Date post: | 29-Dec-2015 |
Category: |
Documents |
Upload: | virginia-moody |
View: | 214 times |
Download: | 0 times |
Solar Probe PlusA NASA Mission to Touch the Sun
SPP EVMS and
Science Investigation Team Participation
Howard Hunter11/15/12
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012
Agenda
EVMS Implementation on SPP CAM Responsibility Project Manager (PM) Involvement
Monthly EV Feedback Monthly EV Workflow Cycle Integrated Baseline Review JHU/APL EVMS Architecture Science Investigation Team (SIT) Participation
Illustrative Trace Example Science Investigation Team EVM Challenges EVMS Going Forward
2
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012
EVMS Implementation on SPP
Using Microsoft Project 2010Transitioning to a Project Server EnvironmentEVM Pilot ProgramStart March 2013Ramp up for 12 months prior to KDP-C
3
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012
CAM Responsibility for EVM
Integrated point of responsibility – Organizational Breakdown Structure & Work Breakdown Structure intersection
Establish and maintain the schedule and budget (Budgeted Cost for Work Scheduled — BCWS)
Report performance / assess earned value (Budget Cost for Work Performed — BCWP)
Monitor all costs charged to the control account (Actual Cost of Work Performed — ACWP)
Generate an Estimate at Completion (EAC) quarterly via Op Plan update
Perform variance analysis Develop and implement corrective action(s), as required
4
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012
Project Manager Involvement in the EVMS
Project Manager PM is the single point of integrated responsibility for technical,
schedule and cost performance EVMS provides PM with a consistent, standard framework for
assessing project performance EVMS provides PM a sound program management tool that
generates data in a format enabling management by exception EVMS provides the PM with early detection of problems, enabling
the PM to understand the potential cost and schedule impact of a problem(s) and be able to correct the problem(s) prior to it becoming a major issue
PM responsible for review, acceptance and sign-off of the Operating Plan and Variance Analysis Reports
PM signs off on final monthly EV data submittal to sponsor
5
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012
Monthly EV Feedback
Schedule status update Negative slack or potential project impacts will be discussed
immediately with the CAM and PM Reporting threshold at Control Account level
Thresholds set for SV and/or CV at $25k +/- current, $50k +/- cumulative, $100k +/- VAC
If the CAM is unable to explain the reason for a variance, the CAM and/or Science Investigation Team will be asked to participate in the explanation process
Cause, Impact, Corrective Action Contract Performance Reporting
Monthly review to be held with sponsor
6
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012
Monthly EV Workflow Cycle
Week 1 Cutoff for Cost & Schedule Baseline as well as WBS & WBS Dictionary changes; MS Project
schedules statused including final BCW”P”; preliminary accounting data available
Science Investigation Team schedule updated and forwarded to JHU/APL monthly (by the 5th calendar day of the month)
Week 2 First run of EV data. Contract Performance Reports delivered internally. Estimated actuals due
(based on SUBC preliminary accounting data). Queries run on schedule and cost data. Initial analysis completed. Op Plan delivered to CAM. Identify required VAR
Science Investigation Team estimated actuals report at WBS level submitted by 10th business day
of the month
Week 3 Project teams prepare and review VAR. Review final CPR and VAR with JHU/APL CAM
Science Investigation Team participate in VAR process - called in on an exception basis Week 4 JHU/APL reporting to sponsor delivered electronically
7
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012
Integrated Baseline Review
Demonstrate an adequate baseline at the Mission level Assure the technical content of SPP defined work is consistent with the
Statement of Work Demonstrate the relationship of planned effort with the IMS
Cost and schedule integration Assess the sufficiency and time-phasing of resource budgets Assure that objective meaningful earned value methods are used
Documentation Responsibility Assignment Matrix (RAM) Integrated Master Schedule (IMS - master through detail) Control Account Plan (CAP) Work Breakdown Structure (WBS)/WBS Dictionary Project Management Control System for the EVMS
Assure the identification of significant technical, schedule and cost risks
