+ All Categories
Home > Documents > Slipform Brochure

Slipform Brochure

Date post: 04-Jun-2018
Category:
Upload: ren-salazar
View: 226 times
Download: 1 times
Share this document with a friend

of 8

Transcript
  • 8/13/2019 Slipform Brochure

    1/8

  • 8/13/2019 Slipform Brochure

    2/8

  • 8/13/2019 Slipform Brochure

    3/8

    The slipform technique is a rapid and economical construction method

    that can achieve considerable cost savings when compared with the

    cost of conventional formwork.

    The slipform construction system becomes viable on regular shaped

    structures generally four storeys or greater in height, although multiple

    uses on shorter structures has been achieved economically in the past.

    ECONOMICAL SOLUTION

    Page 2

    ADVANTAGESThe advantages of the slipform system include:

    Off site assembly

    Greater speed and earlier completion of construction projec ts

    Early completion of lift motor rooms and early installation of lifts,

    plumbing and electrical services

    Reduced craneage as forms are lifted by

    hydraulic jacks Reduced scaffolding and temporary work

    platforms as the slipform system contains its own

    platforms for working. This also results in a

    cleaner and less congested constructed site

    A uniformity of wall sec tions and layouts can be

    achieved with the slipform method this is not

    achievable with conventional formwork systems

    Reduced labour costs, as the system provides

    an intensive work environment

  • 8/13/2019 Slipform Brochure

    4/8

    The slipform system is a hydraulically operated formwork system. 3 tonne hydraulic jacks are

    mounted on strategically located steel yoking frames to lift the formwork as the concrete is

    poured into the forms.

    The formwork system uses 1066mm high steel panels held rigidly by a framework built up from

    steel waler frames, trusses and bracing. The framework provides rigidity to the slipform as well

    as support for timber decking to form a working platform for placement of concrete, rein-

    forcement steel and blockouts for doors and windows.

    Concrete is poured into the forms in layers of approximately 200mm. The setting rates of con-

    crete are constantly monitored to ensure that it is matched with the speed at which the forms

    are raised. The jacks lift the form approximately 25mm per stroke generally producing a slip-

    forming rate of 300mm per hour.

    Slipforming can be performed on either a continuous basis (i.e. 24 hours per day), or a discon-tinuous basis (i.e. pouring to a predetermined height usually within one working day).

    As the formwork is raised, reinforcement is held in the correc t position using guides fixed to the

    top of the yokes. Horizontal reinforcement is threaded under the yokes and tied to the verti-

    cal reinforcement.

    Blockouts for doors and windows can be formed with either timber or steel. These are in-

    stalled as the slipform proceeds and can be stripped from the trailing decks. Similarly with re-

    bates that are used to provide connections between beams, slabs and the slipform walls.

    When the formed concrete is exposed from the bottom of the steel form panels it can besponged or treated if required.

    Page 3

    SLIPFORMING PROCESS

  • 8/13/2019 Slipform Brochure

    5/8

    Structural Systems experienced engineering and operational personnel ensure the smoothoperation of the slipforming process and control of verticality. Structural Systems technica lstaff are always available to advise on all aspects of slipforming including coordination ofvarious trades to optimise resources.

    Page 4

    Typical section through slipform system for vertical structures

  • 8/13/2019 Slipform Brochure

    6/8

    Structural Systems is also heavily involved in the construction of conicalchimneys, cooling towers, piers and other tall concrete structuresinvolving constant or changing thicknesses in walls, diameters and/ orshapes. Structural Systems has been involved in the construction oftapered towers and chimneys from 50m to 275m high with diametersand wall thicknesses changing from 25m to 6m and 700mm to 250mmrespectively.

    While the slipforming process is similar to that used on the standardslipform equipment the logistics and planning require greater attentionthe heights which often make the use of cranes impractical. StructuralSystems experience and expertise ensures the success of such projects.

    Typical section through slipform system for tapered structures

    Page 5

    TAPERED SLIPFORMING

    1. Upper distribution and

    working deck

    2. Working deck

    3. Hanging scaffold

    4. Radius screw

    5. Screw for adjusting wall

    thickness6. Screw for adjusting inclination

    7. Horizontal turnbuckles

    8. Spider beam

    9. Lifting yoke

    10. 3 tonne hydraulic climbing jack

    11. J ack rod

    12. 6 tonne hydraulic climbing jack

    13. Hydraulic jack pump

    14. Hydraulic turnbuckle pump

    15. 6 tonne climbing rod extractor

    16. 3 tonne climbing rod extractor17. High pressure hose 3/8

    18. High pressure hose 1

    19. Distribution pipe

  • 8/13/2019 Slipform Brochure

    7/8

    Page 6

    CONCLUSIONStructural Systems innovative engineering and strict quality control ensures the increasingdemands within the building industry to come up with solutions for difficult construction prob-

    lems are met at the highest level, ensuring an efficient cost effective solution.

    Structural Systems is committed to maintaining the highest level of service at all times and tomeet the changing demands of the building and construction industry.

  • 8/13/2019 Slipform Brochure

    8/8

    Structural Systems (Civil) Pty Ltd

    ABN 31 083 214 43920 Hilly Street

    Mortlake, NSW Australia 2137

    Tel: +61 2 87676200

    Fax: +61 2 87676299

    Web: www.structuralsystems.com.au

    VICTORIA 112 Munro Street, South Melbourne

    VIC 3205 Australia

    Tel: +61 3 9296 8100Fax: +61 3 9646 7133

    WESTERN AUSTRALIA 24 Hines Road, OConnorWA 6163 Australia

    Tel: +61 8 9267 5400Fax: +61 8 9331 4511

    QUEENSLAND Unit 2, 16 Maiella St, StapyltonQLD 4207 Australia

    Tel: +61 7 3442 3500

    Fax: +61 7 3442 3555

    MIDDLE EAST Office 603, Business Avenue, Deira

    PO Box 28987, Dubai, United Arab Emirates

    Tel: +971 4 2948 974Fax: +971 4 2948 984

    AFRICA Block B, 60 Civin Drive, Pellmeadow Office Park

    Bedfordview, J ohannesburg 2008, South AfricaTel: +27 11 409 6700

    Fax: +27 11 409 6789


Recommended