© 2015 HDR, all rights reserved. South Well Field and Water Treatment Plant Pre-Procurement Meeting City of Salina, Kansas September 13, 2016
Transcript

© 2015 HDR, all rights reserved.

South Well Field and

Water Treatment Plant

Pre-Procurement Meeting

City of Salina, Kansas September 13, 2016

INTRODUCTIONS

SYSTEM OVERVIEW

PROJECT OVERVIEW

WATER SUPPY SCOPE

WATER TREATMENT ALTERNATIVES

CITY’S OBJECTIVES

PROGRESSIVE DESIGN BUILD PROCESS

GENERAL PROCUREMENT PROCESS

Martha Tasker, Director of Utilities

Bernie Kitten, Plant Operations Manager

Mark Peterson, Electrical Engineer

Ray Starnes, Lead Water Plant Operator

City Staff - Owner

Lorrie Hill, Project Manager

Don Lindeman, Client Manager

Jessica Adams-Weber, Project Engineer

Stan Christopher, Project Principal

HDR Staff – Owner’s Representative

Introductions

Purpose and Objectives of Meeting

Introduce interested parties to the project

Opportunity for interested parties to meet key staff

Downtown Facilities

o Downtown WTP (20 MGD)

o Downtown Well Field (15 wells)

• Normal: 15.2 MGD

• Drought: 12.4 MGD

o Smoky Hill River Intake (10 MGD)

Former Schilling Air Force Base

Facilities

o Schilling Air Force Base WTP

• Emergency supply only

o South Well Field (5 wells, 3 active)

• Existing Capacity: 2.24 MGD

• Water Rights: 3.7 MGD

System Overview

Goal:

o Provide water supply during drought

Feasibility Study

o Completed in 2015

o Water Supply Alternatives

o Water Treatment Alternatives

Project:

o Improvements to five existing wells

o Raw water lines, finished water lines, and

other utilities

o Construction of new 3.5 MGD WTP

• Lime Softening WTP

• Membrane WTP

Estimated Project Budget:

o Approximately $32M

Project Overview

Continued use of vertical wells and vested

water rights

Offset Wells 1 and 5

Rehabilitate Wells 2, 3, and 4

New for all wells:

o Pumps

o Flow meters

o Pump housing

o Discharge piping

o I&C

o Electrical

Water Supply Scope

Water Well Road

Oh

io S

tree

t

Coagulation with Ferric Addition

Lime Softening

Recarbonation

Gravity Filtration

Disinfection (Chloramines)

Clearwell

High Service Pumping

Solids:

o Gravity Thickening

o Dewatering Lagoons

Water Treatment Alternatives

Aeration

Green Sand Filtration

Nanofiltration (2-stage)

Disinfection (Chloramines)

Clearwell

High Service Pumping

Solids:

o Membrane Waste Solids Separation

o River Discharge or Deep Well Injection

Lime Softening Treatment Membrane Treatment

City’s Objectives

South Well Field and

Water Treatment

Plant

Single Point of Accountability

Establish Project

Budget Prior to Design

Maximize Contractor

Involvement in Design Cost Estimating

Early Collaboration

Between Owner’s Team and D-B Team

Procurement

Pre-Design

• Evaluate Treatment Alternatives

• Establish Project Budget with Contractor Estimates

Design and Cost Estimating

• BODR

• 30%

• 60%

• 90%

GMP

Finalize Design Construction Start-up & Operation

Phase 1

Phase 2

Progressive Design Build Process

RFQ Short-List

(3)

Proprietary Meeting

Interviews Selection

General Procurement Process

Schedule

Procurement 4 to 6 months

Pre-Design, Design, GMP 12 months

Final Design, Construction 18 months

Start-up and Operation/Warranty Period 12 months

© 2015 HDR, all rights reserved.