+ All Categories
Home > Documents > Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road...

Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road...

Date post: 04-Jul-2020
Category:
Upload: others
View: 4 times
Download: 0 times
Share this document with a friend
112
Initial Environmental Examination June 2012 Sri Lanka: Northern Road Connectivity Project Additional Financing North Central Provincial Roads Prepared by Ministry of Local Government and Provincial Councils for the Asian Development Bank.
Transcript
Page 1: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Initial Environmental Examination

June 2012

Sri Lanka: Northern Road Connectivity Project

– Additional Financing

North Central Provincial Roads

Prepared by Ministry of Local Government and Provincial Councils for the Asian Development Bank.

Page 2: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

CURRENCY EQUIVALENTS (as of 5 June 2012)

Currency unit – Sri Lankan rupee (SLR) SLR1.00 = $0 .0076917160

$1.00 = SLR 130.010000

ABBREVIATIONS

ADB – Asian Development Bank ADT – average daily traffic AC – asphalt concrete AP – affected person BIQ – basic information questionnaire CEA – Central Environmental Authority CEB – Ceylon Electricity Board CSC – construction supervision consultant DA – Department of Archeology DBST – double bitumen surface treatment DoAS – Department of Agrarian Services DoF – Department of Forestry DoI – Department of Irrigation DS – Divisional Secretary DSD – Divisional Secretariat Division DWLC – Department of Wild Life Conservation EA – Executing Agency EIA – environmental impact assessment EMP – environmental management plan EMoP – environmental monitoring plan EMS – environment method statement EO – Environment Officer ES – Environment Specialist GN – Grama Niladhari GND – Grama Niladhari Divisions GRC – Grievance Redress Committee GRM – Grievance Redress Mechanism GSMB – Geological Survey and Mining Bureau IEE – initial environmental examination LA – local authority MLGPC – Ministry of Local Government and Provincial Councils MSL – mean sea level NEA – National Environmental Act NRCP (PC) – Northern Road Connectivity Project (Provincial Component) NCP – north central provinc NGO – nongovernment organization PAA – Project approving authority PD – Project Director PHI – Public Health Inspector PIU – Project Implementation Unit PRDA – Provincial Road Development Authority RE – Resident Engineer

Page 3: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

REA – rapid environmental assessment ROW – right-of-way RPPF – Road Project Preparatory Facility TOR – terms of reference

WEIGHTS AND MEASURES

km – kilometer m – meter

NOTE

In this report, "$" refers to US dollars. This initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 4: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Contents

Executive Summary .................................................................................... vi

Chapter 1 - Introduction .............................................................................. 1

1.1. Project Background and the Justification ....................................................... 1 1.2. Extent and Scope of the Study ...................................................................... 2 1.3. Objective of the IEE Report ........................................................................... 3 1.4. Structure of IEE Report .................................................................................. 3 1.5. Applicable Environmental Legislations .......................................................... 4 1.6. Methodology ................................................................................................... 6

Chapter 2 - Description of the Project ........................................................ 8

2.1. Type of the Project ......................................................................................... 8 2.2. Category of the Project .................................................................................. 8 2.3. Need for the Project ....................................................................................... 8 2.4. Location .......................................................................................................... 9 2.5. Analysis of Alternatives ................................................................................ 12 2.6. Size and the Magnitude of Operation .......................................................... 12 2.7. Cost for the Project ...................................................................................... 13 2.8. Proposed Schedule for Implementation ....................................................... 13

Chapter 3 - Project Affected Area ............................................................. 14

3.1. Existing Condition of the Subproject Roads and Proposed Work ............... 14 3.2. Description of the Existing Environment of the Project Affected Area ......... 20

Chapter 4 - Potential Environmental Impacts Screening and Mitigation Measures ............................................................. 31

4.1. Environmental Impacts Associated with Pre Construction and

Construction Stage....................................................................................... 31 4.2. Environmental Impacts Associated with Operation Period .......................... 42

Chapter 5 - Institutional Requirements and Grievance Redress Mechanism ............................................................................ 44

5.1. Institutional Arrangements ........................................................................... 44 5.2. Capacity Building ......................................................................................... 45 5.3. Grievance Redress Mechanism ................................................................... 46

Chapter 6 - Environmental Management Plan (EMP) .............................. 49

6.1. Environment Management plan ................................................................... 49 6.2. Environmental Monitoring Plan (EMoP) ....................................................... 49

Chapter 7 - Public Consultation and Information Disclosure ................ 51

7.1. Public Consultation ...................................................................................... 51 7.2. Information Disclosure ................................................................................. 53

Chapter 8 - Conclusion and Recommendations ..................................... 54

References ................................................................................................ 56

Page 5: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

v

List of Annexures

A. Topographical maps of subprojects

B. Environment Management Plan (EMP)

C. Environmental Monitoring Plan (EMoP)

D. Public Consultation

List of Attachments

1. Flora and fauna list

Page 6: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Executive Summary

1. Introduction

1.1. Project Background and the Justification

1. The proposed Review of Feasibility Study and Detail Design of NRCP (PC) includes

rehabilitation and upgrading of 75.15km5 C class roads (41.55 km) and 2 D class roads (33.60

km) located within 2 DSDs; (Medawachchiya and Kebithigollewa) of Anuradhapura district of

NCP of Sri Lanka with the financial assistant of on-going NRCP ADB Loan 2639.The review of

the proposed roads is being performed by Egis Bceom International, France in association

with the Consulting Engineers and Architects Associated (Pvt) Ltd, Sri Lanka on behalf of the

NCP PRDA under the MLGPC of Sri Lanka.

2. The present review study focuses on updating the Environmental Examination of the

above 7 roads which were conducted during the feasibility stage of NCP road of Anuradhapura

district in 2007. Field work for the former IEE study had been conducted in June 2007 during

the civil war period of the country. During that period, villages of this area were named as

bordering villages and highly affected due to terrorist attacks. Therefore field data collection of

several proposed roads were unable in 2007. Apart from that, there was rapid infrastructure

development in the area after the war. Hence the data on Physical, Ecological, Social and

Economic background of the individual roads may have been changed by now. Therefore the

current review focuses on analysing the gaps of existing reports, update and improve them

with the current environmental condition of the project affected area.

3. The former consolidated IEE report had been prepared in accordance with ADB IEE

guidelines 2003. Hence the present review focuses on rearranging the report in accordance

with ADB SPS 2009 while confirming to the requirements of the “Environmental Framework”

established for NRCP and Environmental Assessment Guidelines of CEA of Sri Lanka.

4. The main objectives of the project are to reduce travel time, cost for transportation,

improve reliability of access; connectivity of the provincial road network to rural and national

highway network thereby enhance the opportunities for economic development of the project

area.

1.2. Extent and Scope of the Study

5. The Environmental Assessment was carried out for a total of 75.15m 5 C and 2 D class

roads located within Anuradhapura districts. The project comprises a total area of 75.15ha

over the project stretch of 75.15 km in an average strip of 10.0 m width. The scope of the study

include: collection of field data, conducting public consultation, preparation of BIQs and

submission to the CEA, preparation of REAs, assessment of potential environmental impacts

and development of mitigation measures for significant impacts, preparation of EMP,EMoP,

preparation of institutional requirements, grievance redress mechanism and finally

consolidated IEE report.

Page 7: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

i

1.3. Methodology

6. The review study was carried out with the data obtained from former IEE report, field

surveys, engineering designs, secondary sources and data from other team of consultants

attached to the review study. Field observation and public consultation sessions for the

proposed study were carried out during the period from 10thDecember 2011 to January 2012.

Public consultation sessions were carried with the affected parties to get their current

perception on the project and those views and suggestions were incorporated to the reviewed

reports.

2. Description of the Project

2.1. Type and the Category of the Project

7. The project activities will involve repair, rehabilitation and/or upgrading of identified 7

provincial roads. According to BIQ’s and Environmental Guidelines for Road and Rail

Development in Sri Lanka of CEA (1997) proposed project roads fall in to un-prescribed

category. Based on the REA Checklist of the ADB classification, NCP roads are categorized

under environment category B. Thus the IEE serves as the complete Environment Assessment

for the proposed project.

2.2. Need for the Project

8. Insufficient maintenance and improvements as well as damages occurred during the

war period in the past has resulted in highly dilapidated conditions of the proposed roads

which lead to disturbance of access and maintaining the social services in the rural areas of

the district. Apart from that poor alignments, narrow road sections, structurally damaged

culverts, causeways and bridges contributes to high vehicle operation costs, long travel time

and high transport costs. Therefore improvement of the provincial road network in these areas

is essential for the rural people to directly access to the semi urban and urban area to engage

in number of social and economic activities easily through proper road communication.

2.3. Analysis of Alternatives

9. All the roads identified for the proposed rehabilitation are very essential link roads to

the interior parts of Anuradhapura district. Even without proposed rehabilitation and

improvement, the roads will continue to be a main transportation link with rural, agricultural and

urban areas. The subproject roads are not located through or close proximity to any national

parks, sanctuaries or any other protected areas demarcated by the relevant authorities.

Further the project will not require any land acquisition from the road side community. Thus,

the proposed improvements will be the best option.

2.4. Size and the Magnitude of Operation

10. Road improvement works for provincial roads under NRCP-PC will involve repair,

rehabilitation and/or upgrading of existing provincial roads. In general road carriageway widths

vary between 2.7 and 5.00 m with the majority of the proposed pavement width being 6.50m.

Shoulder widths vary between 0.50 m to 1.0 m with the majority being 1.00 m. Road formation

width is generally 4.50 m and road RoW between 8.50 m to 11.50 m.

Page 8: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

ii

2.5. Cost for the Project

11. The total cost estimated for the major items associated with the proposed subprojects

works were established by the application of appropriate unit rates to the estimated work item

quantities derived from the results of surveys, test results and design analysis for subprojects.

The finalized estimates of each subprojects will be included in Volume 4 – Cost estimates of

Detail Design and Final Report of the project.

2.6. Proposed Schedule for Implementation

12. Review Feasibility Study and Detailed Design of the proposed project will be completed

in July 2012. Once detailed designs and bid documents are completed, tenders will be

awarded to the successful contractors. ADB is the funding agency for Feasibility Study,

Detailed Engineering Design and for the civil works. Improvement works of the project are

scheduled to be completed within two years.

3. Description of the Existing Environment of the Project Affected Area

3.1. Existing Condition of the Subproject Roads and Proposed Work

13. Selected roads for the rehabilitation and improvement are restricted to 2 DSDs and 2

PSDs namely Medawachchiya and Kebithigollewa. All the proposed roads run through rural,

residential and agricultural areas of Anuradhapura district. The land use beside the proposed

roads include paddy fields, Chena cultivations, scrub lands, small forest patches, mixed home

gardens (coconut, banana) and residences. All these roads start from national roads and

connected with provincial roads of the area. Apart from that number of rural road sections start

from the proposed roads at different locations and runs towards the rural villages and

agricultural areas

14. In general the existing condition of these roads is in unsatisfactory level for the

transportation. During the dry season, the situation of the roads is fairly good with scattered

potholes. However during rainy season it is difficult to travel through these roads due to large

numbers of potholes with water stagnated locations and inundation sections. In general the

terrain of the roads is flat and the alignment mainly straight with few curves.

15. Although electricity is available beside all the roads, telecommunication facilities are

not available in the project area. Several public sensitive locations such as schools, mosque

and temples are located beside the roads and people use these roads to reach these

locations. Many seasonal tanks can be seen beside the roads (Eg.NCANC122, NCANC126,

NCANC127, NCAHC128) while some roads cross the tank bunds (Eg.NCAHC128 and

NCAND139)

Page 9: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

iii

3.2. Description of the Existing Environment of the Project Affected Area

3.2.1. Physical Resources

Topography, Geology and Soil

16. Anuradhapura district is located in the Northern half of Sri Lanka and bordered by 7

districts. The elevation of the land in the district ranges from 30 m to about 200m MSL. The

terrain is undulating nature with the ridges and hills that rise above the base elevation. The

geology of the major part of the district is highly crystalline. There are five rock types within

district which are generally in the Central and Eastern parts named as Highland series.

Reddish Brown Earth – Low Humic Gley association of soil is the most commonly distributed

soil in this district and make up the landscape in the district.

Climate

17. The climate of Anuradhapura district is typical to the Dry Zone of Sri Lanka. This district

receives an annual average rainfall of 1420 mm, mainly by North East monsoons. The annual

average temperature of the district is 27.3oC. The relative humidity of the district varies from 70

– 82% within the year. During the South Western monsoons the wind speed accelerates to 12

km/hr or it rises further to 16 km/hr. Evaporation rate is 35 mm/week and varies from place to

place.

Water Resources

18. Tanks, streams, and springs are the main sources of surface water in the district.

Perennial tanks and seasonal tanks are common in most parts of the district and are mainly

use for the purpose of agricultural activities. Throughout the proposed road sections many

seasonal tanks could be observed. Ground water in the district is mainly used as a source of

drinking water, however at present it is used for agricultural activities in dry season. Ground

water refers to both shallow and deep. Shallow ground water fluctuates with rains and its

availability is seasonal. The quality of ground water varies with the available compounds and

substances of the district.

Air Quality and Noise

19. Number of mettle quarries, crushers and gravel mines are located in Madawachchiya

and Kebithigollewa DS divisions. Therefore ambient air quality of the area may affected due to

emissions from above sites and related transport activities. Apart from that, low addition of

SO2 has occurred due to the heavy usage of fertilizers and soil conditioners within this district.

However atmospheric characteristics such as CO, SO2, dust and other particulate matter of

the air in Madawachchiya and Kebithigollewa areas have not been studied yet.

3.2.2. Ecological Resources

20. The natural vegetation in the Anuradhapura district and the sub-project affected areas

is mainly consists with tropical Dry Mixed Evergreen Forest. The forest cover of the district is

24% of the land area in the district. The vertebrate fauna including fresh water fish,

amphibians, reptiles and mammals have been recorded in the district. Out of the 427 bird

Page 10: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

iv

species recorded in Sri Lanka, many are reported to be present in this district. There are

several Wildlife Parks, Sanctuaries, Strict Nature Reserves and Tropical Wetlands located

within the district. However any of the environmental sensitive areas are not located within or

close proximity to the project area.

3.2.3. Economic Development

Land Use and the Agriculture

21. Anuradhapura is the largest of all districts in Sri Lanka, covering an area of 738953 ha

which is 11% of the whole country’s land surface. The land use beside the project area

include, large extents of paddy fields, scrublands, forested areas, mixed cultivations, Chena

cultivations, home gardens and residences. The majority of the people in the area is farmers

and largely depends on paddy cultivation. Apart from that district economy is predominantly

centred on chena and home gardens with vegetable cultivation. Additionally animal husbandry

including cattle, goat and poultry is also common in some roads.

Industries

22. Apart from agriculture, economy of the Anuradhapura district is predominantly revolves

around tourism industry, inland fisheries, small scale industries and some large scale

industries. However compare to the other districts, industrial contribution in the district is poor.

At present, most of the population in the district depends on tourism industry because of

ancient Sri Lankan culture mainly concentrated to the NCP. Eco-tourism is another

popularizing area based on the eco-cultural history of the Ancient kingdom.

Infrastructure Facilities

23. Except in some rural villages, electricity and telecommunication is available for most

parts of the district. Pipe borne water supply, pit latrines, sewage canal systems and proper

garbage dumping sites are restricted to the urban sector of this district. Telecommunication

facility is mainly obtained through wireless telecommunication services. Common wells have

been constructed mainly for the domestic and agricultural purposes.

3.2.4. Social and Cultural Development

Population and Community

24. A total of 22 DSDs and 19 PSDs are located within the Anuradhapura district and

selected roads for the improvement run through 2 out of 22 DS divisions. The population of the

Anuradhapura district by 2008 was 886,945 and represent all ethnic and religious groups in

the country. Sinhala Buddhist is the commonest ethnic group in the district and this also

applies to subproject areas.

Page 11: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

v

Health and Educational Facilities

25. A total of 60 hospitals distributed in different locations of the district. These include

Provincial general hospital, Base hospitals, District hospitals, Peripheral units, Prison hospital,

rural hospitals, Central dispensary, Maternity homes and Dispensaries. Apart from that

Indigenous Medical Services is also common in the district. Generally the education level of

the district is fairly good and the literacy rate is 90.5%. There are 11 government schools

located along the proposed subproject roads.

3.2.5. Sites of the Cultural, Archaeological and Historical Significance

26. From the 4th century BC, Anuradhapura was the capital city of Sri Lanka and until the

beginning of the 11th century it remained one of the most stable and durable centres of political

power and urban life in South Asia. Today it is recognised as a World Heritage Site by

UNESCO. There are many important religious, historical, cultural and archaeological sites

located within the district. However none of the above significant sites are located close

proximity to the proposed subproject roads except few locally important Buddhist temples and

mosque.

4. Screening of Potential Environmental Impacts and Mitigation Measures

27. Proposed construction activities of the subproject roads can cause several impacts to

the existing environment of the project areas. The potential environmental impacts and

feasible mitigation measures for those impacts are discussed below.

4.1. Environmental Impacts Associated with Pre Construction and Construction Stage

Resources mobilization

28. Mobilization of resources for the project construction activities such as space, human

capital and physical resources is a major task carryout at an early stage of the project. The

space need for various activities of the project includes construction of material processing

plants, storage yards, labour camps, offices and other accommodations. Adequate provision

should be made to mobilize the space, construction equipment’s, vehicles and other

construction materials.

Selection of lands for temporally use

29. Selection of lands for various project activities such as materials processing plants,

storage yards, labour camps etc. should be undertaken by the contractors carefully, away from

environmental and public sensitive areas in accordance with local laws, regulations and in

close consultation with villages and LAs. Selection of local un-skilled and skilled workers can

reduce the requirement of land for labour camps in large scale.

Page 12: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

vi

Acquisition of lands

30. Availability of lands according to the detailed design of the subprojects is important for

the construction activities. Since construction activities are restricted to the existing RoW of the

selected subproject rods, land acquisition will not be required for the proposed activities.

Removal of public utilities

31. Road improvement work may generally impact on electricity facilities which are located

within the existing RoW. Since most of the electrical posts of the proposed projects are located

away from the existing carriage ways, impact will be less due to removal. Recruitment of well

trained and experienced employees, proper coordination with CEB during the removal,

advance notice to the public about the time and duration of the utility disruption will reduce the

accidental damage to the utilities, people and public inconvenience.

Extraction, transportation and storage of construction materials

32. Extraction of construction materials can induce noise, air & water pollution, social

disturbances, health problems, reduction of scenic beauty and damage to ecosystems.

Extraction sites provide breeding sites for vectors and cause accidental damage to people and

wild animals. Transportation and storage of construction materials can disturb the general

public, increase dust and noise nuisance and damage to minor roads. Adhering to

environmental requirements and guidelines issued by the CEA, GSMB and LAs with respect to

extraction, transportation and storage of construction materials will minimize the above

impacts.

Effect on local road net work

33. Since the construction materials required for the project have to be transported from

other areas to the project sites, the local road network can be damaged during transportation

of construction materials. Obtaining permits from LAs to use local road network prior to

construction, avoid transportation of construction materials exceeding the carrying capacity of

the local road network, making provision for repair and restoration If public roads get damaged

are the major steps that can be taken to avoid effect on local road network.

Solid waste disposal and sanitation

34. Solid waste associated with construction and other related works may impose several

negative environmental and social impacts to the subproject affected area including impact on

soil, water, public health and scenic beauty. Selection of the disposal site away from public

and environment sensitive areas, provision of proper solid waste disposal, sanitation and

sewerage facilities to all sites, adhering to the guidelines/recommendations issued by CEA and

LAs will avoid or minimize health hazards and environmental pollution. Selection of majority of

skilled and unskilled workers from the project influence area will avoid waste generation and

sanitation problems from labour camps. This will also avoid conflict situations between workers

and settlers as well as spreading of communal diseases.

Page 13: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

vii

Effect on water resources

35. Construction activities close to the water bodies, poor sanitation at work sites and

disposal of solid waste from labour camps may affect the surface and groundwater of the

project affected area. Excessive use of water for construction activities during dry season may

impact the water supply of the local communities. Awareness of employees about water

conservation, pollution and minimization of water usage, undertaking construction works

affecting water bodies during the dry season, taking necessary steps to avoid entering

wastewater directly in to the water bodies, maintaining smooth water flow by proper drainage

facilities, preventing disruption of water sources used by the community due to construction

work are the major steps that will avoid the effect on water resources.

Soil erosion sedimentation and siltation

36. The project affected area of NCP receives a considerable amount of water during rainy

season. Thus soil erosion, sedimentation and siltation can take place any time during rainy

seasons due to construction activities. Placement of erosion control measures to erodible

areas, undertaking construction activities in erodible sections during dry season, treatment of

clearing and filling areas against flow acceleration are the measures that should be considered

to mitigate soil erosion during the construction stage.

Temporary floods

37. During the rainy season, water stagnation can be observed within the RoW of

subproject roads situated in low elevation, between paddy fields and close to spills of seasonal

tanks. Increasing of embankment height of the inundation sections, minimization of blockage

of drainage paths and construction of cross drainages with sufficient capacity will avoid

location specific temporary floods

Effect on flora, fauna and their habitats

38. Construction activities related to soil erosion, surface runoff, noise and air pollution,

vibration at the project site will potentially disturb the habitats, change the usual behaviour of

wild animals and can affect the natural ecology of the project area. Removal of trees from the

existing RoW and other excavation works has the potential to destroy or injure wildlife.

Conducting awareness of workforce regarding important of fauna, flora and their habitats,

prevent workforce from fishing, hunting animals and gathering fire wood from soundings,

organizing tree planting program in appropriate locations are the major steps that has to be

taken to reduce Effect on flora, fauna and their habitats.

Biodiversity conservation and sustainable natural resource management

39. Since the proposed project activities are restricted to the existing RoW of the

subproject roads, loss of habitats, changes in the land use pattern, modification of existing

habitats, threat to existing biodiversity or introduction of invasive species will not be expected

through the subproject activities. However careful attention should be taken during the

construction phase to avoid/minimize clearing of natural habitats, effect on native species,

introduction of alien species, making awareness of all stakeholders regarding biodiversity

Page 14: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

viii

conservation and periodic assessment to check the introduction of invasive alien species will

be essential for biodiversity conservation.

Protection of archaeological, cultural and religious places

40. None of the proposed subproject roads are not located close proximity to the important

archaeological, cultural and religiously significant locations. However construction activities

may impact to the unidentified significant locations in the subproject affected areas. If any such

important archaeological, cultural and religious sites recovered during project activities, work

should be stopped and immediately inform to the Engineer and Department of Archaeology.

Disruption of traffic

41. Construction activities close to cross drainages, and public sensitive locations may lead

to increase traffic congestion, accidental risk, delays in travel time, increase noise and

disturbance to the public. Advance notice to the road users and roadside communities about

the schedule of construction activities, provision of safe and convenient passage to the

vehicles and passengers during construction of cross drainages, implement traffic

management plans in construction areas according to the traffic rules and regulations, usage

of flagmen and/or temporary traffic signs for construction sites or temporally diversion, are the

measures that have to be undertaken during construction period.

Personal safety of workers and general public

42. Construction related activities both within and outside of the subproject affected areas

could create accidental harm to general public and work force. Organizing awareness

programs about personal safety of the workers and general public, comply with legal

requirements of Sri Lanka for the safety of the workmen, arranging regular safety checks for

vehicles and equipment’s, allocation of responsibility to the trained personnel, arrangement of

proper first aid and transport facilities for injured people, installation of warning signs, speed

limits and signals to particular locations of the road are the major steps that can be taken to

reduce accidental risk.

Impact on socio – economic condition of the area

43. The project will not cause any resettlement issues, damages to the houses, buildings

and other structure, high traffic congestion problems, disturbance or loss of income generating

activities. In overall, the project will cause many socio-economic benefits to the people in the

area such as, provision of connectivity to different economic and cultural importance

institutions, reduction of travel time and cost, and facilitating on-going development initiatives

of the area. However minor negative impacts such as delays and inconvenience while

travelling, increase of dust, noise can be expected during construction phase. However these

can be mitigated by adhering to the EMP of this project.

Effect on existing drainage

44. Land clearing, cut and fill operations, storage of construction materials and other

construction related activities may effect on existing drainage of the project area. Restoration

Page 15: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

ix

of water bodies to its original status after diversion, avoiding storage of construction materials

and disposal of debris around irrigation canals, natural flow paths and cross drainage,

replacing structurally damage structures and maintaining drainage paths and drains clear at all

times are the major steps that can be taken to reduce effect on existing drainage.

