CONCRETE WORKS S1 COÂNG TAÙC BEÂ TOÂNG CONTENTS NOÄI DUNG 1 SCOPE OF WORK NOÄI DUNG COÂNG TAÙC 2 MATERIALS VAÄT LIEÄU 3 EXECUTION THI COÂNG 1 SCOPE OF WORK NOÄI DUNG COÂNG TAÙC 1.1 GENERAL TOÅNG QUAÙT 1.1.1 Works Coâng taùc The work includes furnishing all labour, plant, equipment and materials in connection with the supply, mixing and placing of all concrete and the supply, fabrication and erection of all reinforcing steel, together with all other associated trade work, complete as shown, as specified, or as necessary. Coâng taùc naøy bao goàm cung caáp lao ñoäng, trang thieát bò, vaät tö lieân quan ñeán vieäc cung caáp, troän vaø ñoå beâ toâng; cung caáp, gia coâng, laép ñaët coát theùp phoái hôïp cuøng vôùi caùc Nhaø thaàu khaùc. The Contractor shall make provisions and preparations and do all necessary work to receive or adjoin other work. Nhaø thaàu phaûi döï truø, chuaån bò ñeå noái keát phaàn vieäc cuûa mình vaøo coâng taùc cuûa caùc Nhaø thaàu khaùc. The Contractor shall be responsible for installation of fixings, etc., embedded in concrete, provision of holes, openings, etc., necessary to execute work of other trades. Nhaø thaàu chòu traùch nhieäm laép ñaët caùc chi tieát coá ñònh vaøo beâ toâng; cung caáp caùc loã môû theo yeâu caàu cuûa caùc Nhaø thaàu khaùc. Inspect embedded items and check accuracy prior to placing concrete. Nhaø thaàu phaûi kieåm tra caùc chi tieát choân trong beâ toâng (ñeå ñaûm baûo vò trí chính xaùc) tröôùc khi tieán haønh ñoå beâ toâng. Concrete, formwork and reinforcing steel requirements shall be as BS 8110: 1997, except where modified by this Specification. Caùc yeâu caàu veà beâ toâng, vaùn khuoân, coát theùp phaûi tuaân thuû tieâu chuaån BS 8110: 1997, ngoaïi tröø khi ñaëc ñieåm kyõ thuaät coù qui ñònh khaùc. The Contractor shall ensure that copies of this standard are available on site for reference. Nhaø thaàu caàn coù boä tieâu chuaån naøy taïi hieän tröôøng ñeå tham khaûo. 1.1.2 Record of Work Baùo caùo coâng vieäc The Contractor shall maintain and submit a weekly record in an approved format, such as electronic photos at different locations of the site but not les than 10 locations, which shall indicate major work carried out including temporary Nhaø thaàu thöïc hieän vaø trình baùo caùo haøng tuaàn theo maãu ñònh saün, trong ñoù goàm hình chuïp caùc vò trí khaùc nhau nhöng khoâng döôùi 10 vò trí ôû coâng tröôøng. Hình theå hieän caùc vieäc chính ñang thi coâng goàm caùc haïng muïc thi coâng taïm (neáu coù), laép ñaët Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 1 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006
Transcript
Page 1: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

CONCRETE WORKSS1 COÂNG TAÙC BEÂ TOÂNG

CONTENTS NOÄI DUNG

1 SCOPE OF WORK NOÄI DUNG COÂNG TAÙC

2 MATERIALS VAÄT LIEÄU

3 EXECUTION THI COÂNG

1 SCOPE OF WORK NOÄI DUNG COÂNG TAÙC

1.1 GENERAL TOÅNG QUAÙT

1.1.1 Works Coâng taùc

The work includes furnishing all labour, plant, equipment and materials in connection with the supply, mixing and placing of all concrete and the supply, fabrication and erection of all reinforcing steel, together with all other associated trade work, complete as shown, as specified, or as necessary.

Coâng taùc naøy bao goàm cung caáp lao ñoäng, trang thieát bò, vaät tö lieân quan ñeán vieäc cung caáp, troän vaø ñoå beâ toâng; cung caáp, gia coâng, laép ñaët coát theùp phoái hôïp cuøng vôùi caùc Nhaø thaàu khaùc.

The Contractor shall make provisions and preparations and do all necessary work to receive or adjoin other work.

Nhaø thaàu phaûi döï truø, chuaån bò ñeå noái keát phaàn vieäc cuûa mình vaøo coâng taùc cuûa caùc Nhaø thaàu khaùc.

The Contractor shall be responsible for installation of fixings, etc., embedded in concrete, provision of holes, openings, etc., necessary to execute work of other trades.

Nhaø thaàu chòu traùch nhieäm laép ñaët caùc chi tieát coá ñònh vaøo beâ toâng; cung caáp caùc loã môû theo yeâu caàu cuûa caùc Nhaø thaàu khaùc.

Inspect embedded items and check accuracy prior to placing concrete.

Nhaø thaàu phaûi kieåm tra caùc chi tieát choân trong beâ toâng (ñeå ñaûm baûo vò trí chính xaùc) tröôùc khi tieán haønh ñoå beâ toâng.

Concrete, formwork and reinforcing steel requirements shall be as BS 8110: 1997, except where modified by this Specification.

Caùc yeâu caàu veà beâ toâng, vaùn khuoân, coát theùp phaûi tuaân thuû tieâu chuaån BS 8110: 1997, ngoaïi tröø khi ñaëc ñieåm kyõ thuaät coù qui ñònh khaùc.

The Contractor shall ensure that copies of this standard are available on site for reference.

Nhaø thaàu caàn coù boä tieâu chuaån naøy taïi hieän tröôøng ñeå tham khaûo.

1.1.2 Record of Work

Baùo caùo coâng vieäc

The Contractor shall maintain and submit a weekly record in an approved format, such as electronic photos at different locations of the site but not les than 10 locations, which shall indicate major work carried out including temporary

Nhaø thaàu thöïc hieän vaø trình baùo caùo haøng tuaàn theo maãu ñònh saün, trong ñoù goàm hình chuïp caùc vò trí khaùc nhau nhöng khoâng döôùi 10 vò trí ôû coâng tröôøng. Hình theå hieän caùc vieäc chính ñang thi coâng goàm caùc haïng muïc thi coâng taïm (neáu coù), laép ñaët

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 1 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 2: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

works (if any), formwork erection, steel fixing, concrete work exposed upon, formwork removal, etc.

vaùn khuoân, saét theùp, ñoå betoâng, thaùo vaùn khuoân v.v

Description of material used by location including source and type of cement, source and sizes of aggregates, source and mix proportion of concrete, source and grade of steel bars, etc. Delivery and quantity of material to Site.

Meâu taû vaät tö söû duïng cho caùc vò trí goàm nguoàn goác vaø loïai ximaêng, nguoàn goác vaø kích côõ coát lieäu, nguoàn goác vaø tyû leä troän ximaêng, nguoàn goác vaø cöôøng ñoä coát theùp v.v. haøng ñeán vaø khoái löôïng toàn taïi coâng tröôøng.

Labor force records. Hoà sô nhaân coâng

1.2 APPROVED SUBCONTRACTORS THAÀU PHUÏ ÑÖÔÏC CHAÁP THUAÄN

The Contractor shall not sublet the work of this trade or any section of this trade without the approval of the Client.

Nhaø thaàu khoâng ñöôïc giao moät phaàn hay toaøn boä coâng taùc beâ toâng cho Thaàu phuï maø khoâng coù yù kieán chaáp thuaän cuûa Chuû ñaàu tö.

1.3 ORDER OF WORK TRÌNH TÖÏ COÂNG TAÙC

The order of carrying out the Concretor's work shall be agreed with the Client, and shall conform to that agreed.

Trình töï ñoå beâ toâng phaûi coù söï ñoàng yù cuûa Chuû ñaàu tö vaø phaûi tuaân thuû caùc qui ñònh.

1.4 DRAWINGS BAÛN VEÕ

All plain and reinforced concrete work specified hereafter shall be carried out in strict accordance with the Structural Engineering and Architectural Drawings.

Coâng taùc beâ toâng coù hay khoâng coù coát theùp sau phaûi tuaân thuû nghieâm ngaët caùc chi tieát ghi treân baûn veõ keát caáu, kieán truùc vaø caùc chi tieát sau naøy.

1.5 TESTS THÖÛ NGHIEÄM

1.5.1 Frequency of Tests Soá löôïng thöû nghieäm

The Contractor as a minimum shall undertake 1 set of concrete tests for pours less than 12 m3.

Nhaø thaàu phaûi thöïc hieän ít nhaát moät boä maãu thöû ñoái vôùi khoái ñoå döôùi 12m3.

For pours greater than 12 m3, 1 set of tests shall be undertaken for every 3 delivery trucks or 20 m3.

Ñoái vôùi khoái ñoå treân 12m3 phaûi thöïc hieän moät boä maãu thöû cho moãi ba xe troän (hay moãi 20m3 khoái ñoå).

The tests shall be undertaken by a certified laboratory approved by the Client.

Thöû nghieäm seõ do moät ñôn vò coù ñaêng kyù hôïp leä thöïc hieän, sau khi coù söï ñoàng yù cuûa Chuû ñaàu tö.

In addition to this, all delivery trucks supplying concrete for water tanks or other liquid containing structures shall have one set of test samples taken per delivery.

Ngoaøi ra, caùc xe troän beâ toâng cho haïng muïc beå chöùa nöôùc phaûi tieán haønh thöû nghieäm vôùi moät boä maãu thöû ôû moãi laàn giao beâ toâng.

Each test set shall consist of three cubes tested at 7, 14 and 28 days.

Moãi boä maãu thöû goàm ba maãu hình truï thöû nghieäm sau 7 ngaøy, 14 ngaøy vaø 28 ngaøy.

The test results when evaluated statistically shall show a 0.95 probability of the specified strength being equalled or exceeded.

Keát quaû thöû nghieäm phaûi cho thaáy laø 95% maãu thöû coù cöôøng ñoä töông ñöông hay vöôït cöôøng ñoä yeâu caàu.

1.5.2 Costs of Tests Chi phí thöû nghieäm

The costs of all materials, labour, transport, fees etc. incurred in testing shall be borne by the Contractor.

Chi phí veà vaät lieäu, nhaân coâng, vaän chuyeån, phuï phí lieân quan ñeán coâng taùc thöû maãu beâ toâng seõ do Nhaø thaàu chòu.

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 2 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 3: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

1.5.3 Standards of Tests Tieâu chuaån thöû nghieäm

Concrete compression tests shall be carried out as TCVN 356: 2005

Thöû neùn betoâng seõ thöïc hieän theo tieâu chuaån TCVN 356:2005

Concrete slump tests shall be carried out as TCVN 356: 2005

Thöû ñoä suït betoâng seõ thöïc hieän theo tieâu chuaån TCVN 356:2005

1.5.4 Steel reinforcement. Coát theùp

The Contractor shall, on request, demonstrate to the Client that all reinforcement complies with the Specification and produce manufacturer's certificates and certificates of origin.

Nhaø thaàu phaûi chöùng minh vôùi Chuû ñaàu tö (khi coù yeâu caàu) laø coát theùp söû duïng tuaân thuû caùc yeâu caàu cuûa ñaëc ñieåm kyõ thuaät vaø phaûi phaùt haønh chöùng chæ cuûa Nhaø saûn xuaát, chöùng chæ xuaát xöù.

1.5.5 Aggregates Coát lieäu

Aggregates to be tested every 1000m3 to ensure compliance with the requirements of BS 882, 1201. Test summary to be submitted to the clients appointed project manager for approval.

