+ All Categories
Home > Documents > Social Monitoring Report PRC: Lanzhou Sustainable Urban … · 2017. 3. 13. · Lanzhou Sustainable...

Social Monitoring Report PRC: Lanzhou Sustainable Urban … · 2017. 3. 13. · Lanzhou Sustainable...

Date post: 15-Mar-2021
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
13
Social Monitoring Report Semi-annual Report February 2017 PRC: Lanzhou Sustainable Urban Transport Project Prepared by Lanzhou Western Investment Consultation Co., Ltd. for the People’s Republic of China and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Transcript
Page 1: Social Monitoring Report PRC: Lanzhou Sustainable Urban … · 2017. 3. 13. · Lanzhou Sustainable Urban Transport Project Social Monitoring Report 1 1 Brief Introduction Asian Development

Social Monitoring Report

Semi-annual Report February 2017

PRC: Lanzhou Sustainable Urban Transport Project

Prepared by Lanzhou Western Investment Consultation Co., Ltd. for the People’s Republic of

China and the Asian Development Bank.

This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 2: Social Monitoring Report PRC: Lanzhou Sustainable Urban … · 2017. 3. 13. · Lanzhou Sustainable Urban Transport Project Social Monitoring Report 1 1 Brief Introduction Asian Development

ADB FINANCED PROJECT

PRC: Lanzhou Sustainable Urban Transport Project

External Resettlement Monitoring and

Evaluation Report

(Issue 9)

Lanzhou Western Investment Consultation Co., Ltd.

Lanzhou China

February 2017

Page 3: Social Monitoring Report PRC: Lanzhou Sustainable Urban … · 2017. 3. 13. · Lanzhou Sustainable Urban Transport Project Social Monitoring Report 1 1 Brief Introduction Asian Development

Lanzhou Sustainable Urban Transport Project Social Monitoring Report

1

1 Brief Introduction

Asian Development Bank (ADB) loaned Lanzhou Sustainable Urban Transport

is the first municipal project funded by ADB in Lanzhou. The Loan and Project

Agreements were signed on 30 March 2010, and became effective on 14 July 2010.

June 2012, ADB approved an extension of the loan closing date by 1 year to 30 June

2016; and in June 2016, ADB approved further extension of the loan closing date to

December 2017.

The project consists of four outputs: (i) construction and reconstruction of 33.8 km of

urban roads including BRT facilities and NMT lanes; (ii) advanced traffic management;

(iii) an advanced environmental monitoring system, including air quality sensors; and

(iv) capacity building. All the LAR are induced by the civil works for road construction,

so the monitoring and evaluation reports focus on the output 1, urban roads

construction including BRT facilities and NMT lanes.

Original scope of the Project covers (i) construction of 12 roads with a total length of

22km, (ii) improvement of 7 roads with a total length of 11km, (iii) construction of the

underground comprehensive pipe trench with a total length of nearly 16km, (iv)

construction of a Bus Rapid Transit BRT corridor with a total length of 13km, which

starts from Renshoushan Park in Anning District and ends at Lanzhou West Railway

Station, (v) the construction of dedicated public transport lane.

As of 31 December 2016, among the 19 roads construction which comprised of the

Output1, 7 reconstructed roads and 7 new roads are completed, 3 new roads (511#,

516#, 530#) are under construction, 2 new roads (510#, 574#) are cancelled from the

Project. Due to project delays, ADB, EA, IA and the PMO agreed to change the civil

work packages. Therefore, some section of 511#, 530#, 580#(south) are cancelled

from ADB’s scope of project financing, 516# refers to design change and BRT

corridors realignment. The BRT corridors and 4 new stops will follow road 516#,

Mogao Avenue, road 502#, which will not incur any LAR impacts. Although the road

sections are cancelled from the scope of ADB financing, it is still within the project

scope and hence will be monitored and reported in the reports. Schedules for the

commenced land acquisition, house demolition and construction for roads and

resettlement progress are shown in

Table 1-1.

In Figure 2, the blue lines mean the reconstructed roads, the green lines mean the

completed sections of the new constructed road, and the other colored lines mean the

unfinished or cancelled section of the new construction road. The detailed layout of

the roads is in

Figure 1, Figure 2.

