Site Director, Trawsfynydd Nuclear Site
Dave Wilson
Date: 22 June 2011
10 April 2023 3
Introduction
• Magnox Limited, the NDA and EnergySolutions
• What are we doing?
• Magnox Optimised Decommissioning Plan (MODP)
• Integrated Waste Strategy
• Stakeholder Engagement
10 April 2023 4
Magnox Limited, the NDA and EnergySolutions
100% Owned
Parent Body Agreement
M&O ContractMagnox Limited
NDA
EnergySolutionsEU Ltd
10 April 2023 5
What are we doing?
• Maximise the value of safe electricity generation at 2 sites
• Defuelling at 3 sites• Acceleration of decommissioning at 2 sites• Optimise decommissioning at 3 sites• Reshape the workforce in partnership with the TUs
10 April 2023 6
Magnox Optimised Decommissioning Plan
Wylfa Trawsfynydd Hunterston A
Hinkley Point A
Chapelcross
Sizewell A Bradwell
Berkeley Oldbury Dungeness A
10 April 2023 7
Integrated Waste Strategy
• Very Low-level waste (VLLW)• Low-level waste (LLW)• Intermediate-level waste (ILW)• Metals• Oils• Mini-stores• Asset value and cross-estate
working• Programmisation
10 April 2023 8
Stakeholder Engagement
• Site Stakeholder Groups• The way we engage
– Cooling towers
• Skills for the UK– EdF/Magnox Limited agreement
• Sustainability– The Energy Island; Beyond Chapelcross
• Partnership with local communities
10 April 2023 9
Summary
• Working as a strategic delivery partner for the NDA• Bringing the UK Magnox programme to a dignified end• Clarity of work for each of the Magnox sites• Delivering the customers waste strategy• Engaging with stakeholders and in partnership with our
workforce