Thöû coát lieäu cöù moãi 1000m3 nhaèm ñaûm baûo raèng chuùng tuaân theo caùc yeâu caàu cuûa tieâu chuaån BS 882, 1201. Baùo caùo toùm löôïc seõ trình cho Chuû nhieäm döï aùn pheâ duyeät.

1.5.6 Admixtures Hoãn hôïp

No additives are to be added to the concrete without written permission from consulting engineer.

Khoâng theâm phuï gia vaøo betoâng tröø phi ñöôïc söï ñoàng yù baèng vaên baûn töø Kyõ sö tö vaán.

1.6 STANDARD SPECIFICATIONS ÑAËC ÑIEÅM KYÕ THUAÄT TIEÂU CHUAÅN

1.6.1 References Tham khaûo

This Specification shall be read in conjunction with BS 8110: 1997 Concrete construction which is deemed to form a part of this Specification.

Thuyeát minh kyõ thuaät naøy phaûi ñöôïc ñoïc phoái hôïp vôùi tieâu chuaån Anh 8100:1997 betoâng xaây döïng ñöôïc xem nhö laø taïo neân moät phaàn thuyeát minh kyõ thuaät naøy

All materials and workmanship shall comply with that Standard unless expressly noted otherwise.

Vaät lieäu vaø caùch thöùc thi coâng caàn tuaân thuû tieâu chuaån, tröø phi coù qui ñònh khaùc.

In the event of this Specification being at variance with any provision of this Standard, the requirements of this Specification take precedence over the provisions of the Standard.

Tröôøng hôïp coù khaùc bieät giöõa ñaëc ñieåm kyõ thuaät vaø tieâu chuaån neâu treân, öu tieân aùp duïng noäi dung yeâu caàu cuûa ñaëc ñieåm kyõ thuaät.

Reference to any Standard shall include any amendments thereto and any Standard in substitution therefor.

Vieäc tham khaûo caùc tieâu chuaån khaùc nhau seõ daãn ñeán chænh söûa vaø thay theá tieâu chuaån lieân quan.

1.7 STANDARDS TABLE BAÛNG KEÂ CAÙC TIEÂU CHUAÅN

1.7.1 General Toång quaùt

The following British standards shall also apply: Seõ aùp duïng caùc tieâu chuaån sau:

Standards Table Baûng tieâu chuaån

Standard Description Tieâu chuaån

BS 1881: 1983 - Method of testing concrete.

BS 1881: 1983 - Phöông phaùp thöû nghieäm beâ toâng.

BS 812 - Methods for sampling and testing aggregates.

BS 812 - Phöông phaùp laáy maãu vaø thöû nghieäm coát lieäu.

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 3 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 4: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

BS 6399 – Part 1 - Loading Code Dead and Live Loads.

BS 6399 – Part 1 - Quy phaïm veà taûi (taûi tænh vaø hoïat taûi)

BS 6399 – Part 3 TCVN 2737:1995

- Loading Code Wind Loads.

BS 6399 – Part 3 TCVN 2737:1995

- Quy phaïm veà taûi (taûi troïng gioù).

BS 4449: 1997 - Steel reinforcing bars for concrete.

BS 4449: 1997 - Theùp gia cöôøng beâ toâng.

BS 4483: 1985 - Steel reinforcing wire for concrete.

BS 4483: 1985 - Theùp buoäc cho beâ toâng.

BS 12: 1996 - Specification for Portland cement

BS 12: 1996 - Caùc yeâu caàu kyõ thuaät cho ximaêng portland

BS 5975: 1996 - Formwork BS 5975: 1996 - Vaùn khuoân

BS 8110: 1997 - Concrete Structure. BS 8110: 1997 - Keát caáu beâ toâng.

And any relevant recent updates of these standards.

Vaø caùc caäp nhaät môùi nhaát lieân quan ñeán caùc tieâu chuaån naøy.

1.8 INTERPRETATION GHI CHUÙ

1.8.1 Precedence AÙp duïng öu tieân

The requirements of the British Standards will apply in the first instance, except where the the Vietnamese standards are stipulated in the Vietnamese building authority requirements

Caùc yeâu caàu cuûa tieâu chuaån Anh seõ ñöôïc tuaân thuû tröôùc, tröø tröôøng hôïp caùc tieâu chuaån Vieät Nam ñöôïc cô quan thaåm quyeàn veà xaây döïng cuûa Vieät Nam quy ñònh.

2 MATERIALS VAÄT LIEÄU

2.1 CEMENT XI MAÊNG

2.1.1 Portland Cement Xi maêng Portland

Portland Cement (and rapid-hardening Portland Cement if used under conditions mentioned in Clause “2.1.2 – Special Cements” shall conform in every respect with the requirements of BS 12: 1996

Xi maêng Portland (vaø xi maêng Portland ñoâng cöùng nhanh) neáu ñöôïc söû duïng theo ñieàu kieän ghi ôû tieåu khoaûn “2.1.2 - Xi maêng ñaëc bieät” phaûi tuaân thuû nghieâm ngaët caùc yeâu caàu cuûa tieâu chuaån Anh BS 12: 1996

Cement shall be stored under cover and not in contact with a damp floor or ground and shall be used in the order of delivery.

Löu tröõ ximaêng trong nhaø traùnh aåm öôùt vaø khoâng ñaët treân saøn, vaø ñöôïc söû duïng theo thöù töï haøng giao ñeán.

No cement which is in any way affected by dampness shall be used and if for any reason cement is not used for considerable period, it shall be inspected and tested before use.

Tuyeät ñoái khoâng söû duïng ximaêng ñaõ bò aåm, phaûi kieåm tra vaø thöû nghieäm xi maêng quaù thôøi haïn tröôùc khi duøng.

The brand of cement used shall not be changed without the Clients approval.

Thöông hieäu xi maêng chæ ñöôïc thay ñoåi khi coù yeâu caàu cuûa Chuû ñaàu tö.

2.1.2 Special Cements Xi maêng ñaëc bieät

Quick setting or other special cements shall not be used without the permission in writing of the Client and only under such conditions as the Client may require and set down in writing.

Chæ ñöôïc söû duïng ximaêng ñoâng cöùng nhanh hay loaïi xi maêng ñaëc bieät khaùc khi coù vaên baûn chaáp thuaän hay yeâu caàu cuûa Chuû ñaàu tö.

No extra costs arising from the use of special cements will be accepted unless such special

Khoâng chaáp nhaän chi phí phaùt sinh do söû duïng xi maêng loaïi ñaëc bieät, tröø phi coù quy ñònh roõ reät veà söû

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 4 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 5: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

cement is specified. duïng naøy.

2.1.3 Tests Thöû nghieäm

See Clause “1.5 – Tests” relating to testing. Xem ñieàu khoaûn 1.5 thöû nghieäm

Notwithstanding the production of Certificates of vendor's tests, the Client may at his discretion, require that, after the cement has been brought on to the works, such further tests shall be made as he considers necessary to ensure that the cement complies with the specification.

Maëc duø ñaõ nhaän ñöôïc caùc chöùng chæ thöû nghieäm vaø phaân tích cuûa ñôn vò baùn, Chuû ñaàu tö vaãn coù theå yeâu caàu tieán haønh thöû nghieäm boå sung ñoái vôùi löôïng xi maêng ñöôïc giao ôû coâng tröôøng, ñeå xaùc ñònh xem caùc yeâu caàu cuûa ñaëc ñieåm kyõ thuaät coù ñöôïc tuaân thuû khoâng.

If the Client requires further tests to be made, the cement shall not be used without his permission.

Neáu Chuû ñaàu tö yeâu caàu thöïc hieän thöû nghieäm boå sung thì xi maêng naøy chæ ñöôïc söû duïng khi coù yù kieán cuûa oâng ta.

2.2 AGGREGATES COÁT LIEÄU

2.2.1 Fine Aggregates Coát lieäu mòn

Fine aggregates shall consist of natural sand or of sand prepared from stone, gravel or other material with the requirements of B.S 882, 1201: Part 2: 1973.

Bao goàm caùt töï nhieân vaø caùt töø ñaù, soûi hay vaät lieäu khaùc theo Tieâu chuaån Anh B.S 882, 1201: Phaàn 2: 1973.

Shall be clean, sharp, well washed and screened if necessary, before use.

Coát lieäu phaûi saïch, saéc caïnh, ñöôïc saøng qua vaø röûa saïch tröôùc khi duøng.

The use of granite fines in lieu of sand shall be subject to the approval of the Engineer who may require adjustment to the mix proportion as necessary.

Vieäc söû duïng granite mòn thay cho caùt seõ tuøy vaøo söï pheâ chuaån cuûa Kyõ sö hoaëc Kyõ sö seõ cho pheùp tyû leä troän khi caàn thieát.

2.2.2 Coarse Aggregates Coát lieäu thoâ

Coarse aggregate shall consist of gravel, crushed stone, or crushed gravel or other inert materials of similar characteristics or combination thereof, have hard, strong durable pieces, free from adherent coatings and shall comply with requirements of B.S 882, 1201: Part 2: 1973.

Bao goàm soûi, ñaù nghieàn, soûi nghieàn hay caùc vaät lieäu trô khaùc coù ñaëc tính töông ñöông hoaëc hoãn hôïp, coù maãu cöùng vaø dai beàn, khoâng coù lôùp baùm dinh tuaân theo Tieâu chuaån Anh B.S 882, 1201: Phaàn 2: 1973.

The nominal maximum size of coarse aggregate shall be 20 mm unless otherwise approved or specified by the Client.

Kích côõ danh ñònh toái ña cuûa coát lieäu thoâ laø 20 mm, tröø phi coù caùc quy ñònh khaùc cuûa Chuû ñaàu tö.

2.3 WATER NÖÔÁC

2.3.1 Supply Cung caáp

All water used in mixing with cement for concrete, mortar or grout, in cleaning out or wetting forms, in washing materials or in curing concrete shall be clean and fresh and where available, direct from the Local Authority mains.

Nöôùc söû duïng ñeå troän beâ toâng, vöõa, hoà daàu; laøm veä sinh, röûa vaät lieäu, baûo döôõng beâ toâng, caàn phaûi saïch, môùi vaø neáu coù theå, phaûi laáy töø nguoàn nöôùc thaønh phoá.

2.4 REINFORCING COÁT THEÙP

2.4.1 Steel bars for the reinforcement of concrete

Coát theùp cho beâ toâng

Steel bars for the reinforcement of concrete shall conform to the requirements of BS 4449: 1997 or

Coát theùp gia cöôøng beâ toâng phaûi tuaân thuû caùc yeâu caàu cuûa tieâu chuaån Anh BS 4449:1997 hoaëc tieâu chuaån

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 5 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 6: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

Japanese grade equivalent (JIS). töông ñöông cuûa Nhaät (JIS).

2.4.2 Hard Drawn Steel Wire Mesh Löôùi theùp keùo caêng

Hard Drawn Steel Wire Mesh (generally known as BRC or HRC Mesh) shall conform to the requirements of BS 4483: 1985

Löôùi theùp keùo caêng (thöôøng ñuôïc bieát döôùi teân löôùi theùp BRC hay HRC) phaûi tuaân thuû caùc yeâu caàu cuûa tieâu chuaån Anh BS 4483:1985.

2.5 FORMS VAÙN KHUOÂN

2.5.1 General Toång quaùt

Refer Clause “3.1 – Formwork and Falsework”. Xem ñieàu “3.1 - Vaùn Khuoân vaø Giaøn Giaùo”.

