ADDENDUM #1
SIERRA MADRE RESERVOIR RAHABILITATION
PLAN NO. 1178
Date of Addendum No. 1: October 25, 2016
Addendum No. 1 Page 1 of 2
City of Glendora Addendum No. 1
Sierra Madre Reservoir Rehabilitation Plan No. 1178
October 25, 2016
The Bidder shall execute the certification on page 2 of 2 of this addendum and shall submit the signed certification with Bidder’s Proposal.
I. Modifications to Bid Opening Date: A. Extend Bid Opening Date two (2) additional weeks. B. Bid Opening Date is scheduled for November 10, 2016 at 10:00 a.m.
II. Modifications to Technical Specifications:
A. Revise Section 03314 – Prestressed Concrete Tank.
End of Addendum No. 1
Addendum No. 1 Page 2 of 2
City of Glendora 116 E Foothill Blvd Glendora, CA 91741 Addendum No. 1 October 25, 2016 Prepared by: City of Glendora BIDDER'S CERTIFICATION I acknowledge receipt of the foregoing Addendum No. 1 and accept all conditions contained herein. Dated: ___________________________ Company: ___________________________ Bidder: ___________________________ Title: ___________________________ Signature: __________________________
THIS FORM MUST BE COMPLETED AND SUBMITTED WITH BID
Sierra Madre Reservoir Rehabilitation PRESTRESSED CONCRETE TANK City of Glendora 05/2016 03314-1
SECTION 03314
PRESTRESSED CONCRETE TANK
PART 1: GENERAL
1.01 SCOPE OF WORK
A. This section covers the complete furnishing and installation of seven-wire strand and
bars for circumferential and vertical prestressing, respectively, of concrete walls,
special forming requirements and the complete shotcrete application operation. This section also covers the qualifications for the CONTRACTOR (i.e. GENERAL
CONTRACTOR), Prestressing contractor, and Shotcrete contractors. This section also
covers general requirements for the tank and construction materials used in the tank. If
a discrepancy between this section of the Specifications and any other section of the Specifications occurs, this section shall govern. The words "stressing machine" may
refer to either circumferential wrapping machinery or vertical tendon stressing
equipment.
B. The CONTRACTOR shall furnish and construct the circumferential prestressing and
shotcrete application for the existing concrete reservoir as shown on the Drawings.
C. Concrete work shall conform to the provisions of Section 03300, "Cast-in-Place
Concrete", as supplemented and modified by this section.
1.02 RELATED SECTIONS
Section 03100 Concrete Formwork
Section 03200 Reinforcing Steel
Section 03230 Earthquake Cables
Section 03251 Expansion and Construction Joints
Section 03255 Tank Wall Base and Top Joint
Section 03300 Cast-in-Place Concrete
1.03 REFERENCES
ACI 306R Cold Weather Concreting
ACI 506.3R Guide to Certification of Shotcrete Nozzlemen
ASTM A416 Specification for Uncoated Seven-Wire Stress-Relieved Steel Strand for
Prestressed Concrete
ASTM A722 Specification for Uncoated High-Strength Steel Bar for Prestressing
Concrete
Sierra Madre Reservoir Rehabilitation PRESTRESSED CONCRETE TANK City of Glendora 05/2016 03314-2
AWWA C651 Disinfecting Water Mains
AWWA C652 Disinfection of Water-Storage Facilities
ICRI Concrete Repair Manual
1.04 EXPERIENCE OF GENERAL CONTRACTOR (BIDDER), PRESTRESSING
SUBCONTRACTOR (PRESTRESSOR) AND SUPERINTENDENT
A. Due to the nature of the project, it is the intent of these Specifications to obtain a first
class product with emphasis on overall safety, quality and quality control, both during and after the construction process. Only GENERAL CONTRACTORS and
PRESTRESSING SUBCONTRACTORS experienced in the construction of wrapped
strand prestressed concrete tanks are qualified to bid on and rehabilitate this tank project.
B. The PRESTRESSING SUBCONTRACTOR shall be a specialist contractor
experienced in the prestressing of AWWA D-110 Type I tanks, having prestressed, in
their own name, at least 10 tanks in the last 10 years, which have been in successful service for a minimum of five (5) years, meeting the specified criteria listed herein. All
PRESTRESSING SUBCONTRACTORS are required to be qualified. The bidder
(GENERAL CONTRACTOR) is required to state on the face of his sealed proposal, the name of the qualified tank PRESTRESSING SUBCONTRACTOR.
C. The GENEARL CONTRACTOR (Bidder) shall have been the General Contractor
and/or the Tank Subcontractor on at least two (2) AWWA D110 Type I tanks of either new construction or rehabilitation within the last ten (10) years. The Engineer will
review the qualification package along with the bid package to determine which
contractors meet the requirements.
