+ All Categories
Home > Documents > Single span box

Single span box

Date post: 11-May-2017
Category:
Upload: jaffna
View: 234 times
Download: 6 times
Share this document with a friend
24
NAME OF WORK:- CONSTRUCTION OF SYPHON AQUEDUCT AT R.D. m of L.M.C. OF GIP A DATA FOR AQUEDUCT Discharge 1.326 cumec cumec Bed width 1.72 m m water Side slope 1.5 :1 F.S.D. 0.86 m m Free Board 0.50 m m Bed slope 1 in 5000 C.B.L. 270.95 m 271 m F.S.L. 271.81 m m T.B.L. 272.31 m 272.31 m Span 2.60 m m M.W.D. 1.36 m m B DRAIN DATA :- Catment area of Nalla. 0.30 sqkm = 0.12 Sq mile Nalla Bed (N.S.L) 271.07 m m 1 Hydraulic Design :- Flood discharge as per dicken's formula. Q = C x A 3/2 Q = 1800 x( 0.12 ) 3/4 Q = 360.5 cusec Q = 10.2 Cumec Say = 11.00 cumec Area required for opening Assume Valocity of nalla limited to 3.00 meter/ sec. A = Q / V = 11.00 / 3.00 = 3.667 sqm say 4 sqm Assume box size = 2.00 x 2.00 meter Area of box = 4 sqm Nos. of opening required = 4 / 4 = 1 Note:- (A)Box culvert design as per I.R.C. SP-20 (I) Abutment wall thickness = 0.45 m (Iii) Top slab thickness = 0.25 m (IV) Bottom slab thickness = 0.25 m 2 DESIGN OF TROUGH :- Design Constants:- For HYSD Bars Concrete M-20 1.36 271.81 2.60 271.07 nos GOVERMENT OF RAJASTHAN WATER RESOURCES DEPARTMENT GARARDA IRRIGATION PROJECT 25485 CANAL DATA 0.50 5000 vertical 0.86 1.3261 3.01
Transcript
Page 1: Single span box

NAME OF WORK:- CONSTRUCTION OF SYPHON AQUEDUCT AT R.D. m of L.M.C. OF GIP

A DATA FOR AQUEDUCT

Discharge 1.326 cumec cumec

Bed width 1.72 m m

water Side slope 1.5 :1

F.S.D. 0.86 m m

Free Board 0.50 m m

Bed slope 1in 1 in 5000

C.B.L. 270.95 m 271 m

F.S.L. 271.81 m m

T.B.L. 272.31 m 272.31 m

Span 2.60 m m

M.W.D. 1.36 m m

B DRAIN DATA :-

Catment area of Nalla. 0.30 sqkm = 0.12 Sq mile

Nalla Bed (N.S.L) 271.07 m m

1 Hydraulic Design :-

Flood discharge as per dicken's formula.

Q = C x A 3/2

Q = 1800 x( 0.12 )3/4

Q = 360.5 cusec

Q = 10.2 Cumec

Say = 11.00 cumec

Area required for opening

Assume Valocity of nalla limited to 3.00 meter/ sec.

