The Israel Electric Corporation Ltd. Smart Meter System March 2016 Smart Meter System Annexure “A” Terms and Conditions THE ISRAEL ELECTRIC CORPORATION LTD. PURCHASING DIVISION TENDER & MARKET RESEARCH DEPT.
Transcript
Page 1: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

The Israel Electric Corporation Ltd. Smart Meter System

March 2016

Smart Meter System

Annexure “A”

Terms and Conditions

THE ISRAEL ELECTRIC CORPORATION LTD.

PURCHASING DIVISION

TENDER & MARKET RESEARCH DEPT.

Page 2: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

The Israel Electric Corporation Ltd. Smart Meter System

- i -

TABLE OF CONTENTS

Article # HEADING OF ARTICLE Page #

1 DEFINITIONS 1

2 CONTRACTOR'S DOCUMENTATION 3

3 QUALITY ASSURANCE, REVIEW, INSPECTION AND

TESTING

4

4 WARRANTY 5

5 CHANGES IN THE WORK AND EXERCISE OF

OPTIONS

8

6 PROJECT SCHEDULE 10

7 PROGRESS AND OTHER REPORTS 10

8 UPDATED VERSIONS OF EQUIPMENT AND

SOFTWARE

11

9 RESERVED 11

10 TIME 11

11 DELAYS IN DELIVERY AND FINAL ACCEPTANCE 11

12 RESERVED 12

13 DELIVERY 13

14 TITLE 13

15 RISK OF LOSS AND DAMAGE 14

16 INSURANCE 14

17 RIGHT TO USE WORK REQUIRING CORRECTION 16

18 INTERFERENCE WITH OPERATION 16

19 WORK SITE AND ACCESS 17

20 SAFETY 17

21 ON-SITE SERVICES 18

22 CONTRACTOR'S TEST EQUIPMENT 18

23 FINAL ACCEPTANCE 19

24 FOLLOW-ON SUPPORT 20

25 FORCE MAJEURE 21

26 COMMERCIAL/VAT INVOICES 23

27 PAYMENT 25

28 TAXES AND DUTIES 28

28A ANTI DUMPING LEVY 28

29 GUARANTEES 29

30 PERMITS AND LICENSES 31

31 ASSIGNMENT AND SUBCONTRACT 31

32 INDEMNITY 36

33 LIMITATION OF LIABILITY 36

34 PATENTS/COPYRIGHT 36

35 SUSPENSION 37

36 TERMINATION FOR DEFAULT 39

37 TERMINATION FOR CONVENIENCE OF THE

PURCHASER

41

Page 3: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

The Israel Electric Corporation Ltd.

- b -

38 SETTLEMENT OF DISPUTES 43

39 WAIVER 39

40 SECRECY AND SECURITY 44

41 COMPLIANCE WITH LAWS. ORDINANCES, CODES

AND REGULATIONS

44

42 SEVERABILITY 45

43 LAW GOVERNING THE CONTRACT 45

44 NOTICES 45

FORM 1 CERTIFICATE OF MILESTONE ACHIEVEMENT 46

FORM 2 CERTIFICATE OF FINAL ACCEPTANCE 47

FORM 3 RESERVED

FORM 4 PURCHASER'S LETTER FOR CONTRACTOR'S

PERSONNEL

49

Page 4: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 1 -

Contract No. ___________________

Revised for Contract ________, 2016

THE ISRAEL ELECTRIC CORPORATION LIMITED

TERMS AND CONDITIONS

FOR PURCHASE OF A SMART METER SYSTEM

March 2016

1. DEFINITIONS

1.1 The Contract consists of the Agreement, these Terms and Conditions,

the Specification, and any other Annexures specified in the Agreement.

1.2 Whenever the terms "approval", "as approved", "acceptable",

"satisfactory", "or equal" or other similar terms are used in any

specification, such terms shall, unless expressly stated, mean "as

approved, etc., by the Purchaser or its duly appointed representative".

1.3 The term "Work" or "Works" includes, unless the context clearly

indicates otherwise, all labor, methods, material, equipment, computer

software, intellectual property rights, documentation, training,

transportation and other facilities, services and Follow-on Support

which the Contractor is required to furnish in order to complete the

Contract and are normally considered part of the type of project

covered by the Contract, whether or not fully detailed in the drawings,

if any, or listed in detail in Annexure "B".

1.4 The term "Delivered Duty Paid" or "DDP" shall have the meaning

attributed to it in "Incoterms 2010" issued by the International

Chamber of Commerce as amended, from time to time.

1.5 The terms “Project”, “Basic Contract Price”, "Contract Price",

"Contractor", "Price for Services", "Purchaser", shall have the

meanings attributed to them in the Agreement.

1.6 The term "System" means that the integration of hardware, software,

data, and communications forms a functional unit performing user

designated tasks, all as specified in Annexure "B". For the removal of

doubt the System shall also include any options exercised under this

Contract.

1.7 The term "Software" shall mean computer programs, procedures, rules,

and the associated documentation and data pertaining to the operation,

maintenance and updating of the System.

Page 5: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 2 -

1.8 The terms "Hardware"/"Equipment"/''Device"/"Components" shall

mean any physical element of the System.

1.9 The term "Installation" shall mean physical setup of System Hardware

and startup of system Software.

1.10 The term "Acceptance" shall mean the Purchaser's acknowledgment

that the System satisfies all specified requirements.

1.11 The terms "Inspection & Testing" (“I&T”) shall mean the procedures

for and the processes of exercising or evaluating the System and

implementation of such procedures and processes to verify that the

System, its Hardware and Software satisfy all specified requirements.

1.12 The term "On-Site Services" shall mean services to be furnished by the

Contractor at Purchaser's premises. These services shall be divided into

two categories:

(i) Services to be provided as required by the Contract in the

performance of installation, acceptance, training, testing,

maintenance, warranty, and project management.

(ii) Services to be provided, as requested by the Purchaser,

excluding the above, but including the options stated in article 4

of the Agreement (hereinafter "Optional On-Site Services").

1.13 The term "Final Acceptance" shall have the meaning assigned to it in

Article 23 herein.

1.14 The term "Sub-contractor" refers to the Subcontractors of the

Contractor.

1.15 The term "Work Site" shall be as described in Article 19 herein.

1.16 The term "Start-Up" shall mean the actions required to bring the

system at the Work Site to the same state as it was upon successful

completion of Contractor's tests.

1.17 Reserved.

1.18 The term "Test Equipment and Tools" shall mean the devices, tools,

simulators, and computer programs used for testing the Hardware and

Software components of the System.

1.19 The term "Follow-On Support" shall mean maintenance and support

provided by Contractor, or under its responsibility subsequent to the

Warranty period.

1.20 The term "Documentation" shall mean all technical information,

drawings or documentation required in the Contract, including but not

Page 6: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 3 -

limited to: drawings, analyses, Equipment certifications, data sheets,

inspection test reports, test records, quality plan, installation, operation,

maintenance and storage instructions or manuals, inspection and test

plan and all other specified and standard test reports;

2. CONTRACTOR'S DOCUMENTATION

2.1 Any Documentation required by the Purchaser for approval shall be

submitted by Contractor without unreasonable delay, and no work of

the Contractor affected thereby shall be started until the Purchaser's

written approval has been obtained.

2.2 The Purchaser shall not unreasonably delay any approval or comment

in respect of such Documentation. As far as practicable, each

Document shall bear a cross-reference note referring to the number or

numbers of the Purchaser's Documents showing the same work.

Purchaser's approval or conditional approval with comment signifies

permission to Contractor to proceed with the Work and indicates, but

does not warrant, that Purchaser has seen nothing in the Document at

variance with the Contract. Contractor's proceeding with the Work

prior to Purchaser's approval is at its own risk. Neither approval nor

conditional approval with comment shall relieve Contractor of any of

its responsibilities under the Contract.

2.3 Purchaser reserves the right, subject to any software licensing

restrictions, to reproduce any and all Documentation received from

Contractor under the Contract for Purchaser's use, notwithstanding any

notice to the contrary appearing on the Documentation.

2.4 The Contractor shall be responsible for any discrepancies, errors, or

omissions in the Documentation supplied by it, whether they have been

approved by the Purchaser or not.

2.5 The Contractor shall at its own expense carry out any alterations or

remedial work necessitated by reason of such discrepancies, errors, or

omissions and modify the Documentation accordingly. The

performance of its obligations under this Subarticle shall not relieve the

Contractor of its liability for delays in supplying the Documentation in

accordance with the specified dates insofar as such liability arises as a

result of any discrepancies, errors, or omissions.

2.6 The Purchaser shall be responsible for discrepancies, errors, and

omissions in drawings and information supplied by the Purchaser.

3. QUALITY ASSURANCE, REVIEW, INSPECTION AND TESTING

Page 7: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 4 -

3.1 The Contractor and its Subcontractors shall provide and maintain a

program as will ensure that the quality of the Work will be in

accordance with Annexure "B".

3.2 The Contractor shall be responsible for ensuring that it’s

Subcontractors' quality assurance/quality control programs including

procedures, personnel qualifications, etc. are approved by the

Contractor and are consistent with the specified requirements imposed

by the Purchaser in Annexures “B”.

3.3 The Contractor shall implement the agreed I&T Plans at the times and

in the manner as specified in Annexure "B".

3.4 Purchaser shall have the right to inspect or observe the production,

inspection, or testing of the Work at any time and place including the

Contractor's facilities and those of its Subcontractors where the Work

is being produced. Contractor shall provide ample notification of when

each part of the Work will be ready for tests and inspections. The

witnessing of Contractor's tests and inspections by Purchaser shall not

relieve Contractor of any of its responsibilities or liabilities under the

Contract, nor be interpreted in any way as implying acceptance of the

Work.

3.5 In the event Contractor fails to provide Purchaser with reasonable

facilities and access for such inspection and testing and if in the

opinion of the Purchaser it is necessary to dismantle and/or rework the

System or part thereof for such inspection, then, in coordination with

Purchaser, the Contractor shall dismantle and reassemble the System or

part thereof, perform the rework and bear the expense thereof.

