SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL SEP 2018 1
Transcript

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

1

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

1

EXECUTIVE SUMMARY This report describes project status updates, financial data and observations of the Smart Columbus

Electrification Program over the time period from July – September 2018 (Q6). The reporting period for

financial expenditure data for the City of Columbus was through September 30, 2018.

PROJECT DESCRIPTION AND STATUS The overall goal of this project is to measurably decrease light-duty transportation greenhouse gas (GHG)

emissions expressed in equivalent metric tons of carbon dioxide (MTeCO2) as a result of grid

decarbonization; electric vehicle (EV) fleet adoption; transit, autonomous and multi-modal systems

(implemented via USDOT grant agreement); consumer EV adoption; and charging infrastructure during the

grant period compared to a baseline year (2016).

Priority 1: Decarbonization Objective: In partnership with power providers, by 2030 install 905 MW of utility scale renewable energy

generation capable of serving the Columbus region, procure a minimum of 1.2 million MWh of renewable

energy for the City of Columbus between 2017 and 2022, and save 480 GWh consumed through energy

efficiency and smart grid programs during the time period of the grant.

Q6 Key Highlights:

339,000+

ADVANCED METERING INFRASTRUCTURE (AMI) METERS

INSTALLED TO DATE

23% COMPLETE WITH PRELIMINARY

DESIGN ON THE O’SHAUGHNESSY DAM IMPROVEMENTS PROJECT

THE DIVISION OF

POWER PUBLISHED SPECIFICATIONS

REQUIRING ALL NEW STREET LIGHTS TO

BE LED

12 DC SOLAR

UNITS DEPLOYED

IN Q6

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

2

Priority 2: Fleet Adoption Objective: Work with public, private and academic sectors to place in operation 790 EVs into their fleets by

the end of the grant period.

Q6 Key Highlights:

1 NEW PUBLIC

FLEET EV PURCHASE AND

2 NEW COMMITMENTS

SECURED IN Q6

3 NEW PRIVATE

FLEET EV PURCHASES AND

25 NEW COMMITMENTS

SECURED IN Q6

COLUMBUS ANNOUNCED THEY WILL PURCHASE 32 NEW FLEET EVS

$30,000 AWARDED TO YELLOW CAB OF

COLUMBUS THROUGH THE FIRST ROUND OF THE

TRANSPORTATION SERVICE PROVIDER (TSP)

REBATE PROGRAM

7 PRIVATE FLEET ASSESSMENTS

COMPLETED TO DATE

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

3

Priority 3: Transit, Autonomous and Multi-Modal Systems in the City Objective: Ensure a comprehensive, multi-modal approach to decarbonizing the Columbus region’s mobility

options.

Q6 Key Highlights:

1,000 ELECTRIC

SCOOTERS WERE

DEPLOYED IN THE COLUMBUS

REGION

SELECTED MAY MOBILITY TO

OPERATE LOW-SPEED, SELF-

DRIVING SHUTTLES THAT WILL DRIVE

PASSENGERS AROUND THE SCIOTO MILE

6 ELECTRIC BIKES WERE DEPLOYED

WITH THE COLUMBUS POLICE

DEPARTMENT

10 MILES OF BIKE

INFRASTRUCTURE ADDED IN Q6

Priority 4: Consumer EV Adoption

Objective: Increase EV market adoption as evidenced by the percentage of light duty EV registrations in

Columbus and the surrounding seven-county region, attaining 1.8% of all new and used light duty vehicle

registrations by the end of the three year grant period, representing a 486% increase from the 2015 baseline

of 0.37%.

Q6 Key Highlights:

$100,000

AWARDED TO EIGHT IGNITE ACTION FUND RECIPIENTS

19 RIDE & DRIVE

ROADSHOW EVENTS IN Q6

2,370 TEST DRIVES

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

4

HOSTED 4 EVENTS TO CELEBRATE

NATIONAL DRIVE ELECTRIC WEEK

250 EVS FOR SALE IN

23 DIFFERENT

MODELS FROM

47 DEALERSHIPS

IN CENTRAL OHIO

11 CENTRAL OHIO AUTO DEALERSHIPS WERE INDUCTED INTO

THE NEW ELECTRIFIED DEALER PROGRAM

Priority 5: Charging Infrastructure

Objective: Support the acceleration of EV adoption through installation of charging infrastructure, with the

goal of 925 new charging ports by the end of the grant period.

Q6 Key Highlights:

86 CHARGING PORTS WERE

INSTALLED AT THREE CITY-OWNED PROPERTIES

POSTED THE APPLICATION FOR ROUND 2

OF THE MULTI-UNIT DWELLING (MUD)

INCENTIVE FUNDING

25 APPLICATIONS

RECEIVED FOR AEP OHIO’S EV CHARGING INCENTIVE PROGRAM

12 NEW WORKPLACE

CHARGING PORTS WERE INSTALLED IN Q6

AT TWO SITES

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

5

Playbook: Q6 Key Highlights:

177 ARTICLES PUBLISHED ABOUT

SMART COLUMBUS IN Q6

6 VIDEOS

FINALIZED ABOUT DIFFERENT ELECTRIFICATION INITIATIVES

SOFT LAUNCH OF THE PLAYBOOK WEBSITE. THE OFFICIAL PUBLIC WEBSITE WILL LAUNCH IN OCTOBER.

PROJECT BUDGET AND SCHEDULE REVIEW The reporting period for financial expenditure data for the City of Columbus was based on invoices received

through September 30, 2018. See page 49 for a more detailed analysis.

Activities within the schedule are progressing according to plan. Q6 saw an accelerated effort on Priority 5

with planning for the next rounds of charging infrastructure.

See Appendix B for

comprehensive timelines.

0

200000

400000

600000

800000

1000000

1200000

1400000

Year 2 Spend Year 2 Commitments Year 2 Total

Year 2 Budget Analysis

Year 2 Spend: $690,824

Year 2 Commitments: $625,000

Year 2 Total: $1,315,824

Priority 1

Priority 2

Priority 3

Priority 4

Priority 5

Playbook

Program Management

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

6

MAJOR ITEMS UPCOMING IN Q7 (OCT – DEC 2018) AEP will prepare and submit a filing to the Public Utilities Commission of Ohio (PUCO) for specific

renewable projects. The Columbus Division of Power (DOP) will be working on ways to increase participation of city

facilities in the EcoSmart Choice program. Columbus DOP will deliver the detailed design memorandum for the O’Shaughnessy Dam project. AEP Ohio will continue Advanced Metering Infrastructure (AMI) installation activities. DOP plans to

issue their AMI Request for Proposal (RFP) in Q7. The Columbus Department of Public Utilities (DPU) will issue the Notice to Proceed for the Smart

Street Lighting System consultant. The City of Columbus is working on charging infrastructure deployment for the next 32 units. They

plan to purchase the 32 fleet EVs when charging installation begins.

Convert fleet commitments to procurement to reach procurement goal for end of Year 2. Host an October Private Fleet Electrification Workshop to drive next step action and procurement. Release Round 2 of the Transportation Service Provider (TSP) rebate program. Begin testing for the autonomous shuttle service in October 2018 and prepare for deployment. Decide on rules and regulations governing the operations of mobility devices. Apply feedback from Forth Mobility recommendations.

Deliver the final report from Navigant. Use the Navigant research to improve consumer adoption

programs and make research publicly available via Playbook.

Launch and begin to optimize the Consumer Education Campaign.

Partner with Columbus College of Art & Design (CCAD) to engage students to design public art for a

public charger. Launch The Ohio State University (OSU) Research & Innovation series in October. Execute four Ride & Drive events in October. Launch the integrated survey platform for test drives.

Host two Mobility Ambassador workshops for best practice sharing and a celebration of successes. Share best practices from Ignite Action Fund projects through the Playbook and media outlets. Launch a website landing page for the Experience Center, with online scheduling for test drives. Add all of the existing Electrified Dealers to the online lead management.

Expand Original Equipment Manufacturer (OEM) engagement to Audi, VM, Volvo, Jaguar Land

Rover, Hyundai and Kia.

Certify five more dealers as Smart Columbus Electrified Dealers. Finalize the plan for the 2019 LEAF Smart Columbus incentive. Process and award incentives for AEP Ohio’s EV Charging Incentive Program.

Review and award applications for Year 2 Multi-Unit Dwelling (MUD) funding incentives. Release the Public Access Charging Request for Bid (RFB). Arrange funding for charging for 75 remaining City of Columbus fleet EV purchases.

Develop a scope of improvements for remaining fleet EV chargers in order to finalize locations,

numbers and expected costs. Launch the Playbook to the public by the end of October. Make international connections at EVS31 in Kobe, Japan, and Smart Cities World Congress in

Barcelona, Spain.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

7

TABLE OF CONTENTS

EXECUTIVE SUMMARY ................................................................................................................................ 1

Project Description and Status ....................................................................................................................... 1

Project Budget and Schedule Review ............................................................................................................ 5

Major Items Upcoming in Q7 .......................................................................................................................... 6

TABLE OF CONTENTS ................................................................................................................................. 7

ORGANIZATIONAL STRUCTURE ................................................................................................................ 9

QUARTER IN REVIEW ................................................................................................................................ 10

Priority Overview ........................................................................................................................................... 10

Priority 1 – Decarbonization ..................................................................................................................... 10

Priority 2 – Fleet Electric Vehicle Adoption ............................................................................................... 15

Priority 3 – Transit, Autonomous and Multi-Modal Systems in the City .................................................... 22

Priority 4 – Consumer Electric Vehicle Adoption ...................................................................................... 24

Priority 5 – Charging Infrastructure ........................................................................................................... 37

Playbook ................................................................................................................................................... 44

Contracts and Partner Agreement Status ..................................................................................................... 48

Implementation Plans ................................................................................................................................... 48

Risk Management and Policy Register ......................................................................................................... 48

Budget and Cost Management ..................................................................................................................... 49

Smart City Schedule ..................................................................................................................................... 50

Performance Measurement Plan .................................................................................................................. 50

ACTIVITY LOGS .......................................................................................................................................... 51

Priority 1 Activity Log .................................................................................................................................... 51

Priority 2 Activity Log .................................................................................................................................... 55

Priority 4 Activity Log .................................................................................................................................... 59

Priority 5 Activity Log .................................................................................................................................... 63

Playbook Activity Log .................................................................................................................................... 70

APPENDICES .............................................................................................................................................. 71

Appendix A – Quarterly Indicators and Metric Targets ................................................................................. 71

Appendix B – Schedule ................................................................................................................................ 84

Appendix C – Risk and Policy Register ........................................................................................................ 88

Appendix D – Polk Data ................................................................................................................................ 93

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

8

Appendix E – Communications and Publications

Appendix F – Fleet Assessment Example – Alliance Data

Appendix G – Private Fleet Commitments To Date

Appendix H – Speaking Engagements

Appendix I – Ride & Drive Roadshow Phase 2 Summary

Appendix J – Executive EV Purchases To Date

Appendix K – Ignite Action Fund Round 2 Overview

Appendix L – Ignite Action Fund Round 2 Application

Appendix M – Workplace Charging Ports Installed To Date

Appendix N – Consumer Awareness Survey Findings

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

9

ORGANIZATIONAL STRUCTURE

The new Storyteller, Donna Marbury, started on July 9th. Her role includes publishing content and material for the Playbook.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

10

QUARTER IN REVIEW This section will give an overview on items that happened during Q6 for each of the five project priorities,

program management, priority implementation and coordination items.

PRIORITY OVERVIEW Progress during Q6 is detailed below for the following priorities: Decarbonization; Fleet Electric Vehicle

Adoption; Transit, Autonomous and Multi-Modal Systems in the City; Consumer Electric Vehicle Adoption;

and Charging Infrastructure.

PRIORITY 1 – DECARBONIZATION

Initiative 1.1 – Utility-Scaled Renewables

Strategy 1.1.1 – AEP Solar and Wind Generation

Key Highlights:

AEP Ohio filed with the Public Utilities Commission of Ohio (PUCO) “Amendment to the 2018 Long-

Term Forecast Report of Ohio Power Company” on September 19th to demonstrate the need for at

least 900 MW of renewable projects in Ohio. See

http://dis.puc.state.oh.us/TiffToPDf/A1001001A18I19B53347A02011.pdf.

AEP Ohio filed with PUCO on September 27th for an application for an order approving the inclusion

of two solar energy resources totaling 400 MW of nameplate capacity in the Company’s Renewable

Generation Rider. See http://dis.puc.state.oh.us/CaseRecord.aspx?CaseNo=18-1392.

Next Steps:

Prepare and submit filing to PUCO for specific renewable projects to meet the need.

Strategy 1.1.2 – AEP Research and Development (R&D) to Advance Clean Energy

Key Highlights:

Nothing to report at this time.

Next Steps:

Maintain awareness of potential R&D opportunities.

Strategy 1.1.3 – AEP Distributed Generation Coordination of New Customer Installation

Key Highlights:

Applications to AEP Ohio for interconnection are increasing September over August.

Interconnection service applications ensure proper connection and operation of other sources of

power to work in parallel with AEP Ohio’s transmission and distribution systems. This provides

safety for employees and the public, and maintains reliability and quality of electric service.

Next Steps:

AEP Ohio continues to accept and process applications.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

11

Strategy 1.1.4 – Solar Generator Deployment (DC Solar)

Key Highlights:

Yellow Cab of Columbus obtained a total of eight DC Solar

charging trailers (16 ports) and are using them to charge their

new EV fleet.

DC Solar continues to work with the City of Columbus

Recreation and Parks Department to deploy units at city parks.

One DC Solar unit has been provided for various events throughout Columbus, including Smart Columbus Ride & Drive Roadshow events.

One mobile solar lighting tower unit has been provided to The Ohio State University (OSU).

Two DC Solar charging units (2 ports each) are now deployed at the State of Ohio facilities on West

Broad Street near I-70. The four charging ports are open to the public.

Next Steps:

Continue to collect data from the deployed trailers.

Continue to work with the City of Columbus departments.

Strategy 1.1.5 – Columbus Division of Power (DOP) Green Power

Key Highlights:

DOP has offset 24,142 MWh of power so far in 2018 through the EcoSmart Choice program.

In August, DOP began remarketing the EcoSmart Choice program and promoting the newly

reduced pricing via social media.

In late August, DOP developed a newsletter with data regarding both the EV Rebate and EcoSmart

Choice programs to be mailed out to customers in their monthly bill and emailed through the billing

portal.

Modification of the COBE purchase power agreement has been finalized. COBE is not currently

generating power due to mechanical issues at the plant.

Next Steps:

In Q7, DOP will work with the Department of Public Utilities (DPU) Director’s office, American

Municipal Power and the new City Energy Manager on ways to increase participation of city

facilities in the EcoSmart Choice program.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

12

Strategy 1.1.6 – City of Columbus Wastewater Treatment Plant, Co-Generation

Key Highlights:

Preliminary design plans for the Jackson Pike Co-Generation Wastewater Treatment Plant (WWTP)

are complete. Detailed design is to begin. The goal is to use biogas from City WWTPs as fuel for a

Combined Heat and Power (CHP) plant, which will consume all the biogas being produced and

supply half of the power at two WWTPs.

The Southerly Co-Generation WWTP project has been postponed due to a digester expansion

project. The preliminary design work at Southerly showed the digesters producing significantly less

biogas than the digesters at Jackson Pike due to differences in the way the two plants operate their

processes.

Next Steps:

DPU has some capital work underway at Southerly that will improve the digesters. DPU expects to

reactivate the Southerly Co-Generation project in a few years, after digesters are improved and the

available biogas fuel increases.

Strategy 1.1.7 – Columbus Division of Power Hydroelectric Improvements

Key Highlights:

All field inspections on the O’Shaughnessy Dam improvements project are complete and a

consultant is working on preliminary engineering tasks. The preliminary design phase is 23 percent

complete.

The DOP received the technical memorandums, which make recommendations about specific

pieces of equipment in the powerhouse.

Next Steps:

Deliver the detailed design memorandum in Q7.

Construction is expected to begin in late 2019.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

13

Initiative 1.2 – Grid Modernization and Efficiency

Strategy 1.2.1 – AEP Energy Efficiency

Key Highlights:

AEP Ohio is on track for energy efficiency program participation goals. Numbers will be reported

after the annual compliance filing on or before May 15, 2019.

Next Steps:

Continue marketing and outreach to engage residential and business customers in energy

efficiency programs.

Continue working with City of Columbus neighborhood associations to promote Community Energy

Savers as a way to increase participation and earn awards for an efficiency project in their

communities.

Strategy 1.2.2 – AEP Smart City Vehicle to Home Research

Key Highlights:

Nothing to report at this time.

Next Steps:

Maintain awareness of potential research opportunities.

Strategy 1.2.3 – AEP gridSMART 2.0 Advanced Metering Infrastructure (AMI) Deployment

Key Highlights:

AEP Ohio has installed 339,908 AMI meters in the Smart Columbus service area to date. The

project is around 64% complete.

Next Steps:

Continue AMI installation activities.

Strategy 1.2.4 – AEP Microgrids and Battery Storage

Key Highlights:

AEP Ohio has begun initial discussions with potential site hosts for a candidate project.

Next Steps:

Continue discussions to reach consensus among project participants on the project.

Strategy 1.2.5 – AEP Smart Lighting

Key Highlights:

Nothing to report at this time.

Next Steps:

AEP Ohio is interested in supporting and partnering with the City on smart street lighting.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

14

Strategy 1.2.6 – Columbus Division of Power Grid Modernization (AMI)

Key Highlights:

The DOP’s AMI Request for Proposal (RFP) was reviewed by the DPU Director and city attorney.

Next Steps:

DOP plans to issue the AMI RFP in Q7.

Strategy 1.2.7 – Columbus Division of Power Street Light Technology Conversion

Key Highlights:

The DPU team reviewed all proposals for the Smart Street Lighting System consultant and selected

a partner for the street light technology conversion assessment.

DOP published specifications requiring all new street lights to be LED.

https://www.columbus.gov/utilities/standards/Street-Light-Specifications/

Next Steps:

DPU will issue the Notice to Proceed (NTP) to the consultant once the Director has approved.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

15

PRIORITY 2 – FLEET ELECTRIC VEHICLE ADOPTION

Initiative 2.1 – Public Fleets

Key Highlights:

Smart Columbus has achieved more than 40 percent of its goal to introduce 300 EVs to public

fleets by 2020. The City of Columbus is leading the way in this effort, deploying 93 EVs in 2018,

and announcing plans to purchase 32 more in the coming months.

Smart Columbus is following up with public fleets to confirm EV purchase letters of commitment.

Public fleet vehicle purchase commitments to date are noted below.

PUBLIC FLEET VEHICLE PROGRESS TO DATE

Firm or Municipality Quantity Purchased Additional Expected

City of Columbus 93 107

Columbus Regional Airport Authority 2 Applied for 5 GSE units through

the Volkswagen grant

Mid-Ohio Regional Planning Commission 0 2 (expected in Q7)

City of Hilliard 2 0

City of Dublin 5 5

Franklin County 11 Additional vehicles pending

County approval of more charging

The Ohio State University 3 (1*) 47

City of Westerville 2 0

City of Whitehall 2 0

City of Worthington 0 2 (expected in Q7)

Franklin County Engineer 2 0

Central Ohio Transit Authority 0 10 (expected 2019)

City of New Albany 0 1* (expected in Q7)

City of Delaware 0 1* (expected in Q7)

TOTAL 122 175-180

* indicates Q6 commitments

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

16

WCMH (the local NBC affiliate) and Columbus

Business First interviewed Brandi Braun and John

King of Fleet Management about Smart Columbus’

public fleet initiatives.

The City of Columbus finalized the 2019 Cooperative

EV purchase agreement pricing and contract

structure with Mike Albert Leasing, Ricart and Byers.

This is available to all public and many private fleets

throughout the region.

