+ All Categories
Home > Documents > Shubham Reportmn,mn

Shubham Reportmn,mn

Date post: 02-Apr-2018
Category:
Upload: ajit-jain
View: 226 times
Download: 0 times
Share this document with a friend

of 52

Transcript
  • 7/27/2019 Shubham Reportmn,mn

    1/52

    SUMMER TRAINING AT

    PANKI THERMAL POWER STATION

    PTPSKANPUR

    UPRVUNL

    SUBMITTED BY: SUBMITTED TO:

    SHAILENDRA PRATAP SINGH Mr. T.C.GUPTA

    B.TECH, 3rd YEAR EXECUTIVE ENGINEER

    MECHANICAL ENGINEERING MAINTENANCE AND

    PLANNING DIVISON

    (MPD)PTPS,KANPUR(U.P)

    ROLL NO. : 1004540046

    1

  • 7/27/2019 Shubham Reportmn,mn

    2/52

    HARCOURT BUTLER TECHNOLOGICAL INSTITUTE,

    KANPUR-208002

    ACKNOWLEDGEMENT

    I am extremely thankful to the members of Panki Thermal Power Station

    (PTPS), Kanpur for their kind support and co-operation during my 4 weeks

    of training period.

    I would like to acknowledge Mr. T.C.Gupta(Assistant Engineer,

    Maintainance and Planning divison (MPD IV) for giving me this fortunate

    chance to learn the various applications of mechanical engineering in reallife. I express my sincere gratitude towards him for his wonderful guidance

    in the department and making me understand the various stages of thermal

    power generation.I also express my respectful gratitude towards all other

    engineers and technical staff at MPD for their help and guidance during my

    training period.

    Finally, I thank all those who have helped me in the success of my training

    program. They have added a lot to my knowledge.

    SHAILENDRA PRATAP SINGH

    B.Tech 3rd year

    Mechanical Engineering

    HBTI Kanpur

    2

  • 7/27/2019 Shubham Reportmn,mn

    3/52

    CERTIFICATE

    It is certified that SHAILENDRA PRATAP SINGH, student of 3rd B.Tech

    Mechanical Engineering H.B.T.I. Kanpur has worked on the Project on

    PTPS Kanpur under my guidance and supervision. He has shown sincere

    efforts and keen interest during preparation of this project report. My best

    wishes are with him, his efforts and his future endeavours.

    Mr. T.C.GUPTA

    Assistant Engineer

    MPD IV

    PTPS Kanpur

    3

  • 7/27/2019 Shubham Reportmn,mn

    4/52

    INDEX

    S. NO. CONTENTS PAGE NO.

    1.

    2.

    3.

    4.

    5.

    6.

    7.

    8.

    9.

    10.

    11.

    12.

    13.

    14.

    Acknowledgement

    Index

    Introduction

    Organisational Set-up

    Various divisions for effective working of PTPS

    Water Treatment Plant

    Boiler and Boiler auxiliaries system

    Oil Handling Plant

    Coal Handling Plant

    Milling System

    Coal firing system in the boiler furnace

    Details of Boiler at PTPSSpecifications of the boiler

    Steam generating units and auxiliaries

    Technical specifications of the Milling Plant and

    Fuel Firing System

    2

    4

    6

    8

    11

    13

    15

    15

    16

    17

    19

    2023

    25

    28

    4

  • 7/27/2019 Shubham Reportmn,mn

    5/52

    15.

    16.

    17.

    18.

    19.

    Turbine Maintenance Department (TMD)

    Compounding of the steam turbines

    Governing system of turbine

    Turbine protection testing

    Turbine oil pressure regulating system

    Specifications of 110 MW Turbine

    Important features of Turbine

    Electronic instruments useful for the plant

    Training in Electrical Maintenance Division (TMD)

    Rating of Transformers of Unit 3 and Unit 4Current Transformer (CT)

    Potential Transformer (PT)

    Generator and Exciter

    Introduction to Switch gears, Circuit Breakers and

    Relays

    Devices used for circuit breaking (making)

    Fuse and Iron Clad Switches

    Isolators

    Circuit BreakersThermal Relays

    Grid Substation

    Wave Trap

    Switch Yard

    Tracks for Transformer

    Control & Instrumentation Division

    Various instruments of the C & I department

    Turbo Supervisory equipments

    Water Pollution Control

    Air Pollution Control

    Conclusion

    30

    31

    31

    31

    32

    33

    34

    34

    35

    3536

    36

    37

    38

    38

    38

    38

    3942

    43

    44

    44

    44

    45

    45

    46

    4850

    52

    5

  • 7/27/2019 Shubham Reportmn,mn

    6/52

    INTRODUCTION

    In India there is a very long chain of thermal power project including the

    project in UP. Some of the power projects under Uttar Pradesh Rajya

    Vidyut Utpadan Nigam Ltd. (UPRVUNL) are as follows:

    S.No. Name of Power Project No. of Units Capacity(MW)

    1 Harduaganj A 3 90

    2 Harduaganj B 4 2103 Harduaganj C 3 230

    4 Panki, Kanpur 2 210

    5 Obra 8 550

    6 Obra ext. 5 1000

    7 Anpara 3 630

    8 Anpara ext. 2 1000

    9 Pariksha 2 220

    Panki Thermal Power Station:

    With the industrial development of Kanpur, a thermal power station was

    established at the banks of river Ganga, in the year 1923, which was known

    as Riverside Power House (RPH). In the year 1947, RPH was taken over

    by the Government of UP under the name of Kanpur Electricity Supply

    Administration (KESA). In 1962, RPH reached its maximum capacity of

    100 MW leaving no scope of future development. Government of India

    approved setting up of power station having capacity of 64 MW (2x32 MW).

    The new plant was inaugurated on 17 Sep 1968 by the Prime Minister, Smt.Indira Gandhi.

    In the year 1976, two units of 110 MW each were installed to meet the

    increasing power demand. These units were inaugurated on 30 Jun 1976, by

    the Chief Minister of UP, Mr. N.D.Tiwari.

    6

  • 7/27/2019 Shubham Reportmn,mn

    7/52

    At present 2x32 MW units are not operating due to not having the suitable

    Pollution control machinery. The Central government has commissioned a

    210 MW unit at Panki Power Station.

    At PTPS, 2x105 MW BHEL made coal fired turbo generating units are

    presently in operation. These 105 MW machines were manufactured,

    supplied and commissioned by M/s BHEL, during 1976-77 with features of

    reheating and regenerative feed heating. The Steam Generator is balanced

    draft, radiant, dry bottom, single drum, natural circulation, vertical water

    tube type construction with skin casing and semi direct type of firing system.

    Apart from the above 105 MW units, 2x32 MW Russia made turbo

    generating units were also installed at PTPS in 1967-68, however these units

    have become obsolete and permanently closed now after running for about

    30 years.

    Location:

    PTPS is located in the West Kanpur in between Kalpi Road & the famous

    Grand Trunk Road and is 16 km distant from the Kanpur Central Railway

    Station. It is situated on the banks of lower Ganga canal and is connected

    with the Panki railway station for the easy transportation of coal.