3.6 Contractor shall conduct at its responsibility and expense, all tests and

inspections required by the Contract. Contractor shall repair and

replace, without cost or delay, anything found defective by tests,

inspections and also conduct at its own responsibility and expense re-

inspection and re-testing to ensure that the errors have been corrected

and no additional errors have been introduced.

Any inspection required by statutory authority, governmental

regulation, or other similar authority of the codes or standards must be

carried out by Contractor under its responsibility and expense.

3.7 Purchaser may reject any part of the Work found to be defective or not

in accordance with the Contract, regardless of the stage of its

completion or the time or place of discovery of such errors or any other

errors, and regardless of whether Purchaser's inspector has previously

accepted it. Such inspection by Purchaser shall in no way relieve

Contractor from its obligation to furnish the Work in accordance with

the Contract. Nothing said herein, shall deprive the Purchaser, after

Final Acceptance, of any right, or recourse, other than rejection,

available to it, under the law, or equity.

Page 8: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 5 -

4. WARRANTY

4.1 The Contractor warrants:

4.1.1 Materials and Equipment shall meet or exceed industry

standards as to quality, shall be new and unused in all cases,

and shall meet the performance and other requirements of the

Contract including Annexures "B";

4.1.2 Services shall be of a professional standard consistent with

good engineering practice and shall be rendered by

appropriately qualified personnel;

4.1.3 the Work and all parts thereof (including spare parts) shall be of

the kind and quality described in this Contract, and shall be fit

for the purpose for which it is supplied;

4.1.4 that there will be no systematic failures and design errors (all as

referred to in Annexure "B") in the System, its software,

hardware and design;

4.1.5 that the Software will contain the functionality and will

conform to the requirements specified in Annexure "B"; and

4.1.6 that the Software will operate on all the computers and

operating systems set out in Annexures "B", and on all

computers and operating systems which are upward compatible

with the computers and operating systems set out as aforesaid

4.2 Any part of the Work shall be considered defective or unsuitable if

among other things, it shall develop an undue amount of noise,

vibration, heating, deterioration, corrosion, strain, fatigue or wear

during the warranty period.

4.3 Contractor shall remedy (by no later than the time periods defined in

Annexure "B"), any portion of the Work, which within the warranty

period proves in any way defective as to design, material, workmanship

or skill or which was damaged due to errors or inaccurate written

instructions and/or Services rendered or otherwise not in accordance

with that warranted or unsuitable for the purposes specified in the

Contract. The Contractor shall correct (by repair, replacement or re-

performance) the defective portion of the Work, including, without

limitation, any required correction of erroneous design. Where Work

has to be replaced, such replacement shall be at the Purchaser's

premises.

After the Contractor has elected to repair or correct any part of the

Work more than twice, the Purchaser shall have the right to obligate

Page 9: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 6 -

the Contractor (at the Contractors risk and expense) to replace such

portion of the Work - including, in the case of series failure (as

specified in paragraph 15.5.1 of Annexure B), replacement of all

identical items of the defective Work supplied.

The costs of remedy or replacement shall be at the Contractor's expense

and shall include all shipping costs, both to and from Contractor's

facility, and the appropriate technical advice and direction for removal

of the defective Work and installation of the corrected Work including

On-Site Services as required, except in the case of a series failure the

provisions specified in paragraph 15.5.1 in Annexure B will also apply.

4.4 Any correction or replacement of the Work performed pursuant to the

provisions of this Article shall be done on the same terms and

conditions as provided for herein for the supply of the Work.

The Contractor shall bear the cost of replacing Equipment and

reworking Software damaged by such repair, replacement or

modification.

4.5 The decision to repair or replace Equipment or to rework Software

shall be made with the concurrence of the Purchaser and shall, where

possible, be scheduled consistent with the Purchaser's operating

requirements.

4.6 If Contractor does not respond to Purchaser's request for warranty

assistance and begin and diligently continue to correct any such Work

within the time periods prescribed in Annexure "B", then the

Purchaser, after giving written notice to Contractor, may correct it at

Contractor's expense without prejudice to any other rights of the

Purchaser under this Contract or by law. Without derogating from such

rights, the Purchaser may execute such Work either by its own

workmen or by others and shall be entitled to retain and apply the

balance of any sum which may be otherwise due to the Contractor

under the Contract as may be necessary for the payment of the costs

and expenses incurred in the execution thereof.

4.7 The Warranty Period shall be as follows:

4.7.1 for Warranty in respect of meters, instrument current

transformers (CTs), data concentrators and associated

components, the period shall run for 3 years beginning at the

time of delivery of each deliverable.

In addition, Purchaser shall have an option to extend the

warranty period by a year at a time up to a maximum of 3 years

by giving notice of same to the Contractor by no later than 90

days after the expiration of the warranty period.

Page 10: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 7 -

4.7.2 for Warranty in respect of software systems and associated

hardware, the period shall run for 1 year beginning at the time

of Final Acceptance of the System in respect of the software

and for 3 years beginning at the time of delivery in respect of

the hardware.

4.8 The above warranties shall also apply to any reworked Software,

repaired or replacement parts, commencing from the date of reworking,

repairing or replacement.

4.9 Without derogating from the provisions of Sub-article 4.7 above, the

warranty period on the Hardware or Software supplied under the

Contract shall be extended by a period equal to the period of duration

for which the Hardware or Software or any part thereof or any part

dependent thereon is out of operation due to the Contractor or any other

breach of that warranted herein.

4.10 The warranties set forth in this Contract are exclusive to Purchaser and

replace any other warranties which are disclaimed and excluded by the

Contractor.

5. CHANGES IN THE WORK AND EXERCISE OF OPTIONS

5.1 The Contractor shall not alter any of the Work except as directed in

writing by the Purchaser’s Purchasing Division, but the Purchaser

shall have full power, subject to the provisions hereinafter contained,

from time to time during the period of performance of the Contract, by

notice in writing (hereinafter referred to as a "Change Order") to direct

the Contractor to alter, amend, omit, delete, add to or otherwise vary

any of the Work, and the Contractor shall carry out such variations, and

be bound by the same conditions as far as applicable, as though the said

variations were originally stated in Annexures "B".

The Purchaser may also make changes in the quantity of parts of the

System (including Services) by way of exchanging certain items in the

scope for other items; provided however that the overall price of the

System shall remain unchanged or as otherwise agreed with the

Contractor.

5.2 In any case in which the Contractor has received a Change Order from

the Purchaser, Contractor is required to respond to Purchaser within 21

calendar days, or such time as Purchaser shall specify for a Change

Order. The Contractor shall, where necessary insert or delete the

necessary modifications in the Change Order, and shall include an

explanation of the impacts of the requested changes reflected in the

Change Order (as well as the Contractor's modifications to the Change

Order, if any).

Page 11: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 8 -

5.3 The Change Order (including the Contractor's modifications, if any)

must cover the following items:

5.3.1 Cost, fully detailed (in the case of additional optional services

for software systems available during the course of the Project

and during the year of warranty, the cost shall be calculated

according to Work actually performed, in accordance with the

daily rate stipulated in Table 5 of Annexure “C1”);

5.3.2 Increase or decrease in Contract Price;

5.3.3 Schedule, fully detailed;

5.3.4 Changed date(s) of delivery, if any;

5.3.5 Substitution, spare memory, processor loading, input and output

devices and allowances;

5.3.6 The complement to hardware and software System

performance, spare capacities and testing;

5.3.7 Training, documentation and spare parts;

5.3.8 Other, to the extent they are affected.

5.4 The amount of the difference in the Contract Price payable by the

Purchaser shall be ascertained and determined in accordance with the

non-escalated and unadjusted base rates specified in the Contract

insofar as the same may be applicable, if any. Where rates are not

contained in the said Contract at such date or are not applicable, such

amounts shall be agreed between the Purchaser and the Contractor

having regard to Contractor's actual proven costs incurred, plus an

amount for reasonable profit. Upon reaching an agreement, Purchaser

shall issue the Change Order and the revised provisions of the Contract

shall enter into full force and effect. Failing such agreement, the above

amount shall be determined by arbitration in accordance with Article

38 hereof.

5.5 Any reasonable delay in the performance of the Contract resulting from

any variation in any part of the Work required by the Purchaser shall

not be deemed to be a breach of the Contract and shall extend the

performance time thereof if so notified by the Contractor to the

Purchaser prior to carrying out the Change Order.

5.6 Notwithstanding the provisions above, Contractor may initiate a

request for change. The procedure defined in the preceding paragraphs

shall be followed except that the Contractor shall prepare the initial

drafts of all Change Orders.

5.7 Exercise of Options

5.7.1 The Purchaser shall have the right to exercise any options by the

dates set forth in the Contract.

5.7.2 Purchaser shall provide Contractor with a “Notice of Exercise of

Option”, whereupon Contractor shall have fifteen (15) working

Page 12: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 9 -

days to provide Purchaser with all additional data and

information required for the exercise of the option. Such

additional data and information shall not derogate from or in

any manner, alter or amend the option terms.

5.7.3 Upon finalization of all the details regarding the exercise of an

option, Purchaser shall issue a Change Order or supplementary

order.

6. PROJECT SCHEDULE

6.1 Contractor agrees to maintain and abide by the Project Schedule

forming part of Annexure "I" to the Contract. The Project Schedule

contains major milestones in the performance of the Contract by the

Contractor. The milestones set out therein shall be highlighted in the

Contractor's Progress Reports to be submitted in accordance with

Article 7 below.

6.2 In the event the Purchaser is of reasonable opinion that the Contractor

is unable to keep or maintain the Project Schedule set out in Annexure

"I" or its ability properly to perform the Contract is otherwise impaired

or likely to be impaired, the Purchaser may demand of the Contractor

by notice in writing that it supply reasonable assurances of due

performance to the satisfaction of the Purchaser, in addition to and

without derogating from the guarantees given under this Contract. If

within 15 days of the Contractor's receipt of the Purchaser's demand,

such assurances have not been supplied, such failure shall constitute a

breach of a fundamental term of the Contract.

