Solan Production Operation MAT
Direction for Commissioning and Operation
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 2
REV ISSUE DATE
STATUS AMENDMENT DETAILS ORIGINATED
BY APPROVED
B1 31/05/2014 1st Draft Submitted for client review Genesis Premier
B2 05/06/2014 Final Client comments incorporated Genesis Premier
B3 09/07/2014 Update 1 Update in response to DECC
comments Genesis Premier
B4 19/11/2014 Update 2 Update to incorporate
commissioning and production operations
Genesis Premier
B5 27/11/2014 Update 3 Update to include assessment of
potential environmental impacts of the flotel
Genesis Premier
B6 27/01/2015 Update 4 Update to address Marine
Scotland comments Genesis Premier
B7 03/03/2015 Update 5
Update to address DECC comments and include Floatel
Victory and drill rig impact assessment
Genesis Premier
B8 10/03/2015 Update 6 Update to address DECC
comments Genesis Premier
B9 30/03/2015 Update 7 Update to include consent to
locate addition of the SAL marker buoy
Premier Premier
B10 07/04/2015 Update 8 Update to amend drill rig dates Genesis Premier
B11 15/04/2015 Update 9 Update to biocide information Genesis Premier
B12 01/05/2015 Update 10
Update to vessel information for hook-up and commissioning phase and update with new
chemical permit (CP/699) under PLA/90
Genesis Premier
B13 06/05/2015 Update 11 Update to include consent to locate addition of the Floatel
Victory Genesis Premier
B14 12/05/2015 Update 12 Update to W2W vessel
information in relation to consent to locate requirements
Premier Premier
B15 02/06/2015 Update 13 Update to amend vessel
information and include OPEP Annexes
Genesis Premier
B16 30/06/2015 Update 14 Update to include Flotel Regalia and update document for current
operations Genesis Premier
B17 29/09/2015 Update 15
Update to include consent to locate addition of the Aquaterra trash caps and to include Floatel
Superior
Genesis Premier
B18 30/09/2015 Update 16 Update to include Consent to
Location addition of Waverider Buoy
Premier Premier
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 3
B19 10/11/2015 Update 17 Update to production profiles and
commissioning operations for start-up/first oil
Genesis Premier
This document contains proprietary information belonging to Premier and must not be wholly or partially reproduced nor disclosed without prior written permission from Premier. The master copy of this document is held electronically within Premier’s Document Management System. If you are using a paper copy or a CD issue of this document, it is your responsibility to ensure it is the latest version.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 4
ACRONYMS
CH4 Methane
CMID Common Marine Inspection Documents
CO2 Carbon dioxide
CP Chemical Permit
CtL Consent to locate
DECC Department of Energy and Climate Change
DepCon Deposit consent
DHSV Down Hole Safety Valve
DP Dynamic Positioning
DSV Dive Support Vessel
DTI Department of Trade and Industry
EC European Commission
EIA Environmental Impact Assessment
EPS European Protected Species
ERRV Emergency Response and Rescue Vessel
ES Environmental Statement
ESD Emergency Shut Down
ESP Electric submersible pump
EU European Union
FSV Field Support Vessel
GHG Greenhouse gas
GOR Gas Oil Ratio
H2S Hydrogen Sulphide
HP High pressure
HSE Health, Safety And Environment Inspectorate
HSES Health, Safety, Environmental and Security
Hz Hertz
IBC Intermediate Bulk Container
ICES International Council for the Exploration of the Seas
JNCC Joint Nature Conservation Committee
kg Kilograms
kHz Kilohertz
km Kilometres
KW/m Kilowatts per metre
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 5
LAT Lowest Astronomical Tide
LP Low pressure
m Metres
m³ Cubic metres
m/s Metres per second
MAT Master Application Template
MCZ Marine Conservation Zones
mg/l Milligrams per litre
ml Millilitre
mm Millimeter
MMscfd Million standard cubic feet per day
MODU Mobile Offshore Drilling Unit
MPA Marine Protected Area
MRV Multi-Role Vessel
MW Mega watts
nm Nautical mile
NCMPA Nature Conservation Marine Protected Area
NMVOC Non Methane Volatile Organic Compounds
NPMI Not Permanently Manned Installation
NO Nitrogen monoxide
NO2 Nitrogen dioxide
NOx Nitrous oxides
OCNR Onshore Control Room
OCNS Offshore Chemical Notification Scheme
OCR Offshore Chemical Regulations
OLS Oil Offloading System
OPEP Oil Pollution Emergency Plan
OPOL Offshore Pollution Liability Association Limited
OPPC Oil Prevention Pollution and Control
OSCAR Oil Spill Contingency and Response
OSPAR Oslo and Paris Convention for the Protection of the Marine Environment in the North East Atlantic
OSRL Oil Spill Response Limited
OVI Offshore Vulnerability Index
PLA Pipeline Application
PRA Production Application
rms Root Mean Square
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 6
ROV Remote Operated Vehicle
SAC Special Area of Conservation
SAL Single Anchor Loading
SAT Subsidiary Application Template
SCANS Small Cetacean Abundance in the North Sea
scf/bbl Standard cubic feet per barrel
SCI Site of Community Importance
SEL Sound Exposure Level
SOST Subsea Oil Storage Tank
SOPEP Ship Oil Pollution Emergency Plan
SPA Special Protection Area
SPL Sound Pressure Level
Te Tonnes
UKCS United Kingdom Continental Shelf
VOC Volatile Organic Compounds
WoS West of Shetland
WoSP West of Shetland Pipeline
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 7
1 INTRODUCTION
1.1 Background
The Solan field is located in Block 205/26a in the West of Shetland (WoS) area at
approximately 3°58'10" W, 60°03'50" N. The field lies approximately 95 km from the
Scottish coast and 55 km from the UK/Faroes median line in water depths of
approximately 138 m lowest astronomical tide (LAT) (Figure 1-1).
Figure 1-1 Solan field development
Premier Oil UK Limited (hereafter referred to as Premier) are developing the field via two
production wells with the potential of two further producer wells in the future. Two water
injection wells will be used to maintain reservoir pressure from the start of production
whilst a third water injection well may be drilled in the future.
The facility comprises a jacket substructure, topsides facilities, a subsea oil storage tank
(SOST), and oil offloading system (OLS). The facility is designed to produce a peak flow
rate of 4,000 tonnes (Te) of oil, with a peak of up to 5,000 Te of total liquids.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 8
Both the production and injection wells will be tied back to the jacket and topside facilities
by flexible flowlines and rigid risers. The four leg jacket structure incorporates all
connections for the risers, caissons and J-tubes. The topsides facilities consist of primary
separation, gas treatment to fuel gas quality and power generation.
Oil will be produced via a piled SOST which will be used to store the crude, prior to export
via the OLS hose and then via a dynamically positioned (DP) shuttle tanker. The offloading
hose will be laid on the seabed with a pennant line and buoy to allow recovery to surface
when required. An overview of the field layout is shown in Figure 1-2.
Figure 1-2 Solan development project field layout
Solan will be developed by natural reservoir depletion assisted by water injection for
pressure support and artificial lift (electrical submersible pumps (ESP)) to improve
production rates. Injection water will be supplied by produced water, ballast water from the
SOST and filtered seawater. On completion, the Solan subsea wells and infrastructure will
be monitored, controlled and operated remotely from the shore via systems installed in the
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 9
platform. For at least the first 12 months Solan will be manned to complete commissioning
and manage plant stabilisation.
Produced oil from the Solan Field will be separated and metered in the facilities on the
platform and collected in the SOST prior to being transferred to tanker for export. The
produced gas will be used as fuel gas for onboard power generation. Any surplus gas will
be flared. Produced water will be cleaned-up and re-injected where possible. During
periods of Water injection downtime and during the initial commissioning of the plant post
start-up Ballast water will be cleaned and discharged to sea via the sea water caisson.
therefore there will be zero water discharge (Chrysaor, 2009).
The overall process flow diagram is shown in Figure 1-3.
Figure 1-3 Overall Process Flow Diagram
1.2 Purpose of Current Justification Document
This Justification Document supports a number of applications:
An EIA Direction under the Offshore Petroleum Production and Pipelines
(Assessment of Environmental Effects) Regulations 1999 (as amended);
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 10
A Chemical permit under the Offshore Chemicals Regulations 2002 (as
amended);
A Consent to Locate (CtL) under The Energy Act 2008, Part 4A.
An Oil Discharge Permit under the Offshore Petroleum Activities (Oil Pollution
Prevention and Control, OPPC) Regulations 2005 (as amended 2011).
The applications capture the commissioning works and ongoing production. Table 1-1
summarises the applications supported by this Justification Document.
The commissioning/tank first fill is described in Section 2 and production operations are
described in Section 3.
Table 1-1 Summary of Applications Supported by this Justification Document
Application Portal Reference Description
EIA Direction PRA/157 SP/215 Direction to commence production from new primary field
Chemical Permit PRA/157 CP/371 Includes chemical use and discharge during commissioning and production chemicals during operation
Consent to Locate PRA/157: CL/207 & CL/208
Floating accommodation units
Deployment of MODU Ocean Valiant within 500 m zone of Solan platform
SAL marker buoy within 500m zone (moved from CL/264)
Storage of Aquaterra trash caps (moved from PLA/90 ML/121)
Oil Discharge Permit PRA/157 OLP/198
For commissioning operations:
Discharge of ballast water For production operations:
Production of hydrocarbons
Produced water re-injection
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 11
The project schedule is summarised in Table 1-2.
Table 1-2 Indicative Schedule of Activities
Activity 2015 2016
2017 Q4 Q1 Q2
Dec Jan Feb Mar Apr May Jun
Minimum facilities, fi rst oil P1
First fill of SOST
P1 ESP and Solar gas turbines online
Final commissioning of full facilities
P2 and W2 availability
P2 ESPs
PW Treatment Facilities
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 12
2 HOOK-UP AND COMMISSIONING
2.1 Overview
Figure 2-1 shows the outstanding subsea commissioning operations (as of Nov 2015) for
the Solan development to be undertaken during subsea Phase 6. the current status (Feb
2015) of the Solan infrastructure. After the March 2015 subsea campaign this is expected
to change considerably once the campaign has finished.
Solan will operate on minimum facilities during initial start-up and commissioning. ESP
operation will not commence until plant stability is achieved to reduce stops and starts.
During this period the water injection system will not be available and ballast water which
is displaced by hydrocarbons will be discharged overboard.
Temporary ballast water filters have been installed on the platform and all ballast water will
be routed through these filters. The filter banks are absorption cartridge filters expected to
reduce hydrocarbons to 5mg/l. It is not expected that any hydrocarbons are present in the
fluids from the first fill of the tank. The SOST is currently filled with chemically treated
seawater. The discharge of this has been included on CP/371.
Post first fill of the tank the water injection system is planned to be commissioned. When
available all ballast water will be injected and discharge to sea will only occur if the system
is unavailable. The expected uptime post commissioning of the WI system is 95%.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 13
Figure 2-1 Outstanding commissioning operations (Nov 2015) for the Solan development to be undertaken during subsea Phase 6.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 14
2.2 Interference Test
Upon first oil start-up the water injection system will not be commissioned. The first fill of
oil can be contained if water injection is available however It is currently planned to
perform an interference test between the producer and injection wells to understand Solan
compartmentalisation and to make provision for sidetracks or new well injectors. In order
to perform this test the producers have to be flowed (natural flow without the ESP) and no
injection in order to understand the pressure decline in the injectors. This test is likely to
take between 36 and 48 hours to complete. Water injection can then be brought online
and all fluids injected into the reservoir through the injection wells.
Solan is committed to minimising discharges to the environment. P1 will be flowed
naturally at about 5,000 bpd for a period approximated of 14 days to test the
communication between the producers and the injectors prior to start-up of the well with
the ESP and start-up of water injection. The purpose of the above mentioned test is to
produce a pressure decline pulse at the injectors’ reservoir area in the order of 50 psig.
The Petroleum engineer will be closely monitoring the pressure decline. Any early sign of
effective communication between the producers and the injectors will halt the test which
means water injection can be started.
First fill volume is estimated to be approximated 300,000 bbls of treated water, any fluids
produced will displace the equal amount of fluid from the tank which will be discharged to
sea when water injection is not available.
In addition, as this is a first plant start-up, there will be plant stability issues to manage and
therefore it may be necessary to overboard full first fill volume of the tank.
Every effort will be made to minimise the discharge of water into the sea to minimise
environmental discharge and the pressure decline in the reservoir. All parties are aware of
this requirement which supports the reservoir management plan. After the first cargo off-
load there will be no discharge of production chemicals to sea. A commitment was made
in the Environmental Statement (ES) that production will be shut in when water injection is
not available.
2.3 Chemical Discharges
The fate of the chemicals left in the system after installation of the pipelines and tank will
either be:
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 15
displaced downhole;
discharged to sea from the topsides during the first fill of the SOST;
discharged to sea with the ballast water prior to WI commissioning; or
flowed to the tanker during the first cargo off-load.
These operations have been fully risk assessed as part of the chemical permit SAT
(PRA/157 CP/371). None of the chemicals proposed to be used in these operations were
found to present a risk to the environment; therefore, the overall effects of marine
discharges on the benthic communities and the marine environment are not expected to
be significant.
2.4 Drill Rig
Ongoing drilling operations require the Ocean Valiant Mobile Offshore Drilling Unit
(MODU) to be onsite at the Solan development from the 15th May 2015 for approximately
250 days to allow drilling of P2 and W2 wells with a possible re-spud of W2. The Ocean
Valiant is semi-submersible and will be anchored in place.
2.5 Vessel Use
This section summarises the ongoing vessel requirements associated with the hook-up
and commissioning phase. These include:
A standby Emergency Response and Rescue Vessel (ERRV)
A Dive Support Vessel (DSV)
The Flotel Regalia – accommodation vessel
The Floatel Superior – accommodation vessel to replace the Flotel Regalia
A second standby ERRV will also be on location, however this has been captured
previously in the Solan drilling permit applications. In addition the supply vessel has
already been captured in the Solan drilling permit applications.
Table 2-1 provides an estimate of the anticipated number of vessel and their estimated
fuel. The number of transit days provided allows for coming into port to accommodate
crew changes and the initial mobilisation and demobilisation days.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 16
Table 2-1 Anticipated vessel use during Solan hook up and commissioning phase 2015
Vessel type Duration
(days) Working fuel
consumption (Te/day)1 Total fuel use
(Te)
Walk to work vessel (in transit) 4 28 112
Walk to work vessel (working on DP)
56 18 1,008
Flotel Regalia (in transit) 4 40 160
Flotel Regalia (working on DP) 111 30 3330
Floatel Superior (in transit) 4 40 160
Floatel Superior (working on DP) 103 30 3,090
Standby ERRV (in transit)2 12 3.5 42
Standby ERRV (working)2 70 0.8 56
DSV (in transit) 4 22 88
DSV (working) 16 18 288
Total Fuel Use 8,334
1The Institute of Petroleum, 2000
2Only one standby ERRV captured here as other assessed in Solan drilling application.
The Flotel Regalia will replace the Siem Spearfish as an accommodation vessel. The
Regalia is anticipated to arrive at the Solan field at the earliest on the 1st August until
around the 20th November 2015. The vessel will be used as a walk to work vessel where
the vessel will be on DP to the east of the Solan platform within the 500 m zone and only
connect to the platform in order to transfer personnel and then disconnect and move away
during working hours. The vessel will be on DP at all times and will not use mooring lines
or anchors.
The Floatel Superior will then replace the Flotel Regalia as the accommodation vessel.
The Superior is anticipated to arrive at the Solan field on the 18th November 2015 and stay
until the end of February 2016. The Regalia will overlap with the Superior for
approximately 3 days during the changeover of the accommodation vessels. The vessel
will be used as a walk to work vessel where the vessel will be on DP to the east of the
Solan platform within the 500 m zone and only connect to the platform in order to transfer
personnel and then disconnect and move away during working hours. The vessel will be
on DP at all times and will not use mooring lines or anchors.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 17
3 PROCESS OPERATIONS DESCRIPTION AND PRODUCTION PROFILES
The facility has been designed as a Not Permanently Manned Installation (NPMI) which
can be operated remotely from the Onshore Control Room (ONCR) with the exception of
the hook-up and commissioning phase. However, the installation will always be capable of
operating as a manned platform. It will operate as a manned platform for at least the first
twelve months of production operations or until such time as approval to operate as a
NPMI is granted by the Department of Energy and Climate Change (DECC) / HSE.
The facility comprises of a SOST, a jacket substructure, topsides facilities, and oil
offloading system. The jacket substructure consists of a four leg design and all associated
bracing and stiffening necessary for the environment where it will be installed. It shall also
incorporate all connections for the risers, caissons and J-tubes, from the base of the jacket
to the top of the deck stab-in points. The topsides facilities will consist of primary
separation, gas treatment to fuel gas quality, all necessary Utilities, and Power
Generation. Power will be generated by dual-fuel turbines and a diesel generator. Initially
the turbines will be fuelled by fuel gas taken from associated gas with any excess gas
being flared. When the field becomes fuel-gas deficient the turbines will be fuelled by
diesel.
