SIM 1, TMA pointing and tracking verified
NAT on-TMA Install
PROC-0066
NAT LT Alignment
PROC-68
NAT Functional Tests
PROC-0071
NAT Pointing Map Generation
PROC-0073
TMA Pointing/Tracking Verification
PROC-0074
TAT and NAT Electrical Routing
PROC-0070
SIM 1 Complete
TCS & MCS running on temp setup
ACS Ready
TMA Operational
Accurately pointing (milestone)
TAT on-TMA Install
PROC-0067
TAT LT Alignment
PROC-0069
NAT Ready TAT Ready
TAT Functional Tests(Daytime)
PROC-0072
LT Install on TMA
PROC-0079
TMA Ready
M1 Assy Installation in TMA
PROC-0002
M1 OSS Rack Installation
PROC-0075
M1 Assy Installation(comm)
PROC-0002
M1 Assy LT Align(comm)
PROC-0080
M1 Assy ElectricalRouting
PROC-0085
M1 Assy FacilitiesRouting
PROC-0087
AP InstallationPROC-0063
AP LT Align
PROC-0089
AP Thermal Rack Installation
PROC-0076
AP FacilitiesRouting
PROC-0088
M1 Mirror Installation
(sci)
PROC-0082
M1 CellOn-site
M1 Mirror On-site
(sci)
M1 MirrorOn-site(comm)
M1 Assy Build (comm)
PROC-0046
PF Wavefront Measurements
PROC-0098
Control RackOn-site
AP EquipOn-site
M1 GIS integration
PROC-0091
M1CS testing
PROC-0090
M1CS integration
PROC-0077
M1 Mirror Removal(comm)
PROC-0081
SIM 2 Complete
AP ElectricalRouting
PROC-0086
Dummy M1 Cell Removal
PROC-0039
TEOA On-site
SIM 2 Flow Chart, M1 Complete
M1 Cell in place(milestone)
M1 Alignment Complete
(milestone)
PF SHWS Installation on TEOA
PROC-0093
TEOA/PF SHWS Installation on TMA
PROC-0096
M1 Assy LT Align (sci)
PROC-0083
M1 Assy RemovalPROC-0002
M1 Assy Installation in TMA
PROC-0002
M1 Assy RemovalPROC-0002
PF SHWS ElectricalRouting (temp)
PROC-0095
AP in place(milestone)
TEOA/PF SHWS LT Align
PROC-0097
TMA TEOA DummyRemoval
PROC-0064
TMA Balance
PROC-0078
TMA Balance
PROC-0078
TMA Balance
PROC-0078
S&R Area Ready
TMA accepted
TMA accepted
SIM 1 complete
Instrument Lab available
Mirror Coating(sci)
PROC-0001
Pointing Map Update (PF SHWS)
PROC-0099
PF SHWS Calibration
PROC-0092
Mirror Coating(comm)
PROC-0001
M1 LUT Improvement(milestone)
IWU Install andFit-up
PROC-0083
T-15K ready
T-4Kready
Comp airready
CASA (?)
CASA (?)
CASA (?)
TEOA Instrument Lab Checkout
TMA Servo Re-tune
TMA Servo Re-tune
SE2Einstalled
TEOA CS Integration
PROC-0109
OSS IT Infras in place
Summit IT infras in
place
TEOA PF SHWS Removal
PROC-0100
TEOA Full Config Tele Floor Build
PROC-0101
TEOA Full Config on-TMA Install
PROC-0102
M2 and HS on-TMA LT Alignment
PROC-0103
GF SHWS Install
PROC-0051
TEOA PI Controller Rack Install
PROC-0104
TEOA Electrical Install
PROC-0105
TEOA GIS Integration
PROC-0110
TEOA Functional Tests
PROC-0112
Xbox Install
PROC-0106
GF Wavefront Measurements
PROC-0117
HS Facility Coolant Connect
PROC-0114
GF SHWS Removal
PROC-0052
GF Heat Dump Install
PROC-0053
Initial Day Time Test
PROC-0120
M1 AP Thermal Tuning
PROC-0122
M1 Thermal Control Tuning
PROC-0121
M2 Thermal Control Tuning
PROC-0123
M1/M2 Initial Thermal Tuning
Complete(Milestone)
SIM 2 Complete
M1/M2 Alignment Complete
(milestone)
Xbox Facilities Routing
PROC-0108
Xbox Electrical Routing
PROC-0107
GF SHWS Electrical Install (temp)
GOS Frame Install
PROC-0118
GF Heat Dump Facility Hookup
PROC-0119
TEOA CS Testing
PROC-0111
TMA Balance
PROC-0078
TMA Balance
PROC-0078
GOS Frame on site
TMA accepted
HS-closed loop
Ready
HS Coolant DI Loop Test
PROC-0113
SIM 3 Complete
SIM 3 Flow Chart, M1-M2 Complete
GF SHWS Calibration
PROC-0115
Comp airready
T-4Kready
CASA (?)
