SHORTCOMING REPLY: BHAGWAN MAHAVIR SUPERSPECIALITY GOVERNMENT HOSPITAL AT PLOT NO. H-4, 5, PITAMPURA, DELHI BY M/s PUBLIC WORKS DEPARTMENT (HEALTH), GOVT. OF NCT, DELHI
1. Submit copy of valid consent to establish/consent to operate issued by DPCC for existing hospital project
Reply- Consent to Establish/ consent to Operate is to be obtained by PP.
Annexure 1- CTO from DPCC is obtained
2. Submit copy of authorization under bio-medical waste management rules , 2016 issued by DPCC
Reply- Authorization under bio-medical waste management rules, 2016 issued by DPCC is
obtained.
Annexure 2- BMW authorisation letter obtained
3. Details of ETP and STP to be provided Reply- STP of 253 KLD capacity is proposed based on MBR Technology.
The design of sewage network shall be done in accordance with the CPHEEO guideline, NBC guidelines and reverent Indian Standards. Sewage generation is assumed to be 100%
of flushing water and 80% of domestic water. The following parameters/ site conditions shall be kept in mind when designing the sewage,
Sludge and storm water drainage system.
Natural slope of the area.
Layout of different facility in the complex;
Possibility of using complete or part of the existing sewage network;
Sub-soil water table;
Provision of Sewage lifting station; ( if required)
Provision of venting arrangement for manholes;
Construction of manholes & laying of pipes considering ground condition;
Termination of vent cowl at terrace level;
Provision of adequate slope for horizontal header in the under slung pipes especially
for public toilets
Sewage flow starts with fractional capacity and builds up to full capacity in due
course. An operational plan to meet this demand from a low flow to full flow will be
part of the design.
A summary of board design parameters to be adopted for designing Sewage supply system
is given below.
Table 1: Design Parameters for Sewage Collection System
Different Use Norm Used
Type of Collection System Separate System
Design Period -30 years for sewers and appurtenances -15
years for pumps and electric equipment’s
Peak Factor 3
Minimum velocity 0.6 m/sec
Maximum velocity 3.0 m/sec
Minimum size of pipe 250 mm (ID)
Minimum depth of Sewer 1.0 m from FGL (0.6 m minimum
cushion)
Hydraulic Formula for calculation for
design of sewer lines (As per CPHEEO
manual 3.4.2.1 page no-36)
Manning’s formula V= 1/n*(R^2/3)
*(S^1/2 ) V= Velocity R = Hydraulic mean
depth = A/P S = Slope
Flow conditions in pipe up to 400 mm dia 0.50 full
Flow conditions in pipe up to 300 mm dia 0.67 full
Manning’s Co-efficient ‘n’ 0.011
Shape of sewers Circular
Material of sewers HDPE
Manhole Sizes As per manual on sewerage and sewerage
treatment/ IS4111:1985
For depth above 0.9m & up to 1.65m 900 mm diameter
For depth 1.65m & up to 2.3m 1200 mm diameter
For depth 2.3m & up to 9.0m 1500 diameter
The alignment and slope of the sewer line will follow the road network, drains or natural
ground surface and will be connected to the trunk sewers. The discharge point will be a
treatment plant, a pumping station, a water course or an intercepting sewer. Pumping
stations would be provided at places where the natural slope of the terrain is insufficient to
permit gravity flow or the cost of excavation is uneconomical to do the same
Following are the benefits of providing the Sewage Treatment Plant in the present
circumstances:
Reduced net daily water requirements, source for Horticultural purposes by
utilization of the treated wastewater. This shall consequently lead to a lower
withdrawal from the underground aquifer water sources.
Reduced dependence on the public utilities for water supply and sewerage systems.
Sludge generated from the Sewage Treatment Plant shall be rich in organic content
and an excellent fertilizer for horticultural purposes.
Technology Proposed
Membrane Bio Reactor (MBR)
The MBR is a suspended growth-activated sludge system that utilizes micro porous
membranes for solid/liquid separation instead of secondary clarifiers.