The Smart Columbus team continued its outreach, education, analysis and technical assistance work

with public fleets and private fleets. The team promoted the 2018 Midwest Green Fleet Forum & Expo

(Sept. 24-26), headline sponsored by Smart Columbus and featuring full educational tracks on Smart

Mobility and Electrification, including an EV vendor expo and Ride & Drive. This event featured

leading electrification and smart mobility experts from local, state and national levels, along with

multiple breakout training sessions, networking opportunities, and a showcase of charging and fuel

technologies. Full information is available at www.midwestgreenfleets.com.

The Columbus Regional Airport Authority (CRAA) submitted a proposal to the Ohio Volkswagen

Mitigation Grant Fund focused on replacing five diesel powered Ground Support Equipment (GSE)

units with five new fully Battery Electric GSE units.

Next Steps:

The City of Columbus is working on charging infrastructure deployment for the next 32 units. They

plan to purchase the 32 fleet EVs when charging installation begins.

The City of Columbus will purchase an additional 75 EVs in the second and third quarters of 2019.

The Department of Public Service (DPS) will provide the charging infrastructure to support the EVs.

Continue outreach, education, analysis and technical assistance work with public fleets throughout

Year 2 of the performance period.

Continue working with all partners to facilitate vehicle rebates and incentives, provide administrative

tracking and reporting of activities and deliverables, and offer informational resources on lessons

learned and best practices.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

17

Strategy 2.1.1 – Training and Technical Assistance Workshops

Key Highlights:

The City of Columbus is partnering with Columbus

State Community College (CSCC) on a series of in-

depth, technical automotive trainings. These college-

level classes begin October 21, 2018 through May

11, 2019. The classes will be made available at a

reduced rate to all Municipal Equipment

Maintenance Association-OH members (i.e. other

public fleets). Columbus has eight technicians

included in the classes. The courses are:

o AUTO 2190 - Hybrid Vehicles: Theory and

Operation: This course presents the theory and

operation of hybrid vehicles. This is an informative

course designed to provide a general overview of

various hybrid vehicle systems. Proper safety

precautions and procedures needed to service the

basic systems of hybrid vehicles will be discussed.

o AUTO 2391 - Advanced Alternative Fueled

Vehicles: Diagnosis and Repair: This course builds

on the fundamentals of automotive engine

performance and electrical systems building on the

information and skills obtained in AUTO 2360 and

AUTO 2380. Compressed natural gas, propane, bi-

fuel, hydrogen and other alternative fueled vehicles

will be explored. System safety, diagnosis, live car

servicing and various manufacture’s systems will be

explored through lecture and lab activities.

o AUTO 2390 - Advanced Hybrid Vehicles: Diagnosis

and Repair: This course builds on the fundamentals

covered in AUTO 2190 Hybrid Vehicles Theory and

Operation. The emphasis of this course will focus on high voltage systems: safety, service, diagnosis and

repair. This course is designed to complement the knowledge learned in AUTO 2190, 2280 and 2360 to

prepare student to pass the ASE Light Duty Hybrid/EV Specialist Test (L3).

Next Steps:

CSCC classes to begin in October 2018.

Partners will continue to plan additional quarterly technical trainings throughout Year 2 of the grant

period.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

18

Initiative 2.2 – Private Fleets

Key Highlights:

145 private fleet EVs have been committed, with 25

private EVs purchased to date.

OhioHealth and MedSpeed fleet vehicles launched

telematics monitoring for fleet assessment. The

purpose is to track vehicles – location, speed, engine

load, RPM – to project which EVs would be the best

fit for replacement.

Seven baseline fleet assessments have been

completed to date, including the following: Denison

University, Columbus Zoo and Aquarium, The

Columbus Dispatch, Land Grant Brewing Company,

Yellow Cab of Columbus, Alliance Data, OhioHealth,

VAT Transportation, AAA Ohio, Cardinal Health and

Capabilities Inc. An additional 23 fleets are currently

in the process of collecting data for fleet assessment.

Many of these have historically collected little-to-zero

data on vehicle operation, which has caused delays

in data collection and assessment. Smart Columbus

has given extra attention to these fleets to educate

them about the necessary data required for informed

fleet transition decisions, which is beginning to help these fleets with their fleet electrification process.

See Appendix F for an example of a fleet assessment report.

Example EV Telematics Study: For those fleets requiring a more in-depth analysis of operation and

or economic fit with EV technology, a telematics analysis is offered. Below is an example of a one-for-

one replacement of a 2015 Nissan Rogue with a 2018 Nissan LEAF: 15,095 miles/year.

Next Steps:

Convert fleet commitments to procurement to reach procurement goal for end of Year 2.

Deploy additional telematics assessment for select fleets to determine best fit models for operation.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

19

Strategy 2.2.1 – Secure Purchase Pledges

Key Highlights:

Private fleet commitments for EV purchases have been secured from the following in Q6. See

Appendix G for all private fleet commitments to date.

PRIVATE FLEET VEHICLE PURCHASE COMMITMENTS IN Q6

Organization Quantity Purchased New Commitments*

Alliance Data 0 1

Columbus NEP 3 6

Mill Creek Insurance 0 4

VAT Transportation 0 5

Capabilities Inc. 0 3

Motorists Insurance Group 0 1

Able Roofing 0 5

TOTAL 3 25

*Commitments do not include purchases in Q6 or prior commitments.

Next Steps:

Private fleets will be continuously cultivated for electrification pledges through engagement and fleet

assessment services.

Strategy 2.2.2 – Network Development

Key Highlights:

More than 300 transportation professionals attended the 2018 Midwest Green Fleet Forum.

Members of the Smart Columbus team were feature panelists and speakers during the forum, with

key discussion around private fleet electrification and barrier reduction. Fleets were also assembled

for a Smart Columbus Fleet Meeting during the conference to discuss Smart Columbus resources

and fleet assessments.

Next Steps:

Smart Columbus will be hosting an October Private Fleet Electrification Workshop to drive next step

action and procurement.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

20

Initiative 2.3 – Transportation Service Providers (TSPs)

Key Highlights:

In July, the Smart Columbus team worked with

Transportation Service Providers (TSPs) to award

Yellow Cab of Columbus the $30,000 first round of

the TSP Rebate Program, signing the agreement

with owner and CEO Morgan Kauffman.

o Yellow Cab of Columbus worked with Smart

Columbus to finalize a purchase order for 20

Chevy Bolt EVs by Q7.

Eight DC Solar units with 16 charging points are in operation at the Yellow Cab of Columbus

headquarters.

In September, Yellow Cab of Columbus displayed its new Chevy Bolt taxis at the Midwest Green

Fleet Forum and Expo conference. Several of the company’s staff also attended training sessions at

the conference.

Throughout Q6, the Smart Columbus team finalized Round 2 of the Smart Columbus TSP Rebate

Program. Round 2 is designed to offer rebates to both traditional taxi service providers and drivers for

Transportation Network Companies (TNCs), such as Uber and Lyft, to spur TSP EV adoption

throughout central Ohio.

o Round 2 of the rebate program is currently in final review. It is expected to be voted on by the Columbus

City Council and publicly released in Q7.

The Central Ohio Regional Transit Authority (COTA) continued its plans to electrify one of its major

bus routes, with an expected purchase of up to 10 dedicated electric buses to serve the route during

the performance period of this grant.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

21

Next Steps:

Continue to gather survey data from regional TSPs.

Continue to work with key regional TSPs, including Yellow Cab of Columbus, COTA and the Mid-Ohio

Regional Planning Commission’s (MORPC) ride share program to further EV purchase commitments

and deployment of vehicles and charging.

Implement available TSP vehicle rebate programs to further catalyze deployment of EVs in additional

TSP fleets throughout the seven-county central Ohio region.

Continue to work with public agencies to get EV commitments.

Provide continued EV Technician Training.

Strategy 2.3.1 – Recruit TSP Partners

Key Highlights:

Smart Columbus provided information on the first round of the TSP Rebate Program (available only

to traditional taxi service providers) to Yellow Cab of Columbus and all traditional taxi owners

registered with the City of Columbus.

The Smart Columbus team continued outreach efforts to traditional taxi service providers and TNCs

(i.e. Uber, Lyft, etc.). The Smart Columbus team interfaced with the city’s Vehicle for Hire Board

about Round 1 of the TSP Rebate Program and will be working with them on outreach for Round 2.

Next Steps:

Finalize TSP Rebate Program eligibility for Round 2.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

22

PRIORITY 3 – TRANSIT, AUTONOMOUS AND MULTI-MODAL SYSTEMS IN THE CITY

6 Connected Electric Autonomous Vehicles (CEAVs)

Key Highlights:

In July, The Ohio Department of Transportation’s

DriveOhio initiative, in partnership with Smart

Columbus and OSU, announced the issuance of a

request for proposals to identify a technology

partner that will deploy, operate and maintain a

low-speed, self-driving, “autonomous” shuttle

service around the Scioto Mile in downtown

Columbus. In September, Smart Columbus

announced that May Mobility will operate low-

speed, self-driving shuttles that will begin driving

passengers around the Scioto Mile loop.

In July, Smart Columbus released the first in a

series of a systems engineering document, known

as a Concept of Operations, for the Connected

Vehicle Environment pilot. The Concept of

Operations conveys a high-level view of the

system to be implemented from the viewpoint of

multiple stakeholders including deployment area

residents in Linden neighborhood, COTA and the

City of Columbus DPS. The document is the

culmination of months of research and end-user

engagement and serves to frame the overall

system, sets the technical course for the project,

and serves as a bridge between early project motivations and the technical requirements.

Next Steps:

Testing for the autonomous shuttle service is intended to start in October 2018 and deployment is

anticipated in December 2018, with continuation of service into 2019.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

23

Electric Bikes

Key Highlights:

In August, Smart Columbus placed the six e-bikes procured

through the Electrification Program into operation with the

Columbus Police Department. The e-bikes’ pedal-assist

electric motor enables officers to travel more quickly—up to

28 miles per hour—and arrive at calls while conserving

energy for their work. Mayor Andrew Ginther celebrated the

deployment of the e-bikes by participating in a story with

10TV, the local CBS affiliate, on the e-bikes. The story may

be viewed at: https://www.10tv.com/article/smart-columbus-

provides-pedal-power-police.

Next Steps:

Columbus Recreation and Parks is discussing opportunities

for e-bike deployment with CoGo Bike Share. The main

issues they are looking at are the locations and charging

infrastructure for the bikes.

City Bike Infrastructure

Key Highlights:

The City of Columbus added 10 miles of bike infrastructure in Q6:

o 5.9 miles of bike boulevard (bike boulevard pavement markings and signs);

o 1.7 miles of shared-use path; and

o 2.4 miles of shared lane (sharrow pavement markings and signs).

Next Steps:

Continue construction and planning of bike infrastructure.

Expanded Shared Mobility

Key Highlights:

500 Bird and 500 Lime electric scooters deployed in the

Columbus region in July.

In September, Columbus Mayor Andrew J. Ginther

announced proposed legislation for e-scooters and dockless

rental bikes. In addition, city council approved rules to protect

pedestrians and other mobility device users. The law will go

into effect in October.

Next Steps:

The City of Columbus will be discussing and deciding on rules and regulations governing the

operations of mobility devices.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

24

PRIORITY 4 – CONSUMER ELECTRIC VEHICLE ADOPTION Key Highlights:

In September, Smart Columbus hosted Forth Mobility to get feedback on electrification programs.

Next Steps:

Evaluate and apply feedback from Forth Mobility recommendations.

Initiative 4.1 – Research and Assessment

Strategy 4.1.1 – Consumer Research

Key Highlights:

Navigant was contracted to conduct Phase 2 research on the Logic Model and Research Plan to

link consumer adoption activities to outcomes.

Next Steps:

Deliver the final report from Navigant.

Use Navigant research to improve consumer adoption programs and make research publicly

available via the Playbook.

Share results between consumer adoption activities and outcomes publicly via the Playbook.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

25

Initiative 4.2 – Increase Consumer Awareness for EVs

Key Highlights:

Drive Electric Columbus and Smart Columbus teamed up to host four events to celebrate National

Drive Electric Week (Sept. 8-16).

Conducted strategic planning to inform the Consumer Education Campaign.

Next Steps:

Continue to host EV focused events in the community with partners.

Launch and begin to optimize the Consumer Education Campaign.

Strategy 4.2.1 – Community Events

Key Highlights:

Smart Columbus took advantage of the robust festival season during the summer months and

engaged with thousands of community members at area events. In total, the Smart Columbus team

distributed 5,609 pieces of branded collateral throughout the quarter. See Appendix H for the full list

of events in Q6.

In July, Smart Columbus gave away more than 300 branded materials at the Columbus Jazz & Ribs

festival.

In August, during OSU Welcome Week, Smart Columbus distributed 4,000 branded materials to off

campus students.

Twenty people attended The Big Table conversations about electric cars, hosted by Smart Columbus

and Clean Fuels Ohio’s (CFO) Drive Electric Ohio program. Participants were divided into two

groups, which took turns test driving the cars and talking about how EVs can improve the quality of

life.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

26

Drive Electric Columbus and Smart Columbus teamed up to

host four events to celebrate National Drive Electric Week

(Sept. 8-16).

o Sept. 6: the Drive Electric Week Eve event at the Experience

Center brought together EV owners in the Columbus region.

Smart Columbus distributed 32 EV new owner’s gift bags

during the event.

o Sept. 11: the Smart Columbus team tabled and attended CFO’s

EV Tailgate at Land Grant Brewing.

o Sept. 13: Smart Columbus hosted an ‘E’VIP EV test drive event

for Columbus region executives and community leaders at the

Experience Center.

o Sept. 15: Smart Columbus hosted 50 members of the

community and 18 drives for the Elevate Your Ride Open

House, a family-friendly event that encouraged EV test drives

at the Experience Center.

o Smart Columbus conducted Surprise and Delight activations at

Huntington National Bank’s Easton location and the Easton

shopping center to increase awareness of Smart Columbus, its

EV adoption goals and foster EV advocacy among EV owners.

Dropped 130 swag bags on EV windshields parked at

Acceleration Partner and public charging stations, which

contained Smart Columbus swag and a letter declaring

owners a Smart Columbus “EVIP,” along with a call to

action to sign up for emails about EV owner gatherings.

Smart Columbus intercepted and surprised 10 owners at

Huntington and 7 at Easton, and celebrated their choice

to go electric. The team also handed out 150 donuts and

97 servings of ice cream to passersby, and used the

opportunity to educate non-owners on EVs.

Next Steps:

Co-host the Smart Women, Smart Columbus event with

YWCA, COTA and EmpowerBus in October.

Launch the OSU Research & Innovation series in October.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

27

Strategy 4.2.2 – Local Media Relations

Key Highlights:

Smart Columbus was mentioned in 132 local media stories, earning 6.6 million local media

impressions and 177 total stories, earning 14.4 million impressions.

Smart Columbus issued five news releases related to the Electrification Program:

o Smart Columbus awards $30,000 in rebates to Columbus Yellow Cab to electrify central Ohio taxis.

o Smart Columbus offering $175,000 for EV charging stations at apartments and condominiums in

second round of incentive funding.

o Columbus Police Department rolls out six e-bikes funded by Smart Columbus Electrification Program.

o Smart Columbus celebrates upcoming National Drive Electric Week with rollout of electric vehicles in

fleets throughout the region.

o Eleven car dealerships partner with Smart Columbus to accelerate EV adoption in central Ohio.

Smart Columbus surpassed our 2018 local media relations goals of 100 placements and 4.5 million

impressions in just four months. The team recalibrated the goals to be 75 placements and 225,000

impressions per quarter. The Year 2 local media relations goals represented an intended increase

over the Year 1 media relations benchmark; however, Smart Columbus is earning significantly more

media mentions during Year 2 for three primary reasons:

o Conducting more newsworthy activities as the delivery of both grants mature. The program is issuing more frequent news releases on Electrification Program initiatives, as well as USDOT grant deliverables.

o Engaged Approach Marketing, a local public relations firm, in May 2018. Approach is helping Smart Columbus to more aggressively pursue proactive media coverage about the program.

o Opened the Smart Columbus Experience Center in June, which was a significant media moment during

Q5. The opening alone generated more than 25 local placements in local print, TV and radio outlets.

Next Steps:

Issue news releases for the next phase of the TSP Rebate Program and the Playbook launch.

Strategy 4.2.3 – Social Media

Key Highlights:

Smart Columbus continued a cadence of social media posts and amplified its paid social efforts.

From June-September, our social following saw a 400% month-over-month growth. The increase is

being driven by increased EV content and enhanced channel management by Approach Marketing.

Next Steps:

Continue proactive social cadence and paid posts.

Strategy 4.2.4 – Electric Asset Branding

Key Highlights:

Smart Columbus developed bumper stickers for the new owner’s gifts and fleet vehicles.

Next Steps:

Partner with the Columbus College of Art & Design (CCAD) to engage students to design public art

for a public charger during Q7.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

28

Strategy 4.2.5 – Smart Columbus Experience Center

Key Highlights:

Since the Smart Columbus Experience Center opened the week of June 25, we hosted 4,075 people,

who have taken 123 drives to date. Of those drives, 18% opted in to be contacted by a dealer. The

center is designed to serve as an EV showroom, with EV test drives available to the public. The

center also provides education on the future of mobility, with exhibits developed by Smart Columbus

and EV/technology demonstrations donated by more than 20 partners.

Hosted U.S. Representative Tim Ryan (OH-13) for a visit and tour of the Experience Center on

August 20, and hosted U.S. Congressman Brad Wenstrup (OH-2) for visit and tour of the

Experience Center on August 28.

A number of National Drive Electric Week events (Sept. 8-16) were held at the Experience Center.

See Strategy 4.2.1 for more information on the events.

Smart Columbus held two Big Table events in August – EV 101 & Test Drives, and one hosted by

U.S. Undersecretary of Energy Paul Dabbar.

Smart Columbus hosted a “EV 101” community conversation with 20 members of the public at the

Experience Center around electrification and completed over 10 test drives.

Added the AEP Smart Grid and Smart Ohio augmented reality experience to the Experience

Center, which highlights smart meter technology, EVs, EV charging and more.

Next Steps:

Launch the OSU Research & Innovation series in October.

Co-host the Smart Women, Smart Columbus event with YWCA, COTA and EmpowerBus.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

29

Initiative 4.3 – Drive Consumer Consideration for EVs

Strategy 4.3.1 – Test Drives

Substrategy 4.3.1.1 – Test Drives at the Smart Columbus Experience Center

Key Highlights:

Completed 123 test drives at the

Experience Center. Of those test

drives, 99 drivers completed their

pre and post-drive surveys. This is a

statistically valid sample to represent

the program. All drivers and riders

completed liability waivers.

18% of drivers opted-in to be

contacted by a dealer.

Improved processes, routes and

responsibilities for facilitating test

drives at the Experience Center.

Next Steps:

Rotate vehicles to make the Nissan

LEAF available for test drives.

Integrate the Connected Vehicle

Environment with the test drive

program.

Expand EV educational opportunities

in the showroom for a deeper

education before and after the test

drive experience.

Consider providing gifts as an incentive for test drives.

Launch a pre-registration platform allowing the public to register up to 2 weeks in advance of their

drive from a personal electronic device or on-site. Currently, the platform is only able to schedule

same day drives on-site.

Launch strategies to increase foot traffic to the Experience Center for test drives and EV education.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

30

Substrategy 4.3.1.2 – Ride & Drive Roadshow

Key Highlights:

Hosted 19 Ride & Drive events in Q6 with 2,370 test drives and 353 dealership opt-ins, for a 15%

opt-in rate. Over the life of the project, 7,173 test drives have been conducted at 63 events, 60% of

the way to the goal of 12,000. JP Morgan Chase holds the record for the most drives in one day,

with 276. Overall, JP Morgan Chase completed 903 drives between July 30 and August 3 for Smart

Commute Week. CAS holds the record for the second-highest drives in one day, with 239 drives.

