Date post: | 22-Dec-2015 |
Category: |
Documents |
Upload: | muriel-butler |
View: | 214 times |
Download: | 0 times |
SPS scrubbing run in 2014
H. Bartosik, G. Iadarola, G. Rumolo
LHC Performance Workshop (Chamonix 2014), 22/9/2014
Many thanks to: G. Arduini, T. Argyropoulos, T. Bohl, K. Cornelis, H. Damerau, J. Esteban Müller,
B. Goddard, S. Hancock, W. Höfle, L. Kopylov , H. Neupert, Y. Papaphilippou, G. Papotti, E. Shaposhnikova, M. Taborelli
and the SPS operator crew
Outline
• Introduction
• The 2014 SPS scrubbing run
o Possible cycles
o Scrubbing stages
o Possible supercycle composition
• The doublet scrubbing beam
o Motivation
o Production scheme
o Experience in 2012-13 MDs
• Scrubbing preparation
o Beams from the PS
o SPS setup
o Measurements
Outline
• Introduction
• The 2014 SPS scrubbing run
o Possible cycles
o Scrubbing stages
o Possible supercycle composition
• The doublet scrubbing beam
o Motivation
o Production scheme
o Experience in 2012-13 MDs
• Scrubbing preparation
o Beams from the PS
o SPS setup
o Measurements
Electron cloud in the SPS and scrubbing
• Strong limitation due to e-cloud in the past → Instabilities at injection + incoherent effects→ Emittance blow-up along the batch→ High chromaticity needed for beam stability→ Pressure rise around the machine
• Situation improved gradually due to scrubbing→ Requires days of dedicated running in high electron
cloud conditions→ Secondary Electron Yield reduction by the e-cloud itself
• Scrubbing runs since 2002→ Performed at 26 GeV in cycling mode (~40 s cycle
length)→ Typically limited by heating and/or outgassing → ~1-2 weeks periods
• SPS scrubbing history
43.2 s
2002(14d)
2003(8d)
2004(10d)
2006(5d)
2007(7d)
2008(2.5d)
2012(5d)
2009(1.5d)
Shutdown
400%
2000 (48 b. - 0.8x1011 p/b @inj.)
3.5 μm
SPS scrubbing run 2014
Goals for 2014:
• Qualify the loss of conditioning due to LS1
• Recover 2012 performance with 25 ns beams
• Quantify amount of beam/time needed
• Test “doublet” scrubbing beam
to be used in the LHC in 2015
Qualification criterion beam quality measurements
• Ideally, achieve by the end of the allocated scrubbing time: 25 ns, 4 batches, up to
1.3e11ppb, emittances below nominal, no blowup along the train as in 2012
basis for LIU strategy on e-cloud
mitigation – coating vs scrubbing
From 2014 injector schedule (current version)
Scrubbing originally foreseen in two consecutive weeks (W39-40), before the start-up of the NA
physics. Then split between Weeks 39 and 45
Finally spread over Week 45 plus an additional two-day mini-block in Week 50
Several reasons for splitting the scrubbing run into two blocks (requested by LIU-SPS):
• Gives time to analyze the first block’s results and adapt accordingly
• Untangling scrubbing from the machine commissioning, NA setup and vacuum conditioning of all the newly-installed or vented equipment
• Allows setting up scrubbing beams before the 2nd scrubbing block
⇒ the “doublet” beam – its potential to scrub the SPS can be explored already in 2014 (also in view of LHC scrubbing in 2015)
Pre-scrubbing cycles
Over weeks 41 – 44 some experience will be already gained during the available parallel and
dedicated MD time
Both single bunch and 25 ns beam (1 batch) on short flat bottom cycle (6BP) should be already
set up
Work on recovery performance for nominal 25 ns beam might have already started (with the
consequent scrubbing)
0 5 10 15 20 25 30 35 400
2
4
6
I mai
ns [k
A]
0 5 10 15 20 25 30 35 400
2
4
6
I mai
ns [k
A]
0 5 10 15 20 25 30 35 400
2
4
6
Time [s]
I mai
ns [k
A]
6 BPs (7.2 s)
Inj. Dump
Scrubbing cycles
We will need to accumulate dose and monitor the evolution of beam parameters for both coherent
and incoherent effects
4 or more batches circulating in the machine at 26 GeV
Acceleration to 450 GeV should be fully set up and used for scrubbing qualification
18 BPs (21.6 s)
33 BPs (39.6 s)
Inj. Inj. Inj. Inj. Dump
Inj. Inj. Inj. Inj. Inj. Dump
Inj. Inj. Inj. Inj.