A = Q / V

= 11.00 / 3.00

= 3.667 sqm say 4 sqm

Assume box size = 2.00 x 2.00 meter

Area of box = 4 sqm

Nos. of opening required = 4 / 4

= 1

Note:- (A)Box culvert design as per I.R.C. SP-20

(I) Abutment wall thickness = 0.45 m

(Iii) Top slab thickness = 0.25 m

(IV) Bottom slab thickness = 0.25 m

2 DESIGN OF TROUGH :-

Design Constants:- For HYSD Bars Concrete M-20

1.36

271.81

2.60

271.07

nos

GOVERMENT OF RAJASTHAN

WATER RESOURCES DEPARTMENT GARARDA IRRIGATION PROJECT

25485

CANAL DATA

0.50

5000

vertical

0.86

1.3261

3.01

Page 2: Single span box

for water side force

sst = = 2000 Kg/cm2

= 2400 Kg/cm3

scbc = = 70 Kg/cm2

= 1000 Kg/cm3

m = 13

13 x 70

13 x 70 + 2000

j=1-k/3 = 1 - 0.313 / 3 = 0.90

R=1/2xc x j x k = 0.5 x 70 x 0.90 x 0.313 = 9.80

3 DESIGN OF VERTICAL WALL:- = cm

= 1.36 m span = 2.60 m

1000 x 1.36 ^3

6

419.2 x 100

9.80 x 100

The wall trough is to be designed as a beam having a span of = 2.60 m

between supports Hence thickness should be equal to span/30

span 2.60 x 100

30

20 cm cover = 5 cm 15

x 100

2000 x 0.90 x 15

100 x 20 x 0.3

3.14 x 10 x 10

4 x 100 4 x

= 0.79 x 100 / 6.00 = 13.08 cm

Hence Provided 10 mm bars @ 13 cm c/c

0.1 ( 30 - 10 )

-

100 x 20 x 0.24

4.9

2

using 8 A = 3.14xdia2

= 3.14 x 8 x 8

4 x

= 0.50 x 100 / 2.43 = 20.69 cm

8 @ 20 cm c/c Each face

8 mm F @ mm c/c

4 Design of Horizontal slabe :-

20 cm cover = 5 cm = 15 cm2

= BW+ 2xwall thicknes = 3.41 m

Loading = BW+ wall thickness = 3.21 m

Total width of slab =bw+2x wall thickness

Effective width of slab

cm

20.00

cm

Adopt wall thickness

Effct. Thickness

spacing =A/Ast

Hence Provided mm bars

Adopt thickness of slab "T" =

300Also provided 2 leged shear strirrups

mm bars = 0.50 cm

2

4 x100 100

cm2

100

2.43 cm2

= 4.9=

%

Steel of Each face = =

Area of distribution steel

required= 0.24 %

10

of x section area

A =3.14xdia

2

=

spacing =A/Ast

using 10 mm bars =

minimum steel to be provided for

distribution = 0.3 - = 0.24

45

= 0.79 cm2

0.3 % = 6.00 cm2

100

100

But minimum steel to be

provided=

1.56 cm2

of x section area =

419.24=Ast = BMx100/sstxjxD=

cm

Steel required

= = 8.6730

But providing thickness"D"= Effective

Say 9.00

kgm

Effective depth

required =Rxb = = 6.54

= = 419.2

cm

Max.depth of water

BM=WH^3/6 = BM

0.313m*c+sst

k=m*c

= =

wt. of concrete

wt of water

Page 3: Single span box

Load of water column = mwd x 1000 = 1.36 x 1000 = kg/m2

Wt of slab = wt of concrete x Area of slab = 2500 x 1 x 0.2 = kg/m2

= kg/m2

WL2

1860 x 3.21 x 3.21 Kg-m

8 8

2396 x 100 cm

9.80 x 100

20 cm cover = 5 cm = 15

x 100

2000 x 0.90 x 15

100 x 20 x 0.3

3.14 x 12 x 12

4 x 100 4 x

= 1.13 x 100 / 8.91 = 12.68 cm

Hence Provided 12 mm bars @ 12 cm c/c half the bars will be bent up at to check the

moment developed

0.1 ( 20 - 10 )

- 10

100 x 20 x 0.27

5.43

2

using 8 A = 3.14xdia2

= 3.14 x 8 x 8

4 x

= 0.50 x 100 / 2.71 = 18.51 cm

8 @ 18 cm c/c Each face

< 20

cm

500

Effective depth

required == 15.63 cm=

= 0.50 cm2

Rxb

Max. possible segging moment = =

4 x100 100

mm bars

spacing =A/Ast

Hence Provided mm bars

2.71 cm2

=

Steel of Each face = =

of x section area =

45-

5.43 cm2

100

cm2

100

spacing =A/Ast

hogging

%minimum steel to be provided for

distribution = 0.27

But minimum steel to be

provided= 0.3 %

Area of distribution steel

required= 0.27 %

= 0.3

cm2

100

using 12 mm bars = A =3.14xdia

2

=

= 6.00

= 1.13

of x section area =

But providing thickness = Effective depth

Steel required

Ast = BMx100/sstxjxD=2395.70

= 8.91 cm2

Total load 1860

2396=

1360

Page 4: Single span box

= 1 Nos.

