+ All Categories
Home > Documents > SPE · PDF file• High Torque Motors • Rotary Steerable . ... holes for mud weight...

SPE · PDF file• High Torque Motors • Rotary Steerable . ... holes for mud weight...

Date post: 18-Mar-2018
Category:
Upload: hoangdang
View: 217 times
Download: 3 times
Share this document with a friend
48
SPE DISTINGUISHED LECTURER SERIES SPE DISTINGUISHED LECTURER SERIES is funded principally is funded principally Through a grant of the Through a grant of the SPE FOUNDATION SPE FOUNDATION The Society gratefully acknowledges The Society gratefully acknowledges Those companies that support the program Those companies that support the program By allowing their professionals to participate as lecturers. By allowing their professionals to participate as lecturers. And special thanks to The American Institute of Mining, Metallur And special thanks to The American Institute of Mining, Metallur gical, gical, And Petroleum Engineers (AIME) for their contribution to the pro And Petroleum Engineers (AIME) for their contribution to the pro gram. gram.
Transcript

SPE DISTINGUISHED LECTURER SERIESSPE DISTINGUISHED LECTURER SERIESis funded principallyis funded principally

Through a grant of theThrough a grant of the

SPE FOUNDATIONSPE FOUNDATIONThe Society gratefully acknowledgesThe Society gratefully acknowledges

Those companies that support the programThose companies that support the programBy allowing their professionals to participate as lecturers.By allowing their professionals to participate as lecturers.

And special thanks to The American Institute of Mining, MetallurAnd special thanks to The American Institute of Mining, Metallurgical,gical,And Petroleum Engineers (AIME) for their contribution to the proAnd Petroleum Engineers (AIME) for their contribution to the program.gram.

STEPS TOWARD ULTIMATE STEPS TOWARD ULTIMATE DRILLING PERFORMANCEDRILLING PERFORMANCE

Presented By:Mansour Al Hammad, Saudi Aramco

SPE Distinguish lecturer SeriesMilano, Italy. March 23rd, 2005

OUTLINEOUTLINE

INTRODUCTIONINTRODUCTIONIMPROVEMENT PROCESSIMPROVEMENT PROCESSRESULTSRESULTSCONCLUSIONCONCLUSION

KhuffKhuff Reservoir PropertiesReservoir PropertiesKhuff reservoir is highly heterogeneous and significant variation in porosity and permeability is encountered aerially and vertically

Reservoir properties vary between wells and within the same well at different depths

HRDH-EE HRDH-FF HRDH-GG

10 km 12 km

Acid FracturingAcid Fracturing

Liner

Tubing

Reservoir

Jawb

Riyadh

Qatar

Niban

Hawtah TrendHawtah Trend

Nuayyim TrendNuayyim Trend

WAQR AreaWAQR Area

S. HRDHS. HRDH

Unconsolidated Unayzah “A” Reservoir

Unconsolidated Unayzah “A” Reservoir

High risk for sand production

High risk for sand production

TinatTinat

Liner

Reservoir

Tubing

Jawb

Riyadh

Qatar

NibanWDYH

South Haradh

Consolidated Unayzah “B”Consolidated Unayzah “A”Consolidated Unayzah “A”

Low risk for sand production

Low risk for sand production

HWYHHWYH

GHZL

Screenless FracturingScreenless Fracturing

Liner

Tubing

Reservoir

DESIGN CRITERIADESIGN CRITERIA

Pressure & TempPressure & Temp

FormationFormation

HH22S COS CO2 2

Formation FluidFormation Fluid

AquiferAquifer

RegulationsRegulations

Well objectiveWell objective

Reservoir IsolationReservoir Isolation

Oil reservoirsOil reservoirs

Lost CirculationLost Circulation

Abnormal PressureAbnormal Pressure

Drilling TroublesDrilling Troubles

Well FlowWell Flow

UnconsolidatedUnconsolidated

SLIM SLIM BIGBIG36”

30”

24”

18-5/8”

13-3/8”

9-5/8”

7” Liner

RUS

Ahmadi

Base of Jilh Dolomite

Khuff-D Anhydrite

Pre-Khuff Formation

30”24”

18-5/8”

13-3/8”

9-5/8”

4-1/2” Liner

7” Liner

Biyadh

AhmadiRUS 100’

12” hole

8 3/8” hole

16” hole

12” hole

Top of Arab-D

EARLIER PERFORMANCEEARLIER PERFORMANCEFIRST HORIZONTAL WELL DRILLING CURVE

0

5000

10000

15000

0 40 80 120 160 200days

dept

h

20 Bits

Average 8-3/8” Bit Run110’ – 25 hrs

4.5 fph

1,400 ft Lateral Well206 Total Rig Days

14 Bits

Average 12” Bit Run117’ – 28 hrs

4.2 fph

Total Bits For Well48

PERFORMANCE TRENDPERFORMANCE TREND

NATURAL LEARNING CURVE

INDIVIDUAL INITIATIVES

LEARNING ORGANIZATION

NO IMPROVEMENT

TIME

PER

FOR

MA

NC

E

BENCHMARKBENCHMARK

Performance DrillingPerformance DrillingCompetitionCompetitionNew Technology EvaluationNew Technology EvaluationDrilling TargetsDrilling TargetsMonitoringMonitoringKnowledge ManagementKnowledge Management

