+ All Categories
Home > Documents > Sonatrach's _Well Testing

Sonatrach's _Well Testing

Date post: 03-Apr-2018
Category:
Upload: fabian-vargas
View: 222 times
Download: 3 times
Share this document with a friend

of 23

Transcript
  • 7/29/2019 Sonatrach's _Well Testing

    1/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    Introduction to Hydrocarbon Exploitation

    2005 Abalt Solutions Limited. All rights reserved

    Well Testing

    Section

    By Pratap Thimaiah

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Well Testing

    Well testing procedures are a set of tools which

    properly used can provide valuable clues as tothe condition of production or injection wells.

  • 7/29/2019 Sonatrach's _Well Testing

    2/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Well Testing

    Requirements of the following parties should benormally considered:

    Senior Management

    Explorationists

    Petroleum & Reservoir Engineers

    Production & Facilities Engineers

    Drilling Engineers

    Oil & Gas Trading Partners

    Regulatory Authorities

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Generally oil or gas well production tests may

    be classified as:

    1. Periodic Production Tests

    2. Deliverability Tests

    3. Transient Pressure Tests

    Well Testing

  • 7/29/2019 Sonatrach's _Well Testing

    3/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    1. Periodic Production Tests

    Determination of relative quantities of oil, gas and water producedunder normal producing conditions.

    Aid in well and reservoir operations, meeting legal & regulatoryrequirements.

    Productivity or Deliverability Tests

    Performed on initial completions or recompletions to determinewell capability under various pressure drawdown.

    Aid in selection of well completions & artificial lifts.

    1. Transient Pressure Tests

    High degree of sophistication and determines formation damage

    or stimulation related to individual well or reservoir.

    Reservoir parameters such as permeability, pressure, volume and

    heterogeneities.

    Well Testing

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Periodic Production Tests

    Run routinely to physically measure oil, gas &

    water produced from a well under normalproducing conditions.

    Provide physical evidence of well conditions.

    Unexpected changes such as extraneous water

    or gas production may signal well or reservoirproblems.

    Abnormal production declines may meanartificial lift problems, sand fill up, scale etc.

  • 7/29/2019 Sonatrach's _Well Testing

    4/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    For Oil Wells, results reported as

    Oil production rates in bbl/day

    Gas-Oil ratio in ft3/bbl

    Water-oil ratio in % per system

    For Gas wells

    Gas production in mscf(1000 of standard cubic feetper day)

    Gas production in mmscf

    Hydrocarbon liquids or water in bcpmm

    Periodic Production Tests

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Productivity or Deliverability Tests

    Physical or empirical determination of produced fluid flow versusbottom-hole pressure drawdown.

    They predict what the well should produce at other pressuredrawdowns.

    Successfully applied to non-Darcy, below bubble point flow conditions.

    Do not permit calculation of formation permeability or degree of

    abnormal flow restriction near wellbore.

    Used as an indicator of well flow conditions.

    They involve measurement of BH Static and flowing pressure as well asfluid rates produced to the surface

  • 7/29/2019 Sonatrach's _Well Testing

    5/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Types

    For Oil Wells

    Productivity Index

    Inflow Performance

    Flow after flow

    Isochronal or modified isochronal

    For Gas Wells

    Flow after Flow

    Isochronal or modified isochronal

    Productivity or Deliverability Tests

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Transient Pressure Tests

    Essential to analyse the current behaviour and future performanceof the reservoir.

    Designed to provide a quantitative analysis of the reservoirproperties.

    Conducted by creating a pressure disturbance in the reservoir andrecording the pressure response at the wellbore (bottom-holeflowing pressure)

    Most common tests are:

    Pressure drawdown

    Pressure build-up Multi-rate

    Interference Pulse

    Drill Stem

    Fall off Injectivity

    Step rate

  • 7/29/2019 Sonatrach's _Well Testing

    6/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Information available from a well test includes:

    Effective permeability

    Formation damage or stimulation

    Flow barriers and fluid contacts

    Volumetric average reservoir pressure

    Drainage pore volume

    Detection, length, capacity of fractures

    Communication between wells

    Transient Pressure Tests

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Drawdown Test

    Series of bottom-hole pressure measurements during a

    period of flow at constant producing rate.

    Well is shut-in prior to the flow test for a period of timesufficient to allow the pressure to equalize throughout theformation.

    Main objective

    To obtain the average permeability k of the reservoir within

    the drainage area of the well. Sub-objectives

    Assess the degree of damage of stimulation induced in the

    vicinity of the wellbore through drilling and completion practices.

    To determine the pore volume and to detect reservoir

    heterogeneities within the drainage area of the well.