Page 5: Single span box

o o o

2 x 12 mm F bars

Distibution steel o o 8 mm2 ledge stirrups@ F.B. o

8 mm F @ 20

o o FSL o

10 mm F bars@ 26 c/c

o o o

o o 10 mm F bars@ 13 c/c o

o o o

12 mm F bars@ 24 c/c

o o 12 mm F bars@ 12 o

8 mm F bars@ 18

o o o

o o o o o o o o o o o o o o

o

o o o o o o o o o o o o

Trough Reinforcement Detail

main bars Distribution bars

12mm F 85 c/c 10mm F 250 c/c

o o o o o o o

o o o

2.00 m span

Cut off wall

Retaining wall

0.2

0.200.20

271.81

0.50

3.01

30 c/c

1.36

300 2000

150

150

416

160

240

300

1688

1960

FSD 0.86

0.65CBL 270.95

Page 6: Single span box

u/s section

2:1 2:1

Nalla

Retaining wall

2 :1 1: 1

d/s section

TBL

H.F.L. FSL H.F.L.

Nalla level S/R Nalla level

Cut off wall 3 :1

c.c.m-15

7.015.30

2.92

0.3

0

0.3

0

268.452.00

271.07

272.07

1.00

0.30

R.L. 268.15

268.70

R.L.

CBL

3.00

0.30

270.95

R.L.

1.72

2.000.3

0

1.00

1.5

0

3.30

1.00

0.9

0

1.2

0

4.00

2.00

f.b.

fsd

f.b.

1.72

0.50

fsd

2.000.3

0

1.00

0.45

0.86

0.50

0.3

0

0.40

2.00

0.20

0.86

Canal

3.01

271.81

272.31

0.20

3.00

2.00

0.45

0.200.20

0.20

0.20

7.30

0.3

0

Cut off

wall M20

272.07

0.25

0.25

2.00

Page 7: Single span box

(f) (a)

(f)

O O O O O O O O O O O

( j) (b) (g)

(g)

(d) (d)

(c) (c)

(j) (j)

(e) (e)

(g) (h) (j) (i) (g)

Detail of Reinforcement for box culvert

2

0.25

0.25

0.450.45 2.00

7.20

Page 8: Single span box
Page 9: Single span box
Page 10: Single span box
Page 11: Single span box

NAME OF WORK:-unflume Glacis Fall at R.D.