For the full list of events and results, see Appendix I – Ride & Drive Roadshow Summary.

Next Steps:

Execute four Ride & Drive Roadshow events in October.

Conduct a robust data dive on Ride & Drive Roadshow survey results to date to understand areas

of impact and opportunity.

Strategize how to maximize Ride & Drive Roadshow impact in 2019.

Launch the integrated survey platform for test drives that feeds data into Qualtrics for faster and

more accurate reporting as well as for OSU research purposes.

Substrategy 4.3.1.13 – Extended Test Drives for Executives

Key Highlights:

No extended test drives were recorded, and there was little interest for the option. Only Tesla

vehicles are available in a plug-and-play fashion for this offering.

Executive EV adoption grew from 29 to 30 during Q6. New executives who purchased EVs are

included in the following table. See Appendix J – Executive EV Purchases To Date for the full list.

COMPANY NAME TITLE VEHICLE PURCHASED

Steiner Pat Steiner Chief Administration Officer BMW i3

Next Steps:

Require Mobility Ambassadors for Cohort 2 to help facilitate at least one extended test drive for a

member of their organization’s leadership.

Continue active messaging and celebration of executives who purchase EVs.

Continue to apply peer pressure in the Columbus Partnership Boardroom.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

31

Strategy 4.3.2 – Workplace Electric Vehicle Adoption Campaign

Substrategy 4.3.2.1 – Accelerator Partners Program

Key Highlights:

In August, the Smart Columbus team hosted a Mobility Ambassador event where Ambassadors

had the opportunity to ask questions to a range of service providers about contracting,

communication best practices, safety and tracking. Service providers included COTA, Gohio

(MORPC), EmpowerBus, Chariot, Yellow Cab of Columbus and SHARE. The event was hosted at

Grange Insurance and engaged partners in many phases of mobility benefit package development

and execution including L Brands, IGS, Huntington, Motorists Insurance, CAS, and Grange

Insurance. The team planned this event in response to requests from Ambassadors. The photo

below shows the Smart Columbus team with 38 Mobility Ambassadors.

Continued to work on recruiting 50 more Acceleration Partners.

Continued to offer one-on-one coaching, data collection and benefit deployment assistance.

Next Steps:

Host a Mobility Ambassador workshop for best practice sharing in October 2018 and a Celebration

of 2018 successes in December 2018.

Launch the second cohort of Mobility Ambassadors in December 2018 from newly committed

Acceleration Partner organizations.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

32

Substrategy 4.3.2.2 – Workplace Campaigns (Ignite Action Fund)

Key Highlights:

In July, Smart Columbus awarded $100,000 of funding in Round 1 of the Ignite Action Fund to eight

organizations launching electrification and smart mobility projects: Alliance Data, Steiner, Columbus

Zoo and Aquarium, White Castle, State Auto, CoverMyMeds, Battelle, and OhioHealth.

Nearly $26,000 were awarded to Alliance Data and the Columbus Zoo and Aquarium to fund

electrification projects, with funds from PGAPh. In total, $1.8 million is being leveraged with combined

funds from Acceleration Partner companies to create and promote drive electric and drive less

programs to Columbus region employees. As of September, Alliance Data awarded all 15 of their

rebates for EV purchases/leases via their program supported by the Ignite Action Fund in less than

four months. They also awarded three additional rebates to associates living outside of Central Ohio,

which was solely funded by Alliance Data.

On August 7, the Smart Columbus team hosted a kick-off meeting for Ignite Action Fund recipients to

celebrate their projects and prepare them for success.

In August, Smart Columbus announced that the next round of Ignite Action funding will be supporting

EV rebates launched in 2018 by Acceleration Partner organizations, in an effort to further drive sales

in this calendar year. Applications will be evaluated and approved on a rolling basis. The application

period will close in late October to ensure time for execution in 2018.

Launched Round 2 of the Ignite Action Fund focused on EV purchase/lease rebates. Targeting

three companies for this round of funding. See Appendix K for an overview of Round 2 and

Appendix L for the Round 2 application.

Next Steps:

Continue to support partners as they execute projects and report results.

Share best practices identified through Ignite Action Fund projects through the Playbook and media

outlets.

Strategy 4.3.3 – Consumer Focused Education Campaign

Substrategy 4.3.3.1 – Website

Key Highlights:

2,934 unique visitors from inside the seven-county area visited the Smart Columbus website,

www.smart.columbus.gov, which was launched on June 30th.

Next Steps:

Launch a landing page for the Smart Columbus Experience Center, with online scheduling for test

drives at the center.

Launch and/or refine site content to support the Consumer Education Campaign.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

33

Substrategy 4.3.3.2 – Digital Education

Key Highlights:

Smart Columbus and Fahlgren Mortine developed the creative and media strategies for the

Consumer Education Campaign, drawing insight from the Electrification Coalition, New York State

Energy Research and Development Authority, Forth, Veloz, Electrify America and others.

In September, the Consumer Education Campaign team, led by Fahlgren Mortine, developed

creative concepts for digital, media and website marketing campaigns and presented it to the

internal team and the Forth review committee. The team refined the creative campaign based on

feedback.

The Consumer Education Campaign readied to shoot creative for the campaign.

The Consumer Education Campaign team issued a RFP to local and national media outlets to

develop media strategy for the campaign that incorporates TV, streaming TV, radio, Waze,

programmatic digital media and paid search.

Next Steps:

Begin consumer awareness campaign in Q7 and optimize it in time for holiday/end of the year sales

activities.

The Consumer Education Campaign team will begin to produce the campaign creative.

The creative assets of the campaign will be launched in Q7 and refined based on initial and

continuous data.

Substrategy 4.3.3.3 – B2B Marketing

Key Highlights:

Nothing to report at this time.

Next Steps:

Continue to refine campaign objectives and scope for initial implementation in Q7.

Strategy 4.3.4 – EV Loyalty Program

Key Highlights:

In September, the creative for collateral insert in the new owner’s gift was finalized.

o Smart Columbus developed a strategy to distribute the new owner’s gifts through Electrified Dealer

participants and non-participants.

In September, 44 new owner’s gifts were distributed during National Drive Electric Week events.

Next Steps:

Continue to engage dealers to distribute new owner’s gifts.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

34

Initiative 4.4 – Improving Consumer Sales Experience of EVs

Key Highlights:

As of September 2018, there were 250 EVs in 23 different models for sale from 47 dealerships in

central Ohio. This represents an increase from 184 EVs in June 2018.

During Q6, Smart Columbus witnessed consistently high availabilities of the Nissan Leaf and Prius

Prime, the most affordable BEV and PHEV models, respectively, available in the United States.

Strategy 4.4.1 – Lead Management and Sales Support

Key Highlights:

In Q6, the first two dealers were added to the online lead management tool developed by Fahlgren

Mortine.

Next Steps:

Add all of the existing Electrified Dealers to the online lead management.

Strategy 4.4.2 – Dealer Preparedness and EV Readiness

Substrategy 4.4.2.1 – Dealer and Original Equipment Manufacturers (OEM) Engagement

Key Highlights:

Increased the number of EVs sold in the Columbus market from 18 in Q5 to 23 in Q6.

Certified 11 local dealers as Smart Columbus Electrified Dealers.

Launched National Drive Electric Week incentives at each Electrified Dealership.

Next Steps:

Expand OEM engagement to Audi, VM, Volvo, Jaguar Land Rover, Hyundai and Kia.

Add two additional vehicles to be sold in the Columbus market.

Add a SUV/CUV option into the Experience Center line up for test drives.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

35

Substrategy 4.4.2.2 – Dealer Certification

Key Highlights:

On September 12, during National Drive Electric Week, Smart Columbus inducted 11 central Ohio

auto dealerships into its new Electrified Dealer program, designed to help radically increase EV

adoption in the region. Through the program, dealers have committed to carry PHEV models,

educate sales staff and shoppers on EVs and share data with Smart Columbus to help drive

continued efforts to increase EV adoption.

The first Electrified Dealers collectively carry 16 EVs and PHEVs models ranging from sedans to

SUVs to minivans. The first inductees to the Smart Columbus Electrified Dealer program and the EV

and PHEV models they carry are:

o Buckeye Honda — Honda Clarity

o Buckeye Nissan — Nissan LEAF

o Byers Chrysler Dodge Jeep — Chrysler Pacifica

Hybrid

o Byers Volvo — Volvo XC60 PHEV and Volvo XC90

PHEV

o Dave Gill Chevrolet — Chevy Bolt and Chevy Volt

o MAG BMW — BMW 330e, BMW530e, BMW i3,

BMW i8 and BMW X5 xDrive 40e

o Ricart Ford — Ford Fusion Energi

o Ricart Mitsubishi — Mitsubishi Outlander

o Ricart Nissan — Nissan LEAF

o Ricart Kia — Kia Optima PHEV

o Tansky Toyota — Toyota Prius Prime

Next Steps:

Certify five more dealers as Smart Columbus Electrified Dealers.

Add new brands to the group of Electrified Dealers, including Jaguar Land Rover and Mercedes-

Benz.

Provide a winning gift and public recognition to the top selling Electrified Dealer.

Substrategy 4.4.2.3 – Smart Columbus Dealership Certification EV Sales Training

Key Highlights:

Conducted eight EV sales trainings throughout Q6.

Next Steps:

Conduct an additional five dealer trainings for Electrified

Dealer certification.

Enhance the dealer training to be more interactive and

improve the EV sales approach.

Conduct a second dealer training to the first round of

Electrified Dealers.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

36

Strategy 4.4.3 – Group Purchase Programs

Key Highlights:

Continued to help AEP market its Nissan LEAF group purchase program.

Engaged Nissan on a Smart Columbus-specific group purchase program for the 2019 LEAF.

Launched the Ignite Action Fund, which created group purchasing incentives at workplaces.

Nissan was added as an Accelerator Partner organization, with a national footprint to Nissan’s

group purchase plan.

Next Steps:

Finalize the plan for the 2019 LEAF Smart Columbus incentive.

Begin conversations with added OEMs on conducting a Smart Columbus group purchase program.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

37

PRIORITY 5 – CHARGING INFRASTRUCTURE Key Highlights:

In August, AEP Ohio announced a program to expand EV charging station availability as part of the

Smart Columbus initiative. The project creates a rebate incentive program for the hardware, network

services and installation of charging infrastructure for up to 300 Level 2 charging stations and 75 DC

Fast charging stations. The $10 million program offers rebates for site owners to install charging

stations, with 10 percent of the stations to be located in low-income areas.

The program helps participants by offsetting a

portion of their charging equipment and

installation costs. Maximum amounts vary based

on the type of station, the type of owner and the

public’s ability to access the station. Local

governments installing publicly-available charging

stations may be able to do so with no cost after

participating in the program.

Local governments, businesses and apartment complex owners interested in providing EV charging

are encouraged to apply for the program. Applicants must be commercial or industrial customers in

the AEP Ohio service territory. Complete program details and application materials are available

at www.aepohio.com/evcharge.

The EV charging program and microgrid projects are funded by the Smart City Rider, a new charge

that will end in four years. These programs will provide AEP Ohio, the PUCO and others with

information that will inform the expansion of these technologies throughout the state. To date, 25

applications for the AEP Ohio EV Charging Station Incentive Program have been received,

representing 80 total Level 2 ports at workplace, public and multi-family charging sites. AEP Ohio

has pre-approved applications for 58 ports to begin design work.

Next Steps:

AEP Ohio will process and award incentives for their charging program.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

38

Initiative 5.1 – Residential Charging

Strategy 5.1.1 – Develop Multi-Unit Dwelling (MUD) Infrastructure Plan

Key Highlights:

Continued to work with Year 1 developers to ensure projects are on-track for completion by the end

of Q7. Successful projects from the first round of Smart Columbus MUD funding include:

PROJECTS AWARDED IN ROUND 1 (FIRST HALF)

Developer Entity Name Site Address # of EV Spaces

Anticipated Date of

Activation

SP+ Neil Avenue Garage

(NWD Investments)

300 Neil Avenue

Columbus, OH 43215 4 12/1/2018

SP+ John McConnell Garage

(NWD Investments)

355 John McConnell Blvd

Columbus, OH 43215 4 12/1/2018

SP+ Grandview Yard North

(NWD Investments)

1125 Rail Street

Grandview Heights, OH 43212 4 12/1/2018

SP+ Chestnut Street Garage

(NWD Investments)

44 E. Chestnut Street

Columbus, OH 43215 4 12/1/2018

SP+ Arena Crossing Garage

(NWD Investments)

425 N. Front Street

Columbus, OH 43215 4 12/1/2018

Champion Sunbury Pointe Endeavors, LLC 2183 Rushmore Lane

Sunbury, OH 43074 6 11/1/2018

Champion Oak Creek Apartments/LLC 9000 Oak Village Blvd

Lewis Center, OH 43035 6 9/30/2018

Casto Riverside Sunshine LLC 260 McDowell Street

Columbus, OH 43215 4 11/1/2018

NEP Liberty Street 250 Liberty Street

Columbus, OH 43215 4 12/1/2018

TOTAL 40

PROJECTS AWARDED IN ROUND 1 (SECOND HALF)

Developer Entity Name Site Address # of EV Spaces

Anticipated Date of Contract

Completion

NEP Preserve Crossing 6400 Preserve Crossing Blvd.

Columbus, OH 43230 4 Oct. 2018

NEP Polaris 801 Polaris Parkway

Columbus, OH 43230 4 Oct. 2018

NEP Market Street 7079 Market Street

New Albany, OH 43054 4 Oct. 2018

NEP Waldon Street 700 Waldron Street

Columbus, OH 43215 4 Oct. 2018

Kaufman Gravity Project, LLC 500 W. Broad Street

Columbus, OH 43215 4 Oct. 2018

TOTAL 20

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

39

In August, Smart Columbus posted the solicitation for applications for a new round of MUD incentive

funding.

o $175,000 in additional funding is available to encourage EV charging infrastructure at MUDs.

o Incentives can be redeemed for a value of up to $3,500 per plug or parking space, with a maximum of

$25,000 awarded to any one site.

o Funding will be awarded based on several factors including geographical distribution of projects, outreach

and education plans developed for the proposed project, timeline for completion and proposed budget.

o Applications are available on the Smart Columbus website and the team will begin to review applications

in October 2018.

Next Steps:

Begin performing site visits at Year 1 MUD developments to ensure EVSE equipment is properly

installed and operational.

Review and award applications for Year 2 funding incentives.

Continue outreach to developers for Year 2 funding incentives.

Develop outreach materials.

Strategy 5.1.2 – Residential Charging Research and Assessment

Key Highlights:

The City of Columbus worked with a consultant and the DPU Finance Assistant Director to study

rates and assess EV charging.

AEP Ohio began researching potential technical configurations for residential off-peak charging and

demand response programs.

Next Steps:

AEP Ohio will continue their research.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

40

Initiative 5.2 – Public Access Charging

Key Highlights:

AEP Ohio launched its Commercial EV Charging Station Incentive Program to provide incentives

for business customers to install public access charging. See page 37 for additional information. In

July 2018, Smart Columbus began developing targeted outreach to potential public charging site

hosts to encourage them to apply.

Both broad and targeted outreach included a focus on

specific industry leadership, such as MORPC on the

public side and the Urban Land Institute on the private

side, in order to have a wider impact through their

membership bases.

Mapping of tiered priority charging locations was

included in this outreach for both public and private

entities whose physical site locations lined up with data

from the National Renewable Energy Laboratory

(NREL) public charging siting study.

Outreach to individual public entities about the available rebate incentives included the cities of

Dublin, Delaware, Whitehall and Grove City.

Smart Columbus reviewed potential charging sites for the CCAD public art project and identified

key constraints in branding, policy and engineering.

Due to aesthetics and downtown streetscape standards, members of the Smart Columbus charging

work group worked with AEP, DOP and DPS in order to consider the use of a commercial pedestal

enclosure instead of an exposed frame for the electrical equipment for the EV chargers to be

installed as part of the pilot project RFP at Mound and Fulton streets.

Next Steps:

Awaiting appendix finalization, the City of Columbus plans to release the Public Access Charging

Request for Bid (RFB) in Q7.

On October 23rd, Smart Columbus is presenting to the Downtown Arts Commission for the CCAD

public art project for public chargers in the City of Columbus. Potential sites include the existing

chargers at Goodale Boulevard and Gay Street or the future chargers at Mound and Fulton Streets.

Assist in finalizing the ODOT 2G plans for the utility equipment setup for meter, transformer and

panel for public DC fast charging.

Assist in plan review of public chargers.

Outreach materials developed during the AEP program will be retooled for future rebate programs

based around public charging.

AEP Ohio to process and award incentives for public access charging.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

41

Initiative 5.3 – Workplace Charging

Key Highlights:

Two new workplace charging sites with a total of 12 charging ports were added in Q6, as detailed in

the table below. See Appendix M – Workplace Charging Ports Installed To Date for the full list.

WORKPLACE CHARGING PORTS ADDED IN Q6

Organization Number and Type of Charging Ports

Big Lots 6 – Level 2

Cardinal Health 6 – Level 2

TOTAL 12 – Level 2

205 charging ports have been installed at 25 workplace sites to date, with an additional 12 sites

committed to date.

AEP Ohio launched its EV Charging Station Incentive program to provide incentives for business

customers to install workplace charging. See page 37 for more information.

Supported nine workplace charging applications to the AEP EV Charging Station Incentive

Program.

Next Steps:

Support additional workplace charging sites to apply to AEP incentive funding.

Continue tracking workplace charging deployments as they become operational.

AEP Ohio to process and award incentives for workplace charging.

Huntington Big Lots MORPC

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

42

Initiative 5.4 – Fleet Charging

Key Highlights:

The City of Columbus has installed 94 fleet chargers to date. Overall, 165 chargers have been

installed to date, including chargers at the CRAA, MORPC, OSU, City of Dublin, Franklin County

and Yellow Cab of Columbus.

86 charging ports were installed at three city-owned properties as part of the Part 1 City of

Columbus fleet charging project. These projects were designed to utilize Level 2 charging stations

to power the city fleet vehicles that were delivered earlier this year. These stations include power

management and data collection features that will allow the Smart Columbus team to capture vital

information on the usage of the vehicles. The properties included:

o City of Columbus Parking Garage, 141 N. Front Street – 50 charging ports;

o City of Columbus Department of Fire Facility, 3639 Parsons Avenue – 20 charging ports; and

o City of Columbus Central Outpost Building, 1155 McKinley Avenue – 16 charging ports.

The Smart Columbus team identified potential locations for the next phase of fleet charging. The

final engineering designs for an additional four fleet sites (10 ports) are underway and the chargers

are expected to be installed by March 31, 2019. These locations include:

o City of Columbus Refuse Facility, 4262 Morse Road – 2 charging ports;

o City of Columbus Fleet Management, 4211 Groves Road – 2 charging ports;

o City of Columbus Refuse Collection, 2100 Alum Creek Drive – 4 charging ports; and

o City of Columbus Jerry Hammond Center, 1111 E. Broad Street – 2 charging ports with potential

undergrounding for future chargers.

Data from the fleet chargers were successfully integrated into the Smart Columbus Operating

System.

Next Steps:

Find and request funding for charging for 75 remaining City of Columbus fleet EV purchases.

Develop a scope of improvements for the remaining fleet EV chargers in order to finalize locations,

numbers and expected costs.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

43

Initiative 5.5 – Building and Zoning Changes to Support EV Charging

Key Highlights:

The City of Columbus’ Director of Building & Zoning Services assigned a member of his staff to

assist with drafting city code changes to support future EV adoption. This staff member is currently

drafting code language for an EV parking policy.

