SouthGridTechnical Meeting
Pete GronbechSouthGrid Technical Coordinator
EVOMarch 2012
Q411 Metrics
Overall delivering more CPU (185%) and Disk (236%) than the MoU. Slight increase compared to earlier in the year, but major changes will come with the GridPp4 h/w tranche purchases
Availability/reliability dropped at most sites; Why?
CPU utilisation remains acceptable.
2SouthGrid January 2012
% of promised (by that time) disk available to GridPP
% of promised (by that time) CPU availableAverage SAM (SLL page) availability performance over the last quarterAverage SAM (SLL page) reliability performance over the last quarterAverage SLL untargeted ATLAS test performance (UK test)
Approx. CPU utilisation (wall clock time)
Approx. CPU utilisation (CPU time)
SouthGrid January 20123
UK Tier 2 reported CPU
– Historical View to present
SouthGrid January 20124
SouthGrid SitesAccounting as reported by
APEL
What about the rest of GridPP sites?
SouthGrid January 20125
Other GridPP Tier2 Resources
• NorthGrid
Total available to
GridPPPromised (GridPP MoU
2011)
SiteHEPSPE
C06Storage
(TB)CPU
(HS06)Storage
(TB)
Lancaster 28627 992 3395 515
Liverpool 8390 543 2996 554
Manchester 22264 687 7284 224
Sheffield 4800 298 1198 252
Totals 64081 2520 14873 1545
SouthGrid January 20126
Total available to
GridPPPromised (GridPP MoU
2011)
SiteHEPSPEC
06 Storage (TB) CPU (HS06) Storage (TB)DURHAM 8141 23 3916 104ECDF 14445 177 3118 77GLASGOW 21300 1363 11638 1341
• ScotGrid
Total available to
GridPPPromised (GridPP MoU
2011)
SiteHEPSPEC
06 Storage (TB) CPU (HS06) Storage (TB)UKI-LT2-Brunel 11371 570 6317 176UKI-LT2-IC-HEP 17993 1200 19439 522UKI-LT2-QMUL 28622 1320 6302 956UKI-LT2-RHUL 9558 706 4620 213UKI-LT2-UCL-HEP 2006 159 515 14Totals 69550 3955 37193 1881
• LondonGrid Total available to
GridPPPromised (GridPP MoU
2011)
SiteHEPSPEC
06 Storage (TB) CPU (HS06) Storage (TB)EFDA JET 1772 10.5 0 0Birmingham 3345 195 2119 95Bristol 2247 110 1173 27Cambridge 2445 255 1445 135Oxford 8961 620 2483 255RALPP 18974 1060 13109 440 Totals 37744 2250 20329 951
• SouthGrid
Gridpp4 h/w generated MoU for 2012-14
2012 TB 2013 TB 2014 TB
bham 265 282 346
bris 96 96 116
cam 123 139 167
ox 409 456 549
Jet 19 21 26
RALPPD 830 862 1034
Total 1744 1857 2237
2012 HS06 2013 HS06 2014 HS06
bham 3375 3305 4184
bris 1651 1619 1982
cam 730 770 949
ox 3287 3372 4173
Jet 166 169 208
RALPPD 10082 9959 12243
7SouthGrid January 2012
Old MoU GPP3 h/w 2012 TB
bham 124
bris 35
cam 174
ox 328
RALPPD 573
Total 1244
2012 HS06
bham 2724
bris 1429
cam 1738
ox 2974
RALPPD 16515
Future Resources
• New MoU’s show lack of Storage space at Birmingham, and Jet, with a problem at Bristol in 2014
• Shortage of CPU at Birmingham by 2014.
• This all assumes current levels of resources at sites. Old storage and CPU will come out of warrantee and be retired so new purchases need to maintain enough resource to cover the MoU commitments
SouthGrid January 20128
GridPP4 h/w Grants
SouthGrid January 20129
Brunel
IC
QM
RH
UCL
LAN
LIVMAN
SHEF
DU
EC
GLA
BHAM
BRIS
Cam
OX
RAL
jet
Sussex
68000
133500
107000
66500
7500
78500
40500
92000
32000
5500
33000
114500
35500
14500
13000
45500
109500
0
5000
Actual Grants
Actually £3000
DRI Grants
• An unexpected bonus was the Digital Research Infrastructure Proposal. Work started in late October, and by the end of the year we had submitted grant requests for a total of £3m.
10
Site Gridmon PerfSonnar Inc VAT Grant AwardBirmingham £91,900 £2,000 £112,680 £112,500Bristol £52,000 £2,000 £64,800 £65,000Brunel £132,391 £2,000 £161,269 £161,500Cambridge £37,064 £2,000 £46,877 £47,000Durham £18,183 £2,000 £24,220 £24,000ECDF £90,123 £2,000 £4,000 £115,348 £115,500Glasgow £295,500 £12,000 £4,000 £373,800 £374,000Imperial £295,600 £2,000 £4,000 £361,920 £362,000Lancaster £229,672 £2,000 £4,000 £282,806 £283,000Liverpool £96,187 £2,000 £117,824 £118,000Manchester £165,025 £2,000 £4,000 £205,230 £205,000Oxford £127,464 £2,000 £4,000 £160,157 £160,000QMUL £247,036 £2,000 £4,000 £303,643 £303,500RALPP £64,585 £2,000 £79,902 £80,000RHUL £82,920 £2,000 £101,904 £102,000Sheffi eld £98,500 £2,000 £120,600 £120,500Sussex £21,500 £2,000 £28,200 £28,000Swansea £22,520 £2,000 £29,424 £29,500UCL £20,200 £2,000 £26,640 £26,500Warwick £15,000 £2,000 £20,400 £20,500RAL T1 £216,426 £2,000 £262,111 £262,000Total £2,419,796 £52,000 £28,000 £2,999,755 £3,000,000
Procurement deadlines etc
• Both the GridPP4 h/w grant and the DRI money must be spent before the end of this Financial Year ie 31st March 2012.
• Orders had better be made now or very soon. • Invoices should be paid before 31st March 2012
SouthGrid January 201211
Sussex
• Suspended or Candidate sites• • Later this week, sites in suspended or Candidate
state for longer than 6 months will be closed - COD has collected a list of exceptions from NGIs. This does not affect any GridPP site, except maybe Sussex. I note that as per https://ggus.eu/ws/ticket_info.php?ticket=78177, Sussex is set as 'Uncertified', (my memory says it used to be 'Candidate', although I can't recall what the difference between the two is right now).
• Plans to grid enable….SouthGrid January 2012
12
SL4 EOL
• SL4 support finished yesterday– What servers are still out there
• LCG-CE• DPM• ??
SouthGrid January 201214
SouthGrid January 201215
Conclusions
• SouthGrid sites utilisation level except maybe RALPP?• JET will be setup for ATLAS production new h/w will help.• RALPPD still our lead site.• Sussex, Warwick and Swansea had DRI money, what will this
lead to?• Main goal at the moment is to spend the two grants asap.