  • 7/27/2019 Site Inspection Check List2

    1/38

    AGIP Oil Co. Ltd. Libyan Branch

    El Sharara-Mellitah 30 Pipeline PETROJET

    Libya

    DOC. No. : 0222-160-P-PT-PTJ-0027 REV. No. : A2 Page 36 of 36

    EL SHARARA-MELLITAH 30EL SHARARA-MELLITAH 30 PIPELINESPIPELINES

    CONTRACT NO. 222

    SITE INSPECTION CHECK LIST

    Document No. 0222-160-P-PT-PTJ-0027

    A2 02/01/05 Issued for final approval

    A1 23/12/04 Issued for approvalM. Elamir A. Khater Samir Helmi E. Trovato

    REV. DATE STATUS PREPARED CHECKED APPROVED COMPANY

  • 7/27/2019 Site Inspection Check List2

    2/38

    Inspection Check List RegisterNo

    .

    Control

    Doc.

    No.

    Description Rev. Remarks

    1 FQ-001 PRE-CONSTRUCTION SURVEY A2

    2 FQ-002 PIPE HANDLING AND TRANSPORTATION A2

    3 FQ-003 ROW CONSTRUCTION A2

    4 FQ-004 STRINGING A2

    5 FQ-005 LINING-UP, CLAMPING & WELDING A2

    6 FQ-006 WELDING /Pipe Lines- WELDING /Tie ins A2

    7 FQ-007 NON-DESTRUCTIVE TESTING-RT A2

    8 FQ-008 NON-DESTRUCTIVE TESTING-UT A2

    9 FQ-009 NON-DESTRUCTIVE TESTING-PT & MT A2

    10 FQ-010 NON-DESTRUCTIVE TESTING-VT A2

    11 FQ-011 TRENCHING A2

    12 FQ-012COATING PART1FIELD JOINT COATING HSS &

    REPAIRING OF PIPE COATING

    A2

    13 FQ-013 BEDDING & PADDING A2

    14 FQ-014 LOWERING-IN A2

    15 FQ-015 FOC LAYING A2

    16 FQ-016 HYDROSTATIC TESTING A2

    17 FQ-017 DRYING & NITROGEN FILLING (HOLD) -

    18 FQ-018 COLD BENDING A2

    19 FQ-019 CROSSING A2

    20 FQ-020 CIVIL WORK A2

    21 FQ-021 CATHODIC PROTECTION A2

    22 FQ-022 ELECTRICAL INSTALLATION A2

    23 FQ-023 INSTRUMENT INSTALLATION A2

    24 FQ-024 COATING PART II-COATING FOR GROUND &

    UNDERGROUND FACILITIES

    A2

    25 FQ-025 PIGGING & CLEANING A2

    26 FQ-026 REINSTATEMENT OF ROW AND RESTORATION WORK A2

    27 FQ-027 MECHANICAL INSTALLATION A2

    AGIP Oil Co. Ltd. Libyan Branch

    El Sharara-Mellitah 30 Pipeline PETROJET

    Libya

    DOC. No. : 0222-160-P-PT-PTJ-0027 REV. No. : A2 Page 36 of 36

  • 7/27/2019 Site Inspection Check List2

    3/38

    28 FQ-028 BACKFILLING A2

    29 FQ-029 PAINTING ABOVE GROUND A2

    30 FQ-030 PRE-COMMISSIONING (FOR INSTRUMENT SYSTEM) A2

    31 FQ-031 PRE-COMMISSIONING (FOR ELECTRIC SYSTEM) A2

    32 FQ-032 PRE-COMMISSIONING (FOR CATHODIC PROTECTION SYSTEM) A2

    33 FQ-033 HYDROTEST LVS and PTS (HOLD) -

    34 FQ-034 MATERIAL/EQUIPMENT INSPECTION, RECEIVING AND

    STORAGE

    A2

    PRE-CONSTRUCTION SURVEY

    Location/Area Pipe Size Report No.Alignment Sheet No. : From : To :

    Morphology Situation :

    Plain Hill Desert Land Sand Dunes Rocky Area Wadi

    Type of Vegetation : Open View Cultivated Desert

    Control Doc. No. : FQ-001Control Doc.

    Activities Control Requirements or Accept Criteria Inspection Record Remind

    1. Instruments & toolsPerformance of measuring instrument and tools meet technicalspecification.

    2. Centerline locationCheck-up the information of centerline location and

    measurement.

    3. Stakes

    Each stake is clear, in right location and in right color (type):

    1) Centerline Stake - steel bar (black)

    2) Edge Stake - red flag

    4.Underground

    obstacle

    Site mark of underground obstacle is clear.

    5. Interval of each

    stake

    1) Centerline Stake - steel bar (black)

    2) Edge Stake - red flag

    6. Maintenance Each stake is kept in the effective time period.

  • 7/27/2019 Site Inspection Check List2

    4/38

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    DateNote: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    5/38

    PIPE HANDLING AND TRANSPORTATION

    Location/Area Pipe Size Report No.From : To :

    Control Doc. No. : FQ-002

    Activities Control Requirements or Accept CriteriaInspection

    Record Remind

    1.Pipe acceptance The pipe length and the trim size are complied with the Contract. (Spot Check).

    2.Inspection

    1) Coating of the pipes

    2) Bevel

    3) Pipe identification mark

    4) Coating Visual Inspection

    3.Storage and

    preservation

    The lifting tools are covered with soft material to prevent damage of the coating

    and bevel.

