Page 1 of 1 SSO 700 STF Disinfection Improvements Project ID 10320085 Date Issued: March 5, 2020 ADDENDUM NO. 1 This addendum will only be distributed via e-mail, but will remain available for viewing on the MSDGC website at www.MSDGC.org on the project-specific web page. No hard copy will follow. NOTE: Please be sure to enter the TOTAL NUMBER of Addenda issued on the ‘Official Bid Form’ contained in the Bid Document prior to submitting your bid. The attention of all bidders is directed to the following additions and/or deletions to the Contract Documents. ADDED ITEMS◄ ARE UNDERLINED AND DELETED ITEMS ARE STRUCK THROUGH The Contract Documents for the above referenced project are amended and revised as follows: Attached are the Pre-Bid Meeting attendance sheet and notes
Transcript

Page 1 of 1

SSO 700 STF Disinfection Improvements Project ID 10320085

Date Issued: March 5, 2020

ADDENDUM NO. 1

This addendum will only be distributed via e-mail, but will remain available for viewing on the MSDGC website at www.MSDGC.org on the project-specific web page. No hard copy will follow. NOTE: Please be sure to enter the TOTAL NUMBER of Addenda issued on the ‘Official Bid Form’ contained in the Bid Document prior to submitting your bid. The attention of all bidders is directed to the following additions and/or deletions to the Contract Documents. ►ADDED ITEMS◄ ARE UNDERLINED AND DELETED ITEMS ARE STRUCK THROUGH The Contract Documents for the above referenced project are amended and revised as follows:

Attached are the Pre-Bid Meeting attendance sheet and notes

Pre-Bid MeetingMarch 2, 2020

SSO 700 STF Disinfection Improvements Project

PROJECT ID 10142070

• Introductions• Bid and Construction Schedule• Electronic Bidding• Background• Project Objective • Scope Overview• Existing and Proposed Process• Construction Schedule• Potential Schedule Issues• Project Area• Questions• Site Walkthrough

id and Construction Schedule• Deadline for Questions – March 9, 2020 at 12:00pm • Bid Opening – March 19, 2020 at 12:00pm• Notice to Proceed – May 2020• Consent Decree Substantial Completion (CDSC) – 236 days

after NTP• Project Substantial Completion – 90 days after CDSC • Final Completion – 60 days after Project Substantial

Completion

• SBE Goal – 3%

idding

• This bid is designated as an electronic bid. No hard copies of bid will be accepted.

• The bid will not be read publicly.• Bids shall be submitted at https://vss.Cincinnati-oh.gov until

12:00 pm on Thursday, March 19, 2020.• Questions on the project must be sent via email to

[email protected] until 12:00 pm on Monday, March 9, 2020.

Status of Phase 1 ProjectsBackground

• SSO 700 Storage and Treatment Facility (STF) is required under the Interim Partial Consent Decree (February 2002) and Global Consent Decree (June 2004)

• The SSO 700 STF is a pilot facility commissioned in 2006 to mitigate the impacts of sanitary sewer overflows in the upper reaches of the Mill Creek watershed.

• Designed to store and treat most of the wastewater volume in excess of the downstream sewer capacity.

• Consists of 30 MGD firm capacity (40 MGD installed capacity) influent pumping station, four (4) 1.2 MG above-ground tanks, 15 MGD Chemically Enhanced High Rate Settling (CEHRS), and UV disinfection.

Status of Phase 1 ProjectsConsent Decree

• Two-year effectiveness study to evaluate effectiveness including recommendations for optimizing operations.

• Result of the study is the STF has effectively eliminated overflows and improved water quality in Mill Creek.

• The study identified needed improvements (physical & operational)• Improvements identified under the study were carried out under

two projects, the Reliability Upgrades project in 2017, and the ongoing Facility Improvements project.

• The SSO 700 STF Disinfection Improvements Project is the second phase of the SSO 700 Facility Improvements Project, which is part of the “bridge schedule” of projects that is required to be substantially complete by December 31, 2020.

Status of Phase 1 ProjectsBackground and Project Objective

Objective:• To implement disinfection improvements (provide

chemical disinfection for tank overflows and replace existing UV system for treated flows) at the SSO 700 STF by December 31, 2020 as required by the “bridge schedule” of projects approved by the Regulators.

Status of Phase 1 ProjectsSSO 700 STF Disinfection Improvements Project Scope

• A new Storage and Disinfection Facility (SDF) for chemical storage and feed equipment for 12.5% sodium hypochlorite (NaOCL) for chlorination and 38% sodium bisulfite for dechlorination of Storage Tank 4 (ST-4) overflows. The SDF consists of pre-engineered metal building (PEMB) founded on drilled cast-in-place reinforced concrete piers.

• Installation of chemical feed duct banks to the feed points.• Implementation of electrical and Instrumentation & Controls

(I&C) system improvements in support of upgrades. • Refurbishment of the existing UV system.