The SOST is located on the seabed. Oil will be exported via the oil offloading system to
shuttle tankers.
3.1 Process Description
Reservoir fluids (oil, gas and water) are brought from the seabed with the aid of ESPs
installed in each oil production well.
Production wells P1 and P2 are fitted with wellhead chokes to enable back-pressuring of
the production tubing to assist in prevention of asphaltenes deposition in the production
tubing. The individual flowlines from all production wells are fitted with choke valves at the
platform topsides, which will enable start-up flows to be controlled and will permit back-
pressuring of the flowlines to aid with asphaltenes control.
Reservoir fluids (oil, gas and water) are brought from the seabed to the topsides with the
aid of ESPs installed in each oil production well. The well fluids are directed to a first stage
high pressure (HP) separator and the associated HP gas is used to fuel the power
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 18
generation equipment. Liquids then pass to the second stage low pressure (LP) separator
where further LP gas is taken off and sent to the flare for disposal. From the first and
second stage separators, produced water is directed to the water injection pumps for
injection back into the reservoir. No sand is anticipated in the separators. If sand occurs it
will be manually removed by a recognised contracting company whilst production is offline
and will be disposed of onshore.
During normal fully commissioned operations, as oil enters the SOST, ballast water is
displaced from the bottom of the SOST and will be lifted onto the platform by caisson
pumps, and passed to the water injection system.
If the total of the produced water and ballast water rates falls short of the water injection
rate required for voidage replacement, the water injection volume is supplemented with
deoxygenated seawater taken from the seawater header. The total water injection stream
is then directed to the water injection pumps where it is raised to the required injection
pressure.
Oil will flow to and water to/from the topside facilities to the crude storage tank via rigid
risers on the jacket and rigid and flexible flowlines on the seabed. These will be connected
at the base of the jacket and be protected from dropped objects.
Oil export from the SOST will take place to a DP shuttle tanker. When not in use the
export line will be laid on the seabed, with a pennant line and buoy to allow recovery of the
line to surface.
Oil transfer uses the hydrostatic head of seawater with two displacement water lift pumps
located topsides delivering seawater to allow the oil transfer of up to 42,927 Te (300,000
bbl) a day.
3.1.1 Fuel Gas
Produced gas required for fuel gas will be removed from the process stream from the first
stage separator and will be routed to the fuel gas package, where it will be compressed for
the gas turbine power generators.
The fuel gas will not be stored. Premier will use the fuel gas as it is produced with a small
flare of surplus gas in the early life. The associated gas is a fixed amount for each barrel of
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 19
oil produced as there is no separate gas cap in Solan reservoir. The gas oil ratio (GOR) is
approximately 19.5 to 23 m3/m3 (110-130 scf/bbl) so as the oil production profile declines,
the available associated gas declines with it. As the platform becomes deficient in gas it
will progressively change over to diesel. Initially there was the prospect of importing gas
from the West of Shetland Pipeline (WoSP), this has been discounted due to technical and
cost implications and is no longer a viable option.
3.1.2 Flaring
The flare system will be designed to enable the safe disposal of gas under normal and
emergency operating conditions. The maximum amount of gas flared will be approximately
57 Mm3/d (2 MMscfd). The flare is located on the northwest corner to minimise the wind
effect.
3.1.3 Produced Water
Premier are committed to an operating philosophy of no production without re-injection.
Produced water will be re-injected, where possible, to the reservoir as it eliminates
discharge to the environment and provides the required pressure support to the reservoir.
Premier will submit an addendum to the Solan environmental statement WI/4031/2008 to
address changes to the operating philosophy concerning the discharge to sea of ballast
and produced water.
The produced water system is designed to remove residual dispersed oil, solids and
dissolved gas from the first and second stage separator produced water streams.
Produced water from the separators is directed to the intake of the water injection pumps
while produced oil is directed to the SOST.
As the oil enters the SOST, ballast water is displaced from the bottom of the SOST (Figure
3-1). This ballast water is filtered and deoxygenated and commingled with the separated
produced water at the intake of the injection pumps.
An application for an Oil Discharge permit has been submitted and approved (OLP/198)
for the re-injection of the produced water. A variation will be submitted to OLP/198 to cover
discharge of ballast and drains fluids.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 20
Figure 3-1 Diagram of SOST operation
3.1.4 Seawater Treatment and Injection System
Seawater dosed with hypochlorite is lifted directly using seawater lift pumps. In addition to
supplying the required make-up injection water for reservoir pressure support, the lift pump
also distributes seawater to the cooling water and low pressure seawater supply headers
and can supply fire water if required.
Seawater is coarse filtered prior to distribution to the cooling water supply and injection
water treatment system. A separate low pressure seawater supply is also provided to
distribute seawater to the following users:
Electrochlorination package for hypochlorite generation;
Vacuum pumps for pump seal water; and
Accommodation module.
Seawater for injection is initially comingled with ballast water and is then fine filtered and
deaerated. Oxygen scavenger is also injected at the deaerator to meet the final residual
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 21
oxygen specification. Biocide will also be injected into the system as and when required to
mitigate against microbiological growth.
Injection water from the deaerator is routed to the water injection holding drum, where it
mixes with produced water from the separators. Water is then injected into water injection
wells W1 and W2 via dedicated pumps and discharge manifolds.
3.1.5 Ballast Water
the philosophy is to inject all the ballast water into the reservoir via water injection wells
W1 and W2 due to possible hydrocarbon contamination.
During normal production, ballast water from the SOST is routed to the water injection
treatment system. Prior to mixing with produced water and injection via water injection
pumps, the ballast water is fine filtered and de-aerated. Ballast water will be used for
injection in preference to lifted seawater.
From first oil the ballast water will be discharged to sea to a maximum of the first fill of the
SOST, approx. 300,000 bbls. This is treated seawater and is not expected to contain any
hydrocarbons. To mitigate against discharge of hydrocarbons to sea, temporary ballast
water filters, F-4210A/B/C, have been installed on the Solan platform. These are
absorption cartridge filters designed to remove down to approx. 5mg/l oil in water
concentration.
Post first fill of the SOST the water injection system will be commissioned. Once
commissioned it is expected that all ballast water will be injected to support the Solan
reservoir and minimise environmental discharges. The Solan water injection system has
an expected uptime of approx. 95%. Should the water injection system become
unavailable ballast water will be discharged to sea via the sea water disposal caisson C-
4801. The seawater disposal caisson is fitted with an oil skim pump, P-4083, to allow oil
recovery which is routed back to the Open Drains tank and then back to the Closed Drains
tank.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 22
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 23
3.1.6 Water Injection
The water injection system has been designed to allow for injection of both seawater and
produced water as well as the ballast water which is displaced during the filling of the tank
with oil.
In early field life when oil rates are high the injection water requirements will mostly be met
by displaced ballast water with additional seawater as required. As oil production declines
and water cut rates increase the majority of water injected will be produced water.
During platform start-up operations it is envisaged that the water injection system will be
brought on line before field production commences, using only seawater. In this case
injection at a reduced rate of 204 m3/h (30,800 bpd) will be carried out until ballast and
produced water are available. Following start-up the injection rate can be increased to up
to 212 m3/h.
During normal production, once water injection is commissioned, ballast water will be
drawn from the oil storage system and used as a water injection supply in preference to
directly lifted seawater. The ballast water will be filtered in a temporary filtration system for
the first year of operation as described in section 3.1.5. There is no expectation of oil in the
ballast water but the filtration unit is in place to be used to ensure this is the case as best
practice and will be covered by operating procedures carried out by the Aker/Solan
offshore operations team. Water from the temporary filters will be routed downstream of
the fine filters. Ballast water is introduced to the water injection treatment system upstream
of fine filters, allowing ballast water to be subject to the same de-aeration process as lifted
seawater.
3.1.7 Tanker Offloading
Tanker offloading will take between 24 and 36 hours and is anticipated to occur
approximately every 7 to 10 days once full production is reached. To ensure safe
operations tanker offloading will only commence during daylight hours in the Solan field.
Due to unpredictable weather conditions and limited daylight hours, tanker-fill operations
may occur out-with daylight hours. There is a dedicated Multi-Role Vessel (MRV) which
will assist in tanker hook-up and act as a guard vessel during offloading operations. The
MRV is based at Solan 24/7 with a relief vessel with the same capabilities to perform
duties at Solan during the MRV crew change periods. The MRV also comes equipped with
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 24
oil spill detection equipment (which uses radar to pick up any oil on the sea surface) and
dispersant. The Solan platform also has a spill detection system which uses radar. This
extends outwith the tanker offloading station.
Should any issues arise, the tanker will initiate an Emergency Shutdown (ESD) level 1,
breaking the ‘green line’ between the tanker and the Solan platform. An ESD level 1 will
close the inboard coupler valve on the tanker and disengage the hose end valve which
will spring closed which takes around 24 seconds from disconnection. A break in the
‘green line’ will cause an ESD Level 2 Export Inter-trip on the platform which will stop the
seawater displacement pumps and close the 24” export valve on the SOST, thereby
stopping any further offloading operations. As a further barrier, the MRV can also close
the 16” valve on the Solan single anchor loading (SAL) system by using the dunking
transducer on board to remotely close this valve if required.
3.2 Production Profiles
The amended production profiles provided within the Solan ES Addendum (Premier Oil,
2014a) are shown in Table 3-1 Table 3-2 and Table 3-3. The impact assessment of the
production profile using peak rates is included in the original ES. The current production
profiles, which are average rather than peak rates, are less than those stated in the ES.
Therefore, the worst case impact has already been assessed and is in line with those
stated in the field development plan.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 25
Peak oil production is anticipated in 2016 2019 at a rate of 3,767 2,719 Te/d.
Table 3-1: Anticipated High Case Oil Production Profiles.
Year Average high case annual oil
production rate (Te/d)
2015 2,425 0
2016 3,767 1,473
2017 3,504 2,261
2018 2,192 2,428
2019 1,580 2,719
2020 1,332 1,644
2021 1,154 1,077
2022 899 784
2023 709 644
2024 602 528
2025 537 420
2026 489 389
2027 450 332
2028 418 305
2029 389 274
2030 361 234
2031 314 230
2032 272 206
2033 246 197
2034 228 183
2035 214 161
2036 202 162
2037 190 148
2038 180 144
2039 171 137
2040 163 130
2041 156 124
2042 149 118
2043 143 113
2044 137 109
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 26
Peak gas production is anticipated in 2016 2019 at a rate of 85.7 68.1 Mm3/d.
Table 3-2: Anticipated High Case Gas Production Profiles.
Year Average high case annual gas
production rate (Mm3/d)
2015 55.1 0
2016 85.7 36.9
2017 79.7 56.6
2018 54.3 60.8
2019 39.2 68.1
2020 33 41.2
2021 28.6 27
2022 22.3 19.7
2023 17.6 16.1
2024 14.9 13.2
2025 13.3 10.5
2026 12.1 9.7
2027 11.1 8.3
2028 10.4 7.6
2029 9.6 6.9
2030 8.9 5.9
2031 7.8 5.8
2032 6.8 5.2
2033 6.1 4.9
2034 5.7 4.6
2035 5.3 4
2036 5 4
2037 4.7 3.7
2038 4.5 3.6
2039 4.2 3.4
2040 4 3.3.3
2041 3.9 3.1
2042 3.7 3
2043 3.5 2.8
2044 3.4 2.7
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 27
Water production is anticipated to increase throughout field life and peak in 2044 at a rate
of 4,576 4,010 Te/d.
Table 3-3: Anticipated High Case Water Production Profiles.
Year Average high case annual water
production rate (Te/d)
2015 -
2016 100 0
2017 1,089 0
2018 2,269 220
2019 2,956 974
2020 3,235 2,454
2021 3,435 3,342
2022 3,721 3,177
2023 3,934 3,475
2024 4,054 3,590
2025 4,127 3,457
2026 4,181 3,730
2027 4,225 3,629
2028 4,261 3,813
2029 4,293 3,844
2030 4,325 3,643
2031 4,378 3,889
2032 4,424 3,755
2033 4,454 3,922
2034 4,474 3,935
2035 4,490 3,716
2036 4,504 3,957
2037 4,516 3,813
2038 4,528 3,974
2039 4,538 3,981
2040 4,547 3,988
2041 4,555 3,994
2042 4,563 4,000
2043 4,570 4,005
2044 4,576 4,010
3.3 Chemical Injection System and Flow Assurance
Production chemistry issues occur as a result of chemical and physical changes to the
wellstream fluid as it is transported from the reservoir through the processing system. In
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 28
general, chemicals are required to overcome or minimise a number of the production
chemistry problems that cannot be tackled in other ways and are typically associated with:
Fouling, such as deposition of scales, corrosion products, asphaltenes and
biofouling;
The physical properties of the fluid (foams, emulsions and viscous flow);
Corrosion; and
Environmental or commercial specifications (oily water discharge and the
presence of compounds of sulphur such as H2S).
3.3.1 Chemicals Injected into Production Wells
3.3.1.1 Asphaltene Inhibitor and Solvent Washes
There is a risk of asphaltene precipitation from the P1 and P2 wells. The uncontrolled
precipitation rates could be significant (up to 2 - 3 tonnes per 1,000 bbl of oil production
from P2), and consequently active control and remediation measures will be required.
Asphaltene inhibitor will be required from initial crude production whilst properties of the
crude are verified under operating and laboratory conditions to decide whether ongoing
injection is required.
Asphaltene deposition tends to alleviate with the onset of water production and in general
high water rates are predicted in the Solan development. Consequently asphaltene
inhibitor may only be required for the first few years of production; to be confirmed by
operational experience.
Ashpaltene solvent washes may be required for the flowlines (and for the well production
tubing if asphaltene deposition has occurred there) until the well water cuts are high
(inverted) which is anticipated after 2 to 3 years.
3.3.1.2 Demulsifier
To cater for the uncertainties in emulsion formation and behaviour, demulsifier injection
locations are provided at each wellhead and at the inlet to 1st stage and 2nd stage
separator.
3.3.1.3 Methanol
Methanol should not be required for any routine operation, subject to further detailed
investigation. However, the process design allows for methanol injection at the trees in the
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 29
case of any unforeseen problem such as hydrates, or for use in maintenance operations,
etc.
3.3.1.4 Scale Inhibitor and Scale Squeezes
Calcium carbonate scale formation, and a limited amount of barium sulphate scale, is
likely to occur in the producing wells throughout field life once water production
commences. In order to prevent scale formation, downhole injection of inhibitor will be
required as a proportion of water production. This philosophy assumes that even if an
initial scale inhibitor placement by scale squeeze is carried out prior to production then
continuous scale inhibitor injection may still be required.
In addition to continuous scale inhibition chemical injection, it may be necessary to
conduct reservoir squeezes, particularly if scale formation occurs across the production
well sand screens.
3.3.2 Chemicals Injected into the Oil Processing System
Production chemicals for oil processing including demulsifier, antifoam and asphaltene
inhibitor are required on either a continuous or intermittent basis for injection into the
topsides oil processing facilities.
Production chemicals are exported with the oil. Residual water based chemicals will
partition into the produced water during the separation phase and will be disposed of with
the produced water stream.
3.3.2.1 Diesel Biocide
Facility is provided to inject biocide into the diesel storage feed line and thereby into the
tanks. Diesel biociding will be carried out from the platform should this be required. Biocide
will be applied via a temporary chemical pump set up on the platform. The injection point
topsides is provided as a contingency.
The diesel biocide is a separate formulation from that required for water injection. Manual
dosing immediately prior to or during filling may be adequate unless remote diesel
bunkering is adopted, in which case a dedicated tank and feed line with remotely operated
valve and quantity control would be required.
3.3.2.2 Scale Inhibitor
Scale formation between early-life formation water production carried through into the tank
and the seawater used for displacement and ballast water is not expected to occur except
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 30
possibly for short periods before full water injection breakthrough occurs. Some calcium
carbonate scaling is also possible from displacement water that has been heated by
incoming warm oil. Residual scale inhibitor will be present in the produced water carry-
over from the 2nd stage separator and will provide protection, and any scale that may form
will be minor and would precipitate and fall to the base of the tank.
A contingency scale inhibitor injection point is provided upstream of the inlet separator
should dosing to the wells not be conducted, or to top up squeeze inhibitor returns to
provide sufficient scale control in the process train.
3.3.3 Water Injection Chemicals
Several production chemicals are utilised to optimise the performance of the seawater and
produced water treatment / injection systems. Antifoam, scale inhibitor, biocide and
oxygen scavenger are required either on a continuous or intermittent basis for injection
into the topside seawater treatment facilities.
3.3.3.1 Biocide
Sodium hypochlorite is the principal biocide required to inhibit marine growth within the
lifted seawater. Sodium hypochlorite will be generated in situ by electrochlorination. The
hypochlorite is dosed into the seawater lift pumps, which supplies seawater to the storage
tank displacement water, ballast water and seawater make-up for reinjection.
