CS623
CAD for VLSI
Lecture 31 : Static Timing Analysis
Shankar Balachandran
Dept. of Computer Science and Engineering
Indian Institute of Technology Madras
8/3/2019 Sta Ppt Wid Examples
2/18
CS623
21April
2007
Timing Analysis
Identify the potential performance of a circuit
Many variations in timing
Rise time vs Fall time
Setup, Hold violations
Gate delays and interconnect delays
Exponential number of paths
Clock skew and jitter
8/3/2019 Sta Ppt Wid Examples
3/18
CS623
31April
2007
Dynamic Timing Analysis
Give test vectors at inputs
Observe the changes in all gates
Follow it through to the outputs
Find the worst case time
Not a simple problem :
Order of inputs matter
Simulation is tedious
Mixes logic and timing, which failed and why is difficult
to discern
8/3/2019 Sta Ppt Wid Examples
4/18
CS623
41April
2007
A Simplified Model
Assume rise and fall times are similar
Gate delays are characterized ahead of time
Many good models for predicting interconnect
delay
Assume clock skew = 0
8/3/2019 Sta Ppt Wid Examples
5/18
CS623
51April
2007
A Simple Problem?
Lets ignore interconnect delays for now
What do we need to do :
Perform timing analysis between all flops to flops
Find the worst case delay in each sequential stage
Assign clock accordingly
Design algorithms
Does not solve the inputs and the order of supply
though
8/3/2019 Sta Ppt Wid Examples
6/18
CS623
61April
2007
A Nave Algorithm
Enumerate all paths
Calculate delay on each path
Find the worst case delay
Problem?Exponential Number of Paths
Exponential algorithm
Why is this bad?
Timing analysis done many times during synthesis,
place and route
8/3/2019 Sta Ppt Wid Examples
7/18
CS623
71April
2007
Static Timing Analysis
Done without specifying vectors
A very powerful technique, widely used
A big turn in the EDA industry
Hitchcocks Algorithm
Exhaustive without specifying vectors
Linear in number of gates
Not edges, not paths
8/3/2019 Sta Ppt Wid Examples
8/18
CS623
81April
2007
Basic Sketch
Find when outputs are required at the different
gates
Find out when they are actually arriving
If the signals arrive at every gate before they are
required in every single gate, we are done
Circuit is safe
Else
Pick better gates
Restructure the circuit
8/3/2019 Sta Ppt Wid Examples
9/18
CS623
91April
2007
Arrival Time
1 4 6 5
3 6 6 7
1 4 5 4
0 1 713 18
0 39 15 22
0 1 7 1418
8/3/2019 Sta Ppt Wid Examples
10/18
CS623
101April
2007
Required Time
1 4 6 5
3 6 6 7
1 4 5 4
22
4
0
8
5
3
9
9
9
15
13
15
15
18
22
22
8/3/2019 Sta Ppt Wid Examples
11/18
CS623
111April
2007
Which Nodes are Critical?
Any node where signals arrive just in time
Simply put
Required Time (i) = Arrival Time (i)
Not every node is critical
A path with all nodes that are critical is called the
critical path
8/3/2019 Sta Ppt Wid Examples
12/18
CS623
121April
2007
Which Are Critical?
1 4 6 5
3 6 6 7
1 4 5 4
0 1 713 18
0 3 9 1522
0 1 7 1418
22
4
0
8
5
3
9
9
9
13
15
15
18
22
22
8/3/2019 Sta Ppt Wid Examples
13/18
CS623
131April2007
Definitions
Arrival Time
AT(i) = max [AT(j)] + delay (i) where j fanin(i)
Required Time
RT(i) = min [RT(j)) delay (j)] where j fanout(i)
Remember that delay (j) is subtracted here
Also, notice that min encompasses subtraction
Define Slack
Slack(i) = RT(i) AT(i)
Slack == 0 => Node is critical
A path whose nodes all have slack 0 = critical path
8/3/2019 Sta Ppt Wid Examples
14/18
CS623
141April2007
Slacks
4 4 22 4
0 0 0 0 0
8 8 4 46
1 4 6 5
3 6 6 7
1 4 5 4
8/3/2019 Sta Ppt Wid Examples
15/18
CS623
151April2007
Lets Change Required Time
1 4 6 5
3 6 6 7
1 4 5 4
2
-2
6
3
1
7
7
7
13
11
13
13
16
20
20
Arrive in
the past?
0 1 713 18
0 3 9 15
0 17
1418
22
20
8/3/2019 Sta Ppt Wid Examples
16/18
CS623
161April2007
Lets Redo Slacks
2 2 00 2
-2 -2 -2 -2 -2
6 6 2 24
1 4 6 5
3 6 6 7
1 4 5 4
Critical Edges
Failing Path
8/3/2019 Sta Ppt Wid Examples
17/18
CS623
171April2007
Specifying Required Time
Run as fast as you can
First case
Pick the max(AT) as RT(outputs)
Can the circuit run as fast as T
Second case
Fix RT(outputs) = T
Calculate Arrival Times as before
Calculate slacks as before
Check if there are paths that are violating timing
8/3/2019 Sta Ppt Wid Examples
18/18
CS623
181April2007
Observations on Slacks
For a circuit to run safely
All slacksWhen slacks are less than 0
Relax the constraints
Pick gates with lesser delaysThe model ignores interconnect delay
Easily extendable for interconnect delay
More discussion later
0