All Subsystems and Science Investigation Teams involved8
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012
Proposed EVMS Architecture
Cobra
ACWPBCWS
wInsightDataWarehouse
BCWP
RMIS
VE – ERP SystemSimplified collaborative multi-user environment
Integration with Manufacturing
Resource Planning System
EVMS Architecture Upgrade
9
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012
Science Investigation Team Participation
Capable of working with JHU/APL to meet the intent of the guidelines Define the authorized work elements (WBS) for the project Develop a schedule that reflects the key contractual requirements, significant decision points and key
milestones Provide a logical link from where the work is being performed to project level (vertical dependencies) Provide for identification of product-oriented interdependencies supporting contractual effort
(horizontal dependencies) Maintain a time-phased budget baseline – Performance Measurement Baseline (PMB)
Establish a project baseline summary of the time-phased budgets for all control accounts plus applicable indirect budgets
Record direct costs in a manner consistent with the budgets Ensure accumulation of costs is consistent with the way the work is planned and budgeted in the EVMS
Provide JHU/APL a monthly estimated actuals report Actuals – 533 Estimated Actuals – for work completed but not yet hitting the ledger
Provide JHU/APL with a Milestone Schedule (IMS) The establishment of the IMS and weighted M/S allows JHU/APL to have the ability to accurately
measure performance (Budgeted Cost of Work Performed – BCWP) JHU/APL and the Science Investigation Teams have worked together to determine the proper level of
granularity for the establishment of these milestones Work with the CAM to provide a Variance Analysis Report (VAR) for any cost, schedule or at completion
variance exceeding the established variance thresholds
10
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012 11
Science Investigation Team EVM Process Flow
Prime ContractNNN06AA01C
SubcontractSOW & CDRL
Requirements Flow-down
Matrix
Cost & Schedule Reporting
WBS Detailed
Schedule & Cost Plan
Development
WeightedMilestones
BaselinedCost &
Schedule
ScheduleUpdates
EVM & 533Reports
EV Report& Analysis
EV DataProcessing
Requirements
Management
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012 12
Key Delivery Dates
MS003 Detailed Schedules
001C Updates X Monthly5th calendar day
of monthX X X X
MS005 Financial Mgmt Rpts
001 533M X Monthly 15th of month X X X X X
002 533Q X Quarterly 15th of month X X X X X
003EVM Reports (EA and EAC per WBS)
X Monthly10th business day of month
X X X
004Baseline Change Request
AAs
RequiredAs generated X X X
Subcontract Data Requirements List SPP PROJECT
REV ADATED 6/17/11
DID NO.
ITEM NO
TITLE OR DESCRIPTION OF
DATAAPPR
FREQOF ISSUE
DATE DUE TO APL
PROJECT PHASES
MatrixA B C D E
12
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012
Monthly Estimated Actuals Report
13
Work Completed Work Remaining Total Work
Note 1 Note 2 Note 3 Note 4 Note 5
WBS Description EV Type
Phase B Budgeted
Cost
Actual Cost to Date (E)
Accrued Cost(F)
Total Estimated Cost to Date
(E+F)
Estimate to Complete [ETC]
(H)
Estimate at Completion [EAC]
(G+H) 22* Instrument X
221 Technical Management LOE $ 250,000 25000 4000 29000 $ 230,000 $ 259,000
222 System Engineering LOE $ 200,000 22000 22000 $ 170,000 $ 192,000
223 Science LOE $ 250,000 12000 4000 16000 $ 240,000 $ 256,000
224 Performance Assurance LOE $ 200,000 10000 10000 $ 125,000 $ 135,000
Hardware Development
22A DPU NRE/EM WMS $ 600,000 60000 60000 $ 575,000 $ 635,000
22B LVPS NRE/EM WMS $ 500,000 55000 55000 $ 465,000 $ 520,000
22C Harness WMS $ 300,000 10000 10000 $ 350,000 $ 360,000
22D Sensor WMS $ 400,000 50000 12000 62000 $ 350,000 $ 412,000
22E Hardare Procurements WMS $ 400,000 30000 7500 37500 $ 380,000 $ 417,500
GSE
22B EGSE NRE/EM WMS $ 100,000 10000 5000 15000 $ 75,000 $ 90,000
225 I&T LOE $ - 0 $ - $ -
422 Spacecraft I&T Support LOE $ - 0 $ - $ -
522 Launch Checkout and Early Orbital Ops LOE $ - 0 $ - $ -
622 Pre Launch Science Support LOE $ - 0 $ - $ -
842 Post Launch Science Support LOE $ - 0 $ - $ -
872 Instrument Ops LOE $ - 0 $ - $ -
Total Phase B $ 3,200,000 $ 284,000 $ 32,500 $ 316,500 $ 2,960,000 $ 3,276,500
Note 1 - Cumulative actual costs expensed in General Ledger through current reporting period (even though the General Ledger may be behind)
Note 2 - An expense that has occurred but the transaction has not been entered in the accounting records
