Date post: | 29-Mar-2015 |
Category: |
Documents |
Upload: | savanna-getson |
View: | 212 times |
Download: | 0 times |
Solar Photovoltaic Power Stations
Fully Commissioned in MonthsPhased-In Generation Within One
Month99%+ AvailabilityOffset Substation and Feeder
Expansion CostsImprove Remote Power QualityVirtually Eliminate Transmission
& Distribution LossesNo Fuel Costs or Handling
Solar Photovoltaic Power Stations
Minimal or No Earth Work
Rapid Installation / Startup
No Process Water Required
No Air or Water Emissions
No Avian Mortality Issues
No Fuel Price Risk No Moving Parts No Noise Expandable Moveable
Construction & Operation Benefits
Require few spare parts
Require less exotic skills
Safer repair with easy access
Partial generation during repair
Quick repair No special repair
equipment
Technical Availability
Source: NERC; T. Casten
0%
10%20%
30%40%
50%60%
70%80%
90%100%
Pho
tovo
ltaic
s
Bac
kpre
ssur
e Tu
rbin
esW
indp
ower
Fuel
Cel
ls
Trig
en S
yste
ms
Hyd
ropo
wer
Gas
Tur
bine
s
Com
bine
d C
ycle
Foss
il Fu
eled
Nuc
lear
99%+ Availability
➥ Fewer Forced and Planned Outages
On a 10 MW substation load, 500 kW of PV can reduce transformer temperature 4oC and boost transformer capacity by 410 kW.
Substation Benefits
Locatable anywhere on circuit
Circuit generation avoids system losses
Feeder circuit peaks typically sharper
Lowers transformer temperature
PV can shade transformers Lengthens life of
transformers
Assist Substation Peak Load
Avoid T&D Losses and Expenses
Transmission & Distribution Benefits
Distribution - 95% of outages & quality problems
PV output peaks as line losses increase Distributed PV improves grid stability Greater than 99% power factor
Electricity Lost (% of U.S. Generation)
0%
1%
2%
3%
4%
5%
6%
7%
8%
9%
10%
1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000
Edison Electric Institute
U.S. Energy InformationAdministration
20+ households = smooth load curve.
Displace Grid Extension Costs
Village Power
Power for those not- or under-electrified.
Local sustainable employment.
Midday power available for local
economic development.
Peak power available for
storage and low night demand.
System Configuration
Support Structure •Ground Mount
•Parking / Shade Cover
PV Array
•Flat or Sloped Roof Mount
•Building Integrated
Combiner Box
DCDisconnect
ACDisconnect
Step-up / Isolation
Transformer(s)
Inverter(s) •Sub-
Array•String
Power Management Unit Add-On for:•Backup Power: battery, flywheel, other•Hybrid Generation: wind, generator, other
Grid Power
Off GridVillage Power
Weather
Station
Monitoring
Project Experience
Springerville Generating Station
Springerville, Arizona USA
2.4 MW DC Crystalline, Amorphous
& CdTe Modules Grid-Tied 3-Phase, 34.5 kV 18 150kW Inverters
Commissioned:•1.4 MW - November
2001•1.0 MW - September
2002
Tucson, Arizona USA
43.2 kW
Crystalline Modules
Grid-Tied
3-Phase, 480 V
Two 20 kW InvertersCommissioned
August 2002
City of Tucson Water
Tucson, Arizona USA
216 kW DC
Crystalline Modules
Grid-Tied
3-Phase, 13.8 kV
Two 100 kW Inverters
Commissioned January 2001
DeMoss Petrie Power Station
Tucson, Arizona USA
43.2 kW
Crystalline Modules
Grid-Tied
3-Phase, 13.8 kV
Two 20 kW Inverters
Commissioned September 2000
Irvington Road Power Station
Punjab, India
50 kW DC
Crystalline Modules
Grid-Tied
50 Hz
50 kW Inverter
Commissioned 1999
Bajak Village Power Station
Roseville Fire Station
Roseville, California USA
21.6 kW DC
Crystalline Modules
Grid-Tied
Single-Phase, 240V
Nine 2.5kW String Inverters
Start: August 2002Finish: October 2002
Lodi Station Parking Cover
Lodi, California USA
23.9 kW DC
Crystalline Modules
Grid-Tied
Single-Phase, 240V
Nine 2.5kW String Inverters
Start: October 2002Finish: December 2002
Scott Kaminky, Director of Business Development
GLOBAL SOLAR ENERGY, INC.13075 North Dixon Drive
Parker, Colorado 80138-8727
1.303.583.7252fax 1.303.583.7253cell 1.720.480.7311
e-mail [email protected]