1.05 WORK BY PRESTRESSOR
A. No stressing system falling under any of the following requirements will be considered
unless it has been successfully used on tanks of at least one-half of the diameter, height
and capacity. The GENERAL CONTRACTOR shall submit with his bid the name and location of the CITY and the completion dates of ten (10) tanks on which the proposed
qualifying "stressing machine" and automated shotcrete equipment has been used by
the PRESTRESSING SUBCONTRACTOR within the past ten (10) years. All tanks
listed for the Prestressor's experience requirements must have been prestressed in the Prestressor's own name. Experience of personnel associated with the Prestressor or
hired by the Prestressor will not be considered unless the Prestressor can demonstrate
that the work was contracted and performed directly by the listed Prestressor in its business name.
B. Descriptive literature shall also be submitted with the bid showing the proposed
machinery with the recorders and a typical copy of an actual recording of the applied forces taken from one of the jobs on which such machinery has been used. Any
stressing system that will not provide the substantial equivalent of the above require-
ments will be rejected
Sierra Madre Reservoir Rehabilitation PRESTRESSED CONCRETE TANK City of Glendora 05/2016 03314-3
C. A bid may not be considered responsive unless such data has been submitted with the
bid. This applies to the wrapped strand, tendon-stressing and automated shotcrete equipment.
D. Experience gained by the Prestressor in machine single wire wrapping, internal tendon
systems or external tendon systems will not be considered in meeting the required
experience requirements.
E. If subcontracted, the prestressing firm or individual(s) will be responsible to the
GENERAL CONTRACTOR for the following phases of work:
1. Furnish, stress and pressure grout the vertical prestressing tendons with epoxy.
2. Abrasive blast the exterior concrete core wall and apply shotcrete scratch coat.
3. Furnish and install the horizontal prestressing strand.
4. Apply the shotcrete covercoat over the wrapped strand.
1.06 BID SUBMITTAL REQUIRED BY CONTRACTOR
The following information shall be required to be submitted with the CONTRACTOR's bid
submittal:
A. General contractors shall submit one copy of a qualification submittal along with the sealed bid package on the advertised bid date. The general contractors shall submit a
complete record of their experience in the new construction or rehabilitation of
prestressed concrete tanks conforming to AWWA D110, Type I as indicated in section 1.4, along with their Prestressing Subcontractor qualification. The record shall indicate
the size of the tank, the name and address of the OWNER, the year of completion or
rehabilitation, and the name of the ENGINEER for each project. Experience in the construction or rehabilitation of AWWA D110 Type II or III tanks is not acceptable.
Provide the names, project responsibilities, experience on similar projects and resumes
for personnel responsible for the following: Project Manager, Site Superintendent, and
Quality Control Manager.
B. Construction Equipment, Materials and Methods – Provide the following:
Summary of all equipment to be used in the rehabilitation of the tank.
Construction schedule and plan including labor requirements and
responsibilities, sequencing, materials and methods.
Quality control plan and procedures including testing, correcting
deficiencies, systems and methods, schedule and responsibilities.
List all major suppliers and subcontractors who may work on this project.
C. Financial Capacity – Provide the following:
References for bank and bonding company
Insurance Limits
Warranty Statement
Sierra Madre Reservoir Rehabilitation PRESTRESSED CONCRETE TANK City of Glendora 05/2016 03314-4
D. The contractor shall sign and date the information provided and certify that to the extent of the Contractor’s knowledge, the information is true and accurate, and the
design and construction supervisory personnel for the tank construction will be directly
involved with and used on this project. Substitutions of personnel and/or methods will
not be allowed without the written authorization of the Owner. A bid may not be considered responsive unless the GENERAL CONTRACTOR's, and associated
superintendent's, experience requirements have been submitted with the bid.
1.07 CONTRACT AWARD
The Contract will be awarded on the basis of the methods, material and equipment shown on
the Drawings and specified in these Specifications. The Specifications and Drawings are
based on proven construction techniques that result in successful low-maintenance tank water storage performance. The following specific design criteria and salient characteristics are
considered essential to the successful construction of the specified prestressed concrete tank.
A. Experience in constructing a large quantity of successful tanks, ease of construction,
CONTRACTOR familiarity with this type of tank construction and reduced inspection costs associated therewith.
B. External, continuously wrapped strand circumferential prestressing providing the
desired bond with the shotcrete in addition to the final force specified. (No stressing system based on single wire wrapping, pulling wire through a die or jack-operated,
circumferential tendon or cable systems, based on circumferential movement of the
wrapped wire prestressing steel after it is placed in/around the wall, will be allowed.)
C. Positive anchoring system of circumferential wrapped strand prestressing to the
corewall and spaced as shown on the Drawings.
D. Maximum allowable spacing of circumferential wrapped prestressing strands as shown
on the Drawings.
E. Galvanized circumferential wrapped prestressing strands for long-life performance.
F. Continuous and instantaneous recording and correction of all applied prestressing
forces.
G. A maximum acceptable stress tolerance of +1.5% at any point along the prestressing
steel.
H. No variation in prestressing forces due to friction losses.
I. Automated, wet-mix 10-sack shotcrete applied over a fully abrasively blasted concrete corewall.
J. External paint protection as specified here-in.
Sierra Madre Reservoir Rehabilitation PRESTRESSED CONCRETE TANK City of Glendora 05/2016 03314-5
1.08 NON-RESPONSIVE BID
The information required in Section 03314.01.06 above shall be submitted with the bid
proposal. Failure to submit such information may be deemed a material irregularity which
may cause the bid to be rejected as non-responsive.