    Availability of Raw Material at PTPS:

    The main raw materials used in the plant are as follows:

    Raw Material Source

    Water Lower Ganga Canal

    Coal Jharia Mines of Coal India Ltd., Bihar

    Petroleum Products Indian Oil Corporation Ltd., Kanpur

    7

  • 7/27/2019 Shubham Reportmn,mn

    8/52

    ORGANISATIONAL SET-UP

    CHAIRMAN

    DIRECTORS

    GENERAL MANAGER

    DGM (1) DGM (2) DGM (3) DGM (4)

    Operation & Electrical Coal Handling Headquarters

    Maintenance Stare & Civil

    DGM(I)

    Operation Group Maintenance Group

    EE EE EE EE EE EE EEGP(A) GP(B) GB(C) GP(D) TMD BMD OPERATION

    GENERAL

    AE AE AE AE AE AEAE AE AE AE AE AE

    8

  • 7/27/2019 Shubham Reportmn,mn

    9/52

    AE AE AE AE AE AE OG1 OG2

    AE AE AE AE AE AE AE AE

    AE AE

    DGM (2) (ELECTRICAL)

    Control & EMD EDD Central Purchase

    Instrumentation Division

    EE EE EE EE

    AE AE AE AE AE AE AE AE AE AE AE AE AE AE

    AE

    DGM (3)

    EE EE EE Transport Central

    EFFI TRM Division Purchase Division Division

    AE AE AE EE AE

    AE AE

    AE

    9

  • 7/27/2019 Shubham Reportmn,mn

    10/52

    HQ

    Store Division Power House Dispensary Civil Maintenance Division

    AE AE AE AE AE AE

    AE AE

    ADMINISTRATIVE STRUCTURE OF PTPS

    Employee of factory : GM

    Circle officer : Superintending Engineer

    Divisional officer : Executive Engineer

    Sub-divisional officer : Assistant Engineer

    Staff : Operators, Technicians & 4

    th

    class employee

    The whole set up of management is known as a circle. The total number of

    employees in PTPS is 1536.

    10

  • 7/27/2019 Shubham Reportmn,mn

    11/52

    VARIOUS DIVISIONS FOR EFFICIENT WORKINGOF PTPS

    Water Treatment Plant (WTP):

    This division separates the physical and chemical impurities of water.

    Coal Handling Division (CHD):

    This division takes care of efficient supply of coal and oil fuel to the power

    plant.

    Boiler Maintenance Division (BMD):

    This division looks after the efficient working and performance of boiler, its

    mounting, its accessories, feed pump, milling system etc.

    Turbine Maintenance Division (TMD):

    This division looks after the efficient working of turbine and its accessories.

    Electrical Maintenance Division (EMD):

    This division takes care of the electrical networks and its elements in the

    power station.

    Control and Instrumentation Division (C & I):

    This division takes care of various instruments fitted in the power plants for

    controlling the generation of electricity.

    Electrical Distributors Division:

    This division looks after the distribution of produced electricity to the grid.

    Civil Maintenance Division:This division looks after the construction and maintenance of various

    structures in the power plant.

    Operation General Division (OG 1):

    This division takes care of the sanitation and cleaning etc of the power plant.

    11

  • 7/27/2019 Shubham Reportmn,mn

    12/52

    Operation General Division (OG 2):

    This division is responsible of the management of the power station. It deals

    with the salaries of employees, recording and sending data related to the

    performance of the power plant to the Head Office.

    Store and Purchase Division:

    This division deals with the storage and supply of various spare parts

    requires in the power house along with their purchase.

    Transportation Division:

    This division looks after the transportation of coal.

    12

  • 7/27/2019 Shubham Reportmn,mn

    13/52

    WATER TREATMENT PLANT

    The water treatment plant is required as the water from canal cannot be

    directly used in the boiler because it contains physical and chemical

    impurities which have an adverse effect on plant operation. The turbidity of

    this canal water is 80. The water used in the boiler is Demineralised water

    (i.e. DM water).

    Water from the canal is drawn by the pump house where large physical

    impurities are operated by a screen having a net. This water is converted into

    DM water in the following stages:

    Flculator Plant:

    In this plant the alum is added to water to precipitate dust particles in water.

    Aluminium in alum neutralizes charge dust particles and dust particles

    become very heavy and settle down. Bleaching powder and limestone is also

    added to remove temporary hardness along with chlorine (liquid), which

    removes bacteria and organic matter. Chlorine dosing is must during rainy

    days. The process of sedimentation is applied to remove heavier particles.

    Water is now stored in CST (Condensate Storage Tank).

    Note: PAC (Poly Aluminium Chloride) is used instead of alum, when the

    impurities in the canal water are more than a reasonable limit, especially

    during the rainy season.

    Clarifying Pump House:

    It consists of five clarifying pumps, four service water pump and two

    dividing pumps. Form the clarify pump house, the water goes to the

    condenser and the sand filter.

    Sand Filter:

    These stages are put across the flow of water so as to remove other

    suspended particles, if any. Now the turbidity of water is 2-3.

    13

  • 7/27/2019 Shubham Reportmn,mn

    14/52

    Activated Carbon Filter:

    This filter is employed for removal of bacteria and organic matter through

    oxidation. It uses anthracite coal for filter. The turbidity of the water

    obtained here is 1-2.

    Cation exchanger:

    At this stage, the ions (Ca, Mg, Fe) are absorbed by an ion exchange method

    liberating H+ ions. HCl and resin (-ve) are principal ingredients of chemical

    filters present here. Here the hardness of the water is removed.

    Weak base anion exchanger:

    Here the weak bases (acetic acid, carboxylic acid etc.) are absorbed by

    carefully releasing OH- ions.

    Degasser:

    Here the gases like CO2, O2 and H2 are removed.

    Strong base anion exchanger:

    Here a resin is used which absorbs strong anions like SO 42-, Cl2-, phosphate

    ion, silica etc. and releases OH-.

    Mixed Bed Exchanger:

    Here the remaining ions are extracted through both cation and anion resin.

    The demineralised water is now ready which has the following

    specifications:

    Conductivity : 0.004 siemens/cm2

    pH : 8.5-9

    The desired pH in clear water is between 8.5 and 9. Phosphate dosing is

    done at the end for this purpose. The total capacity of water treatment plant

    is to provide 60 tonnes of water per hour.

    14

  • 7/27/2019 Shubham Reportmn,mn

    15/52

  • 7/27/2019 Shubham Reportmn,mn

    16/52

    Low sulphur High stock oil (LSHS)

    COAL HANDLING PLANT

    A simple schematic diagram of the coal handling plant of PTPS is as shown.

    The raw coal (bituminous coal) is brought to the power plant by the means

    of railways. The wagon tripplers transfer it into the wagon triple hoppers

    (WTH) which empties the coal from the wagons. The wagon capacity is

    around 50-60 tonnes. From WTH the coal is transferred to the vibrators, it

    separates the stone boulders from the coal from where it is then passed to the

    conveyors. The length of the belt is 1000m and speed is approximately 7.2

    km/hr.

    The conveyor carries around 500 tonnes of coal per hour to crusher house

    where the big pieces of coal are separated in a screen and sent to crusher

    through conveyor from where the crushed pieces are transferred to other

    conveyors. These are smaller particles of size ranging from 20 mm to 40 mm

    or below. Then conveyor takes coal from where trippler transfer the coal to

    raw coal bunker (RCB).

    There are two suspension magnets present over conveyor just before crusher

    house. These magnets remove any metallic impurities in the coal moving on

    the conveyor belt.

    The whole process described is valid when the coal brought by the trains

    directly feed the RCB. When there is no train available then the coal comes

    from the coal yard. The coal from the coal yard is dropped with the help of

    bulldozers in the hopper from where it is transferred to the conveyors and

    the process is repeated to carry the coal to the RCB.

    When RCBs are full then the coal coming from the wagon trippler hopper,

    after being crushed in the crusher house is transferred to conveyor which

    carries it to the stacker that spreads the coal in the coal yard with the help of

    boom conveyor. The boom conveyor can rotate 360 times on the stacker

    which moves itself on a track laid over the length of the coal yard.