CASA (?)
Sun Sensor InstallOSS Rack
Ready
TMA Servo Re-tune
Summit IT infras in
place
SE2Einstalled
M6 Assy Install
PROC-0129
M5 Surrogate alignment
PROC-0018
PROC-xxxx
M6 Alignment
PROC-0018
PROC-xxxx
Characterize ALT Axis
PROC-0018
M6 Assy Ready
FOCS/FOTCS testing
PROC-0128
FOCS Integration
PROC-0127
M5 surrogate installation
PROC-0134
SIM 4 Complete
M6 Assy Functional Test
PROC-0132
M5 Surrogate
Ready
Characterize AZ axis
PROC-0018
MCS/TCSRunning on temp setup
Characterize tower stability
PROC-0018
Characterize ALT-AZ rotation
PROC-0018
M6 tilt adjustment (beam pointing)
PROC-0018
M7 Assy Installation
PROC-0135
M7 Alignment
PROC-0018
AOS ref
M7 Assy Ready
Characterize Coudé rotation
PROC-0018
M3 Assy Installation
PROC-0136
M3 Alignment
PROC-0018
PROC-xxxx
M3 Assy Ready
M3 Assy Functional Testing
PROC-0139
M4 Assy Installation
PROC-0141
M4 Alignment
PROC-0018
PROC-xxxx
M4 Assy Ready
Data for TMA and WFC performance
(milestone)
Pin M6
PROC-0133
Daytime thermal testing/tuning
PROC-0149
M6 Electrical Routing
PROC-0130
M3 Electrical Routing
PROC-0137
M6 Facilities Routing
PROC-0131
M3 Facilities Routing
PROC-0138
M4 Facilities Routing
PROC-0143
M3-6 Thermal Tuning Complete
(milestone)
M1-6 Aligned (milestone)
.TMA Ready
TMA Ready
Instrument Lab Ready
Coudé Lab Ready
SIM 4 Flow Chart, Telescope Optics (M1-M6) Complete
FOT Rack Install (Nasmyth)
PROC-0125
FO Hardware Install Instr Lab
PROC-0124
FO Controller Install (OSS/AZ)
PROC-0126
T-4Kready
Data for TMA performance
CASA (?)
SIM 3 Complete
Summit IT Infras in
place
SE2Einstalled
M4 Initial Fit-up
PROC-XXXX
Optical benches Install in Coudé
PROC-0152
M8 LT Align
PROC-0018
PROC-xxxx
Coudé benches on-
site
M9 Assy Installation
PROC-0158
M9 LT Align
PROC-0018
PROC-xxxx
M9 Assy Ready
Coudé Lab ready
Optical Bench Alignment
PROC--0153
M8 Assy Installation
PROC-0157
M8 Assy Ready
M10 Surrogate Installation
PROC-0155
M10 Surrogate CMM Align
PROC-0018
PROC-xxxx
M10 Surrogate
Ready
SIM 5 Complete
SHWS Installed and Aligned
PROC-0018
PROC-0156
Coudé Wavefront measurement
PROC-0018
Pointing Map(milestone)
M9a AssyInstall/Align
PROC-0018
PROC-0164
M9a Assy Ready
WFC-BS1 Assy Install/Align
PROC-0018
PROC-0163
WFC-BS1 Assy Ready
CL2a AssyInstall/Align
PROC-0018
PROC-0165
CL2a Assy
CL3a AssyInstall/Align
PROC-0018
PROC-0167
CL3a Assy
CL2 AssyInstall/Align
PROC-0018
PROC-0166
CL2 Assy
CL3 & CL4 AssyInstall/Align
PROC-0018
PROC--0168
CL3 & CL4 Assy
DL-FM1 AssyInstall/Align
PROC-0018
PROC-0169
DL-FM1 Assy Ready
Telescope Performance(milestone)
Seeing-limited
Alignment complete (milestone)
FIDO Beam Pointing verifications
PROC-0170
Coude Optics Day Time Thermal Test
PROC-0159
Surface Temp
Coude Optics Air knife tuning
PROC-0160
ISB Installation
PROC-0151
Pin benches
PROC-0154
Reconfiguration Testing
PROC-0171
SIM 4 Complete
SIM 5 Flow Chart, Coudé Optics and FIDO Complete
M9a Assy Control System Integration
and Test
M9a Assy Electrical Routing
DL-FM1 Assy Electrical Routing
DL-FM1 Assy System Integration and Test
Comp airready
CASA (?)