Sno. Item L H qty Sno

1 1

Hard soil mixed with kanker/

U/S cut off wall 1 x 26.20 x 0.70 x 2.80 = 51.35

Glacis 2 x 4.90 x 1.60 x 2.80 = 43.90 2

Cistern portion 1 x 8.14 x 25.90 x 2.80 = 590.28

d/s cut off 1 x 26.20 x 0.70 x 1.30 = 23.84

total 709.38

2 cum

3

U/S cut off wall 1 x 26.20 x 0.70 x 0.30 = 5.50

Glacis 2 x 4.90 x 1.60 x 0.30 = 4.70

Cistern portion 2 x 8.14 x 25.90 x 0.30 = 126.49

d/s cut off 1 x 26.20 x 1.45 x 0.30 = 11.40

total 148.09

3 cum 4

5

u/s cut off 1 x 26.20 0.40 x 0.80 = 8.38

Glacis 2 x 4.90 x 1.30 x 0.80 = 10.19

cistern portion 2 x 8.14 x 1.30 x 0.80 = 16.93 6

d/s cut off 1 x 26.20 0.40 x 0.80 = 8.38

wing wall D/S 2 x 0.60 x 1.30 x 0.80 = 1.25

total 45.14

4 cum

7

wing wall U/S &d/s 2 x 1.50 + 0.60 x + 0.4 x 1.70 = 1.43

2

DETAIL ABSTRACT OF COST

100 m of R.M.C. Bardha

Earth work in excavation including loading

unloading disposal and dressing of

excavated area within inial lead of 50m and

lift upto 1.5m in dry or moist including

drsssing of excaveted area ,dewatering

wherever required and all applicable taxes

Cement Concrete in (1:3:6) M10 well mixed

and laid in position complete including all

leads of all construction material Including

Curing and finishing having well graded

broken stone aggregate of maximum size

R.R. Stone masonry (using R.R stones

where 75% stone to be not less than 15 cm

in size in any direction and weighing not less

than 23 kg.) for Foundation including

curing all leads of construction materials &

all taxes and with initial lift /de lift of 5 m from

G.L.etc complete .In cement sand mortar 1:5

R.R. Stone masonry (using R.R stones

where 75% stone to be not less than 15 cm

in size in any direction and weighing not less

than 23 kg.) for superstructure including

curing all leads of construction materials &

all taxes and with initial lift /de lift of 5 m from

G.L.etc complete .In cement sand mortar 1:5

Page 12: Single span box

Glacis 2 x 4.90 x 1.30 + 0.4 x 1.70 + 2.10 = 8

cistern portion 2 x 8.14 x 1.30 + 0.40 x 2.10 = 29.06

d/s cut off 2 x 1.50 + 0.60 x 1.30 + 0.40 x 2.10 = 3.75

2 2

total 34.23 9

5

u/s bed 1 x 0.40 x 23.00 x 0.20 = 1.84

Crest 1 x 0.90 + 0.60 x 23.00 x 0.60 = 10.35

2

Glacis 1 x 4.47 x 23.00 x 0.60 + 1.10 = 87.43

2

cistern bed 1 x 2.20 x 23.00 x 1.00 = 50.60

1 x 2.20 x 23.00 x 0.90 = 45.54

1 x 2.10 x 23.00 x 0.80 = 38.64

1 x 2.00 x 23.00 x 0.50 = 23.00

total 257.40

cum

6

wing wall face 2 x 1.90 x 1.70 = 6.46

Crest 2 x 0.90 x 1.70 = 3.06

Glacis 2 x 4.00 x 1.70 + 2.10 = 15.20

cistern 1 x 6.50 x 2.10 = 13.65

1 x 2.00 x 2.10 + 1.40 = 3.50

total 41.87

sqm

7

wing wall out side 4 x 1.90 x 0.85 = 6.5

side wall out side 2 x 13.44 x 1.05 = 28.2

total 34.68

8 sqm

Plaster in cement sand mortar (1:4) including

raking of joint ,smooth finishing with & curing

etc. including all leads of all construction

matarial complete of thickness ; 20mm

Flush and ruled pointing om stone masonry

including raking of joint and curing etc.

complete including of all leads of all

construction materials in cement mortar 1:3

Providing and laying cement concrete

copping in (1:2:4) with maximum size of

cresher broken aggregate upto 20mm

including shuttering etc with all leads of

material complete in all respect.in thickness

Cement Concrete in (1:2:4) M15 well mixed

and laid in position complete including all

leads of all construction material Including

Curing and finishing having well graded

broken stone aggregate of maximum size

upto 20mm

Page 13: Single span box

wing wall 4 x 1.90 x 0.4 = 3.04

side wall 1 x 13.44 x 0.4 = 5.38

total 8.42

9 sqm

as per item no 1 709.38

cum

Providing and laying cement concrete

copping in (1:2:4) with maximum size of

cresher broken aggregate upto 20mm

including shuttering etc with all leads of

material complete in all respect.in thickness

Rehandling of excaveted matrial inlcuding

loading unloading and dressing within inial

lead of 50 m and lift 1.5 m with cost of

dewatering wherever required and all

applicable taxes and lavies etc. complete in

Page 14: Single span box

NAME OF WORK:-unflume Glacis Fall at R.D. 100 m of R.M.C. Bardha

Item QTY Rate Unit Amount

709.38 34.00 cum 24119.00

Hard soil mixed with kanker/ boulders,morrum

(Rate as per irrigation BSR2006Ch 5/1c)

148.09 1650.00 cum 244349.00

(Rate as per irrigation BSR2006Ch 7/6d)

45.14 1270.00 cum 57328.00

(Rate as per irrigation BSR2006Ch 8/2e)

(Rate as per irrigation BSR2006Ch 8/13a) 34.23 37.00 cum 1267.00

257.40 1973.00 cum 507851.00

(Rate as per irrigation BSR2006Ch 7/5d)

41.87 67.00 sqm 2805.00

(Rate as per irrigation BSR2006Ch 9/4b)

