+ All Categories
Home > Documents > showkat12

showkat12

Date post: 14-Apr-2018
Category:
Upload: showki-wani
View: 214 times
Download: 0 times
Share this document with a friend

of 19

Transcript
  • 7/27/2019 showkat12

    1/19

    1

    LOR Outline Methodology & Construction Logistics

    KHP Cancer Centre at Guys

    Outline Construction Method Statement

    Contents:

    1.0Introduction2.0Hoarding3.0Contractors Vehicle Access Route4.0Traffic Management5.0Vehicle Movements6.0Craneage7.0Programme & Site Operations8.0Construction Methodology9.0Environmental Management

    Appendices

    Appendix A Health & Welfare Facilities

    Appendix B Logistics Drawings

    Appendix C Projected Vehicle Movement Chart

    Appendix D Demolition Outline Method Statement

    Appendix E Substructure & Superstructure Methodology

    Appendix F Contents of Environmental Management Plan

  • 7/27/2019 showkat12

    2/19

    2

    LOR Outline Methodology & Construction Logistics

    1.0 Introduction

    1.1 The construction of the new KHP Cancer Centre at Guys Hospital will take place from

    January 2013 to the autumn of 2015, a period of almost three years including enabling work

    for the demolition of existing buildings and period for archaeological evaluation.

    1.2 The sequence of activities described below is based on a construction programme led by

    necessity to meet an operational opening in the spring of 2016. Planning approval for the

    Cancer Centre is sought from the Council in October 2012, allowing a full contract to be

    awarded by Guys and St. Thomas NHS Foundation Trust (the Trust) for this new facility by

    the end of January 2013.

    1.3 Prior to award of the full contract it is envisaged an Enabling Contract will be awarded for

    demolition of the existing Bloomfield Clinic and Newcomen Centre, currently occupying the

    site. This enabling work will provide the opportunity within the project timetable to evaluate

    any further potential for archaeological remains within the site by the Council, prior to

    development of the Cancer Centre.

    1.4 Laing ORourke currently share developing logistics material and attend coordination

    meetings with the Trust to liaise with other main Contractors whose work is scheduled to

    coincide with the proposed new Cancer Centre. Balfour Beattys work on Guys Tower will be

    on-going for the first 10 months of the Cancer Centre programme. Additionally Laing

    ORourke will liaise and attend meetings with the Traffic Liaison Group and Bankside &

    London Bridge Logistics Group.

    1.5 Laing ORourke is very aware that the surrounding area has been subject to redevelopment

    for a number of years. This can lead to construction activities causing interference to the

    everyday lives of people that live and work close by. A detailed construction methodstatement will be developed and agreed with the council prior to any works commencing.

    This will include covering the following issues that will help alleviate and minimise the

    impact of constructing the new facilities:

    LOR will register with and be part of the Considerate Constructors Scheme for thisproject, embracing requirements to achieve maximum credits where feasible under the

    main assessment headings including; consideration, the environment, cleanliness, good

    neighbour, respectfulness, safety, responsibility, and accountability. LOR has actively

    and enthusiastically supported CCS on many schemes with LOR winning 19 awards for its

    approach and performance already in 2012.

    A neighbourhood liaison officer will be appointed who will be the chief point of contactwith the local community. Leaflet drops will be regularly posted within the local

    community to keep neighbours informed regarding the progress of the work, special

    operations that are taking place and any specific deliveries requiring traffic and

    pedestrian management.

    A clear traffic management plan will be developed in line with the proposals set out inthis outline plan this will include holding delivery vehicles away from the construction

    area until access is available. In developing the plans so far, access arrangements have

    been tested to ensure the vehicles that are intended for use can get to the site easily

    without causing obstruction to traffic or pedestrians. Traffic will be managed carefully toavoid nuisance for the local community, particularly residents and local businesses.

  • 7/27/2019 showkat12

    3/19

    3

    LOR Outline Methodology & Construction Logistics

    Temporary Construction Health & Welfare facilities for the main works are to beaccommodated within the Service Yard to the east of Munro House. Please refer to

    Appendix A. Site Management accommodation is provided within the adjacent Borough

    Wing of main the hospital.

    1.6 All logistics drawings depicted in the text are also included in Appendix A at larger scale for

    further clarity.

    2.0 Hoarding

    2.1 In order to safely segregate the on site operations from the adjacent area we will erect a

    perimeter hoarding around the outside of the site for the duration of our works on site.

    2.2 The hoarding will be solid, constructed of plywood which will be decorated and lit. To allow

    vehicles to safely enter and exit the site it will extend partially into the roadway of

    Snowsfields and of Great Maze Pond, with manned vehicle access gates positioned in

    appropriate locations. Separate pedestrian access gates will also be provided, segregating

    vehicle movements and pedestrians to ensure the safety of site operations and non-

    construction related pedestrians using Snowsfield.

