Southwest Calgary Ring Road 2018 Construction Update Segment 2: Glenmore Trail from 69th Street to 37th Street SW
N
Road Construction • Construct Tsuut’ina Parkway and roundabout to
access 37th Street • New eastbound lanes along Discovery Ridge• Additional road construction where available
Bridge Construction• Start bridge at 37th Street • Continue nine bridges in Sarcee Trail interchange
Traffic Impacts• Detour intersection at Sarcee Trail to the north• Realign ramps at 37th Street• Permanently close 45th Street access to/from
Glenmore Trail• Truck traffic from haul road• Speed reduction on Highway 8 / Glenmore Trail
Elbow River Crossing• Open river realignment• Continue three bridges and one tunnel• Start two stormwater ponds • Realign traffic on Weaselhead Road
Utilities• Richmond stormwater line near 37th Street
69st St
SW
Wes
thill
s Way
SW
Sarc
ee T
rail
SW
45th
St S
W
37th
St S
W
Glenmore Trail SW
37th
St S
W
Wea
selhea
d Rd
Ric
hard
Way
SW
Tsuut’ina Nation
33
5
5
55
Transportation Utility Corridor
5
5
3
3
Future Transportation
Corridor
Pond
Pond
Pond
Elbow River
SWCRR Roads & Ramps
Existing Roads
Stormwater Ponds
Right-of-Way
Road Closure
SWCRR Bridges
Haul Road
River Realignment
Transportation Utility Corridor
# Number of Stage 1 Lanes & Direction of Traffic
Asphalt Plant
Tsuut’ina Parkway
Tsuut’in