Solidny partner w biznesie
Transcript
Page 1: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

Solidny partner w biznesie

wwwmostostalcom 2

1999 2004

Polimex-Cekop

hold majority of

Mostostal

Siedlcersquos

company stock

Merge of Polimex-

Cekop SA and

Mostostal Siedlce SA

ndash establishment of

Polimex-Mostostal

Siedlce SA

1997 1973

Establishment

of Mostostal

Siedlce

Debut of

Mostostal

Siedlce on the

Warsaw Stock

Exchange

2009 2012

Changing of company

structure from multi-

division into

segments- organized

Creating of the

Production Segment

start of

restructurisation

2016

Start up of new workshop

facility in Siedlce

including paintshop

2006

Separation of IPC from

Polimex-Mostostal SA

Start of operation as

Mostostal Siedlce

Change of

company

name into

Polimex-

Mostostal SA

2015

Creating of the Integrated

Part of Company (IPC) which

includes Steel Structures

Division in Siedlce

wwwmostostalcom 3

400 mln PLN per year Sales in 2016

1650 qualified employees Employment level

345 779 Msup2 Workshop area

2 500 TONS - STEEL STRUCTURES

2 500 TONS ndash PLATFORM GRATINGS

7000 TONS ndash GALVANIZING

Capacity per month

ca 70 Share of export

64 TONS

Max Overhead bridge cranes

capacity

wwwmostostalcom 4

403 152 960 Total turnover

PLN

Fabrication in tons Turnover [PLN]

Steel Structures

Platform gratings

Corrosion protection

25 750 191 771 801

25 446 131 503 012

108 616 60 313 223

19 564 924 Sales from other

activity PLN

wwwmostostalcom 5

1250 1250

1200

1150

1200

1280

1050

1100

1150

1200

1250

1300

2010 2011 2012 2013 2014 2015

Industry Economic Guide (PIKS) 2016

wwwmostostalcom 6

Industry Economic Guide (PIKS) 2016

3

3532

42 43

52

0

1

2

3

4

5

6

2010 2011 2012 2013 2014 2015

wwwmostostalcom 7

Industry Economic Guide (PIKS) 2016

0

100

200

300

400

500

600

700

800

900

2011 2012 2013 2014 2015

export

import

wwwmostostalcom 8

CORROSION PROTECTION ndash HOT DIP GALVANIZING

AND PAINTING

Mostostal Siedlce is one of the largest manufacturers of steel structures in Poland

STEEL STRUCTURES PLATFORM GRATINGS

MOSTOSTAL SIEDLCE

wwwmostostalcom 9

A modern line for welded profiles production

Milling machine

Laser Cutting Machine for plates

Two portal cutting machines for plates

Universal Edge Beveller Automatic CNC Drilling amp Thermal Cutting System for Large Plates

wwwmostostalcom 10

STEEL STRUCTURES

Total capacity 2500 tons monthly

25 numeric machines (including Union PCR 150)

150 welding stations

Qualified NDT personnel

wwwmostostalcom 11

Steel structures for power plants waste-to-energy plants petrochemistry metallurgy public buildings Constructions of chimneys towers Support structures of processing lines and pipelines Siloses hoppers tanks Lifting constructions ndash cranes (including harbour cranes) Bridges viaducts footbridges Estacades ladders railings Pallets containers racks

Laser cutting Shot-blasting Tooling of metallurgical profiles Welding of steel girders

wwwmostostalcom 12

wwwmostostalcom

13

wwwmostostalcom 14

Power Plant Togo

700 tons of steel

Petrochemistry Abu Dhabi UAE 450 tons of steel

Power Plant Jamaica

260 tons of steel

Coal Power Plant Westfalen Germany 7 793 tons of steel

Coal Power Plant Ledvice Czech Republik

17 270 tons of steel

wwwmostostalcom 15

Trade Fair Centre Exhibition Hall Kielce Poland

930 tons of steel

Childrenrsquos Hospital of Philadelfia USA 500 tons of steel

Katowice roundabouts Dome Poland 240 tons of steel

Copernicus Centre in Torun Poland 1025 tons of steel

wwwmostostalcom 16

OBI Germany

wwwmostostalcom

Stadium in Stavanger Norway roof construction 250 tons of steel

bdquoWisła Krakoacutewrdquo Stadium in Cracow Poland 840 tons of steel

bdquoLegiardquo Stadium in Warsaw Poland roof construction 2635 tons of steel

17

wwwmostostalcom 18

wwwmostostalcom

Transformer Platform for Wind Power Plant Denmark

Equipment for oil rig modules Norway

Pipe bridges Ormen Lange Norwegian Sea

19

wwwmostostalcom 20

wwwmostostalcom 21

Strasburg Railway Station facade structure

400 tons of steel

Roof construction Warsaw University Library

Poland

bdquoSpodekrdquo Katowice 240 tons of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 2: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 2

1999 2004

Polimex-Cekop

hold majority of

Mostostal

Siedlcersquos

company stock

Merge of Polimex-

Cekop SA and

Mostostal Siedlce SA

ndash establishment of

Polimex-Mostostal

Siedlce SA

1997 1973

Establishment

of Mostostal

Siedlce

Debut of

Mostostal

Siedlce on the

Warsaw Stock

Exchange

2009 2012

Changing of company

structure from multi-

division into

segments- organized

Creating of the

Production Segment

start of

restructurisation

2016

Start up of new workshop

facility in Siedlce

including paintshop

2006

Separation of IPC from

Polimex-Mostostal SA

Start of operation as

Mostostal Siedlce

Change of

company

name into

Polimex-

Mostostal SA

2015

Creating of the Integrated

Part of Company (IPC) which

includes Steel Structures

Division in Siedlce

wwwmostostalcom 3

400 mln PLN per year Sales in 2016

1650 qualified employees Employment level

345 779 Msup2 Workshop area

2 500 TONS - STEEL STRUCTURES

2 500 TONS ndash PLATFORM GRATINGS

7000 TONS ndash GALVANIZING

Capacity per month

ca 70 Share of export

64 TONS

Max Overhead bridge cranes

capacity

wwwmostostalcom 4

403 152 960 Total turnover

PLN

Fabrication in tons Turnover [PLN]

