+ All Categories
Home > Documents > SOP Airport1 Final

SOP Airport1 Final

Date post: 03-Jun-2018
Category:
Upload: vinayak
View: 222 times
Download: 0 times
Share this document with a friend

of 42

Transcript
  • 8/11/2019 SOP Airport1 Final

    1/42

    BITSPilaniHyderabad Campus

    FEASIBILITY OF ESTABLISING

    AIRPORTS IN MEDIUM CITY

    Kaashyap Sarma-2011A2PS378HCourse Name: Study Project

    Supervisor: Dr.V. Vinayaka Ram

  • 8/11/2019 SOP Airport1 Final

    2/42

    BITS Pilani, Hyderabad Campus

    Objectives of the Project

    1. To study the factors controlling airport planning and

    establishment

    Segregating the factors into two broad sectors:

    Technical point of View

    Financial Point of View

    2. Understanding the factors & aspects from the abovementioned outlooks.

    3. Study a sample case study pertaining to the above study.

  • 8/11/2019 SOP Airport1 Final

    3/42

    BITS Pilani, Hyderabad Campus

    What is Planning?

    Planning Philosophy in Airport Design

    The efficient airport as a whole is that which provides the

    required capacity for aircraft, passenger, cargo and vehicle

    movement with maximum passenger, operator and staff

    convenience and at lowest capital and costs.

  • 8/11/2019 SOP Airport1 Final

    4/42

    BITS Pilani, Hyderabad Campus

    Broad determination of the land area required.

    Evaluating of factors affecting airport location.

    Preliminary office study of possible sites.

    Site inspection.

    Environmental study.

    Review of potential sites.

    Preparation of outline plans and estimates of costs

    and revenues.Final evaluation and selections.

    Report and recommendations.

    Airport Site Assessment andSelection

  • 8/11/2019 SOP Airport1 Final

    5/42

    BITS Pilani, Hyderabad Campus

    Regional Plan

    Airport Use

    Proximity to other airports

    Ground accessibility

    Obstruction Clearance

    Visibility

    Topography

    Wind factor Noise Effect

    Weather Factors

    Soil Characteristics

    Airport Site Selection

  • 8/11/2019 SOP Airport1 Final

    6/42

    BITS Pilani, Hyderabad Campus

    Aranmula Airport-Kerala

    This airport is said to be planned to be built upon 700

    acres of land Total Budget Cost-Around 2000 Crore Rupees.

    The terminal building is being designed to handle 1,000

    passengers at a time.

    The main advantage of installing this airport is it wouldboost up the employment rate by creating 1500 direct

    and 6000 indirect jobs.

    Sample Case Study

  • 8/11/2019 SOP Airport1 Final

    7/42BITS Pilani, Hyderabad Campus

    The airport, which is less than 100 km from Cochin InternationalAirport and Trivandrum International Airport, is expected to serve

    four districts in Kerala state, namely Pathanamthitta and some areas

    of Kottayam, Idukki and Alappuzha.

    The project is being funded through equity and debt. The equity

    portion accounts for around Rs 10 billion. The debt-equity ratio is1:1. Three banks including ICICI, IDBI Bank and SBI have funded

    the debt portion.

    The Kerala government has a 10% stake in the company and has

    nominated one member to the board of the company, while the

    Government owned oil company Indian Oil Corporation isnegotiating to pick up a 10% stake. The first phase of the project is

    expected to cost Rs 7.50 billion.

  • 8/11/2019 SOP Airport1 Final

    8/42BITS Pilani, Hyderabad Campus

    ECONOMIC FEASIBILTY

    The Enviro Care report states that the Aviation market in

    the state of Kerala grew faster than the rest of the nation

    which is one of the fastest growing aviation industries in

    the world.

    The government's partial open sky policy has led to

    many overseas players entering the market and the

    industry has been growing both in terms of players and

    number of aircraft.