Impact from dust, noise and vibration

45. Dust, noise and vibrations generated from the project activities will impact to the

roadside communities and people who inhabit around material extraction sites. Implementation

of National Emission Standards and Noise Control Regulations of CEA for project activities,

regular maintenance of machineries, equipment’s and vehicles in a good condition, placement

of crushers and hot mixed plants away from public and environmental sensitive areas and

spraying of water to minimize dust emission will reduce the above impacts.

Road side landscape and road furniture

46. Clearing of all debris and unwanted construction material from construction sites and

other work places, plantation of road side trees, registration of road embankments, edge

treatment of water bodies, provision of road furniture will enhance the scenic beauty beside the

road corridor and public safety during the operation stage.

4.2. Environmental Impacts Associated with Operation Period

Air quality and noise

47. Reduction of existing dust and vehicular emissions, sound pollution due to widening

and surfacing of the road will positively impact to the air quality and the human health in the

area. The tree plantation programmes will also help to compensate any impacts arising from

air pollution due to vehicular emissions.

Drainage congestion

48. The improvement of side and cross drainages will facilitate better water flow and cause

higher speed flow during the rainy season. However PRDA needs to undertake regular

maintenance of the drainage system to avoid drainage congestions and control improper

disposal of debris during maintenance activities to avoid local floods.

Road safety

49. Improvement of the selected roads will provide easy access, increase number of

vehicles and their speed. Therefore enforcement of the speed limits, traffic rules and

regulations, installation of warning signs, marking of centre lines, pedestrian crossings, bus

halts etc. should be incorporated to minimize road accidents and enhance the safety of the

vehicles and road users.

Page 16: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

x

Encroachment of the Right of Way

50. Encroachment of road reservation can be taken place any time after the completion of

construction works. Encroachment activities can impact to the road users, vehicles, pavements

and road side drains. Therefore routine checking from PRDA to remove unauthorized

structures from RoW is necessary.

5. Institutional Requirements and Grievance Redress Mechanism

5.1. Institutional Arrangements

51. The MLGPC is the Executing Agency for the project and has the responsibility of

implementing the overall EMP. The PIU will be established by PRDA of NCP and is

responsible for overall contract administration and the supervision of the contractor regarding

the implementation of Environmental Specifications and Special Environmental Provisions

included in the Contract Document. The contractors will responsible for implementing the EMP

under the day to day supervision of the Construction Supervision Consultant. The CSCs

(Environment Specialist - ES) will also responsible for reporting the implementation of EMP of

project to PIU on monthly basis. The PIU that will be assisted by an Environmental Consultant

intermittently will review the CSCs’ reports on implementation of EMP. The PIU will report the

implementation of EMP of each sub-project to the PD at the MLGPC. The PIU will follow up by

preparing an annual report on implementing EMP to the relevant parties such as CEA and

ADB. CEA is responsible for overall environmental management in the country and will

periodically review the monitoring reports submitted by the PIU and provide guidance and

advice if and when required.

5.2. Capacity Building

52. The public consultations sessions conducted with PRDA of the project revealed that it

is required to strengthen the institutional capacity of PRDA to implement the proposed project

effectively. The relevant staff of PRDA should be made aware of the existing environmental

conditions of the project affected areas together with the policies and legal regulations

concerning construction, operations and the associated potential environmental impacts and

related mitigation measures by the MLGPC before commencing the construction.

5.3. Grievance Redress Mechanism

53. Grievance Redress Mechanism provides an effective approach to resolve issues made

by the affected community on environmental impacts arising throughout the project cycle. This

mechanism will be established by the project proponent; PRDA to address any grievances

presented by Affected Persons. This mechanism will be executed through a Grievance

Redress Committee. However, grievances could be minimized at the initial stage of the project

by careful design, implementation and monitoring of sub-projects and also through sound

communication & awareness among all the stakeholders including APs regarding the project.

Page 17: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

xi

6. Environmental Management Plan (EMP)

6.1. Environmental Management Plan (EMP)

54. To ensure that the proposed project would not generate any negative impact on the

environment, the EMP has been prepared. This was developed based on best practices for

environmental management. The EMP includes the potential impact as a result of project

activities, proposed mitigation measures, the responsible party to implement and supervise

those impacts and the feasible cost measures to be taken to reduce the potential significant

adverse impacts in an acceptable level.

6.2. Environmental Monitoring Plan (EMoP)

55. In addition to the EMP, to ensure that the project would not generate any negative

impact to the overall environment quality, the Environmental Monitoring Plan has been

prepared. This includes information on environmental parameters to be monitored, location,

time and frequency, cost for sampling and stage of subproject on which the monitoring should

be conducted. The EMoP will be a useful tool to monitor the implementation of mitigation

measures included to the EMP.

7. Public Consultation and Information Disclosure

56. Public consultation for the proposed road sections was carried out during the period

from December 2011 to January 2012. Participants generally expressed their views about the

current environmental, social and economic situation of the proposed subproject areas. In

general, the existing condition of these roads is in unsatisfactory level for the transportation

with large numbers of pot holes, erodible edges, collapsed causeways, culverts and bridges.

Therefore transportation especially during the rainy season is very difficult. However under

these conditions, people of the project influence areas heavily use these roads for their day to

day activities. Apart from that, all these roads link with national and provincial roads and

number of rural, agricultural villages. Therefore, rehabilitation and improvement of the roads is

highly requested by the road side communities.

8. Conclusions and Recommendations

57. The construction activities associated with proposed project not expected to cause

significant environmental impacts to the project affected areas. The potential environmental

impacts that have been identified during the study will be temporary, manageable and will

occur only during pre-construction and construction periods. Therefore the proposed

rehabilitation of the project roads is environmentally acceptable.

58. The proposed project is important to achieve several targets with rural sector

development of Anuradhapura district. This will directly contribute to poverty elevation in

respect to income generation, employment, local/forging investments and enhancement of

other social services in the area. Additionally the proposed project will enhance the other

development activities in Anuradhapura district as well as adjacent villagers of Northern,

Eastern, North Western and Central provinces.

Page 18: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

xii

The appropriate category for the roads based on REA checklists of the ADB is category B.

According to BIQs of CEA in Sri Lanka subproject roads categorised under un-prescribed

category. Thus a full EIA for these roads is not required according to the ADB and CEA

Guidelines.

Page 19: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Chapter 1 - Introduction

1. Introduction

1.1. Project Background and the Justification

1. The proposed Review of Feasibility Study and Detail Design of Northern Road

Connectivity Project (Provincial Component) – NRCP (PC) includes rehabilitation and

upgrading of 75.15 km 5 C class roads (41.55 km) and 2 D class roads (33.6 km) located

within Anuradhapura districts of North Central Province (NCP) of Sri Lanka. The Government

of Sri Lanka has received a loan from the Asian Development Bank (ADB) for the Road Project

Preparatory Facility (RPPF ADB Loan 2080) and intends to apply a portion to undertake

preparatory activities for additional financing of the on-going Northern Road Connectivity

Project (NRCP ADB Loan 2639).

2. The present review study focuses on updating the Environmental Examination of 7 C &

D class roads which were conducted during the feasibility stage of North Central Provincial

road of Anuradhapura district in 2007. The former study was conducted by Cardno

International Pty Ltd in Australia with SMEC International Pty Ltd, Engineering Consultants Ltd

and MG Consultants (Pvt) Ltd, in Sri Lanka behalf of the Provincial Road Development

Authority (PRDA) under Ministry of Local Government and Provincial Councils of Sri Lanka

(MLGPC). This was conducted according to the Terms of Reference (ToR) issued by the ADB

(ADB guidelines, 2003) while confirming the CEA guide lines.

3. The review of the proposed roads is being performed by Egis Bceom International,

France in association with the Consulting Engineers and Architects Associated (Pvt) Ltd, Sri

Lanka on behalf of the North Central Provincial Road Development Authority (NCPRDA) under

the Ministry of Local Government and Provincial Councils (MLGPC) of Sri Lanka.

4. Field work for the former IEE study had been conducted in June 2007 during the civil

war period of the country. During that period, villages of this area were named as bordering

villages and highly affected due to terrorist attacks. Also field data collection of several

proposed roads were unable due to above situation for the consultants. Apart from that, there

was rapid infrastructure development in the area after the war. Therefore the data on Physical,

Ecological, Social and Economic background of the individual roads may have been changed

by now. Thus the main objective of the proposed review is to analyse the gaps of existing

reports, update and improve them with the current environmental condition of the project

affected area in accordance with required policies and Guidelines. The previous consolidated

IEE report had been prepared in accordance with the ADB IEE guidelines 2003. Therefore the

current review focus on rearranging the IEE reports in accordance with the ADB Safeguard

Policy Statement (SPS) 2009 while confirming to the requirements of the “Environmental

Framework” established for NRCP and Environmental Assessment Guidelines of CEA (Sri

Lanka).

5. The selected roads for the improvement are located in 2 Divisional Secretaries

Divisions (DSD) ; Medawachchiya and Kebithigollewa of Anuradhapura district which provide

access for the rural people to agricultural areas, adjacent villages, nearest towns, government

Page 20: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

2

offices, hospitals, market places and schools. The dilapidated condition, poor alignments,

narrow road sections structurally damaged culverts, bridges and causeways of the subproject

roads contributes high vehicular operation cost, long travel time and high transport cost.

Therefore the main objectives of the project are to reduce cost for transportation, reduce travel

time, improve reliability of access and improve connectivity of the provincial road network to

rural road network and national highway network.

6. Thus improvement of the provincial road network is mainly seen as a tool for poverty

alleviation, allowing rural people to directly access the semi urban and urban areas to engage

in a number of social and economic activities. Hence the proposed project is intended to

enhance the opportunities for education, economic growth, income generation and new job

opportunities for the people in the rural agricultural area of the district.

7. Under the proposed project following roads are proposed for the Environmental

Assessment.

Table 1 Details of the proposed provincial roads

No Road Number Road Name Length

D Class roads

1 NCAHD083 Kiriketuwewa - Bandaraulpatha – Kapugollewa 20.30

2 NCAND139 Yakawewa – Mahakoongaskada 13.30

Length 33.60

C Class roads

3 NCAHC095 Kebithigollewa – Hendagala 12.90

4 NCANC122 Ethakada - Etambagaskada – Tonigala 6.80

5 NCANC126 Dachchidamana – Paranahalmillewa 4.70

6 NCANC127 Thekkawatha – Pulleliya 5.65

7 NCANC128 Kirigollewa – Hirallugama 11.50

Length 41.55

Total Length 75.15

1.2. Extent and Scope of the Study

8. The Environmental Assessment was carried out as a requirement of the Feasibility

Study for a total of 75.15km 5 C and 2 D class roads located within 2 DSD of Anuradhapura

districts in North Central Province. The project comprises a total area of 75.15ha over the

project stretch of 75.15 km in an average strip of 10.0 m width.

9. The scope of the study was determined by the stipulations given in the ADB, IEE

outline This include:

Field data collection regarding physical, social, economic and environment

background

Public consultation with affected people and other relevant authorities

Page 21: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

3

Preparation of Basic Information Questioners (BIQs) and submission to the CEA

(Central Environmental Authority) for environment clearance

Preparation of REA (Rapid Environment Assessment) checklists for ADB

categorization

Assessment of potential environmental impacts and development of preventive

and/or mitigation measures for significant impacts,

Preparation of Environmental Management Plan (EMP) and Environmental

Monitoring Plans (EMoP),

Preparation of institutional requirements and grievance redress mechanism

Preparation of review consolidated Initial Environmental Examination (IEE) report.

The improvement works are generally envisaged to involve:

Widening to substandard 2 lane status

Minor realignment to alleviate small radius curves.

Upgrading the existing condition of the road with proper surfacing associated with

Double Bitumen Surface Treatment (DBST), Asphalt Concrete (AC) or Concrete

Pavements (CP).

Provisions to road side drainage, improvement of culverts, bridges and other

hydrological structures where necessary.

Installation of traffic warning signs, provision of pedestrian crossings, bus bays and

parking where necessary.

1.3. Objective of the IEE Report

10. The main objective of this IEE report is preparation of comprehensive account on

current environment condition of the project area. Accordingly a single consolidated IEE report

will be submitted for the proposed seven subprojects and submit ADB to facilitate their

decision making.

11. In detail, the consolidated IEE report will address the current Physical, Ecological,

Economic and Social background of the subprojects, anticipated environmental impacts that

will arise due to the project activities, necessary measures that have to be adopted to mitigate

them and public views and suggestions regarding the project etc. Furthermore this IEE report

includes suitable Environmental Management Plan (EMP) and Environmental Monitoring Plan

(EMoP) with recommend institutional arrangements for monitoring the identified environmental

impacts throughout the project cycle.

1.4. Structure of IEE Report

12. In order to fully meet all requirements, the IEE report generally follows the ADB SPS

2009 and EA Guidelines 2003. The structure of the IEE report is organized as follows:

Introduction: Provides an identification of the project and the project proponent,

NCPRDA and an explanation of the purpose of the IEE. It also presents the

Page 22: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

4

organization of the IEE, applicable environmental regulations and an explanation of

the extent of the IEE study.

Description of the Project: In accordance with the ADB SPS 2009 and EA

Guidelines 2003, this section provides the detailed description of the project, need

of the project, project location, and magnitude of operation, environmental category

of the project and implementation schedule.

Description of the Environment: Provides a description of the potentially affected

environment. The description is based on reviews of available documentation,

statistical data, and meetings with government authorities, AP, field surveys and

investigations.

Screening of the Potential Environmental Impacts and Mitigation Measures:

Provides an assessment of potential impacts of the proposed road development in

light of the existing conditions, together with recommended actions to prevent

and/or otherwise mitigate unavoidable impacts expected to be incorporated as

integral parts of the Project.

Institutional Requirements and Grievance Redress Mechanism: Provides a

description on responsible parties to implement, administration and supervision of

the project, address concerns, complaints and grievances of affected population

regarding environmental performance of the project

Environmental Management Plan: Provides a plan for implementing the

recommended mitigation measures for addressing environmental issues and

specifies the responsible agencies, location and timing for implementing the

mitigation measures

Public Consultation and Information Disclosure: Information on public

participatory workshops and consultations with experts and local administration is

presented in this section.

Conclusions and Recommendations: Ultimate conclusions and

recommendations which are finalized by the consultant are stated here with the

analysis of currently available data.

1.5. Applicable Environmental Legislations

13. A large number of recurrent and non-recurrent activities under road and rail

development are presently not covered by the National Environmental Act (NEA)1. However

rehabilitation of existing provincial roads do not fall within the category of “Prescribed Projects”

listed in Gazette Extra-ordinary No. 772/22 of 24th June 1993 and subsequent amendments,

which needs to go through the Environmental Impact Assessment (EIA) process and

subsequent conditional approval from the CEA of the Ministry of Environment and Natural

Resource (MENR). These may, however be subjected to an environmental review, if the

1Central Environmental Authority, 2003.National Environmental Act, Subsidiary Legislation.

Page 23: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

5

Project Approving Agency (PAA); CEA deem it necessary. National laws and regulations that

can be relevant to the project are briefly described in the Table below.

Table 2 Applicable national laws and regulations relevant to the project

Laws and Regulations Provisions and main content

National Environmental Act

No.47 of 1980, Amendment

No.56 of 1988, and other

Amendments

The NEA is a framework environmental statue that makes provision for the

protection, management and enhancement of the environment, for the regulation,

maintenance and control of the quality of the environment, and for the prevention

and control of pollution by implementing the proposed project.

National Environmental

(Noise Control) Regulations

No. 01 of 1996

Regulates maximum allowable noise levels for construction activities during

proposed project activities

National Environmental

(Protection & Quality)

Regulations, No. 01 of 1990

Provides standards for discharging effluents into inland surface water during

proposed project activities.

Fauna and Flora Protection

Act (1993)

An act to amend the fauna and flora protection ordinance (Chapter 469) of 1938,

which provide for the protection and conservation of the fauna and flora of Sri Lanka

and their habitats; for the prevention of commercial and other misuse of such fauna

and flora and their habitats, for the conservation of the biodiversity of Sri Lanka; and

to provide for matters connected there with or incidental thereto.

Felling of Trees Control Act

No. 09 of 1951 as Amended

through Act No. 30 of 1953

This Act sought to prohibit and control the felling of specified trees (mainly intended

to stop indiscriminate felling of specified trees) in the country.

Water Resources Board Act

No. 29 of 1964, Amendment

No.42 of 1999

Control, regulation and development (including the conservation and utilization) of

the water resources; the prevention of the pollution of rivers, streams and other

water resources; the formulation of national policies relating to the control and use of

the water resources.

The Soil Conservation Act,

No. 25 of 1951 Amended in

24 of 1996

An act to make provisions for the enhancement and substances of productive

capacity of the soil, to restore degraded land for the prevention and mitigation of soil

erosion, for the conservation of soil resources and protection of land against

damage by floods, salinity, alkalinity and drought and to provide for matters

connected therewith or incidental thereto

Explosive Act No. 36 of 1976 To provide the control of explosions and regulations of matters connected with

explosive activities.

Fisheries and Aquatic

Resources Act 1996

The Act addresses the management, regulation, conservation and development of

fisheries and aquatic resources during proposed project activities.

Flood Protection Ordinance

No. 04 of 1924

An ordinance for the protection of areas subjected to damage from floods. This

includes declaration of flood areas, preparation of schemes for flood protection and

other rules and regulations regarding flood in the country.

Geological Survey and

Mines Bureau (GSMB) Act

No. 33 of 1992

Regulates the exploration for minerals, mining, transportation, processing, trading in

export of mineral products and usage of quarries and sand mines in the country.

Motor Traffic Act, No 14,

1995, Amended by Act No.

Provision of laws relating to Motor Vehicles and their use on highways including

provisions relating to insurance against third party risk

Page 24: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

6

Laws and Regulations Provisions and main content

05 of 1998

Crown Land Ordinance Act

No. 1947

The act dealing with allocation and control of Crown lands In Sri Lanka for private

and government activities.

Irrigation Act No. 23 of 1983 An act to formulate policies and programmes in regard to the subjects of irrigation,

reservoirs, water resources management and prevention of pollution of rivers,

streams and other water recourses. Promotion, construction, operation and

maintenance of irrigation schemes, drainage and flood control in the country.

Regulations of Local

Authorities

Regulates and control actions and methods taken place within the command area

relevant to the government laws and regulations.

Source: Compiled by the Consultant

14. The following table indicates the key clearance and permits that should be obtained for

the proposed project:

Table 3 Key clearance and permits required for the proposed project activities

Project stage Clearance and permits Activity Relevance

Agency

Pre-construction

stage(Although the

clearances and

approval should be

obtained during

the pre-

construction stage

it should valid

throughout the

project cycle.

However this

should be renewed

before expiry date)

Environment Clearance Implementation of the project CEA

Industrial Mining License

(IML)

Operation of quarries, borrow areas

(material extraction sites) GS&MB

Environmental Protection

License (EPL)

Operation of quarries, crushers,

borrow areas (material extraction

sites)

CEA

Explosive Permits Blasting activities MoD

Local Government

Authorities Trade License

Operation of metal quarries,

crushers, borrow areas, dispersal

sites, labour camps

LAs

Approval for removal of

trees Widening of the CW

DS, DoF,

DWLC, CEA

Construction stage Consent from relevant

government agencies

Construction of bridges, culverts

and other drainage systems

DoI, DoAS,

PDoI

1.6. Methodology

15. The review study was carried out with the data on previously conducted IEE report,

data collected during the field surveys, data on engineering designs, data from secondary

sources and from other team of consultants attached to the review study.

16. The Environmental Assessment of the project has been performed in accordance with

the following policies and guidelines:

Page 25: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

7

Environmental Safeguards Compliance Manual (ESCM) of RDA,

ADB SPS 2009 and EA Guidelines 2003,

Policy and Legal Framework of the Government of Sri Lanka (GoSL) and

Environmental Guidelines for Road and Rail Development in Sri Lanka of CEA

(1997).

17. Field observation for the proposed study was carried out during the period from 10

December 2011 to January 2012. A line transect survey was carried out along all the proposed

roads which is 25 m either side from the centreline and direct observations were made to

identify road side trees, important flora, fauna, environmental sensitive areas, wild life parks,

sanctuaries, and protected forests. However this specified area of investigation was expanded

beyond 25m, when the impacts considered as special and significant. The detailed floral and

faunal survey was not carried out during the previous study therefore it has been included to

the current report. .

18. Further information was collected from villages and respective authorities to

understand the general social and environmental background of the project affected areas

including existing social and environmental problems. Public consultation meetings were

carried out for each and every road with the affected parties to get their current perception on

the project and those views and suggestions are incorporated to review reports. This

information is also used to address the Grievance Redress Mechanism (GRM).

19. The secondary information for the report was gathered from printed materials and other

sources of Government Departments, Authorities, Ministries, Non-Government Agencies

(NGOs) and relevant websites etc.

20. Common EMP (Annex B) and EMoP (Annex C) were prepared for the project and were

included to the reviewed consolidated IEE report and also for the Bid documents.

Page 26: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

8

Chapter 2 - Description of the Project

2. Description of the Project

2.1. Type of the Project

21. A total of 5 C class roads and 2 D class roads including 75.15 km have been identified

within 2 DSD of Anuradhapura districts in NCP for the proposed review study. The existing

provincial roads will be widened and improved to substandard two lane status with 4.50 m

carriageway, shoulders on both sides and earth or line drains where required. The project

activities will involve repair, rehabilitation and/or upgrading of these provincial roads.

2.2. Category of the Project

22. According to Basic Information Questionnaires (BIQ) and Environmental Guidelines for

Road and Rail Development in Sri Lanka of CEA (1997) proposed project roads fall in to un-

prescribed category.

23. Based on the REA Checklist of the ADB classification, NCP roads are categorized

under environment category B. Therefore potential environment impacts associated with the

proposed project are less adverse than category A. Thus the IEE serves as the complete

Environment Assessment for the proposed project.

24. The conditional approval for rehabilitation and upgrading of the proposed sub roads

were granted openly by CEA in October, 2008 without mentioning exact time period. Therefore

BIQs for the proposed 7 subproject roads have been prepared and submitted to the Client to

obtain the environmental clearance if the approval gets expired.

2.3. Need for the Project

25. The proposed C and D class roads belong to the Provincial Road Development

Authority (PRDA) of North Central Provincial council of the country. Since large numbers of C

and D class roads located within the province, it is extremely difficult to rehabilitate or improve

all these roads with the financial assistance of the provincial council. Also the proposed project

area was located within or closed to the war zone, It was unable to do maintenance and

improvement activities as per the requirement. Therefore only location specific maintenance

activities and limited surface maintenance activities are carried out by the PRDA. However

after the war in December 2009, some sections of the project roads properly improved with

DBST or gravel prime layer. Also all the dilapidated subproject roads overlaid with gravels by

the PRDA during last two years.

26. Insufficient maintenance or improvements of the roads, damages occurred during the

war period in the past has resulted in highly dilapidated conditions which lead to disturbance of

access and maintaining the social services in the rural areas of the district. Apart from that

poor alignments, narrow road sections, structurally damaged culverts, causeways and bridges

contributes to high vehicle operation costs, long travel time and high transport costs. In NCP

more than 90 % of people living in rural areas and majority of them engage in agriculture

mainly paddy, chena cultivations, vegetables, fruits and home gardens species. Therefore

Page 27: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

9

improvement of the provincial road network in these areas is essential for the rural people to

directly access to the semi urban and urban area to engage in number of social and economic

activities easily through proper road communication. Apart from that rehabilitation of these

roads is essential to increased road safety, transport efficiency and access to the other

infrastructure facilities. In addition improvement of the road network in the area will positively

impact the living standards of the people with economic, social and cultural values.

2.4. Location

27. The 7 subproject roads identified for the improvement and rehabilitation are located in

Anuradhapura districts of the NCP of Sri Lanka. The list of roads with starting and end points

are indicated in Table 4. The general locations of the Anuradhapura district and the location

map with all subproject roads of the districts are shown in Figure 1 and 2 respectively. The

location maps at 1:50,000 scales are provided for each road section separately as Annexure

A.