2.5.2 Tolerances Sai soá

The standard of the forms shall be such that finished concrete work shall be within the following maximum tolerances:

Tieâu chuaån veà vaùn khuoân phaûi sao cho coâng taùc ñoå beâ toâng coù sai soá nhö sau:

Tolerances table Baûng sai soá

Location Tolerances Vò trí Sai soá

Storey height: +3 mm -6 mm Chieàu cao taàng: +3 mm -6 mm

Openings in walls: Loã môû töôøng:

• Out of plumb +3 mm -3 mm • Khoâng thaúng +3 mm -3 mm

Dimensions: Kích côõ:

• height +3 mm -6 mm • Roäng +3 mm -6 mm

• breadth +3 mm -6 mm • Cao +3 mm -6 mm

Member thickness: +3 mm -3 mm Beà daøy caáu kieän: +3 mm -3 mm

2.5.3 3,000 straight edge test Thöû baèng thöôùc raø daøi 3 m

Notwithstanding the above, a 3,000 mm straight edge placed in any direction on the surface of the formwork shall not disclose deviation in excess of 2 mm.

Ngoaøi ra coøn thöû baèng thöôùc raø daøi 3m ñaët ôû moïi höôùng treân maët vaùn khuoân; ñoä leäch khoâng ñöôïc quaù 2 mm.

2.6 ORIGIN AND SUPPLY OF MATERIALS NGUOÀN CUNG CAÁP VAÄT LIEÄU

2.6.1 General Toång quaùt

It shall be the responsibility of the Contractor to obtain the maximum possible uniformity of colour in the concrete for external walls and thus the cement, sand and aggregate shall be from one origin and one supplier for the whole job.

Nhaø thaàu coù traùch nhieäm ñaït ñöôïc maøu beâ toâng ñoàng ñeàu ñoái vôùi töôøng ngoaøi. Do vaäy xi maêng, caùt, coát lieäu phaûi ñöôïc cung caáp töø moät nguoàn vaø töø moät nhaø cung caáp cho toaøn boä coâng trình.

The origin and supplier of the materials shall be approved by the Client.

Chuû ñaàu tö seõ quyeát ñònh nguoàn vaø nhaø cung caáp.

2.7 CONCRETE GRADES AND MIXES MAÙC BEÂ TOÂNG VAØ HOÃN HÔÏP

2.7.1 Cube Strength Ñoä beàn truï

The following 28 days standard cured crushing strength concretes are specified for this Contract:

Cöôøng ñoä chòu neùn vôõ cuûa beâ toâng sau 28ngaøy baûo döôõng laø.

• 40 MPa minimum throughout except as noted otherwise in this Specification or on the

• 40 Mpa (tröø phi coù quy ñònh khaùc neâu trong ñaëc ñieåm kyõ thuaät) hoaëc baûn veõ.

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 6 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 7: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

drawings.

• 40 MPa to Water and septic tanks • 40 Mpa ñoái caùc beå chöùa nöôùc vaø haàm phaân.

2.7.2 Certified Supplier Nhaø cung caáp ñöôïc chöùng nhaän

Except as expressly specified to the contrary elsewhere, concrete shall be special grade concrete obtained from a Plant certified by the Ready Mixed Concrete Association as capable of making Special Grade Concrete.

Ngoaïi tröø coù quy ñònh khaùc – beâ toâng phaûi laø loaïi: Beâ toâng coù cöôøng ñoä cao ñöôïc saûn xuaát töø nhaø maùy do Hieäp hoäi Beâ toâng ñuùc saün xaùc nhaän.

2.7.3 Client Approved Supplier Nhaø cung caáp do Chuû ñaàu tö chaáp thuaän

Concrete manufactured under conditions in every respect complying with the requirements of BS 8110: 1997 for Special Grade concrete, but obtained from another Plant approved by the Client.

Beâ toâng saûn xuaát theo caùc yeâu caàu cuûa tieâu chuaån BS 8110: 1997 ñoái vôùi beâ toâng coù cöôøng ñoä cao, nhöng ñöôïc mua taïi nhaø maùy khaùc caàn coù söï ñoàng yù cuûa Chuû ñaàu tö.

If the Contractor wishes to employ such a firm, application for the Client's approval for their employment shall be made in writing to the Client at least two weeks before Tenders close, to enable the Client to inspect the proposed plant and approve it, or otherwise.

Neáu Nhaø thaàu muoán söû duïng nguoàn beâ toâng naøy, hoï caàn thoâng baùo baèng vaên baûn ñeán Chuû ñaàu tö ít nhaát hai tuaàn tröôùc khi ñoùng thaàu ñeå Chuû ñaàu tö coù ñieàu kieän tham quan nhaø maùy vaø ra quyeát ñònh cuoái.

Such application shall be accompanied by a letter signed by the Registered Client in charge of concrete making for the firm in question, certifying that their equipment complies with BS 8110: 1997 for Special Grade concrete and setting out the mixes it is proposed to use on this Contract, and consistency of results obtained therefrom.

Vaên baûn naøy caàn keøm theo thö cuûa ñôn vò (coù ñaêng kyù hôïp leä vaø chòu traùch nhieäm saûn xuaát beâ toâng taïi nhaø maùy noùi treân) xaùc nhaän laø daây chuyeàn saûn xuaát cuûa hoï tuaân thuû caùc yeâu caàu cuûa tieâu chuaån BS 8110: 1997, thieát keá hoãn hôïp beâ toâng döï aùn vaø tuaân thuû caùc keát quaû ñaõ ñaït ñöôïc.

2.7.4 Surface Finish Hoaøn thieän beà maët

For concrete at all surfaces which will be visible on completion of the works, the absolute minimum cement content shall be 350 KG/m3 mixed concrete.

Ñoái vôùi beâ toâng aùp duïng treân beà maët thaáy ñöôïc khi keát thuùc haïng muïc coâng trình, löôïng xi maêng toái thieåu trong hoãn hôïp phaûi laø 350 Kg/cm3.

The Contractor shall allow for supplying greater cement content than this, should that be necessary to achieve the specified surface finish.

Nhaø thaàu phaûi döï kieán cung caáp moät löôïng xi maêng lôùn hôn khi coù yeâu caàu hoaøn thieän beà maët.

2.7.5 Screeds Vöõa caùn

Weak concrete screed 50 mm thick shall be placed under all foundations immediately the excavation has been approved by the Client, unless the Client approves or the Specification states that this is not to be done.

Vöõa caùn daøy 50 mm ñöôïc traûi döôùi ñaùy moùng ngay sau khi Chuû ñaàu tö chaáùp nhaän coâng taùc ñaøo ñaát. Tröø khi Chuû ñaàu tö hoaëc Ñaëc ñieåm quy ñònh khaùc ñi.

This may be site mixed concrete, and shall have a minimum crushing strength of 3 MPa at 28 days.

Vöõa caùn coù theå troän baèng t ay vaø cöôøng ñoä neùn toái thieåu sau 28 ngaøy phaûi laø 3 Mpa.

Mix proportions by loose volume shall be either 12 parts of approved graded all-in metal aggregate to 1 part or, 10 parts of clean graded all-in scoria to 1 part cement.

Tyû leä hoãn hôïp trong moät theå tích rôøi phaûi laø 12 phaàn coát lieäu ñaù phaân loaïi töï nhieân vaø moät phaàn xi maêng hoaëc 10 phaàn xæ loø saïch phaân loaïi töï nhieân vaø 1 phaàn xi maêng .

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 7 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 8: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

2.7.6 In-Situ Batching Traïm troän taïi choã

If the Contractor wishes to set up a concrete batching plant on site and manufacture concrete in site, he shall provide full details of equipment, mix proportions, cement source, method of achieving a consistent mix, control of water content etc.

Neáu muoán laäp moät traïm troän beâ toâng taïi hieän tröôøng, Nhaø thaàu phaûi cung caáp caùc thoâng tin ñaày ñuû veà thieát bò troän, tyû leä hoãn hôïp, nguoàn xi maêng , phöông phaùp thöïc hieän moät hoãn hôïp ñoàng nhaát, phöông phaùp kieåm tra löôïng nöôùc.

2.8 CONCRETE DELIVERY GIAO BEÂ TOÂNG

2.8.1 Dockets Phieáu giao nhaän

Delivery Dockets shall be supplied by the producer for each load.

Nhaø saûn xuaát phaûi caáp phieáu giao nhaän ñoái vôùi moãi ñôït giao.

Dockets shall contain as a minimum the following information:

Treân phieáu yeâu caàu ghi roõ:

• Class of concrete. • Loaïi beâ toâng.

• Date and time of mixing. • Ngaøy giôø troän hoãn hôïp.

• Actual weight of cement in mix. • Troïng löôïng xi maêng trong hoãn hôïp.

• Meterage delivered. • Khoái löôïng beâ toâng cuûa moãi xe.

• Identifying number. • Soá thöù töï.

• Slump. • Ñoä suït.

• Quantity delivered. • Khoái löôïng giao.

3 EXECUTION THI COÂNG

3.1 FORMWORK AND FALSEWORK VAÙN KHUOÂN VAØ GIAØN GIAÙO

3.1.1 General Toång quaùt

Particular attention must be paid to the pattern of joints for surfaces which will be visible on completion of the work.

Löu yù caùc maïch noái vaùn khuoân treân caùc beà maët vaøo luùc keát thuùc coâng taùc.

Boxing for all such surfaces must be approved by the Client before fabrication is commenced.

Coâng taùc vaùn khuoân taïi caùc nôi naøy caàn ñöôïc Chuû ñaàu tö chaáp thuaän tröôùc khi thöïc hieän.

3.1.2 Materials Vaät lieäu

Use plywood or insignus pine boxing for all formwork, unless expressly approved otherwise by the Client or specified otherwise elsewhere.

Söû duïng vaùn khuoân baèng vaùn eùp hay goã thoâng, tröø phi coù quy ñònh khaùc neâu trong ñaëc ñieåm kyõ thuaät hay coù yeâu caàu cuûa Chuû ñaàu tö.

Hidden surfaces: - Rough sawn or better grade.

Beà maët khuaát: - Vaùn khuoân baøo thoâ.

Surfaces visible on completion of the work:

- Use wrought formwork shall comprise timber or steel framing lined with 12mm thick smooth faced plywood (or equal as approved by the Consultant). All external angles shall have chamfers formed with 15x15mm wrought hard

Beà maët thaáy ñöôïc khi keát thuùc coâng taùc:

- Söû duïng vaùn khuoân ñöôïc cheá taïo keát hôïp vôùi khung goã hoaëc khung theùp loùt vaùn eùp trôn daøy 12mm (loïai töông ñöông do Kyõ sö duyeät). Taïo vaït meùp 15x15mm ôû caùc goùc ngoøai cuøng cuûa vaùn khuoân goã cöùng tröø phi baûn veõ ñònh roõ vaït meùp

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 8 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 9: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

wood angles formwork, unless larger chamfers are defined on the drawings.

lôùn hôn.

3.1.3 Boxing Ñoùng vaùn khuoân

All concrete work, including foundations, shall be boxed unless specified to the contrary elsewhere in the Specification or expressly approved by the Client.

Coâng taùc beâ toâng, keå caû phaàn moùng, caàn ñöôïc ñoùng baèng vaùn khuoân tröø phi Chuû ñaàu tö hay ñaëc ñieåm kyõ thuaät quy ñònh khaùc ñi.

3.1.4 Joints Moái noái

All joints in formwork between individual boards, between boards and fillets and between adjoining shutters must be mortar-tight and shall remain mortar-tight under the effect of the vibration necessary to give full specified compaction.

Caùc moái noái vaùn khuoân giöõa caùc taám oáp, gôø vaø vaùn khuoân lieàn keà phaûi ñöôïc treùt kín vôùi vöõa vaø duy trì vöõa treùt kín naøy döôùi taùc ñoäng rung ñeå ñaït ñoä ñaàm neùn quy ñònh.

Since grout leakage in formwork may produce unacceptable blemishes in fairface work particular care must be taken to prevent such an occurrence.

Traùnh hieän töôïng vöõa beâ toâng ñoùng treân beà maët caáu kieän thi coâng.