An external sewage network shall collect the sewage from all units, and flow by gravity to
the proposed sewage treatment plant
The STP is being proposed with state-of-the-art membrane separation technology called as
Membrane Bio-Reactor (MBR) which can produce very good quality with highest possible
bacterial reduction without adding any chemicals. MBR (Membrane Bio Reactor) is the
latest technology in wastewater treatment. MBR has many advantages such as higher
quality of treated water, smaller space for installation and easier operation compared to
conventional activated sludge process.
Designed to produce high quality treated water from wastewater the Membrane Bio Reactor
(MBR) is among the latest technologies in biological treatment.
The characteristic of the MBR process is the use of revolutionary submerged polymeric
hollow fibre membranes in the biological process water tank, so as to produce high quality
permeate from domestic sewage, primary and secondary waste water, cooling tower blow
down etc. The MBR is also ideal for retrofitting/augmenting capacity/quality of existing
wastewater plants.
The hollow fibers are combined into bundles and wound around a carrier cartridge, which
gives the membranes the required strength and allows for high-pressure air scour for
cleaning. The MBR can handle very high sludge concentrations in the aeration tank because
of which the size of the aeration tank reduces four to five folds. As the membrane acts as a
fine filter, it does not require any further treatment using sand filters, activated carbon filters,
etc. The MBR is available in standard and customized modules.
Process Description
Figure below shows the principle of the filtration for the flat sheet type submerged
membrane. Activated sludge in the aeration tank is clearly removed by the flat sheet type
submerged membrane. The membrane module consists of housing, aeration diffuser;
permeate water manifold and membrane elements. The membrane element consisting of flat
sheet membranes sandwiching a support panel is set up vertically. Feed water including
activated sludge is filtrated by flat sheet membranes with pore size of 0.1 micron meter. The
air bubbles supplied from the bottom of the membrane elements continuously scour off cake
of activated sludge accumulated on the membrane surface. This is continuous filtration
operation. The air bubbles are also used for the biological reaction to decompose organic
substances included in the raw sewage.
MBR Module
The material of the membrane is PVDF (Poly vinylidene fluoride). PVDF is fluorine
polymer, which has high stability for chemicals and good physical strength. The form of
membrane is fibre reinforced flat sheet membrane. The membrane has small and uniform
pore size. Therefore, the rejection property of this membrane is excellent. Almost all
particles with sizes more than 0.1 micron meter can be removed effectively using this
membrane.
Operation
Sewage from main drain line is collected through gravity pipes into a screen chamber. This
manually cleaned screen is provided to remove floating and big size particles, which may
choke the pumps and pipe lines.
Screened sewage is then passed through equalization tank to homogenize the sewage quality
and also even out flow fluctuations and feed sewage of uniform quality at constant rate to
subsequent treatment units. Air mixing is also provided to mix the contents of the
equalization tank. A coarse bubble aeration grid is provided to distribute air uniformly at the
base of the equalization tank.
After above treatment, raw sewage is fed into aeration basin.
In aeration tank, MLSS (mixed liquor suspended solids) in the range of 12000 to 15000
mg/l are maintained. The high amount of bacteria gives better and complete removal of
organic matter from the raw sewage in relatively small area. Oxygen required for the
bacteria is supplied through the blower. The air is used both for scouring of membranes and
supplying oxygen to bacteria.
The filtration is carried out by the suction pump directly sucking permeates water. The
permeate water produced is clear and devoid of bacteria and viruses to the minimum levels.
As the membranes are continuously under operation, they are polluted with organic or
inorganic substances. Hence, chemical cleaning is carried out once in two to three months
for removing substances polluting and clogging the membranes. Normal cleaners used are
sodium hypo chloride and citric acid.
Preventive measures to Avoid Leaching
Treated sewage from Sewage Treatment Plant will be conveyed to Treated Sewage Tank
through pipelines. All the joints from piping system will be checked periodically and
carrying treated wastewater pipes will be laid in conduits wherever road crossings are
expected. Thus no leaching of treated sewage into nearby water courses shall take place.