    4.Bevel

    Protection

    The bevel ends of the pipe are protected with bevel protector during handling

    and stocking.

    5.SupportsThe supports on the truck shall meet the requirement and shared the weight

    equally. The supports are covered with soft material.

    6.Security The secure belts or other facilities are sufficient to fasten pipes duringtransportation.

    7.On trail

    On each trail:

    1) 30pipes are no more than 3 tires.

    8.Pipe stockpiling

    area inmarshalling

    1) Be level off, tamped and cleaned.

    2) The drainage and anti-rolling measures are ready prior pipes are stocked.

    3) The height of the sand ridge is no less than 200mm.

    4) Pipes are piled in types.

    5) 30pipes are no more than 4 tires.

    6) The damaged pipes are separated.

    9.Pipe stockpiling

    area on site

    1) Be clear from vegetation, stubble, stones and flattened.

    2) The location is kept at least 50m from vertical projection on the ground of

    overhead power line conductors.

    3)The minimum distance from the ground to the bottoms of pipes is 200mm.

    4) The pipes are piled on sand bags or sand ridge with sand bags.

    5) Anti-rolling measures are taken.

    Inspection Conclusion

    Proceeding work: YES NO Date:Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    DateNote: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    6/38

    ROW CONSTRUCTION

    Location/Area Pipe Size Report No.Alignment Sheet No.: From : To :

    Morphology Situation:

    Plain Hill Desert Land Sand Dunes Rocky Area Wadi

    Excavated Material: To Dump Area Piled Up Screen Plant

    Control Doc. No. : FQ-003

    Activities Control Requirements or Accept Criteria Inspection Record Remind

    1.ROW width

    The width of the ROW is 30m when pipelines are

    installed separate trenches, 25m when pipelines areinstalled the same trench.

    2.Underground

    obstacle

    The warning signs for the underground obstacle are in the

    right location and clear.

    3.CleaningThe ditches, dikes and steep slopes are cleared up to

    comply with the requirements of construction.

    4.High/low points

    removal

    The sharp high points and low points are removed to

    allow bending and laying of pipelines in accordance with

    the approved drawing.

    5.Water CrossingThe water crossing prevention measures for the ditches

    are checked.

    6.Vehicle access Graded vehicle access strip is acceptable.

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    DateNote: Activities record format is duly filled and signed.

    TRENCHING

  • 7/27/2019 Site Inspection Check List2

    7/38

    Location/AreaFrom :

    Pipe SizeTo :

    Report No.

    Morphology Situation:

    Plain Hill Desert Land Sand Dunes Rocky Area Wadi

    Work Area Characteristic: Sandy Area Sandy/Rocky Area

    Control Doc. No. : FQ-011

    Activities Control Requirements or Accept Criteria Inspection Record Remind

    1.Centerline The ditching is excavated follow the right centerline stakes.

    2.Warning signThe warning signs for the underground /ground facilities are

    obvious.

    3.Minimum cover

    1) Loose soil areas 1.000 m.

    2) Rocky areas as per AGIP specs no. 3435-160-C-SP-

    TEK-00003, item 6.3

    3) Cultivated areas 1.500 m.

    4.DimensionsThe dimensions (depth, width and slope ratio) of the ditch

    are complied with the procedure.

    5.Cleaning The ditch is cleaned to prevent pipe coating damage.

    6.Soil piling The excavated soil is piled 1m away from the edge of ditch.

    7.Protective measures

    When the route is close to/on the underground facilities,

    Company properties, private properties and Government

    properties, approved protective measures are taken.

    8.High water tableIn the area with high water table, water in ditch is drained in

    time.Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor CompanyName

    Signature

    DateNote: Activities record format is duly filled and signed.

    STRINGING

  • 7/27/2019 Site Inspection Check List2

    8/38

    Location/Area Pipe Size Report No.Alignment Sheet No.: From : To :

    Control Doc. No. : FQ-004

    Activities Control Requirements or Accept Criteria Inspection Record Remind

    1. Pipe sizeThe pipe size is complied with the specifications of

    drawings before stringing.

    2. Off loadingWhen off loading pipes, there are protection measures for

    the pipe ends.

    3. Gap There is a gap every 500 m.

    4. Safe distancePipes are stringed over 1.0 m away from edge of the

    trench bank.

    5. Slope area

    In the case of stringing in slope area:1) If the slope is greater than 15 the stringing is done

    accordance with the progress of welding.

    2) If the slope is greater than 30 pipes are strung in

    trench.

    6. Longitudinal weldThe longitudinal weld of the pipe is positioned within

    30from the 0clock position.

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor CompanyName

    Signature

    DateNote: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    9/38

    LINING-UP AND CLAMPING & WELDING

    Location/Area Pipe Size Report No.From : To :

    Control Doc. No. : FQ-005

    Activities Control Requirements or Accept CriteriaInspection

    RecordRemind

    1. Pipe size The pipe size is correct.

    2. Pipe cleaning

    Before lining-up, the pipe ends are clean no less than 30mm from

    the end surface. The cleaning Crew is no more than 5 welds ahead

    of welding Crew. The pipes are cleaned from inside too.

    3. Bevel face The bevel is cleaned and the dimensions are correct.

    4. Bevel repairing Damaged pipe ends and bevels are repaired as per the procedure.

    5. Clamp removing

    The clamp is removed after.:

    1) Full root bead is completed when internal clamp is used.

