Southern Natural Gas Company2013 Outage Review Meeting
Customer con call and WebexMarch 14, 2013
2
Welcome
Tom DenderSNG Gas Control
Agenda
• Review Unscheduled Outages• Review of Upcoming Outages
– March, April & May• North System
• South System
• South Louisiana
– Outages for the reminder of 2013• North System
• South System
• South Louisiana
• Contacts3
Disclaimers
• Anticipated Impacts are estimates. Actual nominations, market demand, weather and pipeline conditions, etc. will determine if, and through what level, restrictions become necessary.
• Unless otherwise stated, all scheduled dates represent gas days as defined in the Southern Natural Gas Pipeline tariff to mean a period of twenty-four consecutive hours, beginning and ending at 9:00 a.m. (Central Clock Time).
• Scheduled dates are subject to change.
• Projects may be added, altered, delayed or cancelled.
• SNG will provide notice of such additions or changes via SoNet Premier postings.
• Dates as posted on SoNet should be deemed correct in the event of conflicts between SoNet posted dates and dates within this presentation.
4
Color Key for Maps
• Green– No Impact Anticipated
• Yellow– Restrictions are possible– With extended duration, restrictions could be
necessary from time to time– Meter(s) affected are denoted with (M)
• Red– Restrictions are probable
5
6
Southern Natural Gas Pipeline
LA
MS
AL
GA
FL
Enterprise
White Castle
Bear Creek
Muldon
Chattanooga
Atlanta
Thomaston
Albany
Elba
SCAiken
Elba Express
North System
South Louisiana
South System
Compressor Station
Storage FieldLNG
Pearl River
Franklinton
Gwinville
Southern Natural Gas Pipeline Unscheduled Outage Update
LA
MS
AL
GA
FL
Enterprise
White Castle
Bear Creek
Muldon
Chattanooga
Atlanta
Thomaston
Albany
Elba
SCAiken
Elba Express
Thomaston unit outage Projected return 03/22/13
Cap reduced up 100 MMcf/d
Franklinton unit outage Projected return April 18, 2013
Bear Creek unit outage Projected return April 15, 2013
7
Compressor Station
Storage FieldLNG
Pearl River
Franklinton
Gwinville
Enterprise unit outage, return to service unknown
Cap reduced up 125 MMcf/d
8
SNG North SystemMaintenance Review April - May
LA
MS
AL
GA
Logansport
Bienville
Bear Creek Storage
Onward
Pickens
Rankin
Louisville
Muldon Storage
Reform
McConnells
Providence
TarrantPell City
DeArmanville
Bell Mills
Rome
Compressor Station
Storage Field
Huntsville
Chattanooga
Atlanta
Bear Creek Spring Shut-in Test 4/23/13 – 4/29/13
DIQ and DWQ allocated 64%
Muldon Spring Shut-In Test 4/09/13 – 4/15/13
DIQ and DWQ allocated 34%
Pigging 14” Logansport Line 4/23/13 (M) 540000, 051350
Pell City unit maintenance during April
Southern will be conducting other general maintenance during this period
9
SNG South SystemMaintenance Review April- May
MS AL
GA
Enterprise
Gwinville
SelmaAuburn
Ellerslie
Thomaston
Ocmulgee
Hallgate
Wrens
Elmore
York
Gallion
Bay Springs
Compressor Station
Storage FieldLNG
Atlanta
Elba
Hartwell
Elba ExpressAiken
Holy Trinity
Albany
Pavo
Enterprise Station Outage5/06/13 – 5/10/13
Cap reduced up to 400 MMcf/d
Brookman
Riceboro
Pressure Test on the 30” South Main 2nd Loop and 24” South Main Loop
(one line at a time) 5/01/13 – 6/30/13 Cap reduced up to 170 MMcf/d
Southern will be conducting other general maintenance during this period
Gwinville Station Outage4/15/13 – 4/19/13
Cap reduced up to 200 MMcf/d
Thomaston maintenance 4/01/13 – 4/15/13
Cap reduced up to 200 MMcf/d
10
SNG South Louisiana System Maintenance Review April - May
Shadyside
White Castle
Franklinton
Toca
Gwinville
LAMS
Compressor Station
Storage Field
Lacombe
West Leg
East Leg
Pressure Test 24” WC-Franklinton LoopStarting April 8 through the end of June
Cap reduced up to 400 MMcf/d(M) 601400 Sugar Bowl #6
White Castle, ShadysideUnit Maintenance
Scheduled During Pipeline Outage
Lacombe Relocated to Enterprise
Begins Mid April
Pearl River
Southern will be conducting other general maintenance during this period
11
SNG North System Maintenance Review remainder of 2013
LA
MS
AL
GA
Logansport
Bienville
Bear Creek Storage
Onward
Pickens
Rankin
Louisville
Muldon Storage
Reform
McConnells
ProvidenceTarrant
Pell City
DeArmanville
Bell Mills
Rome
Compressor Station
Storage Field
Huntsville
Chattanooga
Atlanta
Bear Creek Fall Shut-in Test 10/15/13 – 10/21/13
DIQ and DWQ allocated 64%
Muldon Fall Shut-in Test 10/01/13 – 10/07/13
DIQ and DWQ allocated 36%
Pressure Test 2nd North MainEast of Louisville
2 to 3 week outage Late Summer or FallNorth system supply maybe reduced
Pressure Test 12” Gadsden Branch Loop during the month
of JulyBear Creek
1 unit down starting mid June for 8 weeks
Muldon field outage starting6/24 for 5 days
Southern will be conducting other general maintenance during this period
12
SNG South SystemMaintenance Review remainder of 2013
MS AL
GA
Enterprise
Gwinville
SelmaAuburn
Ellerslie
Thomaston
Ocmulgee
Hallgate
Wrens
Elmore
York
Gallion
Bay Springs
Compressor Station
Storage FieldLNG
Atlanta
Elba
Hartwell
Elba ExpressAiken
Holy Trinity
Albany
Pavo
Enterprise Station Outage6/10/13 – 6/14/13 and
7/15/13 – October Rose Hill (M) 504001
Cap reduced up to 400 MMcf/d
Rose Hill M/S(M) 504001, 504002
July Outage
Brookman
Riceboro
Maintenance on the 16” South Main Loop
3 weeks in September
Selma unit maintenance 6/03/13 – 6/28/13
Auburn unit maintenance
7/15/13 – 7/30/13
Elmore station outage 7/01/13 – 7/15/13
Cap reduced up to 300 MMcf/d
Southern will be conducting other general maintenance during this period
13
SNG South Louisiana SystemMaintenance Review remainder of 2013
Shadyside
White Castle
Franklinton
Toca
Gwinville
LA
MS
Compressor Station
Storage Field
West Leg
East Leg
Pearl River
White Castle, ShadysideUnit Maintenance
Mid September - mid October
Southern will be conducting other general maintenance during this period
14
Gas Control Contacts • Nancy Barton – Manager
(713) – 420 – 6191 (office) (713) – 204 – 4815 (cell) [email protected]
• Kalman (Kal) Dankovich – Outage Coordinator (713) – 420 – 7522 (office) (205) – 325 – 7305 (Gas Control) [email protected]
• Jerry Peterson – Operations Analyst (205) – 325 – 7345 (office) (205) – 325 – 7305 (Gas Control) [email protected]
• Paul Reed – Operations Analyst (205) – 325 – 7655 (office) (205) – 325 – 7305 (Gas Control) [email protected]
15
Questions?