Figure 1: Schematic Diagram of MBR Technology STP
Supervisors will be employed for overall operation & maintenance of water supply, waste
water treatment and other utility services
Effluent treatment technology
The design of effluent network shall be done in accordance with the CPHEEO guideline,
NBC guidelines and reverent Indian Standards. ETP of 98 KLD shall be installed for
hospital wastewater.
The main objective of Effluent Treatment Plant (ETP) is to remove as much of the
suspended solids and organic matter as possible before the waste water is discharged back to
the environment. When untreated wastewater mixes with groundwater it can create
significant health risks by causing serious infectious diseases to people who have suppressed
immune systems.
1. Preliminary Stage: This stage is also called as pretreatment which is the most essential
treatment process in most of the ETP. It involves bar screens which comes in variety of
shapes and sizes to remove large sized suspended solids like paper, plastics, metals, debris,
rags and many such from incoming raw wastewater/sewage. If these materials are not
removed then they may cause serious damage to plant equipment’s. When wastewater
enters into grit chamber, it slows down the flow of water and thereby removes sand, grit,
sand stones and this process is called as sedimentation.
2. Primary Stage: It uses physical and chemical methods to improve the quality of the
wastewater which was not achieved in previous stage. When wastewater enters to
sedimentation tank or primary clarifiers, heavier solid particles settle to the bottom of the
tank and lighter particles will float up and will be skimmed off from top of the surface using
a process called skimming and thereby removing 60-65% of total suspended solids from
liquid wastewater. This stage may use grit chamber to remove grit. The settled solid is
known as primary sludge which will send to sludge digester for further processing. Now
partially clarified water flows on to the next stage.
3. Secondary Stage: This is the stage which can remove about 80-90% of organic matter by
using a process called biological treatment methods. Most of the hospital ETP uses
“activated sludge process” in which liquid wastewater enters into aeration tank where
wastewater mixes with air to encourage the growth of microbes and hence breakdown of
organic matter takes place. When aerated water enters into secondary clarifier, floatable
matter will be removed and heavier matter settles to bottom which is called as “active
sludge” or secondary effluent. Part of the sludge which still contains microbes will be re-
circulated back to aeration tank to increase the rate of organic matter decomposition. The
left over microorganisms are handled separately in next stage called disinfection.
4. Tertiary stage: This is the final stage which is also known as disinfection stage. This stage
removes any residual suspended solids and other materials which were not removed in
previous stages. The effectiveness depends on the quality of the water being treated. The
major objective of disinfection is to reduce number of microorganisms in the waste water to
be disposed into the natural environment. Disinfection technologies consist of ozone,
chlorine, and Ultraviolet (UV) rays to eliminate toxic chemicals that exist in the wastewater.
This stage removes nitrogen, phosphorous and other toxic contaminants.
Figure 2-Conventional treatment process in ETP
4. Details that the prescribed land use of the area is as per the master plan. (The surrounding area appears to be residential) and is the hospital permitted in the area by the competent authorities.
Reply- It is super specialty Govt. hospital having existing facility of 200 beds, The Hospital started
in the Year 2003 and began with Out Patient Services. Gradually Emergency services and
inpatient services were initiated along with ancillary services such as radiology and laboratory, the
land was allotted for the public facility by DDA.
Annexure 3- DUAC approval letter
5. Details of plans to ensure that infectious chemicals and contagious pathogens are not allowed to come in contact with patients/workers/staff and general public during disposal, recycle, reuse, or use in dual plumbing and flushing
Reply- Agreed, It will be ensured that infectious chemicals and contagious pathogens are not
allowed to come in contact with patients/workers/staff and general public during disposal,
recycle, reuse. For the infectious wastewater from the hospital shall be treated in an in house ETP
and after the tertiary treatment, wastewater shall be discharged to the nearby municipal sewer.
However General wastewater from the block shall be treated in in an in-house STP and after
primary secondary and tertiary treatment, treated water shall be re-use for flushing, horticulture,
HVAC cooling and other miscellaneous purposes.