34.68 45.00 sqm 1561.00

(Rate as per irrigation BSR2006Ch 9/15)

ABSTRACT OF COST

Earth work in excavation including loading unloading

disposal and dressing of excavated area within inial lead

of 50m and lift upto 1.5m in dry or moist including

drsssing of excaveted area ,dewatering wherever

required and all applicable taxes and levies etc.

complete in all respect

Cement Concrete in (1:3:6) M10 well mixed and laid in

position complete including all leads of all construction

material Including Curing and finishing having well

graded broken stone aggregate of maximum size upto

20mm

R.R. Stone masonry (using R.R stones where 75%

stone to be not less than 15 cm in size in any direction

and weighing not less than 23 kg.) for Foundation

including curing all leads of construction materials & all

taxes and with initial lift /de lift of 5 m from G.L.etc

complete .In cement sand mortar 1:5

Masonry in superstructure for Dam and other works.

Cement Concrete in (1:2:4) M15 well mixed and laid in

position complete including all leads of all construction

material Including Curing and finishing having well

graded broken stone aggregate of maximum size upto

20mm

Plaster in cement sand mortar (1:4) including raking of

joint ,smooth finishing with & curing etc. including all

leads of all construction matarial complete of thickness,

20mm

Flush and ruled pointing om stone masonry including

raking of joint and curing etc. complete including of all

leads of all construction materials in cement mortar 1:3

Page 15: Single span box

8.42 146.00 sqm 1229.00

(Rate as per irrigation BSR2006Ch 12/17a)

709.38 23.00 cum 16316.00

(Rate as per irrigation BSR2006Ch 5/8c)

total 856825.00

2 %contengency 17137.00

873962.00

Say RS 8.74 Lacs

Providing and laying cement concrete copping in (1:2:4)

with maximum size of cresher broken aggregate upto

20mm including shuttering etc with all leads of material

complete in all respect.in thickness of 50 mm

Rehandling of excaveted matrial inlcuding loading

unloading and dressing within inial lead of 50 m and lift

1.5 m with cost of dewatering wherever required and all

applicable taxes and lavies etc. complete in all respect

Page 16: Single span box

A Trough

Main verticl wall 10 1.61 / 0.13 = 13 x 2 x 1.4 = 36 @ 0.616 = 22.00

distribution 8 2.90 / 0.2 = 16 x 4 x 7.9 = 506 @ 0.394 = 200.00

shear strirrup 8 2.90 / 0.3 = 11 x 2 x 3 = 66 @ 0.394 = 26.00

Hanch 10 2.90 / 0.3 = 11 x 2 x 0.7 = 15 @ 0.616 = 9.00

Total 257

Kg

Detail of reinforcement

Bars /type Fmmlength of

cc/ space = number x row wt /mt.

total

wt(kg) =@x length total lengh

Page 17: Single span box

(As per I.R.C.SP- 20)

Bar Dia Spacing

a 10 140 2x75+2420= 2570 7010 52 1 133.64 0.616 83

b 12 130 2x75+2420= 2570 7010 55 1 141.35 0.887 126

c 10 140 2x710+2420= 3840 7010 52 2 399.36 0.616 247

d 10 200 2x75+2420= 2570 7010 37 2 190.18 0.616 118

e 10 95 710+710= 1420 7010 75 2 213 0.616 132

f 8 140 710+710= 1420 7010 52 2 147.68 0.394 59

g 8 150 2x200+750= 1150 7010 48 4 220.8 0.394 88

h 10 160 2x75+2420= 2570 7010 45 1 115.65 0.616 72

i 10 140 2x75+2420= 2570 7010 52 1 133.64 0.616 83

j 10 200 7010 2001 12 8 672.96 0.616 415

Total 1214

T1 = 250 T2 = 250 kg

L1 = 2250 L2 = 2250

row of

bars

total

length

Opening 2000 X 2000

Reinforcement required for Barrel 2.00 x2.00 m

Bar mark Shape of Bar

Hunch 150 x 150

weight/met

er (kg)

total

weight

(kg)Length of bar

Length of

concrete No of bars

Page 18: Single span box

(As per I.R.C.SP- 20)