1.09 SUBMITTALS FOR REVIEW
A. Section 01300 - Submittals: Procedures for Submittals.
B. CONTRACTOR shall submit circumferential wrapped strand prestressing wrapping
schedule and the intermediate lock-off elevations for the ENGINEER's review and approval before the wall pour is made.
C. CONTRACTOR shall submit shop drawings of the method of anchoring and splicing
of the circumferential wrapped prestressing strands.
D. The CONTRACTOR shall submit mill certifications for the seven-wire strand and
high-strength threaded bars to verify conformance with these specifications.
E. Shotcrete mix design prepared by the supplier and signed material submittal certifying the proposed mix design meets the requirements of these specifications.
F. Nozzle man certification in conformance with requirements of Section 03314.3.12.D if
hand placed shotcrete is to be applied.
1.10 SUBMITTALS FOR INFORMATION
A. Section 01300 - Submittals: Procedures for Submittals.
B. CONTRACTOR shall submit the prestressing force recording tapes for both the
circumferential and vertical prestressing. These shall become the property of the OWNER.
1.11 QUALITY ASSURANCE
A. Testing of Prestressing Material
1. Prestressing CONTRACTOR shall furnish, at his own expense, Mill test certificates showing the dimensional and physical characteristics of each size,
heat or reel of the prestressing steel he has furnished. Additional tests by a local
testing laboratory and at CONTRACTOR's expense will be required for incomplete certificates and prestressing steel of foreign origin.
2. Prestressing CONTRACTOR shall furnish evidence, to the satisfaction of the
ENGINEER, prior to the preparation of shop drawings and installation of vertical threadbar, that the proposed threadbar tendon anchorage system meets the
requirements of these specifications. The ENGINEER may order additional tests
to be taken. Should such additional tests not meet the specifications, the
Sierra Madre Reservoir Rehabilitation PRESTRESSED CONCRETE TANK City of Glendora 05/2016 03314-6
CONTRACTOR shall be responsible for the expense of these tests; otherwise
such expenses shall be borne by the CITY.
B. Calibration/Accuracy of Prestressing Equipment
1. Before any stressing operation may be started, CONTRACTOR shall calibrate all
recording equipment at an approved testing laboratory to the satisfaction of the
ENGINEER.
2. All continuous force readings for either the vertical or the circumferential
prestressing operations shall be developed with electronic (or the substantial
equivalent) force (strain gauge method) sensing transducers, all having a maximum non-linearity error of +0.5% and a maximum hysteresis error of
+0.25%.
1.12 GUARANTEE
A. The CONTRACTOR shall guarantee the work against defective materials or workmanship for a period of one (1) year from the date of completion. If any materials
or workmanship prove to be defective within one (1) year, they shall be replaced or
repaired by the CONTRACTOR at the CONTRACTOR’s expense.
1.13 PRODUCT DELIVERY, STORAGE AND HANDLING
A. Prestressing steel shall be adequately packaged to protect against intrusion of chemical
contaminants (from the atmosphere or otherwise) for the protection of the steel against physical damage and corrosion during (and subsequently as the result of) shipping and
storage.
B. Prestressing steel that has sustained physical damage through rust or otherwise will be
rejected.
C. All materials and prestressing material delivered to the job site shall be stored off the
ground on planks, supported by 4" x 4" timber, which must be covered with
polyethylene or sizalkraft paper to prevent any moisture from coming up from the bottom.
D. Reels of strand, prestressing tendons, anchors, etc., shall be stacked neatly and as
compact as possible.
E. All materials for tendons and all fabricated tendons shall be covered with tarpaulins in such a manner that water, rain, moisture and dust are kept away.
Sierra Madre Reservoir Rehabilitation PRESTRESSED CONCRETE TANK City of Glendora 05/2016 03314-7
PART 2: PRODUCTS
2.01 SEVEN-WIRE STRAND
A. Hot-dipped galvanized seven-wire strand used for circumferential wrapped strand
prestressing and/or earthquake cables shall meet the following minimum requirements:
Item Specification
Nominal strand diameter 3/8" 1/2" 0.6"
Nominal area after galv.(in2) 0.089 0.153 0.217
Nominal weight (lbs/1000 LF) 303 541 739
Pitch (strand dia.) 12-16 12-16 12-16
Tensile strength (lbs) min. 21,400 38,200 52,700
Yield strength @ 1% extension (lbs) min.
16,000 28,500 39,500
Elongation in 24-inch at fracture min. 4.50% 4.50% 4.50%
Weight of zinc coating (oz/sq ft) min. 0.85 0.85 0.85
B. Hot-dipped galvanized seven-wire strand shall be manufactured in accordance with
ASTM A-416 prior to galvanizing.
C. Single wire prestressing material shall not be utilized in lieu of seven-wire strand prestressing material.
2.02 PORTLAND CEMENT
Portland Cement for the tank construction and shotcrete shall meet the requirements set out in
Section 03300 of these Specifications.