7. PROGRESS AND OTHER REPORTS

7.1 Contractor shall submit to the Purchaser on or about the fifth of each

month a report stating the progress being made in fulfillment of this

Contract up to the last day of previous month.

7.2 The Progress Reports shall include all data relevant to the progress of

Work covering but not limited to the milestones set out in the Project

Schedule.

7.3 Form of Progress Reports.

The information to be reported shall be derived from the Project

Schedule (Annexure I) and shall be inserted in the reports relevant to

progress of the Work which shall be prepared based upon the PERT

Charts relating to all Work packages and tasks and shall be divided

into the following sections:

Page 13: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 10 -

(1) Completed activities (in writing);

(2) On-going activities (in writing);

(3) Planned activities (in writing);

(4) GANTT chart showing all completed, ongoing and planned

activities time schedule vs. their contractual time schedule. The

GANTT and PERT diagrams shall include detailed steps,

critical path that may influence the final date, period of time for

each step, and the responsibility for execution of each step.

7.4 Notification of Delay.

In every case of delay or anticipated delay, from whatever cause, in

fulfillment of the Contract by the Contractor, which is likely to

postpone the Project Schedule milestone dates provided in the

Contract, the Contractor shall notify the Purchaser in writing within

seven days after Contractor becomes aware of the cause of the delay

and the changed date of delivery. Such notification, however, shall not

in any way absolve the Contractor from making every endeavor to

overcome the delay.

8. UPDATED VERSIONS OF EQUIPMENT AND SOFTWARE

Subject to the Contractor's compliance with the technical requirements of the

Contract, the Contractor shall provide the Purchaser with the most updated

versions of Equipment and/or Software available at the required contractual

delivery dates.

9. RESERVED

10. TIME

10.1 The Contractor shall comply with the schedule contained in Annexure

"I".

10.2 In the event of a failure of the System, due to a problem, error or

deficiency in, with or relating to the System itself for which the

Contractor is responsible, which either delays or which prevents

satisfactory Start Up or which delays the satisfactory completion of

Final Acceptance (as specified in Article 23 below) thereof, Contractor

shall be liable for liquidated damages, as set forth in Article 11 below.

11. DELAYS IN DELIVERY AND FINAL ACCEPTANCE

11.1 Delivery

Page 14: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 11 -

Notwithstanding any notification of delay in fulfillment of the Contract

in the circumstances stated in Article 7.4 above, where the

contractually scheduled delivery as set forth in the Contract or any

Change Order, is delayed more than 10 days beyond the specified

delivery date/s (excluding delay/s for which the Contractor is not liable

under the Contract), the Contractor shall pay to the Purchaser, as

liquidated damages, 1% (one percent) of the Contract value of the

delayed goods per full week of delay in delivery.

Where the Contractor has been required to supply a sample or

prototype prior to delivery of the goods and because of delay in the

delivery of the approved sample or prototype, delays are caused to the

delivery of the goods, the Contractor shall be liable for liquidated

damages for the period commencing from the contractually scheduled

delivery date of the sample or prototype, until the contractually

scheduled date of delivery of the goods in respect of which the

prototype has been requested at the rate of one percent (1%) of the total

value (100%) of the goods under the Contract/Order, in respect of

which the prototype, has been requested, per full week of delay.

The Contractor, however, shall not be liable under this Sub-article 11.1

to pay liquidated damages as aforesaid exceeding 10% (ten percent) of

the Contract Price specified in the Agreement.

11.2 Final Acceptance

In addition to the provisions of Sub-article 11.1 above, where the

parties have mutually agreed upon the contractual Project Schedule for

the Final Acceptance as defined in Sub-article 23.1 below, in the event

the contractually scheduled Final Acceptance as agreed between the

parties or by any Change Order, is delayed, the Contractor shall pay to

the Purchaser, as liquidated damages, ½% (half of one percent) of the

Contract Price of the entire Work specified in the Agreement per full

week of delay in Final Acceptance.

The Contractor, however, shall not be liable under this Sub-article 11.2

to pay liquidated damages as aforesaid exceeding 10% (ten percent) of

the Contract Price specified in the Agreement.

11.3 Nothing in Sub-articles 11.1 and 11.2 shall relieve the Contractor of its

obligation to install the System, or relieve it of its obligation to cause

the System to operate as required by the date(s) set forth in the

Contract or as agreed between the parties. The provisions of this

Article shall in no way constitute an abrogation of the Purchaser's legal

rights and remedies in the event of a failure or delay in delivery and/or

Final Acceptance - in each case, in excess of the period for which

liquidated damages are payable.

11.4 Subject to the aforesaid, and provided that delivery is actually achieved

within 10 weeks of the scheduled date therefor and/or Final Acceptance

Page 15: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 12 -

within 20 weeks of the scheduled date therefor, payment of liquidated

damages under Sub-article 11.1 and/or 11.2 shall constitute the sole

remedy and the Contractor's exclusive liability for it's delay in

completion of delivery and/or Final Acceptance, as the case may be.

11.5 In the event that the Contractor fails to make payment of the liquidated

damages referred to in Sub-articles 11.1 and/or 11.2 above within sixty

(60) days after the date of written demand therefor by the Purchaser,

the Contractor shall be deemed to be in breach of the Contract.

12. RESERVED

13. DELIVERY

13.1 Equipment, software and other deliverables supplied shall be delivered

to the Purchaser, Delivered Duty Paid (DDP) except for Israeli Value

Added Tax to the Purchaser's designated site(s) in accordance with the

provisions of Annexure “R”.

13.2 In the event Work or any part thereof has been furnished which is not

in substantial conformance with Annexure "B", and where the

Purchaser has notified the Contractor of such non conformance, then

delivery shall be deemed not to have been effected in respect of such

non conforming Work or part thereof.

14. TITLE

14.1 Equipment.

Title to the Equipment free and clear of all liens and encumbrances

shall pass to the Purchaser upon delivery DDP to Purchaser's

designated site(s) subject to the provisions of Article 13.2 above.

14.2 Software/Licenses

14.2.1 The Contractor shall obtain for the Purchaser and/or provide to

the Purchaser perpetual software and firmware licenses for all

the Contractor and third party software supplied under this

Contract, such software having been supplied on a fully paid-up

basis. These licenses shall survive adaptation of the Work.

14.2.2 It is agreed that Purchaser may use the software at no increased

charge on all and any computer models and operating systems

owned and/or operated by Purchaser at any site where

Purchaser conducts its operations and business, and to make

such copies as it deems necessary for back-up purposes. For the

removal of doubt, it is expressly stated that Purchaser may not

make any of the software available to any third parties (except

Page 16: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 13 -

to contractors performing services for Purchaser in connection

with Purchaser's business and operations).

14.2.3 There shall be no restrictions on Purchaser's rights to use,

modify, expand, add to, or in any way adapt the software or any

portion of it to best suit Purchaser's needs as determined by

Purchaser at any time following the end of the warranty period.

If Purchaser elects to make changes to the Work during the

warranty period, the effect on the warranty shall be mutually

agreed.

14.2.4 The Purchaser shall have the right under the licenses to add

hardware or software from vendors (whether or not they have

previously supplied hardware or software for the Project) or to

interface the hardware and software supplied with other systems

operated by the Purchaser. In such event the Purchaser shall

provide the vendors with documentation of the system as

required. Purchaser has the further right to use the Work, with

or without additions, for purposes not contemplated at the date

of execution of the Contract and not described herein.

15. RISK OF LOSS OR DAMAGE

15.1 Prior to Installation.

Until delivered to Purchaser at the designated delivery place as

provided in Article 13 above, the Equipment (and software) shall be at

Contractor's risk, and if any loss of or damage to the Equipment (and

software) occurs prior to such delivery, Contractor shall, without cost

to Purchaser, promptly make all repairs or replacements necessary to

place the Work in the condition required by the Contract.

15.2 During commencement of and during Installation of the software

systems and associated hardware, Start-Up and testing.

Until the completion of Final Acceptance, the Contractor shall bear

responsibility for loss or damage to the Equipment (and software)

during the installation of the software systems and associated hardware,

Start-Up and testing process. However, the Contractor shall not bear

responsibility for risk of loss or damage caused by an event of force

majeure occurring on Purchaser's Site(s).

15.3 Where the Contractor is responsible, the Contractor shall with due

diligence and dispatch replace the Work lost or damaged at its sole

expense.

15.4 At the request of Purchaser, the Contractor shall, at the expense of

Purchaser, promptly make all repairs or replacements due to any loss of

Page 17: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 14 -

or damage to the Work for which the Contractor is not liable under the

terms of the Contract.

16. INSURANCE

The Contractor shall insure, on its, and/or its Subcontractors own account, their

liabilities under this Contract and any applicable law. Such insurance policies

shall be in force during the whole period of the Contract.

Without derogating from the generality of the aforesaid or from the

Contractor's obligations and those of its subcontractors under the Contract, the

Contractor shall provide and maintain insurance not less than that stipulated in

Annexure “L”.

17. RIGHT TO USE WORK REQUIRING CORRECTION

After the Work has been installed, if it, or any part thereof, or the process

performed thereby, should require correction, the Purchaser shall have the

right to use such Work or any part thereof until such time as it is convenient

for Purchaser at its discretion to remove the Work (or any part thereof) from

operation for correction. Such use shall not constitute Final Acceptance nor

shall it constitute a waiver of any of the Purchaser's rights under the Contract.

18. INTERFERENCE WITH OPERATION

18.1 Contractor shall not interfere with normal operation of Purchaser's

facilities or Equipment or the work of any other contractors or

subcontractors on the Work Site. The Contractor shall so notify

Purchaser in advance where it anticipates unavoidable interference.

Purchaser will in its discretion determine whether such interference is

unavoidable and will, if required, establish the necessary conditions

under which the interference will be permitted. Purchaser shall have

final determination of priorities in case of conflicts with the operations

of other persons on the Work Site.