Annexure 4- dual Plumbing plan is attached
6. Proposals to implement the provisions of the noise rules, and its amendments regarding establishing silence zones around the hospitals
Reply- Necessary measures shall be taken.
7. The certificate shall be obtained from the local body supplying water, specifying the total annual water availability with the local authority, the quantity of water already committed, the quantity of water allotted to the project under consideration and the balance water available. This should be specified separately for ground water and surface water sources, ensuring that there is no impact on other users.
Reply- As the project is already in operational stage since 2003, for the existing project main
source of water is DJB, and no groundwater is being abstracted. However for the expansion site,
Source shall be DJB only. No groundwater shall be abstract during construction as well as
operational stage.
Water bill from DJB is attached as ANNEXURE- III
Annexure 5- DJB bills are attached for the existing facility
8. The air quality index shall be calculated for base level air quality
Reply- Air quality monitoring and analysis has been done by NABL accredited lab.
Annexure 6- Lab data is attached
9. A detailed report on compliance to ECBC 2017 norms Reply- Detailed ECBC compliance Report for the proposed hospital project is attached
Annexure 7- ECBC compliance report
10. Plan for corporate environment responsibility as specified under MoEF&CC memorandum shall be prepared and submitted.
Reply- Corporate Environment Responsibility as specified under MoEF & CC has been prepared.
Annexure 8- CER affidavit
Approval Letter
To,
VIKRAMJIT SINGH BHARAJ A-15, PAMPOSH ENCLAVE,G.K.-1, NEW DELHI -110048
OL-14061727020No. : Date : 03/08/2017
Code : 14061727062
fo"k; % ADDITION AND REMODELLING WORK FOR BHAGWAN MAHAVIR HOSPITAL, PITAMPURA, NEWDELHI
lanHkZ %
mä çLrko ij vk;ksx dh fnukad 05/07/2017 04:30 PM dks vk;ksftr cSBd esa fopkj fd;k x;k Fkk A vk;ksx dh çs{kk,a rFkk fu.kZ; bl çdkj gSa A
egksn; ,
Decisions:
Concept of the proposal accepted.
Observations:
1. The proposal was submitted directly by thearchitects for conceptual consideration of theCommission online.2. The concept of the proposal was foundacceptable.
fouksn dqekj
lfpo
lfpo
1) VIKRAMJIT SINGH BHARAJ A-15, PAMPOSH ENCLAVE, G.K.-1, NEW DELHI -1100482) Health projects Division (North)PWD – G.N.C.T.DSector-6, Rohini, Delhi- 110085
çfrfyfi :
lfpofouksn dqekj
RESI.HOUSES
TO RA
NI BA
GH
7.50 M W
IDE RO
AD
7.50 M W
IDE RO
AD
TO IN
D. A
REA M
AN
GO
L PURI
B.M. 100.00
S. W. D
RAIN
K A C
H H A R O
A D
GREEN
BELT4" D
IA. W
ATER LIN
E BELOW
ELECTRIC
LINE A
BOV
E
9.50 M W
IDE RO
AD
SEWER LIN
E
PITA
M P
URA
CLU
B24" DIA SEWER LINE
S. W. DRAIN
1.35M DRAIN
90.40 M120.40 M
258.30 M
170.00 M
4" DIA
. WA
TER LINE
PARK
(G+4)
BLOCK B(G+2)
(G+5)
COURTYARD
BLOCK A
RAMP
(G+3)
COURTYARD (G+5)
(G+3)TYPE I
(G+3)TYPE I
RAMP
(G+3)TYPE II
RAMP
GARAGESSERVANTS/
SERVANTS/GARAGES
HOSTEL
HOSTELJR.DOCTORS
HOSTELSR.DOCTORS
TYPE IV(G+7)
TYPE V
1 . 0 0 M W
I D E F O
O T P A
T H
DN
BLOCK C
MAINENTRY
BLOCK D
14.20M
170.65M(G+1)
ENTRYRESIDENT'S
RESIDENCES
CAR PARKING
(G+7)
TYPE I(G+3)
TYPE I(G+3)
(G+3)
TYPE II(G+3)
TYPE II
COLLEGE LAND
TYPE III
(G+3)
(G+3)
(G+3)
TYPE III
TYPE III
GURU HA
RKISHAN
MA
RG(RO
AD
NO
43)
RESIDENCES
(G+7)
(G+7)
K
L
K
RAM
P
TYPE IV SC
OO
TERG
ARA
GES (8N
OS.)