MISSIONMISSION

SafelySafely drill and workover drill and workover high high qualityquality, , costcost effective effective oil and gas wells in a oil and gas wells in a timely manner to timely manner to meetmeetcorporate objectivescorporate objectives

RESOURCES ALIGNMENTRESOURCES ALIGNMENT

ENGINEERINGOPERATIONS

SERVICES

TEAM WORKTEAM WORK

Team Spirit Comes FirstTeam Spirit Comes FirstTeam By Organization Team By Organization ResponsibilityResponsibilityBelieve In Goal Then Work For ItBelieve In Goal Then Work For ItCommitment Commitment

PERFORMANCE DRILLINGPERFORMANCE DRILLING

• PDC Bits• High Torque Motors• Rotary Steerable

PERFORMANCE MOTORSPERFORMANCE MOTORS8" extended HT customized for 12" 8" extended HT customized for 12" holes for mud weight 145holes for mud weight 145--155 pcf. 155 pcf. Application.Application.9 1/2" HT first application worldwide. 9 1/2" HT first application worldwide. behind 16" PDC bit.behind 16" PDC bit.6 3/4" extended HT first application 6 3/4" extended HT first application worldwide.worldwide.Use laser carbide technology to Use laser carbide technology to improve BHA wear in abrasive sand.improve BHA wear in abrasive sand.Selectively utilizing RSS push the bit Selectively utilizing RSS push the bit or point the bit concepts.or point the bit concepts.

Bit Trial Test SystemBit Trial Test System

Pay 50% when bit goes thru the Pay 50% when bit goes thru the rotary table.rotary table.Rest based on performance!!Rest based on performance!!

Resulted in more rejection than Resulted in more rejection than approval.approval.

New Bit Trial Test SystemNew Bit Trial Test System

Maximize vendor engineering efforts Maximize vendor engineering efforts prior to proposal.prior to proposal.Performance based equation!!Performance based equation!!Cost= Cost= Target $/ft / Actual$/ft X 0.66 X Bit costTarget $/ft / Actual$/ft X 0.66 X Bit cost

Resulted in more approval than Resulted in more approval than rejection.rejection.

BIT SELECTION GUIDELINESBIT SELECTION GUIDELINES

All Manufacturers are WelcomedAll Manufacturers are WelcomedShare InformationShare InformationFit For Purpose TechnologyFit For Purpose TechnologyWilling to share risk of using noneWilling to share risk of using none--field proven designs.field proven designs.

OPTIMUM DESIGN DEVELOPMENTOPTIMUM DESIGN DEVELOPMENT

Field TestEvaluate

Mfg.Design

Addition Designs to IndustryAddition Designs to Industry

3434”” IADC 135 Bit. Dual seal bearing.IADC 135 Bit. Dual seal bearing.2828”” IADC 445 Bit.IADC 445 Bit.

88--3/83/8”” IADC 637. High wear resistanceIADC 637. High wear resistance55--7/87/8”” IADC 627. IADC 627.

Complex Complex stratigraphicstratigraphic..Abrasive sandstone Abrasive sandstone followed by dense followed by dense dolomitedolomiteSevere bit damage due Severe bit damage due to downhole vibration.to downhole vibration.Abrasive sand causing Abrasive sand causing severe cutter wear .severe cutter wear .

1212””/16/16”” PDC ApplicationPDC Application

1616”” Hole Performance for Big Hole Performance for Big WellsWells

$147$147

$225$225

$126$126

Rotary 17” Average Best

Rate of Penetration Cost Per Foot

RO

P

CP

F

8.3

19

33.5

0 0

40

20

250

125

$/ftft/hr

BITS MARKET SHAREBITS MARKET SHARE

COMPETITION BEST

90%

10%

PERFORMANCE MONITORINGPERFORMANCE MONITORING

By section By section By well and Rig. By well and Rig. Quarterly Review. Quarterly Review. Service Contracts Review Committee.Service Contracts Review Committee.

The UDC

The fastest time for hole section is taken from offset information.

Then the times summed up to generate the UDC.

