SREE RAYALASEEMA HISTRENGTH HYPO LIMITED SY. NO. 13/A1, 16, 17, 23, 67, 68, 69, 70/A, A2, GONDIPARLA VILLAGE, KURNOOL MANDAL AND DISTRICT, ANDHRA PRADESH 3. PUBLIC CONSULTATION Project No. 01182104 January 2018 Sree Rayalaseema HiStrength Hypo Limited Gondiparla Village, Kurnool District, Andhra Pradesh – 518 004 Phone: +91 984899 4505/98480 79064 Email: [email protected] STUDIES AND DOCUMENTATION BY TEAM Labs and Consultants B115117 & 509, Annapurna Block, Aditya Enclave, Ameerpet, Hyderabad500 038. Phone: 04023748 555/23748616, Telefax: 04023748666 SUBMITTED TO MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE GOVERNMENT OF INDIA INDIRA PARYAVARAN BHAWAN, JOR BAGH ROAD, NEW DELHI
Transcript
Page 1: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

SREE RAYALASEEMA HI‐STRENGTH  HYPO LIMITED 

SY. NO. 13/A1, 16, 17, 23, 67, 68, 69, 70/A, A2,  GONDIPARLA VILLAGE, KURNOOL MANDAL AND DISTRICT, 

ANDHRA PRADESH  

        

3. PUBLIC CONSULTATION 

       

   

Project No. 0118‐21‐04January 2018 

 

Sree Rayalaseema Hi‐Strength Hypo Limited Gondiparla Village, Kurnool District, Andhra Pradesh – 518 004 Phone: +91 984899 4505/98480 79064  E‐mail: [email protected] 

STUDIES AND DOCUMENTATION BY TEAM Labs and Consultants B‐115‐117 & 509, Annapurna Block, Aditya Enclave, Ameerpet,  Hyderabad‐500 038. Phone: 040‐23748 555/23748616, Telefax: 040‐23748666      

 

SUBMITTED TO MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE 

GOVERNMENT OF INDIA INDIRA PARYAVARAN BHAWAN, JOR BAGH ROAD, NEW DELHI

Page 2: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 1

13. PUBLIC CONSULTATION 13.0 Introduction

The Ministry of Environment, Forest and Climate Change, (MoEF&CC) Government of

India issued Environmental Impact Assessment notification S.O. 1533 dated September 16,

2006 mandating prior environmental clearance for manufacture of synthetic organic

chemicals industry under category ‘A’ for projects located outside notified industrial

area/estate. The proposed expansion project of Sree Rayalaseema High Strength Hypo

Limited is located at Sy. No. 13/A1, 16, 17, 23, 67, 68, 69, 70/A & A2, etc, Gondiparla

Village, Kurnool Mandal and District, Andhrapradesh. The proponents obtained the

terms of reference from the MoEF&CC, which mandated public consultation vide letter

no. F. No. J-11011/82/2016-IA II (I) dated 21.06.2016. Accordingly the draft Environmental

Impact Assessment was submitted to APPCB Regional Office, Kurnool for conducting

public hearing. The public hearing for the proposed expansion of synthetic organic

chemicals and co-generation power plant was conducted on 29.11.2017 near industry site.

The public hearing was chaired by Sri S. Satyanarayana, Collector and District Magistrate,

Kurnool District and Sri P. Prasada Rao, Environmental Engineer, APPCB Regional Office,

Kurnool.

13.1 Advertisement

Press notification regarding the date, time and venue of the Environmental public hearing

for the proposed expansion was issued in Eenadu, Sakshi (Telugu daily) and The Hans

India (English daily) newspapers on 28.10.2017. Copy of the advertisement is enclosed.

Minutes of the meeting

The minutes of the public hearing is enclosed along with the attendance sheet. Concerns

expressed by speakers during public hearing and responses of the proponent are

presented in table 7.1. Response to written representations is presented in Table 7.2.