CAR PARKING
7. 0 0 M W I D E R O A D
7. 0 0 M W I D E R O A D
7. 0 0 M W I D E R O A D
7. 0 0 M W
I D E R O
A D
7. 0 0 M W I D E R O A D7. 0 0 M W I D E R O A D
7. 0 0 M W
I D E R O
A D
7. 0 0 M W
I D E R O
A D
7. 0 0 M W I D E R O A D
7. 0 0 M W I D E R O A D7. 0 0 M W I D E R O A D
Set back line
Set back line
GRE
EN B
ELT
GRE
EN B
ELT
HARD PAVING
(G+7)
NURSES
Set back line
E
K
J J
M
J
II
I
SUB STATIONELECTRIC
RAM
P TOBA
SEMEN
T
PATHWAY
FROM CAREXIT
PARKING
EXIT7. 0 0 M W I D E R O A D
CAR PARKINGCAR PARKING
CAR PARKING
BELTGREEN
7. 0 0 M W
I D E R O
A D
ENTRY TO OPD
CAR ENTRY
PROPOSED NEWFLOOR-3NOS
PROPOSED NEW FLOOR-1NOS
PROPOSEDSCREENING OPD
HOSPITALBLOCK
COURTYARD
M.C.HEMERGENCYENTRY
1236
5
4163
0
HOSPITALBLOCK
CAR PARKING
7. 0
0 M
W I
D E
R O
A D
UNDER GROUND TANK(EXISTING)
UNDER GROUND TANK(PROPOSED)
UNDER DESIGN
TR
AN
SF
OR
ME
R
WA
TE
R
FIL
TE
R
PLA
NT
PVC TANK
PR
OP
OS
ED
U.G
ST
P
EXISTING
EXISTING TUBEWELL
PROPOSED TUBE WELL
TUBEWELL
TW
EXISTINGDRAINCHANNEL
UN
DE
R
GR
OU
ND
T
AN
K
PU
MP
HO
US
E
16
16
16
16
ESMH ESMH ESMH
ESMH
ESMH
ESMH
EXISTINGSEWER LINE
EXISTINGPUMPINGSTATION
EXISTINGSTPCAP.300m3
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTINGDRAINCHANNEL
EXISTING DRAIN CHANNELCONNECTED TO EXTERNALMAIN DRAIN
EXISTING DRAIN CHANNELCONNECTED TO EXTERNALMAIN DRAIN
EXISTING DRAIN CHANNELCONNECTED TO EXTERNALMAIN DRAIN
LEGEND
SYMBOL DESCRIPTION
EXISTING SEWER MANHOLEESMH
EXISTING SEWER LINEESMH
PS
MH
, ')
I
GOVERNMf NT OF THE NATIONAL CAPITAL TERRITORY OF DELHI OFF ICE OF HfE MEDICAL SUPERINTENDENT
13HAGWAN MAHAVIR HOSPITAL PITAM PURA: DELHI - 110 034
Nn I 2 ( Hfl )/20011/DI f',/13M If/ Ar.c t 'i Da ted:
SANCTION ORDER No. r-
TltP l'.XpPnditure Si.l nct ion of Rs.9,27,639/- (Rupees Ni e Lakh Twenty Seven Thousand
.-1 nd Six Hundred Thirty Nine Only). is accorded by the competent authority in con nection w ith
pr1y111 P 11t l n Delhi Jal Board agilins t Rill No. 749077065344 issuing date 10/07/2018 for the period of
03/06/18 to 04/07/2018 .