Table 4 List of the C & D class roads located within Anuradhapura district

Road no Road name Starting point End point Length

(km)

NCAHC095 Kebithigollewa - Hendagala Kebithigollewa opposite

to the DS office

Hendagala

junction 12,90

NCAHC122 Ethakada - Etambagaskada -

Tonigala Puhudivula Tonigala 6.80

NCAHC126 Dachchidamana -

Paranahalmillewa Mahakumbukgollewa Paranahalmillewa 4.70

NCAHC127 Thekkawatha - Pulleliya Walpola junction Pulleliya 5.65

NCAHC128 Kirigollewa - Hirallugama Unagaswewa junction Hirallugama

junction 11.50

NCAHD083

Kiriketuwewa -

Bandaraulpatha -

Kapugollewa

Kiriketuwewa junction Kapugollewa

Junction 20.30

NCAHD139 Yakawewa -

Mahakoongaskada Rd Yakawewa junction

Nagadaranawa

junction 13.30

Total length 75.15

Page 28: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

10

Figure 1 General Project Location Map of Anuradhapura District

Page 29: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

11

Figure 2 Subproject Roads with Land use Pattern in Anuradhapura District

Page 30: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

12

Feasibility Study and Detailed Design of 400 kms Roads Kilinochchi and Mullaitivu Districts Contract Variation Additional Finance NRCP and NHSP Roads

Detailed Design and Final Report - Volume 5 April 2012 - Page 12

2.5. Analysis of Alternatives

28. All the roads identified for the proposed rehabilitation are very essential link roads to

the interior parts of Anuradhapura district. In general rehabilitation and improvement of the

proposed roads are necessary due to existing severely dilapidated condition of the roads and

the economic development in future. Even without proposed rehabilitation and improvement,

the roads will continue to be a main transportation link with rural, agricultural and urban areas

without significant social and environment impacts. Further the existing subproject roads are

not located through or close proximity to any national parks, sanctuaries or any other protected

areas demarcated by the relevant authorities. Also these subproject roads runs through the

residential and agricultural areas representing numbers of rural villages. Apart from that the

project will not require any land acquisition from the road side community. Thus, the proposed

improvements can be considered as the better option in the area.

2.6. Size and the Magnitude of Operation

29. Road improvement works for provincial roads under NRCP-PC will involve repair,

rehabilitation and/or upgrading of existing provincial roads.

30. The proposed road formation width standards and Rights of Way (RoW) are discussed

in detail in the section of Engineering Assessment of Feasibility Study of the Main Report. It is

proposed that on most of the roads horizontal alignments will follow the existing road

centrelines. Where the irrigation canals exist along the roads in either LHS/ RHS the centreline

should be shifted accordingly. In general road carriageway widths vary between 2.7 and 5.00

m with the majority of the proposed pavement width being 6.50m. Shoulder widths vary

between 0.50 m to 1.0 with the majority being 1.00 m. Road formation width is generally 4.50

m and road RoW between 8.5 m and 11.50 m.

31. For the roads, or sections of roads where lined or dished drains are proposed it is also

proposed to form and seal the pavement right up to the drain lining thereby providing both

additional road width and pedestrian way, while at the same time reduce shoulder erosion

problems and consequent high maintenance costs.

32. The general scope of work for the Provincial roads comprises:

Initial repairs to the existing road surface to prepare it for resurfacing or overlay:

these repairs may include bituminous patching, crack sealing, carriageway edges

and shoulder repairs where traffic damage or erosion has occurred, cleaning of

side drains and road culverts.

In all cases the recommended improvements entail overlaying the existing

pavement with a base or levelling course, designed for the projected number of

Equivalent Standard Axles (ESA’s) over the design life of the road, and resurfacing.

Where a pavement is found to be severely deteriorated, broken or uneven, the

existing surface would first be scarified and reshaped before applying the pavement

surface. Work will also include cleaning of road side drains; and culverts; cleaning

of outlet drains; repairs to road furniture.

In some cases provincial roads will have pavement widening varying between 1.00

m and 3.00 m and/or shoulder widening varying between 0.50 m and 1.50 m.

Page 31: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

13

These widening activities will in most cases involve earthworks, pavement

construction, overlaying of the existing pavement and bitumen surfacing. Work will

also include cleaning of road side drains; and culverts; cleaning of outlet drains;

repairs to road furniture (Culvert Schedule: Refer Detail design Report, Volume 2,

Section 3, Appendix 1-7).

Improvements will be carried out to roadside drains, culverts and bridges. Where

existing structures are sound then culverts will be lengthened and bridges widened

to suit the new road width. Where the condition of culverts and/or bridges is poor,

the structure will be replaced.

Minor realignment may be made to alleviate small radius curves. Widening will be

carried out on the insides of curves for most roads. Known black spots will be

alleviated and in some cases minor adjustments may be made to the vertical

alignment if visibility is considered a problem. This will include approaches to

bridges and railway crossings on embankments.

The improvement works will include where technically appropriate the correction of

irregularities in the road cross-section and severe undulations in the longitudinal

profile.

Bridge repairs, re-decking, widening and in some cases replacement of the

structure of a bridge are the main rehabilitation activities with respect to structures.

More than two-thirds of the structural work entails repair to existing bridge

structures. This work includes structural renovation of substructure and

superstructure elements together with installation/repair of guardrails and

improvement of causeways and vented drifts.

2.7. Cost for the Project

33. The total cost estimated for the major items associated with the proposed subprojects

works (including earth work, pavement, drainage structures and ancillary work) were

established by the application of appropriate unit rates to the estimated work item quantities

derived from the results of surveys, test results and design analysis for subprojects. The

finalized estimates of each subprojects will be included in Volume 4 – Cost estimates of: Detail

Design and Final Report of the project.

2.8. Proposed Schedule for Implementation

34. Review Feasibility Study and Detailed Design of the proposed project will be completed

in July 2012. Once detailed designs and bid documents are completed, tenders will be

awarded to the successful contractors. ADB is the funding agency for Feasibility Study,

Detailed Engineering Design and for the civil works. Improvement works are scheduled to be

completed within two years.

Page 32: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

14

Road side vegetation and surface condition

Chapter 3 - Project Affected Area

3. Description of the Existing Environment

35. A total of 7 subproject roads (05 class C roads and 2 Class D road) including 75.15 km

has been identified within the Anuradhapura district of the North Central Province.

Anuradhapura district is divided in to 22 Divisional Secretary (DS) divisions and

19PradeshiyaSabha (PS) divisions. Selected roads for the rehabilitation and improvement are

restricted to the 2 DSs and 2 Pradeshiya Sabha divisions (PSDs) namely Medawachchiya and

Kebithigollewa (Table 5).

Table 5 List of the roads located within different DS & PS divisions of the district.

Road no Road name Length (km) DS division PS division

NCAHC095 Kebithigollewa - Hendagala 12,90 Kebithigollewa Kebithigollewa

NCAHC122 Ethakada - Etambagaskada – Tonigala 6.80 Medawachchiya Medawachchiya

NCAHC126 Dachchidamana - Paranahalmillewa 4.70 Medawachchiya Medawachchiya

NCAHC127 Tekkawatha – Puleliya 5.65 Medawachchiya Medawachchiya

NCAHC128 Kirigollewa - Hirallugama 11.50 Medawachchiya Medawachchiya

NCAHD083 Kiriketuwewa – Bandaraulpatha - Kapugollewa 20.30 Kebithigollewa Kebithigollewa

NCAHD139 Yakawewa - Mahakoongaskada Rd 13.00 Medawachchiya Medawachchiya

3.1. Existing Condition of the Subproject Roads and Proposed Work

NCAHC095: Kebithigollewa - Hendagala Road (12.90 km)

36. A total of 12.90 km length road starts from B 283 Medawachchiya – Kebithigollewa

road and is opposite to the DS office of Kebithigollewa within the Kebithigollewa town

boundary. The road from starting point up to 9.00 km mainly runs through residential areas of

Hendagama, Thibbiri-wewa, Kirimetiyawa and Ambagaha-wewa including paddy fields, home

gardens and mixed cultivations. Rest of the section beside the road includes scattered

residences with large extent of paddy fields, scrublands, small forest patches with small rocky

outcrops and chena cultivations of Ambagas-handiya, Kokatigollewa and Handagala. The

Ovilbendi-wewa tank and two tanks of Ambagaha-wewa are located 5.1, 7.9 and 8.8 kms RHS

of the road. Large extent of paddy fields is mainly concentrated to 4.00, 5.3 to 5.9, 12.3 and

12.7 kms beside the road. This road terminates at Hendagala junction of

Kebithigollewa,Ratmalgahawewa-Kivulekade road (B 538).

37. The terrain of the road is flat and the

alignment mainly straight with few curves. The

current situation of the road in several sections up to

9.00 km is fairly good during the dry season. During

the rainy season it is difficult to travel due to water

stagnation in pot holes. The road gets inundated at

Page 33: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

15

4.79-5.16, 5.50-6.10 km locations. The end section of the road is highly dilapidated with large

numbers of potholes with water stagnated locations. Electricity is available beside the road and

all most all the houses and government buildings attain electricity from this existing

transmission line. Three government schools of Timbiri-wewa (3.7 km), Hadagala (6.5 km: L)

and Ambagaha-wewa (9.4 km: L) are located beside the road. Additionally Montessori school

of Timbiri-wewa (3.1 km) and Kokatigollewa (12.7 km), cooperative shop of Kirimetiyawa ( 6.2

km) and Buddhist temple: Upulviharaya at Ambagaswewa (9.3 km: L) are also located beside

the road.

38. The existing carriageway of the road varies from 3.5 m to 4.5 m width. Existing RoW of

the road varies from 9.0 to 12 m. The average annual daily traffic volume of the road is 396

vehicles per day. The project aims to rehabilitate and widen the existing single lane to sub-

standard two lane with shoulders of 1.0 m on either side, earth or line drains (1.0 m) where

required. The developed road will have a RoW varies from 8.5 m to 11.5 m and proposed

average carriageway is 4.5 m.

NCANC122: Ethakada - Etambagaskada - Tonigala Road (6.8km)

39. A total of 6.8 km section from Ethakada – Etambagaskada - Tonigala road starts

opposite to the Metal quarry of Puhudivula. The initial section of the road runs through paddy

fields, scrub lands, chena cultivations and home gardens with residences of Puhudivula,

Divulgaskada, and Atambagaskada up to Tonigala junction. In general, the existing condition

of the road is in unsatisfactory level for transportation. The 4 way junction of Atambagaskada

is located around 2.8 km and residences are mainly concentrated to the Atambagaskada. Two

seasonal tanks of Divulgaskada and Atambakaskada are located beside the road at 1.9 and

3.1 kms respectively. The rest of the section after 3.2 km up to Tonigala is covered with scrub

lands, forested area, water stagnated areas, few residences and chena cultivations. The

proposed road section terminates at Tonigala from AA029: Vavuniya – Horowopotanaroad.

40. The terrain is flat thought the road and the alignment

mainly straight with few curves. The 1st6.00 km from

Ethakada junction up to Puhudivula was already

rehabilitated by the PRDA. The rest of the section from

Puhudivula up to Tonigala junction is a gravel section (old

tar road section) and is highly dilapidated with large

numbers of pot holes, erodible edges with water stagnated

areas, unusable culverts and other cross drainages. During

the rainy season transportation through this section is very

difficult due to stagnated water within the RoW. The road gets inundated at 6.00 – 6.24, 9.40 -

12.00 km locations. The significant places located along the road include temple (2.45 km: L),

government school (2.5 km: L) and sub post office

(2.6 km: L) of Atambagaskada with residential

area.

41. The existing RoW of the road varies from 9

- 12 m and the carriageway is 2.7 – 4.2 m. The

average annual daily traffic volume of the road is

443 vehicles per day. The project aims to

Rural residential area of Atambagaskada

Chena cultivation located close to the road

Page 34: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

16

rehabilitate and widen the existing single lane to sub-standard two lane with shoulders of 1.0 m

on either sides, earth or line drains (1.0 m widths) where required. The developed road will

have a new RoW of 9.0 to 11.5 m throughout.

NCANC126: Dachchidamana – Paranahalmillewa Road (4.70 km)

42. The proposed road section starts at Maha-kumbukgollewa junction from A009: Kandy –

Jaffna road close to the 102.00 km post. This road runs through rural agricultural area of

Maha-kumbukgollewa, Kudagama, Ataweeragollewa up to Paranahalmillewa. The land use

beside the road includes scrub lands, paddy fields, chena cultivations, home gardens and

residence. Most of the residences are concentrated from 0.00 km up to 1.00 km. A tank of

Kudagama is located 2.8 km LHS to the proposed road. The proposed 4.7 km road terminates

at Paranahalmillewa junction opposite to the Paranahalmillewa government school.

43. The terrain of the road is flat and

alignment is mainly straight. The existing surface

of the road is fairly good with the motarable

condition in dry season. However during the

rainy season, water stagnated pot holes can be

seen in several locations. The road gets

inundated at 1.30 – 1.45, 1.70-1.90, 2.50 – 3.70

km locations. The electricity is available along

the road and most of the residences beside the

road obtained electricity. No significant

government buildings or other important places

located beside the road.

44. The existing carriageway of the road varies from 3.2 – 4.5 m width. Existing RoW of the

road varies between 9 - 12 m. The average annual daily traffic volume of the road is 438

vehicles per day. The project aims to rehabilitate and widen the existing single lane road from

Maha-kumbukgollewa junction up to Paranahalmillewa junction to sub-standard double lane

with shoulders of 1.0 m width on either side, earth or line drain (1.0 m) where required. The

developed road will have a new RoW ranging from 8.5m to 11.5m and average carriageway of

4.5 m throughout.

45.

NCANC127: Thekkawatha – Pulleliya Road (5.65 km)

46. The proposed road section from Thekkawatha – Pulleliya road starts 2.00 km away

from Thekkawatha junction of Medawachchya – Mannar road (AA014) at Walpola junction.

The 1st 2.00 km has already improved with DBST by the PRDA of NCP. The rest of the

proposed section runs through several rural agricultural villages including Walpola, Kulikkada,

Viralmurippu, Kudagama up to Pulleliya junction. Land use beside the road includes paddy

fields, scrublands, chena, teak cultivations, mixed home gardens and residences. The road

crosses Colombo - Jaffna railway line around 1.1 km point. Several seasonal tanks

Dilapilated condition and road side vegetation

Page 35: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

17

Viralmurippu (1.5 km: L), Kudagama (3.45 km: R) and Puleliya (4.4 km: R) are located beside

the road. The proposed 5.65 km section terminates at Pulleliya junction.

47. The terrain of the existing gravel section is

flat thought and the alignment mainly straight with

few curves. The present situation of the road is

highly dilapidated with large numbers of pot holes,

broken edges, water stagnated areas, inundation

sections (2.10 – 2.20, 3.54 – 3.93, 5.30 -5.45, 6.45

– 6.55, 6.85 -7.08, 7. 32 -7.55), damaged culverts

and bridges. Thus transportation along some

section is very difficult especially the end section

after the Pulley tank. The electricity is available in

the area; both high-tension as well as house

supply lines run parallel to the road. A single

Government school Viralmurrippu (1.4 km: L) two

temples Viralmurippu (2.1 km: L) and Puleliya (5.3

km: R) are located beside the road.

48. The existing carriageway of the road

varies between 3.5-4.5 m. Existing RoW of the

road varies between 9-11m. The average annual

daily traffic volume of the road is 389 vehicles per

day. The project aims to rehabilitate and widen

the existing single lane to sub-standard double lane with shoulders of 1.0 m on either sides,

earth or line drains (1.0 m) where required. The developed road will have a new RoW of 8.5 m

to 11.5 m and carriageway of 4.5 m throughout.

NCAHC128: Kirigollewa - Hirallugama Road (11.50 km)

49. A total of 11.50 km gravel road starts from

Unagaswewa junction of Medawachchiya –

Horowpathana road. The road runs through rural

residential and agricultural areas of Unagas-

wewa, Moragoda, Tharanagollewa and

Hirallugama. The land use beside the road

includes large number of paddy fields, scrub

lands, chena cultivation, mixed home gardens

(coconut, banana) and residences. Four main

seasonal tanks Unagas-wewa (2.5 to 4.2 kms),

Moragoda (5.4 to 5.6 kms), Tharanagollewa

(6.75 to 7.4 kms), Hirrallugama (9.3 to 10.2 kms),

are located beside the road and road runs over

these tank bunds. The spills of above tanks cross

the road at 4.2, 5.6, 7.4 and 10.2 kms

respectively. The proposed road terminates at

Teak plantation at LHS close to the railway crossing

Viralmurippuwa Government School adjacent to the road

Large extent of paddy fields and mixed home gardens besid the road

Road runs over the tank bund

Page 36: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

18

B283: Medawachchiya - Kebithigollewa road at Hirallugama junction.

50. The terrain of the existing gravel road is flat and the alignment includes number of

curves. The existing carriage way of tank bunds is narrow compare to the rest of the section.

Number of rural road sections start from the proposed road at different locations and runs

towards the other rural villages and agricultural areas. The current situation of the road is

suitable for transportation and day to day activities of the people in the area. However several

locations of the road include pot holes with water stagnated areas. Electricity is available from

starting point up to end point and majority of the residences and government buildings

obtained electricity supply from the existing line. Two government schools Unagaswewa (4.2

km: L) and Hirallugama (8.2 km: R) as well as single Buddhist temple of Sri

Sugathawardanaramaya at Moragoda (5.3 km: R) are located beside the road.

51. The existing carriageway of the road varies from 3.5 m to 4.0 m and the existing RoW

of the road varies from 10.0 m to 11.0m. The average annual daily traffic volume of the road is

378 vehicles per day. The project aims to rehabilitate and widen the existing single lane to

sub-standard two lane with shoulders of 1.0 m on either side, earth or line drains (1.0 m)

where required. The developed road will have a new RoWvaries from 8.5 m to 11.5m and

carriageway of 4.5 m throughout.

NCAHD083: Kiriketuwewa – Bandara-ulpatha - Kapugollewa Road (20.30 km)

52. The sub-project road starts from

Kiriketuwewa junction from Vavuniya –

Horowpothana Road (AA029) about 6.00 km away

from Kebithigollewa town towards the

Horowpothana. The starting point up to 5.00 km

includes gravel prime layer. The rest of the section

from Bandaraulpothato Kapugollewa junction is

overlaid with gravel. Large numbers of rural

agricultural villages are located along the road

including Kiriketuwewa, Lunuathulewa, Sinhala-

Ataweeragollewa, Bandaraulpota, Kurulugama, Muslim- Ataweeragollewa, Anaolandewa,

Pathtewa, Weerasole and Kapugollewa.

53. The land use beside the road includes large extents of paddy fields, scrublands,

forested areas, mixed cultivations, home gardens and residences. The majority of the people

in the area is farmers and largely depends on paddy cultivation. Additionally animal husbandry

including cattle, goat and poultry is also common in Anaolandewa, Muslim-Ataweeragollewa

and Weerasole. Number of tanks including Sinhala -Ataweeragollews (3.8, 4.4 kms: L),

Pathtewa (13.2, 14.5 kms: L), Punchikulam (15.9 km: L) and Weerasole (16.8 km: L) are

located close to the road. The end section beside the road includes forest patches, scrub lands

and rocky areas. The proposed road ends at Kapugollewa junction around 20.3 km from

Kapugollewa- Horowpothana Road.

54. The terrain of the initial section about 12 km is flat and the alignment mainly straight

with few curves. The rest of the section includes number of bends with slightly undulating

Water stagnated location within the road

Page 37: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

19

terrain. The current situation of the gravel prime laid section is fairly good with scattered

potholes. The surface of section after 15.00 km is an unsatisfactory level due to large numbers

of pot holes, dilapidated road edges, erodible sections and stagnated pot holes during the

rainy season. Electricity is available along the road. The significant places located beside the

road include Buddhist temple of Lunuatulewa (2.1 km: L), Bodhi tree (4.00 km: L), government

school of BandaraUlpotha (7.2 km), Montessori school (14.00 km: L), government Muslin

school Pathtewa (14.1 km: R), mosque of Weerasole (16.7 km: L) and Jayasumanaramaya

temple Kapugollewaat end section.

55. The existing carriageway of the road varies from 3.5 m to 4.0m width. Existing RoW of

the road varies from 9-12 m. The average annual daily traffic volume of the road is 237vehicles

per day. The project aims to rehabilitate and widen the existing single lane road from

Kiriketuwewa up to Kapugollewa to sub-standard double lane with solders of 1.0 m on either

side, earth or line drains (1.0 m) where required. The developed road will have a new RoW of

8.5 to 11.5 m and average carriageway of 4.5 m throughout.

NCAND139: Yakawewa - Mahakongaskada Road (13.30 km)

56. A total of 13.30 km road starts at Yakawewa

junction from Medawachchiya – Mannar road

(AA014). This road mainly runs through rural

agricultural areas of Yakawewa, Periyakulam,

Galkandegama, Katukeliyawa, Mahakongaskada,

Muslim Halmillewa, and Aneketiya up to

Nagadaranawa. The land use beside the subproject

road includes home gardens and residences, paddy

fields, teak cultivations, small forested areas, scrub

lands, mixed cultivations and chena cultivations.

Number of seasonal tanks including Periyakulam (2.5

km: L), Galkandegama (3.7 km: L), Katukeliyawa (5.1

km) are located close to the road and road runs through Katukeliyawa tank bund from 5.1 km

up to 5.4 km. The road terminates at Nagadaranawa junction from Punewa – Palugollewa

road.

57. The terrain of the road is flat and most of the

alignment is straight with few curves. The road is fairly

good with motarable condition. The proposed road

gets inundated at 6.52 – 6.75, 8.15 – 8.90, 9.55 –

10.20, 14.05 – 14.32, 15.70 – 16.10, 16.33 – 16.72,

17.40 – 8.00, 19.00 – 19.70 km points. The electricity

is available throughout the road and majority of the

houses obtained electricity. The significant places

located along the road include Gaminiwewa

government school and temple of Periyakulam (2.4

km: L&R), government school of Muslim Halmillewa

(10.3 km: L) and Sri Aanandarama temple of

Aneketiya (12 km, L).

Scrublands located beside the road

A tank with water birds located close to the road

Page 38: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

20

58. The existing carriageway of the road varies from 3.5 m to 5.0 m width and the existing

RoWvaries from 10 m to 12.0 m. The average annual daily traffic volume of the road is 768

vehicles per day. The project aims to rehabilitate and widen the existing single lane road from

Yakawewa to Mahakoongaskada to sub-standard double lane with solders of 1.0 m width on

either side, earth or line drain (1.0 m width) where required. The developed road will have a

new average RoW of 8.5 m to 11.5 m and carriageway of 4.5m throughout.

3.2. Description of the Existing Environment of the Project Affected Area

59. This section provides current situation of physical, ecological, economic and social

background of the sub-project affected areas including Anuradhapura district in brief.

3.2.1. Physical Resources

Topography, Geology and Soil

60. The district is located in the Northern half of Sri Lanka and bordered by 7 districts

namely Vauniya, Trincomalle, Polonnaruwa, Matale, Kurunegala, Puttalam and Mannar. The

base elevation of the land in the district gradually increases from about 30 m above mean sea

level in the North Western and Northern fringes of the district to about 200m above sea level at

the Southern and South Eastern boundary from where it rises south of the district to the hill

country. The most characteristic topographic feature of this district is undulating nature of the

terrain, which is presence of ridges and hills that rise distinctly above the base elevation. The

geology of the major part of the district is highly crystalline, formed by metamorphosis of well-

bedded sediments in an old geosyncline.

61. The geology of the district belongs to ancient continent, Gondwanaland. Geology of

North Western boundary area of the district is overlain by geology of Pleistocene and Miocene.

Within district there are five rock types which are generally in the Central and Eastern parts of

the district named as Highland series. Western part of the district consists with Vijayan series

rocks of the Precambrian and the Palaeozoic eras. West of the Vijayan series rocks lie

Pleistocene and post Pleistocene sand and gravel of coastal nature. Appetite mine in

Eppawala, Mica mine in Kebithigollewa and limestone deposits in Palagala to Horowpathana

are the major mineral resources in the district.

62. Reddish Brown Earth – Low Humic Gley association of soil is the most commonly

distributed soil in this district. The Reddish Brown Earth component of this association is better

drained and occupies the upper parts of the undulations that almost exclusively make up the

landscape in the district. Poorly drained Low Humic Gley soil covers the lower parts of the

same undulations.

Climate

63. The climate of Anuradhapura district is typical to the Dry Zone of Sri Lanka. This district

receives an annual average rainfall of 1420 mm, mainly by North East monsoonal component.

High temperature receives from inter monsoons during October to December. Extremely

heavy rains bought in by cyclones and depressions are responsible for high rainfall in some

years.

Page 39: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

21

64. The rainfall generally follows bimodal pattern of distribution. The major one of the two

rainfall peaks is spread over a period of months commencing between late September to

February and are called Maha rains which falls during North-East monsoons. Due to this

relatively longer rainy period, there is a potential for filling up the tanks and sometimes it

causes floods even. As the Maha rains fade away, a dry season sets where there is little or no

rain. During this period decline the water reserves within the district soil dries up, forest

become less lush and the season turns less tranquil.

65. The second rainy season for the year begins any time from mid-March to mid-April and

lasts till May or even June, which is called Yala rain corresponding to Yala season. This is

shorter compared to Maha rain. This rain replenishes the depleted tanks and ground water

reserves to a substantial level. When the short wet season is over, dry weather sets in again

from May or June. In August the condition of climate is really arid and tanks get dried up and

mud gets lined cracked.