Compiled various EV readiness and ‘right to charge’ policies from municipalities, consultants and

stakeholders to gain an understanding of current policies, best practices and their impact on EV

adoption. Using these resources, Smart Columbus began developing policy options for the City of

Columbus to support sustainable city wide EV infrastructure development.

Next Steps:

Finish draft policies for EV readiness and ‘right to charge’ laws and submit them to Building &

Zoning Services to draft the code language.

Begin outreach to the Columbus development community for opportunities for feedback and

recommendations on how EV charging policies can be best developed to benefit all stakeholders

involved.

Decide how to best apply recent fire code changes for EV charging to upcoming projects.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

44

PLAYBOOK

Content Generation

Smart Columbus E-Book

Key Highlights:

Nothing to report at this time.

Next Steps:

E-book will be developed at the end of the grant term.

Content Development and Management

Key Highlights:

The new Storyteller, Donna Marbury, started on July 9th. Her role includes publishing content and

material for the Playbook.

Met with Civitas Marketing, OSU, Columbus DOP and other Smart Columbus team members and

partners to generate and add content to future editorial calendars.

Organized and created content from existing program archives in preparation of the Playbook

launch.

The Smart Columbus team and the City of Columbus Department of Technology experienced

challenges with the website’s content management system during Q6. These technical challenges

delayed the launch of the Playbook section of the website and deployment of assets in the

Playbook.

Next Steps:

Continue to schedule and create content for the Playbook based off of lessons learned and Smart

Columbus programs.

Playbook Delivery Platform – Website

Key Highlights:

The Playbook website had a soft launch in

September. The Playbook will be a hub for the

articles, program archives, videos and other content

generated by Smart Columbus on the learnings and

processes of decarbonization and advancing

electrification.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

45

Next Steps:

Launch the Playbook to the public by the end of October 2018.

Playbook Content: Best Practice Documents and Multimedia Storytelling

Key Highlights:

Generated and collected best practices documents for the Playbook.

Created a Ride & Drive Roadshow video with Civitas Marketing. The video is still being finalized.

Finalized a series of six videos about different Electrification Program initiatives. The videos can be

found here: https://www.youtube.com/channel/UCxa4_Xzz00Ed3fpxlVD6BBw/videos. Videos topics

include:

o Program Overview;

o DC Solar’s partnership with Ohio Dominican University to provide solar panels that help light parking

lots and increase safety for students;

o The City of Columbus’ process of purchasing EVs to use in its fleet;

o The Acceleration Partners program;

o Smart Columbus Live; and

o Installing EV charging at MUDs.

Next Steps:

Continue to develop multimedia storytelling concepts based on upcoming programs and lessons.

Smart Webinars

Key Highlights:

Held webinars on the connected vehicle environment, multi-modal trip planning and the common

payment system, event parking management, the connected EV environment and mobility

assistance for people with cognitive abilities. Click here for a list of published webinars.

Created a plan for Smart Columbus webinars through Q7, with topics including: EV charging at

MUDs, the plan to electrify the taxi business (Smart Columbus TSP Rebate Program) and

Experience Center Live tour and the Acceleration Partner program.

Next Steps:

Schedule and execute webinars in Q7 based on the launch of the Playbook.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

46

Content Dissemination

Smart Columbus E-Book

Key Highlights:

Nothing to report at this time.

Next Steps:

E-book will be developed at the end of the grant term.

Attending and Presenting at EV-related and OEM Dominated Conferences

Key Highlights:

Smart Columbus continues to be a part of community events and take part in pertinent speaking

engagements. In Q6, members of the Smart Columbus team attended the EUCI Smart Cities

Conference, Tennessee Sustainability Transportation Forum, Midwest Green Fleets Forum and

International EV Symposium in Kobe, Japan, among other events and engagements. See Appendix

H for the full list of Q6 speaking engagements.

Next Steps:

In Q7, the Smart Columbus team is scheduled to present at LACoMotion in Los Angeles, and is

planning to schedule other opportunities.

Media Relations and PR

Key Highlights:

Smart Columbus issued five news releases about the Electrification Program.

Smart Columbus was featured in 177 articles during Q6, earning 14.4 million impressions. See

Appendix E for the list of publications and breakdown of regional, national and trade publications.

Next Steps:

Continue to develop and pitch media and public relations strategies through Q7.

Social Media

Key Highlights:

Finalizing B2B social media plan to launch in Q7.

Next Steps:

Social media for the Playbook will be implemented in Q7 along with the public launch of the

Playbook.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

47

Learning Exchanges

Key Highlights:

The Smart Columbus team attended and spoke at the Tennessee Sustainability Transportation

Forum, International EV Symposium in Kobe, Japan, and the US Ignite Forum in Philadelphia,

Pennsylvania.

Smart Columbus connected with the following cities/countries in Q6:

o Tulsa, Oklahoma;

o Raleigh, North Carolina;

o Montreal, Canada;

o Dayton, Ohio;

o Dresden, Germany;

o Seattle, Washington; and

o Charlotte, North Carolina.

Next Steps:

Continue to be opportunistic and drive new learning opportunities to cities.

Make international connections at EVS31 in Kobe, Japan, and Smart Cities World Congress in Barcelona, Spain.

Host officials from the city of Detroit, Michigan in Q7.

Develop an International Advisory Committee

Key Highlights:

Nothing to report at this time.

Next Steps:

The Columbus Partnership will be doing this in alignment with the grant, with the intent to identify

and convene this group in Year 2. It will be paid for separately and will be wider in scope.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

48

CONTRACTS AND PARTNER AGREEMENT STATUS

IMPLEMENTATION PLANS Implementation plans were submitted in prior quarters. No new implementation plans will be submitted.

RISK MANAGEMENT AND POLICY REGISTER Smart Columbus made progress on the Risk and Policy Register during Q6. See Appendix C for the

document.

PARTNER CONTRIBUTION Q6 STATUS UPDATE

American Electric Power (AEP) $22.8M No new updates.

The Ohio State University (OSU) $7.5M No new updates.

Columbus Partnership $7.5M No new updates.

DC Solar $5.4M

DC Solar deployed 12 trailers in

Q6 at $150,000 each, for an

additional $1.8M.

Mid-Ohio Regional Planning Commission (MORPC) $600,000 No new updates.

FleetCarma $900,000 No new updates.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

49

BUDGET AND COST MANAGEMENT Q6 saw an increase in project expenditures as activities ramped up. The reporting period for financial expenditure data for the City of Columbus

was based on invoices received through September 30, 2018.

0

200000

400000

600000

800000

1000000

1200000

1400000

Year 2 Spend Year 2 Commitments Year 2 Total

Year 2 Budget Analysis

0

500000

1000000

1500000

2000000

2500000

3000000

3500000

4000000

4500000

5000000

Program Spend Total Commitments Total To Date

Program Budget Analysis

Year 2 Spend: $690,824 Year 2 Commitments: $625,000 Year 2 Total: $1,315,824

Program Spend: $2,976,673 Commitments: $1,391,839 Total To Date: $4,368,512

APRIL 2017 THROUGH SEPTEMBER 2018

Priority 1 $ 99,950 $ 90,000 $ 189,950

Priority 2 $ 537,200 $ 405,000 $ 942,200

Priority 3 $ 2,351 $ 75,000 $ 77,351

Priority 4 $ 1,521,465 $ 274,839 $ 1,796,304

Priority 5 $ 612,050 $ 547,000 $ 1,159,050

Playbook $ 22,140 $ 0 $ 22,140

Program $ 181,517 $ 0 $ 181,517

Management

Actual Spend Commitments* Total

*Budget commitments

are estimated money

set aside by the PMO

for specific initiatives in

the grant program.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

50

SMART CITY SCHEDULE Activities within the schedule are progressing according to plan. Q6 saw an accelerated effort on Priority 5

with planning for the next rounds of charging infrastructure. See Appendix B for the schedule.

PERFORMANCE MEASUREMENT PLAN The Performance Measurement Plan was submitted to PGAPh with the Q5 report. No new updates were

made to the plan.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

51

ACTIVITY LOGS

PRIORITY 1 ACTIVITY LOG

ITEM TASK LEAD STATUS NOTES

Initiative 1.1 Utility-Scaled Renewables

Carryover Activities

1

AEP will identify and

interview consultants for

implementing the Utility

Scale Renewables

projects.

Sherry Hubbard,

AEP Ohio Completed

AEP issued a RFP for projects and

implementers in 2017.

2 AEP will review renewable

RFP responses.

Sherry Hubbard,

AEP Ohio Completed

AEP Ohio filed with PUCO on September

19th for the “Amendment to the 2018

Long-Term Forecast Report of Ohio

Power Company” to demonstrate the

need for at least 900 MW of renewable

projects in Ohio. See

http://dis.puc.state.oh.us/TiffToPDf/A1001

001A18I19B53347A02011.pdf.

3

AEP will maintain AEP

Ohio website

interconnection service for

customers to install new

distributed generation

projects.

Sherry Hubbard,

AEP Ohio Ongoing

Customers may fill out applications in

digital format and submit via email.

4

AEP will initiate research

on advanced clean energy

technologies.

Sherry Hubbard,

AEP Ohio Completed

AEP Ohio provided grants to two Ohio

universities.

Q6 Activities

1

AEP will continue program

for customer driven

distributed generation

projects and report on new

distributed generation

projects.

Sherry Hubbard,

AEP Ohio Ongoing

The number of applications submitted

have been increasing month over month.

2

Continue deployment of the

10 solar generators from

DC Solar.

Bud Braughton,

City of Columbus Ongoing

DC Solar deployed 12 additional units in

Q6: eight charging trailers at Yellow Cab

of Columbus, two charging trailers at the

State of Ohio West Broad site, and one

charging trailer for the City of Columbus.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

52

ITEM TASK LEAD STATUS NOTES

One trailer is being used for lighting at

OSU.

3

Develop new marketing

material for EcoSmart

program with new pricing.

Patti Austin, DOP Complete

DOP has been marketing via social media

and developed a newsletter that is going

to be mailed out to customers in their

monthly bill and emailed through the

billing portal.

4

Continue plans for using

biogas from City

wastewater treatment

plants as fuel for Combined

Heat and Power.

Patti Austin, DOP In Progress

Plans for the Jackson Pike WWTP are in

progress. The preliminary design work at

Southerly showed the digesters producing

significantly less biogas than the digesters

at Jackson Pike, due to differences in the

way the two plants operate their

processes.

DPU has some capital work underway at

Southerly that will improve the digesters.

We expect to reactivate the Southerly co-

generation project in a couple years, after

we improve those digesters and the

available biogas fuel increases.

5

Columbus Division of

Power to continue design

of rehabilitation of

hydroelectric plants.

Patti Austin, DOP In Progress

All field inspections are complete and

consultant is working on preliminary

engineering tasks. We have received the

technical memorandums, which make

recommendations about specific pieces of

equipment in the powerhouse. We expect

to receive the Detailed Design

Memorandum in Q7. The design phase is

23% complete.

Initiative 1.2 Grid Modernization and Efficiency

Carryover Activities

1

AEP to continue running

Community Energy Savers

program.

Sherry Hubbard,

AEP Ohio Ongoing

Community Energy Savers program

continues to be available for interested

communities.

2

AEP will contract with

research partner on Vehicle

to Home research.

Ryan Houk,

AEP Ohio Not Started

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

53

ITEM TASK LEAD STATUS NOTES

3

Columbus Power to

execute agreements with

vendors for Advanced

Metering Infrastructure.

Kristian Fenner,

DOP In Progress

The AMI RFP is being reviewed by the

Director and City Attorney.

4

Select team and refine

scope for Street Light

Technology Conversion.

Patti Austin, DOP Complete

The DPU team has reviewed all proposals

and selected a team for the street light

technology conversion assessment.

5

Microgrid: Identify sites

meeting PUCO defined

criteria for potential

locations.

Sherry Hubbard,

AEP Ohio Complete

Potential sites have been identified for

further consideration.

6

Microgrid: Begin

conducting preliminary

engineering and design

analysis.

Sherry Hubbard,

AEP Ohio Complete

High level, preliminary engineering and

design analysis has been completed on a

potential candidate site.

7

CES: AEP Ohio with Smart

Columbus representative(s)

to develop strategy to

reach out to Columbus civic

associations to raise

awareness of CES

eligibility, requirements and

benefits.

Sherry Hubbard,

AEP Ohio In Progress

AEP Ohio has begun discussions with

City staff on the potential use of CES to

support goals of increasing residential

energy efficiency audits.

8

CES: Civic associations to

self-identify interest in

participating.

Sherry Hubbard,

AEP Ohio In Progress

AEP Ohio team has met with

representatives from the Linden

Neighborhood to present the CES model

and explore their interest.

9

Columbus Power continue

planning Advanced

Metering Infrastructure –

locations, communications,

IT and data management.

Patti Austin, DOP In Progress The AMI RFP is being reviewed by the

Director and City Attorney.

10

Columbus Power to award

the contract for city for

Street Light Technology

Conversion.

Patti Austin, DOP In Progress A team has been selected and will be

awarded upon Director approval.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

54

ITEM TASK LEAD STATUS NOTES

Q6 Activities

1

Microgrid: Continue

engineering and design

analysis.

Sherry Hubbard,

AEP Ohio In Progress

Engineering and design analysis is

proceeding on one candidate project.

2

Microgrid: Facilitate

conversations with potential

site hosts.

Sherry Hubbard,

AEP Ohio In Progress

Initial discussions have begun with

potential site hosts.

3

CES: AEP Ohio supports

civic associations that

chose to participate by

facilitating meetings,

developing baselines,

assisting with setting goals

and selecting community

projects, co-developing

implementation plans,

preparing marketing

materials and tracking and

reporting progress.

Sherry Hubbard,

AEP Ohio In Progress

AEP Ohio has begun discussions with

City staff on potential use of CES to

support goals of increasing residential

energy efficiency audits. AEP Ohio’s team

has met with representatives from the

Linden Neighborhood to present the CES

model and explore their interest.

4

EE: AEP Ohio reports

savings estimates for

seven counties in Smart

Columbus after filing

annual compliance report

with Public Utilities

Commission of Ohio.

Sherry Hubbard,

AEP Ohio In Progress

Annual compliance report for 2018 to be

filed with Public Utilities Commission of

Ohio on or before May 15, 2019.

5

Columbus Power develop

specifications and prepare

terms and conditions for

Advanced Metering

Infrastructure.

Patti Austin, DOP In Progress The AMI RFP is being reviewed by the

Director and City Attorney.

6

Columbus Power to issue

notice to proceed for LED

street light construction.

Patti Austin, DOP In Progress

The NTP for construction will be issued

once the smart street light technology

assessment has been completed.

7 All new street lights

installed to be LED. Patti Austin, DOP Ongoing

DOP published specifications requiring all

new street lights to be LED.

https://www.columbus.gov/utilities/standar

ds/Street-Light-Specifications/

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

55

PRIORITY 2 ACTIVITY LOG

ITEM TASK LEAD STATUS NOTES

Initiative 2.1 Public Fleets

Carryover Activities

1

Continue to assist other

regional government

entities with EV technical

and safety training.

Andrew Conley,

CFO Ongoing

Hosted the Midwest Green Fleets

Forum & Expo, sponsored by Smart

Columbus, which featured dedicated

educational tracks on Electrification,

Smart Mobility and EV Ride & Drives.

2

City of Columbus and other

committed fleets accept

delivery and begin use of

EVs.

Kelly Reagan,

City of Columbus Ongoing

Fleets continue to commit, purchase

and deploy vehicles. See Appendix A

– Quarterly Indicators and Metric

Targets for details.

Q6 Activities

1

Continue to work with other

regional governments /

institutions to identify

electric fleet acquisition

opportunities.

Andrew Conley,

CFO Ongoing

Continuing to meet with, advise and

assist numerous public fleets

throughout the seven-county central

Ohio region.

2

Provide outreach and

education, analysis, vehicle

demonstrations and

additional resources to

public fleets, as needed.

Andrew Conley,

CFO Ongoing

Hosted the Midwest Green Fleets

Forum & Expo, sponsored by Smart

Columbus, which featured dedicated

educational tracks on Electrification,

Smart Mobility and EV Ride & Drives.

3

Secure additional public

fleet pledges/commitments

to deploy EVs and charging

infrastructure in their

jurisdictions.

Andrew Conley,

CFO Ongoing

Additional commitments were recently

secured from the cities of New Albany,

and Whitehall, and grant applications

were submitted by COTA and CRAA.

4

Continue working with

public fleets on

implementation of EV and

EVSE deployment plans,

including helping public

fleets sign on to City of

Columbus cooperative

purchase/bid package to

streamline acquisitions.

Kelly Reagan, City of Columbus;

Andrew Conley,

CFO

Ongoing

The City of Columbus finalized the

2019 Cooperative EV purchase

agreement pricing and contract

structure with Mike Albert Leasing,

Ricart and Byers. This is available to

all public and many private fleets

throughout the region.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

56

ITEM TASK LEAD STATUS NOTES

5

Plan and host regional

technical workshop and/or

training session for regional

fleets.

Andrew Conley, CFO

Ongoing

The Midwest Green Fleets Forum &

Expo provided numerous Q6 training

workshop sessions. See

http://www.midwestgreenfleets.com/.

Initiative 2.2 Private Fleets

Carryover Activities

1

Coordinate with Consumer

Adoption on Group

Purchase programs and

OEM dealer engagement

strategies that will support

Fleet Transition goals.

Zach McGuire,

Columbus Partnership In Progress

We have active engagement with

dealers and OEMs on fleet adoption,

although it has shown to be less

important than finding actual

convertible fleets, which is where effort

is focused.

2 Continue with baseline fleet

analysis for private sector.

Matt Stephens-Rich,

Electrification Coalition In Progress

Continued efforts with numerous

private fleets to provide analysis,

training and other resources to support

EV deployment.

3

Update/establish total fleet

vehicles available to

transition opportunity.

Matt Stephens-Rich,

Electrification Coalition In Progress

Secured three new private fleet

purchases and 25 new commitments in

Q6.

4

Update/establish fleet

purchasing options for

pledged companies.

Matt Stephens-Rich,

Electrification Coalition In Progress

Mike Albert Fleet Solutions has made

used EV purchasing options available

for Smart Columbus fleets to purchase

in Q6 and Q7.

Q6 Activities

1

Assist private entities with

installing charging

infrastructure.

Matt Stephens-Rich,

Electrification Coalition In Progress

Continued efforts with numerous

private fleets to provide assessment of

charging need for fleet deployment.

2 Continue to contact private

fleet managers.

Matt Stephens-Rich,

Electrification Coalition In Progress

Continued outreach to private fleet

managers and organizations, while

also using membership-based

organizations (chambers of commerce,

industry groups, etc.) to maximize

message and outreach.

3

Assist private fleet

managers with EV

technical and safety

training.

Matt Stephens-Rich,

Electrification Coalition In Progress

Provided technical and safety training to fleets, as needed, for procured vehicles.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

57

ITEM TASK LEAD STATUS NOTES

4

Assist private fleet

managers with

procurement specifications.

Matt Stephens-Rich,

Electrification Coalition In Progress

Provide recommended vehicles to

ensure optimal performance and cost

savings for operation.

5 Continue to receive private

fleet pledges.

Matt Stephens-Rich,

Electrification Coalition In Progress

Secured three new private fleet

purchases and 25 new commitments in

Q6.

Initiative 2.3 Transportation Service Providers

Carryover Activities

1

Coordinate with other fleet

and Consumer Adoption

programs to ensure

competitive pricing for

Group Purchase

Programs.

Andrew Conley, CFO

Kevin McSweeney,

City of Columbus

Ongoing

The City of Columbus finalized the

2019 Cooperative EV purchase

agreement pricing and contract

structure with Mike Albert Leasing,

Ricart and Byers. This is available to

all public and many private fleets

throughout the region. Yellow Cab of

Columbus is purchasing through Mike

Albert Leasing.