    2) More than 60% of the total length of the root bead when

    external clamp is used.

    6. High-lowThe high-low of the pipe with same wall thickness is no more than

    2mm (in small section, at maximum 3mm is allowed).

    7. Pipe piece The pipe piece is longer than twice of the pipe diameter or 1m.

    8.Longitudinal weld. The longitudinal welds of the 30 pipes are positioned within

    30from 0 oclock and offset more than 200mm.

    9.Support

    The aligning pipes are supported and fixed on the load-bearing

    structural wood skids with sand bags. (Remove the skids after the

    welding).

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    DateNote: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    10/38

    WELDING P/LLocation/Area Pipe Size Report No.Alignment Sheet No.: From : To :

    Control Doc. No. : FQ-006

    Activities Control Requirements or Accept CriteriaInspection

    RecordRemind

    1.Welder qualification The re-welding is performed as per the specifications. The welder is qualified.

    2. Welding material

    1) Electrodes, wire used in the pipeline welding are maintained and used in accordance with the

    manufacturer instructions.

    2) Low hydrogen type electrode is baked out before welding, the baking temperature and duration

    as specified by the manufacturer. Backed electrodes are stored in the insulation tank on site.

    3) Electrodes baked for two times shall not be used in the site welding.

    3.Welding equipment All the welding equipments are used under good and safe conditions.

    4.Welding environment

    The welding will stop in the:

    -Very strong wind (As per welding inspector company)

    -Raining or relative humidity > 90%

    5. Pipe preparation1) The pipe is cleaned inside.

    2) The damaged bevel and pipe ends are identified and repaired.

    6.Pre-heating

    Pre-heating temperature is at 10020 for ND30 pipeline WT more than 12,7mm, or

    the ambient temperature is below 0. Except above, it is Pre-heated at 4050

    when the pipe ends are wet, raining or high humidity. The pre-heating range is at least

    100mm from pipe ends.

    7.Welding

    1) Remove internal line up clamp after the first root pass finished; remove external line

    up clamp after 60% of root pass completed.

    2) The cleaning among runs is completed properly.

    3) Preheat 100.

    8.Welds inspection

    1) The surface of weld is free of defect such as scatter, welding slag, surface air bubble,

    non-fusion and undercut, etc. It shall be cleaned if any.

    2) High-low: the pipe with same wall thickness is no more than 1.6mm (in small

    section, at maximum 3mm is allowed).

    3) The longitudinal welds of the 30 pipes are positioned within 30from 0 oclock

    and offset more than 200mm.

    9.Parent material repair

    The small defects or damaged areas on the base metal tested by NDT is repaired and

    eliminated by grinding. The allowed wall thickness decrease and welds repairing is inaccordance with the applicable specifications and standards.

    10.NDTWelds are inspected with specified NDT method and accepted in accordance with the

    specified criteria.

    11.Repair & re-inspection All the rejected welds are repaired and re-inspected according to WPS.

    12.Weld mark Welds are marked in accordance with the procedure.

    13.Seal The welded pipeline is sealed with proper cover to prevent foreign mater entering.

    Inspection Conclusion Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company Welding Inspector

    Name

    SignatureDate

    NON-DESTRUCTIVE TESTING-RT

  • 7/27/2019 Site Inspection Check List2

    11/38

    Location/Area Pipe Size Report No.From : To :

    Control Doc. No. : FQ-007

    Activities Control Requirements or Accept Criteria Inspection Record Remind

    1.Operator qualification Verify the Certificates of the RT operators.

    2.RT equipments Verify the Certificates of the RT equipments.

    3.RT operationOperation is carried out in accordance with the approved RT

    procedure.

    4.Darkroom treatmentThe films are developed and fixed in accordance with the

    procedure.

    5.Film quality1) The sensitivity is proper2) The density range is 2.0-3.5

    3) Free of mechanical and chemical damage.

    6.Films interpretationFilms are interpreted in accordance the specified acceptance

    criteria.

    7.Report All records and testing results shall be documented.

    8.Film storage All films shall be kept properly till hand-over to Company.

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company Welding InspectorName

    Signature

    DateNote: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    12/38

    NON-DESTRUCTIVE TESTING-UTLocation/Area Pipe Size Report No.From : To :

    Control Doc. No. : FQ-008

    Activities Control Requirements or Accept Criteria Inspection Record Remind

    1.Operator qualification Verify the Certificates of the UT operators.

    2.UT equipments Verify the Certificates of the UT equipments.

    3.UT operationOperation is carried out in accordance with the approvedUT procedure.

    4.Indication interpretationIndication is interpreted in accordance the specifiedacceptance criteria.

    5.Report All records and testing results shall be documented.

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company Welding Inspector

    Name

    Signature

    DateNote: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    13/38

    NON-DESTRUCTIVE TESTING-PT/MTLocation/Area Pipe Size Report No.From : To : PT MT

    Control Doc. No.: FQ-009

    Activities Control Requirements or Accept Criteria Inspection Record Remind

    1.Operator qualification Verify the Certificates of the operators.

    2.Material & equipments Verify the Certificates of the material and equipments.

    3.OperationOperation is carried out in accordance with the approved

    procedure.

    4.Indication interpretation Indication is interpreted in accordance the specified

    acceptance criteria.

    5.Report All records and testing results shall be documented.