Note 3 - Total of cumulative actuals plus total accrued costs
Note 4 - The expected cost needed to complete all of the remaining work for a control account whether the expected costs have been budgeted or not
Note 5 - Total estimated cost to date plus estimated cost to complete
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012 14
“EV Capable” – Goal for Science Investigation Team
Capable of working with JHU/APL to meet the intent of the guidelines
Define the authorized work elements for the project (WBS) Schedule that reflects the key contractual requirements,
significant decision points and key milestones– Logical link from where the work is being performed to project level
(vertical dependencies)– Provide for identification of product oriented interdependencies
supporting contractual effort (horizontal dependencies) Maintain a time phased budget baseline - PMB
– Project baseline summary of the time phased budgets for all control accounts plus applicable indirect budgets
Record direct costs in a manner consistent with the budgets– Accumulation of costs is consistent with the way the work is planned
and budgeted in the EVMS
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012 15
Budget Allocation
Budget flows from the Contract Task Order Award into the project CTC and ultimately, its Control Accounts
The Project Manager identifies any Management Reserve, which is held at the Project level
The CAM budget is recorded in the WSA The CAM’s and Project Manager’s signatures on the WSA reflect
its nature as an “internal contract”— a commitment by the PM to provide that much support, and by the CAM to do the work for that amount
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012 16
Work Planning and Resource Allocation
The CA work is further detailed into Work Packages Work Packages are then defined by Subcontractors’ resources
Labor Materials/Procurements Other Direct Charges (ODCs) Travel
The Activities are assigned an EV type according to the type of work, duration, and the way it can be measured. Discrete methods are used wherever possible
Consistent with the SOW, a bottom-up BOE was developed based on the technical understanding of the work. A resource estimate was developed to include: Labor resources allocated by month ODCs time-phased
Subcontracts/subcontractors are identified and incorporated through established JHU/APL processes
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012 17
APL Process IllustrationTrace Account Discussion
Control Account 3.7.U – PRIO Development and Flight ASICS
(Power Remote Input Output ASIC chip)
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012 18
Process Overview Planning
WBS Work Definition/WBS Dictionary Baseline Schedule Budget Allocation RAM Work Planning & Resource Allocation Resource Allocation Baseline Control – BCR, Log, Schedule update Performance Measurement
Execution Cost Performance Reporting Variance Analysis and Corrective Action Planning
Review Management Review
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012 19
WBS
WBSNASA WBS Description CAM Group(s)
37H - 37U 06 Avionics Subsystem (PDU) Nichols SEC, SEE, SEI, SEM, SRI, TEA, TEO, TEQ, V IA
37H 06 PDU BB/EM Command/Telemetry Slice (Design, Manuf.,Test) SEE, TEO, TEQ37J 06 PDU BB/EM Power Switching Slice (Design, Manuf., Test) SEC, SEE, TEA, TEO,
TEQ37K 06 PDU BB/EM Capacitor/Relay Slice (Design, Manuf., Test) SEC, SEE, TEO, TEQ37L 06 PDU EM Fuse Modules (Design, Manuf., Test) SEE, TEO, TEQ37Q 06 PDU EM Development (Design, Manuf., Test) SEC, SEE, SEM, TEO,
TEQ37R 06 PDU FM Development (Slice & Box Manuf. Assy & Test) SEE, TEA, TEO, TEQ37T 06 PDU Test Equipment and GSE SEE, SEI, TEA, TEO,
TEQ, VIA37U 06 PRIO Development and Flight ASICs SEC, SEE, SRI, TEA
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012 20
Work Definition/WBS Dictionary
WBS NASA WBSWBS
Mapping Description WBS Definition37U 06 2.6.10 PRIO Development and Flight ASICs Procure the flight Power Remote Input-Output (PRIO) ASICs.
Includes subcontract cost (NRE and recurring), design review with NASA, update of procurement documents and test vectors (preliminary developed in Phase A), vendor selection and negotiation, and PRIO project engineering, including subcontract monitoring.
WBS Dictionary: A companion document to the WBS that describes the scope for each and every WBS element. The WBS Dictionary covers the entire scope of the project including management and support activities performed as part of the project.