  • 8/11/2019 SOP Airport1 Final

    9/42BITS Pilani, Hyderabad Campus

    Year Duration

    Passenger Traffic Growth RATE- INDIA

    Passenger Traffic Growth RATE- Kerala

    Air Traffic Growth Rate

    Year Duration Passenger Traffic Growth

    RATE- INDIA

    Passenger Traffic Growth

    RATE- Kerala

    2003-04 11%

    2004-05 22%

    2005-06 24%

    2006-07 31% 31.28%

    2007-08 21% 23.74%

    2008-09 6.85% 3.15%

    2009-10 15% 11.66%

    2010-11 16% 10.23%

  • 8/11/2019 SOP Airport1 Final

    10/42BITS Pilani, Hyderabad Campus

    The proposed Airport would provide transport infrastructure topilgrims who wish to travel by air to Sabarimala, the second

    largest pilgrim center in India with annual pilgrims of around 60

    Million (as per Government data for the year 2011).

    The airport is expected to serve Central Travancore region,

    comprising parts of five districts in Kerala state namelyPathanamthitta, Alappuzha, Kottayam, Idukki and Kollam. Out of the

    foreign and domestic tourists' arrival to Kerala, these five districts

    together account for about 21 per cent of foreign tourists and 14

    percent of domestic tourists

  • 8/11/2019 SOP Airport1 Final

    11/42BITS Pilani, Hyderabad Campus

    A Forecast of Indian air traffic has concluded that the domesticpassenger throughput would grow at an average annual rate of

    around 12% between FY-12 and FY-17. The domestic passenger

    throughput is expected to touch around 209 million by FY-17 from 106

    million in FY-11. Similarly, international passenger throughput is

    estimated to grow at an average annual rate of 8% to reach 60 millionpassengers by FY-17 from 38 million in FY-11.

    Global comparison of air travel penetration shows that India stands

    far behind the developed countries like US and Australia (2 air-trips

    per capita per annum). Chinas domestic traffic is five times that ofIndia despite having a population just 10% larger. There is significant

    growth potential as high as 50 times for the Indian civil aviation

    industry as the economy grows, disposable incomes rise and the

    value of time becomes more precious.

    Air Traffic Demand

  • 8/11/2019 SOP Airport1 Final

    12/42BITS Pilani, Hyderabad Campus

    Even though Kerala has only 2.75% of the overall population of India,

    the International aircraft movement in Kerala is 15.28% of overall

    international aircraft movement of India in the year 201112

    During the year 201112, the total number of air passengers to Kerala

    is 9,742,000 compared with 162.3 million air passengers throughout

    India.

    In Kerala, air traffic is evenly spread over the 3 existing airports-Kochi,

    Trivandrum and Kozhikode unlike its neighboring three states of Tamil

    Nadu, Andhra Pradesh and Karnataka where one

    airport viz. Chennai, Hyderabad and Bangalore caters to 80% of the airtraffic of the entire state.

  • 8/11/2019 SOP Airport1 Final

    13/42BITS Pilani, Hyderabad Campus

    ALL was seeming so well financially,

    wasntit?

    Promoters get their piece of pie,

    employment rate boosts up. So itsa win-win, right?

    Apparently it was not!

  • 8/11/2019 SOP Airport1 Final

    14/42BITS Pilani, Hyderabad Campus

    The Kerala State Biodiversity Board observed that 80% of the 500acres earmarked for the project were paddy fields. Conversion of a

    portion of the 3,500-acre paddy field would "impact on the remaining

    wetlands, disturb the food chain, and accelerate the depletion of fish

    resources as well as other flora and fauna in the Pamba river basin.

    The runway is being constructed over the Kozhithode canal, which

    is a tributary of the Pamba river. Several species of fish migrate

    upstream from the river through the canals to the water-logged

    paddy fields. Reclamation of these wetlands would deprive the fishof their breeding grounds. Razing hills in the neighborhood for soil to

    reclaim the fields could lead to biodiversity loss and water shortage.

