Southern Natural Gas Company2014 Outage Review Meeting
Customer con call and WebexJune 18, 2014
2
Welcome
Agenda
• Review Unscheduled Outages • Review of Upcoming Outages
– June/July & August• North System
• South System
• South Louisiana
– Outages for the remainder of 2014• North System
• South System
• South Louisiana
• Contacts3
Disclaimers
• Anticipated Impacts are estimates. Actual nominations, market demand, weather and pipeline conditions, etc. will determine if, and through what level, restrictions become necessary.
• Unless otherwise stated, all scheduled dates represent gas days as defined in the Southern Natural Gas Pipeline tariff to mean a period of twenty-four consecutive hours, beginning and ending at 9:00 a.m. (Central Clock Time).
• Scheduled dates are subject to change.
• Projects may be added, altered, delayed or cancelled.
• SNG will provide notice of such additions or changes via SoNet Premier postings.
• Dates as posted on SoNet should be deemed correct in the event of conflicts between SoNet posted dates and dates within this presentation.
4
Color Key for Maps
• Green– No Impact Anticipated
• Yellow– Restrictions are possible– With extended duration, restrictions could be
necessary from time to time– Meter(s) affected are noted with (M)
• Red– Restrictions are probable
5
6
Southern Natural Gas Pipeline
LA
MS
AL
GA
FL
Enterprise
White Castle
Bear Creek
Muldon
Chattanooga
Atlanta
Thomaston
Albany
Elba
SCAiken
Elba Express
North System
South Louisiana
South System
Compressor Station
Storage FieldLNG
Pearl River
Franklinton
Gwinville
7
Southern Natural Gas PipelineUnscheduled Outage Update
LA
MS
AL
GA
FL
Enterprise
White Castle
Bear Creek
Muldon
Chattanooga
Atlanta
Thomaston
Albany
Elba
SCAiken
Elba Express
Compressor Station
Storage FieldLNG
Pearl River
Franklinton
Gwinville
Toca
8” West Point Line outage.
Auburn
Franklinton compressor station unit outage
Bear Creek unit outage
South Section 28 Erath line outage-Erath, La. To White
Castle Station605200-Sabine
605300-Sea Robin033200-South Sect. Terminal
031900 Lake Larose032400-Crook Chene067000-Petrologistics
8
SNG North SystemMaintenance Review June/July & August
LA
MS
AL
GA
Logansport
Bienville
Bear Creek Storage
Onward
Pickens
Rankin
Louisville
Muldon Storage
Reform
McConnellsProvidence
TarrantPell City
DeArmanville
Bell Mills
Rome
Compressor Station
Storage Field
Huntsville
Chattanooga
Atlanta
Southern will be conducting other general maintenance during this period
AL
16” Logansport Supply line pigging-7/29/14 and 7/31/14Customers may experience
higher than normal pressures
Remediation on 24” North Main Loop line 7/7/14 to
8/10/14Cap reduced 90 MMcf/d
9
SNG South SystemMaintenance Review June/July & August
MS
AL
GA
Enterprise
Gwinville
Selma
AuburnEllerslie
Thomaston
Ocmulgee
Hallgate
Wrens
Elmore
York
Gallion
Bay Springs
Compressor Station
Storage FieldLNG
Atlanta
Elba
Hartwell
Elba ExpressAiken
Holy Trinity
Albany
Pavo
Brookman
Riceboro
Southern will be conducting other general maintenance during this period
Hydro-test 6” Line -26 East Dougherty
6/23/14 thru 7/1/14(M)Ashburn (960050)(M)Douglas (960170)
(M)Fitzgerald (960190)(M)Ocilla (960280)
(M)Sylvester (960340)(M)Tifton area (960378)
Pipeline replacement on the 24” South Main Loop line8/4/14 thru 9/12/14
Capacity reduced up to 100 MMcf/d
12” Main line #1 Opelika, Al. to Albany compressor station pig run. 7-12-14 Customers could experience lower than normal operating pressures.
10
SNG South Louisiana System Maintenance Review June/July & August
Shadyside
White Castle
Franklinton
Toca
Gwinville
LA
MS
Compressor Station
Storage Field
West Leg
East Leg
Pearl River
Southern will be conducting other general maintenance during this period
11
SNG North System Maintenance Review remainder of 2014
LA
MS
AL
GA
Logansport
Bienville
Bear Creek Storage
Onward
Pickens
Rankin
Louisville
Muldon Storage
Reform
McConnells
Providence
Tarrant Pell City
DeArmanville
Bell Mills
Rome
Compressor Station
Storage Field
Huntsville
Chattanooga
Atlanta
Bear Creek Fall Shut-in Test 10/21/14 thru 10/27/14
DIQ and DWQ allocated 64%
Muldon Fall Shut-in Test 10/7/14 thru 10/13/14
DIQ and DWQ allocated 36%
Southern will be conducting other general maintenance during this period
Pipeline relocation on 30” field storage line sometime
this summerStopple by-pass
Pipeline remediation 24” North Main 2nd Loop line
September/October Capacity reduced as much as
95 MMcf/d
Muldon unit maintenance Two weeks in the fall
12
SNG South SystemMaintenance Review remainder of 2014
MS
ALGA
Enterprise
Gwinville
Selma Auburn
Ellerslie
Thomaston
Ocmulgee
Hallgate
Wrens
Elmore
York
Gallion
Bay Springs
Compressor Station
Storage FieldLNG
Atlanta
Elba
Hartwell
Elba ExpressAiken
Holy Trinity
Albany
Pavo
Brookman
Riceboro
Ellerslie unit maintenance In October
Southern will be conducting other general maintenance during this period
Auburn unit maintenance September /October
Pipeline replacement on the 30” South Main 2nd Loop line
9/15/14 thru 11/1/14Capacity reduced up to 240 MMcf/d
Enterprise unit maintenance-
September/October
13
SNG South Louisiana SystemMaintenance Review remainder of 2014
Shadyside
White Castle
Franklinton
Toca
Gwinville
LA
MS
Compressor Station
Storage Field
West Leg
East Leg
Pearl River
White Castle, ShadysideUnit Maintenance
Mid September - mid OctoberWest Leg Capacity impact up to
150 MMcf/d
Southern will be conducting other general maintenance during this period
14
Gas Control Contacts • Adam Krustchinsky – Manager
(713) – 420 – 3265 (office) (713) – 202-7035 (cell) [email protected]
• Kal Dankovich – Outage Coordinator (713) – 420 – 7522 (office) (205) – 420 – 7305 (Gas Control) [email protected]
• Jimmy Reese – Lead Controller (713) – 420 – 7310 (office) (713) – 420 – 7305 (Gas Control) [email protected]
• Daniel Mitchell – Lead Controller (713) – 420 – 5874 (office) (713) – 420 – 7305 (Gas Control) [email protected]
15
Questions?