Solar PV Integration via
LCC HVDC
Transmission
Expansion
August 24, 2020
Bruno Leonardi, EPRI
Alberto Del Rosso, EPRI
Jonathan Ruddy, EPRI
R&D Approach
R&D Goal
PROGRAM
PROJECT
TASK FORCE
EPRI program P40.24-B: HVDC Transmission
Planning
• Increase planner’s knowledge on integration of HVDC technology
• Provide systematic approach, methods and tools for planning transmission expansions with HVDC
• Maintain knowledge base that can quickly be leveraged to support utility members through HVDC projects
• Complete HVDC planning case study in the Southwest Power Pool area
• Update HVDC Planning Guide
• Investigate technical performance issues with the integration of HVDC projects:
• 2019 will focus on sub-synchronous oscillations with increase of inverter-based resources
• [Tech Update] HVDC Planning Guide –2019 Edition
• [Tech Update] HVDC Planning case study
• [Tech Brief] HVDC Sub-Synchronous Oscillations in Transmission Systems (Joint deliverable of P40.024B and P173.03)
Deliverables 2019
40
24B
TP
R&D Objectives
R&D Approach
SPP Generation Interconnection requests by
type
• High number of interconnection requests of utility scale solar PV in the SPP generation queue
High solar irradianceregion
Credits: NREL
Case Study – 2GW LCC Bipole from SW to
Kansas City
Hypothetical future scenario of
large integration of solar
generation
Are of new solar
generation
2GW
Load Area
HVDC link
500 miles
Project scope:
• Feasibility analysis of the HVDC project
• Steady state analysis• Contingency analysis and reinforcement
evaluation
• Reactive Power and Voltage control requirements• QV analysis• Reactive compensation sizing
• Short Circuit strength • GSAT analysis• SSTI screening
• Dynamic performance (transient stability)
• Cost analysis
Area of new solar
generation (2GW)
Case study: Weak sending end
Blackwater (200 MW)
Artesia (200 MW)Sidney (200 MW)
Stegall(110 MW)
Rapid City DC(200 MW)
Miles City(200 MW)
IPP (2400 MW)
PDCI (3100 MW)
TBC (400 MW)
Eel River(320 MW)
Square Butte(500 MW)
Nelson River I(1620 MW)Nelson River II(1800 MW)
Coal Creek(1000 MW)
Oklaunion(200 MW)
Madawaska(350 MW)
Highgate(200 MW)
Quebec –New England(2000 MW)
Welsh(600 MW)
Eagle Pass(36 MW)
Cross SoundCable (300 MW)
Lamar (210 MW) Neptune(600 MW)
Sharyland(150 MW)
Chateauguay(1000 MW)
LCC HVDCVSC HVDC
WATL(1000 MW)
EATL(1000 MW)
Labrador –Island Link(900 MW)
Nelson River Bipole III(2000 MW)
Maritime Link(500 MW)
Hudson TransmProject (660 MW)
Mackinac(200 MW)
McNeill(150 MW)
Determining system strength at HVDC busses
CaseOriginal Case
No HVDC HVDC Added
SE Outage 0
SE Line Outage 1
SE Line Outage 2
SE Line Outage 3
Sending End (SE)
SCR 1.97 3.67 3.2 3.16 2.92 3.1
ESCR 1.39 3.09 2.62 2.58 2.34 2.53
▪ Sending end ESCR low
▪ Receiving end meshed and strong network ESCR 5+ even with outages
ESCR OK but low -Further investigation needed
Receiving End (RE)
SCR 6.45 6.13
ESCR 6.02 5.70
Sending end(rectifier)
Receiving end(inverter)
2 GW power transfer
Network reinforcements
Large load center
(Kansas City area)
Easter NM, NW Texas
Parallel AC grid
Parallel AC grid
LCC HVDC
Area one line diagram
Scenarios analyzed
1. HVDC Bi-pole trip
2. Solid Inverter fault
3. Solid Rectifier fault
HVDC Controls Enabled
1. AC-VDCOL• Aimed at improving stability, particularly voltage, during low
voltage recovery periods• Aimed at reducing risk of commutation failure
2. RAML• Aimed at avoiding firing angle rollback during low rectifier
voltages (e.g., faults)
3. Commutation failure emulation
HVDC Bipole trip
Sending end(rectifier)
Receiving end(inverter)
Parallel AC grid
Parallel AC grid
AC fault
Cleared element
LCC HVDC
2 GW power transfer
HVDC Bipole trip
Rectifier side
generators
speed
up/inverter side
slows down
Solar plants
scramble to
control voltage
under vastly
different
system flows
Steady state QV analysis
indicated that loss of harmonic
filters would lead to nearly zero
reactive margins – HVDC
bipole tripped as remediation
Inverter side AC fault
Sending end(rectifier)
Receiving end(inverter)
Parallel AC grid
Parallel AC grid
AC fault
Cleared element
2 GW power transfer
Inverter side AC fault
DC current
spike due to
AC fault can
be
troublesome
Generators
are stable
on both
ends
Solar plants POI
voltages
recover after
the fault
Rectifier side AC fault
Sending end(rectifier)
Receiving end(inverter)
Parallel AC grid
Parallel AC grid
AC fault
Cleared element
2 GW power transfer
Rectifier side AC fault
DC current
(and
power)
collapse
during fault
All generators
on both
sides are
stable
Conclusions
1. Case study evaluated system performance after integration of 2GW LCC HVDC line to export solar PV generation• Minor system reinforcements needed, mostly to allow exports
• Higher HVDC rating could require major reinforcements
2. No additional dynamic reactive power support needed• ** Under selected N-1 events **
• Transient voltages are reasonable (more thorough evaluation needed)
• In a real project, verify with OEM if HVDC controls can operate at identified SCR range (2-3)
3. Control settings/features of HVDC models is important in preliminary planning studies• May lead to incorrect conclusions (e.g., neglecting DC line dynamics
may lead to excessive dynamic VAR requirements)
• May not represent actual equipment performance in high fidelity