The r ro rosal has been exa mined by the accounts fun ct ionary. The expenditure on this account is
cJ pb it ahle to th1~ major head "2210" 01 110 29 00 (13) OE Bhagwan Mahavir Hospital under demand No.
7 for the yr.ar 2018-19 and will _not exceed the fund s placed as the disposal of the scheme.
No F 2(80)/2004/DHS/BMH/Accts
Cory to :-
1. PAO XXV, Peera Garhi, Delhi.
2. DDO, BMH (with one spare copy) .
3. Dte . Of Audit , GNCTD
4. Guard file .
(DR . AJAY KUMAR GUPTA) HEAD OF OFFICE
Dated :
(DR. AJAY KUMAR GUPTA) HEAD OF OFFICE
- -- - -I ~
Delhi Jal Board --7 ( ) (Government ol NC T of Doi hi) -8 'lTI~ • ~~~------- HQ V;uunalaya Phase 11 , Karol Bagh, New Delhi - 110005
~--:-:~-'t Regu la r Wate r 8111 ,:m; Ir-~ PTTT•cTT ,/;'\ J!Yl
- - -'-- ---N.im o . THE ME DICAL SUPDT Consumer Category : CAT II Bill Date I C, 0\/1 O F NC T) Premise Detail : (No of lloo rs -1) 1 0-JUL-2018 Address · BHAGWAN MAHAVIR Water Usage : DELHI Bill Amount (Rs .) I •OS P ITAL H(4 -5 ),RD N0 .-43 , P IT AM GOVT .HOSPITAL/DISPENSARY 927639 PURi\ Delhi Meter No.: NA74 90770000 -
I Meter Type (DJB/Pvt) : PVT
Bill Due Date
1 Mobile No.: 9 899626367 Meter Size (mm) : 15 27-JUL-2018
I Zone/MR Code : NW3/ 193/BULK Bill No.: 749 077065344 Amount Paya ble After Due Date(Rs .)
Arc a Code : A- 1/Kanhaiya Nagar Bill Cycle : ZALL(B4 -2018 ) (5•4 ,urch.argo wlll bo .,ppllc4Jblo .J ft or duo t.l.ilo )
974021 I Old WCN : 92 112 Bill Basis : REGULAR If bill is not pa id till Bill Duo Dato-New KNO: 7490770000
Wa ter connoct lon m a y be d isconnected
I 1 IIIW~IUllmfflffl lllllHllllll!!mlllll ~~m·m11rnurni~ I
Meter No UoM Current Meler Read Previous Meter Read Current Consumption
Mctor Reading Reading / Motor Motor Reading Reading / Mole r Days Units Onto S tatus Date Statu s -
N/\ 74 90770000 KL 04 -JU L-20 18 100810 / OK 03-JUN-2018 97525 I OK 31 3285
8 111 Details : Curre nt Pe riod ChArQes (OJ-J UN-2018 to 04 -JUL -20 18) Appllcablc Rate Period Doscrlpllon Amount(Rs .) 0-1 JUN-.'01 8 to 04-JUL-2018 Tot;il Consurnplion Chnrgos 569235 96 04 JUN-20 1~ lo 04-JUL-20 18 Soworogo Ch;_1rgo (60 % ol W~\or Consump1,on Chaigo ) 34 1541 50 (l ,J.JUN 20 '8 lo Qd.JUL-20 18 Service C,,argu . Consump11on > 100 KL 1361 61 (} l JUti-2018 tc, 04-JUL-201 8 Additiona l Sowc r.tgo Ma,ntcnanco Chnrgo for Ho~p,tals.lNH 15500 00 n-1 I\IN-701A In 04.JUL,2018 Subtotal 13111 Amount ')27639 15
Ad1uslnion1 Dc1a,1s Alo t. ,slod Below
I
>-Arrear. If any (Rs.) -0 .60
Opening Balance/Adjustment, If any (Rs .) 0
Total Consolidated Bill Amount Payable (Rs.) 927.§l9
Late Payment Surcharge (Rs .) 46381 .93 I Amount with LPSC (Rs .) 974021 81II History Payment Hi story