    16

  • 7/27/2019 Shubham Reportmn,mn

    17/52

    Thus the coal gets stored in the coal yard, which can be used when the train

    carrying coal are unavailable. In PTPS, more than one lakh tonnes of coal

    can be stored in coal yard.

    The coal handling plant also takes care of the storage purification and supply

    of fuel oil, which is used for initial lighting up of the boiler furnace, and

    generation of constant temperature in the furnace during normal operation.

    Mode of operation in Coal Handling Plant:

    1. Bunker filling operation: Coal flow from wagon trippler to boiler

    house bunker

    2. Reclaim operation: Coal flow from stockyard to boiler house bunker

    3. Stacking: Coal flow from wagon trippler to stockyard

    4. Bunker filling and reclaiming simultaneously

    MILLING SYSTEM

    A layout of the milling system at the PTPS is as shown in the figure. In a

    thermal power plant pulverized coal is used for producing heat in the

    furnace. This is because the burning of this state of coal takes place

    completely and also there is lesser problem in ash handling. The coal pieces

    of size 20 mm to 40 mm are taken from the RCB and through raw coal chainfeeder (RCF) their coal pieces are fed to the ball mills. In the ball mills, there

    are steel balls of size 40, 50 and 60 mm and with a net weight of nearly 52

    tonnes. These mills rotate about their axis and this makes the balls collide

    with the coal pieces to break them into pulverized form.

    Ball mills are provided with flue gases at about 300o C that helps drying the

    coal and raises its temperature to about 85-90o C. There is a fan in the circuit

    called as vapour fan, this fan solves three purposes:

    It creates vacuum in the circuit so that the pulverised coal is sucked

    out of ball mill with air.

    If due to any reasons the supply of coal to the ball mill is broken and

    flue gasses are continuously supplied then the temperature of the ball

    mill will rise excessively high. To avoid this vapour fan thus

    recirculates pulverized coal to the ball mill and so temperature of the

    ball mill comes down.

    17

  • 7/27/2019 Shubham Reportmn,mn

    18/52

    For cooling dry cold air is also supplied while recirculation. Cooling

    is must because if the temperature becomes higher enough then the

    coal can catch fire.

    Micro particles of coal are directly sucked by the vapour fan with air andsupplied to the furnace chamber for combustion. The pulverised coal from

    the ball mills is passed through a classifier that acts as a screen separating

    out the bigger particles from the pulverized coal and returning them back to

    the ball mill. From the classifiers the coal goes to the cyclone separators

    where coal particles are separated from the air. The vapour fan pumps out

    the air and the coal particles go to warm conveyor via turnicates. The warm

    conveyor delivers the coal to be stored in pulverized coal bunker (PCB).

    From PCB the coal goes to pulverized coal feeder that feeds the coal to the

    furnace with the help of primary air fan (PAF). This fan takes air from

    primary air heater and pushes the pulverized coal from all four corners of thechamber.

    Secondary air fan (SAF) supplies hot air (taken from secondary air heater) to

    the chamber for combusting the coal properly. Coal is supplied from the all

    sides to have a uniform and complete combustion.

    In PTPS there are three ball mills and four PCBs for each unit of 110 MW.

    From ball mill A, coal can be directly given to PCB A and PCB B via

    turnicates. Similarly from mill B to PCB B & PCB C and from mill Cto PCB C & PCB D. For any different combination of ball mill and from

    those stated above, warm conveyor is used.

    18

  • 7/27/2019 Shubham Reportmn,mn

    19/52

    COAL FIRING SYSTEM IN THE BOILER FURNACE

    The steam generating unit has been designed for firing coal and oil at low

    loads for stablisation. The fuel firing equipment is designed such that therated parameters would be reached when the fuel is fired. The burners are

    located at corners of the furnace tangential to the imaginary circles, having

    their centers co-axial with the center of the combustion chamber. At each

    corner, there are nine compartments arranged as mentioned below.

    There are four coal burner nozzles, three vapour burners and two oil burners

    at each corner. The four coal nozzles are provided with air packets, which

    flow around the coal fuel system. Each of the engine compartments is

    provided with independent air dampers. All the adjustable tips are of

    stainless steel to withstand high temperature.

    Coal Bunkers:

    Total bunkers : 16

    Manufacturer : BHEL

    Capacity : 3.65 ton/hr

    Type : Tilting tangentially

    Pulverised coal fired boiler:

    With the increase in the size of the turbines, the boiler work also increases.They have to supply steam at a high temperature & pressure and in a bulk

    quantity. In such type of the boiler coal is fired in pulverized form, which

    has the following advantages:

    1. Unlimited output capacity.

    2. Even low grade coal can be burned.

    3. Even very fine boiler output control is possible.

    4. High efficiency.

    5. Less possibility if unburned coal.

    Fuel Oil System:

    In the pulverized fuel fired oil boiler firing is used for safe and quick start up

    of boiler ignition of pulverized coal and to bring stability to coal flame under

    low output with eight flexible oil guns, two in each corner. The oil guns are

    located at the top and bottom of secondary air nozzles and in between coal

    nozzles. The oil guns are of pressure atomizing type.

    19

  • 7/27/2019 Shubham Reportmn,mn

    20/52

    DETAILS OF BOILER AT PTPS

    20

  • 7/27/2019 Shubham Reportmn,mn

    21/52

    A boiler is a closed vessel in which water under pressure is converted into

    steam. It is one of the major components of a power plant. It is always

    designed to transfer maximum amount of heat to the boiler water by all the

    three modes of transformer: convection, conduction and radiation. Boilers

    can be classified as water tube boiler and fire tube boiler.

    a. Fire tube boiler:

    In this type of boiler, products of combustion pass through tubes which

    are surrounded by water. Depending on whether the tubes are horizontal

    tube boilers they may be internally or externally fed. An internally fed boiler

    has grate and combustion chamber enclosed including furnace. The grate is

    separate and distinct from the boiler shell.

    A fire tube boiler is simple, compact and rugged in construction. Its initial

    cost is low. A vertical fire tube boiler occupies less floor space. However,

    they are economical only for low pressure and therefore available in small

    sizes having steam capacity of about 15,000 kg/hr.

    b. Water tube boiler:

    In this boiler, water flows inside the tubes and hot gases flow outside the

    tube. The tubes are interconnected to common water channels and to steam

    outlet. Water tube boilers are classified as vertical, horizontal and inclined.

    The number of drums may be one or more. The circulation of water in the

    boiler may be natural (due to difference in density between cold and hot

    water) or forced through the action pumps. Forced circulation has the

    advantages:

    1. Lesser weight of boiler and cheaper foundation.

    2. Lighter tubes.

    3. Freedom from scaling problems.

    4. Greater freedom in configuration of furnace, tubes etc.

    5. Uniform heating of all parts.6. Better control of temperature.

    7. Increased efficiency of boiler.

    8. Quick response to load changes.

    In view of all these modern boilers use forced circulation. However, forced

    circulation means higher investment, more costly maintenance and increase

    21

  • 7/27/2019 Shubham Reportmn,mn

    22/52

    in auxiliary power consumption. The unit is designed for minimum

    continuous value of 375 tonnes/hr, at a pressure of 135 kg/sq. cm and a

    temperature of 540o C. The reheat system steam flows at MCR. The feed

    water temperature of the MCR is 240o C. The unit is balanced draft radiant

    dry bolt on single drum, natural circulation, vertical tube type construction

    with casing and a single reheat system.

    The furnace is arranged for dry ash discharge and is filled with burners

    located at the four pipes. Each corner burner is supplied with coal, vapour,

    and oil filled secondary air components. The unit is provided with three ball

    pipes and arranged to operate with intermediate coal power.