Bar Dia Spacing

a 10 190 2x75+3720= 3870 7010 37 1 143.19 0.616 89

b 12 120 2x75+3720= 3870 7010 59 1 228.33 0.887 203

c 12 190 2x1110+3520= 5740 7010 37 2 424.76 0.887 377

d 10 200 2x75+3520= 3670 7010 36 2 264.24 0.616 163

e 10 95 1110+1110= 2220 7010 74 2 328.56 0.616 203

f 8 190 710+710= 2220 7010 37 2 164.28 0.394 65

g 8 150 2x200+800= 1200 7010 47 4 225.6 0.394 89

h 10 150 2x75+3720= 3870 7010 47 1 181.89 0.616 113

i 10 190 2x75+3720= 3870 7010 37 1 143.19 0.616 89

j 10 200 3300 17 8 953.36 0.616 588

Total 1687

T1 = 400 T2 = 300 kg

L1 = 3400 L2 = 3300

7010

row of

bars

total

length Bar mark Shape of Bar

Length of

structure No of bars

total

weight

(kg)

weight/met

er (kg)

Reinforcement required for Barrel 3.00 x 3.00 m

Opening 3000 x 3000

Length of bar

Hunch 150 x 150

Page 19: Single span box

(As per I.R.C.SP- 20)

Bar Dia Spacing

a 10 155 2x75+4820= 4970 7010 46 1 228.62 0.616 141

b 16 155 2x75+4820= 4970 7010 46 1 228.62 1.578 361

c 12 155 2x1410+4620= 7440 7010 46 2 684.48 0.887 608

d 10 200 2x75+4620= 4770 7010 36 2 343.44 0.616 212

e 16 155 1410+1410= 2820 7010 46 2 259.44 1.578 410

f 10 155 1410+1410= 2820 7010 46 2 259.44 0.616 160

g 8 150 2x200+850= 1250 7010 47 4 235 0.394 93

h 12 155 2x75+4820= 4970 7010 46 1 228.62 0.887 203

i 10 155 2x75+4820= 4970 7010 46 1 228.62 0.616 141

j 10 200 4450 23 8 1289.84 0.616 795

Total 3124

T1 = 450 T2 = 350kg

L1 = 4450 L2 = 4350

Shape of BarOpening 4000 X 4000

No of bars weight/met

er (kg)

total

weight

(kg)Length of bar

Length of

structure

7010

Hunch 150 x 150

Reinforcement required for Barrel 4.00 x 4.00 m

row of

bars

total

length Bar mark

Page 20: Single span box

(As per I.R.C.SP- 20)

Bar Dia Spacing

a 10 160 2x75+5920= 6070 7010 44 1 267.08 0.616 165

b 16 160 2x75+5920= 6070 7010 44 1 267.08 1.578 422

c 16 160 2x1710+5720= 9140 7010 44 2 804.32 1.578 1269

d 12 200 2x75+5720 5870 7010 36 2 422.64 0.887 376

e 16 160 1710+1710= 3420 7010 44 2 300.96 1.578 475

f 10 160 1710+1710= 3420 7010 44 2 300.96 0.616 186

g 8 150 2x200+900= 1300 7010 47 4 244.4 0.394 97

h 16 160 2x75+5920 6070 7010 44 1 267.08 1.578 422

i 12 160 2x75+5920 2570 7010 44 1 113.08 0.887 101

j 10 200 5500 28 8 1570.24 0.616 968

Total 3894

T1 = 500 T2 = 400kg

L1 = 5500 L2 = 5400

Hunch 150 x 150

Reinforcement required for Barrel 5.00 x 5.00 m

7010

Length of bar

weight/met

er (kg)

total

length

Opening 3000 X 3000 Length of

structure Bar mark Shape of Bar No of bars

row of

bars

total

weight

(kg)

Page 21: Single span box

(As per I.R.C.SP- 20)