18.2 Contractor shall not operate any of Purchaser's Equipment or control

devices or those of any other contractor or subcontractor on Purchaser's

premises except at the request of the Purchaser and where such

operation has been conducted with the permission, in the presence of

and under the supervision of the Purchaser.

19. WORK SITE AND ACCESS

Access to the Work Sites shall be agreed between the parties. In the event of

any disagreement, the Site access specified by the Purchaser shall be

determinative. The Work Sites shall include the areas in which the Contractor

is entitled to store its Equipment and the materials required for the execution

Page 18: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 15 -

of the Work as well as those parts of Purchaser's facilities in which the

Equipment is located and other private property.

20. SAFETY

20.1 In the execution of the Work, the Contractor shall take all appropriate

measures for the care and safety of the Work and: (i) safeguard the

Work and everything connected therewith against any loss or damage

and (ii) take all necessary measures to prevent damage or injury to

person or property, insofar as such damage or injury is caused by the

Contractor, Subcontractor or its employees.

20.2 Without affecting the generality of the above, the Contractor shall

comply with the provisions of the Safety Appendix, Annexure “S” and

all instructions issued from time to time by the Purchaser or issued by

the competent authorities under the law or regulations in relation to the

safety of person or property on the Work Site and its surroundings. The

Contractor shall cooperate with the Purchaser in complying with all

mandatory safety measures, which in the Purchaser's opinion are

necessary.

20.3 The Contractor will be responsible for the safe execution of the Work

and the manner thereof and shall supply and maintain when and where

necessary all precautionary measures. No instruction or agreement of

the Purchaser shall relieve the Contractor of its obligations and

responsibility under this Article.

20.4 In the event that the Contractor fails to comply with the provisions of

this Article, the Purchaser shall be entitled to make such arrangements

at the expense of the Contractor and to deduct the costs thereof from

any sums due to the Contractor by the Purchaser.

20.5 The Contractor undertakes to accept the interpretation of the Purchaser

in regard to any law, regulation, order or instruction of the competent

authorities and/or the Purchaser in relation to work safety.

20.6 The Contractor shall be responsible for safeguarding and protecting the

software and Equipment for which it is responsible located at the Work

Site and in every case of damage thereto the Contractor shall at its own

expense, be obligated to make good the damage so caused.

21. ON-SITE SERVICES

21.1 On-Site Services for installation, Start-Up, warranty or repair as

detailed in Clause 3 of the Agreement (relating to the Basic Scope of

Work) and Follow-On Support Services (if any) as detailed in Clause 4

of the Agreement (relating to the options), shall be furnished by

Contractor on its account and are included in the Contract Price. Such

services shall be supplied within the periods prescribed in Annexure

Page 19: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 16 -

"C1", or if not so prescribed, then with reasonable dispatch and shall be

rendered in a competent and diligent manner and in accordance with

the Contract, accepted industry practice and any applicable

professional standards.

21.2 Work performed by Contractor on the Work Site shall be scheduled in

accordance with Purchaser's normal daytime working hours and shall

take into account holidays as observed by the Purchaser. Any

exceptions must be approved by the Purchaser.

21.3 Working hours and days: the working hours and working days of

Contractor's personnel on the Work Site shall not exceed 8 hours per

day, plus a 1 hour lunch break, 5 days per week, Sunday through

Thursday.

21.4 Purchaser shall be entitled to request the Contractor to replace any of

its personnel considered by the Purchaser to be unsuitable for any

reasonable cause, and the transportation of such personnel from Israel

and of replacement personnel to Israel including other traveling and

living expenses en route and all baggage charges shall be at the

expense of the Contractor.

22. CONTRACTOR'S TEST EQUIPMENT

The cost of transportation of any test Equipment imported by the Contractor

for the purpose of the Work from factory to the Work Site in Israel and return

to factory and all other costs of importation and re-exportation are included in

the Contract Price.

23. FINAL ACCEPTANCE

23.1 Final Acceptance of the Work shall occur when the Contractor has

completed all its obligations (including, inter alia, all deliveries and

milestones, including the User Acceptance Tests and Operational

Acceptance Test and after Purchaser's receipt of all final

documentation reflecting all changes and corrections, including those

resulting from the Operational Acceptance Test and the User

Acceptance Tests).

23.2 Upon completion of Final Acceptance, the warranty for the software

systems and associated hardware detailed in Article 4 above shall

commence.

23.6 In the event the Final Acceptance is not achieved, Purchaser may

utilize any of its remedies under this Contract or by law.

23.7 If the results of the pertinent acceptance tests and all other

requirements are satisfied in accordance with the Contract, Purchaser

shall approve Final Acceptance and shall, upon Contractor's request in

Page 20: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 17 -

writing, issue a Certificate of Final Acceptance (Form 2 attached

hereto). Approval by Purchaser of Final Acceptance shall not be

unreasonably withheld.

23.8 Final Acceptance and payment does not constitute a waiver by

Purchaser of any rights with respect to Contractor's continuing

obligations under the Contract.

24. FOLLOW-ON SUPPORT

24.1 Contractor agrees to supply additional optional Follow-On Support

(maintenance) for the software systems as specified in Annexure "B"

after the expiration of the warranty period provided in Article 4.7.2

hereof and to make these services available to Purchaser for a period of

a year at a time up to a maximum of 3 years from the expiration of the

said warranty period, by giving notice of same to the Contractor by no

later than the date of expiration of said warranty period.

24.2 Contractor shall provide evidence of the availability of parts required

for the maintenance and extension of the system supplied to the

Contractor by others for the period stipulated. Contractor shall

undertake to implement the following actions:

24.2.1 Provide parts for a period of 5 years after the delivery of the last

meter or data concentrator.

24.2.2 Ensure transfer to it of all necessary maintenance and

manufacturing documentation including the Source Code if

Subcontractor ceases operations or is otherwise unable to meet

its support, maintenance and spare-part obligations.

24.2.3 Contractor shall further agree that if a Subcontractor can no

longer fulfill its maintenance and spare part obligations,

Contractor shall provide or secure for Purchaser the necessary

parts and services.

24.2.4 Contractor shall also agree that should Contractor cease

operations or otherwise be unable to fulfill its maintenance and

spare-part obligation, Contractor will transfer all necessary

maintenance and manufacturing documentation and required

software and firmware including Source Code for its own

software and the above-mentioned agreements with

Subcontractors, to Purchaser so that Purchaser can provide for

itself or secure from a third party the necessary maintenance

services and spare parts.

25. FORCE MAJEURE

Page 21: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 18 -

25.1 “Force Majeure” shall mean an event or circumstances beyond the

control of the parties, which:

25.1.1 could not have been prevented or avoided by said party by

reasonable foresight; and

25.1.2 occurred for reasons for which the parties were not responsible;

and

25.1.3 fundamentally changes the situation form that which existed at

the time of Signature of the Contract; and

25.1.4 makes it impossible for a party to perform any of its obligations

under the Contract.

Such event or circumstances shall include but shall not be limited to:

fire, flood or other natural disasters; acts or inactions of Governmental

authority; acts of terror or sabotage; war, invasion, act of foreign

enemy, whether war be declared or not, hostile action, civil war,

rebellion, piracy, civil strife, and/or general mobilization of military

reserves; strikes, labor sanctions and/or industrial disputes. For the

removal of doubt, lack of financial resources shall not constitute Force

Majeure.

25.2 Neither party affected by a Force Majeure shall be responsible to the

other for loss or damage due to such Force Majeure.

25.3 Upon becoming aware of the occurrence of any Force Majeure, the

party affected shall notify the other in writing by the fastest means

possible but not later than seven (7) days after becoming aware of the

Force Majeure, and the parties shall promptly thereafter consult with

one another for the purpose of finding a solution to the difficulties in

performing the Contract due to said Force Majeure.

25.4 Any delays resulting from any Force Majeure shall extend performance

time of that part of the Work so affected by the period of such delay, or

such other appropriate period as the Parties may agree upon in writing,

taking into consideration remobilization and other appropriate

arrangements.

25.5 For avoidance of doubt, the parties agree that:

25.5.1 security conditions in Israel similar to those existing at the time

of the Signature of the Contract shall not give rise to Force

Majeure relief;

25.5.2 the Contractor is entitled to a Force Major relief with respect to

any portion of the On Site Services, and to evacuate Israel at its

own cost and responsibility, in the event the government of

Contractor’s country and/or the government of the Contractor’s

Page 22: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 19 -

relevant Non Israeli subcontractor has (after Signature of the

Contract) actually issued an order or recommendation to its

non-Israeli nationals to immediately evacuate Israel;

25.6 Notwithstanding the provisions of Sub-article 25.2 above, provided

that the Contractor has exerted reasonable efforts to mitigate the

impacts of the Force Majeure, the Contractor shall be compensated for

extra costs and expenses only for Force Majeure events affecting the

whole Country of Israel and/or the Site, to the extent that:

25.6.1 Equipment cannot be delivered as per agreed upon

delivery terms and must be stored prior to delivery;

and/or

25.6.2 Bank Guarantees provided by the Contractor should

be extended as detailed in Sub-article 29 below;

and/or

25.6.3 On Site Services are interrupted.

25.7 If due to Force Majeure it shall become impossible to perform the

Contract in whole or a substantial part thereof for a period in excess of

270 days in the aggregate, this Contract may be cancelled by either

party.

25.8 In the event of notice of cancellation of the Contract under Sub-article

25.7 above, or other material disagreements regarding the provisions of

this Article 25, the parties shall immediately consult with one another

for the purpose of agreeing upon the basis for settlement of respective

claims and obligations and shall try to reach an amicable agreement

between the parties, failing which the matter shall be subject to the

provisions of Article 38 below

26. COMMERCIAL/VAT INVOICES

26.1 General

26.1.1 The Contractor shall submit its invoices to the Purchaser for

payment in two (2) original copies addressed to:

The Purchasing Division, The Israel Electric Corporation Ltd.

3rd Floor, Head Office, 1 Netiv Ha'Or Str., South Haifa,

3508510 Israel,

Attention: Mr. Shlomo Zoashnin – Accounting Department

email address: [email protected].

