Sound TransitCapitol Hill Station Construction Noise and Project Update
June 17, 2009
6:00 – 8:00 PM
3
Agenda6:00 Open House
6:30 Presentations– Welcome (Ron Endlich)
– Project Overview (Michelle Ginder) – Construction sequence and activity
– Construction Updates (ped safety, site walls)
• Nighttime Construction Noise (Jeff Munnoch)– Noise Variance Process
– Noise Impacts and Mitigation
– Community Involvement and Next Steps
7:15 Q & A
7:45 Return to Open House
4
• 3.15-mile extension of Initial Segment and Airport Link– Capitol Hill Station– UW Station and crossover
• Schedule– Design: completed– Construction: 6.5 years– System testing: 6 months– Open for Service: 2016
• Adds 70,000 daily riders, 114,000 riders systemwide (2030)
University Link
5
Capitol Hill Station
• Underground station with 3 entrances
• Staging area - station and tunnel excavation at site
• Ridership: 14,000 daily boardings
• Travel time: – 6 minutes to downtown
Seattle (University St.)
– 3 minutes to UW Station
6
Capitol Hill Station Schedule
1
2
3
4
7
1. Demolition and Remediation• Jan. 2009 to mid-2009• 75% Recycling and salvage
goal being met• Construction trailers• Site will be lowered, paved
and remain fenced
8
Recycled and Salvaged Items
• A large amount of materials that otherwise would have been taken to landfills has been removed for re-use.
• Recycled Demolition Material to Date: 2,890 Tons
9
2. I-5 Undercrossing Work
Paramount
Theater
Convention Place Station
PINE STREET
BO
REN
STREET
NB
I-5
SB
I-5
Work Area
Wo
rk Area
• I-5 undercrossing contract awarded in February
• Prepares I-5 structures for future tunnel boring machines– Work being done now to avoid
conflicts with other WSDOT freeway work and later U-Link contracts
– Coordinated agency outreach to public on ramp closures
– Contractor incentives to complete the work early
10
I-5 Ramp Closures
Pine Street
Pike Street
Detour info at www.soundtransit.org/u-link
11
3. Station Excavation, Tunneling• Jan. 2010 to Dec. 2012• Fenced work sites• Denny Way and parts of Nagle Place
closed to traffic• Sidewalks open
– Will be few short term closures
• Single Tunnel Boring Machine (TBM)• 24/7 surface activity to support
tunneling• High truck volumes
12
Construction Walls• Plywood walls will surround and screen main
construction site perimeter 2010-2015• Wall Height:
– 8 ft. tall along Broadway– 16 ft. tall along 10th Ave– Transition from 8 to 16 ft. along northern (John St.) and
southern borders
• Contractor required to maintain fence (repaint annually, graffiti removal within 24 hours)
• Appearance will include ST Art program elements, ST project information, and Capitol Hill business marketing elements
13
Truck Haul Routes(beginning 2010)
• High visibility crossing signs
• Re-stripe crosswalks• Restrict parking at
intersections
14
SDOT Pedestrian Improvements
• Crosswalk and warning signs on the east leg of Summit Ave and Denny Way
• Curb bulb on the SW corner of E Denny Way and Boylston Ave.
• Further options to improve the crossing of Olive Way at Boylston Ave. are under consideration
15
4. Station Construction• Jan. 2013 to Dec. 2015• Less trucking activity• Sidewalks open
– Will be few short term closures• Cut and cover pedestrian tunnel
across Broadway (6 months)– Roadway remains open– Parking restrictions near work
16
Capitol Hill Station
Construction Noise Variance for Nighttime Construction
17
Why must work occur at night?
• Anticipate two years of 24/7 construction activity to support tunneling work at Capitol Hill site beginning in early 2011
• Certain activities are required for tunnel worker safety• Maximizes project safety, efficiency, duration and cost
18
What goes on at night?
• No high impact equipment (jackhammers, concrete saws, etc.)
Type of Equipment:
• Tunnel ventilation fans, pumps, air compressors
• Generators
• Vehicles– hauling and delivery trucks– muck haul trucks– front-end loaders, backhoe– loaders, excavators
19
Noise Mitigation Requirements
Solid plywood construction screening wall between 8-16’ tall around site
20
Stationary equipment (compressors, generators) enclosed in noise reducing material
Noise Mitigation Requirements
21
• Nighttime Truck Operations– No tonal back up alarms– Engine idle limit of 5 minutes– Haul trucks prohibited on 10th
Ave E during night hours – No compression brakes– Muck haul bins lined with
noise dampening material
Noise Mitigation Requirements
22
Existing noise on 10th Ave
Existing noise on Broadway
23
Nightime Noise PredictionsHourly night-time average
54 dba existing65 dba construction+ 0 to11 dba
65 dba existing70 dba construction
+ 0 to 5 dba
24
Monitoring and Responding to Complaints
• Continuous sound monitoring stations • 24 - hour construction hotline: 1-888-298-2395 • Independent response by City Noise Abatement
Specialist • City, ST and contractor will investigate, determine how
to prevent future incidents, and respond back to caller• City review after 1 year
25
Capitol Hill Site Noise Variance• Requires application for Major Public Project Construction Noise
Variance from City of Seattle • Noise variance establishes noise limits for contractor work between
10pm - 7am weekdays, 10pm - 9am weekends, holidays • Daytime construction activities will comply with City’s construction
noise limits
26
Next Steps
• Receive comments and questions tonight
• ST to incorporate feedback into variance application
• City of Seattle (DPD) will hold a public meeting to receive comments late summer
• City will decide whether to approve a noise variance within 60 days after public comment is received
• Contractor will prepare a detailed noise management plan
• Follow-up information at meeting(s) later this year
• Tunnel construction activities begin – early 2011
27
Staying Informed
• Monthly electronic newsletters www.soundtransit.org/subscribe
• Printed and electronic construction alerts
• Regular construction update meetings
• Full time outreach staff
• 24 hour construction hotline 1-888-298-2395