Page 3: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 2

13.2 Concerns expressed by public

Table 13.1 Concerns Raised in Public Hearing and Responses S.No Issue raised by Issue Proponent’s Response

1 Sri T. Venkateswarllu, Ex.Sarpanch, E. Tandrapadu Village

He informed the gathering that the management of the industry have established the industries in their area at about 30 years back and informed that the development of the surrounding villages have been started with the inception of the industry in their area. He opined that the industrialization will impart the development of the surrounding villages by providing employment opportunities to the villagers and informed that the developmental activities in the surrounding villages have been earned out with the active support of the management of the industry. He also informed that their village is having continuous water supply and no other villages in the district have been extended with such facility of having continuous water supply to their villages. He informed that they are facing drinking water scarcity during the summer as Tungabhadra River is being contaminated due to the discharge of sewage into river by Kurnool Municipal Corporation and requested the authorities to take steps for avoiding discharge in to the river. He informed that many of the local people have been employed in the industry and expressed his support for the expansion activity with a request to the management to provide employment to the local villagers in the expansion activity.

Proponent assured to provide employment to the local villagers based on skill level and qualification, as part of the expansion.

2 Smt. N. Ananta Lakshrai, Surpanch, Eanchalingala Village

She explained the developmental activities being carried out by the Chairman of the company in surrounding villages such as widening of the road from Panchalingala to Devamada, laying of GI Pipe line and infiltration well for drinking water supply, Construction of Community halls for all the religions in the area and Construction of schools etc., in the area. She also informed that the industry has provided employment opportunities to their villagers and extended her support to the proposed activity as it will provide employment to the local people.

Proponent assured to provide employment to the local villagers based on skill level and qualification, as part of the expansion.

3 Sri. T. Jayaramudu, He has informed that they do not, have any objections on the Proponent assured to provide

Page 4: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 3

E.Tandrapadu Village

proposed expansion activity of SRHHL and informed that the local villages will be benefited due to the expansion activity as it will provide employment to the villagers. He requested the management to further establish industries in the area and expressed aspirations of the surrounding villages on the management of the industry for providing employment to the local villages and also development of the surrounding villages.

employment to the local villagers based on skill level and qualification, as part of the expansion.

4 Sri M. Nagaraju, MPTC, Gondiparla Village

He has informed that their villages Gondiparla & E.Tandrapadu have been provided with CC Road, Drainage facilities, Drinking water supply on par with the Kurnool Municipal Corporation and informed that all these developmental activities have been carried in their village by the chairman of the company through special funds and MP lads during last two years. He has requested the management to take up the maintenance of green belt along the Gondiparla road side, and also towards village as it will control the impacts of dust pollution if any on the surrounding villages. He has also requested the management to complete the installation of RO Plant at Vasanth Nagar and extended his support for the proposed expansion of the industry.

The proponent informed that the management will establish RO Plants in Devamada, also in E. Tandrapadu villages. The proponent assured to take up avenue plantation along the connecting road for mitigation of dust emissions.

5 Sri K Govindu, Gondiparla Village

He informed that the management of the industry have done many developmental activities in E.Tandrapadu, Gondiparla, Panchalingala villages such as providing RO water supply, Construction of Schools, laying of roads etc.,. He has requested the management to establish many more such industries in the area and also requested to provide employment to the local villagers. He has expressed his support to the proposed expansion as many people in their villages will get employment opportunities during the expansion.

Proponent assured to provide employment to the local villagers based on skill level and qualification, as part of the expansion.

6 Sri Saibaba, Ex-Ward Member, E.Tandrapadu Village

He informed that the establishment of the industry in the area have changed the scenario of the nearby villages and also Kurnool town as the management have carried out all developmental activities in surrounding villages. He informed the gathering that the management of the industry have invested huge amounts for the installation of Pollution Control measures and also the management

Proponent assured to provide employment to the local villagers based on skill level and qualification, as part of the expansion. The proponent has opined that the construction of check dam cum

Page 5: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 4

has taken all possible steps for controlling pollution from the industry. He also informed that he has visited many such Cholor alkali industries existing in Bihar, Rajasthan, & Gujarat etc., and informed that no other industry in the Country has taken Pollution Control measures as like the SRHHL. He has informed that the proposed expansion will provide employment to the local villagers and also will develop the surrounding villagers. He informed that the water in the Tungabhadra River is contaminated due to the discharge of sewage in to the Tungabhadra River by Kurnool Municipal Corporation and requested the Collector & District Magistrate to construct channel all along the river and to discharge the sewage in the downstream of the village & Kurnool town, so that river water will not be contaminated due to the sewage from the Kurnool town. He also informed that the management has taken outmost safety measures in the industry by providing fire engines, extinguishers etc.,. He has requested the management to provide employment to the local villagers who have completed degree course and expressed his support for the proposed expansion of the industry. Finally he has expressed his support for the proposed expansion.

bridge over Tungabhadra River will solve the drinking water problem in the surrounding villages and requested the Collector and District Magistrate for sanction of the approval from the Government.