The SOST is constructed from carbon steel as is the internal pipework. There is a high risk
of corrosive bacteria forming, particularly biofilms, therefore biocidal protection is essential
to protect the integrity of the SOST and internal pipework. Organic biocide will be applied,
from start-up during the first fill of the SOST with oil and then during ongoing normal
operations, to the seawater displacement fluid during offloading of oil from the SOST. The
application of biocide will be reduced as required based on a robust monitoring and
sampling regime.
A shock dose of organic biocide for 2 - 3 hours will be applied every week to the water
injection holding drum once commissioned, to prevent sessile bacteria growth and
possible reservoir / well damage and souring. Organic biocide will also be applied to the
seawater caisson every 3 months and to the umbilical J-Tubes monthly until start up to
maintain the integrity of the pump functions on return to the platform.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 31
3.3.3.2 Scale Inhibitor
During initial injection of seawater there is a risk of scale formation at the injectors due to
the rise in injected water temperature and incompatibility of reservoir and injection water.
Scale inhibitor is therefore continuously dosed into the injected water stream sufficiently
upstream of the mixing point topsides of produced water and seawater/ballast water, to
ensure its full availability at the mixing point. Two alternative injection points are provided,
one upstream of the water injection booster pumps and, to allow for the risk of warm
ballast water return creating scale in the deaerator, one upstream of the deaerator.
3.3.4 Utility Chemicals
There are requirements for various detergent/cleaning materials including:
A general purpose rig wash (SOBO S GOLD 08) to clean light hydrocarbons
from the decks, which will then mix with fluid in the drainage system and be re-
injected, where possible and discharged with the ballast water should the
injection system be offline.
A turbine wash (ZOK 27 GS) used to perform offline washes to maintain turbine
integrity, which will then mix with fluid in the drainage system and be re-
injected, where possible and discharged with the ballast water should the
injection system be offline.
3.4 Corrosion Management
Process levels of H2S have been calculated as being below the sour limits, and therefore
no specific measures are required.
The primary corrosion protection method for the tank is cathodic protection, although the
bottom section of the tank is also coated as a further mitigation against under deposit
corrosion. The cathodic protection design is standard and has been proven in practice by
anode performance in tanker oil and ballast tanks which represent similar environments.
Externally, the tank is protected by cathodic protection without coating. Monitoring of
cathodic protection performance during operations should be easily achieved by ROV
surveys.
Internal pipework is constructed from 25Cr duplex and coated externally therefore no
corrosion threats are envisaged. However, connections with external piping introduce a
galvanic corrosion threat through dissimilar materials.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 32
Internal integrity of the pipelines and umbilicals is achieved through chemical injections
and condition monitoring regime combined with pipeline corrosion allowances. Provision
has been made in the umbilical for chemical injection capability.
Cathodic protection of the riser system will be applied in the form of sacrificial anodes. 3-
layer polypropylene (3-LPP) anti-corrosion coating will be applied to the super duplex
water injection line and oil risers. Anti-corrosion coating has been applied to the infield
pipelines.
In addition to the above as the SOST is constructed from carbon steel as is the internal
pipework an robust biocide strategy is in place. There is a high risk of corrosive bacteria
forming, particularly biofilms, therefore biocidal protection is essential to protect the
integrity of the SOST and internal pipework. Organic biocide will be injected with the
seawater displacement fluids during offload and on a batch basis with the oil from the 2nd
stage into the SOST.
There is a high risk of bacterial growth in the SOST as raw seawater will be used for
displacement, which will contain bacteria and is oxygenated. The seawater will then be
allowed to sit in stagnant conditions ideal for the proliferation of biofilm that leads to
microbial influenced corrosion. Therefore, a biopenetrant is required to prevent
establishment and aid removal of biofilm.
3.5 Drains
The main deck areas are plated. The platform cellar deck is bunded to contain pool fires.
All deck areas are drained to either the Closed drains drum or Open drains tank under the
cellar deck. All liquid from the Closed drains drum is pumped to the second stage
separator. Liquids from the Open drains tank are separated into clean water and
hydrocarbons, water is routed to the ballast water caisson and through the temporary
filters and hydrocarbons are returned to the closed drains drum and then back to 2nd stage
separator. a tank under the cellar deck. All liquid from this tank is pumped to the second
stage separator. Hence, all aqueous liquids are directed to the water injection system and
all organic liquids are directed to the oil export system (Chrysaor Ltd, 2009).
3.5.1 Closed Drains System
The closed drain system collects hydrocarbon liquids and oily water drained from the
topsides equipment. These are routed independently to the closed drain drum, where they
are degassed. The recovered liquids are routed to the second stage separator, whilst the
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 33
flashed vapours are routed to the flare header for safe disposal. Future provision is also
provided for routing the reject oil from any produced water treatment package to the
closed drain drum.
3.5.2 Open Drains System
The open drains system is a single open hazardous area drains system only. This takes
deck open drains, diesel drains, skim from the seawater disposal caisson, and backwash
returns from the seawater fine filter (which may be contaminated with oil from ballast
water). Drainage from non-hazardous areas (i.e. rainwater from areas not credibly
exposed to oil contamination) will not be collected but will be allowed to go over the side of
the decks.
Overboard discharge of oil-contaminated water is not permitted.
Open drains water that could credibly be oil-contaminated shall be routed to the open
drains tank where oil will be skimmed utilising a parallel plate pack followed by bucket-
and-weir oil skimming system. Skimmed oil will be returned to the closed drains drum.
The cleaned, but potentially still oily, water from the open drains tank shall be directed by
pump to the ballast water caissons, where it will co-mingle with the ballast water. From
there it will pass through the temporary filtration package and once water injection is
commissioned to the de-aeration package and water injection systems and onwards for
injection into the reservoir. Prior to water injection commissioning and during first fill of the
SOST the drains water will co-mingle with the ballast water then through the temporary
filtration package and be discharged overboard via the seawater disposal caisson C-4801.
As Solan operate a ‘zero’ discharge operating philosophy, the platform will shutdown
should water injection fail. In the event of a planned prolonged water injection shutdown
(during which there will be no production), for example during the annual shutdown, drains
water may be routed from the open drains tank to the seawater disposal caisson. This
pathway, under normal operating conditions, has the flange removed preventing water
from reaching the caisson. This route may be reinstated during prolonged periods of
process shutdown to ensure safe operation of the platform drains. Should this be required,
an Oil Discharge Permit update will be submitted. Any oily residue will be pumped by the
seawater disposal caisson skim pump to the open drains tank.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 34
4 BASELINE ENVIRONMENT
This part of the document provides a review of the baseline environment and principal
environmental receptors within the area which could be affected by the proposed
installation activities. All infrastructure for the Solan development will be located within
Block 205/26, therefore this section is focussed on the environmental receptors in Block
205/26. These receptors include benthos, birds, fish, marine mammals and other sea
users. This information is gathered from recognised literature sources and draws upon site
specific survey information undertaken by Gardline (2008).
4.1 Metocean Conditions
4.1.1 Water Currents, Waves and Tides
Local current speeds and direction influence the transport, dispersion and ultimate fate of
marine discharges and materials. The general circulation within the North Sea is an anti-
clockwise direction with water entering the North Sea from the Atlantic Ocean north of
Scotland and travelling down the UK east coast to approximately the North Norfolk
coastline where the water current mixes with a weaker current travelling through the
English Channel. The WoS area is predominately influenced by North Atlantic water
(Figure 4-1).
Solan
Development
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 35
Figure 4-1 Prevailing ocean currents in the North Sea
The water current patterns in the WoS area are complex, with various strong non-tidal
currents interacting with the relatively weak tidal flow. Semi-diurnal tidal currents are
relatively weak in offshore northern and central North Sea areas (DTI, 2001). The
maximum tidal current speed within the Solan development area during spring peak flow is
between 0.26 m/s and 0.5 m/s, and during neap peak flow is between 0.11 m/s and 0.25
m/s (Scottish Government NMPI, 2014). Mixing in the water column intensifies with
increased tidal current speed.
The annual mean significant wave height within the area is 2.1-2.4 m. Annual significant
wave power is 24.1-30.0 kW/m of wave crest (Scottish Government NMPI, 2014). During
storms, the re-suspension and vertical dispersion of bottom sediments due to waves and
currents affects most of the North Sea.
4.1.2 Water Temperature
Seawater temperatures vary with season, depth and proximity to land. A seasonal
thermocline can develop during the summer months in response to warmer surface water
floating on top of cooler more dense water. This thermocline breaks down in the autumn
due to seasonal cooling and increasing frequency and intensity of storms causing the
water column to mix. Annual mean surface temperatures in the Solan development area
range from 8-9 ºC, and annual mean seabed temperatures range from 9-10 ºC (Scottish
Government NMPI, 2014).
4.1.3 Winds
Offshore winds in the region may blow from any direction, however winds are
predominantly from southerly and westerly directions (DTI, 2003). A windrose for the area
is shown in PhysE (2009) (see Figure 4-2). Annual wind speed for the area is 11.1-11.5
m/s, with an average range of 10.6-11.0 m/s in spring, 8.1-8.5 m/s in summer, 11.6-12.0
m/s in autumn and 13.1-13.5 m/s in winter (Scottish Government NMPI, 2014). During the
spring (April to June), the area is characterised by a uniform wind distribution with east-
southeast, north-northwest, north and north-northeast winds being predominant. From July
to March, south-southwest, west-southwest and north winds occur with a frequency of
32% (DTI, 2003).
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 36
Figure 4-2 Windrose for the Solan area (PhysE, 2009)
4.2 The Seabed
4.2.1 Bathymetry
The main feature of the region surrounding the Solan area is the Faroe-Shetland Channel,
which reaches depths of up to 1,700 m and is bordered to the northwest by the Faroe
Shelf and to the southeast by the West Shetland Continental Shelf. Just north of 60ºN, the
channel hits the Wyville Thomson Ridge and makes a right-angled turn to the northwest to
form the Faroe Bank Channel.
Quadrant 205 lies over the West Shetland continental slope and the West Shetland
Continental Shelf.
The water depth at the site is 138 m LAT. Depths within the area surveyed by Gardline
(2008) ranged from 125.5 m LAT in the south to 162.2 m LAT in the northwest. Across the
survey area, the seabed shoals towards the south. Across much of the centre and north of
the survey site, and parts of the south, low relief, northeast-southwest orientated striations
were observed. These correlated with areas of gravel, cobbles and boulders found on
sonar records. The maximum gradient within the survey area was 1.9° (Gardline, 2008).
Occasional larger boulders / debris items were identified by side scan sonar.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 37
4.2.2 Sediment and Seabed Features
Site-specific surveys determined that the sediments throughout the area are
predominantly comprised of gravelly shelly sand with northeast-southwest orientated
bands of gravel, cobbles and boulders. In the southeast of the survey are there are
localised areas of gravelly shelly sand and gravel/cobbles (Gardline, 2008). A large area of
sand waves was also identified orientated northwest to southeast across the Solan
development area (Gardline, 1991; Gardline, 2008). Sand ribbons were also observed in
the southeast, east and southwest of the site, and some trawl scarring was observed
(Gardline, 2008). Within the greater survey area, 17 boulders ranging in height from 0.5 to
1.3 m have been identified (Gardline, 2008).
Seabed image examples are provided in Figure 4-3.
Figure 4-3 Seabed image examples (Gardline, 2008)
There was no indication from the acoustic data, seabed imagery or seabed sampling
within the survey area of any Annex I habitats protected under the UK’s Offshore Marine
Conservation (Natural habitats, &c.) (Amendment) Regulations 2010, which implements
the European Commission (EC) Habitats Directive 92/43/EEC.
4.3 Marine Flora and Fauna
This section describes the main receptors of the marine environment.
4.3.1 Plankton
Plankton are drifting organisms that inhabit the pelagic zone of a body of water and
include single celled organisms such as bacteria as well as plants (phytoplankton) and
animals (zooplankton). Phytoplankton are the primary producers of organic matter in the
Fix: 74 Depth: 155 m
Location: 444605 E 6660438 N
Fix: 64 Depth: 144
Location: 444013 E 6658544 N
Fix 74: Coarse shelly sandy sediment with some gravel
Fix 64: Coarse shelly sandy sediment with some gravel and cobbles
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 38
marine environment and form the basis of marine ecosystem food chains. They are grazed
upon by zooplankton and larger species such as fish, birds and cetaceans; therefore, the
distribution of plankton directly influences the movement and distribution of other marine
species. Meroplankton includes the eggs, larvae and spores of non-planktonic species
(fish, benthic invertebrates and algae) that are found in the plankton. This meroplankton
population may have a very different seasonal cycle depending on the life cycle strategy of
the fish species and benthic organisms which inhabit the area.
The composition and abundance of plankton communities vary throughout the year and
are influenced by several factors including depth, tidal mixing, temperature stratification,
nutrient availability and the location of oceanographic fronts. The distribution, abundance,
production and biodiversity of various plankton species and communities are thought to be
profoundly affected by physical pressures such as oceanic circulation, stratification,
nutrient availability and light levels (McQuatters-Gollop et al., 2010).
Plankton communities in the area of interest are influenced by the inflow of Atlantic Ocean
water through the Faroe-Shetland Channel (Johns and Wooton, 2003). Phytoplankton
assemblages in the area of interest are predicted to be a mixture of oceanic and neritic
(shallow water) plankton species (DTI, 2003). Dominant phytoplankton forms in this region
of the North East Atlantic include diatoms of the genus Chaetoceros and Thalassiosira in
addition to dinoflagellates of the genus Ceratium (Johns and Wooton, 2003). Zooplankton
species found in this region include the Calanoid copepods Calanus helgolandicus and C.
finmarchicus as well as a number of Decapoda and Echinodermata larvae.
4.3.2 Benthos
Bacteria, plants and animals living on or within the seabed sediments are collectively
referred to as the benthos. These include species living on top of the sea floor which are
collectively referred to as epibenthic organisms and may be sessile (e.g. seaweeds) or
freely moving (e.g. starfish). Animals living within the sediment (e.g. clams, tubeworms
and burrowing crabs) are termed infaunal organisms. Semi-infaunal animals, including sea
pens and some bivalves, lie partially buried in the seabed.
The structure and distribution of benthic communities can be explained largely by
environmental parameters including temperature, salinity, tidal / wave-induced bed stress,
stratification, depth, and sediment type. Their relative importance varies spatially and
many are intercorrelated (Rees et al., 2007).
Historical surveys have confirmed that the seabed communities of the Shetland
continental shelf are typical of the Boreal province extending south to the North Sea (DTI,
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 39
2003). The abundance of fauna in the area of the Solan development was found to be low
across the site, with slight increases around areas of cobbles and boulders. Crustaceans
(Pagarus sp.), annelids (Lanice conchilega, Ditrupa arietina, Pomatoceros sp.), cnidarians,
molluscs, dogfish and flatfish are commonly recorded. No protected species or habitats of
conservational concern were observed (Gardline, 2008).
4.3.3 Seabirds
In general, seabirds feeding or resting on the sea surface are most vulnerable to water-
borne pollution. The aerial habits of fulmars and gulls, together with their large populations
and widespread distribution, reduce their vulnerability to oil related pollution. Auks (e.g.
guillemots, razorbills and puffins) are most vulnerable in the post-breeding season (July to
August) when they become flightless during periods of moult, thus spending large
amounts of time on the water surface. Generally, vulnerability is lowest during the pre-
breeding and breeding months, increasing as the breeding season ends and birds
disperse into offshore waters (Stone et al., 1995).
JNCC has produced an Offshore Vulnerability Index (OVI) for seabirds encountered within
each offshore licence block in the Southern, Central and Northern North Sea and the Irish
Sea. For each block, an index of vulnerability for all species is given which considers four
factors:
The amount of time spent on the water;
Total biogeographical population;
Reliance on the marine environment;
Potential rate of population recovery.
Each of these factors is weighted according to its biological importance and the OVI is
then derived (Williams et al., 1994). The OVI of seabirds within each offshore licence block
changes throughout the year. This is due to seasonal fluctuations in the species and
number of birds present in an area.
Seabirds present within the immediate vicinity of the Solan area include fulmars, gannets,
great black-backed gulls, kittiwakes, guillemots, razorbills, little auks and puffins. As can
be seen from Table 4-1, the sensitivity of birds to surface pollution in the immediate area
of the Solan field and the surrounding blocks varies throughout the year (JNCC, 1999).
Seabird vulnerability within Block 205/26a during the proposed pipeline operations
(covering a period from June to October with contingency to end of December) is high in
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 40
July, moderate in June, October and November and low in August, September and
December. The overall vulnerability of seabirds to surface pollution is considered low, as
shown in Figure 4-4.