CASA (?)
Coude Servo Re-tune
Air Knife Ready
VBI Filter Wheel Install and Align R&B
PROC-0045
SIM5 M10 Surrogate Aligned
VBI On-site
VBI Optics Mounting
PROC-0045
VBI FM1 (Mounted) WFE Test R&B
PROC-0185
VBI Optics Cleaning(if needed)
PROC-0184
VBI On-site
VBI IL Check Out
PROC-0177
VBI IC GUI
VBI Controller InstallPROC-0176
VBI Optics Installation and
Alignment
PROC-0045
VBI Alignment Setup R
PROC-0045
VBI Interferometric Alignment R
PROC-0045
VBI R WFE performance@ 632.8 nm
VBI Alignment Setup B
PROC-0045
VBI Interferometric Alignment B
PROC-0045
VBI B WFE performance@ 632.8 nm
VBI Functional TestPROC-0189
VBI R&B final performance
VBI Collimating Lens CS Assembly and
Test R&B
PROC-0186
VBI Camera installed and Aligned R
PROC-0045
VBI Camera Installed and Aligned B
PROC-0045
VBI Camera CS Assembly and Test R
PROC-0187
VBI Camera CS Assembly and Test B
PROC-0188
SIM 6a complete
TCS
OCS
ICS
VBI R&B Thermal system operational
DHS
Coudé ready
VBI IL Electrical/Rack Routing
PROC-0175
SIM 5 Complete
FTS Ready
Instru Lab Ready
VBI Daytime Test R&B
PROC-0190
VBI Filter Wheel Setup and Filter Alignment R&B
PROC-0045
VBI Software Testing(milestone)
VBI Electrical Routing
PROC-0179
VBI Facilities routingPROC-0180
VBI Rack Install in Coude
PROC-0178
VBI Transport to Coude
PROC-0181
SIM 6a: VBI
VBI connectivity at Coude ready
Summit End-to End
Simulator
Coude Engineering Workstation
VBI Alignment PrepPROC-0182
VBI Filter Wheel CS Assembly and Test
R&BPROC-0183
CASA 9
CASA 10
Instrument Lab Ready
Coudé readyFTS/FMS
Ready
WFC Components IL Assembly and Test
PROC-0191
WFC Relay OpticsInstall
PROC-0205
Install M5 AssyPROC-0195
M10 Electrical Routing
PROC-0203
Context Viewer Install
PROC-0211
TMA Ready
LOWFS InstallPROC-0212
HOWFS InstallPROC-0213
LOWFS Test and CalibrationPROC-0215
HOWFS Test and CalibrationPROC-0216
Context Viewer Test and Calibration
PROC-0214
WCCS/TCS IntegrationPROC-0198
M10 Functional TestPROC-0207
Install M10 AssyPROC-0204
Non-common path measurement
PROC-0217
M5 Electrical Routing
PROC-0193
M5 Facility RoutingPROC-0194
M5 Rack InstallPROC-0192
SIM5: Optical Bench aligned
WFC Coude Electronics Racks
InstallPROC-0199
SIM8: Lower GOS Ready
WCCS/OCS IntegrationPROC-0218
Context viewer Electrical Routing
PROC-0208
HOWFS electrical Routing
PROC-0210
LOWFS Electrical Routing
PROC-0209
WFC Electronics Racks Cabling Install
and RoutingPROC-0200
WFC Coude Electronics Racks Electrical Routing
PROC-0201
WFC Coude Electronics Racks Facility Routing
PROC-0202
WFC Coude Optical Bench Facility
RoutingPROC-0206
SIM 5:BS1 Installed
SIM Completion
Post M5 Swap System Re-verificationPROC-0196
SIM 6b WFC Integration
M5 Assy Functional test
PROC-0197
WFC System Level Test
PROC-0219
CASA 11
CASA 12
WFC On-site
SIM 7 First Light Initiative
SIM6a CompleteSIM6b Complete
VBI Context Viewer Telescope Co-
pointingPROC-0225
WFC Context Viewer Telescope Co-