Page 4: Social Monitoring Report PRC: Lanzhou Sustainable Urban … · 2017. 3. 13. · Lanzhou Sustainable Urban Transport Project Social Monitoring Report 1 1 Brief Introduction Asian Development

Lanzhou Sustainable Urban Transport Project Social Monitoring Report

2

Table 1-1 Project schedule and resettlement progress

No Road Commencemen

t Time for LAR

LAR

Status Commencement Time

for Road Construction Civil works Status Remark

New road

1 502 Nov. 2011 Completed Mar. 2012 Completed (Jul.2014)

2 511 Sep. 2010 Completed May.2011 Under construction Section Cancellation

3 516 Sep. 2010 Ongoing Aug. 2011 Under construction Design Change

4 530 Nov. 2011 Ongoing Sep. 2011 Under construction Oil pipeline relocation

5 574 Cancelled

6 580 (south of 514, north of 512) Sep. 2010 Completed Apr. 2011 Completed (Dec.2016) Section Cancellation

7 510 Cancelled

8 570 Mar. 2009 Completed Mar. 2010 Completed (Dec. 2010)

9 572 Jul. 2010 Completed Sep. 2010 Completed (Dec. 2011)

10 576 Jul. 2010 Completed Sep. 2010 Completed (Dec. 2011)

11 518 Mar. 2009 Completed Mar. 2010 Completed (Sep. 2011)

12 571(South) Nov. 2009 Completed Mar. 2010 Completed (Dec. 2011)

Reconstructed road

13 580 (between 514 and 512) No LAR Apr.2011 Completed (Sep. 2015)

14 571 (North) No LAR Oct.2010 Completed (Jun.2011)

15 514 No LAR Mar.2011 Completed (Dec. 2011)

16 514-1 No LAR Mar.2011 Completed (May. 2012)

17 514-2 No LAR Mar.2011 Completed (Dec. 2011)

18 578 Additional LAR Completed Sep. 2011 Completed (Dec. 2015)

19 112 No LAR Mar.2011 Completed (Dec. 2011)

Note:Road 574 dropped out and Road 510 postponed were approved by ADB. Road 511, 530, 580(south), 578 cancel from ADB’s financing can be seen in

MEMORANDUM OF UNDERSTANDING 2015.

The figure in No is affiliated to the roads as an index in the current and previous reports.

Page 5: Social Monitoring Report PRC: Lanzhou Sustainable Urban … · 2017. 3. 13. · Lanzhou Sustainable Urban Transport Project Social Monitoring Report 1 1 Brief Introduction Asian Development

Lanzhou Sustainable Urban Transport Project Social Monitoring Report

3

Figure 1 Original Layout and progress of the Road Component in 2015

Page 6: Social Monitoring Report PRC: Lanzhou Sustainable Urban … · 2017. 3. 13. · Lanzhou Sustainable Urban Transport Project Social Monitoring Report 1 1 Brief Introduction Asian Development

Lanzhou Sustainable Urban Transport Project Social Monitoring Report

4

Figure 2 Layout of the Road Component after Project Scope Change in 2016

Page 7: Social Monitoring Report PRC: Lanzhou Sustainable Urban … · 2017. 3. 13. · Lanzhou Sustainable Urban Transport Project Social Monitoring Report 1 1 Brief Introduction Asian Development

Lanzhou Sustainable Urban Transport Project Social Monitoring Report

5

2 Overview of external monitoring

The independent external monitoring and evaluation (M&E) on the resettlement of the Project is taken over by Lanzhou Western Investment Co., Ltd. This external M&E report confines to the Output 1, covers the institutional arrangements, progress of resettlement implementation, APs interviews, public participation, grievance redress, etc. The time limit of this round of M&E is December 31, 2016.

3 Monitoring Period

The external monitoring and evaluation agency submitted 1 report annually from 2010

to 2014 (Issue 1 to Issue 5), 2 reports for 2015 (Issue 6 and Issue 7), and 2 reports for

2016 (Issue 8 and Issue 9). The current report (Issue 9) is covered the monitoring

period from July to December, 2016.

4 Monitoring Findings

In this monitoring period, there is no significant achievements in the LAR including land acquisition, house demolition or agreement signature. Only the negotiations between the PMO and the APs are ongoing. Investigation on the sampling APs was conducted by the external M&E agency for feedback on their satisfaction, compensation, livelihood restoration, public participation, grievance redress, etc.

4.1 LAR and Civil Works Progress

a) Road 511-Compared to the last monitoring period, only partial wall of Lanzhou

Sanzhong Industrial and Technology Co. Ltd was demolished in October 2016.

The demolition didn’t impact the production of the company. All the LAR for the

road is completed including the road construction, but for the 100m road without

underground pipeline and pavement..