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company Welding Inspector

    Name

    Signature

    DateNote: Activities record format is duly filled and signed.

    NON-DESTRUCTIVE TESTING-VT

  • 7/27/2019 Site Inspection Check List2

    14/38

    Location/Area Pipe Size Report No.From : To :

    Control Doc. No.: FQ-010

    Activities Control Requirements or Accept CriteriaInspection

    RecordRemind

    1.Welding inspection

    1) The surface of weld is free of defect such as scatter,

    welding slag, surface air bubble, non-fusion and undercut,

    etc. It shall be cleaned if any.

    2) High-low: the pipe with same wall thickness is no more

    than 1.6mm (in small section, at maximum 3mm is allowed).

    3) The longitudinal welds of the 30 pipes are positioned

    within 30from 0 oclock and offset more than 200mm.

    2.Material & equipmentsVerify the Certificates of the material and equipments and

    technicians.

    3.OperationOperation is carried out in accordance with the approvedprocedure.

    4.Indication interpretationIndication is interpreted in accordance the specifiedacceptance criteria.

    5.Pipe classFrom the different pipe wall thickness shall be grinded of

    groove as per ANSI/ASME B31.4

    6.Report All records and testing results shall be documented.

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company Welding Inspector

    Name

    Signature

    DateNote: Activities record format is duly filled and signed.

    COATING PART I-FIELD JOINT COATING HSS & REPAIRING OF PIPE COATING

  • 7/27/2019 Site Inspection Check List2

    15/38

    Location/Area Pipe Size Report No.From : To :

    Control Doc. No. : FQ-012

    Activities Control Requirements or Accept CriteriaInspection

    RecordRemind

    1.Operator

    qualificationOnly qualified operators are employed to apply shrink sleeves on site.

    2.Equipments and

    tools

    The liquefied gas heater is used for heating, flame spray burning blower is in

    normal condition.

    3.Material

    1) Supplied with qualified certificate of inspection and instruction manual.

    2) Be stored in a dry ventilated area.

    3) Keep products sealed in original packing and avoid exposure to directsunlight, rain, dust or other adverse environmental elements.

    4) The storage temperatures of coating materials as per vendor instructions.

    4.Pipe ends

    cleaning

    Within the length of 50 mm on weld joint on both sides are free from oil dirt,

    soil scar, slag, spatters.

    5.Surface

    treatment of

    pipe joint

    1) The mainline coating edges are beveled to 30.

    2) Warm the joint area to 40-50 before grit blasting.

    3) The width of sand blasting to the coating is no less than 85mm

    6.Appliciation of

    epoxy primer

    Apply mixed epoxy to a minimum uniform thickness of 4 mils on all

    exposed bare metal and less than 10 mm onto the adjacent pipe coating in

    width.

    7. Pre-heatingPreheat the epoxy and the abraded coating to8595 in the whole

    circumference.8.Installation and

    location of tapeInstall the tape in accordance with the procedure.

    10.Checking and

    inspecting

    1) No cracks or holes in sleeve backing.

    2) The overlap of the tape on the existing coating shall be at least 50 mm in

    both sides.

    3) Holiday detection with 20kv voltage of leakage detection.

    4)U.T. for thickness painting / Surface profile comparator

    5) Destructive testing (Peel Test) (Adhesion of top coated system)

    12.Repairing of

    pipe coatingRepair the pipe coating in accordance with procedure.

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    DateNote: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    16/38

    BEDDING & PADDINGLocation/Area Pipe Size Report No.Alignment Sheet No.: From : To :

    Control Doc. No. : FQ-013

    Activities Control Requirements or Accept CriteriaInspection

    RecordRemind

    1.Bottom situation

    of trench

    1) The water has been drained completely.

    2) In soft ground section, the soil at the bottom of trench meet the requirement

    of bedding and trench bottom level; or

    3) Laying bed have finished and leveled up.

    2.Material

    1) The laying bed is consist of fine graded soil or sand with the maximum particlesize of 0-5mm in 75% corresponding proportion, 5-15mm in 15% and 15-20mm

    in 10%.

    2) The padding material is crushed and screened before used in rock area if the

    material is come from the excavated material, and it should meet the requirement

    of work procedure.

    3.Thickness ofbedding

    The bedding thickness is at least 200mm along the ditch bottom.

    4.Padding and FOC

    protection

    1) As-built survey has been carried out and recorded and then 300mm more

    fine material is padded on the FOC, at least 300mm is padding on pipe.

    300mm of fine material is padded on the top of the pipe before laying FOC and

    then 300mm more fine material is padded on the FOC and pipe.

    5.Room left fortie-in

    Pipe at each side of tie-in and FOC joints are left exposed a certain length foroperation and padded later.

    6.Pipeline anchor In high slope the pipeline is anchored with sand or soil bags and the upper andlower part of the block is compact solidly.

    7.Open-cut crossingBedding and padding is carried out in open-cut crossing area meets the drawingsTPYE in the procedure.

    ** Item 4 and 5 : signature by FOC inspector

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    DateNote: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    17/38

    LOWERING-INLocation/Area Pipe Size Report No.Alignment Sheet No.: From : To :

    Morphology Situation:

    Plain Hill Desert Land Sand Dunes Rocky Area Wadi

    Type of Vegetation: Open View Cultivated Desert

    Control Doc. No. : FQ-014

    Activities Control Requirements or Accept CriteriaInspection

    RecordRemind

    1.Ditch dimensionsThe dimensions (depth, width and slope ratio) of the ditch are complied with theprocedure.