Steel Structures

Platform gratings

Corrosion protection

25 750 191 771 801

25 446 131 503 012

108 616 60 313 223

19 564 924 Sales from other

activity PLN

wwwmostostalcom 5

1250 1250

1200

1150

1200

1280

1050

1100

1150

1200

1250

1300

2010 2011 2012 2013 2014 2015

Industry Economic Guide (PIKS) 2016

wwwmostostalcom 6

Industry Economic Guide (PIKS) 2016

3

3532

42 43

52

0

1

2

3

4

5

6

2010 2011 2012 2013 2014 2015

wwwmostostalcom 7

Industry Economic Guide (PIKS) 2016

0

100

200

300

400

500

600

700

800

900

2011 2012 2013 2014 2015

export

import

wwwmostostalcom 8

CORROSION PROTECTION ndash HOT DIP GALVANIZING

AND PAINTING

Mostostal Siedlce is one of the largest manufacturers of steel structures in Poland

STEEL STRUCTURES PLATFORM GRATINGS

MOSTOSTAL SIEDLCE

wwwmostostalcom 9

A modern line for welded profiles production

Milling machine

Laser Cutting Machine for plates

Two portal cutting machines for plates

Universal Edge Beveller Automatic CNC Drilling amp Thermal Cutting System for Large Plates

wwwmostostalcom 10

STEEL STRUCTURES

Total capacity 2500 tons monthly

25 numeric machines (including Union PCR 150)

150 welding stations

Qualified NDT personnel

wwwmostostalcom 11

Steel structures for power plants waste-to-energy plants petrochemistry metallurgy public buildings Constructions of chimneys towers Support structures of processing lines and pipelines Siloses hoppers tanks Lifting constructions ndash cranes (including harbour cranes) Bridges viaducts footbridges Estacades ladders railings Pallets containers racks

Laser cutting Shot-blasting Tooling of metallurgical profiles Welding of steel girders

wwwmostostalcom 12

wwwmostostalcom

13

wwwmostostalcom 14

Power Plant Togo

700 tons of steel

Petrochemistry Abu Dhabi UAE 450 tons of steel

Power Plant Jamaica

260 tons of steel

Coal Power Plant Westfalen Germany 7 793 tons of steel

Coal Power Plant Ledvice Czech Republik

17 270 tons of steel

wwwmostostalcom 15

Trade Fair Centre Exhibition Hall Kielce Poland

930 tons of steel

Childrenrsquos Hospital of Philadelfia USA 500 tons of steel

Katowice roundabouts Dome Poland 240 tons of steel

Copernicus Centre in Torun Poland 1025 tons of steel

wwwmostostalcom 16

OBI Germany

wwwmostostalcom

Stadium in Stavanger Norway roof construction 250 tons of steel

bdquoWisła Krakoacutewrdquo Stadium in Cracow Poland 840 tons of steel

bdquoLegiardquo Stadium in Warsaw Poland roof construction 2635 tons of steel

17

wwwmostostalcom 18

wwwmostostalcom

Transformer Platform for Wind Power Plant Denmark

Equipment for oil rig modules Norway

Pipe bridges Ormen Lange Norwegian Sea

19

wwwmostostalcom 20

wwwmostostalcom 21

Strasburg Railway Station facade structure

400 tons of steel

Roof construction Warsaw University Library

Poland

bdquoSpodekrdquo Katowice 240 tons of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 3: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 3

400 mln PLN per year Sales in 2016

1650 qualified employees Employment level

345 779 Msup2 Workshop area

2 500 TONS - STEEL STRUCTURES

2 500 TONS ndash PLATFORM GRATINGS

7000 TONS ndash GALVANIZING

Capacity per month

ca 70 Share of export

64 TONS

Max Overhead bridge cranes

capacity

wwwmostostalcom 4

403 152 960 Total turnover

PLN

Fabrication in tons Turnover [PLN]

Steel Structures

Platform gratings

Corrosion protection

25 750 191 771 801

25 446 131 503 012

108 616 60 313 223

19 564 924 Sales from other

activity PLN

wwwmostostalcom 5

1250 1250

1200

1150

1200

1280

1050

1100

1150

1200

1250

1300

2010 2011 2012 2013 2014 2015

Industry Economic Guide (PIKS) 2016

wwwmostostalcom 6

Industry Economic Guide (PIKS) 2016

3

3532

42 43

52

0

1

2

3

4

5

6

2010 2011 2012 2013 2014 2015

wwwmostostalcom 7

Industry Economic Guide (PIKS) 2016

0

100

200

300

400

500

600

700

800

900

2011 2012 2013 2014 2015

export

import

wwwmostostalcom 8

CORROSION PROTECTION ndash HOT DIP GALVANIZING

AND PAINTING

Mostostal Siedlce is one of the largest manufacturers of steel structures in Poland

STEEL STRUCTURES PLATFORM GRATINGS

MOSTOSTAL SIEDLCE

wwwmostostalcom 9

A modern line for welded profiles production

Milling machine

Laser Cutting Machine for plates

Two portal cutting machines for plates

Universal Edge Beveller Automatic CNC Drilling amp Thermal Cutting System for Large Plates

wwwmostostalcom 10

STEEL STRUCTURES

Total capacity 2500 tons monthly

25 numeric machines (including Union PCR 150)

150 welding stations

Qualified NDT personnel

wwwmostostalcom 11

Steel structures for power plants waste-to-energy plants petrochemistry metallurgy public buildings Constructions of chimneys towers Support structures of processing lines and pipelines Siloses hoppers tanks Lifting constructions ndash cranes (including harbour cranes) Bridges viaducts footbridges Estacades ladders railings Pallets containers racks