IJ I\\ Id Bill from Date BIii to Dale No ol Days Amount(Rs) Un\\s R•celpl Id Am ou nttR•J D:1tc 74 ~70)26987 04 -MAY-2016 03.JUN-2018 30 73607 1 2604 74907 /059506 736071 00 02-JUL-2016 , , 0 onao31 °o 03-t,Pf'l -7018 04-MAY-201 8 31 6066 19 2143 749077025728 60661 9 00 30-MAY-20 18 /JOM976,c,J9 OP,1AR,?018 03-APR-201 6 33 338435 11 86 749077088106 338435.00 03-MAY-2018 1400 795J5224 31 -JAN-201 8 01-MAR-?01 8 29 291510 1023 74 9077051 428 291510,00 23-MAR-2018 /0'1071 )409?7 0·1-JAN-201 A 3 1.JAN-20 18 27 246320 1028 749077086187 24 6320 00 06-MAR-20 18
Important Message U-.. r- , ... , online boosteir not only mcreasus cllance of water con1a,n,nat1on but also increases !ho llill Please do not use onlme boos ter
-..:..2:. Delhi Jal Board
-7 ?\"' Bill Payment Counter Foil (9--=-:-=:___:.. 1::rfTT! ~,==-t~:i'
""" ~ ~ ;:fu 31)·1
New KNO 7,190770000 Name THE MEDICAL SUPDT (GOVT Bill No, 749077065344 I OF NC T )
B111 Date 10-JUL-20 18 Bill Due Date 27-JUL-20 18 Bill Amoun t (Rs.) 927639
Bil l Amount with LPSC (Rs .): 974021 Payme nt Dale/Amount Paid(Rs.) Cash/Cheque No./0D No .: )
ll 11 Jlllll II. U II• 11:IIJ ll llll lJl!~lmll!ll ll ll~U IIDl!il:ll ll1ill· Name of Bank / Branch r
I I Srn·,co Cycle ZALL Service Route 1 Route Sequence I 92 - -
WEATHER:
ENERGY CONSERVATION AND
BUILDING CODE
Bh
agw
an
Ma
ha
vir H
osp
ital
ASSUMPTIONS:
S. NO. MODEL
INPUT
PARAMETER
S
PROPOSED CASE
1. Exterior Wall
Construction240 mm AAC Block
(U-Value = 0.67 W/m²·°C)
2. Roof
Construction
240mm RCC slab with 120mm Brick Bat Coba
(U – Value = 2.4 W/m²·K)
3. Glazing For Residential : U - factor: 5.6 W/m² mK SHGC : 0.25
4. Shading devices Shading Devices - As per design
5. Lighting Power
Density
[As per ECBC Standard]
Spaces: 7.5 w/sq.m.
Kitchen: 12.9 W/sq.m.
Toilet : 1.5 W/sq.m.
Corriodor : 4.32 W/sq.m. (20% Reduction in common
spaces)
Stairs : 5.2 W/sq.m. (20% Reduction in common spaces)
Parking : 1.76 W/sq.m. (20% Reduction in common
spaces)
ENERGY CONSERVATION AND
BUILDING CODE
Bh
agw
an
Ma
ha
vir H
osp
ital
ASSUMPTIONS: S. NO. MODEL
INPUT
PARAMETER
S
PROPOSED CASE
9 Occupancy
Sensors
Provided
10 Daylight
Sensors
Provided
11 HVAC System
TypeAir Cooled Unitary
Packaged Terminal Air Conditioner
12 Cooling
EquipmentCategory: PTAC
COP : 3.52
13 Coil Capacity Cooling Coil Capacity : 100
Heating Coil Capacity : 100
14 Heating
Equipment
Electric Resistance
15 Base Utility Type: Elevators
Hourly Consumption: 60.0 kW
16 Utility Rates 5.25 Rs/ kWH
ENERGY CONSERVATION AND
BUILDING CODE
Bh
agw
an
Ma
ha
vir H
osp
ital
CONCLUSIONS:
• Criteria 8
- 7Points are being achieved in Criteria 8 due to achievement of benchmark
Energy Performance Index and EPI reduction of 48.7% over the base case.
