Preparation of an action plan for SITWA/ANBO support services Christophe BRACHET, Hubert ONIBON
Popular Tags:
19
1 RAOB/ANBO INFRASTRUCTURE DEVELOPMENT IN THE AFRICAN TRANSBOUNDARY RBOs Preparation of an action plan for SITWA/ANBO support services Christophe BRACHET, Hubert ONIBON
Transcript
Page 1: SITWA Infrastructure Study

1

RAOB/ANBO

INFRASTRUCTURE DEVELOPMENT IN THE AFRICAN TRANSBOUNDARY RBOs

Preparation of an action plan for SITWA/ANBO support services

Christophe BRACHET, Hubert ONIBON

Page 2: SITWA Infrastructure Study

2

Rappels sur la situationBesoins et prioritésProposition de Plan d’actionConclusions

Page 3: SITWA Infrastructure Study

Développer des projets transfrontaliers d’infrastructure de l’eau

Renforcer les cadres transfrontaliers de gestion pour l’intégration régionale

Garantir la sécurité de l’eau pour le développement socio-économique du continent africain, tout en veillant à la protection de l’environnement, à l’atténuation des effets des changements climatiques et à l’adaptation à la variabilité et au changement

3

Objectifs du PIDA pour les Eaux transfrontalières

Page 4: SITWA Infrastructure Study

4

Page 5: SITWA Infrastructure Study

La demande de produits alimentaires va doubler d’ici 2040

Seules 20% des surfaces potentiellement irrigables exploitées en Afrique

Capacités de stockage de l'eau et agriculture irriguée : Afrique au niveau le plus faible au monde

Les grands projets d’infrastructures hydrauliques se comptent en nombre de sites possibles

5

Situation des grandes infrastructures en Afrique

Page 6: SITWA Infrastructure Study

Irrigation: superficie équipée par rapport aux terres irrigables

6

Page 7: SITWA Infrastructure Study

7

L’investissement dans l’irrigation ne suffira pas à éviter une crise alimentaire et une crise de l’eau.

Il faudra aussi un investissement significatif pour: Accroître fortement la productivité de l’agriculture pluviale Accroître (doubler) l’efficience de l’irrigation Développer le commerce intra-africain

La solution à la crise de l’eau agricole se situe en grande partie en dehors du secteur de l’eau : Aspects financiers et institutionnels Ecoulement des produits Contraintes techniques Forts coûts d’investissements

Page 8: SITWA Infrastructure Study

8

Page 9: SITWA Infrastructure Study

Infrastructures vertesInfrastructure : « stock d’équipements, de services

et d’installations nécessaires au fonctionnement d’une société »

Services essentiels fournis par la nature équivalents à la plupart des fonctions des infrastructures : stockage et transfert de l’eau, filtration, transport, écrêtement des crues, protection contre les inondations

9

Page 10: SITWA Infrastructure Study

10

InstitutionMandate for large

water infrastructuresGaps and needs

CICOS Only investigations Institutional set-up for Palambo dam. Studies funding

ENSAP Yes No RBO. PPP models and Capacity buildingKOBWA Only investigations PPP modelsLCBC Only investigations LCBC role in infrastructure developmentLIMCO Only investigations Development of investment planLTA No Development of investment planLVBC No Capacity buildingMRU No Master plan. Studies to be updatedNBA Yes NBA role in Fomi projectNBI No No RBO. Confidence enhancing and capacity

buildingNELSAP Yes PPP models and Capacity buildingOKACOM Only investigations Development of investment planOMVG Yes, including O&M OMVG role in Kaleta projectOMVS Yes, including O&M Gourbassy dam studies. Companies institutional

organisationORASECOM Only investigations

and studiesDevelopment of investment plan

PJTC - Development of investment planVBA Yes DSS and Master plan. VBA role in infrastructure

development ZAMCOM Only investigations Capacity building - Monitoring of infrastructures

developmentZRA Yes PPP models

Page 11: SITWA Infrastructure Study

11

Component Nb.

actions

Nb. activities

Estimated budget (€)

1. Sensitization 3 7 3 200 00

2. Technical support 3 14 10 400 00

3. Good practices and

benchmarking 3 11 5 550 00

4. TOTAL 9 32 1 915 000

Page 12: SITWA Infrastructure Study

12

1.1 Sensitization on importance of transboundary water infrastructures

160 000

Forum on Nexus Water/Food/Energy and Multifunction dams: Role of L/RBOs for Infrastructure development, Water/food/energy Nexus and multi-functions dams, Prioritization and Decision Support Systems, Importance of Green infrastructures, Civil society participation

1 000 00

Meeting on Inland transboundary navigation 30 000Meeting on institutional setting-up (between countries, PPP) of large transboundary infrastructures