26.1.2 Each invoice shall specify:

the date of the invoice,

the Contractor's reference number and invoice number

Page 23: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 20 -

the Purchaser's Order number

and shall include a signed and witnessed statement by the

Contractor as follows:

"We hereby certify that this invoice is correct and true in all

respects and contains a true and full statement of the cost of the

goods and all charges thereon.

We further certify that, to the best of our knowledge, payment

in respect of this invoice has not previously been made".

26.2 Contractor shall attach to its invoice the appropriate form required for

payment (Form 1 or Form 2 (as applicable), attached to this Annexure

“A”) signed by the Contractor and duly approved and countersigned by

the Purchaser;

26.3 The Contractor shall be entitled to submit the invoices for payment:

26.3.1 by no earlier than the date specified in the Table of Payment

Milestones, Annexure C1;

26.3.2 by no earlier than the actual completion of the Milestone

26.3.3 by no later than 30 days after the date of completion of the

Milestone.

26.3A Invoices of Israeli Subcontractors:

Israeli Subcontractors shall invoice the Contractor for any payments

due under the Contract. The invoice shall be issued in the name of the

Contractor in such currency as agreed between the Contractor and the

Israeli Subcontractor, without Israeli VAT and shall state that the

Equipment or Services provided by the Israeli Subcontractor are "FOR

THE ISRAEL ELECTRIC CORPORATION LTD." The

Contractor shall ensure that the Purchaser receives one original copy of

the invoice.

The Israeli Subcontractor shall issue a second original VAT invoice to

the Purchaser containing only the amount of VAT to be paid by the

Purchaser to the VAT Authorities. The Israeli Subcontractor shall

attach an original copy of the invoice sent to the Contractor (without

VAT) to this second invoice and shall send an original copy of the

second VAT invoice to the Contractor.

26.4 The Purchaser shall, after receipt of the invoices, approve the invoices

and in the event of any discrepancies or non-approval, the Purchaser

shall notify the Contractor in writing within forty-five (45) days of

receipt of the invoice and instruct the Contractor to correct the

discrepancy. Any delay in Purchaser's payment due to discrepancies in

Page 24: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 21 -

Contractor's invoices shall not be deemed to be a delay for which the

Purchaser is responsible.

27. PAYMENT

27.1 Method of Payment

27.1.1. Non Financed Contract

27.1.1.1 Unless otherwise agreed between the parties, payment of all

sums due under the Contract shall be effected by way of direct

payment to Contractor's designated bank account.

Payment of VAT to Contractor's Israeli Subcontractors for

Israeli content and/or Services shall be effected in NIS by

direct payment to the Contractor, by direct bank transfer to the

Contractor’s Israeli Subcontractor’s designated bank account.

27.1.1.2 All payments shall be conditioned upon Purchaser's receipt of

the Contract duly executed, the performance guarantee

required under Article 29 below and receipt of the necessary

insurance certificates as stated in Annexure “L”.

27.1.1.3 The Basic Contract Price shall be paid as follows:

(i) in respect of meters, DC’s, CT’s and associated

components and services detailed in Table 2 of Annexure

“C1”, payment shall be made against delivery/performance;

(ii) in respect of software systems and associated hardware

detailed in Table 3 of Annexure “C1” and in respect of Project

services detailed in Table 4 of Annexure “C1”, payment

milestones have been selected that clearly identify the actual

status of the portion of the Work completed rather than

anticipated project progress schedules and payments shall be

made upon satisfactory completion of milestones as set out in

the Table of Payment Milestones, Annexure "C1", duly

approved by the Purchaser by way of Form 1 or Form 2, as

applicable, except for payment for Milestone 5 which shall be

withheld by the Purchaser as retention and shall only be paid

to the Contractor upon satisfactory completion of the relevant

warranty period.

Purchaser will not be required to approve a milestone payment

until all preceding milestones have been approved.

27.1.1.4 The price for Options shall be paid as follows:

Page 25: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 22 -

(i) in respect of extended warranty as detailed in Table 5

of Annexure “C1”, payment shall be made quarterly in

advance upon commencement of each quarter of

extended warranty against receipt by Purchaser of a

down payment guarantee as specified in article 29

hereof.

(ii) In respect of Follow on Support (maintenance) for

software detailed in Table 5 of Annexure “C1”,

payment shall be made quarterly in arrears upon

satisfactory completion of the maintenance.

(iii) In respect of additional services for the software

systems specified in Table 5 of Annexure “C1”,

payment shall be made at the daily rates based on the

actual hours worked as recorded in Purchaser’s work

diary.

(iv) in respect of additional meters, CT’s, DC’s and

associated components detailed in Table 5 of

Annexure “C1”, payment shall be made against

delivery.

27.1.1.5 Reserved

27.1.1.6 Where a Change Order is issued, the Contract Price will be

changed as needed and the Milestone payments will be

adjusted by mutual agreement of Contractor and Purchaser.

27.1.2 Financed Contract

In case of financing, all sums eligible for financing duly paid by the

Purchaser to the Contractor as described in article 27.1.1, will be

reimbursed to the Purchaser through a Financing Institution.

27.2 Terms of Payment

For the basic scope of Work:

27.2.1 Payment for meters, DC’s and associated components and

services, detailed in Table 2 of Annexure “C1”, shall be made

on the 90th day after the 1st day of the month succeeding the

month in which equipment was delivered/service was

performed or the invoice was received, whichever is the later.

27.2.2 Payment for software systems and related hardware, detailed in

Table 3 of Annexure “C1” and for Project services, detailed in

Table 4 of Annexure “C1”, shall be made according to payment

milestones defined in the Table of Payment Milestones,

Annexure "C1" on the 90th day after the 1st day of the month

succeeding the month in which a milestone was achieved or the

Page 26: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 23 -

invoice was received, whichever is the later, after receipt of

invoices and documents attached (as detailed in Article 26

above) .

27.2.3 For the Options:

(i) Payment for optional extended warranty as specified in

article 4.(a)(i) of the Agreement shall be made on the 90th day

after the 1st day of the month succeeding the month in which

each quarter of extended warranty commences or in which the

invoice was received, whichever is the later.

(ii) Payment for optional Follow on Support as stated in article

4.(a)(ii) of the Agreement, satisfactorily performed shall be

made on the 90th day after the 1st day of the month

succeeding the month in which it becomes due quarterly in

arrears or in which the invoice was received, whichever is the

later.

(iii) Payment for optional additional services as stated in

article 4.(a)(iii) of the Agreement shall be made as specified in

article 27.2.1 above.

(iv) Payment for optional additional meters, CTs, DC’s and

associated components as stated in article 4.(a)(iv) of the

Agreement shall be made as specified in article 27.2.1 above.

27.4 Reserved

27.5 Deduction of Income Tax from Source

27.5.1 Consistent with the provisions of Subarticle 28.2 (Taxes and

Duties) detailed below, the Purchaser shall deduct corporate

income tax from source from the invoices of the Contractor

for services rendered, unless the Purchaser has received a

certificate of exemption (or partial exemption) in

accordance with the Israeli Income Tax Ordinance.

27.5.2 In the event the Contractor is a company or body registered

in a country which has a double taxation treaty with the

State of Israel and in the event income tax has been

deducted from source as above, then the Purchaser shall

furnish the Contractor with the certification as to amount

deducted for purpose of Contractor’s use in avoiding double

taxation.

27.6 Set-off

Page 27: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 24 -

The Purchaser shall have the right to set-off from any sum under the

Contract due to the Contractor, such sum(s) as may be due and payable

to the Purchaser from the Contractor.

27.7 Certificates

No certificates given or payments made shall be considered as

conclusive evidence of the performance of the Contract, either wholly

or in part, nor shall any certificates or payment be construed as

acceptable of any defective or non-conforming part of the Work.

Acceptance by Contractor of final payment of the Contract Price shall

constitute a waiver by the Contractor of all claims against Purchaser.

28. TAXES AND DUTIES

28.1 Non Israeli Taxes and Duties.

The Contractor shall be responsible for all taxes, imposts or other

compulsory payments of Non-Israeli origin imposed on or in

connection with the Work.

28.2 Israeli Taxes and Duties.

Notwithstanding the use of the term "Delivered Duty Paid" in this

Contract, the Purchaser shall be responsible for all Israeli taxes, duties

or other compulsory payments, levies and customs, imposed by the

Israeli governmental authorities in connection with the Work,

excluding:

28.2.1 Contractor's Corporate and Service Personnel's Income Tax;

28.2.2 Income Tax due on the Israeli content;

which shall be Contractor’s sole responsibility.

28A. Anti Dumping Levy

28A.1 The Contractor declares that the prices specified in the Contract do not

constitute dumping according to Israeli Law.

28A.2 The Purchaser shall notify the Contractor promptly of any allegation of

dumping or of subsidy and the institution of proceedings or action

against it. The Contractor shall supply the Purchaser with all such

information and assistance to enable it to defend the suit.

28A.3 In the event the competent Israeli authorities determine that the prices

stipulated in the Contract constitute dumping prices and/or that the

prices are subsidized contrary to Israeli Law, and the Purchaser is

Page 28: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 25 -

required, as a result thereof, to pay any anti dumping or subsidy duty or

any other assessment, levy, penalty, fine, obligation or payment, and

incur costs, expenses or fees (including legal fees), the Contractor shall

indemnify and hold the Purchaser harmless for such costs as shall be

imposed on or suffered by the Purchaser.

29. GUARANTEES

29.1. To secure the due, timely and complete performance by the

Contractor of its obligations under the Contract, and as a condition

precedent to Purchaser's making any payment to the Contractor

under Article 27 above, the Contractor shall, at its expense, within

thirty (30) days of the execution of the Contract, provide the

Purchaser with guarantees (one for the meters and associated

components and services and one for the software systems and

associated components and services) for the due performance of the

Contract (“Performance Guarantees”) in the form of a standby letter

of credit (“SBLC”) as per Annexure "E1", if provided by non-Israeli

banks, or in the form of an unconditional on-demand bank guarantee

if provided by a bank in Israel or an approved insurance company in

Israel as per Annexure "E2".