3.1.5 Rigidity Ñoä cöùng

Forms shall be designed so that the deflection of sheathing shall not exceed 1/300-th of the span between supports, and in any case shall not exceed 2 mm.

Vaùn khuoân ñöôïc thieát keá sao cho ñoä leäch cuûa vaùn khoâng vöôït quaù 1/300 nhòp giöõa caùc phaàn ñôõ hay vöôït quaù 2 mm trong moïi tröôøng hôïp.

They shall be of sufficient rigidity and strength to prevent distortion due to pressure from the concrete or other loads incidental to construction.

Vaùn khuoân caàn ñuû cöùng vaø chaéc, khoâng cong veânh döôùi taùc ñoäng cuûa beâ toâng vaø taûi.

Construction shall be such that these surfaces can be stripped without disturbing the boxing or supports to beam or slab soffits, which may require to be left in place for a longer period.

Coâng taùc thi coâng caàn thöïc hieän sao cho coù theå thaùo dôõ vaùn khuoân maët maø khoâng gaây toån haïi ñeán phaàn vaùn khuoân coøn laïi, phaàn gaêng ñôõ daàm vaø daï saøn (vì caùc phaàn naøy ñöôïc duy trì trong khoaûng thôøi gian nhaát ñònh).

3.1.6 Corners and edges Goùc vaø caïnh

25 x 25 mm fillets and chamfers shall be used on all corners, or 25 radius covers where shown on the drawings.

AÙp duïng gôø 25x25 mm vaø vaùt taïi caùc goùc, hay lôùp baûo veä coù baùn kính laø 25 mm taïi caùc vò trí neâu treân baûn veõ.

All external angles in exposed members shall be protected against injury after stripping.

Caùc goùc ngoaøi cuûa caáu kieän hôû phaûi ñöôïc baûo veä sau khi thaùo vaùn khuoân.

Give slight bevel to all projections to ensure easy removal without damage to the concrete.

Taïo ñoä vaùt moûng ñoái vôùi caùc phaàn nhoâ ra ñeå khi thaùo vaùn khuoân khoâng gaây toån haïi cho beà maët beâ toâng.

3.1.7 Wire Ties Theùp buoäc

Wire ties are prohibited in any member in which any face will be in contact with water, exposed to weathering, where discolouration may take place, or where finished concrete is exposed to view.

Khoâng ñöôïc duøng theùp buoäc ñoái vôùi caáu kieän coù beà maët tieáp xuùùc vôùi nöôùc, thôøi tieát (deã gaây ra hieän töôïng phai maøu) hoaëc caáu kieän coù beà maët beâ toâng hôû.

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 9 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 10: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

Where permitted by the Client wire ties shall be cut at least 50 mm below the surface of the concrete and the surface shall be properly pointed up with cement mortar.

Theùp buoäc phaûi ñöôïc caét toái thieåu 50 mm caùch beà maët beâ toâng (taïi vò trí coù söï chaáp thuaän cuûa Chuû ñaàu tö). Phaàn beà maët coøn laïi seõ ñöôïc ñaép vöõa.

3.1.8 Openings Loã môû

All openings, sleeves, fixings, etc., shall be positioned according to the Drawings.

Caùc loã môû, oáng loùt, chi tieát coá ñònh phaûi ñöôïc ñònh vò theo chi tieát neâu treân baûn veõ.

In particular, refer to requirements of other trades.

Ñaëc bieät caàn tham khaûo yeâu caàu cuûa caùc Nhaø thaàu khaùc.

All penetrations now shown on the Structural Drawings shall be approved by the Client before work starts in that area.

Caùc loã chôø ghi treân baûn veõ keát caáu caàn ñöôïc Chuû ñaàu tö chaáp thuaän tröôùc khi trieån khai coâng taùc.

3.1.9 Inspection Doors Cöûa (loã) kieåm tra

Doors or openings required in the formwork for any purpose (such as treating construction joints or cleaning) shall be equipped with fasteners suitable to the pressure to be withstood.

Caàn thöïc hieän loã môû (ñeå xöû lyù caùc moái noái hay laøm veä sinh) vôùi caùc moùc khoùa phuø hôïp vôùi aùp suaát chòu ñöïng.

Such openings shall be provided at suitable positions to facilitate cleaning to formwork before concrete is poured.

Loã môû caàn ñöôïc thöïc hieän taïi caùc vò trí thuaän lôïi cho coâng taùc veä sinh vaùn khuoân tröôùc khi ñoå beâ toâng.

3.1.10 Temporary Fittings Phuï kieän taïm

Bolts and other temporary metal fittings used in formwork erection shall be constructed so as to permit their easy removal to a depth of at least 50 mm from the face without injury to the concrete, and so that upon their removal the cavities left are of the smallest possible size. The cavities shall be filled to the Client's directions.

Bu loâng vaø caùc phuï kieän kim loaïi taïm thôøi khaùc aùp duïng trong coâng taùc döïng vaùn khuoân phaûi ñöôïc thi coâng sao cho chuùng ñöôïc thaùo moät caùch deã daøng ôû ñoä saâu 50 mm tính töø beà maët maø khoâng laøm hö hoûng beâ toâng, vaø sao cho sau khi thaùo vaùn khuoân, loã coù kích côõ nhoû nhaát coù theå vaø ñöôïc traùm baèng vöõa theo höôùng daãn cuûa Chuû ñaàu tö.

3.1.11 Coating of Forms Lôùp phuû vaùn khuoân

No oil-based parting medium may be used. Khoâng ñöôïc söû duïng vaät lieäu loûng coù goác daàu.

The inside surface of all forms may be given a coat of approved material which shall not adhere to or stain the concrete or be incompatible with any final painting or treatment or alternatively shall be saturated with water immediately before placing concrete.

Maët trong vaùn khuoân caàn phuû moät lôùp vaät lieäu ñöôïc duyeät ñeå vaùn khuoân khoâng dính hay khoâng ñeå laïi daáu veát treân beà maët beâ toâng, hay phuû loaïi vaät lieäu khoâng thích hôïp vôùi lôùp sôn, lôùp xöû lyù cuoái cuøng hoaëc phuû loaïi vaät lieäu baõo hoøa nöôùc ngay tröôùc khi thöïc hieän ñoå beâ toâng.

Except for water such coatings shall be applied prior to placing the reinforcing steel so as to avoid fouling of the surface of steel.

Ngoaïi tröø nöôùc, vaät lieäu phuû neâu treân phaûi ñöôïc thöïc hieän tröôùc khi laép ñaët coát theùp ñeå traùnh laøm dô beà maët theùp.

The same type of coating shall be used throughout the job unless otherwise approved.

Chæ söû duïng xuyeân suoát moät loaïi vaät lieäu ñaõ ñöôïc duyeät, tröø khi coù quy ñònh khaùc.

3.1.12 Bulging Vaùn khuoân bò phuø

If, during a pour, undue settlement, bulging or other defects become apparent in the formwork, the Contractor shall cease pouring and shall take all necessary steps to remedy such defects.

Trong quaù trình ñoå beâ toâng, neáu coù hieän töôïng vaùn khuoân bò luùn, phuø, Nhaø thaàu caàn ngöng thi coâng ñeå khaéc phuïc ngay söï coá.

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 10 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 11: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

Where such defect occurs in fairface surfaces, the Client must be immediately notified to enable a decision to be made on whether to continue the pouring when the defect has been remedied, provided that where such remedial work can be completed before the last concrete placed has hardened to the extent that is ceases to become plastic under vibration and where there is no danger of the quality of surface finish being affected the Contractor may elect to continue to pour.

Chuû ñaàu tö phaûi ñöôïc thoâng baùo ñeå xem xeùt vieäc cho pheùp thi coâng tieáp hay khoâng, sau khi söï coá ñaõ ñöôïc khaéc phuïc. Neáu coâng taùc khaéc phuïc hoaøn taát tröôùc khi lôùp beâ toâng ñoå tröôùc ñoâng cöùng (khoâng coøn ñoä deûo khi tieáp xuùc ñaàm rung vaø ôû choã naøo maø chaát löôïng beà maët hoaøn thieän khoâng bò aûnh höôûng), Nhaø thaàu ñöôïc pheùp thi coâng tieáp.

Refer to Clauses “3.4.4 – Compaction”, “3.4.5 - Do Not Disturb Fresh Concrete” and “3.8.4 - Surface Blemishes”.

Xem ñieàu khoaûn “3.4.4 - Coâng taùc ñaàm neùn”, “3.4.5 -Khoâng ñöôïc xaùo troän beâ toâng vöøa môùi ñoå “ vaø “3.8.4 -Caùc khuyeát taät treân beà maët”.

3.1.13 Forms Removal Thaùo vaùn khuoân

This Clause is to be read in conjunction with Clause “3.2, 3.6 – Curing”.

Ñieàu khoaûn naøy phaûi ñöôïc ñoïc cuøng vôùi ñieàu khoaûn “3.2, 3.6 – Baûo Döôõng Beâ Toâng”.

3.2 CURING BAÛO DÖÔÕNG BEÂ TOÂNG

The Contractor's attention is particularly drawn to the following point.

Nhaø thaàu caàn löu yù ñeán phaàn boå sung sau.

The Contractor's attention is drawn to the necessity of proper curing for all concrete surfaces left exposed by the removal of formwork before the expiry of the curing period.

Nhaø thaàu caàn quan taâm ñeán coâng taùc baûo döôõng ñoái vôùi beà maët beâ toâng hôû do vieäc thaùo vaùn khuoân tröôùc khi chaám döùt thôøi gian baûo döôõng.

3.2.1 Cleaning Coâng taùc veä sinh

Immediately before any concreting is commenced, formwork shall be carefully examined to see that all dirt, shavings, sawdust and other refuse has been removed.

Tröôùc khi ñoå beâ toâng phaûi laøm veä sinh vaùn khuoân: queùt buïi, daâm baøo, maït cöa, raùc reán.

See also sub-clause “3.1.12 – Bulging”. Xem tieåu khoaûn “3.1.12 - Vaùn khuoân bò phuø”.

3.2.2 Re-used Formwork Vaùn khuoân söû duïng laïi

Sound, unwarped forms may be re-used provided they satisfy all the specified requirements.

Vaùn khuoân cöùng khoâng cong veânh coù theå söû duïng laïi, mieãn laø phaûi tuaân thuû ñaày ñuû caùc yeâu caàu kyõ thuaät.

They must be thoroughly cleaned each time before re-use, and may need to be resized, retightened or repaired all as directed by the Client.

Vaùn khuoân tröôùc khi ñem ra söû duïng laïi phaûi ñöïôc veä sinh, ñònh côõ laïi hoaëc söûa chöõa theo höôùng daãn cuûa Chuû ñaàu tö.

3.3 FABRICATION AND PLACING OF REINFORCEMENT

GIA COÂNG VAØ LAÉP ÑAËT COÁT THEÙP

3.3.1 References Tham khaûo

Refer to “S2 - Reinforcing Steel” of this Specification.

Xem “S2 - Theùp Gia Cöôøng”, ñaëc ñieåm kyõ thuaät.

3.3.2 Inspection before Concreting Kieåm tra tröôùc khi ñoå beâ toâng

No concrete shall be placed until the Client has had the opportunity to satisfy himself that all the requirements of this Section have been

Coâng taùc beâ toâng chæ thöïc hieän sau khi Chuû ñaàu tö kieåm tra thaáy caùc yeâu caàu veà phaàn naøy ñöôïc tuaân thuû ñaày ñuû.

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 11 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 12: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

properly complied with.

To this end the Contractor shall give the Client two day's notice when he will pour concrete.

Nhaø thaàu seõ göûi thoâng baùo ñeán Chuû ñaàu tö hai ngaøy tröôùc ngaøy döï kieán ñoå beâ toâng.

