.Pettersson EDMS:7019251 Installation – some issues.

Chamonix XV January 2006 T.Pettersson EDMS:701925 5

Session 6 - LHC Installation

Security

• An accident may have catastrophic consequences on the whole project

• The level of safety revels the respect of the schedule, of quality and of the environment

• Everybody shall be involved

• Compression of the planning must be done without compromise on safety

Page 6: Session 6 - LHC Installation Chamonix XV January 2006 T.Pettersson EDMS:7019251 Installation – some issues.

Chamonix XV January 2006 T.Pettersson EDMS:701925 6

Session 6 - LHC Installation

SPS Upgrade Project: phases and milestones

t

Système d’accès SPS

actuel

Système d’accès SPS

actuel

NouveauSystème

d’accès SPS

Mesures compensatoires

Ru

n

’06

SP

S

Ru

n ‘

07

S

PS

+L

HC

Ru

n ‘

’08

S

PS

+L

HC

Introduction d’une voie

câbléeredondante

*Date suivant le schedule des accelerateurs

Voie câbléeredondante

Shutdow

n

Shutdow

n

Page 7: Session 6 - LHC Installation Chamonix XV January 2006 T.Pettersson EDMS:7019251 Installation – some issues.

Chamonix XV January 2006 T.Pettersson EDMS:701925 7

Session 6 - LHC Installation

Compensatory measures 2006: connection with the AUG chains

Page 8: Session 6 - LHC Installation Chamonix XV January 2006 T.Pettersson EDMS:7019251 Installation – some issues.

Chamonix XV January 2006 T.Pettersson EDMS:701925 8

Session 6 - LHC Installation

Status of the QRL installation

Page 9: Session 6 - LHC Installation Chamonix XV January 2006 T.Pettersson EDMS:7019251 Installation – some issues.

Chamonix XV January 2006 T.Pettersson EDMS:701925 9

Session 6 - LHC Installation Flushing and cool-down

configuration

Sector 7-8 Sector 8-1

Point 8

Sur

face

Cav

ern

QSCA QSCB

QSRB

QURC

QUIC

QURA

Sha

ft

QSCC QSCC

Tun

nel

Storage

QURC

QSRA

Page 10: Session 6 - LHC Installation Chamonix XV January 2006 T.Pettersson EDMS:7019251 Installation – some issues.

Chamonix XV January 2006 T.Pettersson EDMS:701925 10

Session 6 - LHC Installation

QRL - performance

• Cold reception tests performed for sectors 7-8 (A and B) and 8-1 • Successful thermo-mechanical validation of the QRL design• Thermometer accuracy, much better than specification• Heat inleaks to 50-75 K (headers E and F) circuit within specification • For sector 7-8 (sub-sectors A and B) heat inleaks to 4-20 K (headers

B, C and D) above specification. • For sector 8-1 heat inleaks to 4-20 K circuit are within specification• Other QRL sectors cold tested with the cryo-magnets:

Page 11: Session 6 - LHC Installation Chamonix XV January 2006 T.Pettersson EDMS:7019251 Installation – some issues.

Chamonix XV January 2006 T.Pettersson EDMS:701925 11

Session 6 - LHC Installation

GENERAL COMMENTS

Jan – April 2006: 11’000 h scheduled in TS assembly workshopmeans 16 – 17 persons full timefully bookedovertime work will be necessary

All our jobs are on the LHC priority list (like the DFB’s, CMS ECAL, …)Only possibility for new items in this period: TS-MME helps in finding a solution towards outsourcing.

Risks will have to be taken in outsourcing most of the activities for AT-VAC,which are not “multiple technology” items. This will require to monitor closely the production in industries (require also efforts).

There are always LHC urgencies (LEIR, SSS in bldg 904, ATLAS) for specificwelding requiring expertise.

No manpower available for the collimators outside the people in the design area.

Priority needed from AB on AB/ATB versus AB/BDI requests.

MME Workpackages

Page 12: Session 6 - LHC Installation Chamonix XV January 2006 T.Pettersson EDMS:7019251 Installation – some issues.

Chamonix XV January 2006 T.Pettersson EDMS:701925 12

Session 6 - LHC Installation

Page 13: Session 6 - LHC Installation Chamonix XV January 2006 T.Pettersson EDMS:7019251 Installation – some issues.

Chamonix XV January 2006 T.Pettersson EDMS:701925 13

Session 6 - LHC Installation

First Series ELQA-PAQ

– Successful qualification of the hardware and software

– NC discovered (EDMS 696203) crossing of spool piece busbars inside SSS HCLQATH001-CR000046

– Time for automatic test (preparation, continuity and highpot checks): 56 min

– Time for manual diagnostic of NC: 90 min

– Handling of NC, MTF, Emails, Meetings, Decision making: Endless

Page 14: Session 6 - LHC Installation Chamonix XV January 2006 T.Pettersson EDMS:7019251 Installation – some issues.

Chamonix XV January 2006 T.Pettersson EDMS:701925 14

Session 6 - LHC Installation

Electrical Quality Assurance and Mr. Polarity

• Electrical Quality Assurance (AT-MEL-EM + HNINP)– To ensure the integrity of the electrical circuits during machine assembly and

commissioning and to guarantee that the electrical interconnections correspond to the LHC powering layout. To ensure traceability of checks while considering all electrical non-conformities

– ELQA is not concerned with the qualification of individual components (polarity, continuity, labeling, electrical integrity, voltage taps, magnet type and position)

• Magnet Polarity Coordination (Mr. Polarity)– To ensure the coherence in the definition of the magnet polarities among MAD

input files, the LHC reference database, field computations, field measurements, interconnection works and the powering of electrical circuits

– To liaise with the different groups responsible for production, measurement, interconnection and powering of the LHC magnets, including the magnets for the arcs, the insertion regions and the transfer lines.

Page 15: Session 6 - LHC Installation Chamonix XV January 2006 T.Pettersson EDMS:7019251 Installation – some issues.

Chamonix XV January 2006 T.Pettersson EDMS:701925 15

Session 6 - LHC Installation

Ready for 8 fronts of QA…

Page 16: Session 6 - LHC Installation Chamonix XV January 2006 T.Pettersson EDMS:7019251 Installation – some issues.

Chamonix XV January 2006 T.Pettersson EDMS:701925 16

Session 6 - LHC Installation

Conclusions

• Schedule – good progress has been made but present rates have to be further increased to meet our success oriented schedule. Presentation indicated some areas of concern that are being attended to. New official schedule will be released during the spring.

• Security – accidents can and must be prevented. Responsibilities are DG-DH-GL-project engineer – no parallel hierarchy exists in matters of security.

• Access systems – LHC is back on track and doing good progress. SPS will be a major challenge to do in parallel.

• QRL – Supplier is getting closer to nominal rates. Issues about leak detection and repair will be permanently present.

• MME support – Presently there is no slack left in the group’s resource allocation. The design office and workshops are providing a major effort handling both planned and unplanned activities – Any new incidents or any badly organised projects will have to wait or will cause delays in other important activities.

• ELQA - Tools are ready. Strategy to be applied must include a global overview of the arcs (act locally, think globally). Treatment of non conformities is highly time consuming. As-built database mandatory.


Recommended