    The steam super heaters consist of four stages which are ceiling, primary

    S/H, platen and final super heaters. The ceiling terms the root of furnace and

    horizontal pass and finishes as the rear wall of the second pass. The primarysuper heater is made up of horizontal bands located at the second pass while

    the platens are located at furnace exits. The portion above the furnace too

    encloses the super heaters. The control of super heater steam is achieved by

    two stages of spray attempration which are located before the platen super

    heater and the other located before the final super heater.

    The re-heaters are in two stages. First and triplex heat exchanges located at

    the second pass which absorbs heat from super heater a steam as well as

    from flue gases. In the second stage exists re-heater located in the horizontal

    pass as penitent tabular loop. Reheated steam temperature control valves and

    the other emergency conditions by an attemprator located in the cold reheat

    lines.

    In order to ensure reliable and continuous operation ample soot blow

    equipment is provided. There are start retractable steam soot blower

    provided at the top of the furnace fully retractable steam soot blowers are

    arranged for the horizontal re-heater and super heater in the rear pass. The

    steam soot blowers are electrically operated.

    SPECIFICATIONS OF THE BOILER

    22

  • 7/27/2019 Shubham Reportmn,mn

    23/52

    Manufacturer : BHEL

    Maximum continuous rating : 375 ton/hr

    Maximum rating without stabilization : 240 ton/hr

    Rated steam pressure at super heater outlet : 139 kg/sq. cm

    Rated steam temperature at upper heater outlet : 540o C

    Rated temperature of feed water at economizer inlet : 240o C

    Rated steam flow through reheater : 324 ton/hr

    Rated steam temperature at reheater inlet : 360o C

    Efficiency of the boiler : 86 %

    Design pressure of the boiler drum : 161 kg/sq. cm

    Design pressure of the reheater : 42 kg/sq. cm

    Motor for FD Fan:

    Type : EL Motor

    Rated output : 330 KWFull load current : 44 A

    Induced Draft Fans (ID FANS):

    It is a continuous type draft fan and its two units are used for each boiler.

    The type is BHEL oxiall-430-2240. The induced draught fan does the

    function of sucking the gas from the furnace, making the gas to flow through

    the various heating surfaces & dust collecting equipment and sending the

    gas out through the chimney with required velocity. The ID fan handles the

    hot flue gases and sends the fly ash causing rapid erosion of impeller;

    enough care is taken at the design stage to select the fan for the worst

    condition.

    Number : two per boiler

    Capacity : 367200 m3/hr

    Temperature of flue gases : 1215o C

    Speed : 990 rpm

    Motor for ID (Induced Draft) Fans:

    Type : EL motor

    Rated output : 440 KWFull load current : 127 A

    Fan design ratings:

    Capacity : 44.6x10 e-4 mm/hr

    Total head developed : 410 mm

    Maximum temperature of medium : 145o C

    23

  • 7/27/2019 Shubham Reportmn,mn

    24/52

    Specific weight of medium : 863 Cp/cm

    Fan speed : 990 rpm

    Fan direction of rotation : clockwise

    Blade type : laminated curved blade

    Type of regulation : inlet valve regulation

    Drive motor:

    Manufacturer : MEEP, Haridwar

    Frame size : 15-5-00-p

    Design : Codena

    Power:

    Rated : 1000 KW

    Actual power required : 740 KW

    Rated voltage : 6600No. of phases : 3

    Voltage & frequency:

    Full load rpm : 990 rpm

    Full load current : 104 A

    Full load frequency : 94 %

    Torque : 4.63

    Frequency : 50 Hz

    Terminal Connections:

    Type : star

    Number : 6

    Note: The 6 leads taken out in the terminal box and connected on 4 brushes,

    form a star.

    STEAM GENERATING UNITS AND AUXILIARIES

    24

  • 7/27/2019 Shubham Reportmn,mn

    25/52

    Supporting structure: It serves for arranging the suspending water wall

    system, steam super heaters, re-heaters, economizers, air pre-heaters,

    galleries insulation and sheet casing.

    25

  • 7/27/2019 Shubham Reportmn,mn

    26/52

    Galleries and stairways: These provide access for maintenance like root

    blowers, valve burners, dampers ant to various main & view holes.

    Boiler drum and drum internals: Boiler drum is made of alloy steel plate

    of thickness and has a diameter of 1800 mm. The drum is of fusion welded

    on hemispherical dished ends. The function of the drum internals is to

    reduce the dissolved solid content with the steam to a prescribed limit.

    Rough mountings: These contents of access doors into the combustion

    regions of super heater, economizers and air burners as well as observation

    pots, explosion doors etc. The rough mountings are made of cast iron or are

    of fabricated design.

    Water walls: The combustion chamber is formed of water wall tubes onfour side diameters 60.3 mm set, at a pitch of 52 mm. In the corner where

    the pulverized coal burners are located, the tubes are bent suitably to provide

    opening for the sending of the tilting tangential burners.

    Re-heaters: The steam re-heaters having a total surface area of 255.1 sq.

    mm are made of pendant and horizontal tabular loops and are in two stages.

    The first stage of horizontal tabular arrangements and the peripheral if

    tabular is used. The steam for super heater flows through bigger tubes

    outside diameter of 85 mm while the steam to be reheated flows outside the

    tube through bigger tubes outside with a diameter of 70 mm. The super

    heated steam from the triflux is drawn through three-way valve arranged in a

    connecting pipe between the outlet of platen super heater and inlet of final

    super heater. The second stage of super heater is suspended in the horizontal

    pass of the boiler as pendant tabular loops. The reheater tubes are welded to

    the inlet and exit heater.

    Economiser:

    The economizer with a heating surface of 4950 sq. cm made of steamless

    tabular loops. The tubes of outside diameter of 32 mm are welded by meansof stubs to the inlet and outlet heater. The heater and horizontal loops rest on

    supporting structure of second pass of the boiler with provision for free

    expansion. The economizer blocks are arranged, with a second pass of the

    heat recovery zone of the boiler so as to achieve recovery of heat in a very

    common economic manner.

    26

  • 7/27/2019 Shubham Reportmn,mn

    27/52

  • 7/27/2019 Shubham Reportmn,mn

    28/52

    inlet. The flue gases extraction ducting is made of alloy steel plate in view

    of the fact that the hot gases will be around nozzles.

    Soot Blower:

    Below root in the furnace a top region the super-heater a reheater zone and

    the economizer coils. Steam is used as the medium. The steam is tapped

    from the pulled of the plate super-heater and the system includes are on the

    reduction valves or safety valves. Four box type soot blowers at the trifler

    reason and simple feed type root blower for economizers are also provided.

    TECHNICAL SPECIFICATIONS OF THE MILLING

    PLANT AND FUEL FIRING SYSTEM

    Pulverising Mill:

    Type : drum mill 800/575

    Number of mills : three

    Rated capacity : 20 tonnes/hr.