Such notice and inspection in no way relieves the Contractor of any obligation under the terms of the Contract.

Thoâng baùo vaø kieåm tra coâng taùc vaùn khuoân cuûa Chuû ñaàu tö khoâng mieãn giaûm traùch nhieäm cuûa Nhaø thaàu theo caùc ñieàu khoaûn hôïp ñoàng.

Concrete poured in violation of the foregoing is liable to condemnation and removal at no extra cost to the Contract.

Beâ toâng ñoå maø khoâng tuaân thuû hai yeâu caàu treân phaûi bò dôõ boû vaø khoâng ñöôïc thanh toaùn theo hôïp ñoàng.

3.4 CONCRETE CONVEYING AND PLACING CHUYEÂN CHÔÛ VAØ ÑOÅ BEÂ TOÂNG

3.4.1 Conveying Chuyeân chôû

The method of conveying the concrete from the mixer (agitator) to the place of deposit shall be such as to ensure that the concrete will be placed in its final position within 20 minutes of cessation of its mixing (agitation).

Vieäc chôû beâ toâng töø nhaø maùy troän (maùy troän) ñeán nôi ñoå phaûi ñaûm baûo laø beâ toâng ñöôïc ñaët ôû vò trí cuoái cuøng trong voøng 20 phuùt sau khi ngöng troän (troän) ñeå traùnh hieän töôïng phaân taàng.

3.4.2 Placing Ñoå beâ toâng

Concrete must be placed as close to its final position as possible and must not be dropped a distance of more than 1500 mm.

Beâ toâng phaûi ñöôïc ñoå gaàn vò trí caàn ñoå, khoâng ñöôïc roùt ôû ñoä cao quaù 1500 mm.

Long chutes may be used with the Clients approval and under unavoidable circumstances.

Trong ñieàu kieän baát khaû khaùng vaø coù söï ñoàng yù cuûa Chuû ñaàu tö, coù theå söû duïng maùng chuyeàn.

Between approved construction joints, the concrete shall be deposited in continuous horizontal layers of such depth and at such rate that no concrete will be placed against concrete which has hardened sufficiently to cause the formation of seams or planes of weakness by reason of failure of the respective deposits to thoroughly unite.

Beâ toâng phaûi ñöôïc ñoå ôû khoaûng giöõa caùc moái noái thi coâng ñaõ ñöôïc duyeät, thaønh töøng lôùp lieân tuïc, vôùi ñoä daøy vaø taàn suaát sao cho khoâng coù lôùp beâ toâng môùi naøo ñoå choàng leân lôùp beâ toâng vöøa ñoâng cöùng, daãn ñeán moái noái hay maët phaúng xung yeáu.

The vertical depth of each deposit shall not exceed 600 mm provided that each deposit shall be capable of being thoroughly compacted by the method of compaction approved by the Client.

Beà daøy moãi lôùp ñoå khoâng ñöôïc vöôït quaù 600 mm neáu ñöôïc ñaàm kyõ vôùi phöông phaùp ñaàm ñaõ ñöôïc Chuû ñaàu tö chaáp thuaän.

The contractor is to submit concrete pouring schedule to the clients appointed project manager for approval before works are commenced.

Nhaø thaàu trình keá hoïach ñoå betoâng cho Chuû nhieäm döï aùn pheâ duyeät tröôùc khi khôûi coâng.

3.4.3 Re-tempering Troän laïi beâ toâng

Re-tempering concrete which has partially hardened (i.e. remixing with or without additional cement, aggregate, or water) is forbidden.

Nghieâm caám vieäc troän laïi moät phaàn beâ toâng ñaõ ñoâng cöùng (coù hay khoâng coù xi maêng, coát lieäu, nöôùc boå sung).

3.4.4 Compaction Coâng taùc ñaàm neùn

During and immediately after placing, concrete shall be thoroughly compacted and worked around reinforcement and embedded fixtures, and into the corners of the forms, by means of

Beâ toâng caàn ñöôïc ñaàm kyõ xung quanh coát theùp, caáu kieän choân, taïi caùc goùc vaùn khuoân vôùi ñaàm duøi (ñaõ ñöôïc chaáp thuaän) trong moät thôøi gian ngaén nhaát.

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 12 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 13: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

approved mechanical immersion type vibrators used in a manner such that every part of the concrete is thoroughly compacted in the shortest practicable time.

Vibration shall not be applied directly or through reinforcement to concrete which has hardened to an extent that it ceases to become plastic under vibration, unless such concrete is at least 3 days old.

Coâng taùc ñaàm rung khoâng ñöôïc taùc ñoäng tröïc tieáp vaøo beâ toâng (hay xuyeân qua coát theùp) ñaõ ñoâng cöùng ñeán möùc khoâng coøn ñoä deûo döôùi taùc ñoäng cuûa ñaàm rung, tröø khi beâ toâng ñoù ñaõ ñöôïc ñoå 3 ngaøy.

The Contractor shall have at least two immersion type vibrators in full working order at each part of the site where concrete is being poured.

Nhaø thaàu phaûi coù ít nhaát hai thieát bò ñaàm duøi hoaït ñoäng toát trong quaù trình ñoå beâ toâng.

If the Contractor is of the opinion that the use of immersion type vibrators is not practicable, he shall seek the approval of the Client, before such work begins, for the method of compaction to be used.

Neáu xeùt thaáy phöông aùn ñaàm duøi khoâng theå söû duïng, Nhaø thaàu phaûi ñöa phöông aùn khaùc cho Chuû ñaàu tö duyeät tröôùc khi aùp duïng.

3.4.5 Do Not Disturb Fresh Concrete Khoâng ñöôïc xaùo troän beâ toâng vöøa môùi ñoå

Care shall be taken that no shock or vibration reaches concrete after setting until it is at least 3 days old, and that any starters projecting from green concrete are not shaken or disturbed.

Khoâng ñöôïc gaây va ñaäp hay ñaàm rung vaøo khoái beâ toâng vöøa ñoâng cöùng (tröø khi beâ toâng ñaõ ñöôïc ñoå ít nhaát 3 ngaøy) keå caû vieäc khoâng ñöôïc lay ñoäng caùc saét chôø gaén vaøo khoái beâ toâng vöøa ñoå.

3.4.6 Placing on DPC, Waterproofing Ñoå beâ toâng treân DPC, lôùp choáng thaám

Where concrete is placed on damp courses etc, extreme care shall be taken in order to avoid any injury to these materials.

Löu yù khoâng laøm raùch lôùp choáng thaám khi ñoå beâ toâng leân treân.

3.4.7 Slabs Saøn

Slabs (including beams forming an integral part of the slab) shall be poured in one operation over the full depth.

Saøn (bao goàm daàm) phaûi ñöôïc ñoå beâ toâng laøm moät laàn vôùi ñoä saâu ñaày ñuû.

The Contractor shall take care to provide a well balanced concrete for this purpose, so as to avoid excess water and mortar appearing on the surface after compacting.

Nhaø thaàu caàn cung caáp ñaày ñuû löôïng beâ toâng thöïc hieän cho moät laàn ñoå, ñeå traùnh löôïng nöôùc vaø vöõa dö xuaát hieän treân beà maët sau khi ñaàm.

The Contractor shall have competent workmen for finishing the floor surfaces to the standard specified.

Nhaø thaàu caàn boá trí thôï laønh ngheà thöïc hieän coâng taùc hoaøn thieän saøn theo quy ñònh cuûa tieâu chuaån.

The use of dryers shall not be permitted without the approval of the Client.

Khoâng ñöôïc söû duïng thieát bò saáy tröø khi coù yù kieán cuûa Chuû ñaàu tö.

3.4.8 Columns Coät

At least two hours shall elapse after depositing concrete in columns before concreting may start in any member supported thereon.

Sau khi ñoå beâ toâng coät hai giôø môùi ñöôïc tieán haønh thi coâng tieáp caùc caáu kieän ñôõ coät.

3.4.9 Inspection Before Concreting Kieåm tra tröôùc khi ñoå beâ toâng

No concrete shall be placed until the Client is satisfied that all provisions of the Specification with respect to foundations, formwork,

Coâng taùc beâ toâng chæ ñöôïc thöïc hieän khi Chuû ñaàu tö xeùt thaáy, qua kieåm tra, caùc qui ñònh cuûa ñaëc ñieåm kyõ thuaät lieân quan ñeán moùng, vaùn khuoân, coát theùp, moái

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 13 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 14: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

reinforcing, construction joints, etc., have been complied with entirely and to his satisfaction.

noái thi coâng ñöôïc tuaân thuû ñaày ñuû.

To this end the Contractor shall give the Client at least 48 hours notice of his intention to pour concrete.

Nhaø thaàu phaûi göûi thoâng baùo tröôùc 48 giôø.

3.4.10 Concreting in Rain Ñoå beâ toâng khi gaëp möa

No concreting shall proceed during times when the rate of rainfall exceeds 1.5 mm per hour or when, in the opinion of the Client, the rainfall is likely to be injurious to the concrete either directly or through run off from directly adjoining surfaces.

Khoâng ñöôïc tieán haønh khi löôïng möa vöôït quaù 1,5 mmm/giôø vaø khi Chuû ñaàu tö xeùt thaáy möa aûnh höôûng ñeán chaát löôïng beâ toâng (moät caùch tröïc tieáp hay giaùn tieáp töø caùc beà maët keá caän).

Unset concrete must be effectively protected against injury from rain.

Beâ toâng chöa ñoâng cöùng caàn ñöôïc che chaén möa baèng caùc vaät lieäu che.

The Contractor shall ensure that he has on site the requisite materials for such protection.

Nhaø thaàu phaûi ñaûm baûo coù ñaày ñuû vaät lieäu che chaén beâ toâng taïi hieän tröôøng.

3.4.11 Clean Formwork Vaùn khuoân saïch

Immediately before any concreting is commenced, all formwork shall be carefully examined to see that all dirt, shavings, sawdust and other deleterious matter is removed.

Vaùn khuoân caàn ñöôïc veä sinh caån thaän tröôùc khi ñoå beâ toâng: khoâng buïi, vuïn goã, raùc reán.

3.4.12 In Wet Situations Trong caùc ñieàu kieän aåm öôùt

Where reinforced concrete is to be in contact with water or saturated ground, the mix shall be adjusted in respect of water cement ratio and minimum cement content on the basis of BS 8110: 1997

Taïi caùc vò trí maø beâ toâng coát theùp tieáp xuùc vôùi nöôùc hoaëc ñaát ngaäm nöôùc, hoãn hôïp beâ toâng caàn ñieàu chænh tyû leä xi maêng – nöôùc vaø löôïng xi maêng toái thieåu treân cô sôû tieâu chuaån BS 8110: 1997

Where these adjustments conflict with the conditions of BS 8110: 1997, the lower value of water cement ratio and the larger cement content shall apply.

Neáu caùc ñieàu chænh naøy coù maâu thuaãn vôùi caùc ñieàu kieän cuûa tieâu chuaån Anh BS 8110:1997, thì aùp duïng tyû leä xi maêng - nöôùc thaáp vaø löôïng xi maêng cao.

The Client shall advise on the job if extra cement is necessary.

Chuû ñaàu tö seõ cho yù kieán veà yeâu caàu löôïng xi maêng boå sung.

3.4.13 Under Water Beâ toâng döôùi nöôùc

Where it is desired to pour concrete under water, special notice in writing shall be given to the Client who may impose such conditions and control as he thinks fit.

Phaûi thoâng baùo baèng vaên baûn cho Chuû ñaàu tö khi coù yeâu caàu ñoå beâ toâng döôùi nöôùc.

The requirements generally will be as in BS 8110: 1997, but the Client reserves the right to alter the details of these requirements.