    2.Dithc cleaning The ditch is cleaned to prevent pipe coating damage.

    3.Holiday detection There is no holiday under

    4.Pre-checkThere are no person, equipment and tools in the ditch. There are no one standing,

    no construction material or tools placed between the pipeline and ditch.

    5.Pipe endsprotection

    The pipe ends are sealed with cups to prevent ingress of foreign objectives.

    6.Lifting

    equipments &tools

    The lifting equipments and tools are under good conditions as per HSE specs.

    7.Lower-in

    4 sidebooms , space 20m, are used to lower-in the 30 pipe, the maximum height

    for the pipeline lift above the ground and above the bottom of the ditch is less

    than 1m.

    Inspection Conclusion

    Proceeding work: YES NO Date:Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    DateNote: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    18/38

    FOC LAYINGLocation/Area Report No.From : To :

    Morphology Situation:

    Plain Hill Desert Land Sand Dunes Rocky Area Wadi

    Type of Vegetation: Open View Cultivated Desert

    Control Doc. No. : FQ-015

    Activities Control Requirements or Accept Criteria Inspection Record Remind

    1.Visual check1) Type of the FOC is complied with the drawing.

    2) No damage and distortion of the reel and cable

    2.Depth & locationThe depth & location of the FOC is complied with the

    procedure.

    3.Caution tape Caution tape is buried above the FOC.

    4.Tie-in of FOC Tie-in of FOC is complied with the procedure.

    5.Spare cable Enough spare cable is left.

    ** Signature by Company FOC inspector

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    DateNote: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    19/38

    HYDROSTATIC TESTINGLocation/AreaFrom :

    Control Doc. No. : FQ-016

    Pipe Size:

    To :

    Report No.

    DRYING & NITROGEN FILLING (OPTION)Location/Area Pipe Size: Report No.From : To :

    Activities Control Requirements or Accept Criteria Inspection Record Remind

    1.Water treatmentTesting water should answer for the requirement of the

    criterion/specification after test and approved by Company.

    2.Testing systemThe testing system should be installed and inspected according

    to relative procedure.

    3.Work permitInform Company and get the Work permit after Testing system

    qualified.

    4.Testing Testing should follow the procedure, and record the changes ofall of the relative parameters.

    5.DrainageDraining should answer for the Testing procedure and HSE

    procedure.

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    Date

  • 7/27/2019 Site Inspection Check List2

    20/38

    Control Doc. No. : FQ-017

    Activities Control Requirements or Accept Criteria Inspection Record Remind

    1.Equipment &ganges

    1) The instruments and equipments used in the process of

    vacuum drying and nitrogen filling are answer for the

    requirement of work procedure.

    2) Pressure gauge and sensor and other instruments

    indispensable shall be examined and acceptable.

    2.Vacuum drying

    1) The installation of vacuum drying system is acceptable

    2) Leak check is acceptable.

    3) Final pressure is acceptable.

    3.Records and

    reports for dryingAll records and reports are accomplished according to the

    requirements of work procedure.

    4.Preparation for

    nitrogen filling

    The equipments for nitrogen filling having been installed

    properly and vacuum drying accomplished acceptable.

    5. Nitrogen inspect Purity and dew point of nitrogen are acceptable and be record.

    6.Pressure inspectionThere is no less than 95% of nitrogen inside of pipeline trunk

    with a pressure of 0.5 bar as minimum.

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    DateNote: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    21/38

    COLD BENDINGLocation/AreaFrom :

    Pipe Size:

    To :

    Report No.Control Doc. No. : FQ-018

    Activities Control Requirements or Accept CriteriaInspection

    RecordRemind

    1.Pipe size The pipe type and size is complied with the drawing.

    2.Pipe coatingThe coating shall be free from bubbles, pits, wrinkles and with uniform

    color.

    3.Mandrel positionThe accuracy of the mandrel position is kept with pre-set rods (the rod atthe center point of bending machine and the rod close to the lift tongue).

    4.Wall thicknessreduction

    Use a pachometer to test the Wall thickness reduction at trial-produce

    phrase of cold bending:1) 5 points on the outer arc of the bending section.

    2) The wall thickness reduction is no less than 95% of the originate wallthickness.

    5.Straight section

    length

    The length of the straight section is not less than 1.5m from the open end

    of the bended pipe.

    6.Out of roundnessThe Out-of-roundness is not more than 2% of the outside diameter of thepipe at any point.

    7.Bend coating Visual and holiday detection of the bend coating.

    8.Identification Check the identification of the bend.

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    DateNote: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    22/38

    CROSSINGLocation/AreaFrom :

    Pipe Size:

    To :

    Report No.Control Doc. No. : FQ-019

    Activities Control Requirements or Accept Criteria Inspection Record Remind

    1.Preparation

    1) All of the underground facilities are located in and/or nearcrossing location.

    2) All necessary information (drawing, distance, depth, structureand geological condition etc.) are provided to the working

    spread.3) Proper warning signs and temporary road are ready in the

    crossing area.4) Ditching depth meets the design requirement.

    2.Equipments All of the equipments used for crossing are in good condition.

    3.Casing installationThe casing pipes for mainline and FOC are installed accordingto the construction procedure.