Laser cutting Shot-blasting Tooling of metallurgical profiles Welding of steel girders

wwwmostostalcom 12

wwwmostostalcom

13

wwwmostostalcom 14

Power Plant Togo

700 tons of steel

Petrochemistry Abu Dhabi UAE 450 tons of steel

Power Plant Jamaica

260 tons of steel

Coal Power Plant Westfalen Germany 7 793 tons of steel

Coal Power Plant Ledvice Czech Republik

17 270 tons of steel

wwwmostostalcom 15

Trade Fair Centre Exhibition Hall Kielce Poland

930 tons of steel

Childrenrsquos Hospital of Philadelfia USA 500 tons of steel

Katowice roundabouts Dome Poland 240 tons of steel

Copernicus Centre in Torun Poland 1025 tons of steel

wwwmostostalcom 16

OBI Germany

wwwmostostalcom

Stadium in Stavanger Norway roof construction 250 tons of steel

bdquoWisła Krakoacutewrdquo Stadium in Cracow Poland 840 tons of steel

bdquoLegiardquo Stadium in Warsaw Poland roof construction 2635 tons of steel

17

wwwmostostalcom 18

wwwmostostalcom

Transformer Platform for Wind Power Plant Denmark

Equipment for oil rig modules Norway

Pipe bridges Ormen Lange Norwegian Sea

19

wwwmostostalcom 20

wwwmostostalcom 21

Strasburg Railway Station facade structure

400 tons of steel

Roof construction Warsaw University Library

Poland

bdquoSpodekrdquo Katowice 240 tons of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 4: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 4

403 152 960 Total turnover

PLN

Fabrication in tons Turnover [PLN]

Steel Structures

Platform gratings

Corrosion protection

25 750 191 771 801

25 446 131 503 012

108 616 60 313 223

19 564 924 Sales from other

activity PLN

wwwmostostalcom 5

1250 1250

1200

1150

1200

1280

1050

1100

1150

1200

1250

1300

2010 2011 2012 2013 2014 2015

Industry Economic Guide (PIKS) 2016

wwwmostostalcom 6

Industry Economic Guide (PIKS) 2016

3

3532

42 43

52

0

1

2

3

4

5

6

2010 2011 2012 2013 2014 2015

wwwmostostalcom 7

Industry Economic Guide (PIKS) 2016

0

100

200

300

400

500

600

700

800

900

2011 2012 2013 2014 2015

export

import

wwwmostostalcom 8

CORROSION PROTECTION ndash HOT DIP GALVANIZING

AND PAINTING

Mostostal Siedlce is one of the largest manufacturers of steel structures in Poland

STEEL STRUCTURES PLATFORM GRATINGS

MOSTOSTAL SIEDLCE

wwwmostostalcom 9

A modern line for welded profiles production

Milling machine

Laser Cutting Machine for plates

Two portal cutting machines for plates

Universal Edge Beveller Automatic CNC Drilling amp Thermal Cutting System for Large Plates

wwwmostostalcom 10

STEEL STRUCTURES

Total capacity 2500 tons monthly

25 numeric machines (including Union PCR 150)

150 welding stations

Qualified NDT personnel

wwwmostostalcom 11

Steel structures for power plants waste-to-energy plants petrochemistry metallurgy public buildings Constructions of chimneys towers Support structures of processing lines and pipelines Siloses hoppers tanks Lifting constructions ndash cranes (including harbour cranes) Bridges viaducts footbridges Estacades ladders railings Pallets containers racks

Laser cutting Shot-blasting Tooling of metallurgical profiles Welding of steel girders

wwwmostostalcom 12

wwwmostostalcom

13

wwwmostostalcom 14

Power Plant Togo

700 tons of steel

Petrochemistry Abu Dhabi UAE 450 tons of steel

Power Plant Jamaica

260 tons of steel

Coal Power Plant Westfalen Germany 7 793 tons of steel

Coal Power Plant Ledvice Czech Republik

17 270 tons of steel

wwwmostostalcom 15

Trade Fair Centre Exhibition Hall Kielce Poland

930 tons of steel

Childrenrsquos Hospital of Philadelfia USA 500 tons of steel

Katowice roundabouts Dome Poland 240 tons of steel

Copernicus Centre in Torun Poland 1025 tons of steel

wwwmostostalcom 16

OBI Germany

wwwmostostalcom

Stadium in Stavanger Norway roof construction 250 tons of steel

bdquoWisła Krakoacutewrdquo Stadium in Cracow Poland 840 tons of steel

bdquoLegiardquo Stadium in Warsaw Poland roof construction 2635 tons of steel

17

wwwmostostalcom 18

wwwmostostalcom

Transformer Platform for Wind Power Plant Denmark

Equipment for oil rig modules Norway

Pipe bridges Ormen Lange Norwegian Sea

19

wwwmostostalcom 20

wwwmostostalcom 21

Strasburg Railway Station facade structure

400 tons of steel

Roof construction Warsaw University Library

Poland

bdquoSpodekrdquo Katowice 240 tons of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 5: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 5

1250 1250

1200

1150

1200

1280

1050

1100

1150

1200

1250

1300

2010 2011 2012 2013 2014 2015

Industry Economic Guide (PIKS) 2016

wwwmostostalcom 6

Industry Economic Guide (PIKS) 2016

3

3532

42 43

52

0

1

2

3

4

5

6

2010 2011 2012 2013 2014 2015

wwwmostostalcom 7

Industry Economic Guide (PIKS) 2016

0

100

200

300

400

500

600

700

800

900

2011 2012 2013 2014 2015

export

import

wwwmostostalcom 8

CORROSION PROTECTION ndash HOT DIP GALVANIZING

AND PAINTING

Mostostal Siedlce is one of the largest manufacturers of steel structures in Poland