pointingPROC-0226
VBIRed+WFC Measurement and
TuningPROC-0227
ICS Ready
Telescope Optics Thermal Control
TuningPROC-0228
VBIBlue+WFC Measurement and
TuningPROC-0229
FLI VerificationPROC-0230
VBI Red + Blue +WFC Measurement
and TuningPROC-0231
SIM Completion VerficationPROC-0232
FLI Achieved
Both VBIs working with WFC
SIM 7 Completion
TMA/Coude V&V (GIS)
PROC-0233
Coude Servo Re-tune
PROC-0224
PA&C On-siteGOS frame install
PROC-0020
PA&C on site
PA&C IL Check Out
PROC-0023
PA&C Controller Install
PROC-0234
PA&C Functional Test
PROC-0023
PA&C final performance
Package X complete
TCS
OCS
GIS
PA&C – Other Systems TBD Testing
PROC-0240
TMA ready for GOS
install and align
GOS Electrical/Rack Temp Routing
PROC-0235
FTS Ready
Inst Lab Ready
PA&C Software Testing
(milestone)
PA&C Electrical routing
PROC-0237
PA&C Facilities routing
PROC-0236
PA&C rack install to OSS
PROC-0020
PA&C transport to OSS
PROC-0238
SIM 8: GOS Integration
PA&C GOS ready for interior assembly
Summit End-to End
Simulator
OSS Engineering Workstation
PA&C GUI
PA&C GOS thermal rack install to
NasmythPROC-0020
PA&C GOS ready for connectivity
Install Lower GOSPROC-0020
Align Lower GOSPROC-0036
GOS frame alignment
PROC-0036
Test Lower GOSPROC-0023
Lower GOS Available
Install GOS coversPROC-0020
Test GOS Thermal - Air
PROC-0023
Install Upper GOS level 1
PROC-0020
Align Upper GOS level 1
PROC-0036
Test Upper GOS level 1
PROC-0023
Install Upper GOS level 2
PROC-0020
Align Upper GOS level 2
PROC-0036
Test Upper GOS level 2
PROC-0023
Install Upper GOS level 3
PROC-0020
Align Upper GOS level 3
PROC-0036
Test Upper GOS level 3
PROC-0023
WFCS Limb Tracker Ready
Lower GOS Functional Test
PROC-0239
ViSP Feed Optics Mounting
PROC-xxxxx
ViSPCS Ready
ViSP Feed Optics install and align
PROC-xxxx
ViSP Daytime Test
PROC-xxxx
ViSP final performance
ViSP system level alignment
SIM 9c complete
TCS
OCS
On-Sun focus tests and boresight
checks
PROC-xxxx
WFCS operational
ICS
DHS
ViSP Instrument system testing and
calibration
PROC-xxxx
ViSP Electrical Routing
ViSP Facilities routing
FTS Ready
Coudé readyInstr Lab
Ready
ViSP Sub-Assemblies IL integration
PROC-xxxx
Optical tests report
ViSP IL checkout
PROC-xxxx
ViSP Rack install
ViSPCP
ViSP Feed Optics testing
PROC-xxxxx
ViSP Rack IL install and Electrical
Routing
Integration and alignment of Slit
assembly
PROC-xxxx
Integration and alignment of FM3
and FM4
PROC-xxxx
Integration and alignment of Grating
assembly
PROC-xxxx
Integration and alignment of
Collimator lens and Modulator
PROC-xxxx
Integration and alignment of optical
carriages
PROC-xxxx
Camera Assembly and Test
PROC-xxxx
ViSP Instrument testing with VBI
PROC-xxxx
VBI operational
ViSPCS integration and test
Carriage Baseplate installed and aligned
ViSP On-site
Optical Bench
Aligned
ViSP IL hardware cleaning and
transport to Coude
Optics mounting in sub-assemblies
ViSP On-site
Lower GOS Ready
SIM9c ViSP integration