Ultimate Drilling Curve Ultimate Drilling Curve

ULTIMATE DRILLING TIME CURVE (UDC) Vs PLANNED DRILLING TIME CURVE (EXISTING) FOR BIG DESIGN PRE-KHUFF WELL

0

5000

10000

15000

0 20 40 60 80 100 120DRILLING TIME, DAYS

DEP

TH, F

T

TD: 14,000'

OPERATING DAYS: 120

OPERATING DAYS: 95

DEVELOPING TARGETDEVELOPING TARGET

DEVELOPING TARGETDEVELOPING TARGETULTIMATE DRILLING CURVE (UDC) VS DRILLING TIME CURVE

FOR SLIM DESIGN KHUFF WELL

0

5000

10000

0 10 20 30 40 50 60 70 80 90DRILLING TIME, DAYS

DEP

TH, F

T

Operating Days: 50TD: 11,900

UDC

EXISTING

OPERATING DAYS: 85

ULTIMATE DRILLING TIME CURVE (UDC) Vs EXISTING DRILLING TIME CURVE (EXISTING) FOR MODIFIED MODIFIED DESIGN KHUFF WELL

0

5000

10000

15000

0 40 80 120

DRILLING TIME, DAYS

DEP

TH, F

T

UDC EXISTING

OPERATING DAYS: 75OPERATING DAYS: 40

TD: 11,900'

DEVELOPING TARGETDEVELOPING TARGET

GOAL SHARINGGOAL SHARING

InIn--house Awareness Campaignhouse Awareness Campaign

Vendors CampaignVendors Campaign–– Bit suppliers awareness.Bit suppliers awareness.–– Performance motors providersPerformance motors providers–– Rig contractorsRig contractors

AWARENESS CAMPAIGNAWARENESS CAMPAIGN

Motivate Field Professional InputMotivate Field Professional InputEmphasize that Emphasize that ““UDCUDC”” is repeating is repeating what was achieved beforewhat was achieved beforeEmpowerment to say NO to any nonEmpowerment to say NO to any non--safe requestsafe requestInvolve Service ProviderInvolve Service Provider

UDC LIFECYCLEUDC LIFECYCLE

Prepare Drilling

ProgramDrill Well

Post Section & Post Well Analysis

DIH +UDC ProjectWeb Page

Extract & Record Lessons Learned & Best

Practices

ProjectLearning

CorporateLearning

ContinuousImprovement

STRATEGYSTRATEGYUSE BEST IN CLASS PRODUCTS USE BEST IN CLASS PRODUCTS OR SERVICES .OR SERVICES .TEAM WORK.TEAM WORK.TRANSFER KNOWLEDGE.TRANSFER KNOWLEDGE.

PRIORITIESPRIORITIES

Quality Well ConstructionQuality Well Construction

Efficient, not Efficient, not ““FastFast””

SAFETY FIRSTSAFETY FIRST

IS IT POSSIBLE TO BEAT UDC ?IS IT POSSIBLE TO BEAT UDC ?

0

2000

4000

6000

8000

10000

12000

14000

0 5 10 15 20 25 30 35 40 45 50

Days

Dep

th (f

t)

HRDH-931 UDC

HRDH-931 Actual

RESULTSRESULTS

Time savingTime savingCost savingCost savingCompetitive environmentCompetitive environmentDrilling more complex wellsDrilling more complex wells

Last PerformanceLast PerformanceHRDH-950 Vs. HRDH-607 DRLG Curve

-2000

3000

8000

13000

18000

0 40 80 120 160 200 240

Time (Days)

Dep

th (f

t)

UDC Time HRDH-950

Actual Time HRDH-950

Actual Time HRDH-607

3 Bits

5,700 ft Lateral Well99 Total Rig Days

9 Bits

Average 8-3/8” Bit Run840’ – 56 hrs

15 fph

Average 5-7/8” Bit Run935’ – 63 hrs

14.9 fph

Total Bits For Well23

HRDH-950 vs HRDH-607

IMPROVED PERFORMANCE25 FEWER BITS

107 FEWER DAYS

4,300 FT LONGER LATERAL

Recognition and RewardRecognition and Reward

Every one involved Every one involved Service providerService providerDrilling contractor Drilling contractor

0

3500

7000

10500

14000

0 15 30 45 60 75 90

HRDH-908UDC

HRDH-934

HRDH-956

HRDH-968

HRDH-949

Rig-Z Performance

2002

2004

IMPROVEMENT WITH TIMEIMPROVEMENT WITH TIME

One-Rig ImprovementOver 18 Months

45% Drilling Time Reduction

CONCLUSIONCONCLUSION

ULTIMATE PERFORMANCE IS A ULTIMATE PERFORMANCE IS A PROFIT OF WELL SPENT PROFIT OF WELL SPENT INVESTMENT IN THE FOLLOWING INVESTMENT IN THE FOLLOWING STEPS STEPS ::

Benchmark

STEPS TOWARDS ULTIMATE STEPS TOWARDS ULTIMATE PERFORMANCEPERFORMANCE

TIME

PER

FOR

MA

NC

E

Resources Alignment

Team Work

Develop Target

Share Goals

Best in Class TechnologyMonitor

Recognize

Reward

Knowledge Management

QUESTIONS????QUESTIONS????

[email protected]@ARAMCO.COM


Recommended