STEEL STRUCTURES PLATFORM GRATINGS

MOSTOSTAL SIEDLCE

wwwmostostalcom 9

A modern line for welded profiles production

Milling machine

Laser Cutting Machine for plates

Two portal cutting machines for plates

Universal Edge Beveller Automatic CNC Drilling amp Thermal Cutting System for Large Plates

wwwmostostalcom 10

STEEL STRUCTURES

Total capacity 2500 tons monthly

25 numeric machines (including Union PCR 150)

150 welding stations

Qualified NDT personnel

wwwmostostalcom 11

Steel structures for power plants waste-to-energy plants petrochemistry metallurgy public buildings Constructions of chimneys towers Support structures of processing lines and pipelines Siloses hoppers tanks Lifting constructions ndash cranes (including harbour cranes) Bridges viaducts footbridges Estacades ladders railings Pallets containers racks

Laser cutting Shot-blasting Tooling of metallurgical profiles Welding of steel girders

wwwmostostalcom 12

wwwmostostalcom

13

wwwmostostalcom 14

Power Plant Togo

700 tons of steel

Petrochemistry Abu Dhabi UAE 450 tons of steel

Power Plant Jamaica

260 tons of steel

Coal Power Plant Westfalen Germany 7 793 tons of steel

Coal Power Plant Ledvice Czech Republik

17 270 tons of steel

wwwmostostalcom 15

Trade Fair Centre Exhibition Hall Kielce Poland

930 tons of steel

Childrenrsquos Hospital of Philadelfia USA 500 tons of steel

Katowice roundabouts Dome Poland 240 tons of steel

Copernicus Centre in Torun Poland 1025 tons of steel

wwwmostostalcom 16

OBI Germany

wwwmostostalcom

Stadium in Stavanger Norway roof construction 250 tons of steel

bdquoWisła Krakoacutewrdquo Stadium in Cracow Poland 840 tons of steel

bdquoLegiardquo Stadium in Warsaw Poland roof construction 2635 tons of steel

17

wwwmostostalcom 18

wwwmostostalcom

Transformer Platform for Wind Power Plant Denmark

Equipment for oil rig modules Norway

Pipe bridges Ormen Lange Norwegian Sea

19

wwwmostostalcom 20

wwwmostostalcom 21

Strasburg Railway Station facade structure

400 tons of steel

Roof construction Warsaw University Library

Poland

bdquoSpodekrdquo Katowice 240 tons of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 6: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 6

Industry Economic Guide (PIKS) 2016

3

3532

42 43

52

0

1

2

3

4

5

6

2010 2011 2012 2013 2014 2015

wwwmostostalcom 7

Industry Economic Guide (PIKS) 2016

0

100

200

300

400

500

600

700

800

900

2011 2012 2013 2014 2015

export

import

wwwmostostalcom 8

CORROSION PROTECTION ndash HOT DIP GALVANIZING

AND PAINTING

Mostostal Siedlce is one of the largest manufacturers of steel structures in Poland

STEEL STRUCTURES PLATFORM GRATINGS

MOSTOSTAL SIEDLCE

wwwmostostalcom 9

A modern line for welded profiles production

Milling machine

Laser Cutting Machine for plates

Two portal cutting machines for plates

Universal Edge Beveller Automatic CNC Drilling amp Thermal Cutting System for Large Plates

wwwmostostalcom 10

STEEL STRUCTURES

Total capacity 2500 tons monthly

25 numeric machines (including Union PCR 150)

150 welding stations

Qualified NDT personnel

wwwmostostalcom 11

Steel structures for power plants waste-to-energy plants petrochemistry metallurgy public buildings Constructions of chimneys towers Support structures of processing lines and pipelines Siloses hoppers tanks Lifting constructions ndash cranes (including harbour cranes) Bridges viaducts footbridges Estacades ladders railings Pallets containers racks

Laser cutting Shot-blasting Tooling of metallurgical profiles Welding of steel girders

wwwmostostalcom 12

wwwmostostalcom

13

wwwmostostalcom 14

Power Plant Togo

700 tons of steel

Petrochemistry Abu Dhabi UAE 450 tons of steel

Power Plant Jamaica

260 tons of steel

Coal Power Plant Westfalen Germany 7 793 tons of steel

Coal Power Plant Ledvice Czech Republik

17 270 tons of steel

wwwmostostalcom 15

Trade Fair Centre Exhibition Hall Kielce Poland

930 tons of steel

Childrenrsquos Hospital of Philadelfia USA 500 tons of steel

Katowice roundabouts Dome Poland 240 tons of steel

Copernicus Centre in Torun Poland 1025 tons of steel

wwwmostostalcom 16

OBI Germany

wwwmostostalcom

Stadium in Stavanger Norway roof construction 250 tons of steel

bdquoWisła Krakoacutewrdquo Stadium in Cracow Poland 840 tons of steel

bdquoLegiardquo Stadium in Warsaw Poland roof construction 2635 tons of steel

17

wwwmostostalcom 18

wwwmostostalcom

Transformer Platform for Wind Power Plant Denmark

Equipment for oil rig modules Norway

Pipe bridges Ormen Lange Norwegian Sea

19

wwwmostostalcom 20

wwwmostostalcom 21

Strasburg Railway Station facade structure

400 tons of steel

Roof construction Warsaw University Library

Poland

bdquoSpodekrdquo Katowice 240 tons of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 7: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 7

Industry Economic Guide (PIKS) 2016

0

100

200

300

400

500

600

700

800

900

2011 2012 2013 2014 2015

export

import

wwwmostostalcom 8

CORROSION PROTECTION ndash HOT DIP GALVANIZING

AND PAINTING

Mostostal Siedlce is one of the largest manufacturers of steel structures in Poland