29.2 The Purchaser may draw on the Performance Guarantee/s in the

event the Contractor fails to remedy a breach of Contract or fails to

take such steps as are satisfactory to the Purchaser in order to

remedy same, after having been given ten (10) days prior written

notice of intent to draw on the guarantee/s.

29.3 The guarantees shall be:

29.3.1 given and maintained until their expiration by:

29.3.1.1 a First Class Non-Israeli Bank, as specified

in Annexure “Y” (as proposed by the

Contractor and approved by the Purchaser);

or

29.3.1.2 an Israeli Bank holding a banking license

received pursuant to the Banking Law

(Licensing) 5741-1981, confirmed by the

Purchaser; or

29.3.1.3 an Israeli insurance company as specified in

Annexure “Y” that has received a valid

license to issue guarantees from the Ministry

of Finance and which is approved by

Purchaser;

Page 29: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 26 -

Guarantees provided by a bank outside of Israel shall be

advised through an Israeli bank, also to be approved by

the Purchaser;

29.3.2 established with immediate effect, in an initial amount

equal to ten percent (10%) - not inclusive of VAT - of

the “Basic Contract Value” for one year, (being the

Basic Contract Value divided by the number of years in

the Basic Frame Contract Period) all as defined in

Annexure “Z”, in respect of the meters and associated

components and services plus the price of any options

exercised and ten percent (10%) - not inclusive of VAT -

of the contract value in respect of the software systems

and associated components and services plus the price of

any options exercised.

29.3.3 maintained in full force and effect until sixty (60) days

after the expiration of the relevant warranty period as

prescribed in Article 4.7. above and any extension

thereof in accordance with the Contract. In respect of the

meters and associated components and services, upon

receipt of the last delivery, the existing guarantee will be

exchanged/updated by a guarantee equivalent to 5% of

the value of the contract actually executed. 29.3.4 amended from time to time, but at least on a semi-annual

basis, to reflect the adjusted Contract Price due to the

issue of Change Orders, if any.

29.4 In addition, where the Purchaser is required by the terms of the

Contract to make payments prior to delivery/performance, such

payments shall be secured by a standby letter of credit in the form of

Annexure “F1” or “F2” attached hereto, as follows:

i) issued, or established by the Contractor, on its account, at a first

class bank, located in the Contractor’s country and advised

through an Israeli bank, both banks to be approved by

Purchaser and in accordance with the other provisions of article

29.3.1 above;

ii) issued or established against the receipt of the down payment,

in an amount, which is not less than that being drawn; Said

guarantee shall be amended from time to time to reflect the

adjusted Contract price, due to the issuance of Change Orders,

if any;

iii) valid until 60 days after scheduled or actual performance of the

last item of the service, whichever is the later (to be extended

upon the occurrence of any event of Force Majeure, or due to

Page 30: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 27 -

any delay on account of the Contractor, or as a result of any

delay agreed to between the parties).

b) The Purchaser may draw on the down payment guarantee, in

the event that the Contractor fails to remedy a breach of

Contract, or fails to take such steps as are satisfactory to

Purchaser in order to remedy the same, after having been given

ten (10) days prior written notice of intent to draw on the

guarantee.

29.5 Any extension of guarantees required under this Article shall be made

at least ninety (90) days prior to the expiration of the then current

validity date. Any failure to extend the guarantees as aforesaid by no

later than sixty (60) days prior to such date shall constitute a breach of

this Article and the Purchaser shall be entitled to draw on the

guarantees in accordance with their terms.

29.6 Should any event of Force Majeure (as defined in Article 25

aforementioned) occur, the Contractor undertakes to extend the validity

of the guarantees from time to time by the period(s) for which the

Force Majeure subsisted and/or continues to subsist.

29.7 The costs of extending a guarantee shall be borne by the Contractor,

unless the Purchaser is obliged by the terms of the Contract to pay or

reimburse such costs to the Contractor. In the event of Force Majeure,

the costs of extension shall be borne by that Party which wishes to

claim such Force Majeure relief.

29.8 The Purchaser's right to draw on the guarantees given under this

Article may be exercised more than once and shall be in addition to

and not in derogation of the exercise by the Purchaser of any of its

other rights and remedies.

29.8 The Contractor shall, if required by Purchaser, supply a Parent

Company Guarantee in the form of Annexure "G" within thirty (30)

days of the execution of the Contract.

30. PERMITS VISAS AND LICENSES

30.1 The Contractor shall be responsible for obtaining on its account all

import, export and other permits/licenses required for the shipment,

delivery, installation and operation of the System and entry and work

permits (Visas) for Contractor's Non-Israeli personnel working in Israel

(and any renewals). The Contractor, on its account, undertakes as a

fundamental condition of the Contract to obtain all permits/licenses and

Type and other approvals required by the Israeli Ministry of

Communications, the Ministry of Environmental Protection, other

Page 31: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 28 -

governmental ministries and/or local authorities, including any

renewals.

30.2 With regard to permits/ licenses for the System or parts thereof to be

obtained from the Israeli Ministry of Communications. The Contractor

undertakes to obtain the required permits/licenses within 40 days of the

signature of the Contract; failing which the Contractor undertakes to

exchange the Equipment with other equipment for which the required

permits/licenses have been received at no additional cost to the

Purchaser.

31. ASSIGNMENT AND SUBCONTRACT

31.1 Assignment

31.1.1 General

Neither party may assign the Contract or all or any of its rights

thereunder without first obtaining the other party's written

approval, which shall not be unreasonably withheld. Approval

may be conditioned upon terms, which if not met, shall render

any approval given null and void.

31.1.2 Assignment by Contractor

In the event the Contractor undergoes corporate or other

reorganization, whereby control therein passes to another entity,

e.g. purchase by another entity, formation of a joint venture or

where there is a change of corporate name, the Contractor shall

ensure that:

31.1.2.1 the new entity assumes all the obligations of the

Contractor under the Contract;

31.1.2.2 all guarantees issued under the Contract in the name

of the Contractor (and, where relevant, its parent

organizations) are reissued to the Purchaser in the

name of the new entity;

31.1.2.3 invoices are issued in the name of the new entity;

and

31.1.2.4 the Purchaser is supplied with all information as to

the reorganization, including:

31.1.2.4.1 the new entity (name, address, place of

registration, registration number,

shareholding etc.)

Page 32: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 29 -

31.1.2.4.2 its financial standing,

31.1.2.4.3 its ability to fulfill the Contractor’s

obligations under the Contract; and

31.1.2.4.1 the change of relevant personnel

involved in administration of the

Contract (including the change of

Israeli representatives).

In any event of such corporate reorganization, the Contractor (if

it is still in existence) and the new entity shall be jointly and

severally responsible for the performance of the Contractor’s

obligations under this Contract.

31.1.3 Assignment by Purchaser

Without derogating from the generality of the aforesaid, the

Purchaser shall be entitled to assign or otherwise transfer its

rights and obligations under the Contract, in the event of any

change to the Purchaser's corporate entity, which is required

under any law, including under the Electricity Sector Law,

1996, or the Government Companies Law, 1975, and/or

pursuant to any decision of the Government of the State of

Israel. The Purchaser shall notify the Contractor of any such

assignment or transfer in writing in advance.

31.2 Subcontract

31.2.1 The Contractor may not subcontract nor otherwise delegate

performance of any part of the Work, without first obtaining the

other party's written approval, which shall not be unreasonably

withheld. Approval may be conditioned upon terms, which if

not met, shall render any approval given null and void.

No subcontract with a value exceeding US$ 50,000.00 shall be

entered into unless included in the subcontractor list, Annexure

"J". Each listing in the subcontractor list must show the name

and address of the subcontractor together with a description of

the extent and character of the portion of the Work to be done

by that subcontractor. Any change in subcontractors or change

in the extent and character of any subcontract must be submitted

for approval and, if approved, will be reflected by a change in

the subcontractor list.

31.2.2 In the event of subcontract of parts of the Work by Contractor

to a subcontractor, the request for approval shall contain the

name and address for each proposed new subcontractor as well

as a description of the portion of the Works to be performed by

such subcontractor.

Page 33: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 30 -

31.2.3 Any of the subcontractors approved for a certain part of the

Work (whether as detailed in the Contract or upon special

request after its execution), may be awarded such part by the

Contractor provided that the Purchaser has been given written

notice thereof. Purchaser’s approval shall not relieve Contractor

from full responsibility for the due fulfillment of all obligations

under or pursuant to the Contract.

31.2.4 The Contractor acknowledges that it has the sole responsibility

for the performance of each subcontract.

31.2.5-6 Reserved

31.2.7 Contractor shall be responsible for the acts and omissions of all

subcontractors and of all persons employed by the

subcontractors. No approval of subcontractors by Purchaser

shall relieve the Contractor of any of the obligations of the

Contract, and Contractor shall remain responsible to Purchaser

as though no subcontract had been made.

31.2.8 If, for sufficient reason at any time during the progress of the

Work, Purchaser determines that any subcontractor is failing

to perform its portion of the Work in accordance with the

Contract, Purchaser, under the terms of Article 36 herein,

may notify Contractor that Contractor is to take immediate

steps to cancel that subcontract and to submit a new

subcontractor for approval. Any Work sublet by any

subcontractor shall also be subject to termination upon

written notification by Purchaser.

31.2.9 Contractor shall incorporate this Contract into all of its

subcontracts so that every subcontractor shall be bound by

the terms of the Contract as far as it is applicable to the

subcontractor's performance of the Work.

31.2.10 Notwithstanding the provisions of Sub-article 31.2.6 above,

the Contractor acknowledges that sole responsibility for the

performance of each and every subcontract remains

incumbent upon it. If in the opinion of the Purchaser,

reasonably exercised, the Subcontractor fails to perform the

Subcontract, and if after having been requested by the

Purchaser to take steps to enforce such Subcontract, the

Contractor fails so to do within a reasonable time of such

request, the Purchaser may, as Beneficiary, and on the

account of the Contractor, take such action against the

Subcontractor as it deems fit.