Bar Dia Spacing

a 10 140 2x75+2420= 2570 7010 52 1 133.64 0.616 83

b 12 130 2x75+2420= 2570 7010 55 1 141.35 0.887 126

c 10 140 2x710+2420= 3840 7010 52 2 399.36 0.616 247

d 10 200 2x75+2420= 2570 7010 37 2 190.18 0.616 118

e 10 95 710+710= 1420 7010 75 2 213 0.616 132

f 8 140 710+710= 1420 7010 52 2 147.68 0.394 59

g 8 150 2x200+750= 1150 7010 48 4 220.8 0.394 88

h 10 160 2x75+2420= 2570 7010 45 1 115.65 0.616 72

i 10 140 2x75+2420= 2570 7010 52 1 133.64 0.616 83

j 10 200 7010 2250 13 8 729.04 0.616 450

Total 1249

T1 = 250 T2 = 250kg

L1 = 2250 L2 = 2250

Bar markLength of

concrete

Opening 2000 X 2000Shape of Bar

weight/met

er (kg)

total

length

row of

barsNo of bars

Hunch 150 x 150

total

weight

(kg)Length of bar

Reinforcement required for Barrel 2.00 x2.00 m

Page 22: Single span box

62 nos main bars Distribution bars 86 nos main bars Distribution bars

12mm F 120 c/c 8mm F 160 c/c 12mm F 85 c/c 10mm F 250 c/c

Wearing coat 75mm thicko o o o o o o o o o o o o

o o o o o o o o o o o o o o o o o o o o o o

Cross section of culvert

60 nos main bars Distribution bars 1.50 m span 2.00 m span

16mm F 125 c/c 10mm F 175 c/c

71 nos main bars Distribution bars

16mm F 105 c/c 12mm F 200 c/co o o o o o o o

o o o o o o o o o o o o o o o o

o o o o o o o o o o

o o o o o o o o o o o o o o o o o o

3.00 m span

4.00 m span

53 nos main bars Distribution bars 65 nos main bars Distribution bars

20mm F 140 c/c 12mm F 175 c/c 20mm F 115 c/c 12mm F 150 c/c

o o o o o o o o o o o o o o o o o o o o o o

o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o

5.00 m span 6.00 m span

NOTES:- 1 Concrete:- M-25 2 Steel:- HSDY as per IS-1786 3 Cover:- 20mmat bottom & 40mm at side

4 In 1.5M, 2.0M &3.0M span only one Bar is to be crankedin each side in four bars in all other span crank alternative bars.

5 All bars cranked one end onlythese are placed with crank on left side and right side alternatively

6 Surface steel at top longitudinal -10mm @300mm c/c length a shown in sketh & transverse -10mm @300c/c all through out in logitudinal

400 5000

790

320 4570

150

6000 400

400 5360

430 480

4840

890

400 400

150 4040

150

150

4000 300

590

290 3650

300

3330

150

370300 3000 300

150 2508

150

506

220 2810

240

1688

130 1575

300

150

150

150

300

375

150

2000 300

160 1960

210

450

7500 450

6600

416

300 3001500

150 1256

Page 23: Single span box

provided steel in the Zone where main steel is not available plus 150mm on either side

93 nos main bars Distribution bars

20mm F 90 c/c 12mm F 125 c/c

o o o o o o o o o o o o

o o o o o o o o o o o o o o o o o o o o o o o o

8.00 m span

62 nos main bars Distribution bars Area & weight of tor Bar

25mm F 120 c/c 12mm F 110 c/c F Factore

6

8

o o o o o o o o o o o o o o o o o o o o o o o o o o 10

o o o o o o o o o o o o o o o o o o o o o o o o o o 12

14

16

18

20

22

10.00 m span 25

28

32

36

40

50 19.64

6.157

8.04

10.17

12.56

3.142

3.801

4.909

1.131

1.539

2.011

2.545

6.31

2.0

7.98

9.85

15.40

2.466

2.98

3.854

4.83

0.785

0.785

0.784

0.784

0.784

0.784

0.785

0.784

0.785

0.784

0.786

0.617

0.888

1.208

1.578

0.222 0.784

0.785

0.786

0.785

wt/m

0.40

A

0.283

0.503

400 10000 400

150

0.785

1120

520 7280

1260

670 8990

150 8400

750

600

400 8000 400

150 6680

150

Page 24: Single span box

Surface steel at top longitudinal -10mm @300mm c/c length a shown in sketh & transverse -10mm @300c/c all through out in logitudinal


Recommended