19 BPs (22.8 s)
Planning (to be steered on the fly)
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Intensity ramp up at 26 GeV on intermediate flat bottom cycle (21.6 s)
First scrubbing block• Intensity ramp up at 26 GeV with 25 ns beams (ideally up to 5 injections – try to push
bunch intensity up to 1.5x1011 p/b?)
0 5 10 15 20 250
1
2
3
4
5
6
7
Time [s]
I mai
ns [k
A]
Inj. Inj. Inj. Inj. Dump
0 5 10 15 20 250
1
2
3
4
5
6
7
Time [s]
I mai
ns [k
A]
0 5 10 15 20 250
1
2
3
4
5
6
7
Time [s]
I mai
ns [k
A]
Possible supercycle (to be coordinated with physics in the PS complex)
Inj.
Week 45
Planning (to be steered on the fly)
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Intensity ramp up at 26 GeV on intermediate flat bottom cycle (21.6 s)
First scrubbing block• Intensity ramp up at 26 GeV with 25 ns beams (ideally up to 5 injections – try to push
bunch intensity up to 1.5x1011 p/b?)
• Study residual electron cloud effects on beam lifetime and quality for nominal beam (e.g. emittance growth, bunch shortening over long flat bottom) while gradually lowering vertical chromaticity setting for stability
Inj. DumpInj. Inj. Inj. Inj.
0 5 10 15 20 25 30 35 40 450
1
2
3
4
5
6
7
Time [s]
I mai
ns [k
A]
Possible supercycle
Studies on long flat bottom cycle (39.6 s)
0 5 10 15 20 250
1
2
3
4
5
6
7
Time [s]
I mai
ns [k
A]
Week 45
0 10 20 30 40 50 600
1
2
3
4
5
6
7
Time [s]
I mai
ns [k
A]
Planning (to be steered on the fly)
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Intensity ramp up at 26 GeV on intermediate flat bottom cycle (21.6 s)
First scrubbing block• Intensity ramp up at 26 GeV with 25 ns beams (ideally up to 5 injections – try to push
bunch intensity up to 1.5x1011 p/b?)
• Study residual electron cloud effects on beam lifetime and quality for nominal beam (e.g. emittance growth, bunch shortening over long flat bottom) while gradually lowering vertical chromaticity setting for stability
• Acceleration and scrubbing qualification
Studies on long flat bottom cycle (39.6 s)
Scrubbing qualification(25 ns std and BCMS, up to 450 GeV)Possible supercycle for scrubbing + qualification
Week 45
Planning (to be steered on the fly)
Monday Tuesday
Second scrubbing block• At this stage doublet beam could be ready including acceleration
• The goal is to accumulate the largest possible electron dose on the beam chambers
• The results of the tests with the doublet beam will be important for the LHC scrubbing in 2015
Wednesday
Week 50
Possible supercycle
Scrubbing with doublet (possibly with acceleration)
Dedicated MD (scrubbing)
18 BPs (21.6 s)
Inj. Inj. Inj. Inj. Dump
Outline
• Introduction
• The 2014 SPS scrubbing run
o Possible cycles
o Scrubbing stages
o Possible supercycle composition
• The doublet scrubbing beam
o Motivation
o Production scheme
o Experience in 2012-13 MDs
• Scrubbing preparation
o Beams from the PS
o SPS setup
o Measurements
“Doublet” scrubbing beam: introduction
Scrubbing with 25 ns beam allowed to lower the SEY of the dipole chambers well below
the multipacting threshold for 50 ns e-cloud free operation with 50 ns beams
Can we go to lower bunch spacing to scrub for 25 ns operation?
• Due to RF limitations in the PS it is impossible to inject bunch-to-bucket into the SPS with spacing
shorter than 25 ns
• An alternative is to inject long bunches into the SPS and capturing each bunch in two neighboring
buckets obtaining a (5+20) ns “hybrid” spacing
0 10 20 30 40 50 60 70
Lo
ng
. be
am p
rofi
le
0 10 20 30 40 50 60 70Time [ns]
E
0 10 20 30 40 50 60 70Lo
ng
. be
am p
rofi
le
0 10 20 30 40 50 60 70Time [ns]
E
0 10 20 30 40 50 60 70Lo
ng
. be
am p
rofi
le
0 10 20 30 40 50 60 70Time [ns]
E
Non adiabatic splitting at SPS injection
0 10 20 30 40 50 60 70
Lo
ng
. be
am p
rofi
le
0 10 20 30 40 50 60 70Time [ns]
E
“Doublet” scrubbing beam: introduction
0 10 20 30 40 50 60 70Lo
ng
. be
am p
rofi
le
0 10 20 30 40 50 60 70Time [ns]
E
0 10 20 30 40 50 60 70Lo
ng
. be
am p
rofi
le
0 10 20 30 40 50 60 70Time [ns]
E
Non adiabatic splitting at SPS injection
0 10 20 30 40 50 60 70Lo
ng
. be
am p
rofi
le
0 10 20 30 40 50 60 70Time [ns]
E
0 10 20 30 40 50 60 70Lo
ng
. be
am p
rofi
le
0 10 20 30 40 50 60 70Time [ns]
E
20 ns5 ns
Scrubbing with 25 ns beam allowed to lower the SEY of the dipole chambers well below
the multipacting threshold for 50 ns e-cloud free operation with 50 ns beams
Can we go to lower bunch spacing to scrub for 25 ns operation?