STEEL STRUCTURES PLATFORM GRATINGS

MOSTOSTAL SIEDLCE

wwwmostostalcom 9

A modern line for welded profiles production

Milling machine

Laser Cutting Machine for plates

Two portal cutting machines for plates

Universal Edge Beveller Automatic CNC Drilling amp Thermal Cutting System for Large Plates

wwwmostostalcom 10

STEEL STRUCTURES

Total capacity 2500 tons monthly

25 numeric machines (including Union PCR 150)

150 welding stations

Qualified NDT personnel

wwwmostostalcom 11

Steel structures for power plants waste-to-energy plants petrochemistry metallurgy public buildings Constructions of chimneys towers Support structures of processing lines and pipelines Siloses hoppers tanks Lifting constructions ndash cranes (including harbour cranes) Bridges viaducts footbridges Estacades ladders railings Pallets containers racks

Laser cutting Shot-blasting Tooling of metallurgical profiles Welding of steel girders

wwwmostostalcom 12

wwwmostostalcom

13

wwwmostostalcom 14

Power Plant Togo

700 tons of steel

Petrochemistry Abu Dhabi UAE 450 tons of steel

Power Plant Jamaica

260 tons of steel

Coal Power Plant Westfalen Germany 7 793 tons of steel

Coal Power Plant Ledvice Czech Republik

17 270 tons of steel

wwwmostostalcom 15

Trade Fair Centre Exhibition Hall Kielce Poland

930 tons of steel

Childrenrsquos Hospital of Philadelfia USA 500 tons of steel

Katowice roundabouts Dome Poland 240 tons of steel

Copernicus Centre in Torun Poland 1025 tons of steel

wwwmostostalcom 16

OBI Germany

wwwmostostalcom

Stadium in Stavanger Norway roof construction 250 tons of steel

bdquoWisła Krakoacutewrdquo Stadium in Cracow Poland 840 tons of steel

bdquoLegiardquo Stadium in Warsaw Poland roof construction 2635 tons of steel

17

wwwmostostalcom 18

wwwmostostalcom

Transformer Platform for Wind Power Plant Denmark

Equipment for oil rig modules Norway

Pipe bridges Ormen Lange Norwegian Sea

19

wwwmostostalcom 20

wwwmostostalcom 21

Strasburg Railway Station facade structure

400 tons of steel

Roof construction Warsaw University Library

Poland

bdquoSpodekrdquo Katowice 240 tons of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 8: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 8

CORROSION PROTECTION ndash HOT DIP GALVANIZING

AND PAINTING

Mostostal Siedlce is one of the largest manufacturers of steel structures in Poland

STEEL STRUCTURES PLATFORM GRATINGS

MOSTOSTAL SIEDLCE

wwwmostostalcom 9

A modern line for welded profiles production

Milling machine

Laser Cutting Machine for plates

Two portal cutting machines for plates

Universal Edge Beveller Automatic CNC Drilling amp Thermal Cutting System for Large Plates

wwwmostostalcom 10

STEEL STRUCTURES

Total capacity 2500 tons monthly

25 numeric machines (including Union PCR 150)

150 welding stations

Qualified NDT personnel

wwwmostostalcom 11

Steel structures for power plants waste-to-energy plants petrochemistry metallurgy public buildings Constructions of chimneys towers Support structures of processing lines and pipelines Siloses hoppers tanks Lifting constructions ndash cranes (including harbour cranes) Bridges viaducts footbridges Estacades ladders railings Pallets containers racks

Laser cutting Shot-blasting Tooling of metallurgical profiles Welding of steel girders

wwwmostostalcom 12

wwwmostostalcom

13

wwwmostostalcom 14

Power Plant Togo

700 tons of steel

Petrochemistry Abu Dhabi UAE 450 tons of steel

Power Plant Jamaica

260 tons of steel

Coal Power Plant Westfalen Germany 7 793 tons of steel

Coal Power Plant Ledvice Czech Republik

17 270 tons of steel

wwwmostostalcom 15

Trade Fair Centre Exhibition Hall Kielce Poland

930 tons of steel

Childrenrsquos Hospital of Philadelfia USA 500 tons of steel

Katowice roundabouts Dome Poland 240 tons of steel

Copernicus Centre in Torun Poland 1025 tons of steel

wwwmostostalcom 16

OBI Germany

wwwmostostalcom

Stadium in Stavanger Norway roof construction 250 tons of steel

bdquoWisła Krakoacutewrdquo Stadium in Cracow Poland 840 tons of steel

bdquoLegiardquo Stadium in Warsaw Poland roof construction 2635 tons of steel

17

wwwmostostalcom 18

wwwmostostalcom

Transformer Platform for Wind Power Plant Denmark

Equipment for oil rig modules Norway

Pipe bridges Ormen Lange Norwegian Sea

19

wwwmostostalcom 20

wwwmostostalcom 21

Strasburg Railway Station facade structure

400 tons of steel

Roof construction Warsaw University Library

Poland

bdquoSpodekrdquo Katowice 240 tons of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 9: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 9

A modern line for welded profiles production

Milling machine

Laser Cutting Machine for plates

Two portal cutting machines for plates

Universal Edge Beveller Automatic CNC Drilling amp Thermal Cutting System for Large Plates

wwwmostostalcom 10

STEEL STRUCTURES

Total capacity 2500 tons monthly

25 numeric machines (including Union PCR 150)

150 welding stations

Qualified NDT personnel

wwwmostostalcom 11

Steel structures for power plants waste-to-energy plants petrochemistry metallurgy public buildings Constructions of chimneys towers Support structures of processing lines and pipelines Siloses hoppers tanks Lifting constructions ndash cranes (including harbour cranes) Bridges viaducts footbridges Estacades ladders railings Pallets containers racks