Thoâng thöôøng aùp duïng noäi dung theo tieâu chuaån Anh BS 8110:1997, nhöng Chuû ñaàu tö coù quyeàn thay ñoåi caùc quy ñònh naøy.

3.5 CONSTRUCTION JOINTS MOÁI NOÁI THI COÂNG

3.5.1 General Toång quaùt

In general, construction joints are detailed in the Drawings and shall not be varied without the Client's express approval.

Moái noái thi coâng ñöôïc ghi chuù chi tieát treân baûn veõ vaø chæ ñöôïc thay ñoåi khi coù yù kieán cuûa Chuû ñaàu tö.

Vertical joints shall be formed with approved Moái noái ñöùng phaûi ñöôïc taïo vôùi taám ngaên ñaõ ñöôïc

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 14 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 15: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

bulkheads. duyeät.

Reinforcement shall run continuously through construction joints unless shown otherwise in the drawings.

Coát theùp caàn ñöôïc ñaët lieân tuïc qua caùc moái noái thi coâng, tröø khi coù quy ñònh khaùc treân baûn veõ.

At least three clear days shall elapse between adjacent pours of concrete.

Ít nhaát ba ngaøy sau môùi ñöôïc ñoå beâ toâng tieáp.

3.5.2 Positions of Joints Vò trí caùc moái noái

The following joint position is the maximum permitted if not shown on the Drawings.

Vò trí caùc moái noái sau ñaây ñöôïc cho pheùp thöïc hieän neáu chöa coù chi tieát ghi treân baûn veõ.

• Slabs • Saøn:

These shall be as shown on the drawings, however, the Precast Flooring Contractor shall submit to the Client within 4 weeks of Tender acceptance, his proposed joint layout, should it vary from that shown.

Thi coâng theo ghi chuù treân baûn veõ, tuy nhieân Nhaø thaàu thi coâng saøn ñuùc saün phaûi trình Chuû ñaàu tö duyeät (boán tuaàn sau khi ñöôïc giao thaàu) sô ñoà moái noái ñeà xuaát neáu coù khaùc bieät so vôùi chi tieát ghi treân baûn veõ.

• Columns and Walls • Coät - töôøng

May be poured in lifts exceeding 1500 mm provided that the Contractor can demonstrate to the Client prior to construction commencement his ability to do so properly and consistently.

Coù theå ñoå beâ toâng töøng ñoaïn cao 1,5 m mieãn laø Nhaø thaàu chöùng minh ñöôïc khaû naêng thöïc hieän toát ñeïp coâng taùc (tröôùc khi trieån khai thi coâng).

• Beams • Daàm

Unless detailed otherwise on the drawings, or approved by the Client, lengths of pours shall not exceed 9 metres for beams.

Tröø khi coù quy ñònh khaùc neâu treân baûn veõ hay coù yeâu caàu khaùc cuûa Chuû ñaàu tö, chieàu daøi khoái ñoå khoâng ñöôïc vöôït quaù 9 m.

Exterior construction joints in external concrete beams, walls and parapets and where indicated or directed by the Client, shall be sealed with an approved 10 x 15 grey polysulphide sealant applied under pressure against an approved continuous polythene tube back up.

Moái noái thi coâng cuûa daàm beâ toâng beân ngoaøi, töôøng, töôøng chaén vaø taïi vò trí do Chuû ñaàu tö chæ ñònh phaûi ñöôïc laøm kín baèng vaät lieäu traùm polysulphide 10x15 baèng phöông phaùp neùn, phuû treân caùc oáng polythene.

Particular care must be taken to strictly follow the manufacturer's instructions for preparation of surfaces and mixing and application of the material.

Caàn tuaân thuû caùc quy ñònh cuûa Nhaø saûn xuaát khi chuaån bò beà maët, troän vaø phuû vaät lieäu traùm.

Refer to ACT drawings for typical details of joints.

Xem caùc baûn veõ cuûa ACT ñeå bieát chi tieát ñieån hình cuûa caùc moái noái.

3.5.3 Preparation of Joints Chuaån bò caùc moái noái

Joints shall be prepared by removing all laitance from the surface against which new concrete is to be poured, so that clean metal is exposed.

Baèng caùch laøm saïch vöõa dö treân beà maët beâ toâng cuõ sao cho coát lieäu ñaù loøi ra.

Chip away from edges so that these are not damaged.

Traû vöõa dö ôû caïnh

In the event of edges being damaged, the Client reserves the right to nominate the method of repair the Contractor shall adopt.

Neáu caïnh bò meû, Chuû ñaàu tö seõ ñeà ra bieän phaùp khaéc phuïc.

Immediately before the new concrete is poured, Tröôùc khi ñoå beâ toâng ñôït sau, caùc beà maët phaûi ñöôïc

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 15 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 16: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

the surface against which it is to be poured shall be thoroughly wetted, after which excess water shall be removed.

töôùi nöôùc ñaày ñuû, khoâng ñeå nöôùc ñoïng treân beà maët caàn ñoå beâ toâng.

3.6 CURING BAÛO DÖÔÕNG BEÂ TOÂNG

3.6.1 General Toång quaùt

The following is in addition to BS 8110: 1997 Quy ñònh sau ñaây boå sung cho tieâu chuaån Anh BS 8110:1997.

All concrete shall be cured for at least 14 days. Beâ toâng caàn ñöôïc baûo döôõng ít nhaát 14 ngaøy.

Since the durability, strength, and water-tightness of the structure will depend on proper curing, the Contractor must pay careful attention to this Clause, whose requirements are the acceptable minimum.

Nhaø thaàu caàn quan taâm ñeán ñieàu khoaûn naøy (coù noäi dung toái thieåu chaáp nhaän ñöôïc) do coâng taùc baûo döôõng beâ toâng coù aûnh höôûng lôùn ñeán ñoä beàn, cöôøng ñoä, ñoä kín nöôùc cuûa keát caáu.

It is recommended to extend the curing period wherever practicable.

Neáu coù ñieàu kieän neân keùo daøi thôøi gian baûo döôõng.

Failure to comply with this Clause may lead to concrete being condemned by the Client, in which case it shall be taken out and replaced and correctly cured at the expense of the Contractor.

Neáu coâng taùc baûo döôõng khoâng ñöôïc quan taâm ñaày ñuû, Chuû ñaàu tö coù theå ra leänh ñaäp boû, thi coâng laïi, baûo döôõng laïi theo ñuùng qui caùch. Chi phí phaùt sinh seõ do Nhaø thaàu chòu.

3.6.2 First 7 Days After Pouring 7 ngaøy ñaàu sau khi ñoå beâ toâng

All concrete and its enclosing forms, and all surfaces at joints shall be kept continuously wet by approved means and shall be thoroughly protected from frost, from direct rays of the sun, and from drying winds.

Beâ toâng, vaùn khuoân, beà maët taïi caùc moái noái caàn ñöôïc giöõ aåm lieân tuïc vôùi vaät lieäu ñöôïc duyeät; ñöôïc baûo veä choáng söông, naéng, gioù khoâ.

To this end, as soon as concrete has set sufficiently, covers of continuously wetted approved materials shall be placed as required, or a system of fine water sprays shall be set up and operated continuously against the work or another suitable method adopted.

Vì vaäy khi beâ toâng vöøa ñaït ñoä cöùng, duøng caùc vaät lieäu baûo veä ñaõ thaám nöôùc ñeå boïc beâ toâng hay duøng heä thoáng phun nöôùc.

The method adopted for any part of the works shall be approved by the Client in advance.

Phöông phaùp baûo döôõng caàn coù yù kieán tröôùc cuûa Chuû ñaàu tö:

"Ritecure" of similar membrane curing shall only be used with the Client's express approval and shall not entitle the Contractor to any extra payment.

Söû duïng maøng “Ritecure” caàn coù söï ñoàng yù cuûa Chuû ñaàu tö vaø chi phí lieân quan seõ khoâng ñöôïc thanh toaùn.

The Contractor shall be responsible for the maintenance of such a membrane in good condition.

Maøng caàn ñöôïc baûo veä toát.

3.6.3 8-14 Days After Pouring 8-14 ngaøy sau khi ñoå beâ toâng

All concrete surfaces shall be protected from direct rays of the sun and from exposure to severe drying winds.

Beà maët beâ toâng caàn ñöôïc baûo veä choáng naéng tröïc tieáp vaø gioù khoâ.

The surface shall be kept damp by occasional hosing, the frequency of this depending on the prevailing weather conditions.

Beà maët beâ toâng caàn ñöôïc giöõ aåm baèng nöôùc voøi meàm.

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 16 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 17: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

At no time during this period shall any surface be allowed to completely dry out.

Khoâng ñöôïc ñeå beà maët bò khoâ raùo. Ñoä aåm ñöôïc ñieàu chænh theo ñieàu kieän thôøi tieát.

3.6.4 Slabs Saøn

Polythene or similar, laid onto the wetted surface as soon as the latter shall have hardened sufficiently, and maintained for at least 14 days, is an acceptable method of curing slabs.

Coù theå duøng vaät lieäu “polythene” hay vaät lieäu töông ñöông ñaët leân beà maët beâ toâng vöøa ñaït ñoä cöùng vaø duy trì vaät lieäu naøy trong voøng 14 ngaøy.

3.6.5 Particular Requirements Yeâu caàu ñaëc bieät

The use of "Ritecure" or similar is forbidden on any surface due to receive any surface treatment.

Nghieâm caám söû duïng maøng “Ritecure” hay vaät lieäu töông ñöông ñoái vôùi beà maët caàn xöû lyù.

The Contractor's attention is drawn to the Schedule of Finishes which shows the extent of surface treatments specified.

Nhaø thaàu caàn quan taâm ñeán danh mucï hoaøn thieän trong ñoù coù quy ñònh phaïm vi xöû lyù beà maët.

3.7 TOLERANCES DUNG SAI

3.7.1 General Toång quaùt

The following tolerances shall apply to the hardened concrete when still supported by the forms.

Dung sai sau ñaây ñöôïc aùp duïng cho beâ toâng ñaõ ñoâng cöùng nhöng vaãn chöa thaùo vaùn khuoân ñôõ.

Closer tolerances shall be maintained where called for elsewhere in the Specification.

Caùc dung sai nghieâm ngaët hôn phaûi ñöôïc tuaân thuû theo caùc yeâu caàu cuûa ñaëc ñieåm kyõ thuaät.

Any work exceeding a Specification tolerance shall be cut out and replaced.

Caáu kieän naøo vöôït quaù dung sai quy ñònh seõ bò ñaäp boû.

These tolerances shall have precedence over those in BS 8110: 1997, if at variance with those shown in that table.

Öu tieân aùp duïng dung sai naøy so vôùi dung sai neâu trong tieâu chuaån Anh BS 8110:1997, neáu xaûy ra khaùc bieät.

3.7.2 Cross Sectional Dimensions of Slabs, Walls, Columns, Beams etc.

Kích côõ maët caét ngang saøn, töôøng, coät, daàm

• For Cross Sectional Dimensions of Slabs, Walls, Columns, Beams etc. the following applies:

• AÙp duïng noäi dung sau ñaây ñoái vôùi caùc kích côõ maët caét ngang saøn, töôøng, coät, daàm.