66. The annual average temperature of the district is 27.30C. Unlike rainfall the

temperature, which is warm throughout the year, shows little variation over the year and

between places in the district. The warmest period is March, May, August and September. The

relative humidity of the district varies in 70 – 82% within the year. During the South Western

monsoons the wind speed accelerates to 12 km/hr or it rises further to 16 km/hr. Evaporation

rate of water from a free water surface is 35 mm/week and varies from place to place.

Water Resources (Ground and surface water)

67. Tanks, streams, and springs are the main sources of surface water in the district and

are the main storages of rain water during whole year. There are 14 large scale tanks, 19

medium scale tanks and2600small scale tanks are located in the district. Major irrigation tanks

found in the district are the Kala wewa, Basawakkulama wewa, Nuwara wewa and Tisawewa

which were built during ancient times. Many other rulers constructed a number of large tanks

such as Padaviya, Nachchaduva, Rajanganaya, Mahavilacchiyawewa which further expanding

the irrigation network. Other than the mentioned reservoirs many ponds which fed by a

network of subterranean channels were constructed to supply water to the district. Egg: Kala

Oya and Kalankuttiya Oya supply water to Southern boundary of the district. The Eastern

boundary runs along the right bank watershed boundary of Nelu Oya along Yan Oya. In

Western, ModaragamAru and KalAru nourish the Western region of the district. Other than the

above mentioned perennial tanks, seasonal tanks are common in most parts of the district.

These are small tanks commonly known as village tanks; store water during the rainy season

and are mainly use for the purpose of agricultural activities. Throughout the proposed road

sections many seasonal tanks could be observed. Following table (table 6) shows the

seasonal tanks observed along the proposed subproject roads during the field survey.

Table 6 Small scale tanks located besides the sub –project affected areas

Page 40: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

22

Road name Chainage (km Name

NCAHC095 Kebithigollewa - Hendagala Road 5.1 (R ) Ovilbendiwewa

7.9 and 8.8 (R ) Ambagahawewa tanks

NCANC122 Ethakada - Etambagaskada - Tonigala

Road

1.9 (R) Divulgaskada tank

3.1 (R) Atambakaskada tank

NCANC126 Dachchidamana – Paranahalmillewa

Road 2.8 (L) Kudagama tank

NCAHC128 Kirigollewa - Hirallugama Road

2.5 to 4.2 (R) Unagaswewa

5.4 to 5.6 (R) Moragodawewa

6.75 to 7.4 (R) Tharanagollewawewa

9.3 to 10.2 (R) Hirrallugamawewa

NCAHD083 Kiriketuwewa – Bandara-ulpatha -

Kapugollewa Road

3.8, 4.4 (L), Sinhala Ataweeragollewawewa

13.2, 14.5 (L) Pathtewawewa

15.9 (L) Punchikulam tank

16.8 (L) Weerasolewewa

NCANC127 Thekkawatha – Pulleliya Road

1.5 (L) Viralmurippu tank

3.45 (R) Kudagamatank

4.4 (R) Puleliyatank

NCAND139 Yakawewa - Mahakongaskada Road

2.5 (L) Periyakulamtank

3.7 (L) Galkandegama tank

5.1 – 5.4 (L) Katukeliyawa tank

68. Ground water in the Anuradhapura district is being mainly use as a source of drinking

water. However at present it has expanded for agricultural activities to support cropping in dry

season. Ground water refers to both shallow and deep. Shallow ground water fluctuates with

rains, more in the well-drained upper slopes of the catena than the poorly drained lower slope.

Shallow ground water resource has been found to be better where the rock is quartzitic/ highly

weathered/ moderately and fractured compared to sites with un-weathered rocks. Large

number of surface water resource located within Anuradhapura district helps stabilize the

ground water resource.

69. The availability of shallow ground water is seasonal. It is abundant during and after the

Maha rains up to about the end of February, moderate from March up to about June and scare

thereafter till the commencement of the Maha rains. Within the district the geology beneath the

unconsolidated overburden is composed of crystalline rocks, which are hard and nonporous.

Hence the availability of deep ground water is very limited. The quality of ground water is

varying with the available compounds and substances of the district. Fluoride and Iron

contents in ground water have been found to be in high. Hardness due to elements such as

Calcium, Magnesium and salinity due to Chloride are other properties that lower the quality of

ground water.

Page 41: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

23

Air Quality and Noise

70. According to the information available at the National Building Research Organization

(NBRO), the concentration of the particulate matters (PM10) in the ambient air at Anuradhapura

in 1999 shows that the measured values are well below the NAAQS (Table 03). However

recent data for air quality is not available. Since number of mettle quarries, crushers and

gravel mines are located in Madawachchiya and Kebithigollewa DS divisions ambient air

quality of the area may affected due to emissions from above sites and related transport

activities. Apart from that, low addition of SO2 has occurred due to the heavy usage of

fertilizers and soil conditioners within this district. However atmospheric characteristics such as

CO, SO2, dust and other particulate matter of the air in Madawachchiya and Kebithigollewa

areas have not been studied yet.

Table 7.Air quality at Anuradhapura in May 1999

Date Start time (hrs) Ruin time (hrs) PM10

Concentration (µg/m3)

Maximum permissible level (µg/m3)

25/05/99 18.00 24 30 100

26/05/99 19.00 24 29 -

27/05/99 19.00 24 37 -

28/05/99 18.40 24 20 -

29/05/99 19.20 24 16 -

30/05/99 19.10 24 33 -

31/05/99 19.15 24 45 -

02/06/99 17.10 24 39 -

03/06/99 17.15 24 37 -

04/06/99 18.45 24 37 -

Source: NBRO

3.2.2. Ecological Resources

71. The natural vegetation in the Anuradhapura district and the sub-project affected areas

is mainly consists of tropical Dry Mixed Evergreen Forest. Natural forests in various states of

disturbance found in the district are the remnants of lush and sprawling natural vegetation.

The forest cover of the district is 24% from the total land area of the district. The forest type in

the district is belong to 3 main categories namely less disturbed natural forest, moderately

disturbed natural forest and highly disturbed natural forests. However due to human

interference over thousands of years, the vegetation in the district has under gone drastic

changes.

72. According to the moisture content available in the rain and soil, there are two types of

forest in the district namely dry and moist. The dry forest type, which is widespread in the

district, consists of the species such as Manilkarahexandra (Palu), Chloroxylonswetenia

(Buruta), Brideliaretusa (Ketakala), Syzigiumcumini(Madan), Vitexpinnata (Mille) and

Beryacordifolia (Halmille) etc. The moist type is found some DS divisions, which are closer to

the rivers, near water holes and in the uplands adjacent to tanks. Alseodaphnesemicarpifolia

(Wewarana), Berryacordifolia (Halmilla), Diosyrosmalabarica (Thimbiri), Terminaliaarjuna

Page 42: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

24

(Kubuk), Madhucalongifolia (Mee) and Schleiereraoleosa (Kone) are the more common trees

in wet and moist areas. Termineliaarjuna (Kubuk) is the most common tree along river banks,

all over the district.

73. When considering the vertebrates fauna, fresh water fish species such as Anguilla

bicolorbicolor (Anda), Mystusvittatus (Ankutta), Channastriata (Lula), Plotosuscanius (Magura),

and Puntiustitteya (Tittaya) are common in this district. Kelaarts toad, Hourglass tree frog,

Common branded caecilian and Small eared toad are the amphibian species recorded in

Anuradhapura district. The serpent reptiles and Tetrapod reptiles recorded in this area include

Earth snake, Bronzeback, Common whip snake, Russell’s viper, Saw scaled viper, Common

wolf snake and Merrem’s hump noses etc,. Out of the 427 bird species recorded in Sri Lanka,

many are reported to be present in this district because of availability of food resources,

favourable condition during migration season and bird favoured habitats such as riverine

forests, tanks and the villus in Wilpattu area. Among mammals Spotted deer, Palm squirrel,

Porcupines, Hare and Indian gerbil are the commonest mammals in the district. Endemic

species such as Red faced Malkoha, Purple faced leaf monkey are abundant species in this

area.

74. During the field observation period a total of 102 floral and 142 faunal species were

recorded. From the total recorded fauna 3 species, 1 reptile (Python molurus - Indian Python)

and 2 mammals (Felis chaus - Jungle cat and Lutra lutra - Indian otter) belong to the

threatened category. The summary of floral and faunal species as well as total recorded

species during the survey is included to the table 7, 8&Attachment 1 respectively.

Table 8 Summary of the floral species recorded during the field survey

Category Number

Number of Family 41

Number of Species 102

Endemic Species 1

Nationally Threatened -

Globally Threatened -

Introduce Species 37

Page 43: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

25

Table 9 Summary of the faunal species recorded during the field survey

Animal Group Total no of species recorded Endemic Threatened Exotic/Migrants

Dragonflies 2 - - -

Butterflies 18 - - -

Mollusks 2 - - 1

Freshwater fish 5 1 - 3

Amphibians 6 1 - -

Reptiles 14 - 1 -

Birds 74 4 - 5/2

Mammals 21 3 2 4

75. There are several Wildlife Parks, Sanctuaries, Strict Nature Reserves and Tropical

Wetlands are located with this district. Mihinthale Sanctuary, Ritigala Strict Nature Reserve,

Hurulu Forest Reserve, Kahalle Forest Reserve and Padaviya Sanctuary provide proper

habitats to fauna and flora within the Anuradhapura district. Some of these forests harbour

favourable habitats for large mammals’ such as elephant.

76. However any of these above mentioned environmental sensitive areas (Wild Life Park,

declared forest or nature reserves) or their wild fauna or flora is not located within or close

proximity to the project area. Therefore they will not be affected by proposed road

development activities in Anuradhapura district.

3.2.3. Economic Development

Land Use and the Agriculture

77. Anuradhapura is the largest of all districts in Sri Lanka, and covering an area of 7179

km2 that covers 10.9 % of the whole country’s land surface. The forest cover in the district is

59.2% while the extent of paddy cultivation is 18.6%. Altogether 515 km3 inland water bodies

distributed within the district. Pattern of human settlements around the roads vary mostly from

rural to semi- urban. The district economy is predominantly centred on paddy, coconut and

home gardens including vegetable cultivation. Cultivation heavily depends on the irrigation

tanks such as Nuwarawewa, Kala wewa, Basawakkulama, Nachchaduwa tank and Thisawewa

built by ancient kings. Apart from that irrigation system of Mahaweli Scheme provides

considerable amount of water for irrigation activities in the area.

78. In the year 2008 alone, 812,554 hectares were cultivated in the district and the paddy

harvest accrued amounted to 12,357 metric tons. 31,092 main irrigation schemes helped in

this regard. In addition to paddy cultivation, a land area of 6,324 hectares was cultivated with

vegetable, 23793 hectares with additional crops and pulses. As per the land utilization in the

district in the year 2008, 128,719.79 ha and 59,084.05 ha were used for paddy and chena

cultivation respectively (Table 7).

Page 44: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

26

Table 10 Land use pattern of subproject affected DSDs in Anuradhapura district -2008

Area A

ban

do

ned

tan

ks (

ha)

Mars

h lan

ds(h

a)

Ch

en

a(h

a)

Fo

rest(

ha)

Resid

en

tia

l(h

a)

Pad

dy (

ha)

Co

co

nu

t(h

a)

Tan

ks (

ha)

Scru

b l

an

ds (

ha)

Str

ea

ms(h

a)

Rese

rvo

irs (

ha)

Oth

er

Kebithigollewa 456.8

4

135.1

6

1686

.4

3735

7.7

8

2528

.97

6914

.65

0.0

7

0.2

8

9328

.37

383.8

4

2222

.13

149.5

7

Medawachchiy

a 197.5

4

6.2

8

6562

.6

1054

8.8

4

3964

.65

9908

.09

6.4

5

0.0

3

1416

9.5

2

111.0

3

3550

.74

219.9

3

Anuradhapura

district 5256

.56

1479

.51

5908

4.1

2332

84.2

6920

7.1

1287

20

948.8

9

3.9

9

1646

82.5

6

4502

.07

4916

6.0

5

5825

.9

79. The government of Sri Lanka has taken several actions to promote the agricultural

economy of the district. Under the Mahinda Chinthanaya programme, plant seedlings are

distributed for cultivators. Under the Construction of Agro wells project, assistance has been

provided for construction of thousands of agricultural wells in the district. Steps have also

been taken to improve the agri industry utilizing new technologies. Millions of money was

allocated for the establishment of Young Farmer Organizations and Youth Farmer Societies on

a village level basis at the aim of inter-change knowledge, experience and to establish Young

Farmer Settlements. Under the Home Gardening project in 2009, cultivators are provided with

coconut seedlings, bee hive boxes, and flower vases.

80. Under the implementation of commercial crop cultivation programme which was started

in 2007, millions of money has been spent on cultivation of Betel, Pepper, Kilo Gova, jack and

other commercial crops such as maize, cowpea, kurakkan, green gram, groundnut, manioc,

sweet potatoes, chilly, and onion. In 2009 Rs. 0.647. Millions of money has been allocated for

the programme of encouraging the production of organic fertilizer and is carried out by the

Provincial Agricultural Department. In the same year a sum of Rs. 2.55 million has been spent

for the purpose of Agricultural systems, soil conservation, educating school children on

agricultural technology, and to implement various programmes beneficial to the farming

community.

Page 45: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

27

81. The land use beside the project area include, large extents of paddy fields, scrublands,

forested areas, mixed cultivations, chena cultivations, home gardens and residences. The

majority of the people in the area is farmers and largely depends on paddy cultivation.

Additionally animal husbandry including cattle, goat and poultry is also common in some

roads. Following table shows the contribution of animal husbandry in project affected DSDs

and Anuradhapura district.

Table 11 Animal husbandry in project affected DSDs and Anuradhapura district in 2006

Area

No

of C

ows

Ann

ual m

ilk

prod

uctio

n (l)

No

of B

uffa

los

Ann

ual m

ilk

prod

uctio

n (l)

No

of g

oats

No

of p

igs

No

of C

hick

en

Kebithigollewa 5760 514650 5082 612470 503 137 3392

Medawachchiya 8256 1949830 1923 352225 2914 212 20440

Anuradhapura district 142320 21456935 58721 9601690 39434 8118 588468

Industries

82. Apart from agriculture, economy of the Anuradhapura district is predominantly revolves

around tourism industry, inland fisheries, small scale industries and some large scale

industries. According to recent estimates 24,592 of the population are employed in various

industries. Out of them 7632 persons are employed in 3453 small scale industries, while 9710

persons are employed in 53 large scale industries. However compare to the other districts,

industrial contribution in the district is poor.

83. The Anuradhapura district Chamber of Commerce, Industry & Agriculture (ADCCIA) is

the foremost business representative body in the district and functioning to promote, develop

and safeguard the agriculture, trade, manufactures, commerce, industries in the district.

According to ADCCIA Anuradhapura is growing at a rapid speed, therefore has great potential

for investors to start their businesses, particularly in agriculture, agro based industries and

livestock sectors.

84. At present, most of the population in the district depends on tourism industry. The

reason behind popularity of tourism industry within the district is ancient Sri Lankan culture.

Irrigation tanks, ruins of castles of several emperors, ancient temples, monastic sites, statures

of load Buddha are the main places, where local and foreign visitors attract towards this

district. Traditional items such as kitchenette appliances, cultural foods, Sinhala clothes,

ornaments etc are sold by the local people around these places. Eco-tourism is another

popularizing this area based on the eco-cultural history of the Ancient kingdom and traditional

day today activities around the cultivations.

Infrastructure Facilities

85. Except in some rural villages, electricity is available for most parts of the district. The

Village Electrification Development Programme currently is being operating to supply electricity

for the people who are not covered by the National Electricity Network. In the year 2009 the

government has spent Rs. 19,577,456 on rural electrification projects.

Page 46: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

28

86. Other than electricity, tele-communication facility is available in most of the areas

mainly through wireless services. Pipe borne water facility is available to limited areas and pit

latrines, sewage canal systems and proper garbage dumping sites are restricted to the urban

sector of this district. PRDA is engaged in construction and maintaining many roads in the

district and helping the people to solve their transport problems and improve their living

standards. Many road development projects are currently undergoing to improve the transport

facility. Common wells have been constructed mainly for the domestic and agricultural

purposes and water is obtained through pipelines.

3.2.4. Social and Cultural Development

Population and Community

87. A total of 22 DSDs and 18PSDs are located within the Anuradhapura district. Selected

roads for the improvement run through 2 out of 22 DS divisions of the district. The population

of the Anuradhapura district by 2010 was 886945 and represent all ethnic and religious groups

in the country. On a community basis there are 808,859 Sinhalese, 72,289 Muslims and 4,502

Tamils. A minority of 1,295 persons belong to other ethnic groups. Mainly five religious groups

represented in the district as follows: 90% Buddhist, 0.5 % Hindus, 8.4% Muslims, 0.8 %

Roman Catholics and 0.3 % other Christians. Table 7 indicates population sizes of the 2 DS

divisions of the district.

Table 12 Population sizes of the project affected DS divisions Anuradhapura district

DS divisions Sinhalese Tamil Muslims Population

Medawachchiya 47303 195 2643 50141

Kebithigollewa 21,057 31 2170 23258

3.2.5. Health and Educational Facilities

Health Facilities

88. A total of 60 hospitals distributed in different locations of the district. These include a

single Provincial general hospital, 10 Base hospitals, 4 District hospitals, 4 Peripheral units, a

single Prison hospital, 23 Rural hospitals, 19 Central dispensary and Maternity homes and 4

Ayurveda hospitals. Out of these, 3 Base hospitals and 6 Central dispensary units are located

at Medawachchiya, Kebithigollewa and Padaviya.

89. During the last four years, the health sector received unprecedented boost in the

Anuradhapura district. From 2006 to 2009 the P.S.D.G institution, World Bank and other

funding institutions have provided a total of Rs. 833 million for assistance of health

development activities of the Anuradhapura district. These funds were allocated for

construction and renovation of hospitals, improve provision of health facilities, procure modern

equipment and upgrade technology, improve standards and facilities at centres dealing with

prevention of communicable diseases and for improvement of transport facilities. Accordingly

one surgery hospital, 3 base hospitals, 4 district hospitals, 7 central hospitals, 24 rural

hospitals and 20 clinics, were established in the district. At the same time, district was

Page 47: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

29

provided with 474 doctors, 504 nurses, and 423 health service personnel. Hospital bedding

capacity was increased to cater for 2987 patients. Apart from that certain amount of money

was spent for the development of Indigenous Medical Services.

Educational Facilities

90. Generally the education level of the district is fairly good. The literacy rate of the district

is 90.5%. The educational level of the people within the district is shown in Table 8.

Table 13 Educational level of the people distributed in Anuradhapura district

Litera

cy r

ate

No

schoolin

g

Atte

ndin

g

gra

de 1

Passed

gra

de 1

-5

Passed

gra

de 6

-10

Passed

GC

E(O

/L)N

CG

E/S

SC

Passed

GC

E(A

/L)

HN

CE

/HS

C

Degre

e

an

d

above

Not sta

red

90.5

5.7

1.5

24

43.6

14.2

5.9

0.6

2.5

91. Within the district altogether 585 schools including 549 government schools, a single

special education unit and 35 piriven as are distributed. Out of them 11 government schools

are located beside the proposed subproject roads and are illustrated in table 9. The student

population in the district amounts 174,359with9228 teachers serving in these schools. Out of

them 594 teachers are in Medawachchiya DSD and 290 teachers are in Kebithigollewa DSD.

Table 14 Government schools located beside the proposed subproject roads

Road name Chainage (km) Name

NCAHC095 Kebithigollewa - Hendagala

Road

3.7 Timbiriwewa government school

6.5 (L) Hadagala government school

9.4 (L) Ambagahawewa government school

NCANC122 Ethakada - Etambagaskada -

Tonigala Road 2.5 (L) Atambagaskada government school,

NCAHC128 Kirigollewa - Hirallugama Road 4.2 (L) Unagaswewa government school

8.2 (R) Hirallugama government school

NCAHD083 Kiriketuwewa – Bandara -

Ulpatha - Kapugollewa Road

7.2 BandaraUlpotha government school

14.1 (R) Pathtewa government muslim school

NCANC127 Thekkawatha – Pulleliya Road 1.4 (L) Viralmurrippu government school

NCAND139 Yakawewa - Mahakongaskada

Road

2.4 (L), Gaminiwewa government school

10.3 (L) Muslim Halmillewa government school

3.2.6. Sites of the Cultural, Archaeological and Historical Significance

92. Anuradhapura is the first historical capital of Sri Lanka and today recognised by

UNESCO as a World Heritage Site, From the 4th century BC, Anuradhapura was the capital

Page 48: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

30

city of Sri Lanka and until the beginning of the 11th century it remained one of the most stable

and durable centres of political power and urban life in South Asia. Although according to

historical records the city was founded in the 4th century BC, the archaeological data put the

date as far back as the 10th century BC.

93. Primary Buddhist attractions in Anuradhapura are the Atamasthana or the 8 main

places of worship located within Anuradhapura town boundary. These eight places include Sri

MahaBodhiya, Lovamahapaya, Ruwanwelisaya, Thuparamaya, Abayagiriya, Jetavanaramaya,

Mirisavetiya and Lankaramaya. In addition to the Atamasthana Mihinthalawa was a thick

jungle area inhibited by wild animals and was a hunting ground reserved for the royals. All this

changed in 250 BC when the son of the Indian Emperor Asoka, Mahinda Maha Thero arrived

at the Missaka Pauwa. Initially it was the Mahinda Maha Thero’s residence, but later

Mihinthale became a main centre for Theravada Buddhism. Sigiriya is rock fortress located

away from the Anuradhapura town. King Kassaypa was made his kingdom in the top of the

“Sigiriya”. It is a culturally significant place that is because it was suggested for eighth wonder

of the world. Another important location is Isurumuniya built by King Devanampiyatissa. The

carving of Isurumuniya lovers on the slab has been brought from another place and placed it

there. Thantirimale, Avukana, Vijithapura and ThalaguluViharaya are also very important

religious, historical, cultural and archaeological sites located within the district.

94. However none of the above mentioned Cultural, Archaeological and Historical

Significance sites are not located close proximity to the proposed subproject roads. But

several locally important Buddhist temples are located left & right hand side beyond the

proposed ROW and any impacts will not expect from the project to these locally important

religious sites (Table 15).

Table 15 Locally important religious places located beside the subproject roads

Road name Chainage (km) Name

NCAHC095 9.3 (L) Upulviharaya at Ambagaswewa

NCANC122 2.45 (L) Temple at Atambagaskada

NCAHC128 5.3 (R) Sri Sugathawardanaramaya, Moragoda

NCAHD083 2.1 (L) Temple at Lunuatulewa

16.7 (L) Mosque at Weerasole

19.3 Jayasumanaramaya temple, Kapugollewa

NCANC127 2.1 (L) Viralmurippu Temple

5.3 (R) Puleliya Temple

NCAND139 2.4 (R) Temple of Periyakulam

12.0 (L) Sri Aanandarama temple of Aneketiya

Page 49: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

31

Chapter 4 - Potential Environmental Impacts Screening and Mitigation Measures

4. Introduction

95. Proposed construction activities of the subproject roads involve widening of single lane

to substandard two lanes with pavements, improvement of road surface, construction of side

drains & embankments, widening or replacement of culverts, and cause ways etc. During the

construction, several activities have to be implemented including removal and re-establishment

of public utilities, removal of road side trees, mining of gravel and sand, quarrying of metal,

transportation of construction materials, disposal of construction waste, establishment of

construction material processing plants, storage yards, labour camps, vehicles and equipment

service yards and other facilities. These activities can cause several impacts to the existing

environment of the project area. Feasible mitigation measures for anticipated impacts have

been suggested to avoid or minimize significant environmental impacts associated with

construction activities while enhancing the positive environmental impacts. Since construction

activities of the all the seven subprojects are similar, environmental impacts and mitigation

measures associated with pre construction, construction and operation stages of the project

describe in general through the following section. These measures need to be included to the

contract conditions and specification of the project.

4.1. Environmental Impacts Associated with Pre Construction and Construction Stage

Resources mobilization

96. Mobilization of resources for the project construction activities such as space, human

capital and physical resources is a major task carryout at an early stage of the project. The

space need for the various activities of the project include construction of material processing

plants, storage yards, labour camps, offices and other accommodations. Adequate provision

should be made to mobilize the construction equipment’s, vehicles and other construction

materials.