Laser cutting Shot-blasting Tooling of metallurgical profiles Welding of steel girders

wwwmostostalcom 12

wwwmostostalcom

13

wwwmostostalcom 14

Power Plant Togo

700 tons of steel

Petrochemistry Abu Dhabi UAE 450 tons of steel

Power Plant Jamaica

260 tons of steel

Coal Power Plant Westfalen Germany 7 793 tons of steel

Coal Power Plant Ledvice Czech Republik

17 270 tons of steel

wwwmostostalcom 15

Trade Fair Centre Exhibition Hall Kielce Poland

930 tons of steel

Childrenrsquos Hospital of Philadelfia USA 500 tons of steel

Katowice roundabouts Dome Poland 240 tons of steel

Copernicus Centre in Torun Poland 1025 tons of steel

wwwmostostalcom 16

OBI Germany

wwwmostostalcom

Stadium in Stavanger Norway roof construction 250 tons of steel

bdquoWisła Krakoacutewrdquo Stadium in Cracow Poland 840 tons of steel

bdquoLegiardquo Stadium in Warsaw Poland roof construction 2635 tons of steel

17

wwwmostostalcom 18

wwwmostostalcom

Transformer Platform for Wind Power Plant Denmark

Equipment for oil rig modules Norway

Pipe bridges Ormen Lange Norwegian Sea

19

wwwmostostalcom 20

wwwmostostalcom 21

Strasburg Railway Station facade structure

400 tons of steel

Roof construction Warsaw University Library

Poland

bdquoSpodekrdquo Katowice 240 tons of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 10: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 10

STEEL STRUCTURES

Total capacity 2500 tons monthly

25 numeric machines (including Union PCR 150)

150 welding stations

Qualified NDT personnel

wwwmostostalcom 11

Steel structures for power plants waste-to-energy plants petrochemistry metallurgy public buildings Constructions of chimneys towers Support structures of processing lines and pipelines Siloses hoppers tanks Lifting constructions ndash cranes (including harbour cranes) Bridges viaducts footbridges Estacades ladders railings Pallets containers racks

Laser cutting Shot-blasting Tooling of metallurgical profiles Welding of steel girders

wwwmostostalcom 12

wwwmostostalcom

13

wwwmostostalcom 14

Power Plant Togo

700 tons of steel

Petrochemistry Abu Dhabi UAE 450 tons of steel

Power Plant Jamaica

260 tons of steel

Coal Power Plant Westfalen Germany 7 793 tons of steel

Coal Power Plant Ledvice Czech Republik

17 270 tons of steel

wwwmostostalcom 15

Trade Fair Centre Exhibition Hall Kielce Poland

930 tons of steel

Childrenrsquos Hospital of Philadelfia USA 500 tons of steel

Katowice roundabouts Dome Poland 240 tons of steel

Copernicus Centre in Torun Poland 1025 tons of steel

wwwmostostalcom 16

OBI Germany

wwwmostostalcom

Stadium in Stavanger Norway roof construction 250 tons of steel

bdquoWisła Krakoacutewrdquo Stadium in Cracow Poland 840 tons of steel

bdquoLegiardquo Stadium in Warsaw Poland roof construction 2635 tons of steel

17

wwwmostostalcom 18

wwwmostostalcom

Transformer Platform for Wind Power Plant Denmark

Equipment for oil rig modules Norway

Pipe bridges Ormen Lange Norwegian Sea

19

wwwmostostalcom 20

wwwmostostalcom 21

Strasburg Railway Station facade structure

400 tons of steel

Roof construction Warsaw University Library

Poland

bdquoSpodekrdquo Katowice 240 tons of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 11: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 11

Steel structures for power plants waste-to-energy plants petrochemistry metallurgy public buildings Constructions of chimneys towers Support structures of processing lines and pipelines Siloses hoppers tanks Lifting constructions ndash cranes (including harbour cranes) Bridges viaducts footbridges Estacades ladders railings Pallets containers racks

Laser cutting Shot-blasting Tooling of metallurgical profiles Welding of steel girders

wwwmostostalcom 12

wwwmostostalcom

13

wwwmostostalcom 14

Power Plant Togo

700 tons of steel

Petrochemistry Abu Dhabi UAE 450 tons of steel

Power Plant Jamaica

260 tons of steel

Coal Power Plant Westfalen Germany 7 793 tons of steel

Coal Power Plant Ledvice Czech Republik

17 270 tons of steel

wwwmostostalcom 15

Trade Fair Centre Exhibition Hall Kielce Poland

930 tons of steel

Childrenrsquos Hospital of Philadelfia USA 500 tons of steel

Katowice roundabouts Dome Poland 240 tons of steel

Copernicus Centre in Torun Poland 1025 tons of steel

wwwmostostalcom 16

OBI Germany

wwwmostostalcom

Stadium in Stavanger Norway roof construction 250 tons of steel

bdquoWisła Krakoacutewrdquo Stadium in Cracow Poland 840 tons of steel

bdquoLegiardquo Stadium in Warsaw Poland roof construction 2635 tons of steel

17

wwwmostostalcom 18

wwwmostostalcom

Transformer Platform for Wind Power Plant Denmark

Equipment for oil rig modules Norway

Pipe bridges Ormen Lange Norwegian Sea

19

wwwmostostalcom 20

wwwmostostalcom 21

Strasburg Railway Station facade structure

400 tons of steel

Roof construction Warsaw University Library

Poland

bdquoSpodekrdquo Katowice 240 tons of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 12: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 12