    4.Inspection *

    1) Offset of crossing centerline is acceptable.

    2) The benchmark of crossing is correct.3) 100% of NDT for the mainline joints are acceptable.

    4) Hydrostatic testing is up to grade.5) Electrical insulation test is carried out and acceptable

    according to the procedure.6) Holiday inspection is acceptable

    ** Item 3 : Signature by FOC inspector

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor CompanyName

    Signature

    DateNote: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    23/38

    CIVIL WORKLocation/AreaFrom :

    Control Doc. No. : FQ-020

    Report No.To :

    Note: Activities record format is duly filled and signed.

    Activities Control Requirements or Accept Criteria Inspection Record Remind

    1.Construction drawingConstruction drawings be used in the work site are approved

    by Company and they are the latest version.

    2.Mateirial inspectionAll of the materials be used in the construction are inspected

    and qualified.

    3.Ground leveling and

    location measurement

    1) Obstacles underground are all fixed and marked.

    2) Obstacles aboveground are all removed, and ground level

    achieve to the requirement of drawings.

    3) Survey and measurement of location are carried out as per

    the procedure, and such work be affirmed.

    4.Equipment foundation

    construction

    Equipment foundation construction be carried out as per the

    regulation of procedure.

    5. Road constructionRoad construction be carried out as per the regulation of

    procedure.

    6.Undergroun building

    1) Underground building construction be carried out as per

    the regulation of procedure.

    2) Floating floor installation meets the requirement of the

    design.

    7.Aboveground building

    1) Aboveground building construction be carried out as perthe regulation of procedure.

    2) Laying of external wall tiles meet the requirement of the

    design.

    8.Fence constructionFence construction be carried out as per the regulation of

    procedure.

    9.Tests and records

    1) All of the inspections and tests are completed as per the

    procedure.

    2) All of the relative records are made out and pass muster.

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    Date

  • 7/27/2019 Site Inspection Check List2

    24/38

    CATHODIC PROTECTIONLocation/Area Pipe Size: Report No.From : To :

    Control Doc. No. : FQ-021

    Note: Activities record format is duly filled and signed.

    Activities Control Requirements or Accept Criteria Inspection Record Remind

    1.Material and

    equipment

    All of the material and equipment should be qualified according to the

    engineering documentation and/or other requirement and proved with

    relative certificates.

    2.Seat testing pile

    position

    The location of testing pile should meet the requirement of approved

    drawings.

    3.Installation

    (testing pile/equipment)

    1) Treating of the cable ends answer for the requirement of procedure.2) The location of welding point is at the correct place.

    3) Steel pipe/casing surface treatment is qualified.

    4) Tools and materials for welding are correct.

    5) The connection of cable to pipe/casing/testing pile/anode is correct.

    6) Sacrificial anodes are installed correct

    7) The coating of all joints are qualified.

    8) Installation and debugging of all equipments for cathodic protection

    should be up to mustard.

    4.Testing

    1) The resistance between welding point and steel pipe/casing shall not

    more than 0.1 Ohm.

    2) All joints are acceptable through holiday inspection.

    3) The potential testing that be carried out according to the procedure

    is up to the mustard.

    4) The system debugging is completed and acceptable.

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    Date

  • 7/27/2019 Site Inspection Check List2

    25/38

    ELETRICAL INSTALLATIONLocation/AreaFrom :

    Report No.To :

    Installing facility: No.:

    Control Doc. No. : FQ-022

    Activities Control Requirements or Accept Criteria Inspection Record Remind

    1.Cable Laying

    Cable laying order, route comply with construction

    drawing, the insulation resistance between cable andgrounding is not less than 500M

    2.GroundingSystem

    Grounding trench depth more than 800MM, Tie-in with

    grounding electrodes and grounding line fastness, thegrounding resistance is not more than 10.

    3.Power

    DistributionPanel

    The position of PDP's construction is comply withconstruction drawing required.

    4.Lighting

    The loops of lighting are right, haven't short circuit

    between different loops and haven't grounding of theloops. the lighting system work right.

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    DateNote: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    26/38

    INSTRUMENT INSTALLATIONLocation/AreaFrom :

    Report No.To :

    Installing facility: No.:

    Control Doc. No. : FQ-023

    Activities Control Requirements or Accept Criteria Inspection Record Remind

    1.Preparation for

    construction

    1. Construction environment meets requirement.

    2. Equipment and tools for installation are ready.

    3. Check the type, certification and instruction of installed

    equipment material.

    4. Pre-fabrication field is ready (if necessary)

    2.Instrument

    installation

    1. Local instrument, remote instrument, level instrument,

    electrical actuator, fire spy head, fuse cable, and other kind of

    instrument installation is according to corresponded

    installation flowchart and procedure.

    2. Installation location is correction as per corresponded

    drawings.

    3. Record.

    3.The connection of

    the instrument to

    process

    Allocation an installation of connection of the instruments to

    process meet requirements.

    4.Installation of

    support

    Supports prefabricate and install as per corresponded drawings

    and procedure.

    5.Cables andjunction

    1. Location of digging, laying of cables, installing of conduits

    and junction boxes are correct.

    2. Record.

    6.EarthingEvery location needing earth is connected to the earthling

    network and connecting is good.

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    DateNote: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    27/38

    COATING PART II-COATING FOR GROUND & UNDERGROUND FACILITIES

    Location/Area Pipe Size: Report No.From :

    Control Doc. No. : FQ-024

    To :

    Note: Activities record format is duly filled and signed.

