Date post: | 27-Mar-2015 |
Category: |
Documents |
Upload: | jordan-armstrong |
View: | 217 times |
Download: | 3 times |
Some things can’t wait for traffic
Capital Beltway HOT Lanes ProjectCapital Beltway HOT Lanes ProjectUpdate – January 2011Update – January 2011
New Travel Choices AheadNew Travel Choices Ahead
Some things can’t wait for traffic
• Project is 55% complete Project is 55% complete
• New bridge spans completed New bridge spans completed at every interchange; at every interchange;
Second phase well underwaySecond phase well underway
• 75% of sound walls completed75% of sound walls completed
• Significant progress on mainline Significant progress on mainline Beltway wideningBeltway widening
– Braddock to Gallows RoadBraddock to Gallows Road– Idylwood Road to Route 7Idylwood Road to Route 7
• Major utility relocations Major utility relocations completedcompleted
Major Milestones Reached in 2010Major Milestones Reached in 2010
Some things can’t wait for traffic
Braddock Rd• New westbound span completed• Old eastbound span demolished• Steel erected for eastbound span
Major Milestones Reached in 2010Major Milestones Reached in 2010
Little River Tnpk• New eastbound span
completed• Old bridges demolished• Steel erected for new
westbound span
Gallows Rd• New southbound span completed• Old northbound span demolished• Steel erected for northbound span
Arlington Blvd• Phase 1 & 2 spans
completed• Old Beltway
spans demolished
Mainline Beltway Significant progress on new outer lanes
Some things can’t wait for traffic
Braddock Rd• Complete new eastbound span• Build HOT Lane connection
Milestones Expected in 2011Milestones Expected in 2011
Little River TnpkComplete new westbound span
Gallows Rd• Complete new northbound span• Begin building HOT Lanes connection
Arlington BlvdComplete finalPhase 3 bridges
Mainline Beltway Shift traffic to new outer lanes by Summer
Some things can’t wait for traffic
Fairfax
Annandale
Tysons
Braddock West to I-495 South Ramp Permanently Closed
Springfield
Braddock Road: New Traffic PatternBraddock Road: New Traffic PatternBraddock Road Westbound to I-495 South - Early 2011
• Left turn with traffic signal to I-495 South• Temporary traffic signal remains in place I-495 South exiting east until Fall 2011
Note: This new configuration is a permanent traffic pattern as part of the final configuration for the Braddock Road interchange
Temp. Traffic Signal I-495 South existing east
Some things can’t wait for trafficMajor Milestones Reached in 2010Major Milestones Reached in 2010
Oak StBridge Completed
Idylwood Rd• Old bridge demolished• Steel, deck completed
Mainline Beltway - Significant progress on new outer lanes: Idylwood Road to Route 7
I-66• Old east and westbound spans demolished• New westbound spans completed• 1st stage of eastbound spans completed
Lee HighwayNew eastbound span completed
W&OD TrailSteel erection completed
Some things can’t wait for trafficMilestones Expected in 2011Milestones Expected in 2011
Idylwood RdBridge completed
Mainline Beltway Shift traffic to new outer lanes by Summer (Idylwood Rd to Route 7)
I-66Complete new I-66 eastbound span and new ramps
Lee HighwayComplete new westbound span W&OD Trail
Bridge Completed
Some things can’t wait for trafficMajor Milestones Reached in 2010Major Milestones Reached in 2010
Jones Branch DriveUtilities, clearing completed
Leesburg Pike RT 7• New westbound
span completed• Steel erected for
new eastbound span
Dulles Toll Road RT 267Steel work completed
Chain Bridge Rd RT 123•New I-495 South bridge completed•Old I-495 North and •South bridges demolished
Westpark Bridge Steel, deck completed for widening
Some things can’t wait for trafficMilestones Expected in 2011Milestones Expected in 2011
Jones Branch DriveComplete HOT Lanes connection
Leesburg Pike RT 7• Complete eastbound
span• Begin and complete 3rd phase – center span Dulles Toll Road RT 267
Complete major steel erection
Chain Bridge Rd RT 123•Complete HOT Lanes spans• Steel erected for I-495 northbound
Westpark Bridge •Complete bridge widening•Steel and deck for HOT Lanes connection
Some things can’t wait for traffic
Mag
arity
Roa
d
Mag
arity
Roa
dLis
le A
veLis
le A
ve
WestinWestin
TowersTowers
LMILMI
Wells
Wells
FargoFargo
MarriottMarriott
TRAFFIC SHIFTTRAFFIC SHIFTEastbound traffic to Eastbound traffic to new eastbound bridgenew eastbound bridge
Tysons
MD
Crescent DrCrescent Dr
Falls Church
• Demolish andDemolish and rebuild center sectionrebuild center section• Build HOT LanesBuild HOT Lanes connectionconnection
Ramp Closed
Ramp Closed Permanently Ramp Closed Permanently Rt. 7 East to I-495 NorthRt. 7 East to I-495 NorthNew Signalized left turn to I-495 North
Route 7: Leesburg PikeRoute 7: Leesburg PikeLate Spring 2011Late Spring 2011 –2012–2012
Some things can’t wait for trafficRoute 123/Westpark Bridge Route 123/Westpark Bridge
October 2009
Some things can’t wait for trafficTysons Galleria
Tysons Corner Center
Galleria Drive
Tysons Blvd
International DriveRoute 123/Westpark BridgeRoute 123/Westpark Bridge2011 - 20122011 - 2012
Dulles Metro
Vienna
Shift I-495 North
Shift I-495 North
Shifted I-495 North
Shifted I-495 North
New I-495 North and HOT Lanes New I-495 North and HOT Lanes bridges under constructionbridges under construction
Some things can’t wait for traffic
October 2009
North
South South
Tysons Corner Center
Tysons Corner Center
Demolished I-495Ramp ClosedRamp Closed
Rt. 123N to I-495NRt. 123N to I-495N
Capital OneCapital One
Traffic Shifted:North
North Bridge
Traffic LightI-495N to Rt. 123STraffic Light
Rt. 123N to I-495NDual Left Turn
Vienna Vienna
McLean McLeanYield
Route 123 Interchange ConstructionRoute 123 Interchange Construction
Traffic Shifts, Ramp Closure, New Traffic Lights Fall – 2010
• New traffic pattern in place until 2012
• Steel erected over I-495 South for HOT Lanes connection to Westpark Br.