  • 7/29/2019 Sonatrach's _Well Testing

    7/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Drawdown Test

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    During flow at constant rate of Qo, the pressurebehaviour of a well in an infinite-acting reservoir

    (unsteady state flow) is given by:

    Can be re-written as:

    Then:

    Semi-log plot of pressure drawdown data

    Drawdown Test

  • 7/29/2019 Sonatrach's _Well Testing

    8/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Drawdown Test

    Other parameters that can be obtained from plot

    Semi-log plot of pressure drawdown data

    If p wf=p1hr hich is found on the extension of the

    straight line at log t (1 hr), then:

    If pressure data measured at 1 hour do not fall on t hat line, the line must beextrapolated to 1 hour and extrapolated value of p1 hr must be used then.

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Steps involved in drawdown test analysis:

    1. Plot (pi - pwf) versus t on a log-log scale.

    2. Determine the time at which the unit slope line ends.

    3. Determine the corresponding time at 1 log cycle,ahead of the observed time in Step 2. This is thetime that marks the end of the wellbore storageeffect and the start of the semi-log straight line.

    4. Estimate the wellbore storage coefficient from:

    Drawdown Test

  • 7/29/2019 Sonatrach's _Well Testing

    9/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Drawdown Test

    Steps involved in drawdown test analysis continued

    5. Plot pwf versus t on a semi-log scale

    6. Determine the start of the straight-line portion assuggested in Step 3 and draw the best line throughthe points.

    7. Calculate the slope of the straight line and determinethe permeability k and skin factor s by applying the

    equations below:

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    8. Plot all the recorded pressure data after teia as afunction of time on a regular Cartesian scale. Thesedata should form a straight-line relationship.

    9. Determine the slope of the pseudo steady-state line,i.e., dp/dt (commonly referred to as m) and use theequation below to solve for the drainage area A,

    10.Estimate the time to the end of the infinite-acting(transient flow) period, i.e., teia, which marks thebeginning of the pseudo steady-state flow.

    Drawdown Test

    where m = slope of the semi-steady-state Cartesianstraight-lineQ = fluid flow rate, STB/day

    B = formation volume factor, bbl/STB

  • 7/29/2019 Sonatrach's _Well Testing

    10/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Steps involved in drawdown test analysis continued

    11.Calculate the shape factor CA from a expression thathas been developed by Earlougher (1977).Earlougher has shown that the reservoir shape factorcan be estimated from the following relationship:

    12.Use Table of shape factor to determine the drainage

    configuration of the tested well that has a value ofthe shape factor CA closest to that of the calculatedone, i.e., Step 11.

    Drawdown Test

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Pressure Build-up Test

    Describes the build up in wellbore pressure with timeafter a well has been shut in.

    Serves to determine the static pressure

    Also serves to determine:

    Effective reservoir permeability

    Extent of permeability damage around the wellbore

    Presence of faults and to some degree the distance tothe faults

    Any interference between producing wells

    Limits of the reservoir where there is not a a strongwater drive or where the aquifer is no larger than thehydrocarbon reservoir.

  • 7/29/2019 Sonatrach's _Well Testing

    11/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Pressure Build-up Test

    In pressure build-up and drawdown analyses,the following assumptions are usually made:

    With regard to reservoir

    Homogeneous

    Isotropic

    Horizontal of uniform thickness

    With regard to fluid

    Single phase

    Slightly compressible

    Constant mo and Bo

    With regard to flow behaviour

    Laminar flow

    No gravity effects

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Pressure Build-up Test

  • 7/29/2019 Sonatrach's _Well Testing

    12/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Horners Plot

    Pressure Build-up Test

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    The Back-Pressure Test-Flow after Flow

    Conventional deliverability test: gauging the ability of the well to flowagainst various back pressures. Rawlins and Schellhardt (1936)

    Shut in the gas well sufficiently long for the formation pressure toequalize at the volumetric average pressure

    Place the well on production at a constant flow rate Qg1 for asufficient time to allow the bottom-hole flowing pressure tostabilize at pwf1 to reach the pseudo steady state.

    Repeat step 2 for several rates and the stabilised bottom-hole flowpressure is recorded at each corresponding flow rate. If three orfour rates are used, the test may be referred to as three-point orfour-point flow test.

  • 7/29/2019 Sonatrach's _Well Testing

    13/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    The Back-Pressure Test

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Conventional back-pressure test

    Length of the flow periods is the most importantfactor to be considered in performing theconventional deliverability test.

    Each rate must be maintained sufficiently long for thewell to stabilise to reach the pseudosteady state.

    The stabilisation time for a well in the centre of acircular or square drainage area may be estimatedfrom:

    The Back-Pressure Test

  • 7/29/2019 Sonatrach's _Well Testing

    14/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Isochronal Tests

    Developed to shorten test times in wells that take long time to stabilize

    Series of single point tests developed to estimate stabilizeddeliverability characteristics without actually flowing the well for timerequired to achieve stabilized conditions.