2.03 SHOTCRETE
A. Fine aggregates shall meet the requirements specified in Section 03300, "Cast-in-Place
Concrete", of these Specifications.
B. A well-graded coarse sand shall be used for all shotcrete applications.
C. Coarse sand shall generally consist of the following gradation:
Sieve Size % Passing by Weight
3/8 inch 100
No. 4 95-100
No. 8 80-100 No. 16 50- 85
No. 30 25- 60
No. 50 10- 30 No. 100 2 - 10
Sierra Madre Reservoir Rehabilitation PRESTRESSED CONCRETE TANK City of Glendora 05/2016 03314-8
The fineness modulus shall fall between 2.70 and 3.00.
D. Rebound materials may not be reused in any form for shotcrete. Rebound is defined as
aggregate mixed with cement, which ricochets off the surface during the application of
shotcrete after collision with the harder surface, reinforcement, or aggregate particles
themselves. The amount varies with the position of the work, air pressure, cement content, maximum size and grading of aggregate, the amount of reinforcing and
thickness of layer.
E. Water shall meet the requirements set out in Section 03300, "Cast-in-Place Concrete", of these Specifications.
F. Air-entrainment and admixtures shall meet the requirements specified in Section
03300, "Cast-in-Place Concrete", of these Specifications.
G. All shotcrete, unless otherwise specified here-in, shall be fibrous reinforced. Such
material shall consist of 100 percent virgin polypropylene fibrillated fibers specifically
manufactured for use as concrete/shotcrete secondary reinforcement. The required
volume of fibers to be added per cubic yard of shotcrete shall be as specified in these Specifications.
The fibers shall be manufactured in accordance with ASTM C-1116 Type III 4.1.3 and
ASTM C-1116 (Ref. ASTM C-1018), Performance Level I5 outlined in Section 21, Note 17. Fibrous concrete reinforcement shall be as manufactured by the
FIBERMESH COMPANY, Chattanooga, TN, phone: (800) 635-2308, or equal.
Acceptable polypropylene fibers shall have the following physical characteristics:
1. Specific gravity = 0.91
2. Tensile strength = 80-110 ksi
3. Fiber length = graded per manufacturer
2.04 SHOTCRETE PROPORTIONING
A. Each one cubic yard of shotcrete material in the ready mix truck or mixer shall consist
of 0.1% (1.5 lbs. per cubic yard) polypropylene fibers as specified here-in and a mix
ratio of 3 lbs. of moist sand to 1 lb. of Portland cement. Up to 50 oz. of PRO- KRETE-R or POZZOLITH 300R may be added at the option of CONTRACTOR
during warm weather conditions.
B. Whenever night temperatures are expected to drop below 35F, shotcrete proportioning shall follow the provisions of ACI 306R, “Cold Weather Concreting”.
C. If the conditions exceed any combination of air temperature 88 degrees F or more, relative humidity of 60% or less and/or wind velocity of 10 miles per hour or more.
The methods described in Section 03052 HOT WEATHER CONCRETING
PROCEDURES, shall be utilized as applicable to the material and application of shotcrete.
Sierra Madre Reservoir Rehabilitation PRESTRESSED CONCRETE TANK City of Glendora 05/2016 03314-9
D. If the batching procedure requires that smaller volumes of cement and sand be used, the
required cement-to-sand ratio shall still be strictly adhered to.
E. Additives other than PRO-KRETE-R or POZZOLITH 300R (such as POZZOLITH
300N or others) shall not be used unless specifically approved by the ENGINEER, after
careful consideration of its corrosive influence on prestressing steels.
F. If used by the shotcreter, the total volumetric air content of the shotcrete before placement shall not exceed 7 percent (plus or minus one percent) as determined by
ASTM C-173 or ASTM C- 231.
G. Unless otherwise specified on the Drawings, shotcrete cylinder strengths at 28 days shall be no less than 4,000 psi. Higher shotcrete cylinder strengths shall not permit a
reduction in the above specified cement contents. The cement content in the above mix
designs may be increased should the specified 28 day strength requirement not be met.
H. The polypropylene fibers and admixtures shall be added to the shotcrete at the time it is
batched and in the amounts specified in the approved mix design. Such additives shall
be mixed in strict conformance to the manufacturer's instructions and recommendations
for uniform and complete distribution. Each certificate of delivery supplied by the shotcrete supplier shall indicate the additive trade name, manufacturer's name and
amount per cubic yard added to each batch of shotcrete.
I. To insure proper penetration around the strand and proper conveyance of the material through the hose, a 5" to 7" slump of the mortar at the pump is recommended.
PART 3: EXECUTION
3.01 CIRCUMFERENTIAL PRESTRESSING EQUIPMENT
A. The circumferential stressing system shall produce a continuously, electronically (or
substantial equivalent) monitored permanent stress or force recording along the full
length of the strand as it is being applied. The stress variation in any strand at any point around the circumference should not be greater than +_1.5 percent of the ultimate
strength of the steel. In addition to this recording, any system which deflects the
tensioned strand between the tensioning device and the wall after it has left the tensioning device, shall provide a similar continuously monitored stress or force record
along the full length of the strand as it is being applied to the wall. These recordings
shall show that either before or after deflection, that the stress variation in any strand at
any point around the circumference shall not be greater than +_ 1.5 percent of the ultimate strength of the steel. No manual recorded force readings, such as hand-held
stressometers will be accepted. This requirement shall be strictly adhered to.