    Heres the Problem

  • 8/11/2019 SOP Airport1 Final

    15/42BITS Pilani, Hyderabad Campus

    Clearly this environmental violation is a cause for whichmany people are protesting against and the people of

    that area quote that such a large project would cause

    irreparable and devastating damage to the environment

    and ecosystem

    Conclusion

  • 8/11/2019 SOP Airport1 Final

    16/42BITS Pilani, Hyderabad Campus

    The case study which I have adopted for my study post

    mid-semester is on the Navi Mumbai International

    Airport(NMIA)

    The proposed airport at Navi Mumbai is located nearPanvel Town on NH4B at a distance of35 km from the

    existing Sahar International Airport in Mumbai. A total

    area of about 2054 Ha is earmarked for the development

    of Navi Mumbai International Airport consisting of airportzone and the area required for offsite infrastructure

    CASE STUDY-2

  • 8/11/2019 SOP Airport1 Final

    17/42BITS Pilani, Hyderabad Campus

    The project is proposed to be executed on the basis ofpublic-private-partnership (PPP)

    The main feasibility analysis is obtained by considering 4

    factors:

    Air Traffic Demand

    Site Evaluation and Project Detailing

    Project Phasing and Cost

    Preliminary Analysis

    INTRODUCTION

  • 8/11/2019 SOP Airport1 Final

    18/42BITS Pilani, Hyderabad Campus

    The Navi Mumbai International Airport (NMIA) isproposed to be developed in an area of 2,054 hectares,

    accommodating parallel independent runways for

    simultaneous and independent operations.

    The airport site is large enough to develop a two runway

    system and is located next to two very important

    communication corridors.

    SITE SELECTION AND PROJECTDETAILING

  • 8/11/2019 SOP Airport1 Final

    19/42BITS Pilani, Hyderabad Campus

    Airport Layout Plan

  • 8/11/2019 SOP Airport1 Final

    20/42BITS Pilani, Hyderabad Campus

    The site has a very good railway connection, whichwould be completed with branches linking directly to the

    current lines with the airport. From the point of view of

    railway connections, this site has great accessibility.

    The site is also said to be suitable considering the windfactors.

    However not all the clearances were sanctioned, a

    few objections were raised too

  • 8/11/2019 SOP Airport1 Final

    21/42BITS Pilani, Hyderabad Campus

    Objections were raised by the Union Ministry of Environment andForests on the current proposed location of NMIA, apparently

    because the construction of the airport would involve reclamation of

    low-lying areas in an ecologically fragile zone as well as destruction

    of several hectares of mangroves.

    There are serious environmental issues. Its construction woulddamage mangrove cultivation in the 2,000 ha (4,900 acres), besides

    the diversion of Gadhi and Ulwe rivers, which according to the Union

    Environment and Forests Ministry is a very serious issue

    considering the destruction Mumbai faced during the 26 July 2005

    floods. As a result of these new developments other locations wereconsidered.

    OBJECTIONS RAISED

  • 8/11/2019 SOP Airport1 Final

    22/42

    BITS Pilani, Hyderabad Campus

    The airport is facing hurdles in the acquisition of private land. Theairport requires 2,042 ha CIDCO needs to acquire 424 ha of

    privately owned land for which CIDCO officials and the State

    Government have been negotiating with the residents of seven

    villages.

    Land acquisition is stuck as the villagers (5,000 families) aredemanding a higher compensation package of 200 million per

    acre. CIDCO then formed a committee composed of the divisional

    commissioner of the Konkan division and local politicians. The

    committee had offered the project-affected-people (PAP) two

    rehabilitation-related compensation options:a) 12.5% of developed land at the ready reckoner rates, in addition to

    monetary compensation

    b) 22.5% developed land in Navi Mumbai.