Table 4-1 Seabird vulnerability to surface pollution by block
Block J F M A M J J A S O N D
204/25 3 4 3 2 3 2 2 4 3 3 3 4
205/21 3 4 3 2 3 3 2 4 3 3 3 4
205/22 3 4 3 2 3 3 2 4 3 3 3 4
204/30 3 4 3 2 3 2 2 4 3 3 3 4
205/26 3 4 3 2 3 3 2 4 4 3 3 4
205/27 3 4 3 2 3 3 2 4 4 3 3 4
202/5 3 3 2 2 2 2 1 4 3 2 3 4
203/1 3 3 2 2 2 2 1 4 4 2 3 4
203/2 3 3 2 2 2 2 1 4 4 2 3 4
Key 1 = Very high 2 = High 3 = Moderate 4 = Low
Figure 4-4 Overall seabird vulnerability to surface pollution
4.3.4 Fish
At present, more than 330 fish species are thought to inhabit the shelf seas of the UK
Continental Shelf (UKCS) (Pinnegar et al., 2010). Many of these species are widespread
across the North Sea, having large extended spawning and nursery grounds. Some of the
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 41
commercial species with recognised spawning and nursery grounds in the area of Block
205/26 are listed in Table 4-2 (Coull et al., 1998; Ellis et al., 2012).
Table 4-2 Spawning and nursery activity of some commercial fish species found in the vicinity of Block 205/26 (Coull et al., 1998; Ellis et al., 2012).
Species J F M A M J J A S O N D Nursery
Norway pout
Sandeel
Mackerel
Blue whiting
Herring
Whiting
Lemon sole
Haddock
Key Spawning Peak Spawning
4.3.5 Marine Mammals
Cetaceans regularly recorded in the North Sea include harbour porpoise, white-beaked
dolphin, minke whale, Atlantic white-sided dolphin, bottlenose dolphin (primarily in inshore
waters) and killer whale (Reid et al., 2003). Risso’s dolphin and large baleen whales are
also occasionally sighted. Spatially and temporally, harbour porpoise, white-beaked
dolphin and minke whale are the most commonly sighted cetacean species in the North
Sea (Reid et al., 2003).
The most common species of cetaceans in the vicinity of the Block 205/26 are harbour
porpoise, Atlantic white-sided dolphin, white-beaked dolphin and minke whale (Table 4-3).
Other published sources of data regarding cetacean distribution in the area include the
SCANS-II (Small Cetacean Abundance in the North Sea) project (SMRU, 2008).
Table 4-3 Cetacean sightings in the vicinity of Block 205/26 (Reid et al., 2003)
Species J F M A M J J A S O N D
Harbour porpoise
Atlantic white-sided dolphin
White-beaked dolphin
Minke whale
Species recorded Species not recorded
Common (or harbour) seals (Phoca vitulina) and grey seals (Halichoerus grypus) are
frequently observed throughout the North Sea. Both the common and grey seal are listed
species in Annex II of the Habitats Directive (see Section 4.5).
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 42
Seals tend to exhibit a general pattern of remaining in close proximity to haul out sites.
Given the distance of the Block 205/26 from the nearest seal haul out site, located
approximately 100 km away on the Orkney Isles (Scottish Government, 2011), seals are
not expected to occur in significant numbers in the area.
4.4 Socio-Economic Environment
4.4.1 Commercial Fishing
Block 205/26 occurs within ICES rectangle 49E6. The UK fishing effort within this area
varies throughout the year. Annually the effort (or importance of the area) can be
considered moderate with an average fishing effort of 788 days (2010 – 2014) per annum.
Approximately 0.44 % of total UK landings between 2010 and 2014 were taken from the
area (Table 4-4) (Scottish Government 2015).
Table 4-4 Fishing Effort by UK Fishing Fleet in ICES Rectangle 49E6 (Scottish Government, 2015).
Year Total Fishing Effort by UK Fishing Fleet (days)
UK total 49E6 49E6 as a % of UK
2010 205,083 1,012 0.49
2011 188,389 994 0.53
2012 185,182 641 0.35
2013 183,413 652 0.36
2014 129,850 639 0.49
Average over 2010 - 2014 788 0.44
The value of landings from ICES rectangle 49E6 over the years 2010 – 2014 are shown in
Table 4-5. In general, the most valuable fisheries in the area are demersal and shellfish
fisheries, although in 2010 the value of pelagic fisheries was much higher than shellfish
than in other years. Over the five years, the average value of demersal, pelagic and
shellfish fisheries in ICES rectangle 49E6 have ranged between 0.67 and 1.36 % of the
UK total.
Table 4-5 Value of Landings (£) by Target Species Group in ICES Rectangle 49E6 (Scottish Government, 2015).
Year Target Species Group (value of landings £) 49E6 as % of
UKCS Demersal Pelagic Shellfish
2010 7,071,130 308,317 62,612 0.98
2011 6,746,227 338 58,225 0.78
2012 5,572,326 1391 44,996 0.67
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 43
2013 6,661,708 1,650 87,088 0.89
2014 8,962,055 572 42,969 1.36
4.4.2 Shipping
A vessel traffic survey was conducted by Anatec on behalf of Premier Oil. The Shipping
Route Positions within 10nm of the Solan central survival location are shown in Figure 4-5
(Anatec, 2015). There are an estimated 835 ships per year passing within 10nm of the
Solan Platform location, corresponding to an average of 2 to 3 vessels per day.
Figure 4-5 Shipping route positions within 10 nm of the Solan location
4.5 Protected Sites and Species
The European Union (EU) Habitats Directive (92/43/EEC) and the EU Birds Directive
(79/409/EEC) are the main driving forces for safeguarding biodiversity in Europe. Through
the establishment of a network of protected sites, these directives provide for the
protection of animal and plant species of European importance and the habitats that
support them.
The EU Habitats Directive and the EU Birds Directive have been enacted in the UK by the
following legislation:
The Conservation (Natural Habitats, &.c.) Regulations 1994 (as amended): These
regulations transpose the Habitats and Birds Directives into UK law. They apply to
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 44
land and territorial waters out to 12 nautical miles (nm) from the coast and have
been subsequently amended several times.
The Conservation of Habitats and Species Regulations 2010: The Conservation of
Habitats and Species Regulations 2010 consolidate all the amendments made to
the Conservation (Natural Habitats, &c.) Regulations 1994 in respect of England
and Wales. In Scotland, the Habitats and Birds Directives are transposed through a
combination of the Habitats Regulations 2010 (in relation to reserved matters) and
the 1994 Regulations.
The Offshore Marine Conservation (Natural Habitats, &c.) Regulations 2007 (as
amended 2009 and 2010): These regulations are the principal means by which the
Birds and Habitats Directives are transposed in the UK offshore marine area (i.e.
outside the 12 nm territorial limit) and in English and Welsh territorial waters.
The Offshore Petroleum Activities (Conservation of Habitats) Regulations 2001 (as
amended 2007): These regulations apply the Habitats Directive and the Birds
Directive in relation to oil and gas plans or projects wholly or partly on the United
Kingdom Continental Shelf and superjacent waters outside territorial waters (‘the
UKCS’) (i.e. outside the 12 nm territorial zone).
The Habitats Directive lists those habitats and species (Annex I and II respectively)
whose conservation requires the designation of special areas of interest. These
habitats and species are to be protected by the creation of a series of ‘Special
Areas of Conservation’ (SACs), and by various other safeguard measures (Sites of
Community Importance (SCIs)) for particular species. The Birds Directive requires
member states to nominate sites as Special Protection Areas (SPAs). Together
with adopted SACs, the SPA network forms the ‘Natura 2000’ network of protected
areas in the European Union.
Of the habitat types listed in Annex I of the Habitats Directive as requiring
protection, four occur or potentially occur in the UK offshore area (EC, 2007):
Sandbanks which are slightly covered by seawater at all times;
Reefs:
o bedrock reefs; made from continuous outcroppings of bedrock which
may be of various topographical shape (e.g. pinnacles and offshore
banks);
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 45
o stony reefs; aggregations of boulders and cobbles which may have
some finer sediments in interstitial spaces;
o biogenic reefs; formed by cold water corals (e.g. Lophelia pertusa)
and the polychaete worm Sabellaria spinulosa;
Submarine structures made by leaking gases; and
Submerged or partially submerged sea caves.
The benthic community recorded in the vicinity of Block 205/26 is characteristic of
communities recorded in the West of Shetland region. No leaking gas features, reefs
(geological or biological) or other potential marine Annex I features were recorded
(Gardline, 2008).
The closest protected areas to Block 205/26 are the Foula SPA and the Wyville Thomson
Ridge SAC which lie approximately 100 km east and 110 km west of the site, respectively
(Figure 4-6). Due to these distances, no adverse effects on any protected areas are
expected from the proposed pipeline operations at the Solan field.
Figure 4-6 Offshore SACs, SCIs and MPAs in Closest Proximity to the Solan Development
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 46
Four of the species listed in Annex II of the Habitats Directive occur in relatively large
numbers in UK offshore waters:
Grey seal (Halichoerus grypus);
Common seal (Phoca vitulina);
Bottlenose dolphin (Tursiops truncatus); and
Harbour porpoise (Phocoena phocoena).
The only one of these species likely to occur within the area is the harbour porpoise.
As a result of the Marine and Coastal Access Act (2009), the Marine Conservation Zones
(MCZ) and Marine Protected Areas (MPA) Project was set up. 30 Nature Conservation
MPAs were designated in July 2014, 13 of which are offshore (beyond 12 nm) (JNCC,
2014). These have been designated to contribute to an ecologically coherent, well-
managed network of MPAs by the end of 2016 to fulfil international and European
commitments.
The nature conservation MPAs (NCMPAs) nearest to the Solan development are the
Faroe-Shetland Sponge Belt, the West Shetland Shelf and Northwest Orkney, located
approximately 23 km northwest, 27 km southeast and 50 km southwest of the site,
respectively. Due to these distances the proposed installation activities are unlikely to
have an impacted on any designated NCMPAs.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 47
5 IMPACT ASSESSMENT
This section presents the results from the identification and assessment of environmental
impacts from the proposed commissioning and operational activities, grouped under the
following headings;
Physical presence;
Seabed Disturbance;
Underwater Noise;
Atmospheric Emissions;
Marine Discharges;
Accidental Events; and
Waste
5.1 Physical Presence
5.1.1 Installation
The vessels which will be on site during precommissioning activities are described in
Section 2.4. These vessels have the potential to impact on other sea users, notably
commercial fishing and shipping. Existing levels of shipping and fishing are described in
Section 4.4.1.
In addition the presence of the jacket and SOST may impact on fishing activities in the
area. This section assesses the impact of the physical presence of the vessels and
infrastructure on other sea users whilst the impacts on the benthic communities are
discussed in Section 5.2.
The two 500 m exclusion zones around the SOST and platform, respectively, will be
unavailable to other sea users to decrease the likelihood of vessel collision.
Consent to Locate applications will be submitted to DECC under this EIA Justification
document and the Collision Risk Management Plan will be implemented. Consent to
Locate CL/264, which covered the installation of the SAL marker buoy, expired on the 31st
of March. The installation of the marker buoy for the SAL system has been delayed and
will now not be fitted until summer of 2015. This installation has been moved to CL/208
and is now covered by this EIA Justification.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 48
In addition when the W1 and W2 wells were suspended in 2008, protective Aquaterra
trash caps were installed onto the wellheads. These remained on the wells until 2013
when they were removed to allow the drilling campaign to commence. At this point they
were laid down on the seabed to allow the opportunity for reinstallation, if required. The
deposit of trash caps was reported under a PON2 (0157) as no consent was sought for
this operation; however, re-installation was not required and it was originally planned to
retrieve the structures under PLA/90 ML121. Due to technical feasibility and operational
risks of recovering the trash caps, Premier now propose to withdraw the trash caps from
the Marine Licence application and add them to the Consent to Locate for the Solan
platform (CL/208) so they will now be covered by this EIA Justification.
The total area of the two protective structures is 8.6 m2 (Table 5-1) of which only a small
proportion actually contacts the seabed. No further impact on the seabed environment is
anticipated from the protective structures remaining on the seabed in their current location
until the end of field life.
Table 5-1 Anticipated foot print
Deposit Number of
objects
Area impacted
by one object (m2)
Approximate total area impacted (m2)
Aquaterra trash caps 2 4.30 8.60
Variation 9 Version 2:
A Waverider Buoy was deployed at the start of the 2015 campaign for metocean data
acquisition to assist with ongoing wellhead fatigue analysis and to assess rig motion
characteristics (approved as per CL/208/7 Version 1).
At 21:57 on 17th September the buoy stopped transmitting data. Premier was informed on
the 18th September by Fugro. The Stand-by vessel was dispatched to investigate and
took some pictures, one of which is shown below (Figure 5-1).
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 49
Figure 5-1 Waverider Buoy with damage shown
The pictures indicated that the buoy had been in a collision with a dent visible, (brown
circle). The buoy was still afloat and at the time we had no concerns about the integrity
of the buoy. Fugro, who supply the buoy were contacted and requested to supply a
replacement buoy. The plan was to swap out old for new, using the existing clump
weight and tether line. We had planned to load the replacement buoy onto the regular
Supply Vessel who had agreed to perform the recovery and re-deployment operation.
As the rig had skidded approximately 250 m away from the buoys location, when the rig
moved from the P2z to the W2 Re-drill location, the buoy was not easily visible from the
rig in anything but a totally calm sea. The Stand-by vessel was asked to sail past the
buoys’ location and verify its condition again. At morning rig call on the 30th September
2015, the rig confirmed that the buoy was no longer on the sea surface and had sunk. A
PON10 has been submitted notifying the relevant authorities (reference TBC). The
location is shown in Figure 5-2.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 50
Figure 5-2 Waverider Buoy location within anchor spread
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 51
The buoy’s location was chosen so that in the event that the buoy sunk for any reason
the buoy would not foul either of the anchor lines adjacent. The anchor lines adjacent to
the buoy’s location contain fibre inserts which cannot tolerate abrasion and must be
kept in the catenary at all times. The anchor lines adjacent to the buoy’s location are
suspending the water at a depth of approximately 150 ft above seabed. The water
depth at the buoy location is approximately 440 ft.
The buoy contains several accelerometers and sufficient computer and signalling
equipment to allow wave data to be transmitted real time to the weather collection
centre. The buoy also contains a battery pack. The buoy contains no foam buoyancy
which would allow it to stay afloat if the integrity of the buoy is breached. Either the
buoy is floating or it is on the seabed. The tether attaching the buoy to the seabed
contains chain segments and several small buoys. With the buoy on the seabed Fugro,
who supply the buoy, estimate that no part of the tether would be more than 275 ft
above seabed.
As the buoy is within the existing catenary structure of the anchor spread and no part of
the tether is capable of coming closer than 163 ft (approx.) of the surface of the sea we
do not consider that the buoy to present a hazard to shipping in its current state. We
would propose to recover the buoy when we have a suitable anchor handling vessel in
the area. This may be when the rig anchor spread is recovered after the current
campaign.
With regards to the existing DSV in the Solan field at the moment, this vessel will not be
in a position to recover the buoy before it comes off contract tomorrow. The contract
cannot be extended as the vessel is committed to another operator and the necessary
pre-job risk assessments and pre checks would prevent the recovery operations being
completed in the time available.
In summary the wave buoy in its current sunk condition represents no danger to
shipping in the area. The area around the rig is patrolled by a dedicated Stand-by
vessel which is on duty 24 hrs a day.
Additionally there is the intention to deploy another Waverider buoy (same model)
approximately 100m away from the current sunk Waverider buoy (as detailed in
CL/208/9).
The area of seabed that the Waverider buoys are contained within an area that has
already been assessed by the anchor spread of the Ocean Valiant therefore there is not
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 52
expected to be any environmental impact. Additionally, the new Waverider buoy is not
expected to present a navigational hazard to other sea users.
5.1.2 Commissioning
Ongoing drilling operations require the Ocean Valiant Mobile Offshore Drilling Unit
(MODU) to be onsite at the Solan development from the 15th May 2015 for approximately
250 days. The Ocean Valiant is semi-submersible and will be anchored in place.
The hook-up and commissioning operations will require additional accommodation in the
form of a DP flotel, the Flotel Regalia. The flotel will be moored next to the Solan Platform
and is expected to arrive at the Solan field on the 1st August and stay for approximately
111 days. The Floatel Superior will replace the Flotel Regalia as accommodation vessel
from the 18th of November and stay for approximately 103 days. The two flotels may
coincide with one another for 3 days before the Regalia leaves.
These vessels will be within the established 500 m safety zone at the Solan platform.
Therefore, restrictions to shipping and fishing in the area will not alter during
commissioning and will not cause any additional disruption to navigation in the area. As
discussed, the area is of relatively low importance in terms of shipping traffic and fishing,
the physical presence of the accommodation vessel in the area during commissioning
activities is not considered to be significant.
5.2 Seabed Disturbance
5.2.1 Commissioning
5.2.1.1 Ocean Valiant
Seabed disturbance associated with anchor chains from the drilling rig Ocean Valiant has
been assessed. The rig will be held in position by a 12 chain and anchor mooring system,
the provisional anchor layout is illustrated in Figure 5-1. A seabed footprint of
approximately 0.12 km2 has been calculated (Table 5-2). All the anchors and chains will be
recovered and so the disturbance to the seabed will be temporary.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 53
Table 5-2 Seabed area temporarily impacted by the drilling rig mooring
Parameter Area (km2)
12 x anchors, 10 m x 10 m per anchor placement 0.0012
12 x anchor chains, with a worse case impact on an area of seabed assumed to be 1,000 m x 10 m per chain
0.12
Total 0.1212
Physical disturbance as a result of anchor scarring can cause mortality or displacement of
benthic species in the impacted zone, direct loss of habitat and direct mortality of sessile
seabed organisms that cannot move away from the contact area at seabed contact points.
