SRI SATHYA SAI NATIONAL PURE DRINKING WATER MISSION
INSTALLATION & MANAGEMENT
1
A PUBLICATION FROM ALL INDIA TECHNOLOGY DIVISION
July 2015
STEPS IN SETTING UP ‘WPS’
2
Survey• Water Vows, Villager Involvement, Infra
Prepare• Villager Motivation & Trust, Report, Funding
Deploy• Village Committee, Reviews
Survey
3
First Visit to the Village• Start the meeting with a heartfelt Prayer
• Explain Bhagawan’s mission briefly-Water Projects , Hospitals, Educational Institutions and other services.
• Explain the spirit of volunteerism in the form of
Sevadal Services and that we expect nothing from them.
• That we believe in the concept of “Manava Sevaye Madhava Seva”
• Clearly detail the purpose of your visit – that we have come only to organize provision of pure drinking water for their good health
Survey
4
First Visit to the Village• Tell them there is no need to donate
money. Seek only their co-operation and Shrama-Dhaan
• Talk about the ill effects of drinking contaminated water. Related health issues.
• Motivate them with narratives of great transformation in other villages because of clean drinking water
• Tell them the cost would be only Rs 2 per 20 liters per day as against Rs 15 to Rs 20 per Lit in market
Survey
5
First Visit to the Village• This cost of Rs 2 would be sufficent to
meet operational costs – Salary, Electricity, Maintenance, Repairs etc.
• In addition they would be able to save enough money to carry out welfare programs in their village, like providing food to the poorest of poor and elderly, medical needs, educational needs, shelter and for festivals of the village
Survey
6
Need Identification – Analysing Water• Take water samples in one litre clean
pet bottles from various sources in the village.
• It is important to lable the bottle properly with date and source location
• Identify a recognized analytical lab – Public or Private
• Send the samples for analysis to determine if they are contaminated
Survey
7
Need Identification – Analysing Water• Analyze for Fluoride, Total Dissolved
Solids, Hardness, Arsenic, Bacteria, Iron etc
• Send the Analysis report to the All India Techno Group Coordinator for evaluation
• The Techno group will determine the type and capacity of the plant, which is normally calculated on the basis of 5 liters of water per person per day
Survey
8
Resources Identification• Note the time when Single and 3-Phase
power supply is available and enquire about voltage fluctuations
• Map the number of water sources in the village. Make sure they are sufficient and reliable?
• Check for any old building room of size – 12x10 or 12x14 ft is available Or a suitable site for constructing a room. Try and use existing infrastructure to limit costs
• Identify responsible and active elders and youth of the village. Involve them from the start
9
Role of Techno Group• The Techno group will determine the
type and capacity of the plant, which is normally calculated on the basis of 5 liters of water per person per day
• Techno group prepares a comprehensive report on viability and fund need.
• It will contain the details of funding by Central and State trusts
• The State trust/SSSO to supervise the civil works, electrical works at site.
Prepare
10
Role of Techno Group• Remember the Central Trust will
release funds only when the State Trust confirms completion of Infrastructure site works.
• The report will be sent to All India President for coments and approval
• Once approved by AIP, the Techno Group Coordinator will visit the identifed village
• A Construction plan and Cost Estimate will be made with the approval of the concerned State President
Prepare
11
Prepare
Gaining Villager’s Confidence and Trust• Conduct Sarva Dharma Bhajans/Nagar
Sankaeertan
• Conduct Medical camps or take up Service Projects
• If possible take them to the nearest WPS to get a good first hand experience of the project and its benefits
12
Prepare
For the Water Purification Plant• Identify a water source or two close
to the plant.
• The plant itself should be in the middle of the village, convinient for all
• Involve the villagers in doing both small and big tasks for the plant. Make them feel its their own
13
DeployVillage Committee• Form a village Water Committee
comprising men, women and youth- two each
• Member of the Sri Sathya Sai Seva Organisation or anyone associated with the Organisation should stay away from all financial transactions and nomination of persons.
• The bank account itself should NOT be associated with Bhagawan’s name in any form
• Sevadal’s role would be limited to reviews once the plant is operational
14
DeployInauguration of the Plant • Once the plant is setup ensure it is
running well by doing several dry runs and wet runs.
• A person from the village should be employed to take care of the complete operations of the plant on a day-to-day basis
• For the inauguration itself, make the mood festive, invite the local collector and other Govt officials
• Reiterate our purpose of doing this, the benefits they would see.
And gracefully step aside for Swami’s Grace to flow in the form of Sai Ganga.
COSTING
15
Specifications:
• Capacity : 1000 Liters/hour • For 2000/2500 people a day• 10 hours of working-Can be increased
by needCost of Equipment (A):
• 3.06 Lakhs with smart card system• To be borne by Central Trust • Includes - Taxes, Installation, Tanks• Excludes – Transportation and any
Insurance
COSTING
16
Cost of Infrastructure (B):
S.N0
DESCRIPTION
1000 Lt REMARKS
01 Building 1,65,000
12X10 -14X12 ft Room
02 Civil Works 15,000
Tiling-fill area-Paints
03 Electricals 5,000
Meter/MCB/cables
04 Transport Actual
To the site location
05 Extras 5,000
Miscellaneous
Total (in Rs)
1,90,000
COSTING
17
Total Cost of the facility (A+B):
S.N0
DESCRIPTION 1000 Lt
500 Lt REMARKS
01 Plant Cost 3.06,860
Funds - CT
02 Infrastructure Cost
1,90,000
Funds -CT
03 Total (in Rs) 4,96,860
<5 Lakhs• The infra cost can be reduced to Rs
80,000 if the village provides a small building, even if it is old.
• Therefore we will make our efforts in this direction to save cost.
• We can make a site decision on this subject.
COSTING
18
Maintenance CostsS.N0 DESCRIPTION HEAD OF ACCOUNT-1000 LIT
PLANTOperating at 70% capacity off take
UNITS
01 Assumption 70% Of Utilization-of 10,000 of capacity
7000 Lit/Day
02 Operations in a Day ( Can be Increased) 10 hrs
03 Operator Salary- Rs 3500 Pm- Rs116 A Day 116
04 Cartridges- Rs 600 /Month OR Rs 20/DAY 20
05 Power/Day=3 Kwx0.70 Factor x 10 hrs x Rs7/kwh
147
06 Membranes @ Rs 1,00,000/30 Months - @Rs 111/Day
111
07 Annual Maintenance Cost - Rs 15000/YEAR 42
Total Operating & Maintenance Cost Per Day (in Rs)
436
COSTING
19
Revenue – Cost = Welfare FundRevenue/Day = Rs2 per day per home X 500 homes @ 70%
Rs 700
Maintenance Costs per day Rs (436)
Net Savings per Day in Village Welfare Fund
Rs 264
Annual Projected Welfare Fund in Account
Rs 95,040
Most important condition for success90% of the village must opt for usage