7 Sri Jagan Mohan, Gondiparla Village

He has appreciated the response of management for providing temporary water line from the industry's premises to Gondiparla village till the commissioning of the permanent water scheme. He has requested the authorities for construction of check dam cum bridge over the Tungbhadra River and opined that this will provide drinking water to the Kurnool town and also to the surrounding villages even during the summer. He also the appreciated the management for providing training programmes for skill development at LVTG College to the students which is very much helpful in providing employment. He has supported the proposed expansion of the industry and requested the management to provide employment to the local villagers.

The proponent has opined that the construction of check dam cum bridge over Tungabhadra River will solve the drinking water problem in the surrounding villages and requested the Collector and District Magistrate for sanction of the approval from the Government. Proponent assured to provide employment to the local villagers based on skill level and qualification, as part of the expansion.

8 Sri Satyanarayana Yadav, Ex-Market

He has informed that the surrounding villages are not having basic infrastructure like roads, water supply, education facilities, sports

Proponent assured to provide employment to the local villagers

Page 6: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 5

Yard Director, E. Tandrapadu Village

facilities etc., prior to the establishment of the factory in the area. He has informed that the management of the industry has constructed Concrete roads, provided water supply & sanitation facilities, constructed schools & community centers, stadiums in the surrounding villages and informed that the only issues prevailing in these villages is unemployment. He requested the management to provide employment to the local villagers in the expansion activity and expressed his support for the expansion of the industry.

based on skill level and qualification, as part of the expansion.

9 Sri Venkata Swamy, MPTC, E.Tadrapadu Village

He informed that the industrialization will provide employment opportunities to the surrounding villagers and opined that the nearby villages are developed due to the establishment of the industry by the management of the M/s. SRHHL in the area at a about 30 years back. He informed that due to the prevailing drought conditions in the area, some of the villagers are migrating to faraway places for their livelihood and informed that the existence of M/s. SRHHL in the area is providing employment to the educated as well as uneducated people in the surrounding villages. He has emphasized the need for supporting the industry by the workers as well as the villagers and extended his support for expansion proposed by the industry.

Proponent assured to provide employment to the local villagers based on skill level and qualification, as part of the expansion.

10 Sri Samuel, E.Tandrapadu Village

He informed that there were no teachers working in the schools in the surrounding villages in the early 1990's and informed that the management of the industry have came forward and taken an initiative for recruiting teachers by selecting 15 No's of educated youth in the surrounding villages. He has informed that the management of the industry is paying salaries to these teachers and also extending financial support to these schools as and when required. He has supported the proposed expansion and requested the management to provide employment to the educated people prevailing in the village based on the eligibility in the proposed expansion activity.

Proponent assured to provide employment to the local villagers based on skill level and qualification, as part of the expansion.

11 Sri Govindu, Devamada Village

He has requested the authorities to provide RO Plant for drinking water in their village and informed that no action has been initiated till now inspite of submitting representation to the

The proponent informed that the management will establish RO Plants in Devamada, also in E.

Page 7: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 6

authorities. He has informed that the management of the industry has initiated the installation of RO plant in Devamada village and requested the management to complete the erection of the RO plant at the earliest. He has supported the proposed expansion of the industry and also requested the management to develop their village by construction of roads, drains, providing irrigation facilities & drinking water supply at Devamada village.

Tandrapadu villages. The proponent assured that the management will construct compound wall for the school in the Devemada village.