    Conducted by alternatively producing the well, shutting in the well andallowing it to build-up average reservoir pressure before beginning ofthe next production period.

    Pressures are measure several time increments during each flowperiod.

    Ex- BHFP could be measured at 0.5,1.0,1.5 etc hrs after beginning ofeach flow period.

    More practical for low-permeability formations.

    Although not required, a final stabilized flow point usually is obtained atthe end of the test.

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Isochronal Tests

  • 7/29/2019 Sonatrach's _Well Testing

    15/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Modified Isochronal Tests

    Time to build up to average reservoir pressure before flowing for acertain period of time may be impractical.

    Isochronal test is modified to shorten test times further and obtainsame data without using the sometimes lengthy shut-in periods

    required to reach average reservoir pressure in the wells drainage

    area.

    The shut-in periods are of equal duration & should equal or exceed

    length of flow periods.

    Shut-in sand face pressures are recorded immediately before each flow

    period and used instead of average reservoir pressures.

    This test is less accurate than the isochronal test.

    Note-As the duration of the shut-in periods increases, the accuracy ofthis test also increases.

    Although not required, a final stabilized flow point usually is obtained at

    the end of the test.

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Modified Isochronal Tests

  • 7/29/2019 Sonatrach's _Well Testing

    16/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Drill Stem Testing

    Provides a method of temporarily completing a well and determining itsproductive characteristics of the specific zones

    DST can provide

    Good data to evaluate productivity zone

    Completions practises

    Extent of formation damage

    Need for stimulation

    Reservoir characteristics that can be estimated from analysis are:

    Average effective permeability

    Reservoir pressure

    Wellbore damage Barriers, permeability changes & fluid contacts

    Radius of investigation

    depletion

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    DST Operations

    Running in hole on drill pipe, bottom hole assemblyconsisting of a packer and a surface operated valve.

    The DST valve is closed while running the drill string,thus pressure inside the drill pipe is very lowcompared to hydrostatic mud column pressure.

    On bottom, the packer is set to isolate desiredformation zone from mud column and control valveis opened to allow formation fluids to enter the drillpipe.

    After a suitable time valve is closed and pressurebuilds-up.

    Control valve is opened again, and the flowing andshut-in periods are repeated to obtain additionaldata

    Drill Stem Testing

  • 7/29/2019 Sonatrach's _Well Testing

    17/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Sequence of Operation:

    Tool is lowered on the drill pipe to a position opposite to theformation to be tested.

    Packer expands against the hole to segregate the mud filledannular section from the interval of interest.

    The test valve allows formation fluids to enter the drill pipeduring the test.

    The equalizing valve allows pressure equalization after the testso the packer can be retrieved.

    By opening the test valve a decline in pressure is obtained.

    During the test, pressures and flow rates are measured as afunction of time.

    Drill Stem Testing

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Drill Stem Testing

  • 7/29/2019 Sonatrach's _Well Testing

    18/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Pressure Vs. Time Plot Point A: As the tool is run in hole the Initial hydrostatic mud pressure is

    recorded.

    Point B: Initial shut in pressure, which is measured by closing the controlvalve and allowing pressure build-up towards static reservoir pressure.

    Point C: Second flowing and shutting in periods permits the calculation ofreservoir parameters. As the control valve is opened, pressure falls to initialflowing pressure.

    Point D: As fluids move up the drill pipe, pressure increases due to flowrestrictions in tools. After a suitable time, the tool is shut-in and termed finalflowing pressure.

    Point E: Pressure then increases to final shut-in pressure

    Drill Stem Testing

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Recommendations We have to consider that the main objective is to record good data.

    Therefore the DST must be planned to accommodate any specificsituation.

    FIRST FLOW: (5-15 minutes), the objective is to remove any excesspressure which may have resulted from setting the packers.

    FIRST BUILD UP: (30-60 minutes)

    SECOND FLOW: (60 minutes)

    SECOND SHUT IN: ( from 30 minutes to several hours) finding out thetransmissibility and other characteristics of the reservoir.

    Drill Stem Testing

    Pressure

    Time

    1 2

    3

    4

    56

    1. Going into the hole2. Initial flow period

    3. Initial shut-in period4. Final flow period5. Final shut-in period6. Coming out of the hole

  • 7/29/2019 Sonatrach's _Well Testing

    19/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Drill Stem Testing

    Analysis methods:

    Horners Plot method to determine permeability

    Type curve matching method to account for wellbore storage.