Two factors minimise these impacts:
Biological communities are in a continual state of flux and are able to either
adjust to disturbed conditions or rapidly re-colonise areas that have been
disturbed;
The active / dynamic nature of much of the seabed environment will aid the
rapid recovery of the disturbed areas, although some seabed scars may
persist.
As discussed in Section 5.2, the majority of seabed species recorded from the European
continental shelf are known or believed to have short life spans (Rees and Dare, 1993).
Therefore, it is expected that the benthic species will be recruited from the surrounding
seabed and so the impacted areas will recover from the physical disturbance.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 54
Figure 5-3 Proposed anchor pattern (Diamond Offshore, 2015)
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 55
There is limited data on the impacts of scarring from oil and gas activities. However,
Coastline Surveys Limited (1999) has undertaken a study on the impacts of marine
aggregate mining on the benthic community. Dredge pits were still visible in coarse gravel
deposits after two years. Recovery time can range from one to 15 years depending on the
currents in the area.
Seabed currents in the Solan development area are strong with a maximum spring tide of
0.5 m/s (Scottish Government NMPI, 2015). Significant erosion of anchor mounds is
considered to start when the seabed critical velocity reaches 0.35 m/s (UK Offshore
Operators Association, 1999). It is therefore likely that significant erosion of anchor
mounds will occur at times. The temporary nature of the anchor placements ensures that
once the anchors have been removed from the seabed, re-colonisation and recovery can
begin.
DTI (2003b) suggests that the recovery of affected areas of seabed from operations such
as anchoring is expected to be rapid on the WoS continental shelf and slope; recovery
may be expected within five years. Impacts to the seabed are unavoidable; however, the
area that will be affected is small in comparison with the surrounding available seabed and
the localised impacts are not likely to result in large-scale changes in the benthic
community.
5.3 Underwater Noise
5.3.1 Hook-up and Commissioning
This section discusses the noise from the vessels associated with the hook-up and
commissioning works. Previously, Premier were to use the Ceona Amazon as the walk to
work vessel, the Siem Spearfish will now be used instead of the Ceona Amazon. The
current noise impact assessment is for the Ceona Amazon, the Siem Spearfish is a
smaller vessel and has less thrusters and power output. Therefore, the current
assessment will likely overestimate the potential impact of the walk to work vessel for the
commissioning phase work during 2015. The Siem Spearfish will be used as the
accommodation vessel from the 20th June until the 1st August, after which the Flotel
Regalia will replace the Siem Spearfish. As the vessels will be both be on DP the following
noise assessment is representative of both accommodation vessels.
The Floatel Superior will replace the Flotel Regalia as the accommodation vessel, there is
a possibility that they could overlap by 3 days. The Superior will initially be to the south
side of the Solan platform until the Regalia leaves when it will move to the east side of the
platform where the Regalia previously was. The Superior will be on DP at times.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 56
For completion this section also considers the noise associated with the drilling rig which
will also be on location (as described in the Solan drilling permit applications). Underwater
sound associated with the hook-up and commissioning operations will primarily result from
the accommodation vessels, and other vessels also in the area, namely, a DSV and two
standby ERRVs. The drilling rig, the Ocean Valiant will also be in the area and so has
been included in this assessment. This section assesses the impact on marine mammals
of noise generated by the accommodation vessel, the drilling rig and associated vessels.
The primary sources of sound from vessels are propellers, thrusters and other machinery
(Ross, 1976; Wales and Heitmeyer, 2002). In general, vessel sound is continuous and
results from narrowband tonal sounds at specific frequencies and broadband sounds.
Acoustic broadband source levels typically increase with increasing vessel size, with
smaller vessels (< 50 m) having source levels 160-175 dB (re 1 μPa), medium size
vessels (50-100 m) 165-180 dB (re 1 μPa) and large vessels (> 100 m) 180-190 dB (re
1μPa) (summarised by Richardson et al., 1995). However, sound levels depend on the
operating status of the vessel and can vary considerably in time. Acoustic energy is
strongest at frequencies below 1 kHz. Sound levels can be increased during use of DP,
which requires the use of thrusters to control a ship’s location.
Sound associated with drilling rigs will propagate from rotating equipment such as
generators, pumps and the drill string. No specific measurements are available for sound
generated by a semi-submersible drill rig. In general, sound from drilling has been found to
be predominantly low frequency (< 1,000 Hz) with relatively low source levels. Source
levels were found to be less than 195 dB (rms) re 1 µPa-m for a drill ship (Nedwell and
Edwards, 2004). A study by Greene (1987) found that the sound generated by drilling
activities from a semi-submersible did not exceed local ambient levels beyond 1 km,
although weak tones were detectable up to 18 km away. Studies have shown that during
drilling underwater sound levels increase when compared to periods of non-drilling, which
has been related to the use of additional machinery and power demands (McCauley,
1998). Drilling sounds, although of a relatively low level, will be continuously generated for
long periods throughout drilling.
This section assesses the impact on marine mammals of noise generated by the
accommodation vessel, the drilling rig and associated vessels. The impact on marine
mammals is determined by modelling the propagation of sound from the walk to work
vessel, the drilling rig and vessels into the surrounding water and comparing the levels
with precautionary thresholds for injury and disturbance to marine mammals (Southall et
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 57
al., 2007). Southall et al. (2007) conducted a review of noise impact studies and used the
results to propose thresholds for injury and disturbance for different:
marine mammal hearing types – low, mid and high frequency hearing;
sound types – pulse, multiple pulse and non-pulse; and
sound metrics – peak unweighted SPL and SEL weighted for different marine
mammal hearing types.
The assessment method used here is based on the JNCC guidance on the protection of
marine European Protected Species from injury and disturbance (JNCC, 2010).
As the Solan field is approximately 95 km from the nearest coastline, it is not expected that
seals will regularly occur in the area (Scottish Government, 2011). Therefore, this
assessment focuses on cetaceans.
The Regalia will sit alongside the platform and connect to the platform to transfer
personnel and then move alongside the platform. The flotel is a column stabilised semi-
submersible vessel. There are three thrusters, six thrusters in total. The thrusters are
NDM3 DP and each thruster is 2.64 MW in power (Prosafe, 2014). A DP system is used
for station keeping, using all six of the thrusters.
The Floatel Superior will replace the Regalia as accommodation vessel, the two flotel
could potentially overlap for 3 days which could increase underwater noise levels during
that time. The Superior has six azimuth thrusters each 3,200 KW. The thrusters are DP3
Knosberg K-Pos DPM-32 (Floatel International, 2015). A DP system is used for station
keeping, using all six of the thrusters.
Other vessels that will also be in the area at the same time as the accommodation vessel
have also been included in the assessment. A DSV will be used for 20 days at the end of
May and two standby ERRVs will be in the vicinity of the field at all times during the
campaign. As a conservative assumption here all vessels have been modelled as being in
the same place at the same time, whereas in reality the vessels will be spread out. As
mentioned previously the Ocean Valiant drilling rig has also been included and has been
modelled as being in the same place as the vessels.
As the two flotels could potentially overlap, additional modelling was carried out to assess
the cumulative impact of all the vessels in the field. The results found that an additional
flotel will only increase the broadband peak SPL by 1 dB. Therefore, the noise assessment
which follows will be representative.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 58
5.3.1.1 Unweighted peak SPL thresholds
Peak SPL is a measure of the loudest instantaneous sound likely to be generated during
an activity. To assess the impact of noise on marine mammals from the thrusters of the
walk to work vessel, the drilling rig and the vessels, the sources have been modelled using
representative spectra from published sound measurements (Figure 5-4).
The frequencies and sound levels generated by the accommodation vessel were modelled
using measurements of six offshore oil production vessels (Erbe et al., 2013). The sound
recordings were combined and the 95th percentile of the measurements were used as a
conservative assumption. The resulting sound spectrum is considered a reasonable
representation of the walk to work vessel due to the use of azimuth thrusters by both
vessel types (Siem Offshore, 2014; Prosafe, 2015; Floatel International, 2015 and Erbe et
al., 2013). As no source spectra were available for sound from a semi-submersible drilling
rig, the drilling noise was represented by a source spectrum for a drillship (Miles et al.,
1987), which is a conservative assumption. The DSV and the standby ERRVs were
represented by a source spectrum for a typical merchant vessel (Wales and Heitmeyer,
2002).
Figure 5-4 Sound sources used to represent accommodation vessel and associated vessels
120
130
140
150
160
170
180
190
1 10 100 1,000 10,000 100,000
1/3
oct
ave
ban
ds
0-p
SP
L (d
B r
e 1
µP
a-m
)
Frequency (Hz)
Walk to work vessel - FPSO [Erbe et al., 2013]
DSV and Standby vessels - Merchant vessel [Wales and Heitmeyer, 2002]
Ocean Valiant - Drillship [Miles et al., 1987]
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 59
Figure 5-5 Modelled unweighted SPL from combined sound sources
5.3.1.2 Weighted SEL thresholds
SEL is a measure of total sound energy over a period of time.
The estimated source spectrum for the combined sound sources of the accommodation
vessel, drilling rig and associated vessels with the hook up and commissioning work was
weighted for marine mammal hearing by applying the Southall et al. (2007) M-weightings
for each marine mammal hearing type – low frequency, mid frequency and high frequency
hearing (Figure 5-5). The resulting weighted source spectra are shown in Figure 5-6.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 60
Figure 5-6 Resulting M-weighted SEL for combined accommodation vessel, drilling rig and vessels
In order to calculate the total SEL experienced by an animal, it is necessary to make
assumptions about the movement pattern of the animal in time. To compare with the
Southall et al. (2007) recommendations, the calculation of SEL should be based on the
animal’s behaviour over a 24-hour period. This is extremely difficult to predict. Therefore, a
scenario has been modelled whereby an animal displays avoidance behaviour by moving
away from the source.
5.3.1.3 Travelling animal
This scenario assumes that an animal exposed to the noise from the accommodation
vessel would display avoidance behaviour, swimming away from the source at a fixed
speed and relative to the source.
Figure 5-7 shows the received unweighted SEL and the cumulative received SEL as the
animal moves away from the source at 5 m/s. While a wide range of cruising speeds are
found in the literature this travelling speed has been assumed for previous assessments
carried out for piling noise (e.g. Theobald et al., 2009). A sensitivity analysis has been
conducted using various swimming speeds and the conclusions were not found to change.
One example is shown: an animal is initially 1 m from the source (Figure 5-7), for an
70
90
110
130
150
170
190
210
1 10 100 1,000 10,000 100,000
Sou
rce
M-w
eig
hte
d S
EL (
dB
re
1µ
Pa
2 s a
t 1
m)
Frequency (Hz)
Unweighted
Low-frequency cetacean
Mid-frequency cetacean
High-frequency cetacean
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 61
unweighted broadband SEL. This starting distance is a very pessimistic assumption and
ignores the more likely scenario of the sound sources being spread out over a large area.
Figure 5-7 Cumulative SEL from the flotel and vessels as an animal travels away at 5 m/s from an initial distance of 1 m.
The results indicate that the Southall et al. (2007) SEL threshold for injury from a non-
pulse (215 dB re 1 µPa2s) will not be exceeded at any point.
5.3.1.4 Comparison with behavioural response thresholds for disturbance
The sound generated by the accommodation vessel, drilling rig and associated vessels
with the hook up and commissioning work will primarily be of non-pulse type and all
hearing classes of cetaceans have the potential to occur in the development area. A
review of the studies collated by Southall et al. (2007) that are relevant to the sound
sources suggests the following:
Low-frequency cetaceans exposed to non-pulse sound appear in general to
show little or no response to received SPL lower than 120 dB re 1 µPa rms and
increasing probability of response at 120-160 dB re 1 µPa rms. However, there
is considerable variation in response and contextual variables such as level of
habituation are at least as important as received sound level. 120 dB re 1 µPa
rms is used here as a conservative threshold.
180
185
190
195
200
205
210
215
220
0 50 100 150 200
Re
ceiv
ed
SEL
(d
B r
e 1
µP
a2 s
)
Time (seconds)
Cumulative Received SEL
SEL injury threshold for cetaceans
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 62
Studies of mid-frequency cetaceans exposed to non-pulse sounds did not find
a consistent level of sound above which a severe response resulted. A severe
response was noted in some studies at 90-120 dB re 1 µPa rms but in other
studies no response was exhibited at 120-150 dB re 1 µPa rms. As mid-
frequency cetaceans are likely to be less sensitive to vessel sound than low-
frequency cetaceans, whose frequency range of most acute hearing overlaps
with the peak frequencies generated by vessels, the disturbance threshold for
low-frequency cetaceans (120 dB re 1 µPa rms) is used here for mid-frequency
cetaceans.
Of high-frequency cetaceans, only the harbour porpoise has been well studied.
Severe and sustained avoidance was found to result for received non-pulse
sound levels above 140 dB re 1 µPa rms. Habituation was noted in some
studies, whereby the response waned with repeated exposure.
Based on these data, the estimated zones of disturbance for each marine mammal
hearing type to multiple pulses during the hook up and commissioning work have been
calculated (Table 5-3). It should be noted that there is considerable uncertainty in these
values, related to paucity of data and variation in the reported responses of marine
mammals to sound levels. In addition, conservative values have been selected, i.e. the
lowest sound levels leading to a severe behavioural response.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 63
Figure 5-8 Modelled unweighted rms SPL and weighted cetacean disturbance zones
Table 5-3 Distances to disturbance thresholds for marine mammals.
Marine mammal
hearing group
Precautionary disturbance threshold
(rms SPL in dB re 1µPa)
Distance to threshold (km)
Area of potential impact (km2)
Low frequency cetacean
120 11.8 437
Mid frequency cetacean
120 2.0 12.6
High frequency cetacean
140 0.15 0.07
The estimated numbers for each species are shown in Table 5-4, using the SCANS data
as described previously.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 64
Table 5-4 Estimated number of animals within potential disturbance zone.
Species
Density (animals/km2)
(SCANS II 2008, Survey Block J)
Total abundance (SCANS II, 2008,
entire survey area)
Number of animals within
disturbance zone
Percentage of
population (%)
Minke whale 0.012 16,391 5 0.03
White-sided dolphin 0.052 27,228 1 0.002
White-beaked dolphin1 0.052 22,398 1 0.003
Harbour porpoise 0.067 375,358 <1 0.000001 Notes: 1Combined data for white-beaked and white-sided dolphin, which can be difficult to distinguish in the field.
5.3.1.5 Conclusions of Noise Assessment
The modelling found that the SPL injury thresholds were unlikely to be exceeded (Figure
5-5). Assuming that an animal would be likely to move away from the sound generated by
the accommodation vessel, drilling rig and associated vessels with the hook up and
commissioning work, the modelling found that the SEL thresholds are also unlikely to be
exceeded for any marine mammal hearing type Figure 5-7. Based on these results, it is
considered unlikely that any marine mammal will be injured by sound generated by the
accommodation vessel, drilling rig and associated vessels with the hook up and
commissioning campaign.
JNCC (2010) acknowledge that chronic exposure to vessel noise has the potential to
cause disturbance to marine mammals. Tentative disturbance thresholds were applied
based on studies of marine mammals exposed to non-pulse sounds reviewed by Southall
et al. (2007). The results suggest that sound generated by the accommodation vessel,
drilling rig and associated vessels with the hook up and commissioning work may be loud
enough to cause disturbance within a few kilometres to a few tens of kilometres (Figure
5-8). These values are very conservative as they are based on the lowest sound levels
reported to cause a severe behavioural response. The numbers of animals affected,
estimated by multiplying the modelled areas of disturbance by the average density of each
species in the Solan area, are low com (Table 5-4).
JNCC (2010) state that the likelihood of disturbance to marine mammals from vessel noise
depends on many factors such as the type of vessel, importance of the area for marine
mammals, the receptor’s behaviour and habituation, etc. As stated above, the reported
response of animals to received sound waned with repeated exposure in some studies.
This suggests that sound from the accommodation vessel may become less disturbing
over time and also that animals may already be habituated to vessel noise.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 65
The Flotel Regalia is anticipated to be on location at Solan for approximately 111 days.
This is a longer duration than the previous accommodation vessel, the Siem Spearfish.
The Floatel Superior will replace the Regalia and will stay for 103 days, the two flotels may
also potentially overlap by 3 days. From the shipping routes shown in Figure 4-5, it can be
seen that on average several vessels pass through the area on a daily basis, therefore
background noise in the area is not expected to be very low. The additional noise from the
commissioning operations at Solan is not anticipated to be above background noise levels.
Based on the above, it is concluded that the accommodation vessel, drilling rig and
associated vessels with the hook up and commissioning campaign will not have a
significant effect and the likelihood of an injury or disturbance offence to marine European
Protected Species (EPS) is negligible.