12 Sri. K. Somanna, Ex-Sarpanch, Gondiparla Village

He informed that he was sarpanch for Gondiparla village during the period from 1970 to 1986 and informed that there were no schools, developmental activities in the village prior to the establishment of the industry. The management of the industry have donated 4 acres of land in the village for establishing High School and since then, the management of the industry have supported the development of the village by as laying of roads, construction of drainages facilities, construction of temples, providing drinking water etc.,. He informed that the villagers are travelling more than 16 km to reach Kurnool town and explained the necessity of construction of bridge over Tungabhadra river connecting Gondiparla to Kurnool town there by the distance will be only about 1.0 Km. He informed that the bridge was not materialized though it was sanctioned by the Government earlier and requested the intervention of the Collector & District Magistrate, Kurnool District, Sri T. G. Venkatesh, Chairman of the Company for sanction of approvals and for the construction of the bridge at the earliest. He has informed that they are welcoming the proposed expansion of the industry and requested the management to provide employment opportunities in the expansion project to their villagers.

The proponent has opined that the construction of check dam cum bridge over Tungabhadra River will solve the drinking water problem in the surrounding villages and requested the Collector and District Magistrate for sanction of the approval from the Government. Proponent assured to provide employment to the local villagers based on skill level and qualification, as part of the expansion.

13 Smt. Hussainamma, Sarpanch, Devamada Village

She informed that there was no much development in their village earlier and the management of the industry have supported the development of the village by providing water facility, irrigation facility, roads etc.,. She has requested the management of the industry for construction of compound wall for the school and also for

The proponent assured that the management will construct compound wall for the school in the Devemada village.

Page 8: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 7

providing teachers to the school. She has expressed her support for the proposed expansion of the industry.

14 Sri Sunanda Reddy, NGO

He welcomed the proposed expansion project and requested the authorities to recommend to MoEF&CC, Govt., of India for sanction of the permissions to the expansion. He opined that the major pollution in the society is unemployment and the industrialization plays an important role in providing employment opportunities to the larger extent. He informed that about 2% of total land, about 3 1/2% of water resources and about 8% of air is being polluted due to the various activities and informed that there is urgent need for the protection of the environment. He has also informed that public hearing of the proposed expansion activity is being conducted in the positive way as the management of the industry have carried out all developmental activities in the surrounding villages. He opined that there is no much water pollution from the industry and he has agreed with opinion expressed by the villagers with regard to the contamination of river Tungabhadra due to the sewage discharged by the Kurnool Municipal Corporation in to the river. He has suggested the management to improve the green belt to 50% to 60% of their area and to plant medicinal/ fruit bearing trees and fruit plants while developing green belt and also appreciated the skill development programme initiated by Sri T.G. Bharath Chairman & Managing Director of the Company to solve the unemployment issue in the area.

The proponent informed that the management will take all possible steps for increasing the green belt area beyond 33% of the site area.

15 Sri. Telika Krishna (NGO)

He has appreciated the management of the industry for providing employment opportunities to the Schedule Caste & Schedule Tribe of the educated people in the surrounding area and requested the authorities to recommend MoEF & CC, GoI, for sanction of permissions to the expansion activity.

Proponent assured to provide employment to the local villagers based on skill level and qualification, as part of the expansion.

16 Sri Nagasena Reddy (NGO)

He has briefly elicited the provisions of EIA Notification of MoEF&CC, GoI and appreciated the management of the industry for conducting the public hearing in true spirit as stipulated in the notification. He has acknowledged the vision of the management for the development of the surrounding villages and requested the

Proponent assured to provide employment to the local villagers based on skill level and qualification, as part of the expansion. The proponent informed that the

Page 9: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 8

management to provide employment to the local villages and also to improve the green belt in the area. He welcomed the proposed expansion of the industry and requested the authorities to recommend to the MoEF&CC, GoI, for issue of approval to the expansion activity.

management will take all possible steps for increasing the green belt area beyond 33% of the site area in addition to avenue plantation along the connecting roads.