B. Any wrapping that does not meet the stress tolerances specified and/or cannot meet the requirements stated above will not be accepted and will be removed at
CONTRACTOR's expense. CONTRACTOR is responsible for all costs associated
with meeting the specified tolerances.
C. The prestressing system shall be capable of applying a continuous wrapped force at any point around the circumference within the specified tolerances. Circumferential
stressing systems based on jack-operated cable or rod-type tendons (such as those
Sierra Madre Reservoir Rehabilitation PRESTRESSED CONCRETE TANK City of Glendora 05/2016 03314-10
placed inside of ducts incorporated in the corewall or placed manually around the
exterior of the corewall) will not be allowed.
D. Since wrapping systems that utilize single solid prestressing material will not provide
the desired bond between the prestressing material and the shotcrete and since single
solid prestressing material will not provide an adequate safety factor against failure,
only machine wrapping systems which utilize seven-wire prestressing strandwrapping will be allowed.
3.02 CIRCUMFERENTIAL PRESTRESSING APPLICATION
A. Wrapped strand shall be anchored to the wall at least once for every coil or reel. Submit method of anchorage shop drawings to the ENGINEER for review.
B. Permanently anchoring one strand to a previously wrapped strand shall not be
permitted.
C. Wrapped strand ends shall be joined by suitable splicing methods that will develop
90% of the full strength of the strand. Submit splicing method shop drawings to the
ENGINEER for review.
D. Use of different steel alloys in the splicing material shall not be permitted.
E. The clear vertical spacing between any two wrapped strands shall be at least 1.5 strand
diameters or 3/8 inch, whichever is larger.
F. Any wrapped strands not meeting the spacing requirements shall be spread by approved methods or must be removed.
G. All cracks, 0.02 inches and larger in the corewall and floor slab, shall be repaired per
Section 03740 EPOXY ADHESIVE INJECTION OF CRACKS IN CONCRETE MEMBERS of these specifications prior to circumferential prestressing of the tank
walls.
3.03 CIRCUMFERENTIAL PRESTRESSING OPERATIONS
A. The initial electronically (or substantial equivalent) recorded steel stress shall not exceed 75 percent of the guaranteed minimum ultimate strength (M.U.S.) of the steel at
any time during or after stressing.
B. An automatic, continuously electronically (or substantial equivalent) monitored permanent recording of the applied force, at any point on the strand, at any point on and
around the tank wall, must be made during the entire circumferential prestressing
application. All such recordings must be based on a continuous reading of the applied
force on the strand between the tensioning drum and the wall when, and as, the strand is being wrapped and laid on the wall.
C. The force setting of the wrapping stressing machinery shall be such that the applied
forces fall within the specified minimum or maximum stress or force limitations; the force setting shall be corrected immediately when the applied force falls outside the
required force tolerance limitations.
Sierra Madre Reservoir Rehabilitation PRESTRESSED CONCRETE TANK City of Glendora 05/2016 03314-11
D. In the event that the stressing machinery is incapable of holding the applied force
within the specified stress or force range, the CITY will order, at the CONTRACTOR's expense, the removal and replacement of such machinery in favor of a different
stressing process capable of maintaining such tolerance requirements.
E. The initial force for the circumferential wrapped strand shall be no less than the
required initial force shown on the Drawings.
F. The continuous, electronically-produced applied-force chart produced during the
application of the strand wrapping becomes the property of the CITY.
G. Manual, individual or intermittent force readings taken on wrapped strand in full physical contact with the wall will not be accepted. Force readings based on anything
other than instantaneous force readings, as the strand is being tensioned, and wrapped
around the tank, will not be accepted.
H. An automatic, continuously electronically (or substantial equivalent) monitored and
simultaneously recorded force-elongation reading must be made for each vertical
stressing procedure.
I. Prior to wrapping, an initial 3/8" thick shotcrete layer shall be applied to the core wall after the surface has been prepared.
J. Wrapping may start when the concrete core wall has reached a compressive strength of
3,200 psi; however, under no circumstance shall the compressive stress exceed 55% of the concrete core wall compressive strength attained at that time.
K. In the event that gaps exceed 3/8 of an inch between the corewall and the applied strand
develop, wrapping shall be discontinued and the exterior wall surface shall be built up with shotcrete to reduce the gap within the 3/8-inch limit.
L. Wrapping over intermediate shotcrete coats or built-up shotcrete areas may commence
12 hours after the shotcrete has been applied or when the shotcrete has reached a
compressive strength of 250 psi, whichever is later.
M. The temperature of the prestressed material during application shall not be allowed to
increase by more than fifty degrees at any time during application due to the method of
stressing. No stressing system that pulls the prestressing material through a die to create a force is permitted.
3.04 SAFETY PRECAUTIONS
A. Every precaution shall be taken to keep personnel and visitors outside the danger area
of breaking strands or bars.