wwwmostostalcom

13

wwwmostostalcom 14

Power Plant Togo

700 tons of steel

Petrochemistry Abu Dhabi UAE 450 tons of steel

Power Plant Jamaica

260 tons of steel

Coal Power Plant Westfalen Germany 7 793 tons of steel

Coal Power Plant Ledvice Czech Republik

17 270 tons of steel

wwwmostostalcom 15

Trade Fair Centre Exhibition Hall Kielce Poland

930 tons of steel

Childrenrsquos Hospital of Philadelfia USA 500 tons of steel

Katowice roundabouts Dome Poland 240 tons of steel

Copernicus Centre in Torun Poland 1025 tons of steel

wwwmostostalcom 16

OBI Germany

wwwmostostalcom

Stadium in Stavanger Norway roof construction 250 tons of steel

bdquoWisła Krakoacutewrdquo Stadium in Cracow Poland 840 tons of steel

bdquoLegiardquo Stadium in Warsaw Poland roof construction 2635 tons of steel

17

wwwmostostalcom 18

wwwmostostalcom

Transformer Platform for Wind Power Plant Denmark

Equipment for oil rig modules Norway

Pipe bridges Ormen Lange Norwegian Sea

19

wwwmostostalcom 20

wwwmostostalcom 21

Strasburg Railway Station facade structure

400 tons of steel

Roof construction Warsaw University Library

Poland

bdquoSpodekrdquo Katowice 240 tons of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 13: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom

13

wwwmostostalcom 14

Power Plant Togo

700 tons of steel

Petrochemistry Abu Dhabi UAE 450 tons of steel

Power Plant Jamaica

260 tons of steel

Coal Power Plant Westfalen Germany 7 793 tons of steel

Coal Power Plant Ledvice Czech Republik

17 270 tons of steel

wwwmostostalcom 15

Trade Fair Centre Exhibition Hall Kielce Poland

930 tons of steel

Childrenrsquos Hospital of Philadelfia USA 500 tons of steel

Katowice roundabouts Dome Poland 240 tons of steel

Copernicus Centre in Torun Poland 1025 tons of steel

wwwmostostalcom 16

OBI Germany

wwwmostostalcom

Stadium in Stavanger Norway roof construction 250 tons of steel

bdquoWisła Krakoacutewrdquo Stadium in Cracow Poland 840 tons of steel

bdquoLegiardquo Stadium in Warsaw Poland roof construction 2635 tons of steel

17

wwwmostostalcom 18

wwwmostostalcom

Transformer Platform for Wind Power Plant Denmark

Equipment for oil rig modules Norway

Pipe bridges Ormen Lange Norwegian Sea

19

wwwmostostalcom 20

wwwmostostalcom 21

Strasburg Railway Station facade structure

400 tons of steel

Roof construction Warsaw University Library

Poland

bdquoSpodekrdquo Katowice 240 tons of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 14: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 14

Power Plant Togo

700 tons of steel

Petrochemistry Abu Dhabi UAE 450 tons of steel

Power Plant Jamaica

260 tons of steel

Coal Power Plant Westfalen Germany 7 793 tons of steel

Coal Power Plant Ledvice Czech Republik

17 270 tons of steel

wwwmostostalcom 15

Trade Fair Centre Exhibition Hall Kielce Poland

930 tons of steel

Childrenrsquos Hospital of Philadelfia USA 500 tons of steel

Katowice roundabouts Dome Poland 240 tons of steel

Copernicus Centre in Torun Poland 1025 tons of steel

wwwmostostalcom 16

OBI Germany

wwwmostostalcom

Stadium in Stavanger Norway roof construction 250 tons of steel

bdquoWisła Krakoacutewrdquo Stadium in Cracow Poland 840 tons of steel

bdquoLegiardquo Stadium in Warsaw Poland roof construction 2635 tons of steel

17

wwwmostostalcom 18

wwwmostostalcom

Transformer Platform for Wind Power Plant Denmark

Equipment for oil rig modules Norway

Pipe bridges Ormen Lange Norwegian Sea

19

wwwmostostalcom 20

wwwmostostalcom 21

Strasburg Railway Station facade structure

400 tons of steel

Roof construction Warsaw University Library

Poland

bdquoSpodekrdquo Katowice 240 tons of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 15: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 15

Trade Fair Centre Exhibition Hall Kielce Poland

930 tons of steel

Childrenrsquos Hospital of Philadelfia USA 500 tons of steel

Katowice roundabouts Dome Poland 240 tons of steel

Copernicus Centre in Torun Poland 1025 tons of steel

wwwmostostalcom 16

OBI Germany

wwwmostostalcom

Stadium in Stavanger Norway roof construction 250 tons of steel

bdquoWisła Krakoacutewrdquo Stadium in Cracow Poland 840 tons of steel

bdquoLegiardquo Stadium in Warsaw Poland roof construction 2635 tons of steel

17

wwwmostostalcom 18

wwwmostostalcom

Transformer Platform for Wind Power Plant Denmark

Equipment for oil rig modules Norway

Pipe bridges Ormen Lange Norwegian Sea

19

wwwmostostalcom 20

wwwmostostalcom 21

Strasburg Railway Station facade structure

400 tons of steel

Roof construction Warsaw University Library

Poland

bdquoSpodekrdquo Katowice 240 tons of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 16: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 16

OBI Germany

wwwmostostalcom

Stadium in Stavanger Norway roof construction 250 tons of steel

bdquoWisła Krakoacutewrdquo Stadium in Cracow Poland 840 tons of steel

bdquoLegiardquo Stadium in Warsaw Poland roof construction 2635 tons of steel

17

wwwmostostalcom 18

wwwmostostalcom

Transformer Platform for Wind Power Plant Denmark

Equipment for oil rig modules Norway

Pipe bridges Ormen Lange Norwegian Sea

19

wwwmostostalcom 20

wwwmostostalcom 21

Strasburg Railway Station facade structure

400 tons of steel

Roof construction Warsaw University Library

Poland

bdquoSpodekrdquo Katowice 240 tons of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 17: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom

Stadium in Stavanger Norway roof construction 250 tons of steel

bdquoWisła Krakoacutewrdquo Stadium in Cracow Poland 840 tons of steel

bdquoLegiardquo Stadium in Warsaw Poland roof construction 2635 tons of steel

17

wwwmostostalcom 18

wwwmostostalcom

Transformer Platform for Wind Power Plant Denmark

Equipment for oil rig modules Norway

Pipe bridges Ormen Lange Norwegian Sea

19

wwwmostostalcom 20

wwwmostostalcom 21

Strasburg Railway Station facade structure

400 tons of steel

Roof construction Warsaw University Library

Poland

bdquoSpodekrdquo Katowice 240 tons of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 18: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 18

wwwmostostalcom

Transformer Platform for Wind Power Plant Denmark

Equipment for oil rig modules Norway

Pipe bridges Ormen Lange Norwegian Sea

19

wwwmostostalcom 20

wwwmostostalcom 21

Strasburg Railway Station facade structure

400 tons of steel

Roof construction Warsaw University Library

Poland

bdquoSpodekrdquo Katowice 240 tons of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 19: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom

Transformer Platform for Wind Power Plant Denmark

Equipment for oil rig modules Norway

Pipe bridges Ormen Lange Norwegian Sea

19

wwwmostostalcom 20

wwwmostostalcom 21

Strasburg Railway Station facade structure

400 tons of steel

Roof construction Warsaw University Library

Poland

bdquoSpodekrdquo Katowice 240 tons of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 20: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 20

wwwmostostalcom 21

Strasburg Railway Station facade structure

400 tons of steel

Roof construction Warsaw University Library

Poland

bdquoSpodekrdquo Katowice 240 tons of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 21: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 21

Strasburg Railway Station facade structure

400 tons of steel

Roof construction Warsaw University Library

Poland

bdquoSpodekrdquo Katowice 240 tons of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 22: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 22

Mostostal Siedlce operates in accordance with the Integrated Management System based on PN-EN ISO 9001 Quality management system PN-EN ISO 14001 Enviromental management system PN-N-18001 OHSAS 18001 Occupational Health and Safety management system PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel structures PN-EN ISO 3834-2 - Quality requirements for fusion welding of metallic materials -- Part 2 Comprehensive quality requirements EN 15085-2 ndash Welding of railway vehicles and components Steel Structures Manufacturer Certificate ndash PIKS (Polish Chamber of Steelwork)

Mostostal Siedlce also puts a big focus on Health Safety and Environment

HSE

OHSAS 18001

PN-EN ISO 9001 PN-EN ISO 14001

Certificate Class E PN-EN ISO 3834 EN-15085-2 Certyfikat PIKS GSI-SLV

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 23: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom

PLATFORM GRATINGS Modern machinery park

Total production capacity 2500 tons monthly

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 24: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 24

Welded gratings Pressed gratings SERRATED gratings (with anti-slip feature) Full pressed gratings louvered gratings Fencing systems benches Straight and spiral stairs Fasteners for gratings Comprehensive service for design and process technology Corrosion protection Delivery and assembly

THE BIGGEST MANUFACTURER in Poland and one of the leading in Europe

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 25: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 25

We have our own design and technology office

30 technologists

Experienced designers and constructors

Projects executed in CAD i BOCAD

Full technological support of projects

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 26: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 26

Platform gratings have plenty of interesting applications They are mostly used as platforms in production plants elements of pipelines platforms in public use facilities spiral stairs steps benches fencing systems

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 27: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 27

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 28: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 28

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 29: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 29

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 30: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 30

Technical Approval of the Institute of Building Technology Approval Certificate rarr Polski Rejestr Statkoacutew (Polish Register of Ships) Hygienic Certificate (National Institute of Hygiene) for gratings steps fasteners and zinc coating European Medal of BCC for platform gratings Certificate of Compliance with Welding Quality Requirements rarr Welding Institute

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 31: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 31

CORROSION PROTECTION

Total capacity 7000 tons of galvanized steel per month Two technological lines for hot dip galvanizing equipped with tanks (Length x Width x Debth)

13000 x 1800 x 3300 mm 7000 x 1800 x 3300 mm

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 32: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 32

Hot dip galvanizing Hydrodynamic painting Zinc spray coating Duplex system (galvanizing + painting)

SPECIALIZATION HOT DIP GALVANIZING The 3rd producer on the Polish market

acc to amount of galvanized constructions

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 33: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 33

Max Dimensions of elements 12500 x 1700 x 2900 mm

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 34: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 34

The modern paintshop with an area of 8000 m2 allows painting of large elements with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

We are able to prepare surface and paint also elements with complicated shapes

Paintshop capacity 3500 tons monthly

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 35: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 35

We offer a full service of Zinc Spray Coating which includes

Mechanical cleaning (shot blasting) to PN-EN ISO 8501-1

Thermal spraying of the metal layer (zinc)

Sealing of the zinc layer with additional paint layers

With this method we protect huge elements (especially for bridges) with maximum dimensions

Length 275 m Width 47 m Height 38 m and maximum weight of 64 tons

The thickness of such metal layer between 50 and 300 microns

We have 9 devices for Zink Metal Spraying with the arc method

Capacity 1000 tons monthly

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 36: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 36

Each stage of the production process and also final products are tested by qualified inspectors Hot Dip Galvanizing process is monitored by technologists and laboratory assistants

Chemical Laboratory Thickness measurement of the zinc coat

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 37: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 37

Certificate of conformity with DASt-Guideline 022 (Hot dip galvanizing of steel structures for the German market) Hygienic Certificate (National Institute of Hygiene) for hot dip galvanizing European Medal BCC for hot dip galvanizing European Medal BCC for Duplex system

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl

Page 38: Solidny partner w biznesie - Siedlce · PN EN 1090-1 Requirements for conformity assessment for structural components PN EN 1090-2 - Technical requirements for the execution of steel

wwwmostostalcom 38

tel +(48) 25 643 94 57 fax +(48) 25 643 96 57

konstrukcjepolimexpl kraty-handelpolimexpl cynkowaniepolimexpl