Percentage Energy Performance Index Points
10% reduction from benchmark (Mandatory) 2
20% reduction from benchmark 3
30% reduction from benchmark 5
40% reduction from benchmark 7
50% reduction from benchmark 10
ENERGY CONSERVATION AND
BUILDING CODE
Bh
agw
an
Ma
ha
vir H
osp
ital
1) ECM’S
2) Envelope Details
3) Sectional Details
4) Schedules
5) External Lighting Calculation
ANNEXURE:
ENERGY CONSERVATION AND
BUILDING CODE
Bh
agw
an
Ma
ha
vir H
osp
ital
ENERGY CONSERVATIVE METHODS (ECM’S):
The proposed building achieves energy reduction by following
ECM’s
1. Efficient HVAC systems.
Residential Area – PTAC COP 3.5
2. Good envelope properties for wall, Roof and Glazing
Wall - 240 mm AAC Block (U-Value = 0.67 W/m²·°C)
Roof - 150mm RCC slab with 120mm Brick Bat
(U – Value = 2.2 W/m²·)
Glazing - U value for Residential = 1.6 W/m²·°C, VLT =
33%
3. Shading devices – As per Design.
ENERGY CONSERVATION AND
BUILDING CODE
Bh
agw
an
Ma
ha
vir H
osp
ital
ENVELOPE DETAILS:
WALLS
ROOF
GLASS For Residential : U - factor: 5.6 W/m² KSHGC: 0.82
Autoclaved Aerated Concrete Blocks (AAC)
Material DescriptionThickness
(mm)Conductivity (w/m.c)
Resistance (m2.C/W)
Outside Surface Resist. 0.059
External Plaster (Cement plaster, sand
aggregate)16 0.72 0.027777778
AAC Block 240 0.17 1.212
Internal Plaster (Gypsum plaster, sand
aggregate)12 0.22 0.063636364
Inside Surface Resist. 0.121
R-Value 1.48U-Value 0.674
Roof
Material DescriptionThickness
(mm)Conductivity (w/m.c)
Resistance (m2.C/W)
Outside Surface Resist. 0.05864
China Mosaic 50 1.5996 0.031257814
20mm Mortar 20 0.72702 0.02750956
40mm Screed 40 0.72 0.055555556
40mm Screed 40 0.72 0.055555556
Brick Bat Coba 120 0.811 0.147965475
150mm RCC 150 1.4 0.107142857
Inside Surface Resist. 0.12063
R-Value 0.60U-Value 2.2
ENERGY CONSERVATION AND
BUILDING CODE
Bh
agw
an
Ma
ha
vir H
osp
ital
ECBC COMPLIANCES. NO. MODEL INPUT
PARAMETERS
PROPOSED CASE
1. Exterior Wall Construction 240 mm AAC Block (U-Value = 0.67 W/m²·°C)
2. Roof Construction (Hall) 240mm RCC slab with 120mm Brick Bat Coba
(U – Value = 2.2 W/m² K)
3. Glazing Glazing properties: DGU: U - factor: 5.6 W/m²·mK SHGC : 0.82
4. Shading devices Shading Devices - As per design
5 Occupancy Sensors Provided
6 Daylight Sensors Provided
7 HVAC System Type Water Cooled Central Plant
8 Cooling Equipment Water Cooled Centrifugal Chiller , COP : 6.3
9 Coil Capacity Cooling Coil Capacity : 100
Heating Coil Capacity : 100
10 Heating Equipment Electric Resistance
11 Base Utility Type: Elevators ,Hourly Consumption: 60.0 kW
12 Utility Rates 5.25 Rs/ kWH
13 Solar Water heating Solar Cells –
A minimum of 20% of hot water required will be requirement will be met by solar
cells
13 Renewable Energy A total of 1.5% of the annual power consumption, will be met by solar energy
(i.e 25kVA)
Bh
agw
an
Ma
ha
vir H
osp
ital