B. At no time shall anyone stand in the line of stressed vertical tendons or stressed strand.
C. No work shall be performed by anyone, other than the prestressing crew, within 100
feet of the wrapping operation or the application of the vertical threadbar stressing operation.
Sierra Madre Reservoir Rehabilitation PRESTRESSED CONCRETE TANK City of Glendora 05/2016 03314-12
D. Where access to the site by persons other than the prestressing crew is outside the
CONTRACTOR's control, while prestressing work is in progress, CONTRACTOR shall erect protective fencing to prevent breaking strand from endangering such
persons.
E. Welding to anchor plates after the threadbars have been assembled shall not be
permitted. In addition, prestressing steel shall not be used as a "ground" for welding operations.
3.05 EXISTING WALL SURFACE PREPARATION
A. Exterior surfaces of reservoir walls shall be prepared prior to the application of shotcrete to remove all deteriorated concrete and bond-inhibiting contaminants. The
surface preparation shall achieve a minimum profile of ICRI Concrete Repair Manual,
CSP5 over a minimum of ninety percent of the surface being prepared.
B. In order to mitigate environmental concerns, conform to environmental constraints, and
achieve the desired profile, the CONTRACTOR shall utilize either a self-contained
mechanical etching or shot blast system combined with a vacuum recovery system, or a
high pressure water jetting system with dust suppression equipment. Abrasive blasting systems that rely on sandblasting or steel shot without a vacuum recovery system or
systems that have not been used successfully in the past to prepare surfaces for
shotcreting and strandwrapping shall not be allowed.
3.06 SHOTCRETE EQUIPMENT
A. Shotcrete mixing shall be in conformance with the requirements of Section 03300,
"Cast-in-Place Concrete", of these Specifications.
B. The delivery equipment shall be of an approved design and size which has previous
given satisfactory results in similar work.
C. The equipment must be capable of discharging mixed materials into the hose under
close control and it must be able to deliver a continuous smooth stream of uniformly mixed material at the proper velocity to the discharge nozzle, free from slugs of any
kind.
D. The nozzle shall be of a design and size that will insure a smooth and uninterrupted flow of materials.
E. Delivery equipment shall be thoroughly cleaned at the end of each shift.
F. Equipment parts shall be regularly inspected and replaced as required.
G. The air capacity of the compressor shall be large enough that the minimum amount of air to be available at the nozzle shall be no less than 400 CFM, irrespective of whether
or not air from the same air supply is used for other purposes.
3.07 SHOTCRETE APPLICATION PROCESS
A. Shotcrete shall be applied under the wet mix process only.
Sierra Madre Reservoir Rehabilitation PRESTRESSED CONCRETE TANK City of Glendora 05/2016 03314-13
B. Nozzles shall be mounted on power driven machinery enabling the nozzle to travel
parallel to the surface to be sprayed at a uniform linear or bi-directional speed.
C. The nozzle shall be kept at a constant distance from the surface, always insuring a right
angle spray direction of the material to the surface.
D. Hand operated nozzles and shotcrete operations dependent on the performance of the
nozzleman will not be accepted except where additional shotcrete is needed to correct flat areas or for architectural surface treatments.
E. Grout materials shall be delivered to the jobsite in ready-mix trucks from approved
batching plants. However, job mixing will be accepted provided automatic weigh batch plants are used.
F. The sand, cement and water shall be premixed before being pumped through a 2"
minimum hose by specially designed mortar pumps.
G. The high velocity impact shall be developed pneumatically by injecting compressed air
at the nozzle.
3.08 SHOTCRETE PLACING AND FINISHING
A. Shotcrete shall be applied in a steady, uninterrupted flow. Should the flow become intermittent for any cause, the machine operator shall direct the nozzle away from the
work until it again becomes constant, or shut off the flow of materials.
B. The nozzle shall be held at approximately right angles to the surface and shall be kept at the proper and constant distance from the surface dictated by good practice standards
for the type of application, type of nozzle and air pressure employed.
C. Sufficient time shall be allowed for each layer of shotcrete to set up so the next layer of shotcrete can be applied without sagging.
D. The shotcrete application shall start at the bottom of the wall and move upward until all
wrapped strands have been covered. Subsequent shotcrete layers may be applied from
the top down or from the bottom up at the discretion of the CONTRACTOR.
E. While the nozzle travels around the tank, the nozzle shall be raised or lowered at a
uniform rate that provides an adequate overlapping of coatings and a uniform finish.
F. The nozzle shall be spiraled up or down around the tank, ending either at the top or bottom of the wall or at the termination of a partial-height strand layer.
G. The wall and/or intermediate layers of shotcrete may be wet down in order to achieve a
saturated surface-dry condition prior to the application of new shotcrete. The moisture
absorption by layers previously applied is relied upon to improve the bond and strength of the shotcrete material and reduce drying shrinkage of the applied shotcrete.
H. The application of the shotcrete in the number and thickness of layers specified here-in
is mandatory for proper penetration of shotcrete behind prestressing material and to reduce shrinkage due to variable drying of the shotcrete.