    Activities Control Requirements or Accept Criteria Inspection Record Remind

    1.Preparation of

    coating

    1) Coating material is qualified.

    2) The tool is suitable for coating operation.

    3) Facility/parts of the system that will be coated has a qualified

    surface treatment.

    4) Work circumstance answer for the requirement.2.Coating

    operation

    Coating operation accord with procedure or the regulation of

    manufactory.

    3.Inspection in

    coating

    1) Visual check is acceptable. (As per Surface profile

    comparator

    2) Holiday inspection is acceptable.

    3) Thickness inspection is acceptable

    4) Peel test is acceptable (if need).

    4.Repair All of the repair have finished and acceptable.

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    Date

  • 7/27/2019 Site Inspection Check List2

    28/38

    PIGGING & CLEANINGLocation/Area Pipe Size: Report No.From : To :

    Control Doc. No. : FQ-025

    Activities Control Requirements or Accept Criteria Inspection Record Remind

    1.Pig and pig traps

    1) Pigs for cleaning and gauging are answer for the

    requirement of work procedure.

    2) Pig receiver and pig launcher are installed correctly.

    2.Cleaning system

    installation

    Pig cleaning system and the relative equipments and instruments

    are installed properly in good state.

    3.Inspection The gauging plate shall be examined and taken photosimmediately after the pigs have get from pig receiver.

    4.Record and reportRecords and reports for the process of pig cleaning and gauging

    have been accomplished according to the work procedure.

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    DateNote: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    29/38

    REINSTATEMENT OF ROW AND RESTORATION WORKLocation/Area Pipe Size: Report No.From : To :

    Morphology Situation: Plain Hill Desert Land Sand Dunes Rocky Area Wadi

    Type of Vegetation: Open View Cultivated Desert

    Control Doc. No. : FQ-026

    Note: Activities record format is duly filled and signed.

    Activities Control Requirements or Accept Criteria Inspection Record Remind

    1.Reinstatement of ROW

    1) Public\ private lawns or courtyards or entrances etc. in the

    ROW have the same or better condition than before.

    2) The cropland and water supply and drainage system andwalls/fences which be destroyed are all be reinstated and

    acceptable.3) All the residual materials and waste materials are moved tothe proper place.

    4) The original physiognomy in other place are all bereinstated.

    5) The bund on the trench is acceptable.

    2.Reinstatement ofbanks and

    embankments

    The banks and embankments which be destroyed are allreinstated and acceptable.

    3. PhotographThe reinstatement of physiognomy be proved by essentialphotographs.

    4.Pipeline marker postsand warning signs

    The marker posts (KP posts, CP posts etc.) and warning signs

    are all setup and installed according to the relative requirementand acceptable.

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    NameSignature

    Date

  • 7/27/2019 Site Inspection Check List2

    30/38

    STATION MECHANICAL INSTALLATIONLocation/AreaFrom :

    Report No.To :

    Control Doc. No. : FQ-027

    Activities Control Requirements or Accept Criteria Inspection Record Remind1.Acceptance to

    Equipment, fitting

    & material

    All equipments, fitting and material meet the requirements of

    engineering and the quality certificates and/or calibration

    certificates are the evidence.

    2.CleaningThe piping system should be cleaned before the installation of

    equipments and fittings.

    3.Inspection to the

    base of theequipment

    Inspect the center line of equipment base.

    4.Installation to the

    equipment, fitting

    and auxiliary

    1) The installation to equipment and fitting accordant

    correspond with the related procedure.

    2) Station weld meets the requirements of the related WPS for

    station

    5. Inspection* 1) Visual check is acceptable

    2) Dimension check is acceptable

    3) NDT check is acceptable

    6. Record and report Records and reports for the process of installation have been

    accomplished according to the work procedure.

    ** Item 5 : Signature by company welding inspector

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    DateNote: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    31/38

    BACKFILLINGLocation/Area Pipe Size Report No.Alignment Sheet No.: From : To :

    Morphology Situation:

    Plain Hill Desert Land Sand Dunes Rocky Area Wadi

    Control Doc. No. : FQ-028

    Activities Control Requirements or Accept Criteria Inspection Record Remind

    1.Backfilling material

    1) There is no stones in which the diameter more than 150mm

    2) The surface material answer for the requirement of original

    morphology situation.

    2.Shape The shape of ground meets the requirements of work procedureafter backfilling.

    3.Residual materialResidual material has been disposed in proper methods

    acceptable.

    4.Backfilling highThe crown high above trench cannot be more than 300mm

    except in cultivated area.

    5.Room left for tie-in

    and FOC joints*

    pipe at each side of tie-in and FOC joints are left exposed a

    certain length for operation and padded later.

    6.Pipeline anchorIn high slope the pipeline is anchored with sand or soil bagsand the upper and lower part of the block is compact solidly.

    7.Crossing areaThe backfilling soil in crossing area meets the requirement of

    design.

    ** Item 5 : Signature by FOC inspector

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    DateNote: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    32/38

    PAINTING ABOVE GROUNDLocation/AreaFrom :

    Report No.To :

    Control Doc. No. : FQ-029

    Activities Control Requirements or Accept Criteria Inspection Record Remind

    1.Preparation of

    painting

    1) The tool is suitable for painting operation

    2) Facility/parts of the system that will be painted has a

    qualified surface treatment

    3) Surface roughness test is acceptable

    2.Painting operationPainting operation accord with procedure, specifications and

    regulation of manufactory.