31.2.11 Notwithstanding the provisions of Sub-articles 31.2.3 and

31.2.7 above, should the Subcontractor make any claim

Page 34: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 31 -

against the Purchaser the Contractor undertakes to indemnify

the Purchaser for any sum, whether capital, costs, interest or

otherwise which the Purchaser may be called upon to pay on

the Contractor's behalf.

31.2.12 As the Contractor is the team leader of subcontractors each

of which possesses expertise in (a) particular field(s) of

Smart Meter systems, the Contractor shall ensure that:

The Purchaser shall, in the presence of or in co-

ordination with the Contractor, have access to the

individual subcontractor leading experts for matters of

consultation or for assistance in connection with the

Work;

Any change of subcontractors approved by the Purchaser

shall be done in consultation with the Purchaser and shall

be no less beneficial to the Purchaser than the

subcontractor who has been changed.

In the event the Purchaser wishes to purchase additional

meters, the Contractor undertakes to ensure that the

Purchaser shall have the unrestricted right to acquire

such additional meters independently.

32. INDEMNITY

The Contractor shall indemnify and hold the Purchaser harmless in respect of

any claims, losses, damages, costs and expenses including attorney's fees and

costs of defense arising or alleged to arise from (i) personal injury to or death

of any person whomsoever, and (ii) any damage to or loss of property or error

or defect in the Work, insofar as such injury, death, damage error or defect or

loss is due to any act, error, omission or default of the Contractor, its servants

or agents, or anyone directly or indirectly employed by it, or anyone whose

acts or any of them may be liable, regardless of whether or not it is caused or

alleged to have been caused in part by Purchaser, or another party, or arising

out of or in connection with the Work being performed by them.

33. LIMITATIONS OF LIABILITY

33.1 The Contractor shall not be liable to the Purchaser for any

consequential loss or indirect damage under this Contract.

33.2 Excluding Contractor’s liability to third parties which is not limited by

this Contact, the Contractor's maximum liability to the Purchaser under

this Contract shall be limited to the Contract Price defined in Clause 6

of the Agreement.

Page 35: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 32 -

34. PATENTS/COPYRIGHT

34.1 The Contractor warrants that no patent, copyright, registered design or

other intellectual property right will be infringed in the manufacture or

supply of the Work or in the use of or derivation of benefit from such

Work by the Purchaser.

34.2 Contractor shall, on its account, pay all royalties and license fees which

may be payable in respect of the Work or any part thereof.

34.3.1 Should an action for infringement be instituted or a claim in

respect thereof asserted, the Contractor shall at its own expense defend

all suits or proceedings instituted against Purchaser for the

infringement of any patent rights, copyright, or other intellectual

property right, provided that, Purchaser gives the Contractor

reasonable notice in writing of the institution of any such suit or

proceedings, permits it to defend them and gives it all such

information, assistance and authority as shall be necessary to enable it

to do so.

Contractor shall save Purchaser harmless against and shall pay all

awards of damages assessed and all costs of suit adjudged against

Purchaser in such suits or proceedings.

34.3.2 In case any part of the Work is held in any such suit to constitute

infringement and its use is enjoined, Contractor shall, within a

reasonable time and at its cost either:

34.3.2.1 secure for Purchaser the perpetual right to continue the

use of such part of the Work by procuring for Purchaser

a royalty-free license or such other free permission as

will enable Contractor to secure the suspension of any

injunction, or

34.3.2.2 replace such part of the Work with an adequate non-

infringing part or modify it so that it becomes non-

infringing without affecting the performance and other

qualities agreed upon.

34.3.3 Purchaser's rights and protection shall survive the Contract.

35. SUSPENSION

35.1 Purchaser may, at any time and at its sole option, suspend all or any

portions of the Work to be performed under this Contract by providing

ten calendar days written notice to the Contractor.

35.2 Upon receipt of any such notice, Contractor shall respond as follows:

Page 36: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 33 -

35.2.1 Immediately discontinue the Work on the date and to the

extent specified in the notice.

35.2.2 Place no further orders or subcontracts for materials,

services, or facilities with respect to the suspended portion of

the Work, other than to the extent required in the notice.

35.2.3 Promptly make every reasonable effort to obtain suspension,

upon terms satisfactory to the Purchaser, of all orders,

subcontracts, and rental agreements to the extent that they

relate to performance of the portion of the Work suspended

by the notice.

35.2.4 Continue to protect and maintain the portion of the Work

already completed, including the portion of the Work

suspended hereunder, unless otherwise specifically stated in

the notice.

35.2.5 Continue to perform Contractor's obligations for the portions

of the Work not suspended.

35.3 As full compensation for such suspension, Contractor will be

reimbursed for the following costs, reasonably incurred, without

duplication of any item, to the extent that such costs directly result

from such suspension of Work:

35.3.1 A standby charge sufficient to compensate Contractor for

keeping (to the extent required in the notice) its organization

and Equipment committed to the Work on a standby status.

35.3.2 All reasonable costs associated with demobilization of

Contractor's facility, personnel and Equipment.

35.3.3 An equitable amount to reimburse the Contractor for the cost

of maintaining and protecting that portion of the Work upon

which activities have been suspended.

35.4 Upon receipt of notice to restart the suspended portion of the Work,

Contractor shall immediately resume performance on the suspended

portion of the Work to the extent required in the notice. Within 21

calendar days after receipt of notice to restart the suspended portion of

the Work, the Contractor shall submit a revised schedule for approval

by Purchaser. If, as a result of any suspension, the cost to Contractor of

subsequently performing the Work or the time required to do so is

changed, an equitable adjustment will be made. Any claim on the part

of Contractor for change in price or extension of time shall be made in

accordance with this Contract.

35.5 Suspension of the Work or any part thereof shall not exceed six months

unless otherwise agreed between the Parties.

Page 37: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 34 -

36. TERMINATION FOR DEFAULT

36.1 Contractor may be considered to be in “default of the Contract” should

the Contractor, at any time act as follows:

36.1.1 Withdraw or announce an intention to withdraw from the

marketplace for work of the type called for under the Contract.

36.1.2 Refuse or neglect to supply sufficient engineers, programmers,

and other skilled personnel; acceptable materials or proper

quantity; or Equipment necessary in all cases, to perform the

Work hereunder.

36.1.3 Fail in any material respect to perform any portion of the Work

hereunder with promptness, diligence, or in accordance with all

of the provisions set forth herein and, in particular, in

accordance with the provisions of Article 30 (Permits, Visas &

Licenses) above and the Mandatory Requirements detailed in

Annexure B.

36.1.4 Make application to Court under any bankruptcy legislation or

be declared bankrupt or insolvent or go into liquidation,

voluntary or otherwise, or be placed under administration,

receivership, trusteeship, judicial management, or compound

with or make any arrangement with its creditors, or take or

suffer any similar action in consequence of debt or should

control and administration of the Contractor be removed from

the persons normally responsible therefor.

36.2 Upon the occurrence of any of the aforesaid events, the Contractor

shall be deemed to be in material breach of this Contract. The

Purchaser shall thereupon notify the Contractor. Upon receipt of

written notice of default, Contractor shall, at its own expense, preserve

all materials, software, documentation, Equipment, and the plant and

undertake immediate steps to remedy such default.

36.3 Should Contractor fail to remedy such default within 21 calendar days

after receipt of such written notice of default, Purchaser may, in

writing, forthwith terminate the Contract in whole or in part, without

further notice or warning and without prejudice to any of Purchaser's

rights to any other relief or remedy, including the right to draw on the

guarantees provided under the Contract or to claim for such damages as

it may suffer by reason of the breach.

36.4 Notwithstanding the provisions of Article 23.6 (Final Acceptance) and

31.2.8 (Subcontract) above, upon receipt of written notice of

termination, Contractor shall, at its own expense and for that portion of

Page 38: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 35 -

the Work affected by any such termination, respond in the following

ways, as applicable:

36.4.1 Immediately discontinue the Work on the date and to the

extent specified in the notice.

36.4.2 Place no further orders or subcontracts for materials,

services, or facilities for the portion of the Work terminated.

36.4.3 Promptly terminate, upon terms satisfactory to Purchaser, all

orders, subcontracts, and rental agreements to the extent that

they relate to the performance of the portion of the Work

terminated. In terminating any such subcontracts, rental

agreements and orders, Purchaser shall not be liable with

respect to consequential, indirect losses or damages suffered

as a result of such termination of the Contract, including but

without limiting the generality of the foregoing, any sum

with respect to loss of profits or business opportunities,

under-utilization of manpower or facilities, occupancy of any

part of plant or facilities, etc.

36.4.4 Perform thereafter only such tasks as may be necessary to

preserve and protect the terminated portion of the Work in

progress and the materials and Equipment at Purchaser's sites

or in transit thereto.

36.4.5 Continue to fulfill Contractor's obligations with regard to the

Work not terminated.

36.4.6 Assist Purchaser in making an inventory of the Work at

Contractor's facility, en route to the Contractor's facility, en

route to the Purchaser, on order from its vendors, or parts of

the Work situated in any other place.

36.4.7 As directed by the Purchaser, assign to Purchaser any

subcontracts and rental agreements.

36.4.8 As directed by Purchaser, transfer to Purchaser possession

and title of hardware and appropriate licenses to software

and associated documentation.

36.5 In the event of such termination, Purchaser may complete the Work by

whatever method it deems expedient (including the hiring of another

contractor or contractors or Purchaser may itself provide any labor or

materials and perform any part of the Work). In such case, Contractor

shall not be entitled to receive any further payment until the Work is

completed. If the unpaid balance of Contractor's compensation

hereunder shall exceed the sum of the expense of completing the Work

plus compensation for Purchaser's additional managerial and

Page 39: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 36 -

administrative costs and such other costs and damages as Purchaser

may suffer, such excess shall be paid to Contractor.

