Light Rail 2014 The Transition from Construction to Operations
Sheila Fennell Business Leader Urban Trasnport
© Interfleet Technology 2013
Rail. Right through
© Interfleet Technology 2013
Rail. Right through
Outline
• Luas – Dublin • Blackpool - UK • Technical • Commercial • Resourcing • Media / Political
© Interfleet Technology 2013
Rail. Right through
Case Study – Luas Dublin
• Opened in 2004 • Three extensions – one
under construction • 36.5km • 54 stops • 66 40m Citadis trams • 30m pax/year • Revenues cover
operating costs
© Interfleet Technology 2013
Rail. Right through
Luas Lessons Learnt
• Safety – Transfer of Safety Case to
Operator – Construction works ongoing
during driver training – Incident prior to opening of
2nd line
• Technical – Sate supplied ticketing
equipment – Radio system – Traffic signalling
© Interfleet Technology 2013
Rail. Right through
Luas Lessons Learnt
• Resources – Mobilisation of Operator – Driver training – Staff attrition – Training of O&M staff
• Political/PR – Opening day event – Overcrowding – Negative to positive media
© Interfleet Technology 2013
Rail. Right through
Blackpool UK
• 127 year old system • Upgrade works 2009 –2013 • 18km • 37 stops • 16 32m Flexity trams • Government funded • Local private operator of
buses and tram
© Interfleet Technology 2013
Rail. Right through
Blackpool Lessons Learnt
• Operator – Step change in technology – Staff turnover
• Safety – Historical exceptions to
safety regulations – Steep learning curve,
SMS, interaction with regulator
© Interfleet Technology 2013
Rail. Right through
Blackpool Lessons Learnt
• Technical – Training refresher courses
• Contractual – Non approved spares
impact on warranty
• PR – Success of new system
from day one – Moving to new timetable
© Interfleet Technology 2013
Rail. Right through
Commercial
• Payment mechanism • Completion and Close
out • System Site • Local Authorities
• Management of PPP contract in O&M phase
© Interfleet Technology 2013
Rail. Right through
Conclusion
• Resources • Safety • Program sufficient
time for technical rectification
• Plan for success