    Type of drive : electric motor Speed : 990/990/171 and 170/175/170 rpm

    Motor capacity : 6030 KW, 6.6 KV

    Lubricating system:

    Discharge pump : 22 l/min

    Pressure of oil at pump : 80 psi

    Quality of lubricated oil reqd. /mill : 350 l

    Oil Cooler:Cooling water required : 7.5 com. /hr at 230o C

    Raw Coal Feeder:

    Type : chain feeder R600

    No. of boiler : three

    Type of drive : elect motor 7.5 KW

    28

  • 7/27/2019 Shubham Reportmn,mn

    29/52

    Coal Burner:

    Total no. of feeder : 16

    Manufacturer : BHEL

    Capacity : 3.65 ton/hr

    Type : tilting tangentially

    Oil Burners:

    Number per boiler : 8 mm to tier

    Type : manual with mechanized atomisation

    Capacity : 800 kg/hr

    Position of burner : at furnace corner

    Cyclone Separator:

    Type : SEA 1600/2Diameter of unit : 1600 mm

    Efficiency : 82%

    Vapour Fan:

    Type : DL-1600-60

    Type of inlet control : damper

    No. of inlet : one

    Runner : 1800 mm

    Speed : 1480 rpm

    Motor:

    Manufacturer : BHEL, Haridwar

    Type : DA 2014-64-67, TPEC

    Rated output : 630 KW, 230 rpm

    Rating : 6.6 KV, 3 phase, 50 Hz

    Weight : 9.76 tonnes

    Ball Mill:

    Mill capacity : 28 tonnes/hr Mill current : 64-68 A

    Coal consumption : 67 ton/hr for 110 MW

    Coal consumption in KW/hr : 0.58 kg

    Coal fineness : 200 mesh

    Classifiers:

    29

  • 7/27/2019 Shubham Reportmn,mn

    30/52

    Type : Raymond type 330, Raymond type 880

    No. of per boilers : 3

    Type of drive : electric motor, 7.5 KW (variable)

    Method of control : Vane control

    Range & efficiency : Adjustable

    TURBINE MAINTENANCE DEPARTMENT (TMD)

    The main works of this department are maintenance of turbine and look afterall the things related with turbine. The steam turbine has been used

    predominantly as mover in all thermal power stations. It is not likely to be

    replaced in the future. Turbines are mainly divided into three groups:

    Impulsive turbines

    Reaction turbines

    Impulsive-reaction turbines

    In both types of turbine, first the heat energy of the steam at high pressure is

    converted into kinetic energy passing through the nozzles. The turbines areclassified as impulsive in impulsive turbinate steam coming at a very high

    velocity through the fixed nozzle impinges on the blade fixed on the

    periphery of the rotor. In the reaction turbine the high pressure steam boiler

    is passed through the nozzle. When the steam comes out through these

    nozzles, the velocity of steam increases relative to rotation and this resulting

    force of steam on the nozzles give the rotating motion to the disc and shaft.

    30

  • 7/27/2019 Shubham Reportmn,mn

    31/52

    The shaft rotates in opposite direction of steam jet. In an impulsive reaction

    turbine the steam expands both in fixed and in moving blades continuously

    as it passes over them. Therefore, the pressure drop occurs gradually and

    continuously over both moving and fixed blades. For e.g. Parsons turbine.

    COMPOUNDING OF THE STEAM TURBINES

    If the entire pressure drop from boiler pressure to condenser pressure is

    carried out in a single stage nozzle, then the velocity of the steam entering

    into the turbine could be very high of the order of 1500 m/s. The turbine

    rotor velocity (blade velocity) will be very high of the order of 3000 rpm as

    it is directly proportional to the steam entering velocity. Such high rpm of

    turbine is not useful for practical purpose and a reduction gear is necessary

    between the turbine and external equipment (generator driven by theturbine). There is also a danger of structure failure of the blade due to

    excessive centrifugal stresses. Therefore the velocity of the blades is limited

    to 400 m/s. The velocity of the steam at the exit of the turbine is sufficiently

    high when single stage blades are used. This gives a considerable loss of

    kinetic energy (about 10-20 %). The compounding can solve the above

    mentioned difficulties associated with the single stage turbine. The

    combinations of the stages are known as compounding. There are three types

    of compounding which are generally done.

    a. Velocity compounding:

    In this type of compounding there is only one set of nozzles and two

    or more rows of moving blades. There is also a row of fixed blades in

    between the moving blades. The function of the fixed blades is only to

    direct the steam coming out from first moving row to the next moving

    row without altering pressure and velocity of the steam. The heat

    energy drop takes place only in the nozzle at the first stage and it

    converts into kinetic energy. The kinetic energy of the steam gained in

    the nozzles is successively used by rows of moving blades and finally

    exhausted from the last row of the blades on the turbine rotor. Aturbine working on this principle is known as velocity compounded

    impulse turbine. For e.g. Curtis turbine.

    b. Pressure compounding:

    A number of simple impulse turbine sets arranged in series is known

    as pressure compounding. In this arrangement, the turbine is provided

    31

  • 7/27/2019 Shubham Reportmn,mn

    32/52

    with one row of the fixed blades at the entry of each row of the fixed

    blades, which work as nozzle. For e.g. Rateau turbine.

    GOVERNING SYSTEM OF TURBINE

    1. Speed range is 2850 rpm to 3360 rpm corresponding to primary oil

    pressure of 2.17 to 2.99 atmosphere at oil temperature of 50o C (3000

    rpm corresponds to 2.38 atm primary oil pressure.)

    2. The non uniform changer (NUC) enables the exchanging of non

    uniformity continuously in the range of 3.5 to 5 %.

    3. Before start of increase of secondary oil pressure, safe oil pressure can

    be achieved by limiter only when the main relay is in engaged

    position.

    4. During the starting of machine upto 2730 rpm, safe oil pressure isregulated by limiter.

    5. When the turbine has taken over the regulation function, the limiter

    works as by-pass valve on the secondary oil system.

    TURBINE PROTECTION TESTING

    The following protection parameters of turbine have to checked & recovered

    in log book:

    1. Primary oil pressure should be 3.05 kg/cm 2

    2. Control gear pressure should be 7.00 kg/cm 2 (regulation oil pressure)

    TURBINE OIL PRESSURE REGULATING SYSTEM

    1. Reset the supply turbine.

    2. Reduce the turbine oil from turbine local panel as described in T.G.set manual.

    3. Further reduce the turbine oil pressure by procedure given above and

    watch so that E.O.P. (A.C.) starts at 0.8 kg/cm2. Now further reduce

    the pressure & water so that E.O.P. (D.C.) gets started automatically

    at 0.7 kg/cm 2.

    4. Mechanical shift tripping.

    32

  • 7/27/2019 Shubham Reportmn,mn

    33/52

    5. Low vacuum tripping.

    SPECIFICATIONS OF 105 MW TURBINE

    Rated output at generator terminals : 110 MW

    Rated speed : 3000 rpm

    Rated steam pressure just before stop valve : 130 kg/sq. cm

    Maximum steam pressure just before stop valve : 146 kg/sq. cm

    Rated temperature just before stop valve : 540

    Reheated steam pressure : 27.4 kg/sq. cm

    Maximum steam pressure before MP casing : 36 kg/sq. cm

    IMPORTANT FEATURES OF TURBINE

    No. of regulated extractions : 8

    No. of wheels in HP rotors : 2 row Curtis, 8 HP (impulse)

    No. of wheels in MP rotors : 12 impulse

    No. of wheels in LP rotors : 4 impulse of double flow design

    No. of high pressure control valves : 4

    No. of interceptor valves : 2Range of critical speed : 1200 to 2500

    Weight of HP rotor : 5.5 Tonnes

    Weight of MP rotor : 11 Tonnes

    Weight of LP rotor : 24 Tonnes

    Direction of rotation : Clockwise from front bearing stand

    Material construction : special cast steel

    HP MP outer casing : Casting of chromium vanadium steel

    HP MP Inner casing : Casting of chromium vanadium

    molybdenum carbon steel

    ELECTRONIC INSTRUMENTS USEFUL FOR THE

    PLANT

    33

  • 7/27/2019 Shubham Reportmn,mn

    34/52

    The following instruments are found to be very useful for the power plant:

    1. PR6422

    2. PR6423

    3. PR6424

    4. CON 010

    5. Conductivity Indicator Controller

    6. pH-Redox Transmitter PP9041

    7. Linear Displacement Transducers, PR9350 Series (LD 5000)

    PR6422, PR6423, PR6424

    Operation and construction:

    The transducers belonging to the PR6422, PR6423, PR6424 series based on

    the eddy currents measuring principle form together with the signal

    converter CON 010 an oscillator circuit, whose amplitude of oscillation isdamped by the proximity of the metallic object w.r.t. face of the transducer.