Selection of lands for temporally use

Outline and impacts

97. Materials processing plants, storage yards, vehicle parks, disposal sites and labour

camps should be established within the subproject affected areas in accordance with local

laws, regulations and in close consultation with villages and LAs. This will avoid/ minimize

social and environmental impacts such as complicit situation b/w workforce and surrounding

communities, soil erosion, removal of green cover vegetation ad trees etc…that can be

aroused during the construction stage.

Page 50: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

32

Mitigation measures

98. Selection of lands for above activities should be undertaken by the contractors

carefully; away from environmental and public sensitive areas. Recruitment of local un-skilled

and skilled workers for the proposed construction activities can reduce the requirement of land

for labour camps in large scale. Provision of adequate compensation/rent for consuming the

selected sites and obtaining official permits from the relevant authorities, if any public utilities

will be used are also essential.

Acquisition of lands

99. Availability of lands according to the detailed design of the subprojects is important for

the construction activities. Since construction activities are restricted to the existing RoW of the

selected subproject rods, land acquisition will not be required.

Removal of public utilities

Outline and impacts

100. Road improvement work may generally impact on the public utilities such as electricity,

pipe born water supply and telecommunication facilities which are located within the existing

RoW. The electricity is available all the subproject roads except few sections. However, there

are no telecommunication and pipe born water supply facilities in any of the proposed

subproject roads.

101. Since most of the electrical posts are located away from the existing carriage ways,

impact will be less due to removal. If the removal of utilities undertake during pre-construction

sage, responsibility for that should be handled by the PIU. If it is undertaken, during the

construction stage it should handle by the contractor under the supervision of PIU.

Mitigation measures

102. Recruitment of well trained and experienced machinery operators, technical officers &

labours, proper coordination with Ceylon Electricity Board (CEB) during the removal of electric

posts will reduce the accidental damage to the utilities, workers and general public. These

activities will also ensure re-establishment of utilities rapidly. Advance notice to the public

about the time and duration of the utility disruption will reduce public inconvenient and provide

adequate time to obtain alternative power sources during the disruption.

Extraction, transportation and storage of construction materials

Outline and impacts

103. All the construction materials for the project activities are available within the project

affected area of Mihintale, Medawachchiya, Ethakada and Kebithigollewa areas of

Anuradhapura district. In general large-scale extraction of construction materials can have

negative impact such as noise, air, water, soil pollution and reduction of scenic beauty with

damage to ecosystems.

104. Soil erosion, lowering of the river beds, destruction of river banks, reduction of sand

replenishment of coastal beaches, coastal erosion and salt water intrusion during the dry

Page 51: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

33

season are main consequences due to sand mining. Nuisance from dust, noise and vibrations

will create health and social disturbance to the people around metal extraction sites.

Stagnation of water in borrow pits, material storage yards and mettle quarries provide breeding

sites for mosquitoes and may cause accidental damage to people and wild animals. The

transportation and storage of construction materials can potentially cause disturbance to the

general public, increase dust and noise nuisance and damage to minor roads.

Mitigation measures.

105. Extraction of construction materials should be undertaken only from the approved

mines and quarries by GS&MB. If new material extraction sites need to be located, they should

exclude places which are close to the public (schools, religious places, hospitals) and

environment sensitive areas. Environmental requirements and guidelines issued by the CEA,

GSMB and LAs should be followed with respect of locating material extraction sites and other

operations including rehabilitation of the extraction sites at the end of their use.

106. Transport, loading and unloading of construction materials should not cause nuisance

to the people by way of noise, vibration and dust. All drivers should obtained license for the

category of vehicles they drive. They should follow the speed limits on roads based on the

traffic rules and regulations. Construction materials should not exceed the carrying capacity of

the trucks.

107. When storage of construction materials all stock piles should be located sufficiently

away from environment and public sensitive locations. Sand, rubble, metal bitumen and

cement should be covered to ensure protection from dust and avoid emissions. Construction

materials should not store around irrigation canals, tank bunds, cross drainage and natural

flow paths. All cement, bitumen (barrels), oil and other chemicals should be stored and

handled on an impervious surface above ground level (e.g. concrete slab) and should be

enclosed ensuring that no storm water flows in to the structure. Adequate ventilation should be

kept to avoid accumulation of fumes and offensive odour that could be harmful.

Effect on local road net work

Outline and impacts

108. In general, sources of construction materials such as borrow pits, quarries and mines

as well as construction material processing plants cannot establish adjacent to proposed

subproject roads. Therefore construction materials should be transported from other areas to

the project sites through the rural road network. However the carrying capacities of the rural

roads are not sufficient to cater the vehicular load and hence, can be damaged during

transportation of construction materials.

109. In generally LAs cannot engage in such immediate maintenance activities due to the

lack of financial capacities.

Mitigation measures

110. Nomination should be given by the contractor in bidding work of the quarries and

borrow areas, which he intends to use roads of adequate capacity for heavy trucks by

providing evidence. If construction vehicles are likely to cause damage to public roads,

provision should be made for their repair and restoration as part of the contract. Contractor

Page 52: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

34

should obtain a permit from LAs to use local roads prior to the transportation of construction

materials, machineries and equipment’s. Construction materials shall not exceed the carrying

capacity of the local road network. Contractor should maintain all roads, which are used for the

transportation of construction materials and other related activities.

Solid waste disposal and sanitation

Outline and impacts

111. Solid waste (construction debris, spoil, and waste generated from labour camps,

officers accommodations) associated with construction and other related works may impose

several negative environmental and social impacts to the subproject affected area including

impact on ecology, public health and scenic beauty. Decaying wastes also attract pests such

as rats and flies which become unhealthy, dirty, and unsightly places to reside in. Labour

camps, garbage disposal sites and material storage yards provide favourable habitats for

vectors of diseases like mosquitoes and rats. Contamination of water bodies with wastewater,

construction debris and spoil will create significant impact on the aquatic lives and people

inhabited in the area.

Mitigation measures

112. To minimize above impacts, strict environmental compliance would be implemented

with regard to disposal of waste. Selection of the disposal site by the contractor should exclude

areas which are close to public and environment sensitive. Prior approval for the disposal site

should be obtained from the LAs via Grama Niladari. All debris and residual spoil materials

(soil, sand, rock, and deadwoods) generated from construction activities shall be re-used

wherever possible for site levelling, back - filling under instruction of Engineers & Construction

Supervision Consultant (CSC). Dump materials should be placed without interference to the

irrigation canals, water bodies, agricultural lands or any other environmental sensitive areas.

113. Contractor should handle and manage waste generated from the construction/labour

camps without contaminating the environmental conditions or affecting the risk of

public/communities living near the sites. Proper solid waste disposal, sanitation and sewerage

facilities (drinking water, urinals, toilets and wash rooms) should be provided to all sites of the

construction/labour camps. Adhering to the guidance from Provincial office of CEA will avoid or

minimize health hazards and environmental pollution. Selection of the location for labour

camps should be approved by the Engineer and comply with guidelines/recommendations

issued by CEA and LAs.

114. Provision of proper drainage facilities to minimize stagnation of water around worker

based camps and keeping the drainage facilities clean to prevent breeding of rats and other

vectors such as flies are necessary. Garbage bins should be provided to all worker based

camps and construction sites, and should be dumped regularly in a hygienic manner under the

inspection of Public Health Inspector (PHI) in the area.

115. To avoid waste generation and sanitation problems from labour camps, majority of

skilled and unskilled workers should be selected from the project influence area. If migrant

labour is brought for construction activities from different areas there may also be conflict

situations among the workers and settlers near worker camps. Spreading of communal

diseases is also possible due to migrant labourers.

Page 53: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

35

Effect on water resources

Outline and impacts

116. Seasonal water bodies, streams, irrigation canals, tanks and community water supply

facilities are located adjacent/across the proposed subproject roads. For the construction and

construction related activities water will be required in significant amount from above sources.

Therefore, excessive use of water for construction activities may impact the local communities

during dry season. Furthermore, construction close to the water bodies, construction of cross

drainages, poor sanitation at work sites, labour camps and dispersal of solid waste may affect

water sources used by local communities in different ways. E.g. the surface water runoff and

groundwater close to the construction site can be polluted with various materials (paints, clues,

lubricants, toxic chemicals, cement and bitumen) use during construction site which in turn

affect the overall water quality of the area.

Mitigation measures

117. Contractor should make employees aware of water conservation, pollution and

minimization of water usage. Water from residential areas should be obtained after consent

from local community. Construction works affecting water bodies have to be undertaken during

the dry season and necessary steps should be taken to avoid entering wastewater directly in

to the water bodies. Pits should be introduced wherever possible to prevent silting of water

bodies as a result of construction work. The upstream and lead-away channels of the bridges

and culverts should be cleaned in order to maintain the smooth water flow downstream and it

should not obstruct or prevent existing flow of water. Excavation of beds of any streams,

irrigation systems, and other water resources should be minimized as much as possible.

118. Public or community water supplies with proper sanitation arrangements should be

provided to the labour camps and other construction related places with the approval from the

relevant authorities, ensuring no raw sewage is released into drains or water bodies. However,

necessary actions should be taken to prevent disruption of water sources used by the

community due to construction work. If disrupted, an alternative water supply sources should

be arranged for the affected community.

119. Water that is contaminated with fuel, oil and grease should not be directly released to

storm water or natural water drainage system. If released, they should be entered to pits

allowing them to filter, settle down and release to the environment as per the guide lines

issued by the CEA. Vehicles and equipment used for the construction activities should be

maintained in good condition, ensuring no undue leakage of oil or fuel is released to water

sources. Equipment and vehicles should not be allowed to wash with drinking water wells or

streams. All toxic and hazardous materials required for construction, including asphalt, fuel;

toxic, hazardous and containing other fine partials should be sited at least 500m away from

water bodies and should prevent their entering into such places.

Page 54: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

36

Soil erosion sedimentation and siltation

Outline and impacts

120. The project affected area of the NCP receives a considerable amount of water during

rainy season. Thus soil erosion, sedimentation and siltation can take place any time during

rainy seasons due to construction activities such as cut and fill operation, land clearing,

construction or reconstruction of new culverts, causeways, and construction of earth and line

drains. Decrease of infiltration of rain water, acceleration of surface runoff, lowering of the river

beds and destruction of the river banks are the main impacts associated with soil erosion.

Mitigation measures

121. Top soil generate from the construction sites (not exceeding 150 mm) should be stored

properly (height not exceeding 2m) and reused for turfing and tree planting activities. Clearing

and filling areas should be treated against flow acceleration and should be carefully designed

to minimize obstruction or destruction to natural drainages. Steep cuts should be limited and

the slop of cuts should be decreased in order to minimize the erosion due to rain. Retaining

structures and deep-rooted grass should be placed in erodible areas, where necessary. Use of

silt traps and erosion control measures where construction activities close to the water bodies

to avoid entering of cement particles, rock, rubbles and waste water is also necessary.

122. All temporary soil dumps should be removed from site to a suitable disposal site. If

temporary soil dumps are left at the site for a long time those dumps should be covered with

thick tarpaulin sheets. Suitable local drainage facilities should be established properly to drain

water in the construction areas. Construction activities including turfing, earth work and

construction of cross drainages should be conducted during dry season (May to September).

Temporary floods

Outline and impacts

123. Inundation sections are recorded during the field survey of several sup project roads

due to poor drainage facilities, roads situated in low elevation, between paddy fields and close

to the spill of seasonal tanks. In addition, water stagnation is also observable within the RoW

of subproject roads during the rainy season. Flooding or stagnation of water will cause public

inconvenience, loss or damage to access or any land or property.

Mitigation measures

124. Increasing the embankment height of the particular sections with construction of new

cross drainages, reconstruction of existing culverts, causeways and bridges with sufficient

capacity will avoid location specific temporary floods. All construction activities should be

properly planned & arranged to minimize the flooding conditions as a result of blocked

drainage paths. The existing drains should be cleaned after site specific construction,

excavations, clearing & grubbing to avoid flooding or stagnation of water.

125. Storing of chemicals and construction materials should be avoided in areas where

those can be washed away by flood. Temporary earth drains should be formed as practically

as possible until required lined or earth drains are provided after excavation and other

construction activities.

Page 55: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

37

Effect on flora, fauna and their habitats

Outline and impacts

126. In general subproject roads run through rural residential and agricultural areas

including home gardens, paddy fields, coconut and other mixed cultivations, scrub lands,

chena cultivations and sometime around forested areas. Additionally perennial tanks, streams

and other stagnant water bodies are also located in these subprojects affected areas. During

construction phase activities such as site clearing, construction of culverts and bridges, mining

and quarrying operations etc., will potentially impact to the ecological resources by disturbing

habitat, increasing soil erosion and surface runoff, creating noise and vibration at the project

site. Some road side trees which locate close to the existing carriageway will need to be

removed from the existing RoW. Removal of trees and other excavation works have the

potential to destroy or injure wildlife with limited mobility; disrupt their breeding, migration and

foraging behaviour. The impacts from noise, vibration, dust emissions and other project related

activities can change the usual behaviour of wild animals and can affect the natural ecology of

the project area if project activities are not undertaken properly.

Mitigation measures

127. Awareness programs should be organized for the workforce to provide necessary

instructions about Importance of flora, fauna and different types of aquatic and terrestrial

habitats. Avoid workforce from disturbing the flora, fauna including hunting of animals,

gathering fire wood from the surrounding habitats and fishing in water bodies and avoid

removal of road side trees as much as possible. If rare, threatened or endangered floral or

faunal species as given in section 3.2.2 are found during construction activities, it should be

immediately informed to Resident Engineer (RE). All construction activities should be planned

in those areas according to the RE followed by environmental specialist of CSC’s instructions.

128. A total of 294 trees from 7 subproject roads {C095 (50 trees), C122 (45 trees), C126

(17trees), C127 (22 trees), C128 (35 trees), D083 (55 trees) and D139 (70 trees)} have been

identified within the proposed ROW and those should be removed during the construction

stage. Regarding the removal contractor shall adhere to the guidelines and recommendation

made by the CEA. .Also it is necessary to obtain permit from the Department of Forest for the

removal of trees. Decision on tree removal should be mainly based on detailed engineering

design. All road side trees subjected to potential removal should be marked and preparation of

inventory done prior to clearing by the contractor. When removing of trees, valuable timber

should be properly stacked and handed over to DoF or rightful owners. Tree planting should

be done in wherever appropriate space along the road side compensating at least 1 tree cut

with planting 3 trees by the contractor. If not, the Executive Agent/ Implement Agent (EA /IA)

will need to find a suitable place in consultation with LA’s and local communities for tree

planting programme. This will help to compensate the floral loss during construction stage and

provide long term benefits to the society and useful in demarcating and protecting the road

reservation. The suitable saplings for the tree planting programme should be selected with the

instruction of DoF.

Page 56: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

38

Biodiversity conservation and sustainable natural resource management

Outline and impacts

129. The subproject affected areas are mainly consist with man-made habitats such as rural

agricultural villages including home gardens, paddy fields, mixed cultivations, chena, water

bodies and associated irrigation schemes. In general road construction activities may Impact

to the surrounding vegetation, i.e. loss of native species and species diversity, increased risk

of invasive species, top soil erosion, seed bank depletion, risk of fire and seed disposal.

Selection of material extraction sites, removal of trees and other excavation works has the

potential to destroy or injure wildlife. It may also impact to the habitat quality, species diversity,

and reproductive success of some species. The noise from construction vehicles, equipment,

material processing plants and vehicle traffic has the potential to disturb breeding, foraging,

and migrating behaviour of wild fauna.

130. Since the proposed project activities are restricted to the existing RoW of the

subproject roads, it would not lead to loss of habitats concerned, changes in the land use

pattern and will not affect the population of any identified floral and faunal species Furthermore

modification of existing habitats, impact to native species and threat to existing biodiversity or

introduction of invasive species will not be expected through the subproject activities.

Mitigation measures

131. Careful attention should be taken especially during the construction phase to avoid or

minimize clearing of natural habitats such as small forest patches, replacement of natural

vegetation and activities which can cause introduction of alien species. Almost all the

stakeholders associated with the construction and pre construction stages of the project

should be made aware of the negative impacts that can arise due to above activities.

Contractor should especially be aware not to introduce alien species during construction

related activities such as transportation of construction materials (Turfing and sub base

materials) machineries, vehicles and equipment’s from the outside areas. Saplings for the tree

planting program should comprise native or endemic species which is suitable to the existing

climatic condition of the subproject areas. Client should undertake periodic assessment of

accidental or unintended introduction of invasive alien species and other construction activities

that can affect natural ecosystems.

132. Although project activities will involve use of natural resources such as water, metal,

sand, earth in the project affected areas; use of those in an unsustainable manner will not be

practiced during construction as well as its operation cum maintenance phases. However

anticipated impacts (eg. removal of trees and green cover vegetation, lowering of river beds,

soil and coastal erosion) can be avoided or minimized by adhering to proposed mitigation

measures through EMPs.

Protection of archaeological, cultural and religious places

Outline and impacts

133. None of the proposed subproject roads are not located close proximity to the important

archaeological, cultural and religiously significant locations. But several locally important

Buddhist temples are located left & right hand side beyond the proposed ROW and any

Page 57: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

39

impacts will not expect from the project to these locally important religious sites (refer Table

14). Since Anuradhapura district is very famous for the archaeological, cultural and religiously

significant locations, construction activities may impact to the unidentified significant locations.

Mitigation measures

134. If any fossils, coins, articles of value antique, structures etc., discovered on the site and

or during the construction work, necessary steps should be undertaken to inform to the

Engineer and Department of Archaeology (DA) immediately. If there are any important

archaeological, cultural and religious sites recovered during project activities, work should be

stopped within 100m in all direction from the site discovery as mention in Antiques Ordinance

in 1940 and Cultural Property Act of 1988. Further, necessary precautions should be

undertaken to avoid entering any workmen or any other person to the above areas. Also

assistance should be taken from DA for further project activities within the relevant site.

Disruption of traffic

Outline and impacts

135. In general Existing Average Daily Traffic (ADT) volumes of the proposed project roads

are low and do not exceed the 800 ADT value (Table 13). However construction activities

close to the construction sites and public sensitive locations may lead to increase traffic

congestion. Further, vehicles involve in transportation of construction materials will increase

accidental risk; noise exhaust emissions, delays in travel time and disturbance to the public.

Table 16 Existing and predicted average daily traffic volumes of seven roads

Source, Detailed Design and Final Report, Volume – 4 (Economic Analysis and Traffic Studies

of current project).

Mitigation measures

136. Advance notice to the road users and roadside communities about the schedule of

construction activities, provision of safe and convenient passage to the vehicles and

passengers especially during construction of culverts and causeways, implement traffic

management plans in construction areas according to the traffic rules and regulations if

necessary in close coordination with local communities/authorities and local police by the

contractor.

137. All signs use for traffic management should be standards and approved by the

engineer/ police. Construction sites and excavated areas should be barricaded with warning

tapes, painted barriers or traffic corns. Usage of flagmen and/or temporary traffic signs for

construction sites or temporally diversion, allocation of properly trained personnel provided

with proper gear including communication equipment and luminous jackets for night use are

other measures that have to be undertaken during construction period.

Personal safety of workers and general public

Outline and impacts

138. Construction related activities both within and outside of the subproject affected areas

could create accidental harm to general public and the work force. Construction of, culverts,

Page 58: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

40

cause ways, surfacing, roadway excavation, removal of road side structures, trees, use of

hazardous substances, processing and transportation of construction materials are the main

causes associated with accidental risk.

Mitigation measures

139. Contractor should organize awareness programs about personal safety of the workers

and general public in the area with proper briefing and training on safety precautions, their

responsibilities for the safety of themselves and others. Contractor shall comply with

requirements for the safety of the workmen as per the International Labour Organization (ILO)

convention No. 62, Safety and Health regulations of the Factory Ordinance of Sri Lanka to the

extent that are applicable to his contract. Other than that, contractor has to comply with

regulations regarding safe scaffolding, ladder, working platforms, gangway, stairwells,

excavations, trenches and safe means or entry and egress.

140. Use of licensed and trained plants and vehicle operators, provision of protective

footwear, helmets, goggles, eye-shields, face masks, ear plugged and clothes to workers

depending on their duty (mixing asphalt, blasting, handling equipment) are the major steps that

can be taken to reduce accidental risk. Apart from that provision of high visibility jackets to the

workers when construction activities are taking place at night with necessary lighting

arrangement, allocation of flagmen during the day time and provision of two red lamps at night

are also necessary. Provision of first aid facilities and emergency transport facilities to the

construction sites and labour camps also important responsibility of contractor.

141. Excavated areas for construction should be barricaded using barricading tapes and

sign boards. Quarry operations, roadway excavations, and blasting should be carried out and

supervised by trained personnel. Explosives for the project activities should be stored in a

secure location in a protected way. Arranging regular safety checks for vehicles and

equipment’s, allocation of responsibility to the relevant personnel, prohibition of alcoholic

drinks and other substances which may impair judgment of workers engaged in construction

activities, arrangement of proper first aid and transport facilities for injured people, installation

of warning signs, speed limits and signals to particular locations of the road.

Impact on socio – economic condition of the area

Outline and impacts

142. There are no built up properties or land that will be affected by the RoW for the roads.

In this context there will be no resettlement issues involved in the proposed project. Other than

that traffic congestion, disturbance or loss of income generating activities will not be practiced

during the project cycle. The significant negative impacts expected during construction

activities are delays and inconvenience of travelling, increase of dust and noise.

143. In overall, the project will cause many socio-economic benefits to the road users and

road side communities. Some of these include, provision of connectivity to different institutions

of socio-economic and cultural importance, reduction of poverty and facilitating on-going

development initiatives etc.

Page 59: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

41

Effect on existing drainage

Outline and impacts

144. Land clearing, cut and fill operations and other construction related activities may lead

to accidental damage to the culverts, bridges and other irrigation structures. Storage of

construction materials and alteration of natural flow paths will create temporary impact to

existing drainages.

Mitigation measures

145. Investigation report should be submitted to the engineer if diversion or close or blocking

of canals, streams or other water sources for proposed construction work. Approval should be

obtained from relevant authorities (DOI, DS, DoAS) prior to such action take place. Restore

the water bodies to its original status once the need for such diversion, close or blockage is no

longer required.

146. Contractor should avoid storage of construction materials and disposal of debris

around irrigation canals, cross drainage and natural flow paths. Provision of temporally

drainage facilities to the construction site will be required, if existing drains are obstructed.

Contractor is responsible for replacing structurally damage structures and maintaining

drainage paths and drains clear at all times.

Impact from dust, noise and vibration

Outline and impacts

147. Dust, noise and vibrations generated from the project activities will impact the roadside

communities and people who inhabit around material extraction sites (mining and quarrying

sites). In general poor air quality is the most immediate pollution effect experience from the

construction sites. Release of Volatile Organic compound (VOL) from storage and transfer of

vehicle/equipment fuels, emission of small amounts of Carbon monoxide, Nitrogen dioxide and

particulates from blasting and dust generated from clearing, grubbing, excavating, backfilling,

dumping, mixing concrete, transportation of materials, storage of soil and metal piles etc. will

be available in the surroundings due to wind.

Mitigation measures

148. Construction related activities closer to public sensitive locations have to be scheduled

in coordination with the relevant authorities (community leaders, schools’ principals, high –

priests or other respective officers) to avoid disturbance to day to day activities of the people.

All machinery, equipment and vehicles should be maintained in a good condition by engaging

skilled mechanics and regularly maintained in compliance with National Emission Standards

(1994). Noise control regulations stipulated by the CEA in 1996 (Gazette Extra Ordinance, No

924/12) should strictly be implemented for crushers, hot mixed plants, construction vehicles

and equipment. The maximum permissible noise levels at boundaries of the land in which the

sources of noise is located for construction activities are 75dB (A) Leqand 50 dB (A) Leq during

day time and night time respectively (Day time: 6.00 am – 7.00 pm, night time: from 7.00 pm –

6.00 am). However Contractor should limit working time for activities that create noise from

6.00 am to 6.00 pm.

Page 60: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

42

149. Crushers and hot mixed plants should be placed with the approval of Engineer, CEA,

and LAs and should be located at least 500 m away from residential and environmental

sensitive areas or other public sensitive locations. Dust extraction units, exhaust silencers and

noise reduction devices can be fitted to the road side crushers, construction vehicles and hot

mixed plants to reduce dust emissions.

150. Dust emissions during transportation of construction materials should be controlled by

enforcing speed limits to the vehicles, providing of dust barriers (canvas, hard polythene,

asbestos sheets) to the public sensitive locations, wet spraying of quarry sites, construction

sites, roads which will be used for the transportation of construction materials at regular

intervals. Tarpaulin covering is mandatory on trucks/lorries which are used for transporting

materials and all construction materials (sand, gravel, metal, cement) should be stored with

proper covering. Suitable actions should be taken to minimize or avoid dirt and mud being

carried to road surface. Contractor should also take actions to prevent bad odour and offensive

smells emanating from chemicals, construction material processing or other construction

activities

151. Note: LAeq'T' means the equivalent continuous, A- weighted sound pressure

determined over a time interval T(in dB).