    LAND ACQUISTION

  • 8/11/2019 SOP Airport1 Final

    23/42

    BITS Pilani, Hyderabad Campus

    India has been experiencing a major expansion of the air

    transportation industry. The total number of commercial

    passengers using Indian airports almost doubled over

    the four years between 2004-05 and 2007-08 from 59 tomore than 116 million.

    This growth has averaged 24.4% per year and has been

    particularly high for domestic traffic.

    AIR TRAFFIC DEMAND

  • 8/11/2019 SOP Airport1 Final

    24/42

    BITS Pilani, Hyderabad Campus

    The primary Air traffic analysis was done by looking at the

    Historical Air traffic trend of MMR

    MMR Demand Forecast

    NMIR Demand Forecast

    It has to be observed that from whatever data we will be

    having, the speculation or the forecast is done initially for

    the MMR zone and then this forecast is projected on to

    the NMIR Demand.

    ANALYSIS

  • 8/11/2019 SOP Airport1 Final

    25/42

    BITS Pilani, Hyderabad Campus

    The driving forces behind this rapid growth in air traffic are:

    1. Deregulation of the aviation sector.

    2. Positive macro economic trends

    3. Tourism

    4. The Emergence of Low Cost and Premium Service

    Carriers

    Why the Rapid Growth??

  • 8/11/2019 SOP Airport1 Final

    26/42

    BITS Pilani, Hyderabad Campus

    CSIA experienced relatively modest slow growth in the number ofpassengers over the two decades preceding the liberalization of the

    Indian air transportation industry during 2003-04, doubling from 6.4

    to 13.3 million passengers (at an annual average compound growth

    rate of 3.5%).

    This growth trend has been interrupted during the current year(2008-09); initially by spiking fuel prices last summer, followed by

    the impact of the worldwide financial crises.

    Though the overall trend during those two decades was generally

    positive, there was significant year to year variation, with temporary

    declines in traffic during the economic recession of the early 1990sand in the period immediately following the terrorist attacks of

    September 11, 2001

    HISTORICAL TREND

  • 8/11/2019 SOP Airport1 Final

    27/42

    BITS Pilani, Hyderabad Campus

    During both previous periods, the number of domesticpassengers had grown at over twice the rate of

    international passengers, but it is also the traffic segment

    most affected by the current crisis.

    Though it is not indicated in these tables, this boomperiod seems to have recently come to an end as the

    industry was hit hard by high fuel costs this past summer

    and the current worldwide financial crisis.

    HISTORICAL TREND

  • 8/11/2019 SOP Airport1 Final

    28/42

  • 8/11/2019 SOP Airport1 Final

    29/42

    BITS Pilani, Hyderabad Campus

  • 8/11/2019 SOP Airport1 Final

    30/42

    BITS Pilani, Hyderabad Campus

    These forecasts were developed using a two step process:

    1. Develop econometric forecasting models according to

    industry practices.

    2. Adjust forecasts for short-term and long-term industry

    trends not reflected in the econometric modelling.

    MMR Demand Forecast

  • 8/11/2019 SOP Airport1 Final

    31/42

    BITS Pilani, Hyderabad Campus

    The specific factors that were considered in this particular case are:

    1. The extent and duration of the impact of the current downturn in air

    traffic caused by fluctuating fuel costs and what has become a

    worldwide financial crisis.

    2. The extent to which an eventual recovery of the world economy will

    lead to a return to the projected medium to long-term trend line (asestablished by the econometric model).

    3. Whether it is feasible to assume that domestic traffic will indefinitely

    continue growing faster than international traffic.

    4. Whether the long-term growth rates resulting from the econometric

    analysis are sustainable in the very long-run once the market begins

    to mature.

    MMR Demand Forecast

  • 8/11/2019 SOP Airport1 Final

    32/42

    BITS Pilani, Hyderabad Campus

  • 8/11/2019 SOP Airport1 Final

    33/42

    BITS Pilani, Hyderabad Campus

    The base forecasts for the High and Low scenarios wereestimated using the same equations, but applying High

    and Low forecasts of the primary independent variables.