    The damping is proportional to the distance between the transducer coil and

    the object.

    The transducers are available for different static and dynamic measuring

    ranges and with different dimensions. The transducers PR6422 and PR6423

    are fitted with a 1m long cable. Transducer PR6424 is fitted with a 4m long

    cable.

    The zero point and gradient of the measuring s/n can be adjusted by means

    of components located under a gas tight cover. The units are delivered fully

    adjusted so that no onside calibration is required. The transducer is

    connected via a self locking, water proof, plug connection. The power

    supply and s/n o/p connections are via screw terminals.

    Intrinsically safe operation is possible when zener barriers are used. The

    units correspond to the relevant VDI, API and ISO standards.

    Application:

    These units are designed for use in many branches of industries and in

    laboratories for measurement and supervision of small displacements and

    vibration on ferromagnetic objects. Such various applications are:

    34

  • 7/27/2019 Shubham Reportmn,mn

    35/52

    Monitoring distances between rotor parts

    Monitoring vibration of mechanical elements

    Monitoring deformation or bending of mechanical parts

    Contact-less measurement of shaft eccentricity, vibration and small

    displacements Transducers operate on the eddy current principle for static and

    dynamic measurements

    Transducers easy to mount and adjust

    Compact design

    This contact-less measuring principle as well as the small size, robust

    construction and the resistance of the transducer to aggressive chemical

    influences, make this system ideal for continuous supervision of all types of

    rational machinery.

    Measuring chains made up of displacements transducers, signal converter

    and the additional electronic equipment belonging to the RMS700 system

    moderately priced and maintenance free supervision of small shaft

    displacements with respect to the shaft bearing or housing in two different

    modes:

    1. Radial, static displacement of the shaft and relative shaft vibration.

    2. Axial, shaft displacement and relative expansion.

    The following static and dynamic relative measurements are necessary for

    supervision of the important mechanical parameters governing turbo-

    machinery breakdown prevention.

    a. Axial position of the shaft with respect to the housing.

    b. Radial position of the shaft with respect to the housing.

    c. Shaft vibration.

    CON 010 (SIGNAL CONVERTER)

    The signal converters contain the electronics necessary for energisation andsignal conversion, which is generally identical for all types. The signal

    converter must be energized with 24 DC with +5 or -5%. The normal

    deviation of the output voltage for the measuring range of connected

    transducer is 4-20V. The converter is delivered together with the transducer

    for which it was calibrated. Therefore, care must be taken that transducer

    and system converter remain together.

    35

  • 7/27/2019 Shubham Reportmn,mn

    36/52

  • 7/27/2019 Shubham Reportmn,mn

    37/52

    the equivalent conductivity of the fluid at the reference temperature of

    25o C for different temperature of the fluid.

    pH-REDOX TRANSMITTER PP9041

    The Philips PP9041 is a pH-redox transmitter with a spam of 10 pH and with

    zero settings at pH 0, pH 2 & pH 4. This allows the following measuring

    ranges to be selected:

    a. pH 0pH 10

    b. pH 2pH 12

    c. pH 4pH 14

    Furthermore, eight mV ranges can be selected with a spam of 1000 mV,

    output current ranges of 0-20 mV of 4-20 mV can be selected to use the

    transmitter for the either electronic or pneumatic control to avoid earthingand/or interfacing problems, both electrode inputs are highly ohmic.

    This allows the use of any electrode as a reference. The features of the

    instrument make it very suitable for water treatment and pressure control

    application.

    TRAINING IN EMD

    Panki Thermal power station has four units for generation. Each unit has a

    separate transformer. Transformer rating depends on the generating capacity

    of each unit. Units 3 and 4 generate power at 11 KV. Units 1 and 2 are

    closed.

    Rating of Transformers of Unit 3 and Unit 4

    KVA H.V. 87500/12500

    L.V. 87500/12500

    No Load Volts H.V. 242000

    L.V. 11000

    Winding Temperature 30 degree c

    Amperes H.V. 298

    L.V. 656

    37

  • 7/27/2019 Shubham Reportmn,mn

    38/52

    Phase H.V. 3

    L.V. 3

    Types of cooling ON/OFF

    Frequency 50 Hz

    Impedance Volts 12.15%

    Vector group symbol Y d 1 1

    Core winding weight 104000 kg

    Weight of oil 34700 kg

    Total weight 187000 kg

    Oil 38550 litres

    Oil circulation 2 x 1800 litres/min

    Air circulation 24 x 50 m3/min

    Type of circuit breaker O.F. (Oil Filter/ A.B.)

    The ratings of major electrical equipments such as all transformers, for 110

    MW units are as follows:

    Power rating of generating transformer : 125 MVA

    Power rating of unit auxiliary transformer (UAT) : 16 MVA

    Voltage transformation ratio of generating transformer : 11/242 KV

    Voltage transformation ratio of UAT : 11/6.6 KV

    Voltage transformation ratio of reserve transformer : 132/6.6 KV

    In PTPS, the generation of electrical power is done at 11 KV. The generated

    power at this voltage goes to the bus bar through transformer which step-up

    the voltage. Then power is ready for transmission and is fed into

    transmission network.

    After the generating transformer, the current transformer and the potential

    transformer are located. After the CT and PT, two circuit breakers are

    connected. One of the circuit breakers is manual while the other is

    automatic. The automatic circuit breaker is air blast circuit breaker (ABCB).

    When excessive current or over voltage or sudden dip in voltage occurs then

    the circuit breaker disconnects the line.

    CURRENT TRANSFORMER (C.T.)

    At this substation a number of current transformers are used. These current

    transformers are used with low ammeters to measure high current in high

    38

  • 7/27/2019 Shubham Reportmn,mn

    39/52

    voltage A.C. circuit where it is not practical to connect instruments or

    ammeters directly from high voltage lines. In addition to insulate the

    instrument from high voltage it steps down the current in known ratio.

    The current transformer has a primary coil of very few turns of thick wire

    connected in series with the line whose current is to be measured. The

    secondary consists of a large number of turns of thin wire and it is connected

    across the ammeter terminals.

    At required voltage the current transformer is of step-up type. But it is sure

    that the current will be step down. Thus if the current transformer has

    primary to secondary ratio of 100:5, then it step-ups the voltage 20 times

    whereas it step-downs the current to 1/20 times of it.

    POTENTIAL TRANSFORMER (P.T.)

    The potential transformers are used to operate as voltmeters. The potential

    coil of wattmeter and relays form high lines. The primary winding of the

    potential transformer is connected across the line carrying the voltage to be

    measured and the voltage circuit is connected across the secondary winding;

    the design of a potential transformer is quite similar to that of a proper

    transformer but the loading of a P.T. is always small. The potential

    transformers are used to measure the high voltage. The potential transformer

    is also used for operating the relays in control circuit.

    For safety the secondary winding it is completely insulated from the high

    voltage of primary side and grounded for boundary protection of the

    operators.

    Three types of cooling techniques are employed for the transformers. These

    techniques are as follows:

    a. Oil Natural Air Force

    b. Oil Natural Air Natural

    c. Oil Force Air Force

    GENERATOR AND EXCITER

    The electric generator is most important part of the power station. The

    principal of electromagnetic induction is used to generate electric power

    39

  • 7/27/2019 Shubham Reportmn,mn

    40/52

    with the help of synchronous generator. All modern type of AC generators

    essentially consists of fixed starter and revolution rotor. An alternating e.m.f.

    is induced when the shaft of the rotor is revolved with the help of a prime

    mover.