30 000

1.2 Support for fund raising 30 000 Meeting on financing of large transboundary infrastructures (with L/RBOs, RECs and Donors). Interests of PPP

30 000

1.3 Sensitization on environmental assessments 130 0004 regional meetings on participation of actors (with L/RBOs and local actor’s representatives)

100 000

Meeting on importance of green infrastructures 30 000 Total Component 1 (Euros) 320 000

Page 13: SITWA Infrastructure Study

13

2.1 Hydrological monitoring and Decision Support Systems 530 000Technical assistance to WHYCOS projects in Africa for Basin wide hydro-meteorological networking, data production and information exchange strategy and mechanisms

200 000

Technical platform on Decision Support Systems (including climate change simulations, water allocation and rainfall – run-off models, etc.)

130 000

Technical support for the development and implementation of seasonal forecasts tools in relation with large infrastructures management

200 000

2.2 Capacity building and capacity development 280 000Develop and train river basin organizations on guidelines for large infrastructures studies and environmental assessment

80 000

Develop tools for large infrastructures cost-benefit analysis 30 000

Enhance RBOs capacity for the development of public private partnership in view of the construction and management of large scale infrastructures

50 000

Page 14: SITWA Infrastructure Study

14

2.2 Capacity building and capacity development (continuation) 280 000Enhance RBOs capacity for policy/decision making, effective regulatory oversight and operation of large infrastructures

50 000

Identify and disseminate technical knowledge of improved approaches to water infrastructures management

30 000

Support selected RBOs for the assessment of large infrastructures potentials

50 000

2.3 Technical studies 230 000Funding of large transboundary infrastructures (Public, PPP…) and institutional set-up models for Operation & Maintenance

60 000

Prioritization of large infrastructures in “no PIDA” basins 30 000Typology of L/RBOs regarding infrastructure development 30 000Set of procedures that can assist RBOs to become financially sustainable

30 000

Case studies of “green/grey” infrastructures couples in transboundary basins

50 000

Total Component 2 (Euros) 1 040 000

Page 15: SITWA Infrastructure Study

15

3.1 Diffusion of good practices 140 000 Exchange of good practices regarding large transboundary water infrastructures

30 000

Handbook on good practices regarding large transboundary infrastructures

20 000

Transboundary water infrastructure projects inventory - data base and update (Inception Report 5.1.1 and DOC8 - WP6) with details of the financial package of each project (terms, sources and structure)

75 000

Publication of an annual newsletter containing news and updates on current transboundary water infrastructure projects (Inception Report 5.1.1 and DOC8 - WP6)

15 000

3.2 Regional dialogues on large water infrastructures 165 000 Diffusion of the West African Dialogue results in other regions

15 000

Organisation of a Dialogue on large water infrastructures in Central Africa

50 000

Page 16: SITWA Infrastructure Study

16

3.2 Regional dialogues on large water infrastructures (cont.) 165 000 Organisation of a Dialogue on large water infrastructures in Southern Africa

50 000

Organisation of a Dialogue on large water infrastructures in East Africa

50 000

3.3 Capacity building and capacity development 250 000 5 Workshops for the exchange of information, for briefing on items of common interest, for peer-group exchanges and advice, and for training on specific topics (DOC5 – WP4)

100 000

Twinning and technical visits between L/RBOs (possibly outside Africa)

100 000

Establish a learning platform for future/scenario planning (in relation with Decision Support Systems)

50 000

  Total Component 3 555 000  Grand Total 1 915 000

Page 17: SITWA Infrastructure Study

Conclusions et recommandationsLes grandes infrastructures hydrauliques ont

souvent une dimension transfrontalière, en amont comme en aval

Les OBT jouent donc un rôle fondamental aux côté des CER, comme l’énonce le PIDA

Outil d’aide à la décision stratégique : Situations actuelle et futures, Impacts des changements climatiques

Comparaison et choix des scenarios prospectifs à l’échelle du bassin - Optimisation économique

17

Page 18: SITWA Infrastructure Study

Conclusions et recommandationsChoix d’un scénario consensuel, partage des

bénéfices et des coûts entre les pays suivant un processus de concertation / négociation

Plan d’action / Schéma directeur transfrontalier : production hydroélectrique, irrigation, navigation, soutien d’étiage, préservation des écosystèmes, protection contre les risques

INFRASTRUCTURES = 50-90% investissementsBarrages multifonctions

18

Page 19: SITWA Infrastructure Study

Conclusions et recommandationsImpacts des changements climatiques : barrages

de rétention comme solution en zone arideInfrastructures vertes : les services rendus par les

écosystèmes multiplient les bénéfices reçus des infrastructures grises

Les infrastructures grises et vertes sont complémentaires et doivent être gérées conjointement

La participation des populations est indispensable dès l’identification du projet : compensations, réinstallation…