Figure 3 Status of demolished attachment and construction of Road 511

b) Road 516-There is no land acquisition or demolition in 2016. For the affected

enterprises, the PMO collaborated with the provincial government to negotiate

the relocation terms with Gansu Disable Solider Sanatorium and the family

dormitory; the other enterprises accepted the fact that it’s necessary to demolish

the building for road construction and looking for the relocation sites now. Usually,

the enterprises must find some candidate relocation sites in advance, and then

they can focus on the compensation negotiation, especially the terms on

transition cost which is related to the relocation site, and require the specific help

from the PMO and local government if need. As to Lanhai Yeast Powder Plant,

the owner agreed and received the compensation in October 2016, and promised

Page 8: Social Monitoring Report PRC: Lanzhou Sustainable Urban … · 2017. 3. 13. · Lanzhou Sustainable Urban Transport Project Social Monitoring Report 1 1 Brief Introduction Asian Development

Lanzhou Sustainable Urban Transport Project Social Monitoring Report

6

to vacate the building once they receive the demolition notice from the PMO. But

the structure have been rented to the Lanzhou Beichen Education Institution

since 2012. The education institution provides remedial courses for the artistic

candidates who prepare for the college entrance exam held on 31 May. For the

affected residential household, the resettlement implementing agency publicized

the policy and negotiates with the APs occasionally. The Aningpu Resettlement

Site will complete and welcome the residents before June 2017 and the APs in

Majiazhuang are willing to move in the resettlement apartments directly to avoid

transition. The progress of residential house demolition will not impact the civil

work of road construction. As of December 31, 2016, road 516 finished 700m

construction in the west section (Road 530 to Zhongbang Ave).

Figure 4 The Lanzhou Beichen Education Institution and residential house

Figure 5 The west section of Road 516 under construction

c) Road 530-The road construction only incurs residential house demolition in

Anningpu Sub-district and the APs hold the same attitudes with those APs in

Road 516. The other important issue is that there’re 3 oil pipes relocation must be

completed prior to the north section of road construction. The relocation of oil pipe

commenced on 6 October 2016, and is estimated to end in May 2017. The south

section of road 530 (Beibinhe W Road to Road 516) finished before 2015 and will

conduct labelling and greening after the north section is completed in December

2017.

Page 9: Social Monitoring Report PRC: Lanzhou Sustainable Urban … · 2017. 3. 13. · Lanzhou Sustainable Urban Transport Project Social Monitoring Report 1 1 Brief Introduction Asian Development

Lanzhou Sustainable Urban Transport Project Social Monitoring Report

7

Figure 6 The relocation of oil pipe in the north section of Road 530

Figure 7 The south section of Road 530

d) Road 580-With the rapid development of Anning District, the planned demolition

quantity in Kongjia’ai increased and the difficulty in LAR led to the cancellation of

south section (Beibinhe W Road to Jianning E Road) of road 580. The other

section (Jianing E Road to Road 511) of road 580 got completed in December

2016 and is incorporated in the municipal road network.

Figure 8 The completed section of Road 580

Page 10: Social Monitoring Report PRC: Lanzhou Sustainable Urban … · 2017. 3. 13. · Lanzhou Sustainable Urban Transport Project Social Monitoring Report 1 1 Brief Introduction Asian Development

Lanzhou Sustainable Urban Transport Project Social Monitoring Report

8

4.2 Resettlement sites

The Anningpu Resettlement Site owned by Anningpu Sub-district Government, is

designed to construct 1.09 million m2 building to relocate the APs induced by any

construction project in Anningpu. The site construction is divided into 2 stages by the

Zhongbang Ave, the first stage (east part) and the second stage (west part). The first

stage includes 8 buildings and expected to relocate 5779 persons of 1806 households

with a construction cost of 0.62 billion RMB. The layout and actual progress of the

resettlement site can be seen in Figure 9. The first stage of the resettlement site built

by Gansu No.7 Construction Group Co. Ltd was planned to implement from

November 2, 2011 to September 30, 2015. The APs induced by the ADB project will

move into 4 buildings (#1, #2, #5, #6) in the first stage resettlement site before June

2017. As of December 31, 2016, all the APs were allocated the units and got the keys

to decorate their apartments. Besides, the first stage incudes 24637 m2 commercial

shops to lease and is expected to bring dividend to the APs.

Figure 9 The design drawing and actual image of the Anningpu Resettlement Site

Figure 10 The construction status of the Anningpu Resettlement Site

4.3 Public Participation

The external monitoring and evaluation agency interviewed the APs including the

persons in transition, those relocated, the residents nearby and the cadres in the

relevant government departments. All the interviewees express their support to the

road construction and the transportation facilities improvement which will bring long

term benefits to their living and work. Regards to the APs in transition or those who

have not yet signed the agreement, they are fully aware of the compensation policy

and received the notice from the officials in resettlement implementing agency timely.