2

Develop detailed strategy

and associated timelines for

TSP EV adoption.

Andrew Conley, CFO

Kevin McSweeney,

City of Columbus

Ongoing

Awarded Round 1 of the TSP Rebate

Program to Yellow Cab of Columbus.

Finalized Round 2, which expands

eligibility to TNC drivers and is

expected to launch in Q7.

3 Assist TSPs with securing

an additional 30 EVs

Andrew Conley, CFO

Kevin McSweeney,

City of Columbus

Ongoing

Ten vehicles were purchased by

Yellow Cab of Columbus, 10 more

were committed, and up to 30 more

can funded through Round 2 of the

TSP Rebate Program.

Q6 Activities

1

Continue to contact TSP

fleet managers and

assessing opportunities.

Andrew Conley, CFO

Kevin McSweeney, City of Columbus

Ongoing

Outreach was performed to all licensed

cab drivers/companies; contacts with

Lyft and Uber, working closely with

Yellow Cab of Columbus.

2

Continue to provide

outreach, education,

analysis, vehicle

demonstrations and other

technical assistance to TSP

fleets as needed.

Andrew Conley, CFO

Kevin McSweeney,

City of Columbus

Ongoing

Hosted the Midwest Green Fleets

Forum & Expo, sponsored by Smart

Columbus, which featured dedicated

educational tracks on Electrification,

Smart Mobility, and EV Ride & Drives.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

58

ITEM TASK LEAD STATUS NOTES

3

Secure additional

pledges/commitments from

TSP fleets in the region.

Andrew Conley, CFO

Kevin McSweeney,

City of Columbus

Ongoing

10 vehicles purchased by Yellow Cab

of Columbus, 10 more committed, and

up to 30 more funded through TSP

Rebate Program Round 2.

4

Continue to assist TSP

fleet managers with EV

technical and safety

training.

Andrew Conley, CFO

Kevin McSweeney,

City of Columbus

Ongoing

Yellow Cab of Columbus exhibited and

participated in the Midwest Green

Fleets Forum & Expo, sponsored by

Smart Columbus, which featured

dedicated educational tracks on

Electrification, Smart Mobility, and EV

Ride & Drives.

5

Continue to market

consumer EV incentives to

TSP contract drivers.

Andrew Conley, CFO

Kevin McSweeney,

City of Columbus

Ongoing

Awarded Round 1 of the TSP Rebate

Program to Yellow Cab of Columbus.

Finalized Round 2, which expands

eligibility to TNC drivers and is

expected to launch in Q7.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

59

PRIORITY 4 ACTIVITY LOG

ITEM TASK LEAD STATUS NOTES

Initiative 4.1 Research and Assessment

Q6 Activities

No activities for Q6.

Initiative 4.2 Increase Consumer Awareness for EVs

Q6 Activities

1

Be opportunistic about

integrating EV promotion

into large scale events

throughout City.

Alex Slaymaker,

Columbus Partnership

McKinzie Harper,

Columbus Partnership

Ongoing

Continue to host activations at the

Experience Center and in the

community promoting EVs.

2

Establish a regular

cadence of media pitches

to deliver a steady

drumbeat of news to the

local community.

Jennifer Fening,

Columbus Partnership Ongoing

Issued five news releases related to

the Electrification Program.

3

Regularly and consistently

issue social media content,

engage with residents and

local influencers and

leverage paid spend to

expand the reach of Smart

Columbus’ social media

channels.

Jennifer Fening,

Columbus Partnership Ongoing

Smart Columbus was mentioned in

132 local media stories in Q6, earning

6.6 million local media impressions.

4 Launch fall semester

design project with CCAD.

McKinzie Harper,

Columbus Partnership In Progress

Continuing to work with CCAD

students through Q7.

Initiative 4.3 Drive Consumer Consideration for EVs

Carryover Activities

1 Execute Ride & Drive

Roadshow.

Alex Slaymaker,

Columbus Partnership Ongoing

Executed 19 events in Q6. Tracking

well to achieve program goals.

2 Cultivate new pledges for

workplace engagement.

Jordan Davis,

Columbus Partnership In Progress

Prospects were identified and the team

is scheduling meetings.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

60

ITEM TASK LEAD STATUS NOTES

3 Schedule dates for Ride &

Drives for Year 2.

Alex Slaymaker,

Columbus Partnership Completed

The team is now focusing on offering

2019 events to new partners.

4 Launch B2B campaign. Jennifer Fening,

Columbus Partnership In Progress Devising strategy for Q7/Q8 execution.

Q6 Activities

1

Continue speaking to

company executive

leadership teams.

Jordan Davis,

Columbus Partnership Ongoing Tracking well.

2

Continue identifying and

engaging with Mobility

Ambassadors.

Alex Slaymaker,

Columbus Partnership Ongoing

Tracking well. Engaging the next

cohort of Ambassadors in December,

and then are integrating them with

cohort 1 that launched in March 2018.

3

Announce final selections

of recipients for the Ignite

Action Fund.

Alex Slaymaker,

Columbus Partnership Ongoing

Awarded $100,000 to eight

organizations in Round 1. The team is

now accepting applications for Round

2.

4

Develop and distribute

communications toolkit

materials to employer

representatives.

Alex Slaymaker,

Columbus Partnership Ongoing

Distributed to existing partners. Will

share with Round 2 partners in

December.

5

Continue recruiting new

companies to join the

Acceleration Partner

Program.

Jordan Davis,

Columbus Partnership In Progress

Prospects have been identified and the

team is scheduling meetings.

6 Continue to distribute New

EV Owner’s Gift.

Zach McGuire,

Columbus Partnership In Progress

Distributed 44 gifts during National

Drive Electric Week. A majority of the

gifts will be distributed in October and

November.

7

Give extended test drives

to Columbus Partnership

members.

Alex Slaymaker,

Columbus Partnership Ongoing

Interest lower than expected for this

option. Tracking low.

8

Continue conducting test

drives at Showroom, on

Ride & Drive Roadshow,

and providing extended test

drives for executives.

Alex Slaymaker,

Columbus Partnership Ongoing

Overall, test drives tracking well and

driving perception shift.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

61

ITEM TASK LEAD STATUS NOTES

9

Develop, test and refine

campaign creative

concepts.

Jennifer Fening,

Columbus Partnership In Progress

Creative campaign shoot scheduled for

October 8-10th. Creative campaign is

expected to go live in November, with

refinements/optimization in December.

10

Develop playbook asset on

the findings of the creative

concept testing.

Donna Marbury,

Electrification Coalition Ongoing To be developed in December.

11 Deliver digital leads to

Columbus dealers.

Zach McGuire,

Columbus Partnership Ongoing

Have been delivering using 2020’s

online secure tool, but have begun

training dealers on our secure online

lead tool.

12 Measure and optimize B2B

campaign.

Jennifer Fening,

Columbus Partnership In Progress Re-evaluating strategic direction.

Initiative 4.4 Improving Consumer Sales Experience of EVs

Carryover Activities

1

Assess current dealership

engagement and make

necessary adjustments.

Zach McGuire,

Columbus Partnership Ongoing

Dealership engagement has been very

good, and we have added 11

Electrified Dealers.

2

Continue to educate

dealers about EVs and how

to increase sales.

Zach McGuire,

Columbus Partnership Ongoing

Trainings for dealers have gone well,

but the training could be improved.

Doing that over next few weeks.

3

Establish lead

management processes

and protocols.

Zach McGuire,

Columbus Partnership Ongoing

Training the dealers on how to use the

secure online tool we have created.

4

Receive best practices

from other cities for used

EVs.

Zach McGuire,

Columbus Partnership Stalled

Have yet to have engagement with

other cities on used car sales.

5

Continue discussions about

OEMs supplying EV

models for Experience

Center at new Smart

Columbus office.

Zach McGuire,

Columbus Partnership Ongoing

We are expanding our OEM reach as

well as dealers for Experience Center.

We also keep current partners

engaged to extend terms for current

vehicles.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

62

ITEM TASK LEAD STATUS NOTES

6

Determine how to assess

and track success of

Dealer Training Program.

Zach McGuire,

Columbus Partnership Ongoing

The dealer training program success,

as of now, will be tracked by sales data

that dealers report back to us.

Q6 Activities

1

Begin the rollout of the

Smart Columbus

Dealership Certification

Program.

Zach McGuire,

Columbus Partnership Complete

Certified 11 Electrified Dealers during

National Drive Electric Week.

2

Actively engage with local

dealership owners and

OEM leadership.

Zach McGuire,

Columbus Partnership Ongoing

Have done that well already, but will

continue to improve.

3 Facilitate dealer trainings. Zach McGuire,

Columbus Partnership Ongoing

Conducted 10 trainings already, and

will continue to improve the training.

4

Continue lead generation

efforts across consumer

consideration strategies

Zach McGuire,

Columbus Partnership Ongoing

Ride & Drives continue to be

successful, but process needs

improvement. Experience Center and

online leads have launched as well,

but need improvement on process.

5

Negotiate group purchase

rates for fleet and

consumer purchases of

new and used vehicles.

Zach McGuire,

Columbus Partnership In Progress

Has been difficult, outside of working

with Nissan. Will look to expand

vehicle options next quarter.

6 Conduct dealer trainings. Zach McGuire,

Columbus Partnership Ongoing

Have conducted eight trainings this

quarter. Will conduct another five new

dealer trainings next quarter.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

63

PRIORITY 5 ACTIVITY LOG

ITEM TASK LEAD STATUS NOTES

Initiative 5.1 Residential Charging

Carryover Activities

1

Develop a decision-

making criterion for L1

and L2 station

installations (MUD).

Megan Stein, CFO Removed Changed to all L2 stations.

2

Begin installation of MUD

EV charging

infrastructure.

Megan Stein, CFO In Progress MUD developers have begun the

installation of EVSE equipment.

3

Columbus Power will

study rates for EV

charging as part of larger

utility rate update.

Patti Austin, DOP In Progress

Columbus is working with a consultant

and the DPU Finance Assistant

Director to study rates and to assess

EV charging.

4

AEP will research

successful smart

charging integration

and off-peak charging

programs or demand

response programs.

Ryan Houk,

AEP Ohio In Progress

AEP Ohio began researching potential

technical configurations for residential

off-peak charging and demand

response programs.

5

Installation of up to

(pending on PUCO

approval) 250 Level 2

residential charging ports

(AEP).

Ryan Houk,

AEP Ohio In Progress

PUCO authorized AEP Ohio to offer an

EV Charging Station Incentives

Program of $10.4 million to business

customers to install 250 Level 2

charging ports, which will include 60

ports for MUDs.

6

Conduct inspections of

completed MUD

projects.

Megan Stein, CFO Not Started Inspections expected to begin in

November 2018.

7

Submit requests for

rebate payments to

Smart Columbus.

Megan Stein, CFO Not Started Rebate requests expected to begin in

December 2018.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

64

ITEM TASK LEAD STATUS NOTES

8

Provide payments to

developers for completed

projects.

Megan Stein, CFO Not Started

Payments are expected to be issued

beginning in November/December

2018.

9 Begin to collect data. Megan Stein, CFO Not Started Data collection is expected to begin in

January 2019.

10 Oversee education

activities. Megan Stein, CFO Not Started

Education activities are expected to

begin once all EVSE stations are

installed.

11

Advise developers in

installing signage

consistent with city

recommendations for

Year 1 projects.

Megan Stein, CFO Not Started

Developers have been provided with a

template of required signage and will

install signage once EVSE equipment

is installed.

12

Address any site

engineering issues with

Year 1 projects.

Megan Stein, CFO Not Started No issues have been identified to date.

13

Ensure appropriate

signage for Year 1

projects.

Megan Stein, CFO Not Started

Assurance of appropriate signage will

be reviewed during site visits prior to

rebates being issued.

14

Publish new (revised)

MUD grant program

solicitation.

Megan Stein, CFO Complete

New MUD incentive program was

announced on August 20th.

https://smart.columbus.gov/News/Sma

rt-Columbus-offering-$175,000-for-

electric-vehicle-charging-stations-at-

apartments-and-condominiums-in-

second-round-of-incentive-funding/

15

Conduct broad outreach

to developers to

encourage applications

for funding for Year 2.

Megan Stein, CFO In Progress Developing outreach materials for a

broad outreach campaign.

16 Recommend projects for

Year 2 funding. Megan Stein, CFO Not Started

No applications for funding have been

received to recommend for award.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

65

ITEM TASK LEAD STATUS NOTES

17

Qualify, at minimum,

three EVSE vendors to

participate in AEP Ohio

grant program.

Ryan Houk,

AEP Ohio Complete

Two network management system

providers, ChargePoint and

GreenLots, representing seven

equipment manufacturers were

prequalified.

18

Develop AEP Ohio

branding

recommendations for

grant program charging

stations.

Ryan Houk,

AEP Ohio Complete

AEP Ohio branding will be required for

all charging stations installed with

grant funding; AEP Ohio reserves the

right to remove its branding at its

discretion.

19

AEP Ohio to publicly

release grant application

to public for incentivized

rebates.

Ryan Houk,

AEP Ohio Complete

AEP Ohio publicly launched its EV

Charging Station Incentives Program

on August 16th. Funding will be

reviewed in three waves with the third

wave anticipated in Q9 (April – June

2019)

20 Process first wave of

grant applications.

Ryan Houk,

AEP Ohio In Progress

AEP Ohio has received 25 grant

applications for 80 Level 2 ports in a

mix of sites: workplace, public and

MUDs.

Q6 Activities

1 Continue to administer

Year 1 MUD projects. Megan Stein, CFO In Progress

Administration continues for Year 1

awards. All EVSE stations will be fully

installed and operational by December

31st.

2 Announce Year 2

awards. Megan Stein, CFO Not Started

No applications have been received

yet for Year 2 funding.

3

Help PMO secure

contracts for Year 2

awards.

Megan Stein, CFO Not Started

Contracts will be issued once

applications are received and awards

are made.

4

Develop marketing and

outreach strategy to help

developers engage and

educate tenants.

Megan Stein, CFO Not Started

A strategy will be developed to

educate tenants once applications are

received.

5

Develop appropriate

signage templates and

recommendations.

Megan Stein, CFO In Progress

Developers have a template of

required signage. Smart Columbus is

designing additional program signage.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

66

ITEM TASK LEAD STATUS NOTES

6 First wave of installations

to be finalized.

Ryan Houk,

AEP Ohio In Progress

AEP Ohio has pre-approved

applications for 58 ports to begin

design work.

7 Continuation of AEP Ohio

grant program.

Ryan Houk,

AEP Ohio In Progress

AEP Ohio will continue their grant

program until it is fully subscribed.

Initiative 5.2 Public Access Charging

Carryover Activities

1 Utilization Tracking

Mechanism.

Bud Braughton,

City of Columbus In Progress

This is being completed under Initiative

5.4 for chargers at Groves Road and

other City fleet sites.

2 Design and specifications

for sites completed.

Bud Braughton,

City of Columbus In Progress

Design changes are being made for

the Mound/Fulton project. Proposal is

to use Milbank as pedestal in lieu of

uni-strut design. Ludlow Street

awaiting agreement.

3

Determine highest

market needs for

charging sites in the

region, apply best

practices to develop lists

of owners/hosts of public

access charging sites.

Bud Braughton,

City of Columbus

Ed Ungar, HNTB

Dr. Stan Young, NREL

Complete

Team is working with local

governments and businesses that

have been identified as priority sites.

4 Construct first 5 fast

charging projects (AEP). Ryan Houk, AEP Not Started

Construction will begin after the EV

Charging Station Incentives are pre-

approved.

5

Continue to develop

public siting

methodology.

Ryan Houk,

AEP Ohio Not Started

PUCO order sets forth “first come, first

served” requirement for awarding EV

charging station incentives. Additional

siting methodology planning will

depend upon information gained after

installations are activated and data is

available.

6

Release rebate program

to begin soliciting EVSE

installations.

Ryan Houk,

AEP Ohio Complete

AEP Ohio publicly launched an EV

Charging Station Incentives Program

on August 16th. Funding will be

reviewed in three waves with the third

wave anticipated in Q9.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

67

ITEM TASK LEAD STATUS NOTES

Q6 Activities

1 Install 5 Level 2 charging

ports.

Bud Braughton,

City of Columbus

80%

complete

Four L2 sites installed at the State

facility located at 1970 W Broad Street.

2

Continue development of

partnerships with site

hosts and secure

commitments.

Bud Braughton,

City of Columbus

Ed Ungar, HNTB

Dr. Stan Young, NREL

In Progress

Contact was made with Columbus

Recreation and Parks, Dublin,

Delaware, Whitehall, et. al. A larger

outreach campaign is underway to

promote public charging within AEP’s

program and for future available funds.

3

Confirm city permitting

and planning functioned

as intended for initial

installations.

Bud Braughton,

City of Columbus Complete

Chargers are being installed at

Walmart on Hilliard-Rome Road under

the city permit process.

4

Install 4 DC fast charging

stations and 8 Level 2

charging ports.

Ryan Houk,

AEP Ohio In Progress

Discussions are underway with three

business customers interested in

potential grant applications for DC fast

charging.

5 Continue engaging and

educating citizens.

Ryan Houk,

AEP Ohio In Progress

AEP Ohio launched its informational

website, http://www.aepohio.com/ev to

increase understanding of EVs and

their benefits.

Initiative 5.3 Workplace Charging

Carryover Activities

1

Assist private entities

with site plans, charging

specifications and

construction.

Matt Stephens-Rich,

Electrification Coalition In Progress

Provide connection with vendors,

contractors, and best practices for

siting and speccing workplace

charging sites.

Q6 Activities

1

Continue discussions

with potential site hosts

and secure

commitments.

Zach McGuire,

Columbus Partnership

Matt Stephens-Rich,

Electrification Coalition

Ryan Houk, AEP Ohio

In Progress

AEP Ohio has held discussions with

more than 50 business customers who

have expressed initial interest.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

68

ITEM TASK LEAD STATUS NOTES

2

Provide facility managers

with any needed training

and assistance.

Zach McGuire,

Columbus Partnership

Matt Stephens-Rich,

Electrification Coalition

Ryan Houk, AEP Ohio

In Progress

AEP Ohio continues to engage in

dialog with interested parties.

Technical assistance is provided when

necessary. Charging providers are

educating interested parties as well

and serve as additional sources of

information.

3

Provide education

materials and

communications

assistance to support

efforts with employees.

Zach McGuire,

Columbus Partnership

Matt Stephens-Rich,

Electrification Coalition

Ryan Houk, AEP Ohio

In Progress

Continuing to distribute workplace

charging guide to workplaces and

private site owners in preparation for

projects to apply to AEP Ohio’s EV

Charging Station Incentive Program.

4 Determine long term plan

for workplace charging.

Zach McGuire,

Columbus Partnership

Matt Stephens-Rich,

Electrification Coalition

Ryan Houk, AEP Ohio

In Progress

AEP Ohio has begun efforts to develop

a strategy to increase the share of

businesses applying for workplace

charging in waves 2 and 3 of the EV

Charging Station Incentive Program.

5 Install 20 workplace

charging ports.

Zach McGuire,

Columbus Partnership

Matt Stephens-Rich,

Electrification Coalition

Ryan Houk, AEP Ohio

In Progress

AEP Ohio has pre-approved

applications for 20 workplace ports to

begin design.

Initiative 5.4 Fleet Charging

Carryover Activities

1

Complete installation of

96 chargers for

Columbus Fleet.

Bud Braughton,

City of Columbus In Progress

Per the City Inspector, one item needs

to be considered at the 141 N. Front

Street Garage by the electrical panel

manufacturer.

2

Begin developing plans

for Year 3 charging

station installations for

Columbus fleet.

Cristina Parady,

Brian Waibl Polania

City of Columbus

In Progress

Four locations were added. Awaiting

the Scope of Improvements document

from the Division of Finance for the

final phase.