Tolerance Table Baûng dung sai

Under Over Döôùi Treân

Dimensions up to 300 mm:

3 mm 9 mm Kích côõ treân 300: 3 mm 9 mm

Dimensions from 300 mm to 600 mm:

6 mm 12 mm Kích côõ töø 300 ñeán 600: 6 mm 12 mm

Dimensions over 600 mm:

6 mm 15 mm Kích côõ treân 600: 6 mm 12 mm

3.7.3 Variations from Plumb Sai soá veà ñöôøng thaúng ñöùng

• For lines and surfaces of columns, piers, walls and in arrises the following applies:

• Ñoái vôùi ñöôøng tuyeán vaø beà maët coät, truï coät, töôøng, caïnh gôø aùp duïng caùc noäi dung sau ñaây:

Tolerance Table Baûng dung sai

In 3,000 mm: 3 mm Trong khoaûng 3 m: 3mm

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 17 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 18: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

In any storey or 6,000 mm maximum:

9 mm Trong khoaûng 6 m (taàng laàu): 9 mm

In 12,000 mm or more: 18 mm Trong khoaûng 12 m hoaëc hôn: 18 mm

• For exposed corner columns, control-joint grooves and other conspicuous lines the following applies:

• Ñoái vôùi coät coù goùc hôû, raõnh xoi coù moái noái kieåm tra vaø ñoái vôùi caùc tuyeán khaùc:

Tolerance Table Baûng dung sai

In any bay or 6000 maximum 6 mm Trong khoaûng 6m toái ña (moãi gian): 6mm

In 12000 or more 12 mm Trong khoaûng 12 m hoaëc hôn: 12 mm

3.7.4 Variation from Level or from Grades Sai soá veà cao ñoä hoaëc cöôøng ñoä

Slabs shall be finished so that a 3,000 straight-edge shall show no out-of-plane exceeding 3 mm.

Saøn hoaøn thieän khoâng ñöôïc coù ñoä leäch quaù 3 mm qua kieåm tra baèng thöôùc raø daøi 3 m.

• For ceilings, beam soffits and in arrises the following applies:

• Traàn, daï daàm vaø caïnh gôø:

Tolerance Table Baûng dung sai

In 3,000 mm: 6 mm Trong khoaûng 3 m: 6 mm

In any bay or 6,000 mm maximum:

9 mm Trong khoaûng 6 m toái ña (moãi gian): 9 mm

In 12,000 mm or more: 18 mm Trong khoaûng 12 m hoaëc hôn: 18 mm

3.7.5 Variation of the Building Grid Thay ñoåi truïc toaø nhaø

• For variations of the Building Grid lines from their true position in plan and related position of columns and walls the following applies:

• Sai soá ôû caùc truïc toaø nhaø: töø vò trí trong baûn veõ vaø vò trí coät, töôøng:

Tolerance Table Baûng dung sai

In any bay or 6,000 mm maximum:

12 mm Trong moät gian hoaëc toái ña 6 m: 12 mm

In 12,000 mm or more: 24 mm Trong khoaûng 12 m hoaëc hôn: 24 mm

3.7.6 Correction of Errors Ñieàu chænh sai soùt

Offsets of column and wall centre lines above and below any floor are not permitted.

Khoaûng caùch thaúng goùc tim coät, tim treân vaø döôùi saøn khoâng ñöôïc pheùp aùp duïng.

Where it is necessary to correct on the next floor a column which has been cast out of position, such correction shall have the approval of the Client.

Khi caàn chænh coät (ñaõ ñoå beâ toâng sai vò trí) ôû taàng keá tieáp, phaûi coù yù kieán cuûa Chuû ñaàu tö.

The general attitude will be to have the offending member removed and made good.

Tinh thaàn chung laø caáu kieän thi coâng sai vò trí caàn ñaäp boû vaø thi coâng laïi.

3.8 SURFACE FINISH HOAØN THIEÄN BEÀ MAËT

3.8.1 General Toång quaùt

Surface finish and truth of line in all concrete work is required to be of a high order, attained

Beà maët hoaøn thieän vaø tuyeán ñuùng cuûa coâng taùc beâ toâng caàn ñöôïc tuaân thuû vôùi caùc yeâu caàu nghieâm ngaët

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 18 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 19: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

by a high standard of formwork, placing of concrete, and composition of concrete.

veà vaùn khuoân, coâng taùc ñoå vaø troän beâ toâng.

3.8.2 Visible Surfaces Caùc beà maët thaáy ñöôïc

All surfaces visible on completion of the works shall be free from surface blemishes, entrapped air bubbles, and ridges and surface displacements greater than 2 mm at joints.

Caùc beà maët hôû vaøo luùc keát thuùc thi coâng caàn phaûi khoâng coù khuyeát taät, boït khí; caùc dòch chuyeån beà maët, noùc maùi taïi caùc moái noái khoâng ñöôïc lôùn hôn 2 mm.

Forms shall be of plywood with joints flushed up with epoxy fillers and the whole surface finished with at least 3 coats of gloss polyurethane to obtain the maximum smoothness when stripping. Refer Clause “3.1 – Formwork and Falsework”.

Vaùn khuoân laøm baèng vaùn eùp vôùi caùc moái noái chìm (queùt vöõa epoxy), toaøn boä beà maët vaùn khuoân caàn phaûi coù toái thieåu 3 lôùp polyurethane boùng ñeå taïo ñoä nhaün toái ña sau khi thaùo dôõ. Xem ñieàu “3.1 - Vaùn Khuoân vaø Giaøn Giaùo”.

In all formwork the set out of tie bolts shall be to the Client's approval.

Coâng taùc ñònh vò bu loâng neo vaøo vaùn khuoân caàn coù yù kieán chaáp thuaän cuûa Chuû ñaàu tö.

Special care shall be taken to compact concrete very carefully at these surfaces.

Coâng taùc ñaàm neùn taïi caùc beà maët naøy caàn thöïc hieän thaän troïng.

The Contractor shall ensure that for such surfaces he uses a mix entirely suited to the finish required, refer to Clause “3.8 - Surface Finish”.

Nhaø thaàu caàn baûo ñaûm söû duïng hoãn hôïp thích hôïp ñeå ñaït ñoä hoaøn thieän caàn thieát, xem ñieàu khoaûn “3.8 -Hoaøn thieän beà maët”.

The general appearance of these surfaces must be neat and uniform with an approved regular joint pattern. Refer Clause “3.1 – Formwork and Falsework”.

Caùc beà maët naøy caàn saïch, ñoàng boä vôùi moái noái ñöôïcduyeät. Xem ñieàu “3.1 - Vaùn Khuoân vaø Giaøn Giaùo”.

3.8.3 Hidden Surfaces Caùc beà maët khuaát

Reasonable care must be taken with these surfaces, and the Structural Dimensions shall not be less than shown on the Drawings.

Caàn coù quan taâm hôïp lyù vôùi caùc loaïi beà maët naøy. Caùc kích thöôùc keát caáu caàn tuaân thuû caùc chi tieát neâu treân baûn veõ.

3.8.4 Surface Blemishes Caùc khuyeát taät treân beà maët

Should defective or honeycombed areas, projecting fins or other blemishes exist, the Contractor shall at once inform the Client and shall under no circumstances undertake any remedial measures without the prior instruction of the Client.

Ñoái vôùi caùc khuyeát taät (roã, phuø,…) Nhaø thaàu caàn phaûi thoâng baùo ngay cho Chuû ñaàu tö ñeå coù yù kieán chæ ñaïo tröôùc khi tieán haønh khaéc phuïc.

The Client reserves the right to reject any defective work back to the next construction joint and to have it replaced.

Chuû ñaàu tö coù quyeàn khoâng chaáp nhaän coâng taùc khaéc phuïc ñeán moái noái thi coâng tieáp vaø yeâu caàu thi coâng laïi.

The Client may, however, order remedial works to be carried out.

Chuû ñaàu tö coù theå yeâu caàu thöïc hieän laïi coâng taùc söûa chöõa.

All work repaired by the use of new materials shall be properly cured in place to the Client's satisfaction.

Coâng taùc khaéc phuïc vôùi vaät lieäu môùi phaûi ñöôïc baûo döôõng ñuùng qui caùch.

Surface plastering or cement washing to cover up poor workmanship will not be permitted.

Khoâng chaáp nhaän coâng taùc daäm vaù baèng vöõa xi maêng ñoái vôùi caùc khuyeát taät.

The cost of any work arising from this Clause shall be borne by the Contractor.

Chi phí cho coâng taùc khaéc phuïc theo yeâu caàu cuûa ñieàu khoaûn naøy do nhaø thaàu chòu.

3.8.5 Slabs Saøn

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 19 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 20: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

In general slabs shall be finished so that a 3000 straight edge shows no out-of-plane exceeding 3 mm and shall have a surface finish achieved from the skilful use of a powered steel float.

Beà maët hoaøn thieän saøn, qua kieåm tra baèng thöôùc raø 3 m, phaûi ñaït ñoä phaúng coù sai soá khoâng lôùn hôn 3 mm. Caàn söû duïng baøn xoa ñieän ñeå ñaït ñoä phaúng caàn thieát.

The use of the spot method of screeding will not be permitted.

Khoâng ñöôïc söû duïng phöông phaùp lôùp vöõa caùn trong hôïp ñoàng naøy.

Screed boards or pipes shall be used in conjunction with vibrating screeds.

Taám hoaëc oáng san vöõa caàn söû duïng chung vôùi ñaàm baøn.

3.9 TRIM AND BUILD IN HOAØN THIEÄN VAØ LAÉP ÑAËT

3.9.1 General Toång quaùt

Trim openings in the work as required. Hoaøn thieän loã môû theo yeâu caàu.

Provide and build in all necessary plugs, bolts, ties, clamps, dowels and fastenings required by other trades, including bolts for timber plates, metal angles, concrete block reinforcement and approved steel and sleeves for pipes.

Cung caáp vaø laép ñaët caùc nuùt, bu loâng, giaèng, keïp, cheâm do caùc Nhaø thaàu khaùc yeâu caàu, keå caû bu loâng cho baûn goã, ke theùp, coát theùp khoái beâ toâng, theùp vaø oáng loàng.

The Contractor shall be responsible for the set out of holes, sleeves and other items to be trimmed for or built in, and shall obtain all necessary information relating thereto from the Subcontractors concerned.

Nhaø thaàu chòu traùch nhieäm ñònh vò loã môû, oáng loùt vaø caùc haïng muïc caàn hoaøn thieän hay laép ñaët khaùc va øphaûi ñöôïc caùc Nhaø thaàu phuï khaùc cung caáp thoâng tin lieân quan.

Every care shall be taken to ensure that as little cutting as possible is needed after pouring is complete.

Löu yù giaûm thieåu vieäc taïo caùc loã môû sau khi keát thuùc ñoå beâ toâng.

3.9.2 Build in Laép ñaët

Build in fixings for steel steps, cartdock leveller trim, column protectors, door protectors etc.

Laép ñaët caùc chi tieát coá ñònh baäc thang theùp, caùc chi tieát baûo veä coät, cöûa.

Build in probes and tobies for temperature recorders, as detailed.

Laép ñaët ñaàu doø, bình cho duïng cuï ño nhieät ñoä theo höôùng daãn.

3.10 SLAB POURED ON HARDFILLING ÑOÅ BEÂ TOÂNG SAØN TREÂN COÁT LIEÄU ÑAÉP

3.10.1 Ground Preparation Chuaån bò coâng taùc ñaát

Refer also to “C1 - Excavations and Backfilling” of the Specification.

Tham khaûo “C1 - Coâng Taùc Ñaøo Ñaép” – Ñaëc ñieåm kyõ thuaät.

When compacting around any works beneath or adjacent to the slab, care shall be taken not to cause any displacement of structure.

Khi ñaàm neùn coâng trình döôùi hay keá beân saøn, caàn thaän troïng ñeå traùnh gaây dòch chuyeån caáu kieän.

Should any waterproofing, hardfill, or underlying ground be disturbed by construction activities, the Contractor shall make good any damage at his own expense to the specified standard before concreting may begin.

Nhaø thaàu phaûi khaéc phuïc ngay caùc thieät haïi gaây ra cho maøng choáng thaám vaø ñaát ôû beân döôùi trong quaù trình thi coâng (chi phí lieân quan do Nhaø thaàu chòu) theo tieâu chuaån qui ñònh, tröôùc khi tieán haønh ñoå beâ toâng.