Page 11: Social Monitoring Report PRC: Lanzhou Sustainable Urban … · 2017. 3. 13. · Lanzhou Sustainable Urban Transport Project Social Monitoring Report 1 1 Brief Introduction Asian Development

Lanzhou Sustainable Urban Transport Project Social Monitoring Report

9

They wish the Aningpu Resettlement Site speed up the construction and equipped

with plentiful public services. For the APs who have relocated in the resettlement sites,

they’re satisfied with the current living status, except the APs in Liujiapu Resettlement

Site consider to improve the quality of water supply and heat supply in the high floors.

The PMO have inquired the Liujiapu Sub-district government on the situation, and

explained that the shortage of pressurization equipment slowed down the water

supply and heat supply (hot water cycle in the radiator system) to the residents in the

high floors. The government will increase the pressurization equipment in the mid

2017.

Figure 11 Interviews with the APs and officials

In terms of the GRM, the PMO did not receive any complaints in 2016. Also, due to a

very limited progress in LAR and construction. It’s found that another mechanism of

grievance and redress is popular and convenient for the public, which is the bulletin

boards system (BBS) in the website of Lanzhou Municipality Government. For the

rapidly development of internet technology and facilities, the population of internet

users, such as smartphone users increased among the urban and rural area.

Therefore, a credibility BBS on public participation, which is operated by a high-level

government become an important and popular service for the governance. There are

2 topics on the LAR issues posted in the bulletin boards during 2016.

Source Details

Page 12: Social Monitoring Report PRC: Lanzhou Sustainable Urban … · 2017. 3. 13. · Lanzhou Sustainable Urban Transport Project Social Monitoring Report 1 1 Brief Introduction Asian Development

Lanzhou Sustainable Urban Transport Project Social Monitoring Report

10

Source Details

Date: 2016-02-22

Post: What’s the planning on the

reconstruction and resettlement site in

Kongjia’ai sub-district?

Reply: After the investigation, the Kongjia’ai

resettlement site will construct 2 buildings with

40000m2 in 2016, and 19#, 20# buildings with

47000m2 are progressing and is expected to

allocate to the residents in 2017.

Respondent: Anning District Government,

2016-02-26

Date: 2016-11-25

Post: When does the Anningpu Resettlement

Site can allocate to the APs?

Reply: After the investigation, the Anningpu

resettlement site have completed the main civil

work now, but some relevant following

administrative procedures are in progress, and

then the apartments allocation will be

implemented in accordance with the

compensation policy.

Respondent: Anning District Government,

2016-11-30

5 Conclusions and Suggestions

There is no obvious LAR progress in 2016 but some good facts state that the LAR and

civil work will make a great progress in 2017. These facts include the increased inputs

and efforts from the local government, the nearing completion of Anningpu

Resettlement Site that APs can move in soon, the nonstop negotiations with the

enterprises narrow the disagreement and so on. The change in engineering design,

slow land acquisition and demolition caused delays in the civil works and it’s found

that the impediment factors are from the non-residential entities while the residential

APs are willing to be relocated.

The resettlement policies have been implemented strictly and fairly. The

compensation rates are higher than that in RP and the implementation is in

accordance with the policy framework. Furthermore, the compensation disbursed to

Page 13: Social Monitoring Report PRC: Lanzhou Sustainable Urban … · 2017. 3. 13. · Lanzhou Sustainable Urban Transport Project Social Monitoring Report 1 1 Brief Introduction Asian Development

Lanzhou Sustainable Urban Transport Project Social Monitoring Report

11

the APs conformed to the agreements by bank card.

The livelihood of the APs is well restored. All the affected areas are in the core region

of Anning District with great population, more job opportunities and booming

economic activities. The APs can easily convert to the off-farm work from agriculture

with their willingness. Besides, the resettlement sites are located in advantage region

with great commercial potential, the APs can benefit from the distributed dividend

from the shop lease. The improved road network including BRT will facilitate the APs

and reduce the transport cost to working and living areas. The relocation apartments

are of a good quality compared to the houses that were demolished.

The PMO must cooperate with the traffic and construction bureaus to manage the

partially finished section of the road efficiently to avoid any potential risk to road users

and residents. For example, no more driving practice without admission in the partially

finished road because of the unskilled driving that may incur accidents.


Recommended