3

Continue to advise and

work with Columbus

Fleet to determine needs:

number, locations,

specifications, etc.

Cristina Parady,

Brian Waibl Polania,

City of Columbus

In Progress

Phase 2 charging design plans are

close to completion. They are waiting

on final fleet duty cycle analyses for

Phase 3 in order to develop the scope

of improvements.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

69

ITEM TASK LEAD STATUS NOTES

4

Continue to advise and

work with other public

fleets to determine

needs: number,

locations, specs, etc.

Andrew Conley,

CFO In Progress

Continuing to assist in outreach,

advise and planning around EVSE

deployment for public fleets.

Q6 Activities

1

Continue developing

plans for charging station

installations for

Columbus fleet.

Cristina Parady,

Brian Waibl Polania,

City of Columbus

In Progress

Plans are 80% complete for 10 fleet

charging ports at four unique fleet

sites.

Initiative 5.5 Building and Zoning Changes to Support EV Charging

Carryover Activities

1 Common Charging

Payment System.

Bud Braughton,

City of Columbus In Progress

Working with the Multi-Modal Trip

Planning App and Common Payment

System.

2 Charging station

specifications complete.

Bud Braughton,

City of Columbus In Progress

Working on design for a pedestal

(Milbank or equivalent).

3

Finalize model site plan

and specifications for

installation of charging

ports.

EIT 1, CoC Not Started

Waiting for the implementation of

public chargers on Mound Street and

Fulton Street.

4

Columbus Power

will continue researching

successful smart

charging integration

and off-peak charging

programs.

Patti Austin, DOP In Progress

Columbus is working with a consultant

and the DPU’s Finance Assistant

Director to study rates and to assess

smart charging integration and off-

peak charging programs.

Q6 Activities

1

Review impact of policy

changes on initial charger

installations.

EIT 1, CoC Not Started

Waiting for the implementation of

public chargers on Mound Street and

Fulton Street.

2

Determine if additional

policy updates are

needed for future

installations.

EIT 1, CoC Not Started

Waiting for the implementation of

public chargers on Mound Street and

Fulton Street.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

70

PLAYBOOK ACTIVITY LOG

ITEM TASK LEAD STATUS NOTES

Carryover Activities

1 Launch Smart Columbus

website Phase 2.

Jennifer Fening,

Columbus Partnership Completed

Phase 2 of the Smart Columbus

website was launched in July 2018.

2 Q6 playbook editorial

calendar.

Jennifer Fening,

Columbus Partnership Completed Submitted to PGAPh in July 2018.

3

Date for Advisory

Committee set and

invitations to participants

distributed.

Jennifer Fening,

Columbus Partnership In Progress

The Columbus Partnership will be

doing this in alignment with the grant,

with the intent to identify and convene

this group in Year 2. It will be paid for

separately and will be wider in scope.

Q6 Activities

1

Smart Columbus to issue

two national news releases

on program

accomplishments or

learnings.

Jennifer Fening,

Columbus Partnership In Progress

Produced five news releases on

program accomplishments and

learnings in Q6.

2 Q7 playbook editorial

calendar.

Donna Marbury,

Electrification Coalition In Progress

Will be submitted to PGAPh in

October 2018.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

71

APPENDICES Included below are key components of the appendix for updates that happened during Q6. All other appendices are included as supplemental

documents. Please refer to the SharePoint site for these files. The documents are labeled according to their appendix number.

APPENDIX A – QUARTERLY INDICATORS AND METRIC TARGETS The Quarterly Indicators and Metric Targets spreadsheet is used as a way to track actual indicator progress against the established

targets/goals for each priority of the project on a quarterly basis. The indicators are provided at the Project, Priority and Initiative level.

Performance indicators are addressed at three levels:

1. The overall project level;

2. The five project priorities (grid decarbonization; fleet EV adoption; transit, autonomous and multi-modal systems in the city; consumer

EV adoption; and EV charging infrastructure); and

3. The specific initiatives under each priority area.

The project, priority and initiative indicators are hierarchical. Priority indicators contribute directly to a project indicator, and similarly, initiative

indicators contribute directly to one of their respective priority indicators. Progress indicators are also defined. Progress indicators encompass

anything that can be numerically evaluated and reflect progress towards objectives, but do not contribute directly to higher level indicators.

Methods and data sources for estimating indicators and tracking progress towards targets are described in the Performance Measurement Plan.

The ‘Adjusted Targets’ spreadsheet outlines the current goals that have been established by the project working groups for each indicator. The

‘Progress’ spreadsheet reports the actual progress of each indicator toward the established targets. The ‘Progress_Y1_P4’ spreadsheet reports

the progress specifically for Year 1 Priority 4 Indicators. This has been separated out due to Priority 4 future program development changes

having been included in the main ‘Progress Tab’.

The ‘Progress’ spreadsheet includes highlighted cells to help clarify how the spreadsheet functions. Cells that are yellow are direct inputs. Cells

that are orange are calculations that are either summing values or converting values to a common unit. Cells that are green are calculations that

are converting the appropriate values into MTeCO2 used to calculate overall GHG emission reductions.

Timelines for indicators that are contingent upon PUCO approval will be adjusted as approval is received.

See the attached Appendix A – SCC-P7-Quarterly Indicators and Metric Targets-Q6.xlsx for more detail.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

72

Below are some clarifications for the targets and progress KPIs:

Targets

The values in the cells highlighted yellow are still being developed as part of the Year 3 plan.

The values in the cells highlighted pink are using Year 1 forecasted values for the Life of Project (LOP) total instead of Year 1 goal totals.

Progress

The MWh of Columbus Division of Power Green Power sold (row 26) was updated for Q5 from an estimated value to actual. As a result,

the Columbus DOP Green Power sold as a percent of Total Power sold (row 37) was also updated.

The total number of ‘other government fleet vehicles’ for Q5 was reduced by two, as two of the purchase orders were delayed due to

bureaucratic reasons.

GHG reductions for EVs in Priority 2 and Priority 4 were updated to show the quarterly reductions in GHGs as cumulative, since it is

assumed that the EVs purchased in prior quarters of the grant period are still in operation and still contributing to a reduction in the region’s

emissions.

As part of Priority 3, the bike infrastructure lane miles (row 104) have been updated from what was shown in previous quarters to be

consistent with how the Electrification Plan defines the metric – including bike lanes, sharrows and shared-use paths.

The consumer ‘Estimated equivalent number of EVs purchased’ (row 109) was changed from an estimated to an actual (135 EVs changed

to 134 EVs).

The estimated number of social media followers that was previously reported for Q5 has increased with actuals (row 120).

The ‘Total Number (cumulative) of Companies with Mobility Ambassadors Identified’ (row 136) that was previously reported for Q5 has

decreased from 38 to 34 with actuals.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

73

Targets

Year 2 (2018) LOP

Q5 Q6 Q7

Q1-Q7

Goal

Total

Q1-Q7

To Date

2019

Total Total

Project Goals Result Result Result Result Result Result Result

% GHG emission reductions from baseline year 0.15% 0.15% 0.15% 0.11% 0.16% 0.23% 0.96%

Total GHG reductions/savings from baseline year (MTCO2) 38,897 39,276 39,868 29,450 41,182 60,719 249,391

Priority 1 - DecarbonizationPriority Indicators

#1: MW of renewable energy capacity installed 0.31 0.15 3.86 0.46 0.45 0.74 0 0 5.96 0 905 905

#2: MWh of renewable energy consumed 11,847 12,337 13,167 11,473 32,005 66,355 76,920 281,520 147,185 242,860 690,620 1,215,000

#3: MWh of energy saved (new renewable energy or energy efficiency) 57,000 57,023 57,090 40,122 40,235 40,235 40,000 280,000 291,705 160,000 40,000 480,000

Initiative 1.1: Utility Scale Renewables

Initiative Indicators

#1: Renewable energy MW capacity installed (Strategies 1.1.1, 1.1.7) 0.31 0.15 3.86 0.46 0.45 0.74 0 0 5.96 0 905 905

Utility Scale Wind Capacity Installed, MW (AEP) (Strategy 1.1.1) 0 0 0 0 0 0 - 0 0 0 900 900

Utility Scale Wind Energy Generated, MWh (AEP) (Strategy 1.1.1) 0 0 0 0 0 0 - 0 0 0 0

Utility Scale Solar Capacity Installed, MW (AEP) (Strategy 1.1.1) 0 0 0 0 0 0 - 0 0 0 0

Utility Scale Solar Energy Generated, MWh (AEP) (Strategy 1.1.1) 0 0 0 0 0 0 - 0 0 0 0

Capacity Installed for New AEP Distributed Energy Customers, MW (Strategy 1.1.3) 0.31 0.15 3.86 0.46 0.45 0.74 - - 5.96 - - -

Columbus DOP Hydroelectric Capacity Installed, MW (Strategy 1.1.7, installed capacity) 0 0 0 0 0 0 - - 0 0 5 5

#2: Renewable energy MWh consumed (Strategies 1.1.3, 1.1.4, 1.1.5, 1.1.6, 1.1.7) 11,847 12,337 13,167 11,473 32,005 66,355 76,920 281,520 147,185 242,860 690,620 1,215,000

MWh for New AEP Distributed Energy Customers (Strategy 1.1.3) 43 156 745 2,096 3,608 5,275 - - 11,923 - - -

MWh of renewable energy consumed through DC Solar mobile generators*, EV charging ports, and lighting towers (Strategy 1.1.4) 0 6 8 8 8 23 54

MWh of Columbus Division of Power Green Power sold (Strategy 1.1.5) 11,804 12,176 12,414 9,369 28,389 61,056 76,920 281,520 135,208 242,860 675,620 1,200,000

MWh from City of Columbus Wastewater Treatment Plant, Co-Generation (Strategy 1.1.6) 0 0 0 0 0 0 - 0 0 - 5,000 5,000

MWh from Columbus Division of Power Hydroelectric Improvements (Strategy 1.1.7, generated energy) 0 0 0 0 0 0 - 0 - - 10,000 10,000

Progress Indicators 0

#1: No. of New AEP Distributed Energy Customers (Strategy 1.1.3) 35 21 60 36 36 31 25 175 219 100 25 300

#2: Number of Deployments of mobile solar generators, EV charging ports, and lighting towers (DC Solar) (Strategy 1.1.4) 0 22 0 0 0 24 0 39 46 15 54

Number of mobile solar generators deployed* (Strategy 1.1.4) 0 1 0 0 0 1 0 2 0

Number of EV charging ports deployed (Strategy 1.1.4) 0 3 0 0 0 22 39 25 15 54

Number of mobile solar lighting towers deployed (Strategy 1.1.4) 0 18 0 0 0 1 0 19 0

#3: Columbus DOP Percent increase of MWh of Green Power sold (Strategy 1.1.5) (original) -7.0% -4.1% -2.2% -26.2% - 1.5% - 2.5% 4%

#3: Columbus DOP Green Power sold as a percent of Total Power sold (Strategy 1.1.5) (updated) 5.7% 5.7% 5.3% 4.3% 12.6% 25.0% 25% 25.0% 25.0% 28.4% 29.0% 29%

Initiative 1.2: Grid Modernization and Efficiency

Initiative Indicators

#3: Combined MWh saved from strategies 1.2.1, 1.2.5, and 1.2.7 57,000 57,023 57,090 40,122 40,235 40,235 40,000 280,000 291,705 160,000 40,000 480,000

MWh saved from AEP Ohio Energy Efficiency Participation (Strategy 1.2.1) 57,000 57,000 57,000 40,000 40,000 40,000 40,000 280,000 291,000 160,000 40,000 480,000

MWh saved from AEP Smart Lighting Program (Strategy 1.2.5) 0 0 0 0 0 0 0 0 0 0 0 0

MWh saved from Columbus DOP LED street lights installed (Strategy 1.2.7) 0 23 90 122 235 235 705 0

Progress Indicators 0

#1: GWh saved as a result of energy efficiency efforts (Strategy 1.2.1) 57 57 57 40 40 40 40 280 291 160 40 480

#2a: AEP AMI meters installed (Strategy 1.2.3) 0 6,600 3,400 72,860 99,676 157,372 100,000 400,000 339,908 128,000 528,000

#2b: AEP Micro Grids installed (Strategy 1.2.4) 0 0 0 0 0 0 0 0 1 1

#3: AEP Smart Lighting Program Smart controller unit installed (Strategy 1.2.5) 0 0 0 0 0 0 0 0 0 - 0

#4: Columbus Division of Power AMI meters installed (Strategy 1.2.6) 0 0 0 0 0 0 0 0 10,000 10,000

#5: Columbus Division of Power LED street lights installed (Strategy 1.2.7) 0 218 628 297 0 0 4,700 1,143 4,500 9,200

QUARTERLY INDICATORS AND METRIC TARGETS

Year 3 (2019)

After

Year 3

Year 1 (2017-2018)

Q1*

Apr-Jun

Q2

Jul-Sep

Q3

Oct-Dec

Q4

Jan-Mar

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

74

Year 2 (2018) LOP

Q5 Q6 Q7

Q1-Q7

Goal

Total

Q1-Q7

To Date

2019

Total Total

Project Goals Result Result Result Result Result Result Result

Priority 2 - Fleet AdoptionPriority Indicators

Fleet Electric Vehicles Purchased 4 3 100 31 15 4 203 341 157 446 3 790

Fleet Electric Vehicles Placed In Operation 4 0 5 0 23 29 81 221 61 456 113 790

Initiative 2.1: Public Fleets

Initiative Indicators

No. of EVs purchased 3 3 95 12 8 1 98 206 122 91 3 300

No. of EVs placed in operation 3 0 5 0 12 6 28 136 26 91 73 300

City of Columbus - EVs purchased 0 0 93 0 0 0 70 170 93 37 30 200

City of Columbus - EVs placed in operation 0 0 0 0 0 1 0 100 1 107 30 70 200

The Ohio State University - EVs purchased 0 0 2 0 0 1 24 26 3 24 50

The Ohio State University - EVs placed in operation 0 0 2 0 2 0 24 26 4 24 50

City of Dublin - EVs purchased 0 0 0 4 1 0 0 4 5 3 3 10

City of Dublin - EVs placed in operation 0 0 0 0 5 0 0 4 5 3 3 10

Franklin County - EVs purchased 3 3 0 5 0 0 0 0 11 10 10

Franklin County - EVs placed in operation 3 0 3 0 5 0 0 0 11 10 10

Other Government Fleets - EVs purchased 0 0 0 3 7 0 4 6 10 24 30

Other Government Fleets - EVs placed in operation 0 0 0 0 0 5 4 6 5 24 30

Progress Indicators

#1: Contacts made with other governments or institutions (Strategy 2.1.1) 16 34 10 40 60 100 14 75 260 40 115

#2: Municipal governments or institutions pledged to electrification (fleet analysis and vehicle acquisition plan) (Strategy 2.1.1) 0 0 5 6 5 2 2 15 18 5 20

#3: City of Columbus and public partner training sessions (Strategy 2.1.1) 1 3 1 1 4 3 1 5 13 4 9

Initiative 2.2: Private Fleets

Initiative Indicators

No. of EVs purchased 1 0 5 9 7 3 75 95 25 355 450

No. of EVs placed in operation 1 0 0 0 11 13 38 65 25 345 40 450

Progress Indicators

#1: Private Sector training sessions (Strategy 2.2.1) 0 1 1 0 1 1 1 7 4 4 11

#2: Establish and distribute EV survey/assessment document (Strategy 2.2.1) 50 1,300 0 0 0 0 0 1,450 1,350 125 1,575

#3: New private company pledged to electrification (Strategy 2.2.1) 0 0 7 6 6 6 0 40 25 15 55

#4: New private fleet vehicles pledged to electrification (Strategy 2.2.1) 20 0 3 34 63 25 0 390 145 60 450

#5: Completed vehicle analysis acquisition plan (Strategy 2.2.2) 5 5 5 4 3 3 5 25 25 20 45

Initiative 2.3: Transportation Service Providers (TSPs)

Initiative Indicators

No. of EVs purchased 0 0 0 10 0 0 30 40 10 0 40

No. of EVs placed in operation 0 0 0 0 0 10 15 20 10 20 40

Progress Indicators

#1: Number of contacts made with TSPs (Strategy 2.3.1) 0 0 3 5 7 2 4 20 17 10 30

#2: TSPs pledged to electrification (Strategy 2.3.1) 0 0 0 2 0 0 2 7 2 48 55

QUARTERLY INDICATORS AND METRIC TARGETS

Year 3 (2019)

After

Year 3

Year 1 (2017-2018)

Q1*

Apr-Jun

Q2

Jul-Sep

Q3

Oct-Dec

Q4

Jan-Mar

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

75

Year 2 (2018) LOP

Q5 Q6 Q7

Q1-Q7

Goal

Total

Q1-Q7

To Date

2019

Total Total

Project Goals Result Result Result Result Result Result Result

Priority 4 - Consumer Electric Vehicle AdoptionPriority Indicators

#1: EV Market Penetration (EVs purchased divided by total vehicles purchased) 0.44% 0.60% 0.58% 0.77% 0.52% 0.85% 1.10% 1.10% 0.85% 1.80% 1.80% 1.80%

#2: Estimated equivalent number of EVs purchased 115 161 147 190 134 255 290 1,359 1002 1639 - 2998

#3: Number of Executives Driving EVs 5 0 0 13 3 1 8 30 30 15 5 50

Initiative 4.1: Research and Development

Progress Indicators

#1: Perceived Desirability, Consumer likelihood, Consumer perception to own an EV (Strategy 4.1.1) See Appendix N of PfMP for Consumer Awareness Survey Findings

Initiative 4.2: Increase Consumer Awareness for EVs

Progress Indicators

#1: Local Promotion - Number of impressions at community events (Strategy 4.2.1) 0 0 0 0 453,155 751,275 50,000 1,000,000 1,204,430 1,000,000 1,000,000 3,000,000

#2: Local Promotion - Number of giveaways distributed at community events (Strategy 4.2.1) 0 0 0 0 1,502 5,609 500 8,500 7,111 200,000 240,000 448,500

#3: Local Promotion - Media Relations - Number of Local Media Placements (Strategy 4.2.2) 0 0 0 0 100 132 15 75 232 45 50 170

#4: Local Promotion - Media Relations - Number of Local Media Impressions (Strategy 4.2.2) 0 0 0 0 3,636,448 6,670,698 1,500,000 7,500,000 10,307,146 4,500,000 5,000,000 17,000,000

#5: Local Promotion - Number of Social Media Followers (Strategy 4.2.3) 0 0 0 0 5,425 956 250 3,000 6,381 4,000 6,000 6,000

#6: Local Promotion - Number of Social Media Impressions (Strategy 4.2.3) 0 0 0 0 142,820 618,878 30,000 82,500 761,698 100,000 125,000 307,500

#7: Local Promotion - Number of EV Assets with Smart Columbus branding (Strategy 4.2.4) 0 0 0 0 93 0 10 100 93 100 50 250

#8: Experience Center - Number of Visitors (Strategy 4.2.5) 0 0 0 0 1,355 2,720 1,000 5,000 4,075 5,000 200 10,200

#9: Experience Center - Number of EV Specific Events (Strategy 4.2.5) 0 0 0 0 5 5 2 4 10 10 2 16

Initiative 4.3: Drive Consumer Consideration for EVs

Initiative Indicators

#1: Number of Dealer Sales Leads generated 0 0 0 0 397 355 TBD 752 700 TBD TBD

Progress Indicators

#1: Number of Experience Center Test Drives Conducted (Substrategy 4.3.1.1) - - - - 0 123 50 200 123 180 20 400

#2: Number of Ride and Drive Roadshow Events Conducted (Substrategy 4.3.1.2) - - 10 4 31 19 10 70 64 53 120