• Steel and deck completed for Westpark Bridge widening
• Upcoming steel erections for I-495 Northbound bridges will occur in two stages
Some things can’t wait for traffic
14
Construction begins Spring 2011Construction begins Spring 2011• Close Jones Branch Drive at connection
point for 22 weeks• Jones Branch Drive needs to be raised
8 feet for construction • All businesses remain accessible
Maryland
Springfield
Jones Branch ConnectorJones Branch Connector
Jones Branch D
rive
Some things can’t wait for trafficNew Travel Choices Ahead for TysonsNew Travel Choices Ahead for Tysons
Some things can’t wait for traffic
• Build outer 2 lanes: 2008 – 2011
• Rebuild/lengthen all bridges & overpasses along alignment: 2008 – 2011
• Shift traffic into two new outer lanes: 2011
• Build inner two (HOT) lanes: 2011 – 2012
• Projected HOT Lanes Opening: Late 2012
General Construction PlanGeneral Construction Plan
Some things can’t wait for traffic
• VDOT landscape architect review underway
• Draft plan to be circulated summer/fall 2011 • VDOT landscape architect site visit to review: • Project design• Right-of Way limits• Site distance • Stormwater management • Community may want to apply for a grant to install “gateway”
landscaping• Additional resources available from the Fairfax County Restoration
Project www.fcrpp3.org
Corridor-Wide Landscaping Plan UpdateCorridor-Wide Landscaping Plan Update
Some things can’t wait for trafficTransurban-Fluor Community GrantTransurban-Fluor Community Grant
• Designed for communities located in neighborhoods surrounding project corridor
• Supports grassroots and non-profit organizations that offer significant benefit to environment, safety, aesthetics or well-being of local communities
• Since 2009 launch, grant program has supported nearly 30 local organizations
• Check out www.virginiahotlanes.com/grant for more information
Some things can’t wait for trafficOperations ReviewOperations Review
Some things can’t wait for traffic
Free to HOV-3, buses, Free to HOV-3, buses, motorcycles and motorcycles and emergency vehiclesemergency vehiclesVariable pricingVariable pricing:: tolls rise or fall based on real-time traffic conditions
Not an everyday toll road:Not an everyday toll road: choose to pay a toll when they need a faster, more reliable travel time
Fully electronic tolling with E-Z Pass:Fully electronic tolling with E-Z Pass: Electronic signs display rates; no toll booths
Ride for FreeRide for Free: Carpools (HOV-3), Motorcycles and Emergency Vehicles
How HOT Lanes WorkHow HOT Lanes Work
Some things can’t wait for traffic
• 36 electronic gantries at nine points along the lanes
• Drivers will pass toll points at highway speeds; gantries will identify a vehicle’s entry and exit points, and total trip distance
• More than four times the amount of vehicles per hour expected to move into and out of HOT Lanes compared to cash-based system
First Fully-Electronic Toll Road in Virginia
Some things can’t wait for traffic
Toll pricing, signage, enforcement • Traffic sensors send data to operations center
where toll prices adjusted on real-time traffic volume
• Toll rates displayed on network of electronic message signs
• Signs approaching access points will inform drivers of real-time toll rates so they can decide whether to enter the HOT Lanes
How HOT Lanes Will WorkHow HOT Lanes Will Work
• Electronic toll gantries located at entry/exit points will track a driver’s trip
• All HOT Lanes users must have a transponder
• Drivers are charged one toll based on distance traveled and real-time traffic conditions
• State Troopers enforcement equipped with technology to aid their enforcement
Some things can’t wait for trafficNew Consumer VideosNew Consumer Videos
Some things can’t wait for trafficNew Consumer VideosNew Consumer Videos
Some things can’t wait for traffic
www.VAmegaprojects.comwww.VAmegaprojects.com
Provides information on:Provides information on:lane closures, travel advisories, email lane closures, travel advisories, email alert sign-up, multiple project linksalert sign-up, multiple project links
www.virginiahotlanes.comwww.virginiahotlanes.com
Provides information on:project details/benefits, detailed construction info/timeline, sign up for progress updates and look ahead at future work
Stay InformedStay Informed