    2.3 Vehicles will predominantly enter the site through the eastern gate in the hoarding on

    Snowsfield and once unloaded exit the site through gates at the western end. Non-site

    traffic will be able to continue their journeys outside the line of the hoarding. Vehicle

    deliveries will also be able to access site through gates at the western end of the site

    hoarding on Snowsfields to the area south of the tower crane on the West side of the site.

    2.4 Clear signage and designated crossing points will identify the safe pedestrian routes that will

    be maintained around the site as part of the co-ordinated traffic control measures that are

    proposed.

    2.5 The site hoarding line is indicated in fig 1, (also drawing LOR-GST-V4-00-02 in Appendix B).

  • 7/27/2019 showkat12

    4/19

    4

    LOR Outline Methodology & Construction Logistics

    Fig 1 plan showing proposed hoarding and delivery vehicle access

    3.0 Contractors Vehicular Access Route

    Fig 2 proposed vehicle access route to and from the construction site

  • 7/27/2019 showkat12

    5/19

    5

    LOR Outline Methodology & Construction Logistics

    3.1 LOR has reviewed the local road layout and identified a route for all deliveries to site to

    follow. In the selection of this route and its associated traffic control measures. Consultation

    has taken place with the Council Highways department. We have prioritised the safety of

    pedestrians and other road users, and identified a scheme that will minimise disruption to

    the local area and allow delivery vehicles to access in the most efficient manner, to shortenthe construction programme and thereby minimise potential nuisance for the local

    community

    3.2 Principally, material delivery access will approach site from the east, from Druid Street and

    into Snowsfields. Vehicles will leave the area via Crosby Row to the south (see fig 2).

    3.3 In order to minimise the risk of disruption to traffic this access route will operate most

    efficiently by extending the one way designation of Snowsfields (east to west) from Weston

    Street to the Great Maze Pond junction (it is already one-way in this direction to the east of

    Weston Street).

    3.4 In order to limit any potential traffic congestion at the Great Maze Pond junction it is also

    proposed to designate Crosby Row as one way (north to south) for the duration of the

    construction works, and to operate a temporary traffic control system (traffic lights) at this

    junction.

    3.5 This access route will be incorporated within all material orders placed for the project and all

    will be actively encouraged to make use of it. By adopting a single route across the project

    material deliveries can be organised to reduce time at site and help avoid congestion in the

    local area. This strategy has also been designed in consultation with the Council Highways

    department.

  • 7/27/2019 showkat12

    6/19

    6

    LOR Outline Methodology & Construction Logistics

    4.0 Traffic Management

    4.1 Our proposed Traffic Management scheme would introduce a temporary 2 way traffic light

    system to control traffic at the Great Maze Pond / Snowsfields junction. (See fig 3 /Drawing

    No L1140)

    Fig 3Proposed Traffic management system

  • 7/27/2019 showkat12

    7/19

    7

    LOR Outline Methodology & Construction Logistics

    4.2 Our preference is for both Snowsfields and Crosby Row to be designated as one way streets

    throughout the duration of the works on site, with a 2-way traffic control system required

    including an over-ride for our gateman to allow vehicles into and out from the site.

    Fig 4

    Wider operation of proposed Traffic Management system

  • 7/27/2019 showkat12

    8/19

    8

    LOR Outline Methodology & Construction Logistics

    4.3 Parking restrictions will need to be managed at the northern end of Crosby Row where

    disabled badge holders are currently able to park on the double yellow lines in that area and

    to Great Maze Pond.

    4.4 Provision for emergency vehicles and fixed bed lorries serving the Hospital and Balfour

    Beatty site, up to 7.5t turning into and out of Great Maze Pond from Snowsfields would bemaintained as indicated on fig 5 (also drawing LOR-GST-V4-00-03 in Appendix B).

    Fig 5 Access arranagments for delivery and emergency vehicles to Great Maze Pond

  • 7/27/2019 showkat12

    9/19

    9

    LOR Outline Methodology & Construction Logistics

    5.0 Vehicle Movements

    5.1 Delivery vehicles will be able to access the site through gates in the hoarding on Great Maze

    Pond or via the gates on Snowsfields (see fig 6).

    5.2 When in operation all gates will have traffic management marshals to control vehiclemovements into and away from site.

    5.3 Laing ORourke will manage traffic and pedestrians during these deliveries. A Site Traffic

    Management Plan will be developed post consent and agreed with the Council prior to

    construction commencing. This will detail the control of deliveries, and site compound

    arrangements to minimise potential of nuisance for local residents.

    .