    Kohlaas type curve matching to determine

    Correa & Ramey for multiphase environments

    Computer matching DST

    /kh

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Injection Well Tests

    Pressure transient testing during injection into

    a well.

    Important for efficient planning & operation ofboth secondary and tertiary recovery projects.

    For analysis, the mobility ratio of injected fluid

    and in situ fluids must be near unity.

    Mobility Ratio

    M= (k/)w(k/)o

    Ratio of mobility of the displacing (injected) fluid to the fluidbeing displaced.

  • 7/29/2019 Sonatrach's _Well Testing

    20/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Procedure Well Shut-in to allow pressure to

    stabilize at initial reservoir pressure

    pi.

    Test begins at t=0 with constant

    injection rate q (taken ve).

    For the constant rate, the injection

    bottom hole pressure Pwf is

    modelled.

    Plot of BHP Pwf vs. logarithmic

    injection time t is plotted and

    forms a straight line with slope m.

    Allows the estimate of formation

    permeability k and skin factor s.

    Injection Well Tests

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Step Rate Injectivity Testing

    Normally used to estimate formation or fracture

    parting pressure, which is the injection pressurethat will initiate a fracture in an un-fractured well orextend an existing fracture.

    Parting pressure determined from the test is

    equivalent to fracture extension/propagationpressure in hydraulic fracturing.

    Helps determine that any injection above parting

    pressure will can result in pre-mature breakthrough, poor sweep, reduced oil recovery etc.

    Procedure

    Well shut-in before test begins .BHP nears

    static reservoir pressure.

    Injection rate stabilized at reduced andconstant rate,stabalization period should belong to achieve steady state or pseudo-steady

    state flow.

    Injection rates are increased step wise.

    In low permeability formations (k10 mD)injection rates of 30 mins is adequate.

  • 7/29/2019 Sonatrach's _Well Testing

    21/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Interference Tests

    Involves creating pressure disturbances in one well and

    measuring the pressure response in the other wells.

    Done by either producing from or injecting into at least onewell, called active well, and observing the pressure response inanother well called observation well.

    Characteristics of pressure behaviour as function of timereflects the reservoir properties.

    Tests can be conducted with more than one active and more

    than one observation well.

    These tests are ideal for establishing continuity of pay zonewithin the reservoir ,estimating volume of hydrocarbons withindrainage area of wells and quantifying reservoir anisotropies.

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Note that a time lag exists between the time when a rate

    change is made at active well and time when pressure transientis seen in the observation well.

    Interference Tests

  • 7/29/2019 Sonatrach's _Well Testing

    22/23

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    A coded signal is sent from anactive well to a shut-inobservation well.

    Signal is generated by producingfrom or injecting into the activewell, shutting in the well,producing again, shutting inagain, and repeating in a regularpattern.

    The well is pulsed so that we canidentify effective of active well onpressure response at observationwell amid noise of reservoirpressure trend.

    Highly sensitive pressure gaugesare used.

    These tests can quantifydirectional reservoir properties,such as permeability.

    Advantages

    Fewer problems withreservoir noise & pressuretrends that cause errors.

    Pulse Tests

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Surface Test Equipments

    Surface Test Tree

    Used in DST operations and are four-way cross with four valves.

    Surface test tree should be able to support the full string weight

    and all four valves should provide a seal with differential pressure.

    Surface test trees with have either a master or production wingvalve or both, hydraulically operated.

    Most trees include a swivel to allow pipe rotation to set packers

    during tests.

    Coflexip Hoses

    High pressure hose used between surface trees & choke manifoldson tests conducted from floating rigs.

    Allows good flexibility & better corrosion resistance.

    Rig permanent Pipe works Information regarding line size, wall thickness, sour service, i nspection

    reports must be checked.

    High and low pressure pipe works need to be present.

  • 7/29/2019 Sonatrach's _Well Testing

    23/23

    Development Phase

    September October 2005abalt solutions limited 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Hydraulic surface safety valve Free standing valve incorporated for additional safety. Used where long high pressure flow lines are used.

    Sand trap Functions as sand separator during testing and used when

    excessive sand production is anticipated.

    Consists of 2 vertical cylinders with screen meshes of varying s izes Normally installed between flow head and choke manifold.

    Sand detection equipment Has an intrusive probe set into the flow line. Used to detect sand grains across multiphase flow conditions.

    Data reader Used to monitor wellhead pressure and temperatures and chemical

    injection upstream of choke.

    Surface Test Equipments

    WellTesting

    2005 Abalt Solutions Limited. All rights reserved

    Other equipments Gauge tanks

    Surge tanks

    Transfer pumps

    Gas diverter manifold

    Oil diverter manifold

    Burners

    Flare lines

    Vent lines

    Emergency shut down systems

    Relief lines

    Surface Test Equipments


Recommended