#3: Number of test drives conducted at the Ride and Drive Roadshow Events (Substrategy 4.3.1.2) - - 810 369 3,624 2,370 1,000 7,800 7,173 6,000 12,000

#4: Number of attendees at Ride and Drive Roadshow Events (Substrategy 4.3.1.2) - - 923 25,000 34,714 30,000 2,000 9,000 90,637 11,000 20,000

#5: Number of Dealer Sales Leads Generated from Ride and Drive Roadshow (Substrategy 4.3.1.2) 0 0 0 0 397 353 150 891 750 750 1,641

#6: Number of extended test drives conducted (Substrategy 4.3.1.3) 0 0 0 0 0 0 5 15 0 20 35

#7: Total Number (cumulative) of Active Companies in Accelerator Partner Program (Substrategy 4.3.2.1) 4 44 46 45 45 48 65 65 48 95 100 100

#8: Total Number (cumulative) of Companies with Mobility Ambassadors Identified (Substrategy 4.3.2.2) 0 0 0 0 34 35 50 50 35 42 60

#9: Number of Ignite Action Fund Applications Received (Substrategy 4.3.2.2) 0 0 0 0 9 10 0 15 19 15 30

#10: Number of Ignite Action Fund Recipients (Substrategy 4.3.2.2) 0 0 0 0 0 8 0 10 8 10 20

#11: Number of Companies Introducing New Mobility Benefits (Substrategy 4.3.2.2) 0 0 0 1 1 4 10 10 6 40 50

#12: Website - Number of unique visits to Website (Substrategy 4.3.3.1) 0 2,026 480 201 14,002 6,988 40,000 100,000 23,697 125,000 150,000 375,000

#13: Website - Average time on Website (in minutes) (Substrategy 4.3.3.1) 0 0 0 0 2 2 2 2 2 2 2 2

#14: Website - Number of dealer referrals from Website (Substrategy 4.3.3.1) 0 0 0 0 0 3 TBD 3 TBD

#15: Education Campaign - Number of Education Campaign impressions (Substrategy 4.3.3.2) 0 0 0 0 0 0 TBD 0 TBD

#16: Education Campaign - Number of Education Campaign engagements (Substrategy 4.3.3.2) 0 0 0 0 0 0 TBD 0 TBD

#17: Education Campaign - Number of Education Campaign website referrals (Substrategy 4.3.3.2) 0 0 0 0 0 0 TBD 0 TBD

#18: Education Campaign - Number of Education Campaign dealer leads (Substrategy 4.3.3.2) 0 0 0 0 0 0 TBD 0 TBD

#19: B2B Marketing - Number of B2B Marketing impressions (Substrategy 4.3.3.3) 0 0 0 0 0 0 TBD 0 TBD

#20: B2B Marketing - Number of B2B Marketing engagements (Substrategy 4.3.3.3) 0 0 0 0 0 0 TBD 0 TBD

#21: B2B Marketing - Number of B2B Marketing Website referrals (Substrategy 4.3.3.3) 0 0 0 0 0 0 TBD 0 TBD

#22: Number of New Owner's Gifts Distributed (Strategy 4.3.4) 0 0 0 0 0 44 150 450 44 600 50 1,100

Initiative 4.4: Improve Consumer Sales Experience of EVs

Initiative Indicators

#1: Total number of EV models available in the Columbus Market - 0 0 18 23 23 15 15 23 23 23 23

#2: Ratio of models sold at dealerships in Columbus vs. models sold in the U.S. - 0% 0% 46% 58% 58% 55% 55% 58% 65% 75% 75%

#3: Ratio of dealerships selling BEVs and/or PHEVs vs. total operating dealerships in the Columbus area - 0% 0% 51% 54% 58% 58% 60% 59% 70% 75% 75%

#4: Ratio of OEMs supplying BEVs and/or PHEVs in Columbus vs. OEMs supplying models in the U.S. - 0% 0% 85% 100% 100% 80% 80% 100% 100% 100% 100%

Progress Indicators

#1: Additional Number of Dealers Actively Engaged (Substrategy 4.4.2.1) 7 1 3 6 3 2 4 14 22 22 0 36

#2: Additional Number of OEMs Actively Engaged (Substrategy 4.4.2.1) 2 2 0 1 2 1 0 9 8 3 1 13

#3: Number of Dealers Certified (Substrategy 4.4.2.2) 0 0 0 0 0 11 5 16 11 15 31

#4: Percentage of Total Columbus Dealerships Certified (Substrategy 4.4.2.2) 0% 0% 0% 0% 0% 14% 17% 17% 14% 33% 33% 33%

#5: Number of Trainings Conducted (Substrategy 4.4.2.3) 2 0 0 0 0 8 5 10 10 50 62

#6: Number of Different Dealers with Trained Salespersons (Substrategy 4.4.2.3) 0 2 0 0 0 11 5 12 11 15 27

#7: Number of negotiated group purchase rates (Strategy 4.4.3) 0 2 0 0 1 1 1 4 4 2 6

#8: Number of BEV and PHEV models eligible for group purchase rates (Strategy 4.4.3) 0 1 0 0 4 0 1 3 5 2 5

QUARTERLY INDICATORS AND METRIC TARGETS

Year 3 (2019)

After

Year 3

Year 1 (2017-2018)

Q1*

Apr-Jun

Q2

Jul-Sep

Q3

Oct-Dec

Q4

Jan-Mar

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

76

Year 2 (2018) LOP

Q5 Q6 Q7

Q1-Q7

Goal

Total

Q1-Q7

To Date

2019

Total Total

Project Goals Result Result Result Result Result Result Result

Priority 5 - Charging InfrastructurePriority Indicators

Number of electric charging station ports installed 65 67 57 24 81 109 133 391 403 526 8 925

L1 39 0 0 0 0 0 73 39 7 80

L2 26 65 57 20 81 109 123 376 358 466 8 850

DC Fast 0 2 0 4 0 0 10 15 6 60 0 75

Initiative 5.1: Multi-Unit Dwelling (MUD)

Initiative Indicators

#1: Number of Level 2 PMO MUD charging ports installed 0 0 0 0 2 0 30 90 60 2 30 90

#2: Number of Level 2 AEP Ohio MUD charging stations installed 0 0 0 0 0 0 15 20 0 40 60

Progress Indicators

#1: Number of MUD developers contacted to install EV Charging infrastructure (Strategy 5.1.1) 10 5 0 0 0 5 5 30 20 15 45

#2: Number of MUD developers who submitted application for MUD rebates (Strategy 5.1.1) 3 0 2 0 0 0 2 12 5 6 18

#3: Number of Level 2 PMO MUD charging ports proposed in approved Site Commitments/MUD Rebate approvals 0 0 48 24 0 0 0 60 72 30 90

Initiative 5.2: Public Access Charging

Initiative Indicators

#1: Number of Level 2 publicly accessible charging station ports installed – City of Columbus 7 7 0 0 4 6 10 5 30 25 24 30 0 5 60

#2: Number of DC fast charging stations installed - AEP 0 0 0 0 0 0 10 15 0 60 75

#3: Number of Level 2 publicly accessible charging station ports installed – AEP 0 7 0 0 0 0 15 30 7 60 90

Progress Indicators

#1: Number of meetings with potential site hosts 3 16 1 3 13 5 4 27 41 18 45

#2: Number of partnerships with site hosts and secure commitments 0 6 0 0 0 2 2 11 8 7 18

Initiative 5.3: Workplace Charging

Initiative Indicators

#1: Number of workplaces offering EV charging 3 4 8 4 4 2 20 45 25 55 100

#2: Number of workplace charging ports installed 49 49 47 24 24 12 35 115 205 135 250

L1 39 0 0 0 0 0 0 0 39 0 0

L2 10 47 47 20 24 12 35 115 160 135 250

DC Fast 0 2 0 4 0 0 0 0 6 0 0

Initiative 5.4: Fleet Charging Stations

Initiative Indicators

Number of level 2 charging station ports installed for Columbus and other public fleets 9 4 10 0 51 91 23 126 165 171 3 300

City of Columbus 0 0 0 0 24 70 0 96 94 104 200

The Ohio State University 1 0 2 0 12 2 23 26 17 24 50

City of Dublin 0 0 0 0 0 0 0 4 0 3 3 10

Franklin County 8 4 8 0 12 0 0 0 32 10 10

Other Government Fleets 0 0 0 0 3 19 0 0 22 30 30

Initiative 5.5: Building and Zoning Changes to Support EV Charging

Progress Indicators

Number of Site plan test cases submitted for permit 1 3 0 1 2 5 0 9 12 3 12

QUARTERLY INDICATORS AND METRIC TARGETS

Year 3 (2019)

After

Year 3

Year 1 (2017-2018)

Q1*

Apr-Jun

Q2

Jul-Sep

Q3

Oct-Dec

Q4

Jan-Mar

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

77

Year 2 (2018) LOP

Q5 Q6 Q7

Q1-Q7

Goal

Total

Q1-Q7

To Date

2019

Total Total

Project Goals Result Result Result Result Result Result Result

PlaybookInitiative Indicators

Number of people educated on Smart Columbus. Intent is to reach city officials, policy makers, business leaders and influencers. 0 0 0 0 157,688 673,452 200,000 500,000 831,140 2,000,000 2,000,000 4,500,000

B.2.1: Content Generation

Progress Indicators

#1: Website - Number of asset downloads, video views, webcast views (B.2.1.3) 0 0 0 0 0 1,000 750 1,250 1,000 1,750 2,000 5,000

#2: Website - Number of unique visitors outside the Columbus region (B.2.1.3) 0 0 0 0 6001 4054 20,000 30,000 10,055 70,000 150,000 250,000

#3: Website - Average minutes spent on site by visitors (B.2.1.3) 0 0 0 0 1.53 2.45 2 2 2.45 2 2 2

#4: Website - Number of newsletter signups (B.2.1.3) 0 0 0 0 0 147 250 1,700 147 1,000 2,700

#5: Content - Number of aggregated program archive documents published (B.2.1.4) 0 0 0 0 0 12 5 80 12 75 45 200

#6: Content - Number of learning tools created and published (B.2.1.4) 0 0 0 0 0 1 12 39 1 48 38 125

#7: Content - Number of organic webinars hosted (B.2.1.5) 0 0 0 0 0 0 2 5 0 8 5 18

#8: Content - Number of media webinars sponsored (B.2.1.5) 0 0 0 0 0 4 0 1 4 2 2 5

#9: Content - Number of webinar attendees (B.2.1.5) 0 0 0 0 0 850 100 300 850 500 350 1,150

B.2.2: Content Dissimenation

Progress Indicators

#1: E-Book - Number of city officials, policy makers, business leaders and influencers who receive Playbook e-book distribution (B.2.2.1) 0 0 0 0 0 0 0 0 0 1,000 1,000

#2: Conferences - Number of national or international speaking engagements on electrification at priority conferences (B.2.2.2) 0 0 0 0 7 5 1 6 12 3 5 14

#3: Conferences - Number of estimated attendees at national or international speaking engagements (B.2.2.2) 0 0 0 0 100 650 100 300 750 300 500 1,400

#4: Media Relations and PR - Number of trade media placements on electrification (B.2.2.3) 0 0 0 0 1 4 3 10 5 10 10 30

#5: Media Relations and PR - Number of trade media impressions on electrification (B.2.2.3) 0 0 0 0 8767 48873 180,000 400,000 57,640 400,000 500,000 1,300,000

#6: Media Relations and PR - Number of national media placements on electrification (B.2.2.3) 0 0 0 0 0 0 1 1 0 2 2 5

#7: Media Relations and PR - Number of national media impressions on electrification (B.2.2.3) 0 0 0 0 0 0 250,000 250,000 0 500,000 500,000 1,250,000

#8: Social Media - Number of impressions (B.2.2.4) 0 0 0 0 142820 618878 30,000 50,000 761,698 100,000 150,000 300,000

#9: Social Media - Number of click-throughs to the website (B.2.2.4) 0 0 0 0 0 818 2,500 3,500 818 5,000 7,500 16,000

#10: Learning Exchanges - Number of significant events hosted by Smart Columbus (B.2.2.5) 0 0 0 0 24 6 6 32 30 16 14 62

#11: Learning Exchanges - Number of conferences or speaking engagements presented by Smart Columbus (B.2.2.5) 0 0 0 0 45 46 15 120 91 60 70 250

#12: Learning Exchanges - Number of conferences or speaking engagements by Smart Columbus Partners, as tracked/reported to SC (B.2.2.5) 0 0 0 0 4 0 0 4 TBD

#13: Learning Exchanges - Number of cities Smart Columbus has traveled to for learning and information exchange (B.2.2.5) 5 2 4 5 6 2 3 18 24 10 20 48

#14: Learning Exchanges - Number of meetings with cities beyond seven county region (B.2.2.5) 0 0 0 0 16 2 4 24 18 12 12 48

QUARTERLY INDICATORS AND METRIC TARGETS

Year 3 (2019)

After

Year 3

Year 1 (2017-2018)

Q1*

Apr-Jun

Q2

Jul-Sep

Q3

Oct-Dec

Q4

Jan-Mar

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

78

Progress

Q1*

Apr-Jun

Q2

Jul-

Sep

Q3

Oct-

Dec

Q4

Jan-

Mar Q5 Q6 Q7

Q1-Q7

Total

Project Goals

% GHG emission reductions from baseline year 0.15% 0.15% 0.15% 0.11% 0.16% 0.23% 0.00% 0.96%

Total GHG reductions/savings from baseline year (MTCO2) 38,897 39,276 39,868 29,450 41,182 60,719 0 249,391

Priority 1 - DecarbonizationPriority Indicators

#1: MW of renewable energy capacity installed 0.31 0.15 3.86 0.46 0.45 0.74 0.00 5.96

#2: MWh of renewable energy consumed 11,847 12,337 13,167 11,473 32,005 66,355 0 147,185

#3: MWh of energy saved (new renewable energy or energy efficiency) 57,000 57,023 57,090 40,122 40,235 40,235 0 291,705

Initiative 1.1: Utility Scale Renewables

Initiative Indicators

#1: Renewable energy MW capacity installed (Strategies 1.1.1, 1.1.7) 0.31 0.15 3.86 0.46 0.45 0.74 0.00 5.96

Utility Scale Wind Capacity Installed, MW (AEP) (Strategy 1.1.1) 0 0 0 0 0 0 0

Utility Scale Wind Energy Generated, MWh (AEP) (Strategy 1.1.1) 0 0 0 0 0 0 0

Utility Scale Solar Capacity Installed, MW (AEP) (Strategy 1.1.1) 0 0 0 0 0 0 0

Utility Scale Solar Energy Generated, MWh (AEP) (Strategy 1.1.1) 0 0 0 0 0 0 0

Capacity Installed for New AEP Distributed Energy Customers, MW (Strategy 1.1.3) 0.31 0.15 3.86 0.46 0.45 0.74 5.96

Columbus DOP Hydroelectric Capacity Installed, MW (Strategy 1.1.7, installed capacity) 0 0 0 0 0 0 0

Conversion to MTCO2 0 0 0 0 0 0 0 0

#2: Renewable energy MWh consumed (Strategies 1.1.3, 1.1.4, 1.1.5, 1.1.6, 1.1.7) 11,847 12,337 13,167 11,473 32,005 66,355 0 147,185

MWh for New AEP Distributed Energy Customers (Strategy 1.1.3) 43 156 745 2,096 3,608 5,275 11,923

MWh of renewable energy consumed through DC Solar mobile generators*, EV charging ports, and lighting towers (Strategy 1.1.4) 0 6 8 8 8 23 54

MWh of Columbus Division of Power Green Power sold (Strategy 1.1.5) 11,804 12,176 12,414 9,369 28,389 61,056 135,208

MWh from City of Columbus Wastewater Treatment Plant, Co-Generation (Strategy 1.1.6) 0 0 0 0 0 0 0

MWh from Columbus Division of Power Hydroelectric Improvements (Strategy 1.1.7, generated energy) 0 0 0 0 0 0 0

Conversion to MTCO2 6,682 6,958 7,426 6,471 18,051 37,424 0 83,012

Progress Indicators

#1: No. of New AEP Distributed Energy Customers (Strategy 1.1.3) 35 21 60 36 36 31 219

#2: Number of Deployments of mobile solar generators, EV charging ports, and lighting towers (DC Solar) (Strategy 1.1.4) 0 22 0 0 0 24 0 46

Number of mobile solar generators deployed* (Strategy 1.1.4) 0 1 0 0 0 1 2

Number of EV charging ports deployed (Strategy 1.1.4) 0 3 0 0 0 22 25

Number of mobile solar lighting towers deployed (Strategy 1.1.4) 0 18 0 0 0 1 19

#3: Columbus DOP Green Power sold as a percent of Total Power sold (Strategy 1.1.5) (updated) 5.7% 5.7% 5.3% 4.3% 12.6% 25.0% 25.0%

Initiative 1.2: Grid Modernization and Efficiency

Initiative Indicators

#3: Combined MWh saved from strategies 1.2.1, 1.2.5, and 1.2.7 57,000 57,023 57,090 40,122 40,235 40,235 0 291,705

MWh saved from AEP Ohio Energy Efficiency Participation (Strategy 1.2.1) 57,000 57,000 57,000 40,000 40,000 40,000 0 291,000

MWh saved from AEP Smart Lighting Program (Strategy 1.2.5) 0 0 0 0 0 0 0

MWh saved from Columbus DOP LED street lights installed (Strategy 1.2.7) 0 23 90 122 235 235 705

Conversion to MTCO2 32,148 32,161 32,199 22,629 22,692 22,692 0 164,521

Progress Indicators

#1: GWh saved as a result of energy efficiency efforts (Strategy 1.2.1) 57 57 57 40 40 40 291

#2a: AEP AMI meters installed (Strategy 1.2.3) 0 6,600 3,400 72,860 99,676 157,372 339,908

#2b: AEP Micro Grids installed (Strategy 1.2.4) 0 0 0 0 0 0 0

#3: AEP Smart Lighting Program Smart controller unit installed (Strategy 1.2.5) 0 0 0 0 0 0 0

#4: Columbus Division of Power AMI meters installed (Strategy 1.2.6) 0 0 0 0 0 0 0

#5: Columbus Division of Power LED street lights installed (Strategy 1.2.7) 0 218 628 297 0 0 1,143

Conversion to MTCO2

      Priority 1 Subtotal GHG Reduction (MTCO2) 38,830 39,119 39,625 29,100 40,743 60,116 0 247,533

QUARTERLY INDICATORS AND METRIC PROGRESS

Year 1 (2017-2018) To Date

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

79

Q1*

Apr-Jun

Q2

Jul-

Sep

Q3

Oct-

Dec

Q4

Jan-

Mar Q5 Q6 Q7

Q1-Q7

Total

Project Goals

Priority 2 - Fleet AdoptionPriority Indicators

Fleet Electric Vehicles Purchased 4 3 100 31 15 4 0 157

Fleet Electric Vehicles Placed In Operation 4 0 5 0 23 29 0 61

Initiative 2.1: Public Fleets

Initiative Indicators

No. of EVs purchased 3 3 95 12 8 1 0 122

No. of EVs placed in operation 3 0 5 0 12 6 0 26

City of Columbus - EVs purchased 0 0 93 0 0 0 93

City of Columbus - EVs placed in operation 0 0 0 0 0 1 1

The Ohio State University - EVs purchased 0 0 2 0 0 1 3

The Ohio State University - EVs placed in operation 0 0 2 0 2 0 4

City of Dublin - EVs purchased 0 0 0 4 1 0 5

City of Dublin - EVs placed in operation 0 0 0 0 5 0 5

Franklin County - EVs purchased 3 3 0 5 0 0 11

Franklin County - EVs placed in operation 3 0 3 0 5 0 11

Other Government Fleets - EVs purchased 0 0 0 3 7 0 10

Other Government Fleets - EVs placed in operation 0 0 0 0 0 5 5

Conversion to MTCO2 2 2 5 5 11 15 0 15

Progress Indicators

#1: Contacts made with other governments or institutions (Strategy 2.1.1) 16 34 10 40 60 100 260