17 Sri Vijaya Reddy (NGO)

He has explained the sailent features of the EIA notification and informed that the public healing has to be conducted on the EIA study being carried out to know the present prevailing environmental conditions in the area and also the impacts of the proposed expansion activity on the surrounding. He also informed that the economic development of the region is vital and industrialization plays a key role in the development of the surrounding villages and therefore he requested the MoEF & CC, GoI, for sanction of approval to the expansion activity. He has requested the authorities to carryout sustainable development of the region by conservation of natural resources such as Land, Air & Water and suggested MOEF&CC, GoI, to direct the technical consultants to study the status of Animal Husbandry, Agricultural Sector and health of the people in the area in the EIA study while issuing TORs to the proponents. He has requested the authorities to inform the industries which have obtained environmental clearance from MoEF & CC, GoI, to allow the public for inspection of their industry under section 10 of the EIA notification. He suggested the management for the extensive development of green belt in the waste lands, along the road sides, etc., also to construct rain water harvesting structures in the area for percolation of rain water and requested the authorities to recommend to MoEF&CC, GoI for sanction permission to the proposed activity.

The proponent informed that the management will take all possible steps for increasing the green belt area beyond 33% of the site area in addition to avenue plantation along the connecting roads.

Page 10: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 9

Table 13.2 Response to Public Representations S. No Represented by Representation Proponent’s Response

1 Sri D. Bala Swami, E.Tandrapadu Village

He extended his support for the proposed expansion activity.

2 Sri D. Suhakar Reddy, Panchalingala village

He extended his support for expansion activity and requested employment to the local villagers.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels.

3 Sri T.V Ram Mohan He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity.

4 Sri.Yarram Nagraj, Gondiparla village

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity as it will provide employment to the local villages and also developmental activities in the surrounding villages.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

5 Sri. K. Srinivasulu, E.Tandrapadu village,

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity as it will provide employment to the local villages and also developmental activities in the surrounding villages.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels.The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

6 Sri B. Venkateshwarudu, E.Tandrapadu village

He extended his support for the proposed expansion activity.

Page 11: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 10

7 Smt. Ananta Lakshmi, Sarpanch, Panchalingala village

She extended her support for the proposed expansion activity as it will develop surrounding villages.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

8 Sri M. Nagaraj MPTC, Gondiparla village

He extended his support for the proposed expansion activity as it will provide employment and developmental activities in the surrounding villages.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

9 Sri P. Satya Narayana, E.Tandrapadu village

He extended his support for the proposed expansion activity as it will provide employment and developmental activities in the surrounding villages.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

10 Sri K. Venkata Swami, E.Tandrapadu village

He extended his support for the proposed expansion activity as it will provide the developmental activities in the surrounding villages.

The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages

Page 12: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 11

and they will construct compound wall for the school in the Devemada village.

11 Sri B. Srinivasulu, E.Tandrapadu village

He requested to recommend toMoEF & CC, GoI for issue of Environmental Clearance for expansion activity as it will provide employment to the local villagers and also developmental activities in the surrounding villages.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

12 Sri G. Ramesh, Alampur village, Telanagana State

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity as it will provide employment to the local villagers and also developmental activities in the surrounding villages.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels.The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

13 Sri B. Beesanna He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity as it will provide employment to the local villagers and also developmental activities in the surrounding villages.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

14 Sri K Dastagiri & Sri G.Mahesh Kumar,

They requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity

The proponent assured that the management will will prefer local

Page 13: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 12

Gondiparla village as it will provide employment to the local villagers and also developmental activities in the surrounding villages.

villagers for employment in the expansion plan based on educational qualification and skill levels. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

15 Sri G. Veeranna Shetty, Gondiparla village

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity as it will provide employment to the local villagers and also developmental activities in the surrounding villages.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

16 Sri P. Venkata Raman, E.Tandrapadu village

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity as it will provide employment to the local villagers and also developmental activities in the surrounding villages.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

17 Sri K. Maddiletti & Sri Nasuruddin, Gondiparla village

They requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity as it will provide employment to the local villagers and developmental activities and also protection of environment in the surrounding villages.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels. The proponent informed that the

Page 14: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 13

management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

18 Sri P. Meera Saheb, E.Tandrapadu village

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity as it will provide employment to the local villagers and developmental activities and also protection of environment in the surrounding villages.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

19 Sri D.Venkateshwar Reddy, Poolathota village

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity as it will provide employment to the local villagers and also developmental activities in the surrounding villages.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

20 Sri B.Shivaramulu, Gondiparla village

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity as it will provide employment to the local villagers and also developmental activities in the surrounding villages.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

Page 15: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 14

21 Sri P Gokari, E.Tandrapadu village

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity as it will provide employment to the local villagers, developmental activities and also to protect environment in the surrounding villages.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

22 Sri K. Venkateshwarlu, Gondiparla village

He extended his support for expansion activity and requested the management to provide employment to the local villagers and developmental activities and also protection of environment in the surrounding villages.