    Fig 6 VehicleMovements into and away from site

    5.4 Many elements of the build will be pre-fabricated away from the site thus reducing the

    number of vehicles deliveries required to access the site. For instance, the main Plant Tower

    at the rear of the building will be delivered in fully fitted out sections as possible, with faade

    glazing and cladding. The external balconies will also be lifted into position as complete

    units.

    5.5 The anticipated main delivery vehicle movements during the construction have been

    assessed. This is identified in the attached Projected Vehicle Movements Chart at Appendix

    B.

  • 7/27/2019 showkat12

    10/19

    10

    LOR Outline Methodology & Construction Logistics

    5.6 Deliveries to site will be managed by use of a co-ordinated web-based system (the Juggler

    System) which will schedule deliveries to and from site. The success and effectiveness of

    such a system has been proven on other Central London Laing ORourke projects such as the

    Cheese Grater and the Crick. Operating with this system allows an effective just-in-time

    strategy to be adopted, smoothing the flow of materials and delivering usable quantities totrade contractors on site whilst eliminating queues of delivery vehicles and the associated

    congestion at the site gate. As well as being extremely efficient, this also minimises potential

    for nuisance to the local community.

    5.7 In addition, to avoid site congestion vehicles en-route to site will be in regular contact to

    ensure that their delivery slot is running to schedule. If there are any anticipated delays, the

    vehicle will park at an agreed holding point away from site, such as London Gateway services

    and await call off into site.

    6.0 Craneage

    6.1 Two tower cranes will be necessary to construct the building;

    i) CT1 - Comedil CTL260, height 60.4m, jib length 40mii) CT2 - Comedil CTL280, height 72.4m, jib length 45m

    6.2 Both cranes will be positioned as shown on the Tower Cranes Lifting Capacity see fig 7

    (also drawing LOR-GST-4-00-01 in Appendix B). A temporary road closure (estimated

    duration of 1 week) will be necessary in Great Maze Pond and in Snowsfields to position a

    large mobile crane for the erection and dismantling of CT1 and CT2

  • 7/27/2019 showkat12

    11/19

    11

    LOR Outline Methodology & Construction Logistics

    .

    Fig 7Proposed tower crane radiia

    6.3 Over-sailing permission (in non-load carrying state) will be required for the buildings

    opposite TC1 and the multi-storey car park opposite TC2. The out of service jib radii are

    shown for both cranes. The cranes will be over-sailing in a non-load state.

  • 7/27/2019 showkat12

    12/19

    12

    LOR Outline Methodology & Construction Logistics

    7.0 Programme and Site Operations

    7.1 Demolition

    7.1.1 Demolition is scheduled to commence in January 2013 and be complete by April 2013. The

    demolition process will include ground floor slab removal and the site ground level will bereduced by approximately 600mm. Existing foundations encountered which are founded

    below this zone will be left for a later phase of the works. Demolition work will require the

    removal and diversion of services, including those in the area of the Scheduled Ancient

    Monument. Again, this will be done in a way to minimise potential for any disruption and

    nuisance to the local community. Please refer to the Demolition Outline Method Statement

    at Appendix D for further details.

    7.2 Ground Works and Archaeological Strategy

    7.2.1 Clear access will be provided for Southwark Archaeology to carry out investigations once the

    existing buildings have been removed. After the archaeological evaluation has taken place itis intended the main contract work is commenced beginning with the removal of existing

    foundations and basements.

    7.2.2 Substructure work including piling operations, new basement construction and extensive

    piling operations will run through to the autumn. During this period the bridging structure

    will be constructed over the Scheduled Ancient Monument which will ensure the roman

    boat is protected and not subjected to any load from the new building. This will also allow

    the boat to be removed in the future if necessary.

    7.2.3 Tower Crane 2 (TC2) will be erected in July 2013 and Tower Crane 1 (TC1) erected by

    October 2013. Each crane will be positioned on a piled foundation structure minimising thesize of foundation above ground and interference with the pedestrian zone particularly in

    Great Maze Pond

    7.3 Superstructure

    7.3.1 The concrete frame forming the superstructure of the building will be commenced in

    December 2013 and take approximately six months. Each floor is formed using pre-cast floor

    lattice units with in-situ concrete then poured once floor units are in position. All columns

    will be off site manufactured components, lifted into position. This will allow a quicker

    construction process and will mean less disruption from vehicles for neighbours.

    7.3.2 Once the building structure is up to level 6 the installation of unitised cladding forming the

    fenestration to the building will commence at level 2. The ground to first floor cladding is left

    off to allow access and avoid damage at this stage. Cladding operations will take

    approximately eight months.