    The rotor provides the magnetic flux to the machine. The winding of three

    generators may be connected either in delta or star arrangement. With star

    arrangement two voltages can be obtained as the line voltage or as the phase

    voltage. The neutral is connected to the earth and this helps in designing a

    protective system in order to keep the temperature rise of various parts from

    exceeding the respective maximum permissible values. Every generator

    requires continuous cooling during its operation. The system cooling

    adopted for the cooling purpose consists of a fan that circulates the air

    through the alternator and the warm air is cooled by the water coolers before

    being circulated again. This system gives good protection against fire inalternator due to restricted air supply. Carbon dioxide can also be easily

    injected to extinguish the fire.

    The exciter provides the direct current mended to excite the rotor field

    magnets. The present on excitation must be absolutely reliable since their

    failures will shutdown the alternators. The higher the total load and more the

    lagging power factor, the greater excitation is required.

    INTRODUCTION TO SWITCH GEARS, CIRCUIT

    BREAKERS AND RELAYS

    40

  • 7/27/2019 Shubham Reportmn,mn

    41/52

    Switch gear in a broad sense covers a wide range of equipments connected

    with switching and protection. A circuit breaker is a switching (current

    interrupting or making) device in switch gear. The basic requirements of

    switching in power system practice are two fold:1. To permit apparatus and circuits to be conveniently put into or taken

    out of service.

    2. To permit appropriate and safe isolation of apparatus and circuits

    automatically, in a pre-determined time period when they develop

    faults.

    DEVICES USED FOR CIRCUIT BREAKING (OR MAKING)

    1. Fuse and Iron Clad SwitchesFuse is an over-current switch in the sense that when the current

    exceeds a pre-assigned value in a circuit or device, it melts and causes

    current interruption. The supply is restored only when a healthy one

    replaces the damaged (melted) fuse in the line. To permit this without

    any danger of shock to the operator, fuses are connected on the load

    side of an iron clad switch.

    41

  • 7/27/2019 Shubham Reportmn,mn

    42/52

    2. Isolators

    An isolator is a switch connected after a circuit breaker. When a

    circuit or a busbar is taken out of service by tripping the circuit

    breaker, the isolator is then open circuited and the isolated line is

    earthed through earth switch so that the trapped line charges are safely

    conducted to ground.

    These devices are used to break or isolate the circuit. They are

    however, slower than circuit breakers in operation. They are used to

    locate and rectify faults in circuit elements and therefore they relieve

    the CB which may also be used for these operations. (However it is

    not advisable to turn CB in off position for a long duration as this may

    damage its springs.) In general, two isolators are put in circuit, one

    each on both sides of CB, in order to facilitate repair of CB as well ascircuit isolation and repair. Air pressure for isolators at Panki thermal

    power station is 16 kg/cm 2.

    3. Circuit Breakers

    Make or break both normal and abnormal currents.

    Appropriately manage the high-energy arc associated with

    current interruption.The problem has become more acute due

    to interconnection of power stations resulting in very high fault

    levels. Current interruption occurs only when it is called upon to do so

    by the relay circuits.

    In fact they are required to trip for a minimum of the internal

    fault current and remain inoperative for a maximum of through

    fault current.

    Rapid and successive automatic breaking and making to aid

    stable system operation.

    3-pole and single pole auto-reclosing arrangement.

    In addition to these breaking and making capabilities, a circuit breaker is

    required to do so under the following typical conditions:

    Short-circuit interruption

    Interruption of small inductive currents

    Capacitor switching

    42

  • 7/27/2019 Shubham Reportmn,mn

    43/52

    Interruption of short-line fault

    Asynchronous switching

    Principles of circuit breaking

    a.DC circuit breaking: effect of decreasing current and increasing arc

    length.

    b. AC circuit breaking: It is performed by several techniques which

    are current-zero period, distortion of AC current wave by arc voltage

    recovery and restriking voltages, single frequency and double

    frequency transients, rate of rise of recovery voltage (RRRV), control

    of RRRV, Resistance switching.

    Current chopping-interruption of low magnetizing currents-Opening

    resistors-capacitive current breaking-Switching of capacitor banks and

    unloaded lines-Interrupting terminal faults and short-line faults.

    Ratings of Circuit Breakers

    Rated Voltage

    Rated insulation

    Rated FrequencyRated normal current

    Rated short circuit breaking current

    Rated short circuit making current

    Rated opening sequence for auto-reclose CBs

    Rated transient recovery voltage for terminal faults (Representation of

    TRV by 4-parameters and 2-parameters)

    CB interrupting time-its components in relation to fault clearing time

    Single-pole auto-reclosing and its effects on system performance

    Classification of Circuit Breakers

    The circuit breakers are mainly classified as follows:

    1. Air-break circuit breaker or miniature circuit breaker

    2. Oil circuit breaker

    3. Minimum oil circuit breaker

    4. Air blast circuit breaker

    43

  • 7/27/2019 Shubham Reportmn,mn

    44/52

  • 7/27/2019 Shubham Reportmn,mn

    45/52

    c. Oil Circuit Breaker:

    In such CB, insulating oil is used as an arc quenching medium. The

    contacts are opened under oil and arc is struck between them. The heat of the

    arc evaporates the surrounding oil and dissociates its substantial volume of

    gaseous hydrogen at high pressure. It has the advantage of better and

    efficient arc quenching medium but on the negative side it involves risk of

    fire.

    d. SF6 CB:

    In such circuit breakers SF6 gas is used as the arc quenching medium.

    The SF6 is an electronegative gas and has a strong tendency to absorb free

    electron. The contacts of the breakers are opened in a high pressure medium

    of SF6 gas and arc is struck between them. The conducting free electrons in

    the arc are rapidly captured by the gas to form relatively large, immobilenegative ions. This loss of conducting electrons in the arc quickly builds up

    enough insulation strength to extinguish the arc. The SF6 CB has been found

    to be very effective for high power and high voltage service.

    The advantages of SF6 CBs are as follows:

    1. Very short arcing time.

    2. Can interrupt much larger current.

    3. Noiseless operation.

    4. No moisture problem.

    5. No risk of fire.

    6. Low maintenance cost.

    The only disadvantage of SF6 CB is that SF6 is costly thereby increasing the

    cost of CB.

    Types of indoor switchgears:

    a. Stationary Cubicle type

    b. Draw-out or Truck type

    c. SF6 filled switchgeard. Fuse-switch units

    e. Flame proof or Explosion proof switchgear

    f. Cellular type

    g. Corridor switchboard

    h. Mimic diagram board

    i. Metal-clad switchgear

    45

  • 7/27/2019 Shubham Reportmn,mn

    46/52

    j. Isolator and earthing switch-Vertical break isolator-Double break

    isolator

    THERMAL RELAYS

    A thermal relay consists of a bimetallic strip which is heated by the means of

    a heating coil that is supplied through a current transformer. An insulated

    arm carrying contact is pivoted and is held in contact with the strip with the

    help of a spring. The tension of spring can be varied by rotating the sector

    shaped plate.

    Under normal working conditions, the strip remains straight, but when the

    strip is heated it bends and the tension of the spring is released thus the relay

    contacts are closed which energises the trip circuit. The setting of relay can

    be achieved by varying the tension of the spring. The construction ofbimetallic element consists of two nickel-alloyed strips and steel strips

    welded together. These strips have high heat resistivity and are free from

    thermal secondary effects and aging. Each of theses strips is subjected to an

    artificial aging process and they are individually calibrated under currents.