Road side landscape and road furniture

Outline and impacts

152. Maintenance of road side landscape and provision of road furniture is a must to

enhance the scenic beauty beside the road corridor and public safety during the operation

stage. Road landscape include tree plantation, registration of road embankments and other

slopes, edge treatment of water bodies while road furniture include foot paths, railings, storm

water drains, traffic signs, speed limits, and any other such items.

Mitigation measures

153. All debris, piles of unwanted earth, spoil materials, temporally structures should be

cleared away, from the road sides and from other work places and disposed at locations

designated or acceptable to the RE. Road landscape activities have to be done as per either

detailed design or typical design guide lines given as part of the bid documents. Road furniture

items are provided as per the design given in the bid documents

4.2. Environmental Impacts Associated with Operation Period

Air quality and noise

154. The major air quality pollution factor in the project area at present is dust emission from

gravel and sandy roads. Therefore it is expected to reduce the existing dust emission after

proper surfacing of the roads. Further, alignment of roads, widening and surfacing will allow

considerably higher speed for vehicles with minimum accelerations and decelerations which in

turn reduce the vehicular emissions and sound pollution compare to current situation. This

condition will positively impact the air quality and the human health in the area. The tree

Page 61: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

43

plantation programmes will also help to compensate any impacts arising from air pollution due

to vehicular emissions.

Drainage congestion

155. The improvement of the road side drainage including culverts and causeways through

the project is expected to facilitate better water flow, causing higher speed flow during the

rainy season. However, stagnation or blocking of the water flow may occur due to improper

disposal of debris during maintenance activities or ignorance of the public by disposing

garbage in the side drainage. Stagnation of sediments and waste materials will obstruct road

side drainage, culverts and main holes. The PRDA needs to undertake a regular maintenance

of the drainage system to avoid drainage congestions which may cause local flooding, and

ultimately lead to destruction of the road.

Road safety

156. Improvement of the selected roads will provide easy access, increase number of

vehicles and their speed. Therefore enforcement of the speed limits, traffic rules and

regulations as well as installation of warning signs, marking of centre lines, pedestrian

crossings, bus halts etc. should be incorporated to minimize road accidents and enhance the

safety of the vehicles and road users.

Encroachment of the Right of Way

157. Encroachment of road reservation can be taken place any time after the completion of

construction works. Encroachment activities can impact to the road users, vehicles, pavements

and road side drains too. Therefore routine checking from PRDA to remove unauthorized

structures from RoW is necessary. In addition, enforcement of rules and regulations is also

needed to minimize encroachment of the RoW.

Page 62: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

44

Chapter 5 - Institutional Requirements and Grievance Redress Mechanism

5. Institutional Requirements of the Project

5.1. Institutional Arrangements

158. The MLGPC is the Executing Agency (EA) for the project and has the responsibility of

implementing the overall EMP. The Project Implementation Unit (PIU) will be established by PRDA of

NCP. The PIU will be responsible for overall contract administration and the supervision of the

contractor regarding the implementation of Environmental Specifications and Special Environmental

Provisions included in Contract Document. In practice, the detailed implementation of EMP will involve

following parties.

Contractors

Construction Supervision Consultants (CSCs)

Project Implementation Unit

Project Director (PD) of MLGPC

159. The contractors will responsible for implementing the EMP under the day to day supervision of

the Construction Supervision Consultant. The CSCs (Environment Specialist - ES) will be responsible to

provide technical advice and job training to the contractors as well as daily supervision of

implementation of EMP by the contractor and reporting the implementation of EMP of project to PIU on

monthly basis. The PIU that will be assisted by an Environmental Consultant intermittently will review

the CSCs’ reports on implementation of EMP and coordinate with other relevant Government agencies

or LAs to take necessary actions if any environmental impacts could not be mitigated as it was planned

in the EMP or if any additional mitigation measures will be required.

160. The PIU will report the implementation of EMP of each sub-project to the PD at the MLGPC.

The PIU will follow up by preparing an annual report on implementing EMP to the relevant parties such

as CEA and also for ADB. CEA which is the responsible for overall environmental management in the

country, will periodically review the monitoring reports submitted by the PIU and provide guidance and

advice if and when required. The responsibility hierarchy of project implementation is as follows.

Page 63: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

45

Figure 3 Responsibility hierarchy of project implementation

5.2. Capacity Building

161. Capacity building is an integral part of the project and addresses the adequacy of

PRDA institutional capacity regarding social, environment and engineering aspects of the

project.

162. The public consultations sessions conducted with PRDA of the project revealed that

the human and physical resources are in satisfactory level with compared to the PRDD of

Northern Province. However; it is required to strengthen the institutional capacity of PRDA to

implement the proposed project effectively. The relevant staff of the PRDA should be made

aware of the proposed technical framework together with the existing environmental, social

conditions of the project affected areas, policies and legal regulations concerning construction

operations and the associated potential environmental impacts and related mitigation

measures by the MLGPC before commencing the construction. This will ensure sustainable

availability of skilled and empowered human resource throughout the project and for the future

projects as well.

163. The PRDA through PIU shall organize orientation sessions and regular training

sessions for relevant technical and management staff of PRDA, contractor and his staff during

CEA

CSC- Resident

Engineer (RE)

Project Manager

(Contractor)

Environmental Officer (Contractor)

CSCs-

Environment

Specialist (ES)

EA - MLGPC

PD– PRDA

Contractor

PIU

(Safeguards)

PIU

(safeguards)

Page 64: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

46

pre- construction stage of the project. With regard to environmental performance, methods on

implementing and monitoring the EMP, agreements on checklists and reports, methods

maintained by field staff on EMP implementation, activities related to EMoP, preparation and

submission of monitoring reports, etc should be focused. This will ultimately enhance their

capabilities for day to day supervision and implementation of EMP and EMoP with

incorporating social and engineering aspects.

5.3. Grievance Redress Mechanism

164. Grievance Redress Mechanism (GRM) provides an effective approach to resolve any

issues made by affected community on environmental impacts arising throughout the project

cycle. This mechanism will be established by the project proponent, with PRDA to address

grievances presented by Affected Persons (APs). Since most of the environmental impacts are

construction related complaints (issues related to dust, noise and vibration, effect on land, loss

of access, local road network, deteriorating water quality and quantity, soil erosion and safety

issues) managing those is mainly the contractor's responsibility.

165. However, these grievances could be minimized at the initial stage of the project by

careful design, implementation and monitoring of sub-projects and also through sound

communication & awareness among all the stakeholders including APs regarding project

activities. Furthermore, adhering to mitigation measures addressed in EMP by contractor (with

the help of Environmental Officer) under the careful supervision of CSCs /ES and the

representatives of RDA and CEA will minimise construction related grievances.

5.3.1. Grievance Redress Committee

166. This mechanism will be executed through a Grievance Redress Committee (GRC) and

consists of following Members;

A representative from PRDA (Project Director)

A representative from community leader/ Grama Niladhari (GN)

A representative from contractor/ EO/ Project Manager

A representative from CSC (Engineer/ES)

A representative from relevant DSD (Divisional Secretary/Additional Divisional

Secretary)

167. Almost all the stakeholders related to the GRM should be aware and instructed by PIU

regarding the established grievance process, the requirement of grievance mechanism, goals,

benefits, relevant laws and regulations of GRM. They should also be instructed about

procedures of taking/ recording complaints, handling of on-the spot resolution of minor

problems, taking care of complainant and most excellent response to distressed stakeholders.

Page 65: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

47

The Affected community should especially be made aware of the procedure , venue and the

responsible person to contact when making a complain (Wildau. S., et al, 2008)2.

5.3.2. The Process of Grievance Redress Mechanism

168. Complaints of APs can be made as an individual or as a group in verbal or written form

through letters/suggestion boxes and telephone conversation. Received complaints will be

screened to determine if they are eligible to be addressed by GRM. If the complaint is rejected,

the complainant is informed about the decision and the reasons for rejection. If the complaint is

accepted, it can be resolved through GRM of the project (Fig 12). Solutions for complaints

should be handed over to complainant in written form and actions to be taken to mitigate those

impacts should be informed to the responsible institution / individual.

Figure 12 Responsibility hierarchy of resolving public complaints

2 Wildau, S., Moore, C., Atkins, D., and O’Neill, E. 2008. A Guide to Designing and Implementing

Grievance Mechanisms for Development Projects. Office of the Compliance Advisor/Ombudsman,

International Finance Corporation, Washington, D.C.

Complaints by individuals,

Groups, or institutions

Complaints by People’s

representatives: political,

religious, community

GRC Secretary

(Complaints to GRC in written form

GRC meeting

Convey the decision to APs

Decision to be

taken within 3

weeks of

receipt of

complaint

Page 66: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

48

169. When people encounter an issue, first step is submission of complaint to the

Contractor/PM/EO through community leader/GN. If the complaint is simple and the answer is

straightforward, it should be directly provided within 2 days to the compliant.

170. If the reply could not be provided immediately or not within his authority or if the

response for the complaint is at an unsatisfactory level for the complainer, it should be

forwarded to the Grievance Redress Committee A GRC meeting must be convened and an

answer for the complaint should be provided within 3 weeks to the complainant.

Note: Refer to Designing and implementing grievance redress mechanisms, a guide for implementers of

transport projects in Sri Lanka (2010) by ADB for further details.

Page 67: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

49

Chapter 6 - Environmental Management Plan (EMP)

6. Environment Management Plan and Monitoring Plan

6.1. Environment Management plan

171. To ensure that the proposed project would not generate any negative impact on the

environment, the EMP has been prepared as a matrix and attached as Annex B. This was

developed based on best practices for environmental management. The EMP includes the

potential impact as a result of project activities, proposed mitigation measures, the responsible

party to implement and supervise those impacts and the feasible cost measures to be taken to

reduce the potential significant adverse impacts in an acceptable level.

172. There must be professional expertise with the contractor side to prepare Environment

Methods Statement (EMS), based on the EMP which is prepared under the feasibility study.

EMS is a document which is prepared by contractor to declare mitigation measures for

anticipated environmental impacts during pre-construction and construction phase such as

operation of metal quarries, asphalt plants, crusher plants and clearing of land etc. Clearances

and permits which need to be taken from government departments and institutions are also

included in the comprehensive EMS. It also comprises of measures to be taken for

environmental protection, methods for saving energy, reduce wastes and losses, prevention or

minimizing pollution, disposing of pollutants comply with the existing stipulations and laws. The

comprehensive EMS clearly explains that the contractor usually takes action to minimize

environmental impacts during project activities. The organization structure of implementing

comprehensive EMS comprises an environmental supervision department. Thus

environmental protection around the construction site is directly controlled by the technical

department which is usually supervised by a Resident Engineer (RE) and ES of the CSC.

6.2. Environmental Monitoring Plan (EMoP)

173. In addition to the EMP, to ensure that the project would not generate any negative

impact to the overall environment quality, the Environmental Monitoring Plan (EMoP) has been

prepared (Annex C). This includes information on environmental parameters to be monitored,

location, time and frequency, cost for sampling and stage of subproject on which the

monitoring should be conducted. The EMoP will be a useful tool to monitor the implementation

of mitigation measures included to the EMP. Monitoring of the quality of water, air and noise

during the construction stage is a responsibility of the contractor by the approved Government

Agency. All the monitoring activities such as site supervision, removal of trees, material

extraction, verification of permits etc. by the contractor will be supervised by the ES of the

CSC. The environmental monitoring report will be submitted to the PIU of PRDD, which will

include the result of environmental monitoring into its environmental report that will be reported

to the PD at the MLGPC.

Page 68: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

50

174. The criteria for selection of sampling locations for the EMoP are as follows.

Air quality- Environment and public sensitive areas and places where potential

increase of traffic.

Water quality- Stream/tanks/wells and construction sites close to other water

bodies (irrigation canals) where local communities use water or supporting their

lives, and those with available water almost all over the year.

Noise and vibration- Environment and public sensitive areas that might be

affected by the used of heavy equipment.

Page 69: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

51

Chapter 7 - Public Consultation and Information Disclosure

7. Introduction

175. In line with NEA in Sri Lanka, public consultation and information disclosure is

undertaken through public notice prior to the approval by CEA for the particular project.

According to ADB Environmental Guidelines public consultation and information disclosure is

the main activity carried out during the initial stage for an IEE. The aim of the process is to

understand the view point of the public about the project and respond to their concerns and

suggestions during the early stage of the project.

176. Providing information regarding the project objectives, activities, expected outcomes

etc at an early stage to the public, especially for the APs will ensure community awareness

and avoid conveying misinformation to the APs. Furthermore, incorporating environmental

concerns to the decision making process through the public consultation will avoid or minimize

conflict situations that can arise during the construction stage

7.1. Public Consultation

177. Public consultation for the proposed road sections was carried out during the period

from December 2011 to January 2012 (Figure 6.1). During the individual as well as group

discussions APs were brief about the project objectives, expected outcomes, proposed

improvement works, impacts that can be aroused due to the proposed work, grievance redress

mechanism etc. Participants generally expressed their views about the project, current

environmental, social and economic situation of the proposed subproject areas. The list of

participants for the public consultation sessions is provided in Annex D.

Figure 4 Public consultation Walpola (NCANC127)Periyakulam (NCAHD139) and Kudagama

(NCAHC122) villages

Page 70: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

52

7.1.1. Consultation Findings

178. All these roads are very essential link roads to the interior part of Medawachchiya and

Kebithigollewa of Anuradhapura districts. At present these roads are in a deteriorated

condition because of lack of periodic maintenance. Thus rehabilitation and improvement of the

roads are essential to create efficient transportation facility for the general public, thereby

reduce vehicle operation cost and transportation cost. Furthermore, improvement of these

roads will contribute the social and economic development of the region.

179. In general, the existing condition of these roads is in unsatisfactory level for the

transportation. Many of these roads face the problem with large numbers of pot holes, erodible

edges, collapsed causeways, culverts and bridges. Therefore transportation especially during

the rainy season, through these road sections is very difficult due to water stagnation within

the RoW. Thus improvement of roads with sufficient RoWs, CWs and provision of adequate

drainage facilities with adequate diameter based on the hydrological studies in the area is

essential.

180. Although these roads are in dilapidated conditions, people of the project influence

areas including government servants, farmers, businessmen, school children, security forces

and private sector employers, heavily use these roads for their day to day activities. Once

these roads are developed, all the above people will have better access; therefore will be

benefitted by saving their precious time. Furthermore, with compare to the previous situation,

with the improvement of these roads, people can directly access the town areas to engage in a

number of social and economic activities. Other than that new technologies can be transferred

from urban areas towards development of the interior parts of this district. Therefore, all most

all the people in these areas are in favour of welcome the project, because improvement of the

road may create positive impacts to the people living in the area.

181. Majority of the roads proposed under the project are gravel or sandy roads. Therefore,

dust emanation during the dry season cause inconvenience to the road users as well as road

side community. The level of dust emission will increase during the construction period due to

different type of construction activities. Hence, dust suppression measures are extremely

important during the construction phase to minimize public inconvenience.

182. All the proposed roads for the improvement, link with national roads in one side and

with provincial roads in other side through number of rural, agricultural villages. On the other

hand, numbers of rural roads which direct to paddy fields and internal villages starts from

these roads. Therefore once the proposed roads are constructed, they act as main link

Page 71: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

53

between national and rural roads. According to NCPC officers, the proposed ADB project is a

timely intervention in overall development efforts of the province, especially for rural sector

development. Because roads are the basic infrastructure facility that contributes to other

development and directly contribute to poverty elevation in respect of income, employment and

enhancement of basic services. Although PC spends a large sum of money annually, most

goes for carpeting of existing roads. Therefore proper reconstruction of the roads is essential

with other related facilities.

183. Annexure D indicates a summary of public consultations made during the field survey

on selected roads

7.2. Information Disclosure

184. In accordance with ADB’s Information Disclosure policy, the MLGPC will submit the

final IEE report and the EMP to the ADB for disclosure on ADB’s website. This will ensure that

the MLGPC will provide relevant environmental information to ADB Board consideration for

project appraisal.

185. If the IEE carried out in accordance with the ToR (Terms of Reference) provided by the

CEA, Government of Sri Lanka should be made available to the general public in the project

area including affected people and to other stakeholders through DS office, GN office, LAs,

Provincial offices of CEA prior to the project approval. The information should be made

available in a timely manner in three languages (Sinhala, Tamil and English) in the country to

the above stakeholders. This will ensure incorporating affected people’s concerns and inputs

into project design and implementation.

186. During project implementation, project information boards have to be established on

either end of the project corridor displaying the project name, stretch of the road, type of

rehabilitation, time frame, cost of the project, funding agency, implementing agency with other

salient feature of the project. This will ensure further awareness about the project to the

stakeholders including APs.

Page 72: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

54

Chapter 8 - Conclusion and Recommendations

187. The construction activities associated with proposed project not expected to cause

significant environmental impacts to the project affected areas. The potential environmental

impacts that have been identified during the study will be temporary, manageable and will

occur only during pre-construction and construction periods. Therefore the proposed

rehabilitation of the project roads is environmentally acceptable.

188. The development of provincial roads is important for all other development projects

within the province as well as adjacent villagers of 4 other bordering provinces (Northern,

Eastern, North Western and Central) and complementary for on-going road development plans

in the NCP. Additionally road development projects directly contribute to poverty elevation in

respect of income generation, employment, local/forging investments and enhancement of

other social services. Thus proposed ADB funded provincial road project is important to

achieve above targets with rural sector development of war affected areas.

189. The selected subproject roads for the improvement are extremely important for future

development of the area. All selected subproject roads start from National A or B class roads

and 6 roads out of seven end with C or D class provincial roads through number of rural and

agricultural villages.

Egg. NCANC122 is very important road starts from National B class road (B:

283) Medawachchiya - Kebithigollewa and end with National A class road

(A029) Vavuniyawa - Horowpothana. Development of this road is very

essential and economically important i.e. almost all the people in the area are

farmers. Thus their agro and dairy products including vegetable, grains, paddy

and curd could be transported to both sides where the prices are high at

Vavuniyawa, Medawachchiya and Kebithigollewa. This is also act as a bypass

road between A:029 and B:283.

NCAND139 is also important bypass between A014 and A009. Since the road

is located close to district boarder of Vavuniya, this will help the town

development of Poonewa area and Ulukkulama road in Vavuniya district.

NCAHD083 is directed to interior part of the Kebithigollewa i.e. over 15 rural

agricultural villages and over 15% of the total population from Kebithgollewa

DSD.

190. Environment impact and risk associated during the construction phase mainly include

vehicle emissions; diesel emissions from large construction vehicles, equipment, material

processing plants and generators. Release of airborne contaminants including particulate

matter, dust and volatile compounds will be available in the surroundings due to wind. All these

emission causes impacts such as respiratory problems, nuisance to the road users as well as

road side communities. The potential environmental impacts associated with construction

stage are temporary and manageable through adhering to the EMP of the project.

191. Large numbers of small, medium and mass scale mettle quarries, crushers and gravel

mines are located in Medawachchiya and Krbithigollewa DS divisions. Therefore environment

impacts due to emissions from metal quarries, crushers, gravel mines and related transport

Page 73: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

55

activities are in significant level. These two DSDs act as main supplier for above materials to

NCP, NP and EP. Although number of infrastructure development projects is underway in the

NCP including road developments projects, no updated reliable baseline information regarding

water quality, air and noise/ vibration even in the Anuradhapura town of the NCP. Therefore

monitoring of above parameters is recommended during preconstruction stage to establish the

baseline parameters of subproject affected areas of Medawachchiya and Kebithigollewa. This

is essential for repeated checking and monitoring changes of the quality of water, air and noise

during the construction and operation periods. These results should be incorporated with the

contract documentation to establish performance action thresholds, pollution limits and

contingency plans for the contractor’s performance. Adequate budgetary provisions must be

ensured to undertake these monitoring activities.

192. The appropriate category for the NCP roads based on REA checklists of the ADB is

category B. According to BIQs and the Environmental Assessment Guidelines of CEA (Sri

Lanka) subproject roads categorised under un-prescribed category. Since all the construction

activities are restricted to the existing RoW, land acquisition, resettlement activities and

reclamation of paddy fields are not involved. Apart from that none of the project roads are

located within national parks, sanctuaries, important biological habitats or wet lands as

declared by the relevant authorities. Thus a full EIA for these roads is not required according to

the ADB Guidelines.

Page 74: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

56

References

An illustrated guide to the butterflies of Sri Lanka. R.N.Gamage, ISBN 978- 955-50360-

0-9, (2007).Tharanjee Prints, Maharagama.

Asian Development Bank, Designing and implementing grievance redress

mechanisms, a guide for implementers of transport projects in Sri Lanka (2010).

Manila, Philippines.

Asian Development Bank, Policy Paper, Safeguard Policy Statement (2009). Manila,

Philippines

Central Environmental Authority. Environmental Guidelines for Road & Rail

Development in Sri Lanka (1997).

Central Environmental Authority, Environmental Atlas of Sri Lanka (2005).

Central Environmental Authority. National Environmental Act, Subsidiary Legislation,

Copied by the CEA as at 2003.

Department of census and Statistics under the Ministry of Finance and Planning

Statistical Abstract (2010). Colombo, Sri Lanka,

Environmental Safeguards Compliance Manual prepared under the Technical

Assistance Project (TA: 4736-SRI); Capacity Building for Environment & Social Division

(ESD) of the Road Development Authority (RDA), Submitted for Review & Approval to

the Board of Directors, RDA of the Ministry of Highways & Road Development, (June,

2007). Colombo, Sri Lanka,

Initial Environmental Examination Report: Subgroup II, North Central Provincial Roads.

ADB Loan 2080 SRI .Road Project Preparatory Facility Consulting Service for

Feasibility Study and Detailed Engineering Design of Provincial Roads. Cardno

International Pty Ltd, SMEC International Pty Ltd, Engineering Consultants Ltd and

MG Consultants (Pvt) Ltd, (2007) Sri Lanka.

IUCN Sri Lanka and the Ministry of Environment and Natural Resources. The 2007

Red List of Threatened Fauna and Flora of Sri Lanka, (2007). Colombo, Sri Lanka.

xiii+148 pp.

Panabokke, C. R, Soils and Agro Ecological Environments of Sri Lanka (1196).

National Resources Energy & Science Authority Publication.

Resource Profile. Anuradhapura district. District Secretariat Division, (2010).

Anuradhapura District.

Resource Profile. Medawachchiya Divisional Secretariat Division. . Divisional

Secretariat Division, (2010). Medawachchiya

Road Development Authority. Environmental and Social Safeguards Manuals,

Prepared under the Technical Assistance Project (TA 4736-SRI): Capacity Building of

Page 75: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

57

the Environmental and Social Division of the Road Development Authority of The

Ministry Of Highways And Road Development. (2007).Colombo

Wildau, S., Moore, C., Atkins, D., and O’Neill, E. A Guide to Designing and

Implementing Grievance Mechanisms for Development Projects. Office of the

Compliance Advisor/Ombudsman, International Finance Corporation, (2008).

Washington, D.C.

World Conservation Monitoring Centre. Dictionary of the protected areas, Sri Lanka

Final Draft. Protected Areas Data Unit, (December 1988).

Page 76: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Annexure A: Topographic maps of proposed seven provincial roads in Anuradhapura district

Map No

Road no Road name Length (km)

1 NCAHC095 Kebithigollewa – Hendagala

12,90

2 NCAHC122 Ethakada - Etambagaskada – Tonigala

6.80

3 NCAHC126 Dachchidamana – Paranahalmillewa

4.70

4 NCAHC127 Thekkawatha – Pulleliya

5.65

5 NCAHC128 Kirigollewa – Hirallugama

11.50

6 NCAHD083 Kiriketuwewa - Bandaraulpatha – Kapugollewa

20.30

7 NCAHD139 Yakawewa - Mahakoongaskada Rd

13.30

Page 77: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared
Page 78: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared
Page 79: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared
Page 80: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared
Page 81: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared
Page 82: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared
Page 83: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared
Page 84: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared
Page 85: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Annex B: Environment Management Plan for the North Central Provincial roads

Potential Environmental Impact

Mitigation Action Approximate Location

Mitigation Cost

Institutional Responsibility Indicators or Means of Verifications

Standards

Implementa-tion

Supervision

Pre construction and Construction stage

1. Selection of lands for temporally use

Selection of lands in accordance with local laws, regulations and in close consultation

with LAs Identification of lands away from

environmental and public sensitive areas

Provision of adequate compensation for consuming the selected sites to the owners

All sub project roads Cost estimated by the land owners

Contractor PRDA/PIU/ LAs

Public inconvenience, soil erosion, waste accumulation

Technical specification/ local laws, regulations

2. Removal of public utilities

Advance notice to the public about the time and the duration of the utility disruption

Recruitment of well trained and experienced machinery operators, technical officers & labors

Proper coordination and consent from CEB for the removal of electric posts and re-establishment

Throughout the sub project roads where electrical posts need to be shifted.