Sierra Madre Reservoir Rehabilitation PRESTRESSED CONCRETE TANK City of Glendora 05/2016 03314-14
I. Each layer of wrapped prestressing steel shall be covered with a minimum thickness of
3/8-inch shotcrete over the steel.
J. The shotcrete cover coat, over the final strand layer, shall be applied in at layers of
equal thickness to provide the required thickness of this coat.
K. Each layer of shotcrete shall be completed for the full circumference and full height of
the layer before the next layer of shotcrete may be applied.
L. All shotcrete coatings shall be built up in layers no greater than 3/4 inch in thickness
until the final required thickness has been obtained. The CONTRACTOR shall
demonstrate by a reliable means that each layer applied is the proper thickness.
M. Unless otherwise specified on the Drawings, the minimum shotcrete cover over all
wrapped steel shall be 1.5 inches.
N. If required on the Drawings, after the specified shotcrete cover over the wrapped prestressing strand has been completed, the exterior surface shall be given an
acceptable float finish true to line and curvature of the tank and to details shown on the
Drawings.
O. If a float finish is required on the Drawings, plaster or hand-applied shotcrete may be used to build up and level the surface to obtain the desired surface finish and
projections.
P. The finish coat mix (if a smooth float finish is required on the Drawings), shall consist of a minimum of one sack of cement for each 3-1/2 cubic feet of moist plaster sand.
Q. If no finish requirements are shown on the Plans, it is intended to have a natural
original gun finish of the shotcrete cover coat.
R. CONTRACTOR shall take every possible precaution to protect adjacent buildings,
concrete surfaces, vehicles, equipment, etc., from being damaged by overshooting
shotcrete and by materials carried away by the wind and shall be responsible for the
cost to clean overspray of shotcrete from these items.
S. Overshot shotcrete and rebound material deposited on the tank roof slab shall be
removed before it adheres to the concrete surface.
T. CONTRACTOR shall pay for all damages caused by the shotcrete operation under this contract.
3.09 SHOTCRETE TESTS
All shotcrete operations, testing, and prequalifying, shall conform to the entire Section 1910
of the 2013 California Building Code (CBC).
3.10 HAND PLACED SHOTCRETE FOR REPAIRS ONLY
Sierra Madre Reservoir Rehabilitation PRESTRESSED CONCRETE TANK City of Glendora 05/2016 03314-15
A. To insure a high quality shotcrete application, the CONTRACTOR shall satisfy the
ENGINEER that the nozzleman has had sufficient and acceptable experience in the application of structural shotcrete.
B. Pool and ditch shotcrete construction experience will not be considered as experience
for qualifying the nozzleman, unless approved by the ENGINEER.
C. The nozzleman shall be capable of applying thin coats of even and uniform thickness.
D. The nozzleman shall be a certified nozzle man in accordance with ACI 506.3R before
he may start any work.
3.11 RESTRICTIONS ON SHOTCRETE OPERATION
A. Shotcrete shall not be applied under such strong wind conditions that a considerable
amount of cement and moisture will be removed by the wind from the mortar spray
between the nozzle and the surface on which the shotcrete is applied.
B. Shotcrete may be applied in cold weather provided the wall surface is not frozen.
C. The temperature during the day must be expected to rise to at least 40F and the night temperature of the night after the shotcrete application must not be expected to drop
below 27F.
D. The use of Type III Portland cement is required (when readily available) in the event
shotcrete is applied at temperatures below 40F. The CONTRACTOR may apply shotcrete under these conditions solely at his own risk.
E. Whenever rain or frost has damaged shotcrete not yet set, the shotcrete must be removed and replaced.
F. If there is a possibility of damage, the CONTRACTOR shall consult with the
ENGINEER to determine if the shotcrete has been damaged by rain or frost before
applying any additional layers.
3.12 SHOTCRETE WATERCURING
A. Intermediate layers of shotcrete are not required to be cured if an additional shotcrete
layer is applied on the entire wall surface within 12 hours of completing the application of the previous layer. Keep shotcrete layer damp by hand curing or other means after
12 hours has elapsed since the layer was applied until the next shotcrete layer is
applied.
B. An indiscriminate use of continuous watercure for intermediate layers shall be avoided.
C. The final completed shotcrete layer, which is not required to receive any additional
coatings, shall be cured with plastic sheeting for a period of at least seven (7) days.
Plastic sheets used shall prevent loss of moisture from shotcrete as much as possible. Membrane curing methods utilizing curing compounds or wax-based residuals will not
be permitted.
Sierra Madre Reservoir Rehabilitation PRESTRESSED CONCRETE TANK City of Glendora 05/2016 03314-16
D. Wall coatings if required and specified in Section 09900, "Painting and Coating", shall
be applied no later than five (5) days after completion of the curing. If conditions make it impossible to apply coatings within the five (5) day period, or if no coatings are
required, shotcrete shall be cured for a period of ten (10) days instead of the seven (7)
days specified above.
3.13 CLEANING AND WATERPROOFING
A. After construction is completed, the interior of the tank shall be completely hosed out
and cleaned of all dirt and loose material.