36.6 If such expense, compensation, costs, and direct damages shall exceed

such unpaid balance, Contractor and its sureties, if any, shall be liable

for and shall pay the excess to Purchaser. Nothing in this clause shall

require Purchaser to proceed with the Work, if Purchaser determines

that abandoning the Work is in Purchaser's best interests. Failure of

Purchaser to exercise any of its rights hereunder shall not excuse

Contractor from compliance with the provisions of the Contract nor

prejudice the rights of Purchaser to recover damages for default.

37. TERMINATION FOR CONVENIENCE OF THE PURCHASER

37.1 The Purchaser shall have the right to terminate the Contract, in whole

or in part, for its convenience after giving the Contractor seven (7)

working days written notice.

37.2 In the event of such termination, the Purchaser shall pay the

Contractor, termination charges as follows:

37.2.1 with respect to all Equipment shipped and Work completed

prior to the effective date of termination:

37.2.1.1 the Contract Price for such portion thereof as is

separately priced in the Contract; and

37.2.1.2 the direct actual proven incurred cost, plus an

amount for reasonable profit which shall not

exceed ten percent (10%) of the said costs, for

such portion thereof as is not separately priced in

the Contract;

37.2.2 with respect to raw materials, work in process and finished

goods not shipped:

37.2.2.1 the direct actual proven cost of the progress in the

Work, based on the prices set forth in the Contract

(including material, labor and overhead directly

attributable to same, as certified by the auditors of

the Contractor) plus reasonable profit which shall

not exceed ten percent (10%) of the said cost - less

salvage value;

37.2.2.1 reasonable cancellation charges assessed against

the Contractor by its vendors and subcontractors

but which shall in no event deviate from the

principles as to assessment of termination charges

Page 40: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 37 -

as set out above and which shall not include any

profit of the Contractor with respect thereto.

37.3 In the event of such termination, the Contractor shall make all

reasonable efforts to minimize its costs and to use any materials or

equipment on hand as a result of such termination in the performance

of other contracts or otherwise to third parties, to the extent possible.

37.4 In presenting the charges claimed under this Article, the Contractor

shall reasonably substantiate the cost thereof. If, in the opinion of the

Contractor, the information necessary to substantiate the said costs is

proprietary, the financial records involved will be examined by the

Contractor's auditors or, at the option of the Purchaser, by such other

independent accounting firm as is acceptable to both parties.

37.5 It is expressly agreed between the parties that the Purchaser shall not

be required to pay to the Contractor, its vendors or subcontractors any

sum with respect to consequential, indirect losses or damages suffered

as a result of such termination of the Contract, including but without

limiting the generality of the foregoing, any sum with respect to loss of

profits or business opportunities, under-utilization of manpower or

facilities, occupancy of any part of plant or facilities, etc.

37.6 In the event that any amounts have been paid on account of the

Contract Price by the Purchaser and same exceed the amount of such

termination charges, such excess amount shall be refunded promptly to

the Purchaser. In the event that the amount of the termination charges

exceed the amount which has been paid on account of the Contract

Price by the Purchaser, then the Purchaser shall promptly pay the

Contractor the difference between the amount of such charges and the

amount previously paid.

38. SETTLEMENT OF DISPUTES

38.1 Both parties shall attempt to resolve their disputes pertaining to the

Contract amicably between themselves in the normal course of the

Contract administration. Should disputes not be resolved between the

parties in this manner, disputes shall be referred to senior management

for resolution.

38.2 Where the parties are still unable to resolve their disputes amicably,

either party may notify the other in writing of its intention to have the

dispute settled by arbitration and shall in the notification propose a

single neutral arbitrator.

38.3 In the event the Parties fail to agree upon the appointment of an

arbitrator within sixty (60) days of the date of the aforesaid

notification, either party may refer the appointment of the arbitrator to

Page 41: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 38 -

the Chairman of the Israel Bar Association who shall appoint the

arbitrator and such appointment shall be binding upon both parties.

38.4 The arbitration shall be conducted in English in accordance with the

Arbitration Law 5728-1968 of Israel, and shall be held as promptly as

possible at such place in Israel as may be mutually agreed upon

between the parties and at such time(s) as the arbitrator may determine.

This Article constitutes an arbitration agreement of the parties as

defined in the aforesaid Arbitration Law. The decision of the arbitrator

shall constitute an award.

38.5 Neither party may refuse to perform or delay the performance of any

obligation under this Contract unless the arbitrator has made an order

which allows it to do so. Subject to the foregoing and until the final

decision of the arbitrator, this Contract will continue to be fully

performed by both parties.

39. WAIVER

The agreement of either of the parties to waive any of the conditions contained

in the Contract or to deviate from them in any particular case shall not

constitute a precedent nor shall such waiver be construed in any other case.

The failure of either party to exercise any of its rights granted to it under this

Contract shall not be construed as a waiver thereof.

40. SECRECY AND SECURITY

40.1 Subject to the provisions stated hereunder, the Contractor undertakes

to maintain the secrecy of all information received by it in its capacity

as Contractor in executing the Work including, all plans or other

documents relating to the Work. The Contractor shall refrain from any

act, which is likely to endanger the secrecy of the information received

by him. No information, plan or other document shall be delivered by

the Contractor to any person whatsoever except such person authorized

by the Purchaser for the purpose of fulfilling their functions.

40.2 The Contractor undertakes to safeguard the plans and documents in its

possession in a secure place, access to which shall be restricted to such

persons authorized by the Contractor. Upon the completion of the

perusal of the documents by the Contractor, or its use thereof, or on the

completion of the Works, whichever event occurs first, the plans and

documents shall be returned by the Contractor to the Purchaser.

40.3 The Purchaser shall supply the Contractor with entry permits for its

workers to enable them to enter the Purchaser's premises, and the

Contractor shall be responsible for the renewal of such permits to the

extent necessary and shall return them to the Purchaser when such

employees leave the Work.

Page 42: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 39 -

40.4 The Contractor shall abide by any and all rules which the Purchaser

may have in effect or hereafter put into effect at the Work Site

pertaining to use of cameras and security procedures or requirements.

40.5 The Contractor shall fully comply with the provisions of Annexure K

(Security)

41. COMPLIANCE WITH LAWS, ORDINANCES, CODES AND

REGULATIONS

41.1 The Work performed by Contractor shall comply with the applicable

requirements of all laws, ordinances, codes and regulations of legally

constituted authorities having jurisdiction. Contractor shall obtain

certificates of compliance where required. If Contractor performs any

of the Work contrary to such laws, ordinances, codes and regulations,

Contractor shall bear any expense arising therefrom including the costs

to bring the Work into compliance.

41.2 Cost increases on account of any changes in the Specification/Contract,

due to changes in the Israeli Law, shall be treated as change orders and

shall be governed by Article 5 above, provided, however, that any such

cost increases, which, in the aggregate, exceed 20% of the Contract

Price, shall entitle the Purchaser to terminate the Contract. Such

termination shall not be considered a breach of contract.

41.3 In the event that there shall be, during the Contract period, any changes

in Israeli Laws, which shall increase the Contractor’s overall costs of

performance, then:

41.3.1 If the cost increase is up to 5% of the Contract Price, such cost

shall be borne by the Contractor;

41.3.2 If the cost increase is between 5% and 10%, then the Purchaser

shall bear the increase from 5% to 10% and any cost increase in

excess of 10% shall be borne equally by the Purchaser and the

Contractor.

41.4 Contractor shall fully comply with the provisions of Annexure “V”

throughout the duration of the Contract.

42. SEVERABILITY

Should one or more of the provisions contained in the Contract be determined

to be invalid, illegal, or unenforceable in any respect, the validity, legality and

enforceability of the remainder of the Contract shall be unaffected. The

affected provision shall be amended or interpreted, if possible, so as to correct

the deficiency and give effect to the intent of the parties.

Page 43: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 40 -

43. LAW GOVERNING CONTRACT

This Contract shall be governed by and construed in accordance with the laws

of Israel.

44. NOTICES

All notices hereunder shall be in writing and may be served upon Contractor

or its duly authorized representative or representatives at the address specified

in the Agreement or upon Purchaser addressed to The Israel Electric

Corporation Limited, Halechi Str, Bnei Brak, Israel, or to such other address

as may be shown in the contract documents and should be directed to the

attention of Mr. Miki Levy, Contract Manager, Marketing Division, National

Metering Unit. Either party may change its address for service of notices by

appropriate notice in accordance with the provisions hereof.

Page 44: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 41 -

FORM 1

CERTIFICATE OF MILESTONE ACHIEVEMENT

WE (insert name and address of Contractor ) ________________________________)

HEREBY CERTIFY THAT THE FOLLOWING ITEMS CONSTITUTING

MILESTONE (insert Milestone Number and Description ) HAVE BEEN

DULY COMPLETED IN FULL COMPLIANCE WITH ALL THE

REQUIREMENTS STATED IN CONTRACT (insert Contract No. )

Annexure “C1”

Seq. No.

Item Description Comments

_______________________________ ________________________________

CONTRACTOR DATE

______________________________ ___________________

PURCHASER’ s REPRESENTATIVE DATE

Page 45: Smart Meter System - IEC Meter System/Smart Meter Project-Annexure A- Gen...Smart Meter System March 2016 ... attributed to it in "Incoterms 2010" issued by the International Chamber

- 42 -

FORM 2

CERTIFICATE OF FINAL ACCEPTANCE

WE (insert name and address of Contractor ) HEREBY

CERTIFY THAT THE SYSTEM(S) HEREINAFTER LISTED, HAVE

SUCCESSFULLY PASSED FINAL ACCEPTANCE, IN ACCORDANCE WITH

APPROVED PROCEDURES, MEET ALL THE REQUIREMENTS STATED IN

CONTRACT (insert Contract No )

System ID

according to Annexure “C1”

System Description System Serial No. Acceptance Test

Report No.

_________________________ __________________

CONTRACTOR DATE

PURCHASER’S SIGNATURE HEREINBELOW CONSTITUTES ACCEPTANCE

OF SAID SYSTEM(S)

_________________________ __________________

PURCHASER DATE