9

Construction Schedule• Consent Decree Substantial Completion – 236 days from Notice to

Proceed. Requirements:• All equipment installed• Preliminary O&M manuals approved• Factory Acceptance Testing complete and accepted by MSDGC• Equipment Startup and Checkout complete and accepted by

MSDGC• Instrumentation and Control System Site Acceptance Testing

complete and accepted by MSDGC• Although UV refurbishment can be completed in the above-

mentioned construction duration, this activity is not tied to the CDSC milestone.

Construction Schedule• Project Substantial Completion – 90 days after Consent Decree

Substantial Completion. Requirements:• Consent Decree Substantial Completion has occurred.• Functional Testing, Functional Acceptance Testing, and

Operation Acceptance Testing and accepted by MSDGC.• All trainings completed.• Warranty start dates document has been submitted and

approved.• Preliminary Record Drawings shall have been received and

accepted by MSDGC

Construction Schedule• Final Completion – 60 days after Project Substantial Completion.

Requirements:• Project Substantial Completion has occurred.• Any contractual obligation outstanding at either Substantial

Completion has been satisfied.• All punch list items have been satisfactorily completed to the

City’s requirements.• All restoration, seeding, final cleaning, and site demobilization

have occurred.

Potential Schedule Issues

• The Pre-Engineered Metal Building (PEMB) lead time following acceptance of shop drawings may vary significantly among specified and non specified PEMB suppliers. The CONTRACTOR shall consider his bid on confirmed delivery dates and prices from PEMB suppliers to meet project schedule requirements.

• UV system lead time is more than 26 weeks. Submittals will be available from vendor within 8 weeks after acceptance of purchase order and equipment delivery is approximately 18 weeks after approved submittals.

Project AreaSSO 700 Storage and

Treatment Facility

SSO 700 Storage and Treatment Facility (STF)

SITE WALK THROUGH

QUESTIONS???

SSO 700 Storage and Treatment FacilityAddress: 420 Cavett Dr.

Reading, OH45215

MEETING NOTES

Page 1 of 5

Generated by:

Rev 4, 01/ 01/20`````````````````````````````````````````````````````````````````````````````````````````````````````````````12

Project ID: 10142070 Project Name: SSO 700 STF Disinfection Improvements Subject: Pre-Bid Meeting Meeting Date: 3/2/2020 Meeting Time: 1:30 PM Location: WEEC 209 & 210 Meeting Manager: Erwin Mamacos Recorder: Jared Hutchins

Attendees:

Name Company/Division Erwin Mamacos MSD Tony Klimek MSD Rob Kneip MSD Ray Schork MSD Rick Hamant MSD Joe DiOrio MSD Pete Caldwell MSD Tom Miller MSD Jared Hutchins Black and Veatch Jon Sandman Langdon Inc. Todd Harris Triton Services Dave Huseman Electrical Process Solutions Jim Pelton Pelton Environmental Dave Wilson BL Anderson Kristian Conway Berkel and Company Eric Yerian Howell Contactors Brad Miller BCI Ben Call BCI Bryan Gesner Smith Corp. (present but forgot to sign in)

Outcomes:

Discussion Summary/Key Points Decisions 1. Introductions – Erwin Mamacos and the project team ran through introductions

and reviewed the agenda. 2. Bid and Construction Schedule

a. Deadline is March 9 at noon for bidder questions. Some questions have already been received. Responses will be addressed via addendum.

b. Bid opening is March 19 at noon. Bids received after this date/time cannot be accepted.

c. MSD anticipates construction NTP by first week of May 2020. d. There are three milestones associated with this project:

i. Consent Decree Substantial Completion (CDSC): 236 days ii. (Contract) substantial completion: 90 days

iii. Final completion: 60 days e. SBE goal is 3%.

MEETING NOTES

Page 2 of 5

Generated by:

Rev 4, 01/ 01/20`````````````````````````````````````````````````````````````````````````````````````````````````````````````12

Discussion Summary/Key Points Decisions 3. Electronic Bidding

a. No hard copies. b. Bids will not be read publicly. c. Website for submitting bidder questions was shared.

4. Background a. Consent Decree with USEPA and Ohio EPA to eliminate SSOs and reduce

CSOs. The SSO 700 Storage & Treatment Facility (STF) was commissioned in 2006 to mitigate SSOs in the upper reaches of the Mill Creek sewershed. The SSO 700 STF was identified as an interim solution for this site, which could become final or temporary based on the final remedy for the sewershed.

b. 2 Year Effectiveness Study concluded the interim facility adequately addresses SSOs, but improvements were identified. These improvements were carried under two projects: Reliability Project in 2017 and the ongoing Facility Improvements project.

c. This project is the second phase of the Facility Improvements project with a Consent Decree milestone of 12/31/2020.