5.3.2 Operation of Platform
Noise will be generated from operation of the platform; however, this will have negligible
impact underwater where there are sensitive receptors and is therefore not taken forward
for further consideration in this assessment.
5.4 Atmospheric Emissions
Gaseous emissions contribute to global atmospheric concentrations of greenhouse gases
(GHGs), regional acid loads and in some circumstances low-level ozone and
photochemical smog formation. The main GHGs are carbon dioxide (CO2), methane
(CH4), nitrous oxide (N2O) and halogenated fluorocarbons; the latter are now strictly
controlled under the Montreal Protocol.
Table 5-5 summarises the emissions associated with the hook-up and commissioning
during 2015 for the Siem Spearfish for 56 days and four days in transit, the Flotel Regalia
for 111 days and 4 days in transit, the Floatel Superior for 103 days and 4 days in transit
and associated supporting vessels. Emissions have been calculated using emission
factors from the Environmental Emissions Monitoring System (EEMS) Atmospherics
Calculations (EEMS, 2012). Based on an estimated total fuel use of 8,334 tonnes, it can
be seen that the emissions associated with the installation vessels equate to
approximately 0.3 % of CO2 generated by UK domestic and international shipping
emissions in 2012 (DFT, 2014).
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 66
Table 5-5 Anticipated atmospheric emissions from the support and accommodation vessels during 2015
Source Total fuel use (Te)
Emissions (Te)
CO2 NOx N2O SO2 CO CH4 VOC
Siem Spearfish 1,120 3,584 67 0.25 4.5 17.6 0.2 2
Flotel Regalia 3,490 11,168 207 0.8 14 55 0.6 7
Floatel Superior 3,250 10,400 193 0.72 13 51 0.6 6.5
Vessels supporting hook-up and commissioning whilst the accommodation vessels are on location
474 1,517 28 0.1 1.9 7.4 0.09 0.9
TOTAL 8,334 26,669 495 2 33 131 2 17
UK domestic and international shipping CO2 emissions (2012) (DFT, 2014)
8,600,000
Total vessel CO2 emissions as a percentage
0.3%
The atmospheric emissions associated with the accommodation vessels may result in
short-term deterioration of local air quality within the vicinity of the vessel. In the exposed
conditions that prevail offshore, the emissions generated are expected to rapidly disperse,
ensuring that all released gases are present in very low concentrations outside the
immediate vicinity of the vessel. It should be noted that the accommodation vessels will
not be onsite at the same time. Emissions from the vessels are therefore assessed to be
an impact of minor magnitude.
The impact will be mitigated by the optimisation of vessel efficiency and minimising fuel
use. Due to the high dispersion rates and minimal nature of the emissions in relation to
total UKCS emissions, no further mitigation measures are proposed.
5.4.1 Production Operations
Atmospheric emissions resulting from production operations have the potential to impact
on local air quality, transboundary and cumulative air quality and to contribute to regional /
global effects such as acid rain, low level ozone and global climate change. The main
sources of atmospheric emissions during production are from:
Power generation for the Solan platform;
Flaring of a small amount of surplus gas in the early life of the field;
Power generation for shuttle tankers and support vessel; and
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 67
Venting from shuttle tankers during oil loading.
Fuel combustion processes produce nitrogen monoxide (NO) and nitrogen dioxide (NO2),
as well as various derivatives that result from the chemical reaction of NO and NO2 with
other elements and compounds in the atmosphere. The emission of NOx compounds and
their derivatives can result in a wide variety of adverse impacts to human health and the
environment. These impacts can occur on both a local scale, caused by the immediate
effect on the surrounding environment, or on a wider global scale, caused by the
transportation of NOx compounds over national boundaries by wind and current
(transboundary).
The emission of NOx can have a detrimental impact on human health. Ground level ozone,
which is a major contributor to smog, is formed in the atmosphere through the reaction of
NOx with volatile organic compounds (VOCs) in the presence of light and heat. NOx also
reacts with water, ammonia, and various other compounds in the atmosphere to produce
nitric acid vapour and other particulate matter. Both ozone and particulate matter
contribute to lung and respiratory problems in humans and prolonged exposure can cause
damage to lung tissues, acute bronchitis, emphysema, chest pains, and aggravation of
respiratory conditions such as asthma.
NOx emissions can lead to deterioration in local air quality. Consequently local receptors
should be identified in order to assess the potential impacts. There are no receptors in
close proximity to the Solan installation. The nearest receptors in the area are the
Schiehallion field (35 km to the North) and Clair (90 km North East).
The Solan platform is located approximately 55 km from the UK/Faroes median line and
95 km from the Scottish coast so there is unlikely to be a potential for trans-boundary
transport of atmospheric contaminants. The increase in emissions from the Solan platform
in relation to existing operations in the area is not a significant additive effect when
considering the total annual offshore emissions from the UKCS.
Emissions of VOCs may result from oil loading. VOCs are of environmental concern due to
the regional and global scale impacts associated with their role in the formation of low-
level ozone and emission of greenhouse gases. Low-level ozone is not emitted directly but
is formed by a complex mechanism involving VOCs and nitrogen oxides in the presence of
sunlight. The low-level ozone is known to damage vegetation and high concentrations are
toxic to humans. Due to limited time period over which these emissions will take place, the
regional scale of the ozone likely to be formed and the distances the emissions must be
transported from the Solan development before encountering any sensitive receptors
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 68
(such as urban or agricultural areas), it is likely the environmental impact of these
emissions is of relatively low significance.
5.4.1.1 Power generation for the Solan platform
Power generation on the Solan platform will be supplied by dual-fuel turbine generators.
Initially the turbines will be fuelled by fuel gas taken from the associated gas with any
excess gas flared. When the field becomes fuel gas deficient the turbines will be fuelled by
diesel.
When both turbines are in operation, offloading to tanker is occurring and PWRI is
occurring, Premier estimate the peak operating load will be 4.3 MW, utilising an estimated
1.34 MMscf of gas per day. However, due to increased efficiency with higher load, the
worst case gas use of 1.56 MMscf of gas per day corresponds to an operating load of 3.8
MW. Using this figure, an annual contribution of approximately 27,530 tonnes of CO2
represents 0.19 % of the total CO2 emissions during 2012 from UKCS oil and gas
installations (Table 5-6).
Table 5-6 Annual Atmospheric Emissions resulting from Power Generation at Solan
Emissions (Tonnes)
CO2 NOx SO2 CO CH4 VOC
Emissions due to power generation for Solan platform
27,530 554 0.12 73 191 31
Total emissions from UKCS offshore exploration and production
14,119,482 47,743 2,559 21,369 47,678 60,470
Emissions from power generation on Solan as % of 2012 UKCS emissions
0.19 1.16 0.005 0.34 0.40 0.05
The mitigation measures employed for atmospheric emissions from the Solan platform
include;
All engines, generators and other combustion plant will be well maintained
and correctly operated to ensure that they are working as efficiently as
possible to minimise emissions;
Emissions will be monitored and reported in line with the EU ETS Permit for
the installation; and
Predicted emissions will be minimised by ensuring that vessel engines are
well maintained. Low sulphur diesel will be used at all times.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 69
5.4.1.2 Flaring of a small amount of surplus gas in the early life of the field
Premier will use fuel gas as it is produced with a small flare of surplus gas in the early life.
As the oil production profile declines, the available associated gas declines with it and
flaring of surplus gas will cease. The quantity of gas flared will be kept to a minimum and
the Solan platform will have a Flare and Vent Consent in place by the start of production.
Flaring results in an annual contribution of approximately 34,778 29,286 tonnes of CO2
which represents 0.28 0.24 % of the total CO2 emissions during 2012 from flaring from
UKCS oil and gas installations (Table 5-7).
Table 5-7 Annual Atmospheric Emissions Resulting from Flaring at Solan
Emissions (Tonnes)
CO2 NOx SO2 CO CH4 VOC
Flaring emissions from the Solan platform 34,778 29,286
15 13 0.16 0.13
83 70 224 188 25 21
Total flaring emissions from UKCS offshore exploration and production
12,358,635 2,220 17,959 39,608 41,364 43,477
Emissions from flaring on the Solan platform as % of 2012 UKCS emissions from offshore oil and gas activities
0.28 0.24 0.67 0.57
0.00 0.21 0.18
0.54 0.46
0.06 0.05
5.4.1.3 Power generation for shuttle tankers and support vessel
Table 5-8 summarises the anticipated emissions from the power generation of the shuttle
tankers and the support vessel during crude loading operations. As the table shows, the
emissions associated amount to approximately 1.12 % of CO2 generated by UK domestic
and international shipping emissions in 2012. This is therefore assessed to be an impact
of minor magnitude.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 70
Table 5-8 Estimated Emissions Associated with Shuttle Tanker and Support Vessel Operations.
Source Total
fuel use (te)
Emissions (Te)
CO2 NOx N2O SO2 CO CH4 VOC
Shuttle Tanker 24,674 78,957 1,466 5.4 99 387 4.4 49
Support Vessel (anchor handling tug)
5,475 17,520 325 1.2 22 86 1.0 11
Total shuttle tanker loading emissions
30,149 96,477 1,791 6.6 121 473 5.4 50
UK domestic and international shipping CO2 emissions (2012) (DFT, 2014)
8,600,000
Total shuttle tanker loading and support vessel CO2 emissions as a percentage
1.12%
The impact will be mitigated by the optimisation of vessel efficiency and the avoidance of
unnecessary operation of power generation/combustion equipment. MARPOL
requirements will be complied with, including the use of shuttle tankers and a support
vessel with an IAPP Certificate. The overall risk to the environment is assessed to be
medium.
5.4.1.4 Venting from shuttle tankers during oil loading
During the loading of crude oil onto the shuttle tanker, VOC emissions (principally CH4 and
Non-Methane Volatile Organic Compounds (NMVOC)) will be produced, with the potential
for associated impacts.
VOC recovery packages are not fitted as standard on UKCS shuttle tankers; however,
Premier have three tankers which will alternate tanker offload duties at Solan: Navian
Oslo, Stena Natalia and the Scott Spirit, all of which have VOC recovery packs fitted. The
VOC recovery process is based on the direct absorption of VOCs in a side stream of the
loading oil. Using this process the oil containing the absorbed VOC is re-mixed with the
main oil-loading stream.
Atmospheric dispersion modelling of the pollutant concentrations of VOCs (CH4 and
NMVOC) from the loading of crude oil to the shuttle tanker generated worst case surface
level concentrations of 8,183 µg/m3.These concentrations were predicted approximately
20 m from the shuttle tanker and were found to drop off considerably by 500 m.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 71
On consideration of the mitigation measures that will be employed including, if possible,
the blanketing of cargo gas with inert gas and the use of VOC recovery equipment, the
residual risk to the environment of the VOC emissions associated with the shuttle tanker is
assessed to be low.
5.5 Marine Discharges
5.5.1 Potential Impacts
Chemical discharges will present a localised impact immediately around the discharge
point resulting in potential impacts to plankton, benthos, fish and mammal species. All
chemicals used and discharged as part of the SOST installation and as part of the
commissioning and operational phase have undergone a risk assessment as discussed in
the Chemical Permit SAT and variations.
During the first fill of the SOST, there is a requirement to discharge some of the chemicals
used during the installation phase. These discharges have been risk assessed as part of
the Chemical Permit SAT and it is concluded that they are unlikely to have a significant
impact on the marine environment. There will be no routine discharge of chemicals during
the operational phase as all production chemicals will either be exported with the
hydrocarbons or will be re-injected downhole.
The exception to this are the chemicals used during grouting operations as these
chemicals are exempt from the Offshore Chemical Regulations (OCR). During grouting
operations, some chemicals will be discharged subsea. RX-9022 is a Cefas registered
Gold rated chemical with no product warnings and no hazard warnings. It is
biodegradable, non-bioaccumulating and of moderate toxicity. The product is soluble in
water and will quickly disperse in the marine environment.
NF-6 is a non-Cefas registered defoamer product. It is considered to be readily
biodegradable and have a low toxicity with TLM96 > 1100 mg/l for the rainbow
trout (Oncorhynchus mykiss) and TLM96 > 83644 ppm for the mysid shrimp
Mysidopsis bahia. The product does not contain any known endocrine
disruptors and will readily disperse in the marine environment.
DF-700 is a non-Cefas registered an anti-foam product which is dispersible in
water and is not considered to be a marine pollutant.
CEMI 52.5 N is a non-Cefas registered cement product which is not considered
to be hazardous to the environment. However, a large release of cement in
water can lead to a pH increase and thus be toxic to aquatic organisms.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 72
Shell Naturelle Fluid HF-E 46 is a non-Cefas registered hydraulic oil product
which is not soluble in water and contains components with the potential to
bioaccumulate. It may cause the physical fouling of aquatic organisms,
although is considered to be practically non toxic with LL/EL/IL50 > 100 mg/l for
aquatic organisms. The product is considered to be readily biodegradable and
is not classified as dangerous to the marine environment
A full chemical risk assessment for chemicals covered by OCNS is provided in a separate
document in the Risk Assessment section of the Chemical Permit SATs.
There may be some localised impact associated with the discharge of grouting chemicals
to the marine environment. However, volumes of chemicals associated with the grouting
operations are small and combined with the toxicity and biodegradability properties of the
chemicals proposed, the environmental impact associated with their use is expected to be
negligible.
Discharges of grey and black water from vessels may have immediate local impact on
water quality (deoxygenation) and resultant impacts on marine flora and fauna. Release of
food waste to sea can have potential food chain impacts through introduction of an
anthropogenic food source (although this may have a positive effect in that nutrients are
provided for fauna). Discharges of grey, black and food waste releases are not expected
to adversely affect marine flora and fauna, which are expected to rapidly recover.
5.5.2 Mitigation
Premier will review Common Marine Inspection Documents (CMID) as part of vessel
assurance. The chemical selection process will aim for the lowest environmental impact
for given technical requirements. Use and discharge of chemicals will be kept to a
minimum commensurate with the operations to be undertaken.
5.6 Accidental Events
5.6.1 Oil Spill Risk
Accidental spills of hydrocarbons and chemicals are recognised as potentially damaging to
the environment. The history of the oil and gas industry shows that the accidental events
which could cause large-scale spillage of oil are rare. Despite the recent Macondo blowout
resulting in a large oil spill in the Gulf of Mexico and the Montara blowout resulting in a
large oil spill in the east Timor Sea, the probability of a large-scale uncontrolled oil spill
event occurring remains very low.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 73
Although unlikely, an accidental loss of containment from the Solan facilities or a vessel
collision is possible. A number of mitigation measures are in place to lower the likelihood
of an incident. The Solan Offshore Oil Pollution Emergency Plan (OPEP) was approved by
DECC on 4th September 2014 (Premier Oil, 2014c). The worst case assessment of an oil
spill from the Solan development has been assessed in this OPEP. To update the OPEP
for additional work, Solan Offshore OPEP Annex 1 (Safe Scandinavia) (Premier Oil,
2014d) and Annex 2 (Ocean Valiant) (Premier Oil, 2015) have been submitted and
approved by DECC.
The following updates have subsequently been submitted and approved for additional
work: Annex 3 (Floatel Victory), Annex 4 (Ocean Valiant as a Flotel (retracted)), Annex 5
(Ocean Valiant as a drill rig) and Annex 6 (Flotel Regalia).
Potentially significant sources of environmental risk that could occur from accidental spills
and non-routine events during the activities at Solan include:
Loss of well control (blow-out) resulting in a release of crude oil from the
reservoir;
Spill of chemicals / hydrocarbons from Solan platform;
Diesel bunkering during production activities;
Damage to the SOST and resultant release of hydrocarbons;
Release of hydrocarbons during oil loading to the oil offload tanker;
Spill due to vessel collision.
5.6.2 Oil Spill Prevention
Following the published Macondo report, Premier has taken the recommendations put
forward in the report into consideration when developing the design features and operating
procedures at the Solan development. The prevention of hydrocarbon or chemical spills is
of the highest environmental priority during operations at the Solan development.
The Solan wells, Solan platform, the SOST, the offloading facilities and the offload tanker
are all within four 500 m safety exclusion zones. These zones maximise the protection of
subsea equipment and protect third parties such as fishermen and thereby minimises the
risk of events such as snagging and vessel collision which could lead to oil release.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 74
5.6.2.1 Loss of Well-Control (Blow-out)
A loss of well control (blow-out) can result in an accidental release of crude oil from the
reservoir. Although the likelihood of a hydrocarbon or chemical spill from the Solan wells is
remote, there is a potential risk for organisms in the surrounding marine environment.
Both platform and subsea trees and wellheads are designed with a maximum working
pressure of 5,000 psig (345 barg) and a maximum temperature rating of 105 oC. Wellhead
equipment and xmas trees are maintained and inspected as per industry appropriate
standards. This will be carried out using an ROV and recorded on the maintenance
system.