#2: Municipal governments or institutions pledged to electrification (fleet analysis and vehicle acquisition plan) (Strategy 2.1.1) 0 0 5 6 5 2 18

#3: City of Columbus and public partner training sessions (Strategy 2.1.1) 1 3 1 1 4 3 13

Initiative 2.2: Private Fleets

Initiative Indicators

No. of EVs purchased 1 0 5 9 7 3 25

No. of EVs placed in operation 1 0 0 0 11 13 25

Conversion to MTCO2 1 1 1 1 7 18 0 18

Progress Indicators

#1: Private Sector training sessions (Strategy 2.2.1) 0 1 1 0 1 1 4

#2: Establish and distribute EV survey/assessment document (Strategy 2.2.1) 50 1,300 0 0 0 0 1,350

#3: New private company pledged to electrification (Strategy 2.2.1) 0 0 7 6 6 6 25

#4: New private fleet vehicles pledged to electrification (Strategy 2.2.1) 20 0 3 34 63 25 145

#5: Completed vehicle analysis acquisition plan (Strategy 2.2.2) 5 5 5 4 3 3 25

Initiative 2.3: Transportation Service Providers (TSPs)

Initiative Indicators

No. of EVs purchased 0 0 0 10 0 0 10

No. of EVs placed in operation 0 0 0 0 0 10 10

Conversion to GHG (MTCO2) 0 0 0 0 0 6 0 6

Progress Indicators

#1: Number of contacts made with TSPs (Strategy 2.3.1) 0 0 3 5 7 2 17

#2: TSPs pledged to electrification (Strategy 2.3.1) 0 0 0 2 0 0 2

Priority 2 Subtotal GHG Reduction (MTCO2) 2 2 5 5 18 39 0 39

QUARTERLY INDICATORS AND METRIC PROGRESS

Year 1 (2017-2018) To Date

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

80

Q1*

Apr-Jun

Q2

Jul-

Sep

Q3

Oct-

Dec

Q4

Jan-

Mar Q5 Q6 Q7

Q1-Q7

Total

Project Goals

Priority 3 - Transit, Autonomous and Multi-Modal Systems in the CityPriority Indicators

Total GHG reductions/savings from baseline year (MTCO2) 0

Progress Indicators

#1: Autonomous Electric Vehicles Deployed (USDOT) 0 0 0 0 0 0 0

#2: Number of platooning truck trips (USDOT) 0 0 0 0 0 0 0

#3: Number of electric bicycles deployed 0 0 0 0 0 6 6

#4: Bike infrastructure lane miles added 1.60 4.34 1.40 0.00 1.10 10.00 18.44

Priority 3 Subtotal GHG Reduction (MTCO2) 0 0 0 0 0 0 0 0

Priority 4 - Consumer Electric Vehicle AdoptionPriority Indicators

#1: EV Market Penetration (EVs purchased divided by total vehicles purchased) 0.44% 0.60% 0.58% 0.77% 0.52% 0.85% 0.85%

#2: Estimated equivalent number of EVs purchased 115 161 147 190 134 255 1,002

#3: Number of Executives Driving EVs 5 2 6 13 3 1 30

Initiative 4.1: Research and Development

Progress Indicators

#1: Perceived Desirability, Consumer likelihood, Consumer perception to own an EV (Strategy 4.1.1)

Initiative 4.2: Increase Consumer Awareness for EVs

Progress Indicators

#1: Local Promotion - Number of impressions at community events (Strategy 4.2.1) 453,155 751,275 1,204,430

#2: Local Promotion - Number of giveaways distributed at community events (Strategy 4.2.1) 1,502 5,609 7,111

#3: Local Promotion - Media Relations - Number of Local Media Placements (Strategy 4.2.2) 100 132 232

#4: Local Promotion - Media Relations - Number of Local Media Impressions (Strategy 4.2.2) 3,636,448 6,670,698 10,307,146

#5: Local Promotion - Number of Social Media Followers (Strategy 4.2.3) 5,425 956 6,381

#6: Local Promotion - Number of Social Media Impressions (Strategy 4.2.3) 142,820 618,878 761,698

#7: Local Promotion - Number of EV Assets with Smart Columbus branding (Strategy 4.2.4) 93 0 93

#8: Experience Center - Number of Visitors (Strategy 4.2.5) 1,355 2,720 4,075

#9: Experience Center - Number of EV Specific Events (Strategy 4.2.5) 5 5 10

See Appendix N of PfMP for Consumer Awareness Survey Findings

QUARTERLY INDICATORS AND METRIC PROGRESS

Year 1 (2017-2018) To Date

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

81

Q1*

Apr-Jun

Q2

Jul-

Sep

Q3

Oct-

Dec

Q4

Jan-

Mar Q5 Q6 Q7

Q1-Q7

Total

Project GoalsInitiative 4.3: Drive Consumer Consideration for EVs

Initiative Indicators

#1: Number of Dealer Sales Leads generated 397 355 752

Progress Indicators

#1: Number of Experience Center Test Drives Conducted (Substrategy 4.3.1.1) - - - - 0 123 123

#2: Number of Ride and Drive Roadshow Events Conducted (Substrategy 4.3.1.2) - - 10 4 31 19 64

#3: Number of test drives conducted at the Ride and Drive Roadshow Events (Substrategy 4.3.1.2) - - 810 369 3,624 2,370 7,173

#4: Number of attendees at Ride and Drive Roadshow Events (Substrategy 4.3.1.2) - - 923 25,000 34,714 30,000 90,637

#5: Number of Dealer Sales Leads Generated from Ride and Drive Roadshow (Substrategy 4.3.1.2) 397 353 750

#6: Number of extended test drives conducted (Substrategy 4.3.1.3) 0 0 0

#7: Total Number (cumulative) of Active Companies in Accelerator Partner Program (Substrategy 4.3.2.1) 4 44 46 45 45 48 48

#8: Total Number (cumulative) of Companies with Mobility Ambassadors Identified (Substrategy 4.3.2.2) 34 35 35

#9: Number of Ignite Action Fund Applications Received (Substrategy 4.3.2.2) 9 10 19

#10: Number of Ignite Action Fund Recipients (Substrategy 4.3.2.2) 0 8 8

#11: Number of Companies Introducing New Mobility Benefits (Substrategy 4.3.2.2) 1 1 4 6

#12: Website - Number of unique visits to Website (Substrategy 4.3.3.1) 0 2,026 480 201 14,002 6,988 23,697

#13: Website - Average time on Website (in minutes) (Substrategy 4.3.3.1) 1.53 2.45 2.45

#14: Website - Number of dealer referrals from Website (Substrategy 4.3.3.1) 0 3 3

#15: Education Campaign - Number of Education Campaign impressions (Substrategy 4.3.3.2) 0 0 0

#16: Education Campaign - Number of Education Campaign engagements (Substrategy 4.3.3.2) 0 0 0

#17: Education Campaign - Number of Education Campaign website referrals (Substrategy 4.3.3.2) 0 0 0

#18: Education Campaign - Number of Education Campaign dealer leads (Substrategy 4.3.3.2) 0 0 0

#19: B2B Marketing - Number of B2B Marketing impressions (Substrategy 4.3.3.3) 0 0 0

#20: B2B Marketing - Number of B2B Marketing engagements (Substrategy 4.3.3.3) 0 0 0

#21: B2B Marketing - Number of B2B Marketing Website referrals (Substrategy 4.3.3.3) 0 0 0

#22: Number of New Owner's Gifts Distributed (Strategy 4.3.4) 0 44 44

Initiative 4.4: Improve Consumer Sales Experience of EVs

Initiative Indicators

#1: Total number of EV models available in the Columbus Market - 18 23 23 23

#2: Ratio of models sold at dealerships in Columbus vs. models sold in the U.S. - 46% 58% 58% 58%

#3: Ratio of dealerships selling BEVs and/or PHEVs vs. total operating dealerships in the Columbus area - 51% 54% 58% 58%

#4: Ratio of OEMs supplying BEVs and/or PHEVs in Columbus vs. OEMs supplying models in the U.S. - 85% 100% 100% 100%

Progress Indicators

#1: Additional Number of Dealers Actively Engaged (Substrategy 4.4.2.1) 7 1 3 6 3 2 0 22

#2: Additional Number of OEMs Actively Engaged (Substrategy 4.4.2.1) 2 2 0 1 2 1 0 8

#3: Number of Dealers Certified (Substrategy 4.4.2.2) 0 11 0 11

#4: Percentage of Total Columbus Dealerships Certified (Substrategy 4.4.2.2) 0 13.92% 13.92% 13.92%

#5: Number of Trainings Conducted (Substrategy 4.4.2.3) 2 0 0 0 0 8 0 10

#6: Number of Different Dealers with Trained Salespersons (Substrategy 4.4.2.3) 0 2 0 0 0 11 0 13

#7: Number of negotiated group purchase rates (Strategy 4.4.3) 0 2 0 0 1 1 0 4

#8: Number of BEV and PHEV models eligible for group purchase rates (Strategy 4.4.3) 0 1 0 0 4 0 5

Priority 4 Subtotal GHG Reduction (MTCO2) 65 155 238 345 420 564 0 564

QUARTERLY INDICATORS AND METRIC PROGRESS

Year 1 (2017-2018) To Date

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

82

Q1*

Apr-Jun

Q2

Jul-

Sep

Q3

Oct-

Dec

Q4

Jan-

Mar Q5 Q6 Q7

Q1-Q7

Total

Project Goals

Priority 5 - Charging InfrastructurePriority Indicators

Number of electric charging station ports installed 65 67 57 24 81 109 0 403

L1 39 0 0 0 0 0 0 39

L2 26 65 57 20 81 109 0 358

DC Fast 0 2 0 4 0 0 0 6

Initiative 5.1: Multi-Unit Dwelling (MUD)

Initiative Indicators

#1: Number of Level 2 PMO MUD charging ports installed 0 0 0 0 2 0 2

#2: Number of Level 2 AEP Ohio MUD charging stations installed 0 0 0 0 0 0 0

Progress Indicators

#1: Number of MUD developers contacted to install EV Charging infrastructure (Strategy 5.1.1) 10 5 0 0 0 5 20

#2: Number of MUD developers who submitted application for MUD rebates (Strategy 5.1.1) 3 0 2 0 0 0 5

#3: Number of Level 2 PMO MUD charging ports proposed in approved Site Commitments/MUD Rebate approvals 0 0 48 24 0 0 72

Initiative 5.2: Public Access Charging

Initiative Indicators

#1: Number of Level 2 publicly accessible charging station ports installed – City of Columbus 7 7 0 0 4 6 24

#2: Number of DC fast charging stations installed - AEP 0 0 0 0 0 0 0

#3: Number of Level 2 publicly accessible charging station ports installed – AEP 0 7 0 0 0 0 7

Progress Indicators

#1: Number of meetings with potential site hosts 3 16 1 3 13 5 41

#2: Number of partnerships with site hosts and secure commitments 0 6 0 0 0 2 8

Initiative 5.3: Workplace Charging

Initiative Indicators

#1: Number of workplaces offering EV charging 3 4 8 4 4 2 25

#2: Number of workplace charging ports installed 49 49 47 24 24 12 0 205

L1 39 0 0 0 0 0 39

L2 10 47 47 20 24 12 160

DC Fast 0 2 0 4 0 0 6

Initiative 5.4: Fleet Charging Stations

Initiative Indicators

Number of level 2 charging station ports installed for Columbus and other public fleets 9 4 10 0 51 91 0 165

City of Columbus 0 0 0 0 24 70 94

The Ohio State University 1 0 2 0 12 2 17

City of Dublin 0 0 0 0 0 0 0

Franklin County 8 4 8 0 12 0 32

Other Government Fleets 0 0 0 0 3 19 22

Initiative 5.5: Building and Zoning Changes to Support EV Charging

Progress Indicators

Number of Site plan test cases submitted for permit 1 3 0 1 2 5 12

QUARTERLY INDICATORS AND METRIC PROGRESS

Year 1 (2017-2018) To Date

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

83

Q1*

Apr-Jun

Q2

Jul-

Sep

Q3

Oct-

Dec

Q4

Jan-

Mar Q5 Q6 Q7

Q1-Q7

Total

Project Goals

PlaybookInitiative Indicators

Number of people educated on Smart Columbus. Intent is to reach city officials, policy makers, business leaders and influencers. 157,688 673,452 831,140

B.2.1: Content Generation

Progress Indicators

#1: Website - Number of asset downloads, video views, webcast views (B.2.1.3) 0 1,000 1,000

#2: Website - Number of unique visitors outside the Columbus region (B.2.1.3) 6,001 4,054 10,055

#3: Website - Average minutes spent on site by visitors (B.2.1.3) 1.53 2.45 2.45

#4: Website - Number of newsletter signups (B.2.1.3) 0 147 147

#5: Content - Number of aggregated program archive documents published (B.2.1.4) 0 12 12

#6: Content - Number of learning tools created and published (B.2.1.4) 0 1 1

#7: Content - Number of organic webinars hosted (B.2.1.5) 0 0 0

#8: Content - Number of media webinars sponsored (B.2.1.5) 0 4 4

#9: Content - Number of webinar attendees (B.2.1.5) 0 850 850

B.2.2: Content Dissimenation

Progress Indicators

#1: E-Book - Number of city officials, policy makers, business leaders and influencers who receive Playbook e-book distribution (B.2.2.1) 0 0 0

#2: Conferences - Number of national or international speaking engagements on electrification at priority conferences (B.2.2.2) 7 5 12

#3: Conferences - Number of estimated attendees at national or international speaking engagements (B.2.2.2) 100 650 750

#4: Media Relations and PR - Number of trade media placements on electrification (B.2.2.3) 1 4 5

#5: Media Relations and PR - Number of trade media impressions on electrification (B.2.2.3) 8,767 48,873 57,640

#6: Media Relations and PR - Number of national media placements on electrification (B.2.2.3) 0 0 0

#7: Media Relations and PR - Number of national media impressions on electrification (B.2.2.3) 0 0 0

#8: Social Media - Number of impressions (B.2.2.4) 142,820 618,878 761,698

#9: Social Media - Number of click-throughs to the website (B.2.2.4) 0 818 818

#10: Learning Exchanges - Number of significant events hosted by Smart Columbus (B.2.2.5) 24 6 30

#11: Learning Exchanges - Number of conferences or speaking engagements presented by Smart Columbus (B.2.2.5) 45 46 91

#12: Learning Exchanges - Number of conferences or speaking engagements by Smart Columbus Partners, as tracked/reported to SC (B.2.2.5) 4 0 4

#13: Learning Exchanges - Number of cities Smart Columbus has traveled to for learning and information exchange (B.2.2.5) 5 2 4 5 6 2 24

#14: Learning Exchanges - Number of meetings with cities beyond seven county region (B.2.2.5) 16 2 18

QUARTERLY INDICATORS AND METRIC PROGRESS

Year 1 (2017-2018) To Date

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

84

APPENDIX B – SCHEDULE Snapshots of each of the priorities are located below. See the Smart Columbus Q6 Schedule Update.pdf for the full schedule.

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

85

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

86

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

87

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

88

APPENDIX C – RISK AND POLICY REGISTER Risk is an uncertain event or condition that, if it occurs, has a positive (opportunity) or negative (threat) effect on a project’s objectives. The Risk

Register is used to identify, rate, rank and mitigate risks prior to the start of a project. It assists the team by focusing attention on higher ranking

items requiring more analysis and mitigation strategies. The Risk Register is a living document to be updated on a periodic basis and reviewed

during the Monthly Project Review meeting. See the Q6 Risk and Policy Register.xlsx spreadsheet in addition to the snapshots included.

Risk Terminology

DEFINITION EXAMPLES

Risk: An uncertain event or condition that, if it occurs, has a positive or

negative effect on one or more project objectives.1

Risk Acceptance: A risk response strategy whereby the project team decides

to acknowledge the risk and not take any action unless the risk occurs. 1

A potential change is design standards; reacting when and if it is

incorporated into the project objectives.

Risk Avoidance: A risk response strategy whereby the project team acts to

eliminate the threat or protect the project from the risk impact. 1

Usually involves change the project plan to eliminate the threat entirely.

Could include extending the schedule; reducing scope, changing the

strategy or approach. 1

Risk Mitigation: A risk response whereby the project team acts to reduce the

probability of occurrence or impact of a risk. 1

Taking early actions such as conducting workshops, partnering, draft

reviews, and other pre-emptive or non-conventional activities to lower the

likelihood of occurrence

Risk Transference: A risk response strategy whereby the project team shifts

the impact of a threat to a third party, together with the ownership of the

response. 1

When a Contractor has capabilities that the A/E does not possess,

transferring scope and responsibility contractually to the Contractor.

Risk Exploitation: A (opportunity) risk response strategy whereby the project

team seeks to eliminate the uncertainty associated with an upside risk by

ensuring the opportunity definitely happens. 1

Assigning an organization’s most talented resources to reduce the time to

completion or using new technologies or technology upgrades to reduce

cost and duration required to realize project objectives. 1

Risk Sharing: A (opportunity) risk response strategy whereby the project

team seek allocate some or all of the ownership of the opportunity to a third

party who is best able to capture the opportunity for the benefit of the project. 1

Forming risk sharing partnerships, teams, special-purpose companies, or

joint ventures, which can be established with the express purpose of

taking advantage of the opportunity so that all parties gain from their

actions. 1

Risk Enhancement: A (opportunity) risk response strategy whereby the

project team seeks to increase the probability and/or the positive impacts of an

opportunity. 1

Adding more resources to an activity to finish early. 1

1. Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK ® Guide) – Fifth Edition

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

89

Priority 1 – Decarbonization

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

90

Priority 2 – Fleet Electric Vehicle Adoption

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

91

Priority 4 – Consumer Electric Vehicle Adoption

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

92

Priority 5 – Charging Infrastructure

SMART COLUMBUS ELECTRIFICATION PROGRAM QUARTER 6 ACTIVITY REPORT: JUL – SEP 2018

93

APPENDIX D – POLK DATA IHS Markit (Polk) data is listed below through program Q5 (Q2 2018). Due to the report timing, Polk

data will only available through August 2018. Per IHS representative, the latest information will be

available on October 15th and will be provided to the Foundation on this date. For consistency, this data

will continue to be provided one quarter behind the report.

TIMEFRAME EV PHEV TOTAL (EV+PHEV)

TOTAL SALES %

Jan 2017 21 18 39 7,281 0.54%

Feb 2017 14 15 29 8,786 0.33%

Mar 2017 24 23 47 10,030 0.47%

2017 Q1 Total 59 56 115 26,097 0.44%

Apr 2017 19 13 32 8,659 0.37%

May 2017 32 21 53 9,704 0.55%

Jun 2017 42 36 78 8,587 0.91%

2017 Q2 Total 93 70 163 26,950 0.60%

Jul 2017 32 25 57 8,254 0.69%

Aug 2017 18 23 41 9,026 0.45%

Sep 2017 25 15 40 8,758 0.46%

2017 Q3 Total 75 63 138 26,038 0.53%

Oct 2017 44 19 66 8,005 0.79%

Nov 2017 18 28 46 8,097 0.57%

Dec 2017 49 32 81 8,540 0.95%

2017 Q4 Total 111 79 190 24,642 0.77%

Jan 2018 13 23 36 7,243 0.50%

Feb 2018 15 23 38 8,385 0.45%

Mar 2018 27 33 60 10,215 0.59%

2018 Q1 Total 55 79 134 25,843 0.52%

Apr 2018 54 19 73 9,028 0.81%

May 2018 56 35 91 10,422 0.87%

June 2018 - - - - -

2018 Q2 Total - - - - -