The proponent informed that the management will take all possible steps for increasing the green belt area beyond 33% of the site area in addition to avenue plantation along the connecting roads. The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels.

23 Sri K. Govind, Gondiparla village

He extended his support for expansion activity and requested the management to provide employment to the local villagers and developmental activities and also protection of environment in the surrounding villages.

The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village. The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels.

24 Sri P Sudhakar & B. Ravi Kumar,

They extended support for expansion activity and requested the management to provide employment to

The proponent assured that the management will will prefer local

Page 16: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 15

E.Tandrapadu village the local villagers and developmental activities and also protection of environment in the surrounding villages.

villagers for employment in the expansion plan based on educational qualification and skill levels.

25 Sri Y. Chenna Kesava Reddy, Hyderabad

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance and suggested the management for utilization of CSR budget for effected local villages, employment opportunities to the villagers, construction of rain water harvesting structures, and conducting regular medical camp.

The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

26 Sri D. Suryachandra Reddy, Gondiparla village

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity as it will provide employment to the local villagers and also developmental activities in the surrounding villages.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels.

27 Sri R.Raja Sekhar Reddy, Poolathota village

He extended his support for expansion activity as it will provide employment to the local villagers and also developmental activities in the surrounding villages.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels.

28 Sri Sanku Srinivasulu Jai Bheem Youth Association, Hayath Nagar, Ranga Reddy District, Telangana

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity.

29 Sri B Venkatesh, "Dalitha Sankshema Samithi", Hyderabad

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity.

The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

30 Sri K Madhu Swami, E.Trandapadu village

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity as it will provide employment to the local villagers and developmental activities and also protection of

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational

Page 17: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 16

environment in the surrounding villages. qualification and skill levels. 31 Sri Pavan Kumar Reddy,

Gondiparla village He extended his support for the proposed expansion activity as it will provide employment and developmental activities in the surrounding villages.

The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels.

32 Sri P. Krishnaiah, Paryavarana Parirakshana Samithi (NGO), Dwarakapuram, Hyderabad

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity as the industry is implementing all the measures.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels.

33 Sri S.Sudhakar Reddy, Gondiparla village

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity as it will provide employment to the local villagers and developmental activities and also protection of environment in the surrounding villages.

The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

34 Sri Y.Mahananda Reddy, Danda Kondamma Charitable Trust, Kadapa.

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance and suggested the management for utilization of CSR budget for effected local villagers, employment opportunities to the villagers, construction of rain water harvesting structures, and conducting regular medical camp.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels.

35 Sri Y.M N Reddy, Danda Kondamma Charitable Trust, Kadapa.

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance and suggested the management for utilization of CSR budget for effected local villages, employment opportunities to the villagers and development of green belt.

The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

Page 18: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 17

36 Sri T Maddiletty & Sri P Narasimha Swami, E.Tandrapadu village

They requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity as it will provide employment to the local villagers and developmental activities and also protection of environment in the surrounding villages.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels.

37 Sri S. Venkateshwarlu, Neethaa Swachanda Seva Society, Abudullah Khan Estate, Kurnool

He has suggested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity and requested the consultant to provide health status, crop production details from nearby agricultural lands within 10 Kms radius and also suggested rain water harvesting structures.

Rain water harvesting is proposed as part of the expansion, and it is proposed utilize storm water run off partially.

38 Sri V.Vijay Kumar (NGO), Environmental Protection Committee, Hyderabad

He has suggested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity and requested the consultant to notify the health status of the people living within 10 Kms of radius, providing medical facilities to the labour of that area, providing incentives to the rural and semi-urban areas, allocation of CSR funds for health facilities & Construction activities.

All employees both permanent and contract undergo health check up during recruitment and periodically based on their age.