Cost estimated by CEB

Contractor/ PRDA/ PIU

PRDA / CEB

Damages to the existing utilities, Public complains

Technical specification

3.Extraction, transportation and storage of construction materials

Obtain all permits and licenses required for collection and processing of materials from relevant authorities such as CEA, GSMB, DOF, DWLC, and LAs

Consideration of environmental requirements and guide lines issued by the CEA, GSMB and LAs

Planning of construction activity to ensure that haulage of materials does not take place during night

Construction materials should not exceed the carrying capacity of the trucks

Transport loading and unloading of materials should not cause nuisance to the public

Storage of cement, bitumen, oil and other chemicals on an impervious surface above ground level and should be enclosed

Materials extraction sites, storage yards within the sub project affected areas/ outside area

Engineering cost

Contractor PRDA/ CEA/ CSCs/ LAs/ GSMB/ PHI

Visual inspection/ Increase of vector breeding sites/ Public complains

GSMB Act. Act No 33 of 1992) National Environment Act. No 47 of 1980 Laws and regulations of respective LAs National Emission Standards(1994) and CEA water quality

Page 86: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Potential Environmental Impact

Mitigation Action Approximate Location

Mitigation Cost

Institutional Responsibility Indicators or Means of Verifications

Standards

Implementa-tion

Supervision

ensuring that no storm water flows in to the structure.

Provision of adequate ventilation should be kept to avoid accumulation of fumes and

offensive odor to storage yards. Storage of sand, rubble, mettle bitumen

cement in covered areas to ensure protection from dust, emissions.

Restoration of the material extraction sites once after burrowing

standards National Environmental (Noise Control) Regulations No.1 1996

4. Effect on local road network

Obtain a permit from LAs to use local road network prior construction

Construction materials should not exceed the carrying capacity of the local road network.

provision should be made for repair and restoration, If public roads get damaged

Roads which use for transportation of construction materials.

Engineering cost

Contractor PRDA/ CSCs/ LAs

Visual inspection/ Public complains

Laws and regulations of respective LAs

5. Solid waste disposal and sanitation

Minimize health hazards and environmental pollution based on CEA guidelines.

Selection of disposal site away from public and environment sensitive areas

Re-use of debris and residual spoil materials wherever possible under instruction of Engineers & CSC.

Provision of proper solid waste disposal, sanitation and sewerage facilities to all sites

Dumping of garbage in a hygienic manner under the inspection of PHI in the area.

Minimize/avoid stagnation of water around worker based camps.

Selection of local un-skilled and skilled workers for the proposed construction activities

Labor camps, construction sites, offices, disposal sites and material storage yards.

Engineering and environment cost

Contractor PRDA/ CSCs/ LAs/ PHI/ CEA

Visual inspection/ Environmental pollution Public complains/ Workers health

Laws and regulations of respective LAs

6. Effect on water resources

Awareness of employees on water conservation, pollution and minimization of water usage

All streams, tanks, irrigation canals cross or run parallel

Engineering and environme

Contractor PRDA/ CSCs PIU/

Visual inspection/

CEA water quality standards

Page 87: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Potential Environmental Impact

Mitigation Action Approximate Location

Mitigation Cost

Institutional Responsibility Indicators or Means of Verifications

Standards

Implementa-tion

Supervision

Prevent entering waste water directly in to water bodies.

Storage of toxic and hazardous construction materials at least 500m away from water bodies

Avoid excavation of beds of any irrigation systems or other water bodies.

Introduction of sediment traps/check dams to serve as catch drain from disturbed areas before discharging into waterways

Cleaning of upstream and lead-away channels of cross drainages to maintain a smooth water flow.

Maintaining vehicles and equipment in good condition, to prevent leakage of oil or fuel

Prevention of disrupting community water sources.

to the roads All causeways and culverts construction sites Sub project roads which runs over the tank bunds

nt cost DoI/ CEA Temporally floods Environmental pollution Public complains Workers health Soil erosion, sediment load in streams and canals

7. Soil erosion sedimentation and siltation

Placement of erosion control measures to erodible areas.

Undertake construction activities in erodible sections during dry season.

Limitation of steep cuts and the reduction of slop of cuts.

Treatment of clearing and filling areas against flow acceleration.

Covering of temporary soil dumps with thick tarpaulin sheets until remove from the site

Re-use of top soil generated from construction sites for turfing and tree planting activities.

Intercept and divert clean upslope/run on water around or through the construction site to keep clean and dirty water separate from each other;

Erosion and sediment controls shall be monitored regularly and immediately following

All vulnerable areas for soil erosion Cut and fill areas Culverts and causeways construction sites

Engineering and Environmental cost

Contractor PRDA/PIU/ LAs/ CSC

Visual inspection (Turbidity and sedimentation)

Technical specifications Soil Conservation Act. No 53 of 1951, Amendment in1996

Page 88: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Potential Environmental Impact

Mitigation Action Approximate Location

Mitigation Cost

Institutional Responsibility Indicators or Means of Verifications

Standards

Implementa-tion

Supervision

rainfall and inspections results shall be recorded. The controls shall be maintained or replaced as appropriate. Sediment shall be cleared when sediment traps have reached 50-60% capacity;

Wherever possible during the course of the works, exposed soil areas shall be progressively stabilised or protected by an appropriate method to minimise erosion potential;

All fill shall be sufficiently compacted to minimise erosion potential;

Cut batters shall be formed to a stable slope consistent with soil properties and adequately protected from erosion;

Land shaping operations shall leave the reshaped surface in a roughened condition to encourage infiltration and minimise runoff;

Regraded, cleared or disturbed lands including stockpiled soil materials which shall remain exposed to erosion for a period of 14 days or more shall be rendered erosion resistant within 5 days. Temporary protection shall be provided by use of plastic sheeting or seeding with cover crops, annual grass species or mulch, even if the area shall be subject to further regrading or subsequent construction.

8. Temporary floods

Increase the embankment height of the inundation sections.

Construction of cross drainages with sufficient capacity.

Avoid storage of construction materials and disposal of debris around water resources.

Maintain sheath water flow of drainage system without any blockages/stagnation.

All flood prone areas Causeways and culverts construction sites.

Environmental cost

Contractor PRDA/ DoI/ PDoI/ CSCs/

Visual inspection/ Public complaint Impact to the public

Technical specifications Irrigation act. No, 23 0f 1993

Page 89: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Potential Environmental Impact

Mitigation Action Approximate Location

Mitigation Cost

Institutional Responsibility Indicators or Means of Verifications

Standards

Implementa-tion

Supervision

Provision of temporary earth drains to the construction sites.

Undertaking construction works affecting water bodies/flood plain during dry season.

properties

9. Affect on flora, fauna and their habitats

Awareness of workforce regarding important of fauna, flora and their habitats.

Prevent workforce from fishing, hunting animals and gathering fire wood from soundings.

Removal of road side trees adhering to the CEA guidelines and recommendation.

Decision on tree removal based on Detailed Engineering Design

Marking road side trees subjected to removal and preparation of inventory prior to start clearing.

Valuable timber should be properly stacked and handed over to the DoF or rightfull owners.

Organizing tree planting program in appropriate locations

Selection of the native or endemic saplings for the tree planting programme

All construction areas of sub project roads Removal of trees throughout the sub project road where necessary. Material extraction sites

Environmental cost

Contractor (Under Supervision of PIU)

PRDA/ DWLC/CEA/ DoF CSCs

Impact to the animals and their migration paths Visual inspection

Fauna and Flora Protection Act (1993). Felling of trees (Amendment Act No:01 of 2000 and Act to Amend felling of trees control)

10. Biodiversity conservation and sustainable natural resource management

Awareness of all stakeholders regarding Bio Diversity conservation.

Avoid clearing of natural habitats and replacement of natural vegetation.

Avoid introduction of invasive plants to the project area by means of accidental transport.

Periodic assessment to check the introduction of invasive alien species

Use of natural resources in sustainable manner.

Throughout the sub project roads All material extraction sites

Environmental cost

Contractor (Under Supervision of PIU)

PRDA/ CSCs

Impact to the habitats Visual inspection

Fauna and Flora Protection Act (1993).

11. Disruption of traffic

Provide an advance notice to local communities about the schedule of

All construction sites, roads which use for

Engineering cost

Contractor PRDA/ Local police

Traffic congestions/

Motor Traffic Act. No 14 of

Page 90: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Potential Environmental Impact

Mitigation Action Approximate Location

Mitigation Cost

Institutional Responsibility Indicators or Means of Verifications

Standards

Implementa-tion

Supervision

construction activities

Provision of safe passage/ alternative routes to the vehicles and passengers.

Implementation of traffic management plans in close coordination with local police and public

Installation of traffic warning signs, temporary traffic lights or flagman at the construction sites

Schedule movement of large trucks and plant in off-peak traffic times.

transportation of construction materials.

Public complain/ Accidents

1995, Amendment Act No: 5 of 1998

12. Personal safety

Proper briefing and training of workers on safety precautions, and their responsibilities.

Use of licensed and well trained operators for handling of machinery, equipment and material processing plants

Provision of first aid facilities and emergency transport to the nearest hospital

Provision of protective instruments and clothes to workers, based on their duty

Arranging regular safety checks of workers, vehicles and plants

Establishment of road engineering aspects and sign boards to reduce accidents

Storage of explosive materials in a secure location in a protective way.

All construction sites, material extraction sites, close to public sensitive locations and roads which use for transportation of construction materials.

Engineering cost

Contractor/ Local police

PRDA/ PIU/ Local police/ CSCs

Number of accidents/ Visual inspection/ Public complains

Safety and Health regulations of the Factory Ordinance of Sri Lanka

13. Effect on existing drainages

Obtaining approval from DOI, DS, DoAS prior to diversion, close or blocking of water sources.

Restoration of water bodies to its original status once after construction.

Prevent storage of construction materials and disposal of debris around cross drainages.

Provision of temporally drainage facilities until requires line or earth drains are provided.

Inundation sections, construction sites of causeways, culverts, earth or line drains

Environmental cost

Contractor PRDA/DoI/ DoAS/CSC

Visual inspection, public complaint, local traffic

Technical specifications/ Irrigation act

Page 91: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Potential Environmental Impact

Mitigation Action Approximate Location

Mitigation Cost

Institutional Responsibility Indicators or Means of Verifications

Standards

Implementa-tion

Supervision

Replacement of structurally damaged drainage structures.

14. Impact from dust, noise and vibration

Implementation of National Emission Standards and Noise Control Regulations of CEA for project activities.

Regular maintenance of machinery, equipment and vehicles in a good condition.

Prevent bad odor and offensive smell emanating from chemicals, material processing or other construction activities

Placement of crushers and hot mixed plants away from public and environmental sensitive areas.

Arrangement of construction activities closer to public sensitive locations coordination with the relevant authorities.

Placement of exhaust silencers and noise reduction devices to the road side crushers, construction vehicles and hot mixed plants

Storage of construction materials with proper covering, provision of dust barriers, spraying of water and control of vehicular speed to minimize dust emission.

Throughout the road, material extraction sites/processing plants/public sensitive locations and built up areas. Locations of extraction, transportation and storage of construction materials.

Environmental cost

Contractor PRDA/ CEA CSC/ LAs/

Visual inspection/ public complaint

National Emission Standards (1994) Noise Control Regulations by CEA

Operation Stage

15. Air quality and noise

It is expected to reduce existing dust after surfacing of the roads. Proper alignment and surfacing of the road will help to reduce the vehicular emissions.

Throughout the sub project roads

Maintenance cost determined

by the

PRDA

PRDA PRDA Visual inspection

Technical specifications

16. Drainage Congestions

Regular maintenance of drainage system

Avoid dumping garbage and other spoil material

Throughout the sub project roads

Maintenance cost determined

PRDA/ DoI/ PDoI

PRDA/ DoI/ PDoI

Visual inspection Temporally

Technical specifications

Page 92: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Potential Environmental Impact

Mitigation Action Approximate Location

Mitigation Cost

Institutional Responsibility Indicators or Means of Verifications

Standards

Implementa-tion

Supervision

by the

PRDA

flood Increase of vector breeding sites

17. Safety of road users

Enforcement of speed limits, traffic rules and regulations

Installation of the warning signs.

Provision of bus bays, pedestrian crossings and payments to the appropriate locations

Particular locations of the sub project roads

Cost, determined by the PRDA

PRDA/ Local police

PRDA/ Local police

Number of road accidents Visual inspection Public complaints

Traffic rules and regulations Safety regulations

18. Encroachment of RoW

Enforcement of rules and regulations

Routine checking to remove unauthorized structures

Throughout the subproject roads

Labour cost determined by PRDA

PRDA PRDA Visual inspection

Based on rules and regulations of PRDA

Abbreviations

CEA - Central Environmental Authority CEB - Ceylon Electricity Board CSCs - Construction Supervision Consultants DoAS - Department of Agricultural Services DoF - Department of Forest DoI - Department of Irrigation DWLC - Department of Wildlife Conservation

PIU - Project Implementation Unit PRDA - Provincial Road Development Authority PDoI - Provincial Department of irrigation RoW - Right of Way GN - Grama Niladari

EMP - Environment Management Plan EO -Environmental officer GSMB -Geological Survey & Mines Bureau DS - Divisional Secretory LA -Local Authorities

PHI - Public Health Inspector

Page 93: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Annex C: Common Environmental Monitoring Plan for the NCP roads

Environmental component

Project stage

Parameters to be monitored

Location Frequency Standards Rate (Rs.) Implementation Cost

Implementation Agency

Supervision

1. Air Quality

A. Pre Construction stage

SO2, NO2, CO, Pd, TSPM

Three locations from the sub project affected areas e.g.

Junctions which roads connected to the Class A & B Roads,

Rural agricultural villages,

Locally important environment sensitive areas (Forested, Scrublands, inland water bodies)

A single time /each location

NAAQS of Sri Lanka

Per sample Rs. 100.000

Rs. 300.000 RRDA by engaging approved monitoring agency (GoSL)

PIU, RRDA , LA (EO)

B. Construction Stage

Do Do Two times/ Year/each location

Do Per sample Rs. 100.000

Rs. 600.000 Contractor by engaging approved monitoring agency (GoSL)

PIU, RRDA , LA (EO), CSC

C. Operation Stage

Do Do A single time/each location

Do Per sample Rs. 100.000

Rs. 300.000 PRDA by engaging approved monitoring agency (GoSL)

RRDA , LA (EO)

2. Water Quality

A. Pre Construction stage

EC, TSS, DO, BOD, PH

Oil and grease, Pb E.Coli

Three locations from the sub project affected areas (Rivers, streams, tanks, wells est.) throughout the year

A single time /each location

CEA Water Quality Regulations

Per sample Rs. 10.000

Rs. 30.000 PRDA by engaging approved monitoring agency (GoSL)

PIU, RRDA , LA (EO)

Page 94: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Environmental component

Project stage

Parameters to be monitored

Location Frequency Standards Rate (Rs.) Implementation Cost

Implementation Agency

Supervision

B. Construction Stage

Do

Do Three times /Year/ each location

Do Per sample Rs. 10.000

Rs. 90.000 Contractor by engaging approved monitoring agency (GoSL)

PIU, RRDA , LA (EO), CSC

C. Operation Stage

Do

Do A single time/each location

Do Per sample Rs. 10.000

Rs. 30.000 PRDA by engaging approved monitoring agency (GoSL)

RRDA , LA (EO)

3. Noise

A. Pre Construction stage

Noise level (dB level)

Three locations from the sub project affected areas e.g.

Junctions which roads connected to the Class A & B Roads,

Culvert or causeways construction sites,

Public and environment sensitive areas

A single time/each location Both during day and night

National Environmental (Noise Control) Regulations,

Per sample Rs. 20.000

Rs. 120.000 PRDA by engaging approved monitoring agency (GoSL)

PIU, RRDA , LA (EO)

B. Construction Stage

Do Do Two times/Year/ each location Both during day and night

Do Per sample Rs. 20.000

Rs. 240.000 Contractor by engaging approved monitoring agency (GoSL)

PIU, PRDA , CSC, LA (EO), CSC

C. Operation Stage

Do Do A single time/each location Both during

Do Per sample Rs. 20.000

Rs. 120.000 PRDA by engaging approved monitoring agency (GoSL)

PRDA, LA (EO)

Page 95: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Environmental component

Project stage

Parameters to be monitored

Location Frequency Standards Rate (Rs.) Implementation Cost

Implementation Agency

Supervision

day and night

Total cost Rs 18,30,000

Abbreviations:

CEA- Central Environmental Authority CO- Carbon Monoxide,

CSC- Construction Supervision Consultants DO- Dissolved Oxygen EC-Electrical Conductivity

PRDA Provincial Road Development Authority SO2- -Sulphur Dioxide TSPM- Total suspended Particulate Matter TSS- Total Suspended Solis BOD- Biological Oxygen Demand

EO- Environmental Officer NAAQS- National Air Quality Standards NO2- - Nitrogen Dioxide Pb- Lead PM10-Particulate Matter <10

Page 96: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Annex D: Public Consultation

Name of the road Date of consultation

Place of consultation

Participants & Address Outcomes & Concerns

NCAHC095: Kebithigollewa - Hendagala Road

22nd

& 23rd

December, 2011

Kebithigollewa Handagama Ambagaha-Handiya Kokatigollewa

Mr. I.A. Lathief (Development Officer /Planning), DS office, Kebithigollewa Mr. S. Padmasiri (Three wheeler driver), Handagama Kebithigollewa. Mr. T. Ranbanda (Famer), Handagama, Kebithigollewa. Mr. S. Kumarasiri (Clerk), Handagama, Kebithgollewa. Mrs. G. Somalatha (Famer), Ambagaha-Handiya Pihimbigollewa. Mr. P. Sarath Kumara (Army), Ambagaha-Handiya Pihimbigollewa. Mr. K. H. Herath (Famer), Kokatigollewa, Kebithigollewa. Mrs. Kanthi Herath (Famer), Kokatigollewa, Kebithigollewa.

General view of the people: This is a previously tar laid road section, however currently has converted to highly dilapidated road due to neglected maintenance. Most of the people including government servants, farmers, businessmen and private sector employers from number of villages around Kebithgollewa live beside the road. This is also a link road between Kebithigollewa-Medawchchiya and Medawachchiya – Rathabalagahawewa roads. Therefore, people heavily use this road for their day to day activities with transport difficulties. Apart from that agro products in the area can be transported to Kebithigollewa, Horowupothana or Medawachiya where prices are comparatively higher. Environment pollution resulting from dust during the dry season while water stagnation within the carriage way during the rainy season are the main impacts to the road side community and road users. Thus improvement of the proposed road is essential. Other views and suggestions: The improvement of the road with proper drainage facilities may create positive impacts to the people in the area. This road is being heavily used by the people in and around the Kebithigollewa area, so widening of the existing carriage way and raising of the embankment between paddy field areas and other inundation areas are essential through the project. Construction activities should be carried out during the dry season and attention should be taken to minimize public inconvenience due to dust Vehicle speed should be properly control due to transportation of construction materials and other related activities

Page 97: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Name of the road Date of consultation

Place of consultation

Participants & Address Outcomes & Concerns

Job opportunities should be given through the project to local skilled and unskilled workers

NCANC122: Ethakada - Etambagaskada - Tonigala Road

24th & 25

th

December 2011

Medawachchiya. Puhudivula Divulgaskada Kongollewa Atambagaskada

Mr. W.M.S.N. Wijepala (Administrative officer ) GN/DS, Office, Medawachchiya. Mr. Nimal Ananda (Driver), Puhudivula, Ataweeragollewa. Mrs. R.P. Nanadani, Divulgaskada, Ataweeragollewa. Mr. U.P Nilantha (Famer), Kongollewa, Ataweeragollewa. Mrs. T Balahamy (Famer), 4 km Post, Atambagaskada, Ataweeragollewa. Mrs. R.C. Rupa Chandani (Famer), Atambagaskada, Ataweeragollewa. Mr. P.S Senavirathne (Retired Army), 6 km post, Atambagaskada. Mr. S Thilakarathne (Famer), Ambagaskada,

General view of the people: The proposed section of the road is highly dilapidated (stagnation of water, poor drainages facilities, silted/blocked and structurally damaged culverts, uneven road surface due to soil erosion etc.). Therefore transportation through the proposed section is very difficult. Currently large number of heavy vehicles daily runs through the road for transport of metal from the quarry located close to the end point of the rehabilitated section. Thus people will gain advantage from the rehabilitated section as well as proposed road section as expected. Also people in the area were affected during the prevailed complicit situation due to terrorists. Thus most of the rehabilitation and maintenance activities were not implemented at the proper time. Therefore people expect government will give priority for road development in the area including this road, because two government schools (Lolugaswewa and Puhudivula) and number of rural and agricultural villages are located beside the road with considerable amount of residences. The area is highly polluted due to the activities related to the existing mass scale metal quarry and the transportation of metal through heavy vehicles. E.g. Dust distributed from the quarry is highly impact to the road users and road side community in the area. Other views and suggestions: The improvement of the road section with slightly alignment, widening of existing carriage way and improvement of the drainage facilities may create positive impacts to the road users and road side community. If the rest of the section is rehabilitated people can travel both side of the road, Medawachchiy - Kebithigollewa as well as Vavuniya -

Page 98: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Name of the road Date of consultation

Place of consultation

Participants & Address Outcomes & Concerns

Ataweeragollewa. Mr. Samna Piyathissa (Civil Security Force), Atambagaskada, Ataweeragollewa. Mr. Ananda Jayathissa (Civil Security Force), Atambagaskada, Ataweeragollewa.

Kebithigollewa. Agricultural products can easily transport to the high prizes markets and sell at competitive prices from nearest town areas Good quality daily needs and other equipment can be obtained at reasonable prizes from nearest town areas. Arrangement should be made with the owners of existing metal quarry regarding the future maintenance activities. The construction activities should be handled by skilled project manager/ supervisors with well-trained machinery operators.

NCANC126: Dachchidamana – Paranahalmillewa Road

26th & 27

th

December 2011

Mahakumbukgollewa Kudagama

Mr. T. Danapala (Famer), Mahakumbukgollewa, Punewa. Mr. U. Kapuruhamy (Farmer), Kudagama, Ataweeragollewa. Mr. Sarath Gunarathne (Three wheel driver), Kudagama, Ataweeragollewa. Mrs. Samitha Jayalath Kumari (Farmer), Kudagama, Ataweeragollewa. Mr. N. Pradeep Ananda (Farmer), Kudagama, Ataweeragollewa. Mrs. A Sriyani (Famer),

General view of the people: This is very important road section which, connect A009 road and inner part of the rural agricultural area of Medawachchiya. Development of this road positively affect mainly for the farmers in the area and the children of Paranahalmillewa school. Currently the surface condition of the road is fairly good for the transportation during dry season. However during the rainy season transportation through the road is very difficult due to the stagnation of water in pot holes and muddy situation in several sections. Therefore people along the road and project influence area are in favour of welcome of this project because they think it is an immediate requirement. Other views and suggestions: Proper attention should be taken to avoid dust due to construction related activities. Construction work should not disturb the day to day activities of the people and should be restricted to the dry season. Construction work should be completed within the scheduled time by the contractor without long lasting difficulties to the people.

Page 99: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Name of the road Date of consultation

Place of consultation

Participants & Address Outcomes & Concerns

Kudagama, Ataweeragollewa.

Proper attention should be taken during construction of culverts, because most of the culverts along the road are not properly functioning and inlet level of several culverts do not match with the ground level.

NCANC127: Thekkawatha – Pulleliya Road

2nd

January, 2012

Walpola, Kullikada Wiralmurippu

Mr. H. Ranjith Senanayaka (Businessmen), Kullikada, Medawachchiya. Mr. P.Nimal Ranasinghe (Civil Security force), Kulikkada, Medawchchiya. Mr. K. Upali Senavirathne(Meson), Kulikkada, Medawachchiya. Mr. D.N. Senavirathne (Famer), Kulikkada, Medawachchiya. Mr. K.B. Wijesinghe (Famer), Kulikkada, Medawchchiya. Mr. B. Ranasinghe (watcher), Wiralmurippu, Medawchchiya. Mr. A. Siripala (Famer), Kulikkada, Medawchchiya. Mr. J. Dissanayaka (Driver),

General view of the people: The proposed road section for improvement provides main transportation link to Medawachchiya – Mannar road, Puleliya junction and inland rural agricultural area of Medawachchiya DS division. Also 3 government schools and a rural hospital are available in the area. Therefore development of the road is very important and it provides easy access to Madawachchiya railway station too. However existing situation of the road surface is highly dilapidated. Eg. Existing carriage way is totally damaged in some section. The inundation sections, potholes, erodible sections and water logged areas contribute to further deterioration and increasing the travel time and damaged to the vehicles. Currently public transport service was stopped by the authorities due to poor road condition. Thus improvements of the road is essential to avoid hazardous driving conditions and inconvenient of the people. Other views and suggestions: In general people like to welcome the project and promised to give their support due to the current problems associated with transportation of the road. The improvement of the road will benefit the people, especially the government servants, schooling of children and farmers. If the road condition is good, public transport will facilitate for the government and private sector service as before.