B. Roof, floor and wall-footing cracks, which may have developed from drying shrinkage, shall not be taped or chipped out and caulked. All cracks larger than 0.02 inches shall
be repaired in accordance with Section 03740 EPOXY ADHESIVE INJECTION OF
CRACKS IN CONCRETE MEMBERS and shall be completed prior to applying the interior coating and exterior waterproofing at no additional cost to the CITY.
C. Exterior Waterproof Coating: The exterior coating shall be applied and cured prior to
backfilling in accordance with Section 07182 - RESERVOIR/VAULT WATER-
PROOFING.
3.14 DISINFECTING AND FILLING
A. Prior to filling, testing and disinfecting, the reservoir shall be swept clean and the
walls, floor, columns, and underside of the roof shall be sprayed with a high pressure stream of potable water to wash down all dust, dirt, etc. The high-pressure hose and
nozzle shall be of sufficient size to deliver a minimum flow of 50 gpm. All water, dirt,
and foreign material accumulated in this cleaning operation shall be collected and removed from the reservoir.
B. The reservoir shall be disinfected by chlorination. Chlorination shall be performed in
accordance with the requirements of AWWA C652, Method 2, with the following
modifications.
C. After the tank is cleaned and waterproofed, water containing 50 PPM of chlorine shall
be sprayed on all walls, columns, underside of roof areas, inlet piping, outlet piping,
and drain piping.
D. Water containing 50 PPM of chlorine shall be brought to such a depth that when the
tank is filled with potable water, the resulting chlorine solution is 1.5 to 2 PPM. The
water containing 50 PPM of chlorine shall stand for 24 hours prior to filling the tank.
E. The tank shall be filled in approximately eight-foot increments with 8 normal working hours between each increment for observation of possible leaks through the subdrains,
the reservoir wall, or the wall-footing joint. The filling of the reservoir shall be
coordinated with the OWNER. The OWNER will supply the water for the initial filling of the reservoir at no cost to the CONTRACTOR.
F. If only damp spots and small puddles of water are noted, the 8-foot incremental filling
can continue. If major leaks are noted, they should be thoroughly investigated prior to
Sierra Madre Reservoir Rehabilitation PRESTRESSED CONCRETE TANK City of Glendora 05/2016 03314-17
continuing to fill the tank. All leaks shall be repaired to the satisfaction of the CITY at
no additional cost to the CITY.
G. The tank should only be filled during normal working hours. At the end of each day the
reservoir and perimeter drain should be checked for evidence of any kind of leakage.
H. The chlorine concentration residual shall be monitored and adjusted while filling, if
necessary, so that when the reservoir is full the resulting chlorine concentration is approximately 1.5 to 2 PPM.
I. After filling the reservoir to the overflow level, there shall be a 24 hour soak period.
After the 24 hour soak period, a water sample shall be taken for bacteriological testing. After an additional 24 hour soak period, a second water sample shall be taken for
bacteriological testing. The disinfection process shall be accepted if samples taken for
both bacteriological tests conform to AWWA Standard C-651 and are found to be satisfactory.
If either test is positive, the CONTRACTOR shall correct the cause of the
bacteriological contamination, rechlorinate and retest the reservoir until two
consecutive satisfactory bacteriological test results are obtained, at no additional cost to the CITY. If bacteriological testing results continue to be positive, the contractor shall
drain the reservoir, re-disinfect, fill, and retest the reservoir water, all at no additional
cost to the CITY.
J. If the reservoir fails testing for bacteriological contamination or for leakage and water
must be discharged, cost of additional water to fill the reservoir will be deducted from
the total contract price.
K. Conduct testing for volatile organic compounds (VOCs) per Los Angeles County
Department of Public Health (DPH) requirements.
3.15 WARRANTY PERIOD PROVISIONS
A. This section shall be applicable during the entire specified warranty period of the tank.
B. A warranty inspection of the complete reservoir shall be conducted during the eleventh
month following the Notice of Completion. Representatives of the general contractor
shall attend this inspection and provide all necessary work and equipment required for the inspection such as lighting, ventilation, and safety equipment. All work found to be
defective at this time shall be repaired or replaced in accordance with the original
specifications and to the satisfaction of the CITY. The CONTRACTOR shall clean and
disinfect the reservoir after repairs to the interior are completed, or, disinfect the reservoir if no repairs to the interior are required, after the tank inspection. If the tank
was seeded, the CONTRACTOR shall remove the seeding material residue.
C. All equipment, materials, and labor required to perform the inspection, make the necessary repairs, and disinfect the tank shall be provided by the CONTRACTOR at no
additional cost to the CITY except that the CITY will provide water for the initial
filling of the tank with the same restrictions as provided in the initial testing period. The CONTRACTOR will be responsible for repairing any leaks that may develop as a
result of any warranty work.
Sierra Madre Reservoir Rehabilitation PRESTRESSED CONCRETE TANK City of Glendora 05/2016 03314-18
D. If the eleventh month falls on or between the date of May 1 and September 30, then the
inspection may be delayed and shall be performed no earlier than October 1 which would be longer than eleven months.
END OF SECTION