All wells will be operated within their defined operational envelope. The flowrates from
blowouts of a completed well will be controlled:
By daily monitoring the annulus pressure;
Through the use of an actuated master and wing valve fitted on all wells,
i.e. two independent safety barriers for controlling fluid flow;
Through the use of a Surface Controlled Downhole Safety Valve (DHSV)
fitted on all well; and
By high and low pressure trips resulting in automatic shutdown of the well.
Staff will have received standard industry well control training.
Loss of well control will be mitigated as far as practicable through controls applied during
the design of the well. The well has been engineered by Premier in accordance with
internal design policies and procedures in line with current best industry practices and then
reviewed and approved by the third party independent well examiner and the Health,
Safety and Environment (HSE) Inspectorate.
Premier has in place a call off contract with a Well Control company (Wild Well Control,
Inc.) for the provision of well control services. Wild Well Control, Inc. specialise in
controlling blow outs and provide services to aid the drilling of relief wells.
5.6.2.2 Topside Chemical and Hydrocarbon Release
There is a potential risk of unplanned discharge of production chemicals or hydrocarbon
release from the Solan platform. This could arise as a result of a misuse or technical
failure during transfer of chemicals between the supply vessel and the platform.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 75
Depending on the scale of the event, this could lead to a deterioration of the water quality
and toxicity to organisms in the water column.
The Solan platform has key preventative and mitigating measures in place which are
designed to prevent overboard discharge of pollutants or contaminated water to the sea to
meet the platform environmental standard of zero discharge to sea. The procedures in
place to minimise the risks of a chemical or hydrocarbon spill occurring are summarised
below.
Bunded areas and the drains system are provided in process and utility areas to control
the spread of chemical and hydrocarbon spillage across plated decks in the event of loss
of containment from pipework, vessels, tanks or relevant equipment and to provide
drainage from plant and equipment that contain hydrocarbon/ flammable fluid contents,
from washdown water or rainwater that may contain hydrocarbons and chemical storage
areas. By design, loss of containment in process areas will be routed to the open drains
system.
Sources for open drains include:
1) Bunded areas beneath equipment in hydrocarbon service. These are intended to collect
deluge water, washdown water, maintenance spillages, and possible leakage from
equipment. Bunded areas are provided where drainage flowrate is significant or where
deck plating is used for catching the spillage.
2) Drip trays beneath smaller equipment items such as pumps and filters, in water service.
These are intended to collect maintenance spillages. Some equipment items such as the
chemical injection package, generators, pumps, etc. may be provided with built-in drip
retention as part of the skid to contain any leaks or spills.
3) Bunded area at the chemical storage area on the weather deck
4) Deck drains for contaminated deck areas. These are intended to collect washdown
water, fire hose water and rain water.
5) Helideck drains. These will collect rainwater, deluge water, fire hose water and aviation
fuel spills.
Bunding is provided around vessels containing significant liquid inventories (such as the
inlet or second-stage separators).
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 76
This document details the management of chemicals on the Solan Platform, and complies
with the Premier Oil standard for ‘Compliance with Offshore Chemical regulations 2002 (as
amended). This procedure applies to all chemicals stored and used on the Solan offshore
platform. This procedure includes the chemical management relating to:
Small containers;
Drums, up to 200 litres;
Tote tanks;
Intermediate Bulk Containers (IBCs) up to 1,000 litres; and
Intermediate Bulk Containers (IBCs) over 1,000 litres;
The procedure provides information on:
Permitting;
Control of the chemicals on board the installation;
The correct methods to adopt when using the Installations chemicals;
Decanting of chemicals from the tote tanks and IBCs;
The use of various chemicals found on the Installation;
Chemical spillages and the process of reporting; and
Monitoring of the Solan Platform’s chemicals stock.
The potential for chemical spillages has been mitigated by having the facility of a
designated bunded lay-down area on the weather deck for the chemical tote tanks, short
length purpose-built chemical hoses/connections and hard piping to fixed storage tanks.
The probability of a chemical spill occurring is low and does not add significantly to the
overall risk of a spill in the area. Therefore it is not expected that there will be any
associated cumulative effects in the marine environment.
It is necessary that all types of hose on board the Solan Platform are recorded and
inspected on a regular basis to ensure the safety of personnel, and to ensure that the
equipment is well-maintained and fluid containment is assured.
This document aims to ensure that all hoses shipped out or manufactured for the Solan
are correctly tested before fitting and are accompanied with test certification, and that
hoses are safely used and maintained.
The procedure contains a Hose Management Register which details
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 77
The location and specifications of every tagged hose.
Fitness for service / condition assessment for every individual hose.
Schedule for the installation, inspection, and replacement of damaged
hoses and the replacement of all hoses coming to the end of their life cycle.
In the unlikely event of an oil spillage, the platform oil spill detection system will ensure
early detection and will minimize the potential impact of a spill.
The Solan Platform has a Rutter Sigma S6 Oil Spill Detection with Surveillance System
which uses two radar systems, with radar heads located at the SE and NW corners of the
platform, to detect oil spills within a 360° panorama of the surrounding area.
No operator configuration is required to acquire and track oil spill targets. The system will
automatically acquire all oil spill targets within a range of four nautical miles of the radar
installation.
Oil spills can be tracked, and information such as size and thickness of the spill will then
be used by the system to give a calculation which will estimate the spill volume. The Rutter
Sigma S6 provides a very high level of scrutiny in oil spill detection.
The MRV will also be available to check the sea surface during initial filling of the SOST
and offloading, and to report to the Control Room Operator if any oil is observed.
5.6.2.3 Diesel Spill during Bunkering
Spillages from bunkering of diesel fuel to the platform may potentially occur as a result of a
hose becoming disconnected or overfilling of the diesel bund.
Diesel is non-persistent oil that rapidly evaporates from the surface of the sea, and when it
is spilt on the sea surface it spreads rapidly and disperses to form a sheen on the sea
surface within hours of the release. This could have a potential environmental impact on
seabirds through damage to feathers.
Several measures are in place to minimise and prevent a small-scale hydrocarbon spill
during re-fuelling:
Bunkering of diesel fuel will only take place during daylight hours
Non-return connections and dead man closures will be used on bulk transfer hoses
All transfers will be controlled by written instruction with the operations
Supervisors and communication links tested prior to transfer.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 78
The bunkering operation will be monitored both by the supply boat and
onshore/offshore control rooms (and deck personnel during manned operation).
There will be a thorough inspection and maintenance regime on all refuelling
equipment.
All transfer operations will be suspended in rough weather
Spill kits will be available at strategic areas of the platform.
The MRV will also be available to check the sea surface during bunkering, and to report to
the Control Room Operator if any oil is observed.
Impacts from a diesel spill during bunkering are therefore expected to be low.
5.6.2.4 Oil Spill from the SOST
The SOST, and oil offloading systems, including the oil and water connections and the
loading base and loading hose, are designed to ensure no leakage of oil or ballast water to
the environment.
To assist with control of any potential spill, such as by damage caused to the SOST or
corrosion, the SOST and its associated facilities are designed to allow the ballast water
caisson level to be reduced below LAT to a sufficient level to ensure a slight internal
negative pressure relative to the sea, so that any leakage occurring will be of seawater
into the tank rather than of oil or ballast water out.
The SOST is designed to withstand multiple pressure cases including internal pressure
due to static pressure from the platform, a reduction in external pressure at the seabed
caused by the trough of the 100 year wave (a reduction of nominally 1 bar in external
pressure at the sea bed) and an external static differential pressure (excluding wave
loading) equivalent to drawing the water level in the ballast water caissons to 10m below
LAT.
The following SOST protection measures are also in place:
The SOST base is coated against under-deposit (and other) corrosion.
The SOST is affixed to the seabed with a suitable number, length and
distribution of piles to ensure its stability under all design environmental
conditions.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 79
The SOST and the OLS are provided with over-trawable with sloping sided
protection structure and anti-snag features to mitigate against accidental
damage.
The MRV will also be available to check the sea surface in the vicinity of the SOST and to
report to the Control Room Operator if any oil is observed.
5.6.2.5 Oil Spill during Oil Loading
There is a potential risk of a spill whilst loading hydrocarbons into the oil offload tanker.
There are several operations-specific control measures in place to mitigate against such
an incident, including:
Connection will only occur during daylight hours and in suitable weather
conditions;
Flow/pressure monitoring, alarms and observation from the shuttle tanker and
storage vessel to detect spills;
Telemetry to shut down oil export in an incident;
Self-sealing oil export hose;
Integrated dry-break valve in export line allowing emergency disconnection;
Regular checks of the integrity of the hose and cargo tanks will be carried out;
and
The MRV will be on site during oil offloading and has a spill detection system
on board which is the same as the system used on the Solan platform.
The impact of a hydrocarbon spill associated with the connection to the oil offload tanker
during oil loading would be significant and include a possible requirement for counter-
pollution resources on a national scale. However, the overall risk to the environment is low
when the mitigation measures discussed are taken into account.
5.6.2.6 Vessel Collision Risk
There is a potential for a vessel collision with the Solan platform. This could lead to a loss
of vessel inventory but accidents leading to the total loss of the vessel inventory are
extremely rare events.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 80
In the unlikely event of an accidental spill of diesel fuel from a vessel, a diesel slick would
form on the sea surface. Diesel is non-persistent oil that rapidly evaporates from the
surface of the sea, and when it is spilt on the sea surface it spreads rapidly and disperses
to form a sheen on the sea surface within hours of the release.
The platform complex will be surrounded by a 500 m safety exclusion zone. Shipping
routes are not permitted to travel close to the Solan platform, greatly reducing the potential
for vessel collision.
5.6.3 Oil Spill Modelling
The worst case hydrocarbon spill scenarios have been assessed as part of the Solan
Offshore OPEP (Premier Oil, 2014c). The OPEP presents the worst-case modelling
scenarios for the largest and most persistent hydrocarbon inventories.
Both stochastic and deterministic modelling has been undertaken using the SINTEF Oil
Spill Contingency and Response (OSCAR) modelling package. Solan crude is not
characterised within the OSCAR oil database, therefore for modelling illustration Maya
crude was used as an analogue to Solan crude.
Stochastic and deterministic modelling was carried out for the following scenarios: well
blowout from the production well P1, total inventory loss from the SOST, total inventory
loss from the largest shuttle tanker and diesel release. A summary of the parameters used
within the modelling and the results is presented below, with further detail provided in the
Solan Offshore OPEP (Premier Oil, 2014c). .
5.6.3.1 Well Blowout
Scenario 1a: Well Blowout: declining rate over 30 days. Initially at 4,020 m3 on day 1
declining to 893 m3 per day by day 30, towards Faroese median line (offshore). Scenario
1b: Well Blowout: declining rate over 30 days. Initially at 4,020 m3 on day 1 declining to
893 m3 per day by day 30, towards UK shoreline (onshore).
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 81
Results from the deterministic modelling indicate that a well blow-out over 30 days, without
response interventions, under the worst case conditions of a 30 knot onshore wind, would
beach on the Shetland coastline after 2 days, the Faroes coastline after 8 days and the
Norwegian coast after 12 days (Figure 5-9).
Figure 5-9 Well blowout: a) in the direction of the Faroes (left) and b) the UK (right)
5.6.3.2 Release of SOST Inventory
Scenario 2a: Subsea Tank Release: Instantaneous loss of 50,625 m3 of Solan crude,
towards Faroese median line (offshore).
Scenario 2b: Subsea Tank Release: Instantaneous loss of 50,625 m3 of Solan crude,
towards UK shoreline (onshore).
An instantaneous loss of the SOST inventory was modelled over 30 days, without
response interventions, under the worst case conditions of a 30 knot onshore wind. The
results indicate that shoreline oiling would occur on the coast of Shetland after 4 days and
the Faroes coastline after 6 days (Figure 5-10).
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 82
Figure 5-10 Loss of SOST inventory: a) in direction of the Faroes (left) and b) the UK (right)
5.6.3.3 Release of Offload Tanker Inventory
Scenario 3a: Offload Tanker Release: Loss of 121,700 m3 from all cargo oil tanks, 3,000
m3 of heavy fuel oil, and 600 m3
of diesel. Towards Faroese median line (offshore).
Scenario 3b: Offload Tanker Release: Loss of 121,700 m3 from all cargo oil tanks, 3,000
m3 of heavy fuel oil, and 600 m3
of diesel. Towards UK (onshore).
An instantaneous loss of the shuttle tanker inventory was modelled over 30 days, without
response interventions, under the worst case conditions of a 30 knot onshore wind. The
results indicate that shoreline oiling would occur on the coast of Shetland after 4 days, the
Faroes coastline after 7 days and the Norwegian coast after 16 days (Figure 5-11).
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 83
Figure 5-11 Loss of shuttle tanker inventory: a) in direction of the Faroes (left) and b) the UK (right)
5.6.3.4 Diesel Release
Scenario 4a: Diesel Release: 3,550 m3 instantaneous release from Solan field location.
Towards Faroese median line (offshore).
Scenario 4b: Diesel Release: 3,550 m3 instantaneous release from Solan field location.
Towards UK (onshore).
An instantaneous loss of marine diesel was modelled over 30 days, without response
interventions, under the worst case conditions of a 30 knot onshore wind. The results
indicate that shoreline oiling would occur on the coast of Shetland after 8 days and that
oiling is not expected elsewhere on the UK coastline or on the Norwegian coastline (Figure
5-12).
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 84
Figure 5-12 Loss of marine diesel: a) in direction of Faroes (left) and b) the UK (right)
5.6.4 Potential Impacts
A number of protected areas have been identified that have the potential to be impacted
as a result of an oil release to sea from Solan field operations. There are no offshore
protected areas in close proximity to the Solan development, the nearest being the Wyville
Thompson Ridge and Darwin Mounds located approximately 107 km and 110 km
respectively, west of the development and the Solan Bank Reef located approximately 158
km southwest of the development.
Stochastic modelling output for the worst case scenario of instantaneous release of
approximately 120,000 m3 of solan crude from the offload tanker suggested that, of these
offshore Sites of Community Interest (SCIs), only the Solan Bank Reef could be (<20 %
probability) impacted by a total loss of hydrocarbons from the shuttle tanker (Premier Oil,
2014a). In addition, the Pobie Bank SCI east of Shetland could also be impacted (<20 %).
There are no NCMPAs within the immediate vicinity of the Solan Development; however,
there are a number in close proximity: the Faroe Shetland Belt approximately 20 km to the
northeast, the Northeast Faroe Shetland Channel approximately 200 km north, the West
Shetland Shelf approximately 27 km south and the North West Orkney MPA approximately
50 km southeast of the Solan location (see Figure 4-6). The worst case stochastic
modelling outputs suggest that each of the MPAs listed may be impacted following a Tier 3
spill (up to 20 %).
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 85
There are no onshore protected areas within the immediate vicinity of the Solan
Development, the nearest being Foula, an island off the west coast of Shetland located
approximately 95 km to the east of the Solan Development location which is protected due
to the birds that inhabit the island (see Figure 4-6).
The potential risk to seabirds from oil and diesel pollution is through damage to feathers
resulting in loss of mobility, buoyancy, insulation and waterproofing. Birds may also be at
risk from toxicity through ingestion of hydrocarbons and may face starvation through
depletion of food sources. The birds most affected are those such as guillemots, razorbills
and puffins that spend large periods of time on the water, particularly during the moulting
season when they become flightless (DTI, 2001).
Major oil spills can result in direct mortality to marine mammals, although generally, they
are less vulnerable than seabirds to fouling by oil. Cetaceans have smooth hairless skin
over a thick layer of insulating blubber, so oil is unlikely to adhere persistently or cause
breakdown in insulation. However, they are at risk from chemicals evaporating from the
surface of an oil slick at sea, especially within the first few days. They may inhale vapours
given off by spilt oil, their eyes may be vulnerable to major pollution, and individuals may
drown as a result of associated symptoms. Neonatal (very young) seal pups are
particularly at risk from oil coming ashore. In addition, a major release of oil or diesel may
deplete marine mammals’ food sources (SMRU, 2008).
The impact that may be caused by a spill is dependent on the location of the spill, its size,
the properties of hydrocarbon or chemical that is spilt, the prevailing weather and
metocean conditions at the time of the spill, the sensitivities of environmental receptors
that could be impacted by the spill, and the success of the contingency plans.
Hydrocarbon spills have a detrimental effect on water quality and a resultant effect on
marine organisms, benthos, plankton, fish and shellfish, seabirds, conservation sites and
commercial fishing.
5.6.5 Oil Spill Response
The response resources range from the Field Support Vessel (FSV) on site with
dispersant (Tier 1 response) to Oil Spill Response Limited’s (OSRL) response capabilities
(Tier 2/3 response) and ultimately the activation of the National Contingency Plan. Premier
has access to specialist oil spill response services provided by OSRL. In the event of an
oil or diesel spill, there are three planned levels of response, depending on the size of the
spill:
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 86
Spill will be monitored and allowed to disperse naturally. If spill is relatively
small ‘prop washing’ may aid dissipation (Tier 1);
Air surveillance and dispersant spraying through OSRL (Tier 2); and
Clean-up equipment and specialist staff available through OSRL. (Tier 3).