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012 21
3.7.U Control Account Schedule - Baseline
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012 22
APL Responsibility Assignment Matrix
$$ Amount Thru Cost A
. San
to
N. F
ox
D. E
ng
J. V
onM
ehle
m
K. C
oope
r
L. S
uthe
r
R. C
onde
G. H
eyle
r
R. P
eris
on
J. T
roll
R. V
augh
an
M. B
utle
r
V. B
aile
y
B. W
illia
ms
D. S
riniv
asan
G. O
ttman
R. N
icho
ls
M. R
eid
371 Avionics Lead Engineering & Management $340,067 X372 IEM BB/EM GIIF Card - G&C and Instrument Interface Card (Design, Manuf.,Test) $931,980 X377 IEM BB/EM SCIF Card- Spacecraft Interface Card (Design, Manuf. & Test) $99,419 X378 IEM BB/EM Chassis (Design, Manuf.) $143,757 X379 IEM BB/EM Box Development (Design, Assembly, Integration, Test) $322,073 X37C IEM BB/EM/FM Procurement Contract Support (e.g. Processor, SSR, DC/DC Conv., OCXO) $2,534,401 X37E Spacecraft and IEM Test Equipment and GSE (Testbeds, Box and Board GSE) $954,291 X37G PDU Lead Engineering & Management $405,686 X37H PDU BB/EM Command/Telemetry Slice (Design, Manuf.,Test) $518,234 X37J PDU BB/EM Power Switching Slice (Design, Manuf., Test) $232,699 X37K PDU BB/EM Capacitor/Relay Slice (Design, Manuf., Test) $312,092 X37L PDU EM Fuse Modules (Design, Manuf., Test) $65,372 X37Q PDU EM Development (Design, Manuf., Test) $724,195 X37R PDU FM Development (Slice & Box Manuf. Assy & Test) $3,087 X37T PDU Test Equipment and GSE $1,192,096 X37U PRIO Development and Flight ASICs $978,257 X37W TRIO/VRIO BB/EM Development (Design, Manuf., Test, and GSE) $142,579 X
Work Breakdown Structure (WBS)
Organizational BreakdownStructure (OBS)
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012 23
Work Statement Authorization Document (WSA)
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012 24
Baseline Change Request Form
Budget
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012 25
Baseline Change Request Form
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012 26
3.7.U Control Account Schedule (Updated)
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012 27
Control Account Plan (CAP)
Program: Description: Approval:IYL01PHB RBSP Phase B Program ManagerRun Date: Status Date: Functional Manager8/6/2008 9:28 6/30/2008 Cost Account Manager
CAM WBS[4] Apr-08 May-08 J un-08 J ul-08 Aug-08 Sep-08 Oct-08 Nov-08 Dec-08 CumulativeNICHOLS
1.3.7.G PDU Lead Engineering & Management BCWS 42,799 54,641 53,927 40,914 39,299 41,183 46,493 36,192 50,239 405,6861.3.7.H PDU BB/EM Command/Telemetry Slice (Design, Manuf.,Test) BCWS 66,240 59,440 62,447 56,363 47,372 52,489 66,666 51,620 55,599 518,2341.3.7.J PDU BB/EM Power Switching Slice (Design, Manuf., Test) BCWS 33,494 29,733 25,271 20,465 14,730 19,237 27,109 32,936 29,723 232,6991.3.7.K PDU BB/EM Capacitor/Relay Slice (Design, Manuf., Test) BCWS 30,053 37,118 31,546 44,947 35,440 31,385 33,444 30,972 37,186 312,0921.3.7.L PDU EM Fuse Modules (Design, Manuf., Test) BCWS 3,588 3,453 3,408 3,430 10,134 12,340 8,782 6,894 13,343 65,3721.3.7.Q PDU EM Development (Design, Manuf., Test) BCWS 83,650 70,899 79,807 84,527 82,856 74,454 96,074 74,956 76,973 724,1951.3.7.R PDU FM Development (Slice & Box Manuf. Assy & Test) BCWS 0 0 0 0 0 0 0 0 3,087 3,0871.3.7.T PDU Test Equipment and GSE BCWS 157,290 117,877 134,075 131,421 133,987 157,052 165,631 102,655 92,108 1,192,0961.3.7.U PRIO Development and Flight ASICs BCWS 182,937 -60,702 42,811 131,634 17,903 99,100 21,188 31,928 17,255 484,054
CAM Totals: BCWS 600,051 312,459 433,292 513,701 381,721 487,240 465,386 368,153 375,513 3,937,516
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012 28
3.7.U LABR Control Account Schedule Status (through 6/30)
Weighted Tasks
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012 29
3.7.U LABR Control Account Schedule Status (through 6/30)
Schedule Status
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012 30
3.7.U LABR Control Account Schedule Status (through 6/30)
Earned % = 30.36%
BCWP = 30.36% x $206,784 = $62,780 for Labor
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012 31
Variance Analysis Report (VAR)
Required when CV,SV, or VAC exceed variance thresholds
Required at the Control Account level, can be done at higher levels
Memo for the record
Not cheap when done properly
More expensive when done poorly
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012 32
Science Investigation Team EVM Challenges
Start-up hurdles Understanding the capabilities of the financial system at each
institution Learning curve for each institution and their major
subcontractors Setting up weighted milestones that are appropriate for each
team which provide enough insight to produce useful EV data Short turn-around time for processing and analyzing data Procurements lag time into the system Invoicing lag time
Solar Probe PlusA NASA Mission to Touch the Sun
APL Proprietary November 15, 2012
EVMS - Going Forward
Continue working on implementation for SPP. Current efforts include: Setting up control logs (CBB, MR, UB & BCR form) Working with Instrument Providers to set up IMS, weighted M/S, Est.
Actuals Meeting with Instrument Providers at their facilities
Finishing the IMS for Phase B Initiate workshop-type formats for CAM training Training Group Supervisors and CAMs Setting up VAR workshops
Finalize testing of subcontractor and material performance methodology
33