Page 100: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Name of the road Date of consultation

Place of consultation

Participants & Address Outcomes & Concerns

Kullikada, Medawchchiya.

Job opportunities should be offered to the local skilled and unskilled workers as well as to the sub-contractors through the project. Practical solution should be given to the inundation section such as installation of new causeways, culverts, elevation of embankment and reconstruction of existing culverts with sufficient diameter of the pipes.

NCAHC128: Kirigollewa - Hirallugama Road

3rd

& 4th

January, 2012

Kiragaswewa Unagaswewa Moragoda Hirallugama

Mr. K.M Upali (Famer), Keeragaswewa, Medawachchiya. Mr. K. Tikiribanda (Famer), Keeragaswewa, Medawchchiya. Mr. P.B Upali Wadimune (Famer), Unagaswewa, Keeragaswewa, Medawachchiya. Mr. A. Kumara (Civil Security Service), Unagaswewa, Keeragaswewa, Medawachchiya. Mr. Susantha Harischandra (Famer), Moragoda, Ataweeragollewa, Medawachchiya. Mr. R. Nilantha (Driver), Hirallugama, Medawachchiya.

General view of the people: This is very important rural agricultural road located in the Kebithigollewa area. Since this is an agricultural area, people need fairly good road for transportation of their products (paddy, vegetables and B anion) to the nearby towns with minimum impact to the vehicles and with reasonable cost. There are 4 different sections of the proposed road runs through the tank bunds which located along the road and some are through their spills. The CW of the tank bunds are not sufficient for the vehicles which are used for the different activities. However widening of the road is also a problem due to tank bunds. During the rainy season, water runs across the road due to above spills. This situation is highly inconvenient to the people and they want to find an alternative road during heavy rains. Furthermore the existing cause ways close to the spills are not in good condition. So rehabilitation or replacement of these cause ways is needed through the proposed project. Other views and suggestions: Widening of the existing carriage way, surfacing of the road with DBST, improvement of the culverts and causeways etc. will avoid transport difficulties, reduce travel time and cost for transportation. Alternative access should be provided when construction over the existing tank bunds and causeways (spills).

Page 101: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Name of the road Date of consultation

Place of consultation

Participants & Address Outcomes & Concerns

Mr. M.M Rathnayaka (Busnessman), Hirallugama, Ataweeragollewa.

Since this area obtained significant amount of rain, it is important to improve existing culverts and causeways as much as possible before the rainy season. Avoid storage of any construction materials along the tank bunds and restriction of the construction work over the tank bunds during the rainy season

NCAHD083: Kiriketuwewa - Bandaraulpatha - Kapugollewa Road

5th & 6

th

January, 2012

Kebithigollewa Horawapathana Garandiulpotha Unawatulawa Sinhala ataweeragollewa Krulugama

Mr. P.R.Thilakaratne, DS/Kebithigollewa Mr. M.A.H.B. Jayasundara, Asst. Director.Plannig/ Horawapathana

Mr. A. Ariyapala (Famer),

Garandiulpotha,

Kebithigollewa.

Mr. P. Rupawathee

(Businessmen),

Unawatulawa,

Kebithigollewa.

Mr. A. Rajarathne

(Mechanics), Sinhala-

Ataweeragollewa,

Kebithigollewa.

Mr. V.B Ranbanda

(Farmer), Kalawediulpotha,

General view of the people: Although initial section is recently rehabilitated by the PRDA, it is highly in un-satisfactory level due to present situation. Considerable numbers of pot holes can be seen throughout the rehabilitate section and fill with water during the rainy day. Therefore, it is difficult to ride/ drive bicycles and vehicles through this section. Since the project affected area is located considerably away from main markets in the area (Kebithigollewa and Horowpothana) majority of the people suffer due to existing situation of the road and lack of transport facility. Therefore, people think, current project will avoid those types of conditions in the future. Most of the causeways and bridges in the end section of the road have already been properly constructed by the PRDA. However, rehabilitation of the road is essential considering all hydrological investigations, since this area is highly erodible due to over flowing of seasonal tanks, natural flow paths, lack of earth and cross drainages. Other views and suggestions: Since number of seasonal tanks, paddy fields, small water streams and irrigation canals are located beside/through the road improvement activities with proper drainage facilities may create positive impacts to the existing environment and project affected communities.

Page 102: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Name of the road Date of consultation

Place of consultation

Participants & Address Outcomes & Concerns

Pathtewa Weerasole

Krulugama, Kebithigollewa.

Mr. T, M Ariyawansa

Gamini (Meson),

Kalawediulpotha,

Kurulugama,

Kebithigollewa.

Mr. U. Upali Herath

(Meson), Kelawediulpotha,

Kurulugama,

Kebithigollewa.

Mr. Nishantha Vijaya

Kumara (Famer),

Kelawediulpotha,

Kurulugama,

Kebithigollewa.

Mr. M. Rahuman

(Businessmen),

Anaulandewa,

Kebithigollewa.

Mr. N.A.M Rasul

(Mechanics), Pathtewa,

Kebithigollewa.

Mr. N.R. Smile (Famer),

Paththewa, Kebithigollewa.

Construction activities should be carried out during dry season and attention should be taken to minimize public inconvenience due to dust. Vehicle speed should be properly controlled due to transportation of construction materials and other related activities. Job opportunities should be offered to local skilled and unskilled workers through the project.

Page 103: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Name of the road Date of consultation

Place of consultation

Participants & Address Outcomes & Concerns

Mr. R. T. Uduma lebbe

(Farmer), Weerasole,

Kebithigollewa

NCAND139: Yakawewa - Mahakoongaskada Road

7th January,

2012 Yakawewa Periyakulam

Mr. P. Tilakasiri (Farmer),

Yakawewa,

Medawachchiya.

R. T Gunathilaka (Farmer),

Yakawewa,

Medawachchiya.

M. Darmasena (Civil

Security) Periyakulam,

Medawachchiya.

Mr. T.S wikramasinghe

(Farmer) Periyakulam,

Medawachchiya.

Mr. D. Padmasiri (Civil

Security) Periyakulam,

Medawachchiya.

Mr. R. Kumarasinghe (Civil

Security) Periyakulam,

Medawachchiya.

Mr. M. Dingiribanda

(Farmer), Periyakulam,

Medawachchiya.

General view of the people: The improvement of the road will provide number of benefits to the road uses as well as road side community. This is very important road section, because people in and around five main villages (Katukeliyawa, Periyakulam, Yakawewa, Mahakongaskada and Thanniyan kualm) use Periyakulam temple and Gaminiwewa Governmrnt School for their religious and schooling activities. In addition this road section is important as an alternative road to travel A009 and A014 roads with minimum traffic & short distance without reaching to the Medawachchiya town. This is also an important link road between number of villages located in Mannnar and Anuradhapura districts. Apart from that, since the road is close to district boarder of Vavuniya, it was badly affected during the war time. Therefore surfacing and other road furniture should be properly developed. This will also help the town development of Poonewa area and Ulukkulama road in Vavuniya district. Other views and suggestions: The positive impacts due to project include easy transportation of agricultural products to the nearest towns, schooling of the children, day to day activities of the farmers, security forces, government and private sector servants etc. This road is being heavily used by the people in and around the area between A009 & A014 roads. Thus construction activities should be carried out with a minimum impact to the road side communities and road users. Phase construction is one suggestion

Page 104: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Name of the road Date of consultation

Place of consultation

Participants & Address Outcomes & Concerns

Mahakongaskada

Mr. S. Rajakaruna

(Farmer), Periyakulam,

Medawachchiya.

Mr. K.B Jayathilaka

(Farmer), Periyakulam,

Medawachchiya.

Mr. S. Siripala (Farmer),

Periyakulam,

Medawachchiya.

Mr. A. Lasantha Aberathne

(Farmer),

Mahakongaskada, Punewa.

Mr. S.Ananda Kumara

(Army officer),

Mahakongaskada, Punewa,

Number of roads located around the proposed project road, especially rural and other PC, will be used by the contractor for transportation of construction materials. (Eg. In general, contractors select gravel mining sites very close to the sub project area). However at the end of project activities, these roads become highly dilapidated situation and contractors do not engage in rehabilitation activities of those roads. The existing carriage way of the existing tank bunds are not sufficient to move two vehicles at opposite directions Therefore, widening existing tank bunds located through the road is important. Majority of the people in the area are farmers. Since the farming activities are seasonal lack of income generation activities during the rest of the year is a problem faced by the community. Therefore, If job opportunities can be allowed through the project, villages can actively participate to the project related activities.

Page 105: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Attachment 1

Terrestrial and Aquatic Floral species recorded in subproject affected areas of NCP

Abbreviations:

HA: Habit TS: Taxonomic status CS: Conservation status T: Tree E: Endemic

TR: Threatened S: Shrub G: Grass N: Native H:Herb

I-Introduced C: Climber or Creeper

Family Species Local Name Habit TS

Amaranthaceae

Alternanthera sessilis Mukunu Wenna H N

Aerva lanata Polpala H N

Anacardiaceae

Anacardium occidentale Cadju T I

Lannea coromandelica Hik T N

Mangifera indica Amba T I

Spondias dulcis Amberella T I

Annonaceae

Annona glabra Wel Attha T I

Alstonia macrophylla Havari Nuga T I

Alstonia scholaris Ruk Attana T N

Cerbera odollam Gon Kaduru T N

Nerium oleander Kaneru H I

Plumeria rubra Araliya S N

Thevetia peruviana Kaduru T N

Aponogetonaceae Aponogeton crispus Kekatiya H N

Araceae

Alocasia macrorrhizos Habarala H I

Colocasia esculenta Gahala H N

Lagenandra sp. Ketala H E

Alocasia macrorrhiza Habarala H N

Lasia spinosa Kohila H N

Arecaceae

Areca catechu Puwak T N

Cocos nucifera Pol T N

Phoenix pusilla Indi S N

Caryota urens Kitul T N

Asclepiadaceae Calotropis gigantea Wara S N

Asparagaceae Asparagus racemosus Hathawariya C N

Asteraceae

Eupatorium odoratum Podisinnamaran S I

Mikania cordata Watu Palu C N

Vernonia cinerea Monara Kudumbiya H N

Bombacaceae Ceiba pentandra Pulun T I

Boraginaceae Cordia sp Lolu T N

Page 106: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Family Species Local Name Habit TS

Cactaceae Opuntia dillenii Pathok H I

Caricaceae Carica papaya Gas Labu T I

Clusiaceae Mesua ferrea Na T N

Colchicaceae Gloriosa superba Niyangala C N

Combretaceae

Terminalia arjuna Kumbuk T N

Terminalia catppa Kottamba T N

Terminalia bellinica Bulu T N

Convolvulaceae Ipomoea aquatica Kankung C N

Ebenaceae Diospyros malabarica Thimbiri T N

Euphorbiaceae

Bridelia retusa Keta Kela T N

Macaranga peltate Kenda T N

Manihot esculenta Maiokka S I

Manihot glaziovii Gas Maiokka T I

Ricinus communis Beheth Endaru S I

Drypetes sepiaria Weera T N

Phyllanthus polyphyllus Kuratiya T N

Croton laccifer Keppetiya S N

Fabaceae

Adenanthera pavonina Madatiya T I

Albizia saman Para Mara T I

Delonix regia May Mara T I

Desmodium heterocarpon Et Undupiyali H N

Desmodium triflorum Undupiyali H N

Erythrina variegata Erabadu T N

Gliricidia sepium Weta Mara T I

Gliricidia seplum Ginisiriya T I

Leucaena leucocephala Ipil Ipil T I

Mimosa pudica Nidi Kumba H I

Tamarindus indica Siyabala T I

Abrus precatorius Olinda C N

Cassia flstula Ehela T I

Bauhinia racemosa Maila T N

Cassia auriculata Ranawara T N

Lamiaceae Hyptis suaveolens Madurutala H I

Lauraceae Alseodaphne semicarpifolia Wewarana T N

Malvaceae

Hibiscus tiliaceus Beli Patta T N

Thespesia populnea Gansurya T N

Martyniaceae Martynia annua Nagadarana H I

Page 107: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Family Species Local Name Habit TS

Meliaceae

Swietenia macrophylla Mahogani T I

Azadirachta indica Kohomba T N

Moraceae

Artocarpus hetarophyllus Kos T I

Artocarpus incisus Del T I

Ficus religiosa Bo T I

Ficusbenghalensis Nuga T N

Musaceae Musa x paradisiaca Kesel T I

Myrtaceae

Psidium guajava Pera T I

Syzygium caryophyllatum Dan S N

Syzigium cumini Madan T N

Pandanaceae Pandanus kaida Wetake S N

Poaceae

Bambusa vulgaris Una T N

Oryza sativa Wi G N

Themeda cymbaria Mana G N

Pontederiaceae Eichhornia crassipes Japan-Jabara H I

Rutaceae

Chloroxylon swetenia Burutha T N

Aegle marmelos Beli T I

Limonia acidissima Divul T N

Murraya koenigii Karapincha T N

Mitragyna tubulosa Helamba T N

Rhamanaceae Ziziphus oenoplia Eraminia C N

Salviniaceae Salvinia molesta Salvinia H I

Sapindaceae

Filicium decipiens Pihimbiya T N

Schleierera oleosa Kone T N

Sapotaceae

Madhuca longifolia Mi T N

Manilkara Hexandra Palu T N

Solanaceae Solanum melangena Elabatu H N

Tiliaceae

Muntingia calabura Jam T I

Berya cordifolia Halmilla T N

Typhaceae Typha angustifolia Hambupan S N

Urticaceae Trema orientalis Goda kirilla T N

Verbenaceae

Lantana camara Ganda Pana S I

Tectona grandis Tekka T I

Vitex pinnata Mille T N

Gmelina asiatica Demata T N

Page 108: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Terrestrial and aquatic faunal species found in subproject affected areas of NCP..

Abbreviations

Phylum/Family/ class Species name Common name Status

Class- Insecta

Order: Odonata Dragonflies

Family: Libellulidae Neurothemis tullia Black velvet wing Indigenous

Rhyothemis variegata Variable glider Indigenous

Order: Lepidoptera Butterflies

Family - Papilionidae Papilio polymnestor Blue mormon Indigenous

Pachliopta hector Crimson rose Indigenous

Family - Pieridae Prioneris sita Painted saw-tooth Indigenous

Appias albino Common albatross Indigenous

Catopsilia pomona Lemon emigrant Indigenous

Eurema brigitta Small grass yellow Indigenous

Eurema hecabe Common grass yellow Indigenous

Family - Nymphalidae Parantica aglea Glassy tiger Indigenous

Danaus genutia Common tiger Indigenous

Euploea core Common crow Indigenous

Junonia lemonias Lemon pansy Indigenous

Junonia iphita Chocolate soldier Indigenous

Hypolimnas misippus Danaid Eggfly Indigenous

Neptis hylas Common sailor Indigenous

Acraea violae Tawny costor Indigenous

Melanitis leda Common evening brown Indigenous

Orsotriaena medus Nigger Indigenous

Ypthima ceylonica White four-ring Indigenous

Class- Amphibia Amphibians

Family – Bufonidae Bufo melanostictus Common toad Indigenous

Euphlyctis cyanophlyctis Skipper frog Indigenous

Duttaphrynus melanostictus Common house toad Endemic

Euphlyctis hexadactylus Sixtoe green frog Indigenous

Family – Ranidae Limnonectes limnocharis Common paddy field

frog

Indigenous

Family -

Dicroglossidae

Fejervarya limnocharis Common paddy field

frog

Indigenous

Molluska Mollusks

Family: Achatinidae Achatina fulica Exotic

Family: Ariophantidae Cryptozona bistrialis Indigenous

Class- Ostecthyes Bony fishes

Page 109: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Family - Poeciliidae Gambusa affinis Guppy Exotic

Family - Cichlidae Oreochromis mosambicus Tilapia Exotic

Oreochromis niloticus Tilapia Exotic

Family - Channidae Channa ara Giant snakehead Endemic/ Vulnerable

Channa striata Murrel Indigenous

Class – Reptilelia Reptiles

Family – Agamidae Calotes calotes Green garden lizard Indigenous

Calotes versicolor Common garden lizard Indigenous

Family- Gekkonidae Hemidactylusbrookii Spotted house gecko Indigenous

Hemidactylus frenatus Common house-gecko Indigenous

Family - Bataguridae Melanochelys trijuga Parker's black turtle Indigenous

Family - Testudinidae Geochelone elegans Indian star tortoise

Taraka ibba

Indigenous

Vulnerable

Family- Elapidae Naja naja Cobra Indigenous

Family - Trionychidae Lissemys punctata Kiri ibba Indigenous

Vulnerable

Family - Varanidae Varanus bengalensis Land monitor Indigenous

Varanus salvator Water monitor Indigenous

Family - Viperidae Echis carinatus Vali polonga Indigenous

Vulnerable

Daboia russelii Russell’s viper Indigenous

Family- Boidae Python molurus Indian Python Indigenous/

Threaten

Class- Aves

Birds

Family – Accipitridae Accipiter badius Shikra Indigenous

Haliastur indus Brahminy Kite Indigenous

Haliaeetus leucogaster White bellied sea eagle Indigenous

Spilornis cheela Crested serpent eagle Indigenous

Family – Alcedinidae Alcedo atthis

Common kingfisher Indigenous

Ceyx erithacus Oriental dwarf kingfisher Indigenous

Family- Apodidae Cypsiurus balasiensis Asian Palm Swift Indigenous

Family – Ardeidae Ardeola grayii

Pond Heron

Indigenous

Ardea cinerea Grey heron

Indigenous

Ardea purpurea Purple heron Indigenous

Nycticorax nycticorax Night heron Indigenous

Bubulcus ibis Cattle Egret Indigenous

Butorides striatus Little green heron Indigenous

Casmerodius albus Great egret Indigenous

Mesophoyx intermedia Intermediate Egret Indigenous

Page 110: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Egretta garzetta Little Egret Indigenous

Family –Bucerotidae Ocyceros gingalensis Sri Lanka grey hornbill Endemic

Family- Burhinidae Burhinus oedicnemus Eurasian thich knee Indigenous

Family – Capitonidae Megalima rubicapilla Small barbet Indigenous

Family –

Centropodidae

Centropus sinensis Greater Coucal Indigenous

Family- Cerylidae Ceryle rudis Pied kingfisher Indigenous

Family – Charadriidae Vanellus indicus Red-wattled Lapwing Indigenous

Family – Cisticolidae Prinia socialis Ashy Prinia Indigenous

Family – Columbidae Chalcophaps indica Emerald Dove Indigenous

Columba livia Domestic Pigeon Indigenous

Ducula aenea Green Imperial Pigeon Indigenous

Streptopelia chinensis Spotted Dove Indigenous

Family – Coraciidae Coracias benghalensis Indian Roller Indigenous

Family – Corvidae Corvus macrorhynchos Large-billed Crow Indigenous

Corvus splendens House Crow Indigenous

Dicrurus macrocercus Black Drongo Indigenous

Corvus splendens Grey necked crow Indigenous

Dicrurus caerulescens White-bellied Drongo Indigenous

Eudynamys scolopacea Asian Koel Indigenous

Family – Dicaeidae Dicaeum erythrorhynchos Small flower pecker Indigenous

Family – Estrididae Lonchura Malacca Black headed Munia Indigenous

Family – Halcyonidae Halcyon capensis Stork billed kingfisher Indigenous

Halcyon smyrnensis White throated kingfisher

Indigenous

Family –

Hemiprocnidae

Hemiprocne coronata

Crested Treeswift

Indigenous

Hirundo rustica

Barn Swallow

Indigenous

Pycnonotus luteolus White-browed Bulbul Indigenous

Family –Nectariniidae Dicaeum erythrorhynchos Pale-billed Flower pecker

Indigenous

Nectarina lotenia Loten’s Sunbird Indigenous

Nectarina zeylonica Purple-rumped Sunbird Indigenous

Nectarina asiatica Purple Sunbird Indigenous

Family – Laniidae Lanius cristatus Brown shrike Migrant

Family –

Magalaimidae

Megalaima zeylanica Brown-headed Barbet Indigenous

Family – Meropidae Merops philippinus Blue tail bee eater Indigenous

Family –

Muscicapidae

Aegithina tiphia Common Iora

Indigenous

Copsychus saularis Oriental Magpie Robin

Indigenous

Saxicoloides fulicata Indian Robin Indigenous

Family – Picidae Dinopium benghalense Red backed woodpecker

Indigenous

Family – Passeridae Lonchura striata White-rumped Munia Indigenous

Passer domesticus House sparrow Indigenous

Family –

Phalacrocoracidae

Phalacrocorax niger Little Cormorant Indigenous

Indian cormorant Indigenous

Page 111: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Family – Phasianidae Gallus domesticus Domestic fowl Exotic

Gallus lafayetii Sri Lanka Jungle fowl Endemic

Pavo cristatus

Indian Peafowl Indigenous

Dendrocygna javanica Lesser Whistling duck Indigenous

Family – Pittidae Pitta brachyuran Indian pitta Migrant

Family- Podicipedidae Tachybaptus ruficllis Little grebe Indigenous

Family – Psittacidae Psittacula krameri Rose-ringed Parakeet Indigenous

Family –

Pycnonotidae

Pycnonotus cafer Red-vented Bulbul Indigenous

Family- Floceidae Ploceus philipinus Baya Weaver Indigenous

Family-Reliday Amaurornis phoenicurus White-breasted Water hen

Indigenous

Porphyrio porphyria Purple swamp hen Indigenous

Gallinula chloropus Common moorhen Indigenous

Family – Sturnidae Acridotheres tristis Common Myna Indigenous

Family – Sylviidae Orthotomus sutorius Tailor bird Indigenous

Turdoides affinis Yellow-billed Babbler Indigenous

Pellornum fuscocaoillum Sri Lanka Brown capped Babbler

Endemic

Family –

Threkiornithidae

Mycteria leucocephala Painted Stork Indigenous

Anastomus oscitans Asian openbill Indigenous

Class- Mammalia Mammals Indigenous

Family – Pteropodidae Pteropus giganteus Flying fox Indigenous

Rousettus leschenaultia Dog faced fruit bat Indigenous

Cynoptrrus sphinx Short nosed fruit bat Indigenous

Family –

Cercopithecidae

Semnopithecus vetulus Purple-faced leaf monkey

Endemic

Macaca sinica Sri Lanka toque monkey Endemic

Semnopithecus priam Grey langur Indigenous

Family – Canidae Canis familiaris Domestic dog Exotic

Family – Felidae Felis catus Domestic cat Exotic

Family – Herpestidae Herpestes smithii Black-tipped mongoose Indigenous

Family – Bovidae Bubalus bubalis Water buffalo Exotic

Bos indicus Domestic cattle Exotic

Family – Sciuridae Funambulus palmarum Palm squirrel Indigenous

Ratufa macroura Giant Squirrel Indigenous

Family – Leporidae Lepus nigricollis Black-naped hare Indigenous

Family – Tragulidae Moschiola kathygre Sri Lanka pigmy mouse-deer

Endemic

Family – Hystricidae Hystrix indica Procupine Indigenous

Family- Soricidae Suncus murinus Musk shrew Indigenous

Family – Muridae Rattus rattus House rat Indigenous

Mus musculus House mouse Indigenous

Bandicota indica Malabar bandicoot Indigenous

Family- Canidae Canis aureus Sri Lanka jackal Indigenous

Family- Felidae Felis chaus Jungle cat Indigenous/TR

Family- Mustellidae Lutra lutra Indian otter Indigenous/TR

Page 112: Sri Lanka: Northern Road Connectivity Project Additional ...€¦ · Sri Lanka: Northern Road Connectivity Project – Additional Financing North Central Provincial Roads Prepared

Family- Viverridae Viverricula indica Ring taild civet cat Indigenous

Family - Elephantidae Elephas maximus Elephant Endemic Vulnerable

Family – Cervidae Axis axis Spotted deer Indigenous

Family – Suidae Sus scrofa Wild boar Indigenous


Recommended