    The same adjustment was carried out for 2008-09. In the

    case of 2009-10, the following adjustments were made:

    High: The growth rate predicted by the regression

    equation was multiplied by 0.8.

    Low: The regression growth rate was multiplied by 0.2.

    These multiplication factors are obtained from the

    previous regression constants

    Forecast Scenarios

  • 8/11/2019 SOP Airport1 Final

    34/42

    BITS Pilani, Hyderabad Campus

    The procedure followed to allocate potential passengertraffic is the following:

    Review airline preferences and plans

    Estimate the proportion of the passenger and cargo

    markets for which NMIA has a comparative advantage

    Analyse saturation levels at CSIA

    Derive passenger levels at NMIA

    Derive cargo levels at NMIA

    NMIA Passenger Forecast

  • 8/11/2019 SOP Airport1 Final

    35/42

    BITS Pilani, Hyderabad Campus

    The primary results are:

    NMIA is forecasted to handle over 20 million passengers by the end

    of Phase 1 in 2017-18. This would increase to just under 40 million

    passengers by 2022-23 and almost 62 million by 2031-32.

    International passengers are forecasted to reach over 10 million

    passengers by the end of Phase 2 and over 16 million by 2031-32

    Domestic passengers are forecasted to reach over 28 million by

    2022-23 andover 44 million over the long run.

    Direct international transit passengers are forecasted to increase toover 1 million over the first 24 years of operation of the airport.

    RESULTS

  • 8/11/2019 SOP Airport1 Final

    36/42

    BITS Pilani, Hyderabad Campus

    Phase 1 (2013-14 to 2016-17): In Phase 1, the airport is initiallydesigned with a level of service adequate to satisfy the demand of

    10 million passengers.

    Phase 2 (2017-18 to 2021-22): The Phase 2 development at the

    airport is designed to meet the demand for 25 million passengers.

    Phase 3 (2022-23 to 2026-27): The Phase 3 development of theairport is designed with a level of service adequate to satisfy a 45

    million passenger's demand.

    Phase 4 (2027-28 to 2031-32): The airport is ultimately designed

    with a level of serviceadequate to satisfy a 60 million passengers

    demand by providing NMIA with additional boarding gates and apronarea to satisfy the additional demand

    PROJECT PHASING

  • 8/11/2019 SOP Airport1 Final

    37/42

    BITS Pilani, Hyderabad Campus

    Development Stages

  • 8/11/2019 SOP Airport1 Final

    38/42

    BITS Pilani, Hyderabad Campus

    Project Cost by Phases

  • 8/11/2019 SOP Airport1 Final

    39/42

    BITS Pilani, Hyderabad Campus

    The primary results of this analysis are presented in termsof the following indicators:

    Net Present Value (NPV) of the annual net cash flows

    Internal Rate of Return (IRR)

    FINANCIAL FEASIBILITY

  • 8/11/2019 SOP Airport1 Final

    40/42

    BITS Pilani, Hyderabad Campus

    The final results which were obtained included the followingmethodology

    Estimating revenues at each Airport over the various development

    phases, based on traffic projections and the price and tariff for use of

    the terminals, facilities and services

    Project annual Operating Costs (OPEX) for the various facilities,including personnel, administration and maintenance;

    Incorporate the preliminary cost estimates (CAPEX) for investment

    requirements

    Prepare annual cash flows for the established planning horizon (30

    years)

    Determine the financial viability of the project in terms of its

    Financial Internal Rate of Return (IRR) under different scenarios

  • 8/11/2019 SOP Airport1 Final

    41/42

    BITS Pilani, Hyderabad Campus

    FINAL RESULTS

  • 8/11/2019 SOP Airport1 Final

    42/42

    BITSPilaniHyderabad Campus

    Thank You


Recommended