    These relays assume a temperature higher than the surrounding parts and

    must have a short circuit capacity corresponding to the breaking capacity of

    circuit breaker itself. This is achieved by using the heat resisting bimetal

    material of suitable dimensions having large thermal time constant.

    These over current tripping relays are used mostly for motor controls and

    their heating elements are designed to withstand short time overload upto

    seven times the full load current.

    Only the smaller size of the indirect current heated bimetallic elements from

    4A to 6.5A are used while 30A motor protective circuit breaker will call for

    the additional fuses for the protection of winding along with relays. The

    smallest thermal relays of 400A circuit breakers are short circuit proof upto

    200 times their top current rating, i.e. upto 8 KA which is adequate.

    Ratings of thermal relay are as follows:

    With winding-temperature indication type R.B. form- H2AW74

    Contact capacity for

    (a) Cooker control 5A & 230V

    (b) For all arms 0.2A & 125V (D.C.)

    (c) For trip 0.2A & 125V (D.C.)

    46

  • 7/27/2019 Shubham Reportmn,mn

    47/52

    Power supply 230V (A.C.)

    Bushing Sec. Thermal Current Ratio VA Accuracy

    A6 AS1 + AS2 -- -- --

    B6 BS1 + BS2 400/1 60 5P20C6 CS1 + CS2 -- -- --

    N N1S1 - N1S2 400/1 60 5P20

    N N2S1 - N2S2 -- -- --

    GRID SUBSTATION

    The Panki grid substation has five buses at different voltage levels namely:

    1. 220 KV bus

    2. 132 KV bus3. 33 KV bus

    4. 25 KV bus

    5. 25 KV bus

    Some of the power supplied by Panki thermal power station to the grid

    substation is fed back for the purpose of operation of auxiliary components.

    WAVE TRAP

    This is used for communication by means of which, two grid substations

    may communicate and receive messages.

    SWITCHYARD

    The air at high pressure required for ABCB is produced by the compressor.

    There are two compressors for this purpose at PTPS. Both the compressors

    are run by the diesel engines. This is to ensure that interruption of power

    supply does not effect the operation of CB. The compressor maintains thepressure of air in main air tank. The compressor starts automatically when

    pressure of air in main tank falls below 33 kg/cm 2 and stops automatically

    when pressure in main tank has reached 40 kg/cm 2.

    Each ABCB is provided with its own subsidiary air tank. This tank contains

    air at pressure of 23 kg/cm 2 which is the operating pressure of the ABCB.

    47

  • 7/27/2019 Shubham Reportmn,mn

    48/52

    The subsidiary tank ensures that sufficient air is available for ABCB

    operation while its operation does not affect the main tank pressure.

    Similarly, subsidiary tank of isolation contain air at pressure of 16 kg/cm 2.

    Two sets of contact are provided for each phase of ABCB so that one of

    these may operate if the other fails.

    TRACKS FOR TRANSFORMER

    Transformers are placed on the tracks (similar to railway tracks). This is

    done to aid the transportation, loading, unloading and installation of

    transformer. Using these tracks, transformer may be taken to the cranes

    which then lift and place the transformer on the vehicle. Similarly, cranes

    download these transformers which are then transported through the tracksto the site of installation.

    CONTROL & INSTRUMENTATION DIVISION

    This is the backbone of a thermal power plant. Various parameters in various

    auxiliaries are controlled from here. The equipments are very sensitive and

    can even pick up minute disturbances. Automatic control compares the

    actual value of the plant output with the desired value, determined the

    deviation and produces control signal which will reduce the deviation to zeroor a small value. The industrial automatic controllers that are employed in

    the control and instrumentation section are as follows:

    1. Two position or on-off controllers

    2. Proportional controllers

    3. integral controllers

    4. Proportionally-integral controllers (PI)

    5. Derivative controllers

    6. Proportionally-integral-derivative controllers (PID)

    Various instruments of the C&I department

    1. Boiler Drum: There are numerous red and green lights in the control

    room. The light continuously indicates the boiler drum steam and

    water level. When the level goes in the danger region, on alarm is

    activated.

    48

  • 7/27/2019 Shubham Reportmn,mn

    49/52

  • 7/27/2019 Shubham Reportmn,mn

    50/52

    Since the rotor moves at a very high speed of about 2900 rpm to 3000 rpm,

    due to impinging of steam at high temperature, the expansion of rotor takes

    place. This is called eccentricity.

    Bearing Temperature

    Bearings are made of those metals, which melt at 100o C. Therefore

    allowable temperature is 7.5o C. Platinum resistance thermometers are used.

    The oil pressure is maintained at 35 kg/cm 2 at the header and a pressure of

    15.8 kg/cm 2 at ball bearing.

    WATER POLLUTION CONTROL

    Main source of pollution in PTPS is polluted water that comes out. It is not

    made to flow as such into nearby river. Rather it is first purified by effluent

    treatment plant. Waste in the water us called sludge is collected in sludge,dyeing beds. From there it is taken away by trolleys once in a year. The

    general working of plant is as follows-

    Step-1

    Polluted water comes for treatment through gate A of inlet drain. It is first

    through screen. Before being collected in grease trap which is * feet deep,

    big particles, polythene, rappers etc. have already been screened before

    collection of water into oil and gases trap. Some dust and heavy parts and

    oil, grease come in the upper parts which is sucked by oil and grease pump.

    Oil is collected into drum from time to time this oil is sent to boiler for use.

    Step-2

    Water from oil and grease trap goes to a 17A deep chamber, here water

    remains stand still for some time, heavy sludge, particles and impurities that

    do not dissolve in water settles down. Water from here goes to aeration tank

    through feed pumps.

    Step-3

    Aeration tanks are deep tank where oil is mined in water. There are 3aerators for this purpose. An aerator is basically a tabulator that is like a fan

    and rotates in water. In this way oxygen is mixed in water. This is necessary

    for the life of small bacteria that clear the water and makes it natural; 35 kg

    lime and 15 kg urea are mined in water. They are used as water purifiers.

    50

  • 7/27/2019 Shubham Reportmn,mn

    51/52

    Step-4

    From aeration tank water comes to air fan tank. Motor is the center of

    purifier which rotates at the speed of two rotations per hour. It amplifies due

    to centripetal force created by the rotating sludge and by the particles which

    move toward the centre of the tank.

    Step-5

    Pure water is discharged from the center i=of the air fan tank. Sludge pumps

    from the center of air tank fan pit and send it into sludge drying beds. Water

    vaporizes from this sludge beds and sludge remarks that are thrown away by

    turn from time to time.

    AIR POLLUTION CONTROL

    Air pollution occurs due to ash present in the exhaust gas released from the

    chimney of the power plant. Therefore, fly ash can almost effectively be

    prevented from entering into atmosphere by employing electrostatic

    precipitation technique.

    51

  • 7/27/2019 Shubham Reportmn,mn

    52/52

    CONCLUSION

    It was worth an educational experience to see the working of variousmechanical devices in practical, which I had just read about in books.

    The process of knowing about the various stages of thermal power

    generation (from coal) including the boiler & its auxiliaries, the steam

    generating units & auxiliaries and the compounding, governing, protection

    testing & regulation of turbines was a great experience.

    Observing the practical implementation of the various mechanical devices

    like boilers, turbines, pumps, compressors, fans and the electrical

    equipments like current transformers, potential transformers, generators,exciters, switch gears, circuit breakers etc. added a lot to my knowledge.

    To know about the various stages in a water treatment plant was a new

    experience.

    And lastly, I would like to mention about the team work, co-ordination and

    time management which exists among the various departments of the unit.

    This has really helped me to learn about the job skills.

    52


Recommended