39 Sri Chepuri Raju, "Dalitha Bahujana Party", Hyderabad,

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity.

40 Sri Pushadapu Kodanda Venkataramana, Gondiparla village

He extended his support for expansion activity and requested the management for development of green belt, employment to the local villagers, developmental activities in the surrounding villages & providing drinking water to the surrounding villages.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels.The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.The proponent informed that the management will establish RO Plants in

Page 19: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 18

Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

41 Sri Patanjali Shartri, E.Tandrapadu

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance for expansion activity as it will provide employment to the local villagers and developmental activities and also protection of environment in the surrounding villages.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels.The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village. Proponent assured to implement all necessary pollution control measures to reduce the impact on surrounding areas.

42 KK Reddy, Vikas Rural Development Society, Hyderabad,

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance and suggested the management for utilization of CSR budget for education & health facilities, providing employment to the local villagers and to implement measures for environmental protection in the area.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels. Proponent assured to implement all necessary pollution control measures to reduce the impact on surrounding areas.

43 Sri Mattaiah President, Mother Organization (NGO), Hyderabad

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance and suggested the management for utilization of CSR budget for education & health facilities, providing employment to the local villagers and to implement measures for environmental protection in the area.

The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

44 Sri Kiran Reddy (NGO), Hyderabad

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance and suggested the management for utilization of CSR budget for education & health facilities, providing employment to

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational

Page 20: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 19

the local villagers and to implement measures for environmental protection in the area.

qualification and skill levels. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

45 Sri Ch. Kashiviswanatham, Hyderabad

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance and suggested the management to provide employment opportunities in the surrounding villages and developmental activities and also protection of environment in the surrounding area.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

46 Sri P Subhaan, E.Tandrapadu

He extended his support for expansion activity and suggested the management to provide employment opportunities in the surrounding villages and developmental activities and also protection of environment in the surrounding area.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village. The proponent assured to implement all pollution control measures as suggested by MoEFCC and APPCB to ensure least impact on the surrounding villages.

47 Sri K Lakshmi, Sarpanch, Gondiparla village

He extended his support for expansion activity and suggested the management to provide employment opportunities in the surrounding villages.

The proponent assured that the management will give outmost preference to the surrounding villages for providing employment in the

Page 21: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 20

expansion activity. 48 Sri Sekhar Babu,

Gondiparla village He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance and suggested the management to provide employment opportunities in the surrounding villagers and developmental activities and also protection of environment in the surrounding area.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

49 Sri T Ramalingeshwara, Gondiparla village

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance as the industry will develop surrounding villages.

The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

50 Sri G.Jagan Mohan, Gondiparla village

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance and suggested the management to provide employment opportunities in the surrounding villagers and developmental activities and also protection of environment in the surrounding area.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

51 Sri C. Laskhmanna, E.Tandrapadu village

He extended his support for expansion activity as it will provide employment to the local villagers and also develop the surrounding villages.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels.. The proponent informed that the

Page 22: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 21

management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

52 Sri M Krishna Murthy, NGO, Hyderabad

He extended his support for expansion activity and suggested the management to implement the measures for control of Air & Water pollution, development of green belt, spending CSR funds in the effected villages and to provide it will provide employment to the local villagers.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels.The proponent assured to implement pollution control measures as suggested by MoEFCC and APPCB to ensure minimum impact on the surrounding villages. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village. The proponent informed that the management will take all possible steps for increasing the greenery above 33% and avenue plantataion along the connecting road.

53 Sri A Sudharsanam, NGO, Cheyuta Rural Development Society, Vadapally Village, Damaracherla Mandal, Nalgonda District, Telangana State

He extended his support for expansion activity and suggested the management for development of green belt, spending CSR funds in the effected villages and to provide employment to the local villagers.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall

Page 23: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 22

for the school in the Devemada village. The proponent informed that the management will take all possible steps for increasing the greenery above 33% and avenue plantataion along the connecting road.

54 Sri K. Venkateshwarlu, E.Tandrapadu

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance suggested the management to provide employment opportunities in the surrounding villagers and developmental activities and also protection of environment in the surrounding area.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

55 Sri B.Venkatesham President, Prakruthi Rural Development Society, Gundrampally Village, Nalgonda District, Telangana State

He extended his support for expansion activity and requested the management to develop the surrounding villages.