The Client will require inspecting all hardfill before DPC or waterproofing is placed on it.

Chuû ñaàu tö seõ kieåm tra lôùp ñaù ñaép tröôùc khi ñoàng yù cho traûi maøng choáng thaám.

3.10.2 Waterproofing Coâng taùc choáng thaám

Waterproofing shall be laid where shown over Ñaët maøng choáng thaám treân saøn tröôùc khi laép ñaët coát

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 20 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 21: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

the area of the slabs, immediately before the placing of reinforcement and extreme care shall be taken to protect waterproofing from damage of any kind.

theùp. Löu yù khoâng ñöôïc laøm hö haïi maøng naøy.

Any waterproofing damaged by construction work shall be repaired as directed by the Client before concrete is placed.

Caàn khaéc phuïc ngay lôùp maøng choáng thaám, neáu coù hö haïi xaûy ra do thi coâng xaây döïng, tröôùc khi ñoå beâ toâng.

3.10.3 Reinforcing Coát theùp

Reinforcing as shown on drawings shall be supported on concrete blocks of at least 50 x 50 base area and at least 2 per m2.

Coát theùp theo chi tieát qui ñònh treân baûn veõ seõ ñöôïc ñôõ treân caùc khoái beâ toâng taïi vò trí coù ñeá vôùi kích côõ toái thieåu 50x50 vaø ít nhaát coù 2 ñeá treân moãi m2.

Reinforcing in top of slab to be supported on stools – 2 per m2.

Coát theùp taïi ñænh saøn seõ ñöôïc ñôõ treân caùc chaân ñôõ (2 caùi treân moãi m2).

3.10.4 Formed and Sawn Joints Moái noái taïo hình, moái noái cöa xeû

These shall be made as and where shown in the Drawings.

Caùc moái noái ñöïôc thöïc hieän theo caùc chi tieát vaø vò trí neâu treân baûn veõ.

This shall be done using a 8 mm blade, by a Specialist Sub-Contractor.

Thaàu phuï chuyeân ngaønh thöïc hieän caùc moái noái vôùi löôõi bay 8 mm.

The sawing of sawn joints shall be done as soon after the pouring of the concrete as the concrete shall have hardened sufficiently to permit sawing to be done without damaging the concrete.

Thöïc hieän cöa xeû moái noái ngay sau khi beâ toâng vöøa môùi ñoå xong, do beâ toâng vöøa ñuû cöùng ñeå vieäc cöa xeû khoâng gaây toån haïi cho beâ toâng.

As late as possible boxed joints shall be similarly sawn.

Sau ñoù caùc moái noái ñaõ taám vaùn khuoân seõ ñöôïc cöa xeû töông töï.

As late as possible in the Contract, the joints in the general service and store areas shall be filled with an approved polysulphide sealant.

Moái noái taïi khu vöïc dòch vuï toång hôïp, nhaø kho ñöôïc traùm baèng vaät lieäu bòt “polysulphide” ñöôïc chaáp thuaän.

No joint filler is required in tiled or epoxy finished floors.

Khoâng caàn traùm moái noái saøn laùt gaïch hay saøn phuû epoxy.

The Contractor's attention is drawn to the necessity of ensuring that all sawing is done in straight continuous lines.

Nhaø thaàu caàn ñaûm baûo laø coâng taùc cöa xeû moái noái phaûi thaúng vaø lieân tuïc.

The Contractor shall ensure that no foreign matter is permitted to enter a saw cut, thereby making the placing of the filling unsatisfactory and shall take positive steps to overcome this.

Nhaø thaàu phaûi coù bieän phaùp di dôøi caùc taïp chaát tröôùc khi traùm kín caùc moái noái.

3.10.5 Surface Finish Hoaøn thieän beà maët

• Basement floors • Saøn taàng haàm

The concrete floor shall be finished using a powered float. The concrete should lightly broomed.

Saøn beâ toâng caàn ñöôïc hoaøn thieän baèng thieát bò xoa chaïy ñieän. Beâtoâng caàn ñöôïc taïo nhaùm baèng choåi.

• Plant rooms: • Gian maùy

The stores floor surface shall receive an application of an integral mineral aggregate based hardtopping (Natural Grey) at the rate of 3 to 5 kg/m2.

Beà maët saøn nhaø kho caàn ñöôïc traûi coát lieäu ñaù khoaùng cöùng vôùi tyû leä 3 ñeán 5 kg/m2.

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 21 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 22: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

Use: Duøng vaät lieäu

Sika – CHAPDUR and ANISOL E CURING AGENT

Sika-Chapdur vaø vaät lieäu baûo döôõng ANISUL E

Or Hoaëc

MBT – MASTERTOP 100 and MASTERKURE 128

MBT-MASTER TOP 100, MASTER KURE 128

The application of the material shall be carried out under the direct continuous supervision of a specialist provided by the product supplier.

Ñöôïc aùp duïng döôùi söï giaùm saùt cuûa Ñaïi dieän Nhaø cung caáp saûn phaåm.

The hardener should be applied in two layers by broadcasting by hand.

Phuï gia seõ ñöôïc raûi baèng tay thaønh hai lôùp.

Approximately two-thirds of the total quantity should be applied in the first broadcast and balance in the second.

Raûi 2/3 phuï gia cho lôùp raûi ñaàu; 1/3 coøn laïi cho lôùp thöù hai.

First shake on application Lôùp raûi ñaàu

Mark the floor area in bays of convenient size and keep the required number of bags of the hardener ready for each bay depending on the rate of application specified.

Chia khu vöïc saøn thaønh töøng gian coù kích côõ thích hôïp; chuaån bò saün soá löôïng tuùi phuï gia cho moãi gian theo tyû leä söû duïng ñaõ quy ñònh.

Broadcast the powder evenly by hand on the floor surface after the concrete has been floated and evaporation of bleed water.

Duøng tay raûi ñeàu phuï gia treân beà maët beâ toâng ñaõ ñöôïc xoa hoaøn thieän vaø nöôùc beâ toâng dö ñaõ boác hôi.

Apply first on floor areas adjacent to walls, columns, joints, doorways where the concrete is likely to loose moisture rapidly.

Tröôùc heát raûi phuï gia taïi khu vöïc saøn gaàn töôøng, coät, moái noái, loái cöûa ñi, do ñoä aåm nôi ñaây boác hôi nhanh.

After the application the hardener darkens in colour indicating absorption of moisture from concrete and when the concrete has stiffened enough to prevent float blades from digging into the surface, float the applied surface using power floats.

Phuï gia ñoåi maøu saäm khi thaám aåm beâ toâng; sau khi beâ toâng ñoâng cöùng ñuû ñeå löôõi thieát bò xoa khoâng gaây toån haïi, duøng thieát bò xoa hoaøn thieän maët beâ toâng.

Float just enough to bring excess moisture to the surface.

Coâng taùc xoa caàn thöïc hieän sao cho löôïng nöôùc dö xuaát hieän treân beà maët beâ toâng.

Second shake on application Lôùp raûi tieáp theo

Follow with the second application of the hardener as the first application proceeds to the next bay.

Baét ñaàu lôùp raûi thöù hai khi tieán haønh lôùp raûi thöù nhaát cho gian keá tieáp.

Broadcast the remaining third of the hardener evenly by hand, compensating with extra material over areas under applied during the first broadcast.

Raûi ñeàu 1/3 löôïng phuï gia coøn laïi. Tröø hao löôïng phuï gia söû duïng loá ôû lôùp raûi ñaàu.

As soon as the second layer has darkened by moisture absorption, float the surface with a power trowel equipped with float blades or disc floats.

Khi lôùp thöù hai ñoåi maøu saäm do thaám aåm beâ toâng, hoaøn thieän beà maët baèng ñóa xoa.

Finish Hoaøn thieän

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 22 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006

Page 23: SGP - ACT S1 - Rev.0 - Concrete Works - May 29_ 06.doc (for TENDER).pdf

To obtain a fine non slip finish, trowel the surface after it stiffens further using a power float keeping the blades as flat as possible without digging in the surface.

Phaûi ñaït beà maët hoaøn thieän nhaùm vôùi bay vaø thieát bò xoa maø khoâng laøm haïi beà maët.

Work areas Process Areas Khu vöïc gia coâng cheá bieán

Provide a smooth power float finish, suitable for the direct application of an Epoxy topping.

Hoaøn thieän vôùi thieát bò xoa ñieän, phuø hôïp vôùi vöõa epoxy phuû maët.

Curing Döôõng hoä

Start curing immediately after final finishing using a liquid membrane curing compound on all concrete surfaces.

Tieán haønh coâng taùc döôõng hoä sau lôùp hoaøn thieän cuoái cuøng baèng caùch thöïc hieän lôùp maøng loûng döôõng hoä treân beà maët beâ toâng.

Ensure the compound chosen is compatible will the floor finishes to be placed later.

Löu yù aùp duïng lôùp maøng thích hôïp vôùi loaïi beà maët hoaøn thieän.

3.11 CONCRETE WATER TANKS BEÅ BEÂ TOÂNG CHÖÙA NÖÔÙC

3.11.1 General Toång quaùt

Great care shall be taken in the construction of the water reservoirs to ensure complete water tightness of the Structure.

Löu yù ñeán ñoä kín nöôùc khi ñoå beâ toâng beå nöôùc.

Careful preparation of all construction joints to ensure proper bonding between old and new concrete, the installation of water sealants in the construction joints, joints sealants and the application of an internal membrane water barrier is required.

Thöcï hieän caån thaän caùc moái noái thi coâng ñeå baûo ñaûm ñoä lieân keát giöõa hai khoái beâ toâng cuõ vaø môùi. Yeâu caàu laép ñaët vaät lieäu kín nöôùc vaøo caùc moái noái thi coâng, maïch noái vaø traûi maøng choáng thaám beân trong beå.

3.11.2 Water sealant Vaät lieäu kín nöôùc

SIKA – HYDROTITE CJ – 0725 – 3K SIKA-HYDROTITE CJ-0725-3K

Install hydrotite rubber sealing strips in all construction joints in accordance with the Sika manual.

Ñaët daûûi cao su kín nöôùc vaøo caùc moái noái thi coâng theo höôùng daãn cuûa Nhaø saûn xuaát Sika.

3.11.3 Rebated joints Moái noái moäng

SIKAFLEX 1a SIKA FLEX 1a

Install Sikaflex joint sealer in 20 x 20 rebated primed joints on the internal wall face of all construction joints in accordance with the recommendation in the Sika manual.

Traûi vaät lieäu SIKAFLEX vaøo caùc moái noái moäng 20x20 ôû maët trong caùc moái noái thi coâng, theo höôùng daãn cuûa Nhaø saûn xuaát Sika.

3.11.4 Water Barrier Maøng choáng thaám nöôùc

On the interior face of all tanks (Walls and Floors) as well as the top of the roof slab apply a flexible cementitious water proof membrane such as SPECTITE CW 100 or equal and approved.

ÔÛ maët trong beå nöôùc (töôøng vaø saøn), ñænh saøn maùi seõ phuû maøng choáng thaám SPECTITE CW100 hoaëc vaät lieäu töông ñöông ñöôïc chaáp thuaän.

Apply to a minimum thickness of 2mm in two coats, all in accordance with the Spectite Manual.

AÙp duïng hai lôùp vôùi ñoä daøy toái thieåu 2 mm, theo höôùng daãn cuûa Nhaø saûn xuaát Spectite.

Project Name: Saigon Pearl Development – Phase 2 Concrete Works Page 23 of 23 Project Location: HCMC Specification Rev. 0 The English prevails May 29, 2006