    7.3.3 The installation of balconies will commence several levels below the ongoing cladding

    installation activity. Balconies will be installed at a rate of two units per day. It is proposed to

    use a temporary support frame to allow the delivery lorries to be quickly unloaded. Each

    balcony and support frame would be lifted to an upper floor for programmed installation.

  • 7/27/2019 showkat12

    13/19

    13

    LOR Outline Methodology & Construction Logistics

    7.3.4 The modularised Plant Tower will be delivered and installed over a four month period

    commencing in February 2014. Each level of the Tower will be delivered in four separate

    units.

    7.3.5 Internal fit-out work will commence mid 2014 including plant and equipment installations,

    followed by testing and commissioning. The building will be complete by the autumn of2015.

    8.0 Construction Methodology

    8.1 Further detail of specific construction operations can be found in the Substructure &

    Superstructure Methodology document at Appendix E, covering:

    Piling Basement Excavation Drainage Basement Slab Construction Columns & Walls Ground Floor Slab Superstructure

    9.0 Environmental Management

    9.1 An Environmental Management Plan for the project is being developed. The full detail will

    be developed post consent and agreed with the Council prior to construction commencing.

    The plan will include:

    Site Waste Management Plan Air Quality and Dust Management Plan Noise and Vibration Management PlanThe contents of the developing EMP plan is included at Appendix C.

  • 7/27/2019 showkat12

    14/19

    14

    LOR Outline Methodology & Construction Logistics

    Appendix A

    Health & Welfare Facilities

  • 7/27/2019 showkat12

    15/19

    15

    LOR Outline Methodology & Construction Logistics

    Appendix B

    Logistics Drawings

  • 7/27/2019 showkat12

    16/19

    16

    LOR Outline Methodology & Construction Logistics

    Appendix C

    Projected Vehicle Movements Chart

    This chart depicts the total projected construction vehicle movements throughout the demolition

    and construction period. Movements will include removal vehicles taking away demolition and

    excavated material and all deliveries, including fixed bed and articulated vehicles. The chart is

    illustrated to show the different phases of the work.

    Appendix D

    Demolition Outline Method Statement

  • 7/27/2019 showkat12

    17/19

    17

    LOR Outline Methodology & Construction Logistics

    Appendix E

    Substructure & Superstructure Methodology

  • 7/27/2019 showkat12

    18/19

    18

    LOR Outline Methodology & Construction Logistics

    Appendix F

    Draft Contents - Environmental Management Plan

    CONTENTS

    1. Environmental Policies, Strategy and Scope1.1 Environmental Policies1.2 Laing ORourke Strategy and Approach

    1.3 Scope of Works

    1.4 Environmental Plan Scope

    1.5 Environmental Representatives and Roles

    1.6 Project Environmental Objectives and Targets

    2. Project Specific Legislation and Client Requirements2.1Client BREEAM and Sustainability Requirements

    2.1.1 BREEAM2.1.2 Responsible Sourcing2.1.3 Building User Guide2.1.4 Green Guide2.1.5 Considerate Constructors2.1.6 Sustainable Timber2.1.7 Monitoring Environmental Impacts2.1.8 Site Waste Management Plan and Waste Targets2.1.9 Ecological Value/Enhancing Ecology/Biodiversity2.1.10 Other RequirementsAir Permeability/EPCs/Noise & vibration2.1.11 Materials Procurement (VOCs)

    2.2 Project Specific Planning / Legislation and Permits3. Key Environment Plan Documents

    3.1 Initial Project Assessment (IPA)3.2 Aspects and Impacts Control Register (AIR)3.3 Site Waste Management Plan (SWMP)

    4. Environmental Emergency Planning4.1 Emergency Contacts4.2 Safety Hazards4.3 Safety Guidelines4.4 Response Procedure4.5 Flooding4.6 High Winds Incidents4.7 Disturbance / Damage to protected Species4.8 Leaks and Spills

    4.8.1 Light product spills on concrete/asphalt (less than one drum)4.8.2 Product spills on concrete/asphalt (up to ten drums)4.8.3 Light product spills on land/soil

    4.9Disposal of contaminated materials (liquid and solid)

  • 7/27/2019 showkat12

    19/19

    19

    LOR Outline Methodology & Construction Logistics

    5. Reporting, Auditing and Inspections5.1Head Office Reporting5.2Environmental Auditing5.3Non Conformance, Corrective and Preventative Actions5.4Environmental Consultation Records5.5Inspections and monitoring5.6Specialist Monitoring Equipment and Calibration5.7Complaints Register and Reporting5.8Environmental Incident Reporting

    6. Training and Competence6.1Toolbox Talks, Induction and other training6.2Environmental Instruction / Operational Control6.3Communication

    7. Corporate Responsibility7.1 CR Challenge7.2 Construction skills