• Due to RF limitations in the PS it is impossible to inject bunch-to-bucket into the SPS with spacing
shorter than 25 ns
• An alternative is to inject long bunches into the SPS and capturing each bunch in two neighboring
buckets obtaining a (5+20) ns “hybrid” spacing
“Doublet” scrubbing beam: introduction
10 20 30 40 50 60 70
0.5
1
1.5
2x 10
11
Bea
m p
rof.
[p
/m]
10 20 30 40 50 60 701
1.05
1.1
1.15
1.2
1.25
1.3
1.35
1.4
Time [ns]
Ne /
Ne(0
)
Close to the threshold all the electrons produced after a bunch passage are absorbed before the next one small accumulation over subsequent bunch passages
PyECLOUD simulation
Std 25 ns beam
e-cloud enhancement mechanism:
10 20 30 40 50 60 70
0.5
1
1.5
2x 10
11
Bea
m p
rof.
[p
/m]
10 20 30 40 50 60 701
1.05
1.1
1.15
1.2
1.25
1.3
1.35
1.4
Time [ns]
Ne /
Ne(0
)
More e- production and shorter e- decay accumulation possible
PyECLOUD simulation
Std 25 ns beam
Doublet beam
e-cloud enhancement mechanism:
“Doublet” scrubbing beam: introduction
“Doublet” scrubbing beam: SPS simulation results
MBA dipole magnet MBB dipole magnet
• Significantly lower multipacting threshold for large enough intensity per doublet
“Doublet” scrubbing beam: SPS simulation results
• Significantly lower multipacting threshold for large enough intensity per doublet
• Beam orbit modulation needs to be applied to condition a wide enough area of the
chamber
-0.02 -0.01 0 0.01 0.020
0.2
0.4
0.6
0.8
1sey = 1.35
Position [m]
Sc
rub
bin
g c
urr
en
t (5
0eV
) [A
/m2]
MBB - 26GeV
-0.02 -0.01 0 0.01 0.020
0.2
0.4
0.6
0.8
1sey = 1.30
Position [m]
Sc
rub
bin
g c
urr
en
t (5
0e
V)
[A/m
2]
0.60e11ppb0.70e11ppb0.80e11ppb0.90e11ppb1.00e11ppb1.10e11ppb1.20e11ppb6btc 25ns1.20e11ppb
Intensity per bunch of
the doublet (b.l. 4 ns)
(b.l. 3 ns)
• First machine tests have been conducted at the SPS at the end of 2012-13 run in order
to validate the production scheme and obtain first indications about the e-cloud
enhancement
• The production scheme has been successfully tested for a train of (2x)72 bunches with
1.7e11 p per doublet
42 660
1
2
3
Time [ms]
200
MH
z R
F V
olta
ge [
MV
]
4
-10
1st inj.
0.92 0.94 0.96 0.98 1 1.02-0.02
0
0.02
0.04
0.06
Time [s]
Bea
m p
rofi
le [
a.u
.]T
urn
0.92 0.94 0.96 0.98 1 1.02
100
200
300
400
500
Measurements by to T. Argyropoulos and J. Esteban Muller
“Doublet” scrubbing beam: first test at the SPS
“Doublet” scrubbing beam: first test at the SPS
42 36043600 360235983596359466 359235900
1
2
3
Time [ms]
200
MH
z R
F V
olta
ge [
MV
]
4
-10
1st inj. 2nd inj.
0 5 10 15 200
0.5
1
1.5
2
2.5
Time [ns]
Lo
ng
itu
din
al b
ea
m p
rofi
le [
a.u
.]
First bunch (of 2 single) after the second inj.
After 1st inj.
After 2nd inj.