The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

56 Sri K.Sathish Kumar, Gondiparla village

He extended his support proposed expansion activity and requested the management to carry out developmental activities, such as laying roads, education facilities, providing RO plants, etc., in the villages.

The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

57 Sri H. Madhubabu, President, Rural Environmental Health Education Society, Hyderabad

He supported the proposed expansion activity and also suggested the environmental consultant to notify the health status of the people, crop production details within 10 Kms of radius, construction of rain water harvesting structures, sprinkling of water on the roads, development of green belt to 50%, employment

The proponent assured that the management will give preference for surrounding villages for providing employment in the expansion activity. Rain water harvesting is proposed as part of expansion, and CSR activities are

Page 24: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 23

to the local people, medical facilities & regular conducting of medical camps, drinking water facilities nearby villages, education facilities, development of roads and spending CSR funds by forming a committee.

also proposed which involves providing social infrastructure and skill development.

58 Sri Dundigala Anjaiah, President, Adarsha People's Agricultural Rural Development Education Society, Hyderabad

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance and suggested the management to improve the green belt and to provide employment to the local villagers.

The proponent informed that they will ensure improvement of green belt and provide employment to local villagers based on qualification and skill levels.

59 Sri K.Chandra Shakar Prasad, Telangana Rastra Swachhanda Samsthala Samakya, Telangana state

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance.

60 Sri K. Shankar (Secretary) Adarsha People's Agricultural Rural Development Education Society, Hyderabad

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance.

61 Sri Janardhan Reddy, NGO, Hyderabad

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance as the industry provides employment to the local villagers.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels.

62 Sri K Nagaraju, Alampur, Jogulamba District

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance as the industry provides employment to the local villagers.

The proponent assured that the management will will prefer local villagers for employment in the expansion plan based on educational qualification and skill levels.

63 Sri Nagasena Reddy, NGO, Hyderabad

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance and suggested the

The proponent assured to provide pollution control measures as suggested

Page 25: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture

Sree Rayalaseema High Strength Hypo Limited Environmental Impact Assessment Report

Team Labs And Consultants 13 - 24

management to carry out the expansion activity following the conditions stipulated by the Pollution Control Board.

by MOEFCC and APPCB to ensure least impact on surrounding villages.

64 Sri L C Shekar, President, Sri Vamshi Arts Academy, Ramannapet, Nalgonda District

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance and suggested the management for implementation of measures for protection of environment, green belt development, spending CSR budget for developmental activities & health facilities.

The proponent assured that the management will give preference to the surrounding villages for providing employment in the expansion activity. The proponent assured to provide pollution control measures as suggested by MOEFCC and APPCB to ensure least impact on surrounding villages.

65 Sri J. Sanjeev, President, Praja Telangana Journalist Welfare Association

He requested to recommend to MoEF & CC, GoI for issue of Environmental Clearance and suggested the management for providing employment to the local villagers, utilization of CSR budget for education & health facilities and also for environmental protection in the area.

The proponent assured that the management will give preference to the surrounding villages for providing employment in the expansion activity. The proponent assured to provide pollution control measures as suggested by MOEFCC and APPCB to ensure least impact on surrounding villages. The proponent informed that the management will establish RO Plants in Devamada and E. Tandrapadu villages and they will construct compound wall for the school in the Devemada village.

Page 26: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture
Page 27: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture
Page 28: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture
Page 29: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture
Page 30: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture
Page 31: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture
Page 32: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture
Page 33: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture
Page 34: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture
Page 35: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture
Page 36: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture
Page 37: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture
Page 38: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture
Page 39: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture
Page 40: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture
Page 41: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture
Page 42: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture
Page 43: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture
KIRAN
Rectangle
Page 44: SREE RAYALASEEMA HI STRENGTH HYPO LIMITEDenvironmentclearance.nic.in/writereaddata/Public Hearing...Aditya Enclave, Ameerpet, ... 2006 mandating prior environmental clearance for manufacture
KIRAN
Rectangle

Recommended