    3.Inspection in

    painting

    1) Visual check is acceptable2) Thickness check is acceptable

    3) Destructive tests is acceptable

    4) Check of adhesion is acceptable

    4.Repair All the repair have finished and acceptable

    **Note : Signature by painting inspector contractor

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    Date

    Note: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    33/38

    PRE-COMMISSIONING (FOR INSTRUMENT SYSTEM)LocationFrom :

    Report No.To :

    System :

    Control Doc. No. : FQ-030

    Activities Control Requirements or Accept Criteria Inspection Record Remind1. Preparation prior to

    pre-commissioning

    1) Mechanical completion is ready

    2) Personnel for pre-commission are ready.

    2. Pre-commissioning

    All equipments are subjected to the following tests

    The connections and continuity test

    Insulation testVerify every instrument in good condition and calibration.

    3. Record Each record required is ready

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    Date

    Note: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    34/38

    PRE-COMMISSIONING ( FOR ELECTRIC SYSTEM)LocationFrom :

    Report No.To :

    System:

    Control Doc. No. : FQ-031

    Activities Control Requirements or Accept Criteria Inspection Record Remind1.Preparation prior to

    pre-commissioning

    1) Mechanical completion is ready

    2) Personnel for pre-commission are ready.

    2.Pre-commissioning

    Check and test following items:

    Solar panels unit

    Control boardLow voltages switchboard (D.C or A.C.)

    Storage battery

    Trailer-movable diesel generator

    Rectifier cabinet

    3.Record Each record required is ready

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    Date

    Note: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    35/38

    PRE-COMMISSIONING (FOR CATHODIC PROTECTION YSTEM)

    LocationFrom :

    Report No.To :

    System:

    Control Doc. No. : FQ-032

    Activities Control Requirements or Accept Criteria Inspection Record Remind1.Preparation prior to

    pre-commissioning

    1) Mechanical completion is ready

    2) Personnel for pre-commission are ready.

    2.Pre-commissioning

    Check and test following items:

    Insulating joints and casing protection pipes

    Reference cells and test points

    Ground bedsDC feeders (TR/R)

    Electrical cables

    Pipeline natural potential

    3.Record Each record required is ready

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    Date

    Note: Activities record format is duly filled and signed.

  • 7/27/2019 Site Inspection Check List2

    36/38

    HYDROTEST LVS and PTS

    Number of LVS and PTSFrom :

    Report No.To :

    Control Doc. No. : FQ-033

    ActivitiesControl Requirements or Accept

    Criteria

    Inspection

    RecordRemind

    1.Water for PressureTest

    The water for pressure test comply with the requirement

    of procedure.

    2.Testing SystemThe pressure test system shall be installed and checkedaccording to the related procedure and obtained

    Companys approval.

    3.Testing Pressure

    During testing it shall be in accordance with the

    requirement of the procedure and the pressure comply

    with the procedure.

    4. DewateringDewatering shall be in accordance with the Testing

    procedure and HSE procedure after testing.

    5. RecordEach record required is in accordance with the

    requirement.

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    Date

    MATERIAL/EQUIPMENT INSPECTION, RECEIVING AND STORAGE

  • 7/27/2019 Site Inspection Check List2

    37/38

    Purchase Order No. :

    Goods Name :

    Packing List No. :

    Report No. :

    Control Doc. No. : FQ-034

    Activities Control Requirements or Accept CriteriaInspection

    RecordRemind

    1.Acceptance

    of material and

    equipment

    The material and/or equipment are inspected as per the Purchase Order and Packing

    List for acceptance with qualified certificates. Damaged or unqualified material is

    reported to Warehouse Supervisor and managed according to the procedure.

    2.Piece count

    and visual

    check

    The account is correct, the packing is not damaged and polluted, the goods is free from

    damp and corrosion.

    3.Storage andpreservation

    Accepted material or equipment is stored in accordance with the relevant procedure;

    preservation measures are taken according to the storage requirements of the material

    recommended by material Vendors.4.Control of

    Non-conformed

    Products

    Unacceptable material or equipment is isolated and marked. No non-conformed

    material is issued for construction. Detail inspection record of damaged and unqualified

    material or equipment is provided.

    5.Requirements

    for warehouse.

    The warehousing is complied with the following items:

    1) closed by fences.

    2) At least 10cm support is padded and graded for drainage.

    3) The elements are shielded with proper material (like polyethylene, tarps or

    temporary structures).

    4) The boxes and package are not stacked unless allowed by Vendors instructions.

    5) Visual check for the material is convenient.

    6) Identification marks are clear and visible.7) Materials on shelves are carefully classified.

    8) Other specifications in the Vendors instruction.

    6.Handling &

    transporting

    equipments.

    The handling and transporting equipments are operated under good condition.

    Inspection Conclusion

    Proceeding work: YES NO Date:

    Approved by Contractor Rep. QA/QC Contractor Company

    Name

    Signature

    Date

  • 7/27/2019 Site Inspection Check List2

    38/38

    AGIP Oil Co. Ltd. Libyan Branch

    El Sharara-Mellitah 30 Pipeline PETROJET

    Libya

    DOC. No. : 0222-160-P-PT-PTJ-0027 REV. No. : A2 Page 36 of 36