These arrangements make realistic provision for immediately mitigating the effects of an
oil spill on the marine environment and in particular bird populations and fisheries
resources.
Premier has in place a call off contract with a Well Control company (Wild Well Control,
Inc.) for the provision of well control services. Wild Well Control, Inc. specialise in
controlling blow outs and provide services to aid the drilling of relief wells. As a member of
Offshore Pollution Liability Association Limited (OPOL), Premier can demonstrate financial
responsibility should there be the need to drill a relief well.
The Solan Offshore OPEP (Premier Oil, 2014c) provides full details of the response
procedures and techniques that will be used in the event of an accidental release of
hydrocarbons.
5.7 Waste
5.7.1 Potential Impacts
Waste will be generated during all phases of the Solan Development. Careful
consideration is given to minimising the amount of waste generated and controlling its
eventual disposal such that waste is only disposed of if it cannot be prevented, reclaimed
or recovered. The impacts of wastes associated with the Solan development were
assessed in the Solan Development ES (Chrysaor Ltd., 2009).
Waste will be generated from the oil offload tankers and support vessel which will be
present on site during production operations. Waste will also be generated by the
accommodation vessels present during commissioning activities. Some special waste is
expected for example empty chemical/oil containers, batteries etc. All waste will be
transferred onshore for recycling/disposal.
5.7.2 Mitigation Measures
Premier is committed to reducing waste production and to disposing of waste to landfill
only if cannot be prevented, reclaimed or recovered. The project HSE plan (AB-SO-SA-
PL-0005) and the individual vessel garbage management plans will be used throughout
the operations. These will identify the types of waste generated and management
procedures for each waste stream.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 87
Legal requirements will be adhered to including use of transfer/consignment notes, use of
registered waste carriers licensed disposal sites.
Premier’s vessel assurance process will include compliance with the project Waste
Management Plan. Vessel operators will be required to maintain a Waste Record Book
and submit monthly reports of waste sent to shore.
With the application of the above control measures, the impact of waste production will be
minimised; however, given the nature of some of the wastes likely to be produced e.g. oily
wastes from the vessels, the overall impact is considered to be minor.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 88
6 ENVIRONMENTAL MANAGEMENT
Effective health, safety, environmental and security (HSES) performance is a key objective
for Premier, equal to all other key business objectives. An integrated HSES Management
System has been established and maintained that achieves this by:
Leadership and Commitment
Providing strong and visible leadership and commitment in HSES performance.
Policy and Strategic Objectives
Setting policy and strategic objectives that support the commitment to compliance
with all relevant statutory legislation and continuous improvement and take due
account of industry codes and practices and any other requirements to which the
company subscribes.
Organisation, Resources & Documentation
Establishing and populating a fit for purpose organisational structure for the
effective management of HSES and fully defining the HSES responsibilities of each
function.
Appointing management representatives who are responsible for and have the
resources to implement this policy.
Ensuring that all employees and contractors have adequate HSES awareness,
skills and competence.
Selecting and managing contractors to ensure their HSES performance meets
Premiers requirements.
Maintaining appropriate HSES documentation.
Risk Evaluation and Management
Identifying health, safety, environmental and security risks to people, the local
biodiversity and physical assets arising from Premier operations.
Managing risks to levels that are as low as reasonably practicable in line with legal
and other obligations and the strategy for continual improvement.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 89
Planning
Ensuring that HSES critical facilities and equipment are fit for purpose and meet
defined HSES and reliability targets.
Controlling activities and operations through the use of documented procedures
and practices.
Managing changes in people, plant and processes to avoid adverse HSES
consequences.
Maintaining emergency preparedness to manage the response to mitigate the
effect of and facilitate recovery from unplanned events.
Monitoring and Implementation
Monitoring HSES performance to determine compliance and keeping records in
support of the HSES Management System.
Recording areas of non-compliance and addressing these through corrective
actions.
Open reporting and investigation of all HSES related incidents.
Audit and Review
Auditing and reviewing compliance with the HSES Policy and the adequacy of the
HSES Management System.
All documented policies, procedures and practices will be consistent with the HSES Policy
and with the requirements of the HSES Management System. It is the responsibility of
every employee to comply with these and to assist Premier in their implementation.
The Premier environmental management system is certified to the international standard
ISO14001, with surveillance audits carried out by an external party on a 6 monthly basis.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 90
7 CONCLUSIONS
The potential environmental impacts of the commissioning and operation of the Solan
complex have also been identified and assessed and the outcome is summarised in Table
7-1.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 91
Table 7-1 Impact Assessment Summary (Commissioning and Operation)
Potential Impact Assessment
Seabed disturbance
The long term presence of the Solan complex will result in the permanent
loss of sedimentary habitat during the lifetime of the SOST and
installation. There will also be temporary disturbance associated with the
mooring of the accommodation vessel (seabed footprint of 0.12 km2) and
the mooring of the drill rig (seabed footprint of 0.12 km2).
Noise
Noise caused by dynamic positioning of the flotel is not likely to have a
significant effect on the receiving environment and the likelihood of an
injury or disturbance offence to marine EPS is negligible.
Noise will be generated from operation of the platform; however, this will
have negligible impact underwater where there are sensitive receptors.
Atmospheric emissions
Emissions associated with the operational activities will comprise
approximately 0.19 % of UKCS offshore exploration and production
activities emissions in 2012, therefore the impact is considered to be
minor.
Emissions associated with the accommodation vessels will comprise
approximately 0.2 % of CO2 generated by UK domestic and international
shipping emissions in 2012, therefore the impact is considered to be
minor.
Marine discharges
During the first fill of the SOST, there is a requirement to discharge some
of the chemicals used during the installation phase. These discharges
have been risk assessed as part of the Chemical Permit SAT and it is
concluded that they are unlikely to have a significant impact on the
marine environment. There will be no routine discharge of chemicals
during the operational phase as all production chemicals will either be
exported with the hydrocarbons or will be re-injected downhole.
Accidental events
Premier has the appropriate mitigation measures and responses in place
to limit the likelihood and control any spills that may occur. The possibility
of hydrocarbon spills during production operations will be covered under
the Solan field OPEP.
Waste
The impact of waste production will be minimised via the Project HSE
Plan and vessel waste management plans; special waste may be
generated but quantities will be small therefore the impact is considered
to be minor.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 92
The Solan area is of relatively low importance in terms of commercial fishing and shipping.
These industries are not expected to be significantly impacted by the pipeline installation
commissioning, or production operations.
Spawning and nursery grounds of several commercially important fish species also fall
within Block 205/26. Localised disturbance to the seabed will occur due to the physical
presence of the infrastructure. Due to the area impacted (5,480 m2) and the rapid recovery
time of benthic communities, the impacts on the seabed are considered to be of low
magnitude, and of an overall negligible risk to the environment.
The phytoplankton community in the area is dominated by diatoms including Chaetoceros
species and Thalassiosira species, and dinoflagellates of the genus Ceratium, while in
terms of abundance the zooplankton communities are dominated by copepods in
particular Calanus species. Due to rapid doubling times, plankton are unlikely to be
significantly impacted by the small and temporary nature of these operations. Benthic
species are typical of communities of the Boreal province extending south to the North
Sea. Crustaceans (Pagarus sp.), annelids (Lanice conchilega, Ditrupa arietina,
Pomatoceros sp.), cnidarians, molluscs, dogfish and flatfish are commonly recorded.
During commissioning and normal operations of the platform noise will have a negligible
impact. Noise caused by dynamic positioning of the flotel and vessels associated with the
hook-up and commissioning activities is not likely to have a significant effect on the
receiving environment and the likelihood of an injury or disturbance offence to marine EPS
is negligible.
The CO2 emissions from the accommodation vessel associated with commissioning
operations comprise around 0.2 % of the total UK domestic and international shipping CO2
emissions in 2012. There may be a small localised impact on local air quality in the vicinity
of the vessels but due to the high dispersive conditions in the area impacts are expected
to be negligible. The CO2 emissions associated with production operations comprise
around 0.19 % of UKCS offshore exploration and production activities emissions in 2012,
therefore the impact is considered to be minor.
Chemical use and discharge relating to the proposed operations has been assessed for
potential environmental impacts using both quantitative and qualitative approaches and it
is concluded that the proposed chemical use and discharge will not constitute a significant
risk to the environment.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 93
Accidental spills of hydrocarbons and chemicals are recognised as potentially damaging to
the environment. The history of the oil and gas industry shows that the accidental events
which could cause large-scale spillage of oil are rare. Although unlikely, an accidental loss
of containment from the Solan facilities or a vessel collision is possible during installation
and operation. A number of mitigation measures are in place to lower the likelihood of an
incident. An approved Oil Pollution Emergency Plan is also in place, which meets the
requirements of relevant legislation and guidance.
Transboundary impacts from emissions, discharges and accidental releases were
assessed. The Solan facilities are located approximately 55 km from the UK/Faroes
median line, therefore there is unlikely to be a potential for trans-boundary transport of
atmospheric contaminants.
The release of a worst case well blow-out release of crude oil would be likely to have a
transboundary impact. However, due to the spill prevention and response procedures in
place, the likelihood of a significant spill event occurring is considered very low. Any
transboundary incident will be managed through the Solan Field OPEP (Premier Oil,
2014c).
Premier has examined the environmental sensitivities of the Solan area in this EIA
Justification MAT submission and considered the significance of impacts during the
proposed time of operations. It is concluded that the procedures in place during proposed
activities will minimise the environmental impact of the operations. As such, the execution
of the Solan Development, incorporating the procedures identified in the EIA Justification
MAT, is not expected to have a significant impact on the environment.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 94
8 REFERENCES
Chrysaor Ltd. (2009). Solan Development Environmental Statement. Revision 06. DECC
Ref: W/4031/2008.
Coull, K.A., Johnstone, R. and Rogers, S.I. (1998). Fisheries sensitivity maps in British
waters. UKOOA Ltd.
Department for Transport (DFT) (2014). https://www.gov.uk/government/statistical-data-
sets/env02-greenhouse-gas-emissions (Accessed on 26/05/14).
Dernie, K.M., Kaiser, M.J., and Warwick, R.M. (2003). Recovery rates of benthic
communities following physical disturbance. Journal of Animal Ecology. 72: 1043-1056.
DTI (Department of Trade and Industry) (2001). Report to the Department of Trade and
Industry. Strategic Environmental Assessment of the mature areas of the offshore North
Sea – SEA 2. Consultation Document, September 2001.
DTI (Department of Trade and Industry). (2003). Strategic Environmental Assessment of
the Mature Area North and West of Orkney and Shetland. Prepared for the Department for
Business Enterprise and Regulatory Reform. Consultation Document.
EC (2007). Interpretation Manual of European Union Habitats. Available at
http://ec.europa.eu/environment/nature/legislation/habitatsdirective/docs/2007_07_im.pdf
(accessed March 2014).
EEMS. (2012). EEMS-Atmospheric Emissions Calculations.
Ellis J.R, Milligan S.P., Readdy L., Taylor N., and Brown M.J. (2012) Spawning and nursery
grounds of selected fish species in UK waters. CEFAS Technical Report 147.
Erbe, C., McCauley, R. McPherson, C. and Gavrilov, A. (2013). Underwater noise from
offshore oil production vessels. JASA Express Letters. 133(6).
Floatel International. (2015). Information sheet for the Floatel Superior. Available at:
http://www.floatel.se/filer/Floatel__Superior_Data_Sheet_.pdf.
Gardline. (1991). Survey Report Proposed Drilling Sites UKCS 201/30a & 205/26a May to
June 1991. Ref 3485.
Gardline. (2008). Senergy Floyds on Behalf of Chrysaor UKCS 205/26a. Solan SL4 Rig
Site and Environmental Survey, Survey Report, April/May 2008. Ref 7599.
JNCC (1999). Seabird vulnerability in UK waters: Block Specific Vulnerability.
JNCC (1999). Seabird vulnerability in UK waters: Block Specific
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 95
JNCC (2010). The protection of marine European Protected Species from injury and
disturbance. Guidance for the marine area in England and Wales and the UK offshore
marine area. Draft June 2010.
JNCC (2013). Consultation on possible Nature Conservation Marine Protected Areas in
Scotland’s Seas. Available at: http://jncc.defra.gov.uk/scottish-mpa-consultation, accessed
April 2014.
Johns, D. and Wooton, M. (2003). Plankton Report for Strategic Environmental Assessment
Area 4. SAHFOS, Plymouth Marine Laboratory.
McQuatters-Gollop, A., Edwards, M., Reid, P.C. and Johns, D. (2010). Healthy &
Biologically Diverse Seas Evidence Group Technical Report Series: Evaluation and gap
analysis of current and potential indicators for Plankton.Information Centre, Norway.
Nedwell, J. R. and Edwards, B. (2004). A review of measurements of underwater man-
made noise carried out by Subacoustech Ltd, 1993-2003. Subacoustech Report ref:
534R0109. 29 September 2004.
PhysE (2009). Metocean Design Criteria, Solan Field 60.06°N, 3.97°W (West of Shetland).
Volume 1: Engineering Reference Document. Report Reference: C196_07-R280-7F (Vol.
1)
Pinnegar, J.K., Cheung, W.W.L. and Heath, M. (2010). Fisheries. MCCIP Annual Report
Card 2010-2011, MCCIP Science Review. Lowestoft, UK: MCCIP. Available from
http://www.mccip.org.uk/arc ,accessed October 2010.
Premier Oil (2014a). Solan ES Addendum. DECC reference W/4031/2008.
Premier Oil (2014b). Solan Development Wells OPEP. DECC reference 1864.
Premier Oil (2014c). Solan Field OPEP. DECC reference 2142.
Premier Oil (2014d). Solan Field Offshore OPEP Annex 1. DECC reference 2174.
Premier Oil (2015). Solan Field Offshore OPEP Annex 2. DECC reference 2212.
Prosafe (2015). Flotel Regalia information sheet. Available at:
http://www.prosafe.com/regalia/category137.html
Rees, H. L., Eggleton, J. D., Rachor, E. and Vanden Berghe, E. (2007). Structure and
dynamics of the North Sea benthos. ICES Cooperative Research Report No. 288.
Reid, J.B., Evans, P.G.H. and Northridge, S.P. (Eds.) (2003). Atlas of cetacean distribution
in north-west European waters. JNCC, Peterborough.
Richardson, W.J., Greene, C.R., Malme, C.I. and Thomson, D.H. (1995). Marine Mammals
and Noise. Academic Press.
Production MAT Direction for Commissioning and Operation
AB-SO-SE-RA-0015
North Sea Rev B19, November 2015 Page 96
Ross, D. (1976). Mechanics of underwater noise. Pergamon, New York. 375 pp.
Scottish Government (2011). Consultation on seal haul out sites. Available at:
http://www.scotland.gov.uk/Publications/2011/03/22093944/8, (Accessed January 2014).
Scottish Government. (2013). Fishing Effort and Quantity and Value of Landings by ICES
Rectangle. Available at: http://www.scotland.gov.uk/topics/statistics/browse/agriculture-
fisheries/rectangledata (Accessed March 2014).
Scottish Government NMPI website. National Marine Plan Interactive. Available at:
http://www.scotland.gov.uk/Topics/marine/seamanagement/nmpihome/nmpi, accessed
March 2014.
Siem Offshore. (2014). Siem Spearfish – Offshore Subsea Construction Vessel Information
sheet.
SMRU. (2008). SCANS-II. Small cetaceans in the European Atlantic and North Sea. Final
Report to the European Commission under project LIFE04NAT/GB/000245. Available from
SMRU, Gatty Marine Laboratory, University of St Andrews, St Andrews, Fife.
Southall, B. L., Bowles, A. E., Ellison, W. T., Finneran, J. J., Gentry, R. L., Greene, C. R.
Jr., Kastak, D., Ketten, D. R., Miller, J. H., Nachtigall, P. E., Richardson, W. J., Thomas, J.
A. and Tyack, P. L. (2007). Marine mammals noise exposure criteria: initial scientific
recommendations. Marine Mammals. 33(4).
Stone, C.J., Webb, A., Barton, C., Ratcliffe, N., Reed, T.C. and Tasker, M.L. (1995). An
Atlas of Seabird Distribution in North-West European Waters. Peterborough: JNCC.
Theobald, P. D., Lepper, P. A., Robinson, S. P. and Hazelwood, R. D. (2009). Cumulative
noise exposure assessment for marine using sound exposure level as a metric. IN:
Proceedings of the 3rd International Conference Underwater Acoustic Measurement:
Technologies & Results (UAM2009), 21 - 26 June 2009, Nafplion, Greece.
The Institute of Petroleum (2000). Guidelines for the calculation of estimates of energy use
and gaseous emissions in the decommissioning of offshore structures.
Wales, S. C. and Heitmeyer, R. M. (2002). An ensemble source spectra model for
merchant ship-radiated noise. Journal of the Acoustical Society of America. 111: 1211-
1231.
Williams, J.M., Tasker, M.L., Cater, I.C. and Webb, A. (1994). A Method of Assessing
Seabird Vulnerability to Surface Pollutants. Seabird and Cetaceans Branch JNCC