5. Project Objective a. Implement disinfection improvements for Storage Tank No. 4. b. Refurbish existing ultraviolet (UV) system. This work is not tied to CDSC

milestone date of December 31, 2020, but based on schedule estimates it should be capable of being completed by this date.

6. Scope Overview a. Disinfection chemical storage and feed systems using 12.5% sodium

hypochlorite solution and 38% sodium bisulfite. b. Storage and Disinfection Facility (SDF) Building, consisting of pre-

engineered metal building (PEMB) to house chemical systems, founded on a drilled shaft deep foundation.

c. Yard Improvements (chemical feed DBs, utility connections) d. Electrical/I&C Improvements e. UV System Refurbishment

7. Existing and Proposed Process a. Raw Sewage Pump Station conveys flow to the four onsite storage

tanks. Flow initially goes to ST-1, then to ST-2/ST-3 which float together as a single tank. From ST-2 flow is conveyed to the Chemically Enhanced High Rate Settling (CEHRS) process which consists of an Actiflo® ballasted flocculation process, followed by UV disinfection. Treated effluent is routed to Mill Creek. CEHRS solids are routed to either the interceptor or the CEHRS Solids Pump Station which pumps solids to ST-1. ST-4 received raw sewage, and the disinfection improvements project will disinfect and dechlorinate ST-4 overflows. Tank overflows are directed to Mill Creek. Storage tanks are drained and flushed after events.

MEETING NOTES

Page 3 of 5

Generated by:

Rev 4, 01/ 01/20`````````````````````````````````````````````````````````````````````````````````````````````````````````````12

Discussion Summary/Key Points Decisions 8. Construction Schedule

a. CDSC definition has been clarified for this project. The specifications include the definition from the Consent Decree: “The system may be placed in full operation and will both function as perform as designed. This includes all control systems, instrumentation and residual handling systems”. Requirements include:

i. All equipment installed ii. Preliminary O&M Manuals approved

iii. Factory acceptance testing completed and accepted by MSD iv. Equipment startup/checkout completed and accepted by MSD v. I&C System Site Acceptance Testing complete

b. Project Substantial Completion requires: i. Functional Testing

ii. Functional Acceptance Testing iii. Operational Acceptance Testing iv. All trainings complete v. Warranty start dates

vi. Preliminary record drawings submitted and accepted c. Final Completion requires:

i. Any contractual obligations outstanding from CDSC and project substantial completion have been satisfied

ii. All punchlist items addressed iii. Final restoration completed iv. Demobilization

9. Schedule Considerations a. The PEMB lead times may vary drastically among the specified PEMB

vendors. Consider this for bid preparation. b. UV equipment is a long-lead item; this should be accounted for in bid

preparation. c. If there are schedule concerns please bring these to MSD’s attention for

consideration. 10. Project Area

a. The site address is 420 Cavett Drive in Reading, Ohio. Site access is from Riesenberg Ave.; do not follow Cavett Drive to access the site.

11. Questions

a. Has the Tank No. 4 foundation vendor been contacted regarding this project? Note 7 on sheet S01 indicates the VSC contractor is to be contacted.

The project team has not had formal contact with the VSC, although they may be aware through informal communications. If there are concerns raised by the VSC vendor, this should be

MEETING NOTES

Page 4 of 5

Generated by:

Rev 4, 01/ 01/20`````````````````````````````````````````````````````````````````````````````````````````````````````````````12

Discussion Summary/Key Points Decisions

b. Has contaminated soil been encountered onsite?

c. How long is the UV system allowed to be offline for work?

d. The original project was designed such that no soil was to leave the site. Does all soil need to be maintained onsite?

brought to MSD’s attention. A pesticide (Deldrin) has been encountered during previous work at this location, but not during the ongoing project. A site conditions allowance, Bid Item 5, is intended to address contaminated soil if encountered. ATC is on the consultant’s team to provide expertise should impacted soils be encountered during the project. We want to minimize the duration the system is offline. It will not be a short-term outage since there will be significant work to complete all the panel modifications. Dry weather periods such as August would be preferable from MSD’s perspective. The PTI recognizes that plant outages will be required to perform the UV work. MSD operates UV at this location year-round. Yes, all soil must remain onsite. The final grading plan accounts for the current spoils piles and site excavation for the new SDF building.

MEETING NOTES

Page 5 of 5

Generated by:

Rev 4, 01/ 01/20`````````````````````````````````````````````````````````````````````````````````````````````````````````````12

Discussion Summary/Key Points Decisions 12. Site Walkthrough – attendees drove to the site to view and discuss areas of

work included in the project scope. a. If any questions are asked in the field, it is required to submit them

officially. All questions will be officially responded to by MSD and will become part of a future addendum.

b. There is not a lot of active construction ongoing at the site; however, MSD asks all attendees to wear PPE.