Profile of the first doublet
• First machine tests have been conducted at the SPS at the end of 2012-13 run in order
to validate the production scheme and obtain first indications about the e-cloud
enhancement
• The production scheme has been successfully tested for a train of (2x)72 bunches with
1.7e11 p per doublet
• The possibility of injecting a second batch without degrading the circulating beam has
also been shown
“Doublet” scrubbing beam: first test at the SPS
Measurement Simulation
First results looked very encouraging, e-cloud enhancement confirmed by:
• Measurements with the electron cloud detectors (agreement with measured
cloud profile gives an important validation for our simulation model and code)
25ns std. (1.6e11p/bunch)
(1.6e11p/doublet)25ns “doublet”
“Doublet” scrubbing beam: first test at the SPS
First results looked very encouraging, e-cloud enhancement confirmed by:
• Measurements with the electron cloud detectors (agreement with measured
cloud profile gives an important validation for our simulation model and code)
• Dynamic pressure measurements observed in the SPS arcs
First results looked very encouraging, e-cloud enhancement confirmed by:
• Measurements with the electron cloud detectors (agreement with measured
cloud profile gives an important validation for our simulation model and code)
• Dynamic pressure measurements observed in the SPS arcs
“Doublet” scrubbing beam: first test at the SPS
Provided that we can produce and preserve a good quality (multiple batches, large
bunch intensity), this beam will be used during the two-day mini-scrubbing run at the
end of the 2014 run
Acquired experience will be very important for the definition of the LIU-SPS
strategy with respect to e-cloud and scrubbing and for the LHC scrubbing in 2015
To be noted• Need to commission the new transverse damper for doublets at injection
• SPS BQM software was updated for doublet beams
Outline
• Introduction
• The 2014 SPS scrubbing run
o Possible cycles
o Scrubbing stages
o Possible supercycle composition
• The doublet scrubbing beam
o Motivation
o Production scheme
o Experience in 2012-13 MDs
• Scrubbing preparation
o Beams from the PS
o SPS setup
o Measurements
Beam requirements
From the PS:Before first scrubbing week (W45):
• 25 ns beam (std. production scheme and BCMS, 72 b., up to 1.5e11 ppb)
• 50 ns beam (std. production scheme, 36 b., up to 1.7e11 ppb) – as backup
In addition, before second scrubbing block (W50):
• 25 ns beam for doublet production (>1.5e11 ppb, long bunches at extraction)
From earlier SPS setup and MDs:Before first scrubbing week (W45):
• Basic setup (injection, orbit, working point, RF, damper) of 26 GeV flat bottom cycle (with 25 or
50 ns beams, Q20)
• Setup of 25 ns LHC filling cycle
Before second block (W50):
• Setup of “doublet” beam at 26GeV (capture of multiple batches, orbit, working point, RF,
damper) and possibly acceleration
Measurements
Tests which compromise the scrubbing efficiency should be kept to the minimum possible
Collect as much data as possible to learn about ecloud effects and scrubbing in the SPS
• BCT/FBCT (to estimate beam dose)• Longitudinal parameters (BQM, mountain range, faraday cage scope)• Beam transverse oscillations
o BBQ, LHC BPMs, Headtail monitor, fast pickup from HBWD feedback setup, new
digitizers on BPW exponential pickups • Beam transverse size
o Wirescanners (bunch by bunch), BGI (?)• Pressure along the ring (1 Hz rate)
o Special attention to the a-C coated magnets• Dedicated e-cloud equipment
o Electron cloud monitors (MBA StSt, MBB StSt, MBB a-C, MBB copper)o Shielded pickup o In situ SEY measurement (if available)o Removable StSt sample (for lab SEY measurement)o COLDEX
Summary and conclusions
In the past, SPS was strongly limited by e-cloud
• Scrubbing proved to be an effective mitigation for 25 ns beams up to nominal intensity
• 25 ns beams delivered to LHC in 2012 were well within design report specs
Scrubbing run 2014
• To recondition SPS after LS1, since large parts of the SPS were vented
• 1st block: 7 days (week 45)
• Qualify the loss of conditioning due to LS1
• Recover 2012 performance with 25 ns beams
• 2nd block: 2(3) days (week 50)
• Test scrubbing with doublet (also in view of LHC in 2015)
• Experience gained will be needed for LIU decision about SPS coating
• Need to prepare beams from the PS and test instrumentation in SPS
0 0.5 1 1.50
2
4
6
8
10
12x 1028
Frequency [GHz]
Bea
m p
ow
er s
pec
tru
m
25 ns beamdoublet beam
No additional impedance heating is expected with the doublet beam (same total intensity)– Beam power spectrum is modulated with cos2 function
– Lines in the spectrum can only be weakened by the modulation
“Doublet” beam: beam induced heating
Thanks to C. Zannini